LRT Line 1 (Metro Manila)

The Light Rail Transit Line 1, commonly referred to as LRT Line 1 or LRT-1, is a light rapid transit system line in Metro Manila, Philippines, operated by Light Rail Manila Corporation (LRMC) and owned by the Light Rail Transit Authority (LRTA) as part of the Manila Light Rail Transit System. Originally referred to as Metrorail and the Yellow Line, LRT Line 1 was reclassified to be the Green Line in 2012. It travels in a general north–south direction from Baclaran to Monumento, and then east–west from Monumento to Fernando Poe Jr. Currently, the line consists of 20 stations and runs on 19.65 kilometers (12.21 miles) of fully elevated route. Although it has the characteristics of light rail, such as with the type of rolling stock used, it is more akin to a rapid transit system owing to its total grade separation and high passenger throughput.

LRT Line 1
LRTA 13000 class train at Balintawak station, August 2023
Overview
StatusOperational
OwnerDepartment of Transportation
Light Rail Transit Authority
Line number1
LocaleMetro Manila, Philippines
Termini
Stations20
WebsiteLRTA, LRMC
Service
TypeLight rapid transit
SystemManila Light Rail Transit System
Services1
Operator(s)Light Rail Manila Corporation
Former operators
Depot(s)Baclaran
Zapote (future)
Rolling stockLRTA 1000 class
LRTA 1100 class
LRTA 1200 class
LRTA 13000 class
Daily ridership216,667 (2022)[1]
Ridership78 million (2022)[1]
History
OpenedDecember 1, 1984; 39 years ago (1984-12-01)[2]
Last extensionOctober 22, 2010; 13 years ago (2010-10-22)[3]
Technical
Line length19.65 km (12.21 mi)
Number of tracksDouble-track
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Loading gauge4,050 mm × 2,600 mm (13 ft 3 in × 8 ft 6 in)[4]
Minimum radiusMainline: 100 m (330 ft)
Depot: 25 m (82 ft)
Electrification750 V DC overhead lines[5]
Operating speed60 km/h (37 mph)
SignallingAlstom Atlas 100 ETCS Level 1[6][7]
Former systems
Maximum inclineMainline: 3.535%[9]
Depot spur line: 4%[9]
Average inter-station distance903.65 m (2,964.7 ft)
Route diagram

First envisioned in a 1977 study conducted by Freeman Fox and Associates which suggested a street-level railway in Manila, the government revised this recommendation to an elevated system. In 1980, President Ferdinand Marcos created the LRTA and construction of the line began the following year. With its partial opening in 1984 and completion the following year, it became the first rapid transit service in Southeast Asia.[10] LRT Line 1 would become one of the busiest among Metro Manila's three rapid transit lines; it served 216,667 daily average passengers in 2022, making it the second-busiest, just behind the MRT Line 3.[1]

The line is integrated with the public transit system in Metro Manila, and passengers also take various forms of road-based public transport, such as buses and jeepneys, to and from a station to reach their intended destination. Although the line aimed to reduce traffic congestion and travel times in Metro Manila, the transportation system has only been partially successful due to the rising number of motor vehicles and rapid urbanization. Expanding the network's revenue line to accommodate more passengers, through extension projects,[11] is set on resolving this problem.[12]

Route edit

The line is predominantly aligned to the path of Taft Avenue (Radial Road 2) which was chosen largely due to its straight course. Later on, as Taft Avenue ends, it shifts to Rizal Avenue and Rizal Avenue Extension (Radial Road 9) then turning right on EDSA before ending at the corner of North and West Avenues and EDSA. The south extension will span from the Quirino Avenue, Harrison Avenue, and Taft Avenue Extension intersection, then would travel down from Redemptorist Road, Roxas Boulevard, and Manila–Cavite Expressway, afterwards, it will traverse through the Parañaque River and will enter Ninoy Aquino Avenue until reaching and traversing the C5 Extension Road; and will once again enter Coastal Road, crossing the Las Piñas-Bacoor Boundary Bridge along the Zapote River, and traverse through the Alabang–Zapote Road and Aguinaldo Highway intersection, until reaching Niog station located along Bacoor Boulevard in Bacoor, Cavite.

The line links the cities of Quezon City, Caloocan, Manila, and Pasay, with the upcoming stations passing through the cities of Parañaque, Las Piñas, and Bacoor in Cavite.

Stations edit

The line serves 20 stations along its route. A twenty-first station is yet to be constructed.[13] Eight stations which are part of the south extension are also set to be constructed south of Baclaran. Malvar station in Caloocan was previously proposed during the construction of the northern extension located between Monumento and Balintawak, becoming a bargaining object during the entire extension line's construction in the jurisdiction of Caloocan. However, the planned Malvar station was completely shelved by the Aquino administration.[14]

Three stations serve as connecting stations between other lines in the metro. Doroteo Jose is indirectly connected to the Recto of the LRT Line 2 through a covered walkway; Blumentritt is immediately above its PNR Metro Commuter Line counterpart; and EDSA is connected to the Taft Avenue station via a covered walkway. No stations are connected to other rapid transit lines within the paid areas, though that is set to change when the North Triangle Common Station, which has interchanges to MRT Line 3 and MRT Line 7, opens in 2023.

Legend
Existing terminus
List of stations
Name Distance (km) Connections Location
Between
stations
Total
North Triangle
Interchange with   Manila MRT
  •  MMS  North Avenue
  •  18   33   64  SM North EDSA
Quezon City
Fernando Poe Jr. 0.000
  •  1  Roosevelt Avenue
Balintawak 1.870 1.870
  •  1  Balintawak Interchange
  •  5   8   9   13   19   20   21   22   37   38   40   52  Ayala Malls Cloverleaf
Monumento 2.250 4.120
  •  1  Monumento
Caloocan
5th Avenue 1.087 5.207
  •  8   14   35   42   54  5th Avenue
R. Papa 0.954 6.161
  •  8   42   54  R. Papa
Manila
Abad Santos 0.660 6.821
  •  8   42   54  Hermosa Street
Blumentritt 0.927 7.748
  •  42  Blumentritt
Tayuman 0.671 8.419
  •  42  Tayuman
Bambang 0.618 9.037
  •  42  Bambang Street
Doroteo Jose 0.648 9.685
Carriedo 0.685 10.370
  •   Escolta Ferry Station
Central Terminal 0.725 11.095
  •   Lawton Ferry Station
United Nations 1.214 12.309
Pedro Gil 0.754 13.063
Quirino 0.794 13.857
Vito Cruz 0.827 14.684
Gil Puyat 1.061 15.745
Pasay
Libertad 0.730 16.475
EDSA 1.010 17.485
  •  1  Taft Avenue
Baclaran 0.588 18.073
Redemptorist
  •  35   49  Baclaran
Parañaque
Manila International Airport
  •  35   49  MIA Road
Asia World
Ninoy Aquino
Dr. Santos
Las Piñas Las Piñas
Zapote
Bacoor, Cavite
Niog
Proposed interchange with   Manila LRT
Stations, lines, and/or other transport connections in italics are either under construction, proposed, unopened, or have been closed.

Operations and services edit

The line operates from 4:30 a.m. PST (UTC+8) until 10:15 p.m. on weekdays, and 5:00 a.m. until 9:45 p.m on weekends and holidays.[15] It operates almost every day of the year unless otherwise announced. Special schedules are announced via the PA system in every station and also in newspapers and other mass media. During Holy Week, a public holiday in the Philippines, the rail line is closed for annual maintenance, owing to fewer commuters and traffic around the metro. Normal operation resumes after Easter Sunday.[16] During the Christmas and year-end holidays, the operating hours of the line are shortened due to the low ridership of the line during the holidays.[17]

History edit

Planning and funding edit

 
LRTA Class 1000 being built in Bruges in 1982

The 1977 Metro Manila Transport, Land Use and Development Planning Project (MMETROPLAN), a fourteen-month study conducted by Freeman Fox and Associates and funded by the World Bank, recommended the construction of a street-level light rail line in Manila. Following a review by the Ministry of Transportation and Communications, later the Department of Transportation (DOTr), the proposal was revised to an elevated railway to avoid building over the city's many intersections,[18] while the option for an underground line was rejected due to the high water table in Manila;[19] this raised the project's cost from ₱1.5 billion to ₱2 billion. An alignment along Rizal and Taft avenues, which spanned from Monumento, Caloocan in the north to Baclaran, Pasay in the south, was selected because it followed a relatively straight path for most of its route.[18]: 36  On July 12, 1980, President Ferdinand Marcos created the Light Rail Transit Authority (LRTA) and assigned First Lady and Governor of Metro Manila Imelda Marcos as its chairman. While the LRTA confined its roles to policy making, fare regulation, and future planning, the line's operations were assigned to Metro, Inc., a sister company of Meralco. The line came to be referred to as Metrorail.[20]

The Belgian Government granted a ₱300 million soft and interest-free loan for the project's construction, with a repayment period of 30 years. Additional funding was later sourced from a ₱700 million loan, provided by a Belgian consortium consisting of ACEC, La Brugeoise et Nivelles, Tractionnel Engineering International, and Transurb Consult. The consortium also supplied the line's first light rail vehicles, power control, signalling, and telecommunications, as well as provided training and technical assistance. Designed as a public utility rather than a profit center, the line was expected to incur a deficit through 1993, but complete its repayments within a period of 20 years.[20]

Construction and opening edit

The government-owned Construction Development Corporation of the Philippines was the project's sole contractor.[18]: 36  Single column cast-in-place concrete piers carrying precast concrete T-girders and a concrete deck slab were used for the original line from Monumento to Baclaran. The columns are spaced apart by 20 to 27 meters (66 to 88 ft) rising from a cap on top of bored or driven concrete piles. Four of the 2.1-meter (7 ft) wide girders are side by side in each span to accommodate bidirectional standard-gauge railway tracks located 6.1 meters (20 ft) above the street level.[19]

Driven piles were originally used for 80 percent of the project, with spread footings being used for the remaining portion. However, during construction, it was determined that bored piles should be utilized in some areas to mitigate noise and avoid potential damage to nearby buildings. Additionally, the original use of stockpiled precast piles caused clutter on the streets during construction.[19]

In 1981, an economic recession hit the country and the government's were unable to provide counterpart funds for civil works and right-of-way acquisition, which amounted to 60 percent of the project's total cost, led to a delay in construction.[21]: 170  Work finally resume after the Economic Recession and the EDSA Revolution in September of that year along Taft Avenue, between Epifanio de los Santos Avenue (EDSA) and Libertad Street.[22] In order to make way for Carriedo station and a segment of tracks approaching the Pasig River, a department store and a classroom building owned by FEATI University were demolished.[18]: 36 

The southern section, between the Baclaran and United Nations stations, was inaugurated on September 11, 1984, by President Ferdinand Marcos. Commercial operations along this section commenced on December 1. The line became fully operational on May 12, 1985, when the northern section between Central Terminal and Monumento opened. During the first several years, two-car trains that could accommodate up to 748 passengers were utilized. This amounted to a capacity of 20,000 passengers per direction.[23]

Capacity expansions edit

First phase edit

 
The trains procured under the first phase of the capacity expansion in November 2006.

Line 1 would eventually reach capacity in the 1990s due to traffic congestion and air pollution. The line fell so far into disrepair due to premature wear and tear that trains headed to Central Terminal station had to slow to a crawl to avoid further damage to the support beams below as cracks reportedly began to appear.[18] The premature aging of Line 1 led to an extensive refurbishing and structural capacity expansion program with a help of Japan's official development assistance.[12]

The capacity expansion project was one of the flagship projects of the administration of President Fidel V. Ramos.[12] A loan agreement for the first phase of the capacity expansion project was signed in 1994.[12] In August 1996, a consortium of Marubeni Corporation, Adtranz, and ABB was awarded the contract and was signed the following September.[24][25] The project, undertaken at a cost of ₱4.1 billion,[26] involves the procurement of seven four-car trains that were ordered from Hyundai Precision, and the refurbishment and conversion of the original two-car trains into three-car trains in 1999. In line with the introduction of the four-car trains, the station platforms were also extended.[12] The project was completed in 2002.[12]

During the first phase of the capacity expansion, a labor strike was launched by employees of Meralco Transit Organization (METRO, Inc.) in July 2000 as their operations and maintenance contract with the Light Rail Transit Authority (LRTA) was about to expire. It paralyzed the operations of the line for a week. The LRTA decided not to renew its contract with METRO, Inc. that expired on July 31, 2000, and the former assumed operational responsibility,[27] LRTA undertook this responsibility until September 12, 2015, when the operations and maintenance of the line were privated to the Light Rail Manila Corporation for thirty-two years as part of the line's south extension.

Second phase edit

 
The trains procured under the second phase of the capacity expansion undergoing a test run in November 2006.

Another capacity expansion project was initiated in April 2000 during the administration of President Joseph Estrada due to the high demand of passengers in line with the completion of the MRT Line 3 (and eventually, LRT Line 2).[28][26] Funded through an ₱8.893-billion loan from the Japan Bank for International Cooperation,[29] the second phase of the capacity expansion project was divided into two packages. Package A involves the procurement of twelve four-car trains, upgrades to the signalling and communications equipment, and upgrades to the stations and depot. Package B, on the other hand, involves the procurement and installation of air conditioning units for the 1000 class trains, replacement of faulty air conditioning units of the 1100 class trains, renovation of 4 kilometers (2.5 miles) of railway track and railway sleepers, and procurement of equipment and spare parts used for track works. The installation of equipment for the automatic fare collection system was also included in the capacity expansion project.[28]

North extension edit

 
Balintawak station, one of the two stations constructed under the north extension project in 2016.

With the completion of the first phase of the MRT Line 3 in 1999, there were plans to extend Line 3 towards Monumento station (Phase 2) to create a seamless rail loop around Metro Manila.[30] However, the extension was shelved by then-President Gloria Macapagal Arroyo in favor of a 5.7-kilometer (3.5-mile) extension of the LRT-1 to the MRT-3 North Avenue station. The project involved the construction of three stations: Balintawak, Roosevelt (renamed Fernando Poe Jr.) , and a common station at North Avenue. However, due to disputes in the common station's location, the station would only begin construction in 2017. This was also known as the MRT–LRT Closing the Loop project.

In September 2008, then-mayor of Caloocan Enrico Echiverri, petitioned the government to construct Malvar station, an intemediary station between Balintawak and Monumento.[31] Two months later, two thousand residents from Barangay Bagong Barrio, where the station would be built, staged a protest along EDSA to urge the government to build the station.[32] Malvar station would eventually be approved in July 2009.[33] Though it was reported that the feasibility study for the station was completed,[34] construction has yet to start.

Construction eventually began in June 2008.[35] The joint venture of DMCI and First Balfour built the viaduct and the two stations,[36] while the electrical and mechanical systems contracts were assigned to different contractors.[34][37]

The project was intended to integrate the LRT Line 1 and MRT Line 3 operations. Structure gauge tests were eventually conducted in the extension by February 2010, which found that the LRT Line 1 trains can run on MRT Line 3 tracks.[38] On February 25, 2010, as part of the 24th anniversary of the People Power Revolution, President Arroyo and Vice President Noli de Castro rode an MRT-3 train from Santolan to North Avenue before transferring to a Line 1 train that passed along the extension until Monumento.[39] Balintawak station opened on March 22, 2010,[40] while FPJ station opened seven months later, on October 22.[3]

To integrate the operations of the LRT Line 1 and MRT Line 3, the then-Department of Transportation and Communications, under Secretary Jose de Jesus, launched an auction for a temporary five-year operations and maintenance contract for the two lines. The bidding was set by July 2011. Over 21 companies from around the world expressed interest to bid which included Metro Pacific Investments, Sumitomo Corporation, Siemens, DMCI Holdings, San Miguel Corporation, and others.[41] After de Jesus resigned from the DOTC,[42] his successor, Mar Roxas, halted the auction process and was later shelved.[43]

An extension to the North Triangle Common Station is set to open in 2023.

Privatization edit

A plan to privatize the line was pursued as part of the south extension project. The bidding was set for August 2013, but failed.[44] The project was rebidded, and on September 12, 2014, the operation and maintenance of LRT Line 1 and the construction of a ₱65 billion extension project to Bacoor, Cavite was awarded to the Light Rail Manila Corporation (LRMC), a joint venture company of Metro Pacific's Metro Pacific Light Rail Corporation (MPLRC), Ayala Corporation's AC Infrastructure Holdings Corporation (AC Infra), and the Philippine Investment Alliance for Infrastructure's Macquarie Infrastructure Holdings (Philippines) PTE Ltd. (MIHPL) (with Sumitomo Corporation following in May 2020).[45][46] The consortium signed a concession agreement with the DOTr and LRTA on October 2, 2014.[47][48] LRMC contracted the operation and maintenance of the line for 20 years to RATP Dev under its subsidiary RATP Dev Transdev Asia, a joint venture between Transdev and RATP Dev on December 8, 2014.[49][50] The 32-year concession started on September 12, 2015.

Rehabilitation edit

A rail replacement program commenced in 2016, as a continuation of the previous rail replacement program completed by the Light Rail Transit Authority.[51] LRMC signed a contract with First Balfour for the structural restoration project of Line 1 on April 19, 2017,[52] and in November 2018, LRMC tapped First Balfour and MRail, a subsidiary of Meralco for the rehabilitation of rectifier substations.[53]

LRMC has also rehabilitated the first and second-generation trains to add more trains servicing the line.[54][55]

Station facilities, amenities, and services edit

 
Baclaran station, the line's southern terminus, in 2008

All stations in Line 1 are elevated, with the exception of Zapote station.

Station layout and accessibility edit

Most stations are composed of only one level, accessible from the street below by stairway, containing the station's concourse and platform areas separated by fare gates. Some stations tend to have a concourse level below the platforms. The single-level stations of Line 1, however, was not built with accessibility in mind, due to the lack of barrier-free facilities such as escalators and elevators. Some stations, such as Monumento and EDSA, are connected at concourse level to nearby buildings, such as shopping malls, for easier accessibility. Some trains have spaces for passengers using wheelchairs.

As of November 8, 2009, folding bicycles are allowed to be brought into trains provided that it does not exceed the LRTA's baggage size limitations of 2 by 2 feet (20 by 20 in).[56] The last car of each train are also designated as "green zones", where folding bicycle users can ride with their bikes.[57]

All stations have side platforms except for Baclaran, which has one side and one island platform. Due to the high patronage of the line, part of the platform corresponding to the front car of the train is cordoned off for the use of women, children, elderly and disabled passengers.[58]

Shops and services edit

Inside the concourse of some stations are stalls or shops where people can buy food or drinks. Stalls vary by station, and some have fast food stalls. The number of stalls also varies by station, and some stations tend to have a wide variety.

Stations such as Monumento and Baclaran are connected to or are near shopping malls and/or other large shopping areas, where commuters are offered more shopping varieties.

Ridership edit

The current designed daily ridership of the line is 560,000 passengers[59] and currently aims to increase the number of passengers being served on the line to more than 800,000 passengers, as the line's south extension is set to be fully operational by 2027.

On January 9, 2012, the line served a record 620,987 passengers during the Feast of the Black Nazarene (Carriedo station is near to the Quiapo Church), and since the day falls on a working weekday.[60] In 2018, the line carried 300,000 to 500,000 passengers daily, due to the increased number of trains, from 86 vehicles to 113 vehicles available for daily trips. This gradually reduces the waiting time of passengers from 5 minutes to as much as 2 to 3.5 minutes.[61][62] It also carried as much as 14.63 million passengers monthly in 2018.[61] However, as of 2023, the waiting time has been officially reported at 5 to 6 minutes.[63]

Rolling stock edit

 
Different types of rolling stock at the line's depot in Baclaran, Pasay. The newer fourth-generation trains are the red trains on the right.

The line at various stages in its history has used different configurations of two-car, three-car, and four-car trainsets. The two-car trains are the original first-generation BN and ACEC trains (railway cars numbered from 1000). Most were transformed into three-car trains, although some two-car trains remain in service. The four-car trains are the more modern second-generation Hyundai Precision / Adtranz (1100), third-generation Kinki Sharyo / Nippon Sharyo (1200), and fourth-generation Construcciones y Auxiliar de Ferrocarriles (CAF) / Mitsubishi (13000).[64][65][66]. There are 259 railway cars grouped into 126 trains serving the line: 63 of these are first-generation, 28 second-generation, 48 third-generation, and 120 fourth-generation cars. Some of the cars, especially those from 1st generation, were decommissioned due to them being cannibalized or involved in accidents. Such as 1037, which was severely damaged in the Rizal Day bombings in 2000, it was subsequently decommissioned afterwards and eventually scrapped.[5][67]

The maximum design speed of these cars ranges between 60 and 70 kilometers per hour (37 and 43 mph), but only run at a maximum operational speed of 60 kilometers per hour (37 miles per hour).[68][69] Until 2011, all trains ran at the maximum speed until it was downgraded to 40 kilometers per hour (25 miles per hour) due to the deteriorating condition of the railway tracks, except for the north extension which continued running on the 60 km/h (37 mph) maximum speed. After a three-year rail replacement program, the operating speed was restored to 60 km/h (37 mph) on April 5, 2021.[70]

The line's fleet is being modernized to cope with increasing numbers of passengers. In the initial phase of its capacity expansion program completed in 1999, the line's seven four-car second-generation trains were commissioned providing an increased train capacity of 1,358 passengers while the original two-car trains capable of holding 748 passengers were transformed into three-car trains with room for 1,122.[64] As part of the second phase of expansion, twelve new trains made in Japan by Kinki Sharyo and Nippon Sharyo were purchased in 2005 and were introduced in December 2006, providing a capacity of 1,388 passengers.[29][65][71][72] The fourth-generation trains, ordered in 2017 with Japanese funding for the south extension to replace the first-generation trains,[73][74][75][76] were delayed in deployment due to the need to rectify factory defects in the roofs of the units that went undetected prior to delivery due to the inability to conduct factory inspections during the COVID-19 pandemic.[77] Rectification works were conducted with costs shouldered by the manufacturer. The new train sets entered revenue service on July 20, 2023.[78]

Prior to 1999, the first-generation trains were notorious for its lack of air conditioning, relying instead on forced-air roof ventilation for cooling.[79] This however resulted in hot and stuffy rides. Although the entry of the second-generation trains in 1999 marked the introduction of air-conditioned trains in the line, the problem was fully addressed after a preparatory rehabilitation program completed in 2001 allowed the installation of air conditioners to the older rolling stock in 2004.[80][81][82]

LRMC has also built an in-house laboratory for production, manufacturing, fabrication and repair of train parts that are no longer available in the market.[83]

The Passenger Assist Railway Display System, a passenger information system powered by LCD screens installed near the ceiling of the train that shows news, advertisements, current train location, arrivals and station layouts, are already installed in the third-generation trains, along with the trains of Line 2 and the first-generation trains of Line 3. As of the 4th quarter of 2023, these units were discreetly removed and prior to removal, were no longer operating.

Rolling stock of LRT Line 1
 
First-generation LRTA 1000 class (1984)
 
Second-generation LRTA 1100 class (1999)
 
Third-generation LRTA 1200 class (2006)
 
Fourth-generation LRTA 13000 class (2023)

Depot edit

The line maintains an at-grade depot in Baclaran, Pasay. It serves as the center of the operations and maintenance of the line. It is connected to the mainline through a spur line. Before its expansion, the depot had a capacity of 145 light rail vehicles and an area of 6.4 hectares (16 acres).[84] It was expanded to an area of 10.6 hectares (26 acres) to accommodate 197 vehicles, with Shimizu Corporation and First Balfour implementing the project.[85] Expansion works were completed after the depot was inaugurated on February 23, 2022.[86]

A satellite depot is being constructed in Zapote as part of the line's south extension project. When completed, the satellite depot will handle 72 light rail vehicles.[85]

Other infrastructure edit

Signalling edit

 
Alstom Atlas 100 signal lights

Throughout its history, the line used different signalling systems. The line currently uses the Alstom Atlas 100 solution based on ETCS Level 1.

The original signalling system used in the LRT Line 1 was based on fixed block and relay type trackside systems. Trains had an automatic train stop system that activates if the train passes by a red signal or over-speeding. Based on a procurement plan published by the Light Rail Transit Authority, most of the signalling equipment, including track circuits, were supplied by ACEC.[8]

In 2007, as part of a capacity expansion project, the signalling system was replaced with a signalling and train control system based on automatic train protection (ATP) and automatic train supervision (ATS) using Siemens technology. The ATP system monitors the speed of the trains, while the ATS system directs train operations. Prior to the 2022 upgrade, the signalling system was designed to operate at a headway of 112 seconds.[5][87] Aside from the ATP and ATS systems, its subsystems include train detection through axle counters, and microprocessor-based interlocking.[87]

The signalling system was again upgraded as part of the line's south extension. Alstom was awarded a contract in February 2016 to supply the signalling and communications systems for the line.[7] Alstom supplied the Atlas 100 solution based on ETCS Level 1. The testing and commissioning phase of the upgraded signalling system started in November 2021 and was completed on February 1, 2022.[6]

Tracks edit

 
 
twinblock ties employed on the Direct fixation tracks (left) and Ballast tracks (right)

The tracks have three types: ballasted, slab tracks and concrete plinth. Ballasted sections are found in the original 13.95-kilometer (8.67-mile) section from Baclaran to Monumento, while slab tracks are found in the north extension, and the newer Cavite extension uses concrete plinths, like the MRT-3 and LRT-2. For the ballasted and ballastless tracks, the rails are supported by twin-block concrete railroad ties, and have a track center distance of 3.2 meters (10 feet).[87][88]

The tracks in the original 13.95-kilometer (8.67-mile) line consist of 50-kilogram-per-meter (100-pound-per-yard) rails designed to the EB 50T rail profile, while the tracks in the future extension line consist of 54-kilogram-per-meter (110-pound-per-yard) rails designed to the UIC 54 rail profile.[9]

Due to the deterioration of the rail tracks in the original line, speed restrictions were implemented in 2011 except for the north extension.[70] In 2012, a contract to replace 23 kilometers (14 miles) of rails was awarded to the joint venture of Oriental and Motolite Marketing Corporation, Korail, Erin-Marty Fabricators Company, Inc., and Jorgman Construction and Development Corporation.[89] However, there were delays in the project implementation until February 2014, when the then-Department of Transportation and Communications issued a notice to proceed for the joint venture.[90] The first phase of the replacement started in 2014,[91] while the rails at Monumento station were replaced in March 2015.[92] The first phase of the rail replacement was completed in December 2015.[51] The second and final phase of replacement works commenced in August 2016 by the Light Rail Manila Corporation,[51] which contracted Joratech[93] to replace 26 kilometers (16 miles) of rails[51] and was completed in 2017.[94] This was intended to increase the operating speed from 40 kilometers per hour (25 miles per hour) to 60 kilometers per hour (37 miles per hour) and was achieved on April 5, 2021.[70]

Extensions edit

South extension edit

 
Construction of the Cavite Extension Project viaduct along Ninoy Aquino Avenue in July 2021.
 
The girder launcher along Radial Road 1 approaching Roxas Boulevard in November 2021.
 
Construction of Manuyo Uno station viaduct along C-5 Road Extension in April 2023.
 
Construction of Manila Line 1 south extension depot (Manuyo Uno station) along C-5 Road Extension in April 2023.

Plans for an extension to the province of Cavite were pitched as early as 1999, with the original plan being the MRT Line 6, which was identified in the Metro Manila Urban Transportation Integration Study Master Plan by the Japan International Cooperation Agency in 1999. This would have constructed a 12 to 15-kilometer elevated railway from Baclaran to Imus, with extensions leading to Cavite City (10.0 km), Dasmariñas (14.5 km), Airport, Sucat (9.0 km), and Alabang (12.0 km).[95][96] However, the project never materialized.

The extension was first approved by the National Economic and Development Authority in 2000, while the Implementing Agreement for the project was approved in 2002, to be undertaken by SNC-Lavalin as a public-private partnership project.[97][98] The proposal however was subsequently terminated in 2006.[99] In the same year, the government worked with International Finance Corporation, White & Case, Halcrow and other consultants to conduct an open-market invitation to tender for the extension and for a 40-year concession to run the extended line.[99][100] However, the project was shelved months before Gloria Macapagal Arroyo would end her term as President.[101]

The project was subsequently re-approved by President Benigno Aquino III in March 2012, again as a public-private partnership project,[102] with construction expected to start by 2014. However, a myriad of problems caused the project to be delayed; right-of-way issues and the initial failed bidding of the line's privatization in 2013. Subsequently, the Light Rail Manila Corporation (LRMC) was awarded the concession by 2014 before the line was privatized on September 12, 2015. The issues were resolved in 2016 and on May 4, 2017, the 11.7-kilometer (7.3-mile) South Extension Project, also known as the Cavite Extension Project, broke ground.[103][104] When completed, it would be the third rail line extending outside the Metro Manila area (after the east extension of Line 2 and the construction of Line 7).[105]

The project is divided in two phases—Phase 1 covers five stations from Redemptorist to Dr. Santos, while Phase 2 covers the remaining three stations from Las Piñas to Niog.[11] The two-phase project would be implemented in a hybrid funding scheme, which combines the funds from the Japanese official development assistance and LRMC, the private proponent.[106] Civil works on the extension began on May 7, 2019.[107] The project, pegged at ₱64 billion, has suffered cost overruns due to construction delays caused by the COVID-19 pandemic and pending right-of-way issues of the extension's second phase.[108]

The line would be extended from Parañaque southwards, connecting Las Piñas and Bacoor to the Mega Manila railway network. It would involve the construction of eight stations (Redemptorist, Manila International Airport, Asia World, Ninoy Aquino, Dr. Santos, Las Piñas, Zapote, Niog) and another two planned stations (Manuyo Uno and Talaba), the construction of three intermodal facilities, one satellite depot located at Zapote, and mass upgrades to the existing Baclaran depot. The construction of the extension line is being built using a full span launching method, renowned as one of the fastest methods of construction for bridges and elevated viaducts that cuts time and total land space needed for construction. As the first railway line to utilize the new construction method, a total of 203 pi-girders were used for the construction of the extension's first phase;[109] the last of which was laid on February 7, 2022.[110] The project is expected to cater more than 800,000 passengers daily once completed.[103][104]

The LRMC partnered with Bouygues Construction for the civil works,[111] Alstom for the installation of the signalling and communication systems,[7] and the RATP Dev Transdev Asia[112] for the overall engineering, procurement, consultation, construction and assistance services for the project.

In August 2023, businessman Manny Villar bared plans to take over the extension project, noting the difficulty of LRMC extending the line to Cavite due to right-of-way issues. A portion of the extension will pass by Villar's properties in Las Piñas, and according to Villar, right-of-way acquisition "will not be a problem". He also plans to further extend the line into Cavite province should the unsolicited proposal be approved.[113]

On December 19, 2023, the first test run along the extension was successfully conducted using an LRTA 1100 class train.[114]

As of November 11, 2023, the project is 94.1% complete. Phase 1 of the extension is expected to be operational by the fourth quarter of 2024,[115] with full operations by 2027.[116]

The Light Rail Manila Corporation stated that the LRT1 Cavite Extension Phase 1 was 97% complete as of March, 2024 (the Redemptorist Station, Asia World Station, Ninoy Aquino Station and Dr. Santos Station were 93.3%, 83%, 88% and 94.1% finished, respectively).[117]

Incidents and accidents edit

Rizal Day bombings edit

On December 30, 2000, during the Rizal Day, a 1000 class LRV train (Car number 1037) was involved in the Rizal Day bombings at Blumentritt station. The attack on the line killed some 22 people and injured hundreds. Eight members of both Jemaah Islamiyah and the Moro Islamic Liberation Front (MILF), which include Hambal, Asia's most wanted man, and Fathur Rahman al-Ghozi, were charged with plotting and masterminding the attacks in 2003, some three years after the attacks. Three suspects were put on trial,[118][119] with al-Ghozi receiving 17 years in prison due to the illegal possession of explosives. Al-Ghozi later died in a firefight after attempting to escape from prison.

Other incidents edit

  • On January 3, 2008, a fire blazed at a shopping mall in Baclaran. Due to the smoke, the Baclaran station was temporarily closed. A provisional service was implemented between EDSA and Monumento (at the time, the north extension was not opened yet), with southbound trains still proceeding towards Baclaran to only serve as a turnback siding.[120] The station remained closed the following day[121] until it was reopened a few days later.[citation needed]
  • On August 11, 2008, a fire blazed in a mall near the Baclaran station. The station was closed to the public until the station was reopened on August 13.[122]
  • On December 8, 2008, a train encountered a glitch while approaching Carriedo station.[123]
  • On February 18, 2011, two trains (1G and 3G) collided near Fernando Poe Jr. station in Quezon City at the reversing tracks, around a kilometer away to the east. There were no passengers on board when the incident happened. The cause of the collision is yet to be determined, whether due to driver error or technical malfunction.[124]
  • On April 15, 2011, a door malfunction disrupted the operations of Line 1 at Blumentritt station.[125]
  • On June 21, 2011, at 8:00 AM, a train suffered a short circuit in one of its electrical components at Libertad station. On the same day, at 2:23 PM, a power cable was hit by lightning, disrupting the line's operations for three hours.[126]
  • On August 30, 2012, at 5:50 AM, a woman committed suicide after jumping in front of an approaching train at EDSA station. Operations were disrupted until operations resumed at 9:40 AM.[127]
  • On December 21, 2012, a train stalled at the Monumento station.[128]
  • On November 14, 2014, a signaling fault at Fernando Poe Jr. station limited the operations between Monumento and Baclaran stations. The situation normalized at 3:57 PM.[129]
  • On May 23, 2015, thousands of passengers were stranded after two trains (1G and 3G) collided near the Monumento station. A train driver was hurt after the impact caused his head to slam into the dashboard of the train.[130] The accident, later revealed to be caused by power fluctuation that affected the signalling system, forced passengers to alight from the station until services was restored around 1 pm at the same day.[131]
  • On March 10, 2016, a 1G train car door was left open while running between Central Terminal and Pedro Gil stations. The problem was fixed at the Pedro Gil station.[132]
  • On March 22, 2016, the doors of a 1G train car at the Central Terminal station failed to open, leaving passengers trapped inside the train.[133][134]
  • On September 26, 2016, a faulty door in a 1G train car suddenly slammed shut in less than a second. No one was injured.[135]
  • On November 6, 2017, a man's leg got stuck when a train door closed at the Gil Puyat station. The man was dragged at the platform when the train was moving, leaving the man with severe injuries. The man was then sent to a nearby hospital, where he was confined in an intensive care unit. According to a report, a number of trains, particularly the 1000 class (1G) trains, do not have sensors, that detects an object between doors.[136]
  • On November 27, 2017, an 1100 class (2G) train door malfunctioned after a passenger forcibly opened it at Vito Cruz station, causing the sensor to malfunction. The train continued its journey with the door left open, and a passenger recorded this incident on camera.[137]
  • On February 20, 2018, at around 6:00am, a train at R. Papa station unloaded 120 passengers after the air pressure gauge inside the train malfunctioned. The operations returned to normal 30 minutes later.[138]
  • On July 21, 2018, at around 6:00 AM, a contact wire sparked near Libertad station. A provisional service between Fernando Poe Jr. and United Nations stations was implemented. Normal operations resumed at 2:59 PM after the cable was fixed.[139]
  • On September 26, 2018, a faulty 1G train door was unable to open at the Balintawak station. A passenger pushed the door open and was able to disembark. The next passenger pushed the door but it abruptly closed on him but managed to get through.[140]
  • On October 3, 2019, a mechanical problem limited the LRT-1 operations between Monumento and Baclaran stations. The operations returned to normal at 1:50 AM.[141]
  • On November 6, 2020, a 1G train car emitted smoke at Gil Puyat station at 2:00 PM due to a catenary fault. Passengers were evacuated, and the line implemented a provisional service from Balintawak to Central Terminal and vice versa.[142] The situation normalized at 8:00 PM.[143]
  • On April 4, 2022, a train suffered a glitch at Tayuman station, causing a speed restriction of 25 kilometers per hour (16 miles per hour). Operations normalized at 7:34 AM.[144]
  • On February 17, 2023, operations were limited between Fernando Poe Jr. and Gil Puyat due to electrical problems.[145]
  • On April 14, 2023, at 10:17 AM, a speed restriction of 25 kilometers per hour (16 miles per hour) was put in place in the whole train line due to the reported fault of the affected LRV.[146] At 10:25 AM, the operations stop in whole line due to the fault of affected train at Bambang station northbound[147] and the line implemented a provisional service from Baclaran to Central Terminal and vice versa at 10:52 AM.[148] Operations normalized from Baclaran to Fernando Poe Jr. and vice versa at 11:01 AM.[149]

References edit

  1. ^ a b c Abadilla, Emmie V. (April 12, 2023). "10 regional airports up for sale - Bautista". Manila Bulletin. Retrieved April 13, 2023.
  2. ^ "Manila Timeline (LRT, MRT)".
  3. ^ a b Calonzo, Andreo C. (October 22, 2010). "DOTC: LRT Line 1's Roosevelt Station now open". GMA News Online. Retrieved August 13, 2021.
  4. ^ (PDF). Part 2. Employer’s Requirements - LRT Line 1 – 4th Generation Rolling Stock (Report). Department of Transportation (Philippines). October 16, 2015. p. 3. Archived from the original (PDF) on December 27, 2021. Retrieved February 26, 2022.
  5. ^ a b c Department of Transportation and Communications; Light Rail Transit Authority (June 4, 2012). MANILA LRT1 EXTENSION, OPERATIONS AND MAINTENANCE PROJECT (PDF). Public-Private Partnership Center (Report). Retrieved June 7, 2020.
  6. ^ a b officialLRT1 (February 1, 2022). "LRMC completes upgrade of LRT-1 signalling system". Light Rail Manila Corporation. Retrieved February 2, 2022.{{cite web}}: CS1 maint: numeric names: authors list (link)
  7. ^ a b c "Alstom to supply an integrated metro solution to Manila". Alstom.com. February 12, 2016.
  8. ^ a b (PDF). Light Rail Transit Authority. Archived from the original (PDF) on April 30, 2006. Retrieved March 13, 2022.
  9. ^ a b c (PDF). LRT 1-South (Cavite) Extension Project (Report). Department of Transportation (Philippines). 2015. pp. 98–103, 121, 126, 148–149. Archived from the original (PDF) on December 16, 2021. Retrieved December 16, 2021.
  10. ^ Marasigan, Lorenz S. (January 28, 2021). "New trains for LRT-1 arrive in PHL". BusinessMirror. Retrieved July 13, 2021.
  11. ^ a b Balinbin, Arjay L. (January 18, 2021). "LRT-1 Cavite Extension more than halfway complete, Transport dep't says". BusinessWorld. Retrieved August 7, 2021.
  12. ^ a b c d e f Japan International Cooperation Agency (2004). Metro Manila LRT Line 1 Capacity Expansion Project (PDF) (Report). Retrieved December 4, 2021.
  13. ^ . Light Rail Transit Authority. Archived from the original on May 28, 2014. Retrieved June 10, 2014.
  14. ^ (Press release). Caloocan City Public Information Office. November 3, 2008. Archived from the original on August 4, 2010. Retrieved August 13, 2021.
  15. ^ "LRT-1 Train Service Hours". Light Rail Manila Corporation. August 26, 2020. Retrieved March 28, 2022.
  16. ^ "LRMC releases LRT-1 train schedule for 2022 Holy Week". Manila Standard. April 6, 2022. Retrieved April 6, 2022.
  17. ^ Grecia, Leandre (December 21, 2021). "Here are the LRT-1, LRT-2, MRT-3 schedules for Christmas 2021". Top Gear Philippines. Retrieved March 28, 2022.
  18. ^ a b c d e Satre, Gary L. (June 1998). "The Metro Manila LRT System — A Historical Perspective" (PDF). Japan Railway & Transport Review. Vol. 16. EJRCF. Retrieved June 11, 2019.
  19. ^ a b c "Light rail transit rides high; Elevated route is designed to clear snarled traffic below". Engineering News-Record. McGraw Hill Education. January 20, 1983. p. 54.
  20. ^ a b . Light Rail Transit Authority. Archived from the original on June 9, 2019. Retrieved April 19, 2019.
  21. ^ Provision of Travelway Space for Urban Public Transport in Developing Countries. UN-HABITAT. 1993. ISBN 9789211312201. Retrieved June 15, 2019.
  22. ^ . Light Rail Transit Authority. July 14, 2014. Archived from the original on July 14, 2014. Retrieved July 14, 2014.
  23. ^ Rimmer, Peter J. (2013). Rikisha to Rapid Transit: Urban Public Transport Systems and Policy in Southeast Asia. Elsevier. pp. 190–191. ISBN 9781483150529.
  24. ^ Marcelo, Ellen S. (August 29, 1996). "P2.77-B LRT I contract awarded : Marubeni - ABB group wins". Manila Bulletin.
  25. ^ Villegas, Paul N. (September 24, 1996). "LRTA, Marubeni Corp. sign P1.94-B pact to expand LRT 1". Business World.
  26. ^ a b "LRT to get facelift with new modernization program, says administrator". The Philippine Star. April 9, 2000. Retrieved April 8, 2022.
  27. ^ Abadilla, Emmie V. (August 1, 2000). "LRT operations revert to gov't, Metro contract expires". Manila Bulletin.
  28. ^ a b Japan International Cooperation Agency (2012). Ex-Post Evaluation of Japanese ODA Loan Project - LRT Line 1 Capacity Expansion Project (II) (PDF) (Report). Retrieved December 4, 2021.
  29. ^ a b (Press release). Light Rail Transit Authority. December 7, 2006. Archived from the original on July 8, 2008. Retrieved April 6, 2022.
  30. ^ "MRTC gets support on Edsa MRT-3 phase 2 project". The Philippine Star. February 24, 2003. Retrieved February 6, 2022.
  31. ^ Laude, Pete (September 15, 2008). "Caloocan wants LRT station in Bagong Barrio". The Philippine Star. Retrieved November 11, 2023.
  32. ^ Laude, Pete; Botial, Jerry (November 4, 2008). "Caloocan residents want additional LRT station". The Philippine Star. Retrieved November 11, 2023.
  33. ^ Lectura, Lenie (December 22, 2010). . Business Mirror. Archived from the original on March 9, 2012. Retrieved August 13, 2021.
  34. ^ a b . Light Rail Transit Authority. Archived from the original on September 28, 2011. Retrieved February 6, 2022.
  35. ^ "History of MRT3". Retrieved November 11, 2023.
  36. ^ "LRT 1 North Extension". First Balfour. Retrieved November 10, 2021.
  37. ^ CHAPTER 5 - PROJECT IMPLEMENTATION PLAN (PDF). PREPARATORY STUDY FOR LRT LINE 2 EXTENSION PROJECT - FINAL REPORT (Report). October 2011. Retrieved February 6, 2022.
  38. ^ Ronda, Rainier Allan (February 11, 2010). "LRT trains can run on MRT to solve overloading woes". The Philippine Star. Retrieved February 6, 2022.
  39. ^ Burgonio, TJ; Montecillo, Paolo (February 26, 2010). . Philippine Daily Inquirer. Archived from the original on February 27, 2010. Retrieved February 6, 2022.
  40. ^ "LRT opens Balintawak station". ABS-CBN News. March 22, 2010. Retrieved August 13, 2021.
  41. ^ "Ayala, San Miguel, Meralco, 21 others interested in MRT-3, LRT-1". ABS-CBN News. April 14, 2011. Retrieved February 18, 2022.
  42. ^ "DOTC chief de Jesus resigns". ABS-CBN News. June 1, 2011. Retrieved February 18, 2022.
  43. ^ Montecillo, Paolo G. (July 13, 2011). "DOTC reviews MRT-LRT central station project". Philippine Daily Inquirer. Retrieved February 18, 2022.
  44. ^ "LRT-1 Cavite extension bidding 'a failure'". Rappler. August 29, 2013. Retrieved February 26, 2022.
  45. ^ "Japan's Sumitomo joins Pangilinan-Ayala consortium for LRT-1". ABS-CBN News. May 29, 2020. Retrieved May 29, 2020.
  46. ^ "DOTC awards LRT-1 Cavex PPP; starts bid for LRT-2 O&M". Official Gazette of the Republic of the Philippines. September 13, 2014. Retrieved December 4, 2021.
  47. ^ "PPP contract signed for Manila LRT 1 project". InfraPPP. October 6, 2014. from the original on January 24, 2021. Retrieved December 4, 2021.
  48. ^ . Social Patrol. Archived from the original on May 5, 2017. Retrieved May 8, 2017.
  49. ^ "Light Rail Manila Corp inks operation and maintenance contract with French firm RATP Dev for the LRT1 extension project". France in the Philippines and in Micronesia – Embassy of France in Manila. from the original on February 5, 2018. Retrieved February 4, 2018.
  50. ^ (PDF). International Finance Corporation. Archived from the original (PDF) on February 4, 2018. Retrieved February 4, 2018.
  51. ^ a b c d officialLRT1 (August 31, 2016). "LRMC commences 26-km rail replacement in LRT-1". Light Rail Manila Corporation. Retrieved November 10, 2021.{{cite web}}: CS1 maint: numeric names: authors list (link)
  52. ^ Marasigan, Lorenz S. (April 19, 2017). "LRMC signs P980-million deal with First Balfour for repair of LRT 1". BusinessMirror. Retrieved November 10, 2021.
  53. ^ Camus, Miguel R. (November 17, 2018). "P650-M rehab of LRT1 power system set". Philippine Daily Inquirer. Retrieved November 10, 2021.
  54. ^ "LRMC spending P1B to rehabilitate old trains of LRT-1". Interaksyon. June 8, 2017. Retrieved February 26, 2022.
  55. ^ Camus, Miguel R. (February 23, 2018). "LRMC signs P450-M deal for train rehab, upgrade". Inquirer.net.
  56. ^ "Wala pong limit sa diameter ng wheels. Kaugnay naman po ng bagahe, hanggang 2 feet x 2 feet po ang maximum dimension na pinapayagan sa LRT-2". Twitter. Retrieved May 15, 2022.
  57. ^ GMANews.TV, SOPHIA DEDACE (November 18, 2009). "Bikes, trains, and fewer cars with LRT's Bike O2 project". GMA News Online. Retrieved May 15, 2022.
  58. ^ #LRT1 Customer Advisory. March 9, 2022. Retrieved March 9, 2022.
  59. ^ Salamat, Marya (October 14, 2014). "'Best to keep LRT1 run by public servants' — consumer groups". Bulatlat. Retrieved March 25, 2022.
  60. ^ Martin, Sammy (January 11, 2012). "Light rail transit sets new ridership record". The Manila Times. Retrieved January 9, 2022 – via PressReader.
  61. ^ a b Mercurio, Richmond (September 23, 2018). "LRT-1 posts record 14.63 million ridership in August".
  62. ^ Marsigan, Lorenz S. (May 24, 2018). "LRMC sees LRT 1 passengers increasing by 75% in 2021". BusinessMirror.
  63. ^ Light Rail Manila Corporation [@officialLRT1] (May 23, 2023). "Hi! The minute interval is not the train's arrival at the station but the interval of the train that departs at the end line. The train arrival will depend on your location which is every 5-6 minutes in every station. Thank you for your understanding. Ingat po sa biyahe!" (Tweet). Retrieved June 1, 2023 – via Twitter.
  64. ^ a b . Light Rail Transit Authority. Archived from the original on May 17, 2006. Retrieved April 7, 2006.
  65. ^ a b . Kinki Sharyo. Archived from the original on July 17, 2011. Retrieved March 8, 2010.
  66. ^ "MANILA LINE 1 LRV". www.caf.net. Retrieved December 9, 2023.
  67. ^ Cahiles, Gerg (December 30, 2019). "How the Rizal Day bombings changed the PH's security landscape". CNN Philippines. Retrieved December 16, 2021.
  68. ^ Razon, Evangeline M. (June 1998). "The Manila LRT System" (PDF). Japan Railway and Transport Review. 16: 38–39. Retrieved December 15, 2009.
  69. ^ Otaki, Tsutomu (2007). (PDF). KS World. 14. Kinki Sharyo: 12–13. Archived from the original (PDF) on September 28, 2011. Retrieved January 15, 2010.
  70. ^ a b c officiallrt1 (April 4, 2021). "LRMC increases LRT-1 speed to 60kph". Light Rail Manila Corporation. Retrieved April 25, 2021.{{cite web}}: CS1 maint: numeric names: authors list (link)
  71. ^ . Light Rail Transit Authority. March 9, 2006. Archived from the original on April 24, 2006. Retrieved April 7, 2006.
  72. ^ Olchondra, Riza T. (December 7, 2006). "'3G' trains to serve LRTA riders Dec. 11: More comfortable, safer rides assured for commuter". Philippine Daily Inquirer. Archived from the original on February 22, 2013. Retrieved February 7, 2010.
  73. ^ "CAF and Mitsubishi win LRV contract in Manila". Railway PRO. November 21, 2017. Retrieved February 20, 2022.
  74. ^ Camus, Miguel R. (November 21, 2017). "LRT-1 to get new train cars from Japan's Mitsubishi". Inquirer.net.
  75. ^ "CAF awarded Manila rolling stock contract". Metro Report International. November 20, 2017. Retrieved June 7, 2020.
  76. ^ "CAF TO SUPPLY 30 LRVS TO MANILA (THE PHILIPPINES)". Construcciones y Auxiliar de Ferrocarriles. Retrieved May 19, 2019.
  77. ^ Arcangel, Xianne (February 17, 2023). . CNN Philippines. Archived from the original on February 18, 2023. Retrieved February 23, 2023.
  78. ^ Recuenco, Aaron (July 19, 2023). "New, state-of-the-art train sets await LRT-1 riders starting July 20". Manila Bulletin. Retrieved July 19, 2023.
  79. ^ Ronda, Rainier Allan (August 15, 2003). "No more 'sweaty' LRT rides". The Philippine Star. Retrieved November 11, 2023.
  80. ^ . Light Rail Transit Authority. Archived from the original on May 22, 2013. Retrieved January 19, 2010.
  81. ^ Varella, Benjie (September 26, 2003). . The Manila Times. Archived from the original on April 15, 2005. Retrieved April 7, 2006.
  82. ^ . Light Rail Transit Authority. Archived from the original on May 22, 2013. Retrieved June 11, 2014.
  83. ^ officiallrt1 (April 23, 2021). "LRMC and DOST-MIRDC ink knowledge-sharing partnership on rail technology". Light Rail Manila Corporation. Retrieved April 12, 2022.{{cite news}}: CS1 maint: numeric names: authors list (link)
  84. ^ "Construction works launched for LRT-1 Cavite extension". Railway Pro. May 10, 2019. from the original on December 13, 2021. Retrieved December 13, 2021.
  85. ^ a b "LRT Line 1 Expansion of Existing Depot at Baclaran". First Balfour. Retrieved December 3, 2021.
  86. ^ Argosino, Faith (February 23, 2022). "Baclaran Depot of LRT-1 Cavite Extension project completed". Manila Bulletin. Retrieved February 23, 2022.
  87. ^ a b c Japan International Cooperation Agency; Oriental Consultants Co., Ltd.; ALMEC Corporation; Katahira & Engineers International; Tonichi Engineering Consultants, Inc. (July 2013). LRT LINE 1 CAVITE EXTENSION PROJECT (PDF). STUDY ON RAILWAY STRATEGY FOR ENHANCEMENT OF RAILWAY NETWORK SYSTEM IN METRO MANILA OF THE REPUBLIC OF THE PHILIPPINES - FINAL REPORT (Report). Vol. 1. (PDF) from the original on December 27, 2021. Retrieved January 13, 2022.
  88. ^ Japan International Cooperation Agency; Oriental Consultants Co., Ltd.; ALMEC Corporation; Katahira & Engineers International; Tonichi Engineering Consultants, Inc. (July 2013). APPENDICES (PDF). STUDY ON RAILWAY STRATEGY FOR ENHANCEMENT OF RAILWAY NETWORK SYSTEM IN METRO MANILA OF THE REPUBLIC OF THE PHILIPPINES - FINAL REPORT - LRT LINE 1 CAVITE EXTENSION PROJECT (Report). Vol. 1. Retrieved January 13, 2022.
  89. ^ (PDF). Project No. 2 Systematic Replacement of Gantry Anchor Bolts of I-RT 1 Revenue Line. Department of Transportation and Communications. Archived from the original (PDF) on January 26, 2022. Retrieved April 19, 2022.
  90. ^ "LRT 1 rail supplier targets to complete contract in November". Manila Bulletin. February 11, 2015. Retrieved April 8, 2022 – via Yahoo News Philippines.
  91. ^ "Replacement of LRT 1 worn out steel rails to start next month". Manila Bulletin. November 13, 2014. Retrieved February 25, 2022 – via Yahoo News Philippines.
  92. ^ Locsin, Joel (March 7, 2015). "LOOK: LRT-1 tracks replaced at Monumento station". GMA News. Retrieved April 8, 2022.
  93. ^ "Systematic Rail Replacement - 26, 458 lm LRT1 Mainline Tracks". Joratech. Retrieved April 24, 2022.
  94. ^ Cordero, Ted (February 1, 2018). "LRMC to raise LRT1 train speed to 60 kph". GMA News. Retrieved February 25, 2022.
  95. ^ "METRO MANILA URBAN TRANSPORTATION INTEGRATION STUDY: FINAL REPORT SUMMARY" (PDF). Japan International Corporation Agency. March 5, 1999. Retrieved July 17, 2023.
  96. ^ "METRO MANILA URBAN TRANSPORTATION INTEGRATION STUDY TECHNICAL REPORT NO. 7: TRANSPORTATION PROJECT REVIEW" (PDF). Japan International Corporation Agency. 1999. Retrieved July 17, 2023.
  97. ^ Valencia, L. B. (April 1, 2002). . Manila Bulletin. Archived from the original on February 19, 2022. Retrieved February 19, 2022.
  98. ^ Valencia, L. B. (September 15, 2004). . Manila Bulletin. Archived from the original on April 15, 2005. Retrieved February 14, 2022 – via Light Rail Transit Authority.
  99. ^ a b (PDF). MANILA LRT LINE 1 SOUTH EXTENSION PROJECT. Light Rail Transit Authority. 2006. Archived from the original (PDF) on July 20, 2007. Retrieved February 14, 2022.
  100. ^ (PDF). MANILA LRT LINE 1 SOUTH EXTENSION PROJECT. Light Rail Transit Authority. 2006. Archived from the original (PDF) on February 21, 2007. Retrieved February 14, 2022.
  101. ^ Montecillo, Paolo (February 25, 2010). . Philippine Daily Inquirer. Archived from the original on February 27, 2010. Retrieved February 14, 2022.
  102. ^ Ang, Dean (March 23, 2012). "Government approves LRT Line 1 Cavite Extension Project". AutoIndustriya.com. Retrieved November 11, 2023.
  103. ^ a b Barrow, Keith (May 4, 2017). "Manila breaks ground on LRT 1 Cavite extension". International Railway Journal. Simmons-Boardman Publishing. Retrieved May 4, 2017.
  104. ^ a b Cordero, John Ted (May 4, 2017). "DOTr, LRMC break ground for LRT-1 Cavite extension project". GMA News Online. Retrieved May 5, 2017.
  105. ^ "LRT Line 1 Cavite Extension and Operation & Maintenance". ppp.gov.ph. Public-Private Partnership Center. Retrieved July 6, 2021.
  106. ^ Cordero, Ted (July 4, 2018). "Tugade says LRT1 Cavite extension to be completed in 2021". GMA News Online. Retrieved July 8, 2018.
  107. ^ Orellana, Faye (May 7, 2019). "Construction of LRT-1 Cavite extension begins". Philippine Daily Inquirer. Retrieved July 20, 2021.
  108. ^ Abadilla, Emmie V. (April 13, 2023). "Phase1 LRT-1 Cavite Extension extension cost balloons due to delays". Manila Bulletin. Retrieved November 11, 2023.
  109. ^ . NationBuilder PH. Archived from the original on February 5, 2022. Retrieved February 5, 2022.
  110. ^ Dela Cruz, Raymond Carl (February 7, 2022). "LRMC, contractor complete LRT-1 Cavite Extension viaduct". Philippine News Agency. Retrieved February 14, 2022.
  111. ^ "LRT-1 Cavite Extension features world-class construction technology". Wheels.ph. October 1, 2020.
  112. ^ "Manila". RATP Dev.
  113. ^ Cabuag, VG (August 17, 2023). "Villar: PAVI wants to extendLRT-1 up to Silang in Cavite". BusinessMirror. Retrieved November 11, 2023.
  114. ^ Yu, Lance Spencer (December 20, 2023). "FAST FACTS: What's the LRT-1 Cavite Extension?". Rappler. Retrieved December 20, 2023.
  115. ^ Rosel, Trixee (November 11, 2023). "Progress rate of LRT-1 extension construction now at 94%". Manila Bulletin. Retrieved November 11, 2023.
  116. ^ Dumlao-Abadilla, Doris (March 15, 2022). "LRT-1 Cavite extension gears up for 2024 start of operations". INQUIRER.net. Retrieved March 15, 2022.
  117. ^ Cordero, Ted (March 6, 2024). "Phase 1 of LRT1 Cavite extension now 97% complete - LRMC". Retrieved March 7, 2024.
  118. ^ Tubeza, Philip (July 8, 2003). . Inquirer. Philippine Daily Inquirer. Archived from the original on December 6, 2003.
  119. ^ . Department of Justice (Republic of the Philippines). July 7, 2003. Archived from the original on July 25, 2008.
  120. ^ "Baclaran fire disrupts LRT operations". GMA News and Public Affairs. January 3, 2008. Retrieved November 1, 2021.
  121. ^ "LRT closes Baclaran station again". GMA News and Public Affairs. January 4, 2008. Retrieved November 1, 2021.
  122. ^ "LRT Baclaran terminal resumes operation; mall fire 'under control'". GMA News and Public Affairs. August 13, 2008. Retrieved November 1, 2021.
  123. ^ Dedace, Sophia (December 8, 2008). "LRT Line-1 trips disrupted – report". GMA News. GMA News and Public Affairs. Retrieved November 1, 2021.
  124. ^ Castro, Doland (February 18, 2011). "2 LRT trains collide". ABS-CBN News. Quezon City, Metro Manila: ABS-CBN News and Current Affairs. from the original on May 26, 2020. Retrieved May 26, 2021.
  125. ^ "Door problem disrupts LRT operations anew". GMA News and Public Affairs. April 15, 2011. Retrieved November 1, 2021.
  126. ^ "Lightning disrupts LRT-1 operations for 3 hours". GMA News and Public Affairs. June 21, 2011. Retrieved November 1, 2021.
  127. ^ Cayabyab, Zhander (August 30, 2012). "Woman commits suicide inside LRT station". ABS-CBN News. Retrieved November 10, 2021.
  128. ^ "Glitch disrupts LRT-1 operations in Monumento". GMA News and Public Affairs. December 21, 2012. Retrieved November 1, 2021.
  129. ^ "Glitch isolates LRT-1's Roosevelt station". GMA News and Public Affairs. November 14, 2014. Retrieved November 1, 2021.
  130. ^ Gonzales, Yuji Vincent (May 23, 2015). "2 LRT trains collide due to technical glitch; at least 1 hurt". INQUIRER.net. South Caloocan, Metro Manila. from the original on February 4, 2016. Retrieved May 26, 2021.
  131. ^ Palma, Paola (May 23, 2015). . CNN Philippines. Metro Manila. Archived from the original on January 1, 2016. Retrieved May 26, 2021.
  132. ^ . CNN Philippines. March 11, 2016. Archived from the original on March 18, 2016. Retrieved October 30, 2021.
  133. ^ Bajo, Ramil; Galupo, Rey (March 23, 2016). "LRT passengers trapped as LRT doors fail to open". The Philippine Star. Retrieved October 30, 2021.
  134. ^ People Trapped inside LRT and One Passed Out Because the Door Won't Open!. YouTube (video). Archived from the original on December 14, 2021.
  135. ^ Yee, Jovic (September 28, 2016). "LRT-1 door slams shut on passengers; no one hurt". Philippine Daily Inquirer. Retrieved October 30, 2021.
  136. ^ Bajo, Anna Felicia (November 7, 2017). "Man ends up in ICU after foot got stuck in moving LRT train's door". GMA News. Retrieved October 30, 2021.
  137. ^ Bacungan, VJ (November 28, 2017). . CNN Philippines. Archived from the original on October 30, 2021. Retrieved October 30, 2021.
  138. ^ Pascual, Jekki; Aquino, Lyza; Reyes, Isay (February 20, 2018). "LRT-1, MRT nagkaaberya, nagpababa ng mga pasahero". ABS-CBN News. Retrieved June 1, 2021.
  139. ^ "Mga pasahero ng LRT-1 pinababa matapos magka-aberya". ABS-CBN News (in Filipino). July 21, 2018. Retrieved November 1, 2021.
  140. ^ "YOU SHALL NOT PASS: Malfunctioning train door closes by itself, makes disembarking a challenge for commuters". Coconuts Manila. September 28, 2018. Retrieved October 30, 2021.
  141. ^ Galvez, Daphne (October 3, 2019). "Glitch stalls LRT-1's Monumento – Roosevelt operations". Philippine Daily Inquirer. Retrieved May 26, 2021.
  142. ^ Marquez, Consuelo (November 6, 2020). "LRT-1 train catches fire in Pasay; management limits train ops". INQUIRER.net. Retrieved April 25, 2021.
  143. ^ Marquez, Consuelo (November 6, 2020). "LRT-1 resumes regular operations after technical woes at Gil Puyat Station". INQUIRER.net. Retrieved May 26, 2021.
  144. ^ "LRT1 ops temporarily affected by train glitch; normal ops resumed —LRMC". GMA News. April 4, 2022. Retrieved May 5, 2022.
  145. ^ Cua, Aric John Sy (February 17, 2023). "LRT-1 operations limited after electrical problems". The Manila Times. Retrieved February 17, 2023.
  146. ^ 25kph speed restriction has been put in place from Baclaran to Roosevelt. Twitter. April 14, 2023. Retrieved April 14, 2023.
  147. ^ A stop for safety has been put in place from Baclaran to Roosevelt. Twitter. April 14, 2023. Retrieved April 14, 2023.
  148. ^ Limited operations of LRT-1. Twitter. April 14, 2023. Retrieved April 14, 2023.
  149. ^ Resumed operations. Twitter. April 14, 2023. Retrieved April 14, 2023.

External links edit

  •   Media related to LRT Line 1 (Metro Manila) at Wikimedia Commons
  • Light Rail Manila Corporation

line, metro, manila, line, redirects, here, light, rail, transit, systems, indonesia, palembang, cibubur, line, light, rail, transit, line, commonly, referred, line, light, rapid, transit, system, line, metro, manila, philippines, operated, light, rail, manila. LRT Line 1 redirects here For the light rail transit systems in Indonesia see Palembang LRT and Cibubur Line The Light Rail Transit Line 1 commonly referred to as LRT Line 1 or LRT 1 is a light rapid transit system line in Metro Manila Philippines operated by Light Rail Manila Corporation LRMC and owned by the Light Rail Transit Authority LRTA as part of the Manila Light Rail Transit System Originally referred to as Metrorail and the Yellow Line LRT Line 1 was reclassified to be the Green Line in 2012 It travels in a general north south direction from Baclaran to Monumento and then east west from Monumento to Fernando Poe Jr Currently the line consists of 20 stations and runs on 19 65 kilometers 12 21 miles of fully elevated route Although it has the characteristics of light rail such as with the type of rolling stock used it is more akin to a rapid transit system owing to its total grade separation and high passenger throughput LRT Line 1LRTA 13000 class train at Balintawak station August 2023OverviewStatusOperationalOwnerDepartment of TransportationLight Rail Transit AuthorityLine number1LocaleMetro Manila PhilippinesTerminiFernando Poe Jr BaclaranStations20WebsiteLRTA LRMCServiceTypeLight rapid transitSystemManila Light Rail Transit SystemServices1Operator s Light Rail Manila CorporationFormer operators Meralco Transit Organization 1984 2000 Light Rail Transit Authority 2000 2015 Depot s BaclaranZapote future Rolling stockLRTA 1000 classLRTA 1100 classLRTA 1200 classLRTA 13000 classDaily ridership216 667 2022 1 Ridership78 million 2022 1 HistoryOpenedDecember 1 1984 39 years ago 1984 12 01 2 Last extensionOctober 22 2010 13 years ago 2010 10 22 3 TechnicalLine length19 65 km 12 21 mi Number of tracksDouble trackCharacterElevatedTrack gauge1 435 mm 4 ft 8 1 2 in standard gaugeLoading gauge4 050 mm 2 600 mm 13 ft 3 in 8 ft 6 in 4 Minimum radiusMainline 100 m 330 ft Depot 25 m 82 ft Electrification750 V DC overhead lines 5 Operating speed60 km h 37 mph SignallingAlstom Atlas 100 ETCS Level 1 6 7 Former systems ACEC fixed block relay type ATS 1984 2007 8 Siemens fixed block ATP ATS 2007 2022 Maximum inclineMainline 3 535 9 Depot spur line 4 9 Average inter station distance903 65 m 2 964 7 ft Route diagramLegend extension under construction MMS Line 3 North Avenue Line 7 3 7 MMS MMS under construction Fernando Poe Jr Balintawak E1 AH 26 E1 N160 North LuzonExpressway Quezon CityCaloocan Monumento 5th Avenue CaloocanManila R Papa Abad Santos Blumentritt PNR Tayuman Bambang Doroteo Jose Recto Line 2 Carriedo Pasig River Central Terminal United Nations Pedro Gil Quirino Vito Cruz ManilaPasay Gil Puyat Libertad EDSA 3 Taft Avenue Line 3 Pasay Depot Baclaran extension under construction PasayParanaque underconstruction Redemptorist MIA Asia World Ninoy Aquino Dr Santos ParanaqueLas Pinas Las Pinas Las PinasBacoor Zapote Depot Zapote Niog This diagram viewtalkedit First envisioned in a 1977 study conducted by Freeman Fox and Associates which suggested a street level railway in Manila the government revised this recommendation to an elevated system In 1980 President Ferdinand Marcos created the LRTA and construction of the line began the following year With its partial opening in 1984 and completion the following year it became the first rapid transit service in Southeast Asia 10 LRT Line 1 would become one of the busiest among Metro Manila s three rapid transit lines it served 216 667 daily average passengers in 2022 making it the second busiest just behind the MRT Line 3 1 The line is integrated with the public transit system in Metro Manila and passengers also take various forms of road based public transport such as buses and jeepneys to and from a station to reach their intended destination Although the line aimed to reduce traffic congestion and travel times in Metro Manila the transportation system has only been partially successful due to the rising number of motor vehicles and rapid urbanization Expanding the network s revenue line to accommodate more passengers through extension projects 11 is set on resolving this problem 12 Contents 1 Route 1 1 Stations 1 2 Operations and services 2 History 2 1 Planning and funding 2 2 Construction and opening 2 3 Capacity expansions 2 3 1 First phase 2 3 2 Second phase 2 4 North extension 2 5 Privatization 2 6 Rehabilitation 3 Station facilities amenities and services 3 1 Station layout and accessibility 3 2 Shops and services 4 Ridership 5 Rolling stock 5 1 Depot 6 Other infrastructure 6 1 Signalling 6 2 Tracks 7 Extensions 7 1 South extension 8 Incidents and accidents 8 1 Rizal Day bombings 8 2 Other incidents 9 References 10 External linksRoute editThe line is predominantly aligned to the path of Taft Avenue Radial Road 2 which was chosen largely due to its straight course Later on as Taft Avenue ends it shifts to Rizal Avenue and Rizal Avenue Extension Radial Road 9 then turning right on EDSA before ending at the corner of North and West Avenues and EDSA The south extension will span from the Quirino Avenue Harrison Avenue and Taft Avenue Extension intersection then would travel down from Redemptorist Road Roxas Boulevard and Manila Cavite Expressway afterwards it will traverse through the Paranaque River and will enter Ninoy Aquino Avenue until reaching and traversing the C5 Extension Road and will once again enter Coastal Road crossing the Las Pinas Bacoor Boundary Bridge along the Zapote River and traverse through the Alabang Zapote Road and Aguinaldo Highway intersection until reaching Niog station located along Bacoor Boulevard in Bacoor Cavite The line links the cities of Quezon City Caloocan Manila and Pasay with the upcoming stations passing through the cities of Paranaque Las Pinas and Bacoor in Cavite Stations edit The line serves 20 stations along its route A twenty first station is yet to be constructed 13 Eight stations which are part of the south extension are also set to be constructed south of Baclaran Malvar station in Caloocan was previously proposed during the construction of the northern extension located between Monumento and Balintawak becoming a bargaining object during the entire extension line s construction in the jurisdiction of Caloocan However the planned Malvar station was completely shelved by the Aquino administration 14 Three stations serve as connecting stations between other lines in the metro Doroteo Jose is indirectly connected to the Recto of the LRT Line 2 through a covered walkway Blumentritt is immediately above its PNR Metro Commuter Line counterpart and EDSA is connected to the Taft Avenue station via a covered walkway No stations are connected to other rapid transit lines within the paid areas though that is set to change when the North Triangle Common Station which has interchanges to MRT Line 3 and MRT Line 7 opens in 2023 Legend Existing terminus List of stations Name Distance km Connections Location Betweenstations Total North Triangle Interchange with nbsp Manila MRT 3 7 nbsp Manila MRT MMS North Avenue nbsp Bus routes 18 33 64 SM North EDSA Quezon City Fernando Poe Jr 0 000 nbsp EDSA Carousel 1 Roosevelt Avenue Balintawak 1 870 1 870 nbsp EDSA Carousel 1 Balintawak Interchange nbsp Bus routes 5 8 9 13 19 20 21 22 37 38 40 52 Ayala Malls Cloverleaf Monumento 2 250 4 120 nbsp EDSA Carousel 1 Monumento nbsp Bus routes 9 14 35 37 42 54 Monumento Caloocan 5th Avenue 1 087 5 207 nbsp Bus routes 8 14 35 42 54 5th Avenue R Papa 0 954 6 161 nbsp Bus routes 8 42 54 R Papa Manila Abad Santos 0 660 6 821 nbsp Bus routes 8 42 54 Hermosa Street Blumentritt 0 927 7 748 nbsp PNR nbsp Blumentritt nbsp Bus routes 42 Blumentritt Tayuman 0 671 8 419 nbsp Bus routes 42 Tayuman Bambang 0 618 9 037 nbsp Bus routes 42 Bambang Street Doroteo Jose 0 648 9 685 nbsp Manila LRT nbsp Recto nbsp Manila MRT 8 Lerma nbsp Bus routes 2 3 Hidalgo Street 13 19 20 21 Avenida 42 Doroteo Jose 5 6 7 14 17 34 38 40 49 52 53 54 Quiapo Carriedo 0 685 10 370 nbsp Pasig River Ferry Service nbsp Escolta Ferry Station Central Terminal 0 725 11 095 nbsp Bus routes 5 6 7 14 17 23 24 25 27 34 38 40 42 48 49 52 53 54 Liwasang Bonifacio nbsp Pasig River Ferry Service nbsp Lawton Ferry Station United Nations 1 214 12 309 nbsp Bus routes 5 6 7 14 17 23 24 25 27 34 38 40 42 48 49 53 54 UN Avenue Pedro Gil 0 754 13 063 nbsp Bus routes 5 6 7 14 17 23 24 25 27 34 38 40 42 48 49 53 Herran Street Quirino 0 794 13 857 nbsp Bus routes 5 6 7 14 17 23 24 25 27 34 38 40 42 48 49 53 Quirino Avenue Vito Cruz 0 827 14 684 nbsp Bus routes 5 6 7 14 17 23 24 25 27 34 38 40 42 48 49 53 Ocampo Street Gil Puyat 1 061 15 745 nbsp Bus routes 5 6 7 10 11 12 14 17 23 24 25 27 34 38 40 42 48 49 53 62 Buendia Avenue 4 Taft Avenue Pasay Libertad 0 730 16 475 EDSA 1 010 17 485 nbsp Manila MRT 3 Taft Avenue nbsp EDSA Carousel 1 Taft Avenue Baclaran 0 588 18 073 Redemptorist nbsp Bus routes 35 49 Baclaran Paranaque Manila International Airport nbsp Bus routes 35 49 MIA Road Asia World nbsp EDSA Carousel 1 PITX nbsp Bus routes 4 5 6 7 14 18 22 23 26 27 28 29 30 31 32 34 43 47 52 55 PITX Ninoy Aquino Dr Santos Las Pinas Las Pinas Zapote nbsp Bus routes 23 27 29 31 32 Longos Bacoor Cavite Niog Proposed interchange with nbsp Manila LRT 6 nbsp Bus routes 27 29 31 Niog 32 SDMC Stations lines and or other transport connections in italics are either under construction proposed unopened or have been closed Operations and services edit The line operates from 4 30 a m PST UTC 8 until 10 15 p m on weekdays and 5 00 a m until 9 45 p m on weekends and holidays 15 It operates almost every day of the year unless otherwise announced Special schedules are announced via the PA system in every station and also in newspapers and other mass media During Holy Week a public holiday in the Philippines the rail line is closed for annual maintenance owing to fewer commuters and traffic around the metro Normal operation resumes after Easter Sunday 16 During the Christmas and year end holidays the operating hours of the line are shortened due to the low ridership of the line during the holidays 17 History editPlanning and funding edit nbsp LRTA Class 1000 being built in Bruges in 1982 The 1977 Metro Manila Transport Land Use and Development Planning Project MMETROPLAN a fourteen month study conducted by Freeman Fox and Associates and funded by the World Bank recommended the construction of a street level light rail line in Manila Following a review by the Ministry of Transportation and Communications later the Department of Transportation DOTr the proposal was revised to an elevated railway to avoid building over the city s many intersections 18 while the option for an underground line was rejected due to the high water table in Manila 19 this raised the project s cost from 1 5 billion to 2 billion An alignment along Rizal and Taft avenues which spanned from Monumento Caloocan in the north to Baclaran Pasay in the south was selected because it followed a relatively straight path for most of its route 18 36 On July 12 1980 President Ferdinand Marcos created the Light Rail Transit Authority LRTA and assigned First Lady and Governor of Metro Manila Imelda Marcos as its chairman While the LRTA confined its roles to policy making fare regulation and future planning the line s operations were assigned to Metro Inc a sister company of Meralco The line came to be referred to as Metrorail 20 The Belgian Government granted a 300 million soft and interest free loan for the project s construction with a repayment period of 30 years Additional funding was later sourced from a 700 million loan provided by a Belgian consortium consisting of ACEC La Brugeoise et Nivelles Tractionnel Engineering International and Transurb Consult The consortium also supplied the line s first light rail vehicles power control signalling and telecommunications as well as provided training and technical assistance Designed as a public utility rather than a profit center the line was expected to incur a deficit through 1993 but complete its repayments within a period of 20 years 20 Construction and opening edit The government owned Construction Development Corporation of the Philippines was the project s sole contractor 18 36 Single column cast in place concrete piers carrying precast concrete T girders and a concrete deck slab were used for the original line from Monumento to Baclaran The columns are spaced apart by 20 to 27 meters 66 to 88 ft rising from a cap on top of bored or driven concrete piles Four of the 2 1 meter 7 ft wide girders are side by side in each span to accommodate bidirectional standard gauge railway tracks located 6 1 meters 20 ft above the street level 19 Driven piles were originally used for 80 percent of the project with spread footings being used for the remaining portion However during construction it was determined that bored piles should be utilized in some areas to mitigate noise and avoid potential damage to nearby buildings Additionally the original use of stockpiled precast piles caused clutter on the streets during construction 19 In 1981 an economic recession hit the country and the government s were unable to provide counterpart funds for civil works and right of way acquisition which amounted to 60 percent of the project s total cost led to a delay in construction 21 170 Work finally resume after the Economic Recession and the EDSA Revolution in September of that year along Taft Avenue between Epifanio de los Santos Avenue EDSA and Libertad Street 22 In order to make way for Carriedo station and a segment of tracks approaching the Pasig River a department store and a classroom building owned by FEATI University were demolished 18 36 The southern section between the Baclaran and United Nations stations was inaugurated on September 11 1984 by President Ferdinand Marcos Commercial operations along this section commenced on December 1 The line became fully operational on May 12 1985 when the northern section between Central Terminal and Monumento opened During the first several years two car trains that could accommodate up to 748 passengers were utilized This amounted to a capacity of 20 000 passengers per direction 23 Capacity expansions edit First phase edit nbsp The trains procured under the first phase of the capacity expansion in November 2006 Line 1 would eventually reach capacity in the 1990s due to traffic congestion and air pollution The line fell so far into disrepair due to premature wear and tear that trains headed to Central Terminal station had to slow to a crawl to avoid further damage to the support beams below as cracks reportedly began to appear 18 The premature aging of Line 1 led to an extensive refurbishing and structural capacity expansion program with a help of Japan s official development assistance 12 The capacity expansion project was one of the flagship projects of the administration of President Fidel V Ramos 12 A loan agreement for the first phase of the capacity expansion project was signed in 1994 12 In August 1996 a consortium of Marubeni Corporation Adtranz and ABB was awarded the contract and was signed the following September 24 25 The project undertaken at a cost of 4 1 billion 26 involves the procurement of seven four car trains that were ordered from Hyundai Precision and the refurbishment and conversion of the original two car trains into three car trains in 1999 In line with the introduction of the four car trains the station platforms were also extended 12 The project was completed in 2002 12 During the first phase of the capacity expansion a labor strike was launched by employees of Meralco Transit Organization METRO Inc in July 2000 as their operations and maintenance contract with the Light Rail Transit Authority LRTA was about to expire It paralyzed the operations of the line for a week The LRTA decided not to renew its contract with METRO Inc that expired on July 31 2000 and the former assumed operational responsibility 27 LRTA undertook this responsibility until September 12 2015 when the operations and maintenance of the line were privated to the Light Rail Manila Corporation for thirty two years as part of the line s south extension Second phase edit nbsp The trains procured under the second phase of the capacity expansion undergoing a test run in November 2006 Another capacity expansion project was initiated in April 2000 during the administration of President Joseph Estrada due to the high demand of passengers in line with the completion of the MRT Line 3 and eventually LRT Line 2 28 26 Funded through an 8 893 billion loan from the Japan Bank for International Cooperation 29 the second phase of the capacity expansion project was divided into two packages Package A involves the procurement of twelve four car trains upgrades to the signalling and communications equipment and upgrades to the stations and depot Package B on the other hand involves the procurement and installation of air conditioning units for the 1000 class trains replacement of faulty air conditioning units of the 1100 class trains renovation of 4 kilometers 2 5 miles of railway track and railway sleepers and procurement of equipment and spare parts used for track works The installation of equipment for the automatic fare collection system was also included in the capacity expansion project 28 North extension edit See also MRT Line 3 Metro Manila Line merge with LRT Line 1 nbsp Balintawak station one of the two stations constructed under the north extension project in 2016 With the completion of the first phase of the MRT Line 3 in 1999 there were plans to extend Line 3 towards Monumento station Phase 2 to create a seamless rail loop around Metro Manila 30 However the extension was shelved by then President Gloria Macapagal Arroyo in favor of a 5 7 kilometer 3 5 mile extension of the LRT 1 to the MRT 3 North Avenue station The project involved the construction of three stations Balintawak Roosevelt renamed Fernando Poe Jr and a common station at North Avenue However due to disputes in the common station s location the station would only begin construction in 2017 This was also known as the MRT LRT Closing the Loop project In September 2008 then mayor of Caloocan Enrico Echiverri petitioned the government to construct Malvar station an intemediary station between Balintawak and Monumento 31 Two months later two thousand residents from Barangay Bagong Barrio where the station would be built staged a protest along EDSA to urge the government to build the station 32 Malvar station would eventually be approved in July 2009 33 Though it was reported that the feasibility study for the station was completed 34 construction has yet to start Construction eventually began in June 2008 35 The joint venture of DMCI and First Balfour built the viaduct and the two stations 36 while the electrical and mechanical systems contracts were assigned to different contractors 34 37 The project was intended to integrate the LRT Line 1 and MRT Line 3 operations Structure gauge tests were eventually conducted in the extension by February 2010 which found that the LRT Line 1 trains can run on MRT Line 3 tracks 38 On February 25 2010 as part of the 24th anniversary of the People Power Revolution President Arroyo and Vice President Noli de Castro rode an MRT 3 train from Santolan to North Avenue before transferring to a Line 1 train that passed along the extension until Monumento 39 Balintawak station opened on March 22 2010 40 while FPJ station opened seven months later on October 22 3 To integrate the operations of the LRT Line 1 and MRT Line 3 the then Department of Transportation and Communications under Secretary Jose de Jesus launched an auction for a temporary five year operations and maintenance contract for the two lines The bidding was set by July 2011 Over 21 companies from around the world expressed interest to bid which included Metro Pacific Investments Sumitomo Corporation Siemens DMCI Holdings San Miguel Corporation and others 41 After de Jesus resigned from the DOTC 42 his successor Mar Roxas halted the auction process and was later shelved 43 An extension to the North Triangle Common Station is set to open in 2023 Privatization edit A plan to privatize the line was pursued as part of the south extension project The bidding was set for August 2013 but failed 44 The project was rebidded and on September 12 2014 the operation and maintenance of LRT Line 1 and the construction of a 65 billion extension project to Bacoor Cavite was awarded to the Light Rail Manila Corporation LRMC a joint venture company of Metro Pacific s Metro Pacific Light Rail Corporation MPLRC Ayala Corporation s AC Infrastructure Holdings Corporation AC Infra and the Philippine Investment Alliance for Infrastructure s Macquarie Infrastructure Holdings Philippines PTE Ltd MIHPL with Sumitomo Corporation following in May 2020 45 46 The consortium signed a concession agreement with the DOTr and LRTA on October 2 2014 47 48 LRMC contracted the operation and maintenance of the line for 20 years to RATP Dev under its subsidiary RATP Dev Transdev Asia a joint venture between Transdev and RATP Dev on December 8 2014 49 50 The 32 year concession started on September 12 2015 Rehabilitation edit A rail replacement program commenced in 2016 as a continuation of the previous rail replacement program completed by the Light Rail Transit Authority 51 LRMC signed a contract with First Balfour for the structural restoration project of Line 1 on April 19 2017 52 and in November 2018 LRMC tapped First Balfour and MRail a subsidiary of Meralco for the rehabilitation of rectifier substations 53 LRMC has also rehabilitated the first and second generation trains to add more trains servicing the line 54 55 Station facilities amenities and services edit nbsp Baclaran station the line s southern terminus in 2008 All stations in Line 1 are elevated with the exception of Zapote station Station layout and accessibility edit Most stations are composed of only one level accessible from the street below by stairway containing the station s concourse and platform areas separated by fare gates Some stations tend to have a concourse level below the platforms The single level stations of Line 1 however was not built with accessibility in mind due to the lack of barrier free facilities such as escalators and elevators Some stations such as Monumento and EDSA are connected at concourse level to nearby buildings such as shopping malls for easier accessibility Some trains have spaces for passengers using wheelchairs As of November 8 2009 folding bicycles are allowed to be brought into trains provided that it does not exceed the LRTA s baggage size limitations of 2 by 2 feet 20 by 20 in 56 The last car of each train are also designated as green zones where folding bicycle users can ride with their bikes 57 All stations have side platforms except for Baclaran which has one side and one island platform Due to the high patronage of the line part of the platform corresponding to the front car of the train is cordoned off for the use of women children elderly and disabled passengers 58 Shops and services edit Inside the concourse of some stations are stalls or shops where people can buy food or drinks Stalls vary by station and some have fast food stalls The number of stalls also varies by station and some stations tend to have a wide variety Stations such as Monumento and Baclaran are connected to or are near shopping malls and or other large shopping areas where commuters are offered more shopping varieties Ridership editThe current designed daily ridership of the line is 560 000 passengers 59 and currently aims to increase the number of passengers being served on the line to more than 800 000 passengers as the line s south extension is set to be fully operational by 2027 On January 9 2012 the line served a record 620 987 passengers during the Feast of the Black Nazarene Carriedo station is near to the Quiapo Church and since the day falls on a working weekday 60 In 2018 the line carried 300 000 to 500 000 passengers daily due to the increased number of trains from 86 vehicles to 113 vehicles available for daily trips This gradually reduces the waiting time of passengers from 5 minutes to as much as 2 to 3 5 minutes 61 62 It also carried as much as 14 63 million passengers monthly in 2018 61 However as of 2023 the waiting time has been officially reported at 5 to 6 minutes 63 Rolling stock edit nbsp Different types of rolling stock at the line s depot in Baclaran Pasay The newer fourth generation trains are the red trains on the right The line at various stages in its history has used different configurations of two car three car and four car trainsets The two car trains are the original first generation BN and ACEC trains railway cars numbered from 1000 Most were transformed into three car trains although some two car trains remain in service The four car trains are the more modern second generation Hyundai Precision Adtranz 1100 third generation Kinki Sharyo Nippon Sharyo 1200 and fourth generation Construcciones y Auxiliar de Ferrocarriles CAF Mitsubishi 13000 64 65 66 There are 259 railway cars grouped into 126 trains serving the line 63 of these are first generation 28 second generation 48 third generation and 120 fourth generation cars Some of the cars especially those from 1st generation were decommissioned due to them being cannibalized or involved in accidents Such as 1037 which was severely damaged in the Rizal Day bombings in 2000 it was subsequently decommissioned afterwards and eventually scrapped 5 67 The maximum design speed of these cars ranges between 60 and 70 kilometers per hour 37 and 43 mph but only run at a maximum operational speed of 60 kilometers per hour 37 miles per hour 68 69 Until 2011 all trains ran at the maximum speed until it was downgraded to 40 kilometers per hour 25 miles per hour due to the deteriorating condition of the railway tracks except for the north extension which continued running on the 60 km h 37 mph maximum speed After a three year rail replacement program the operating speed was restored to 60 km h 37 mph on April 5 2021 70 The line s fleet is being modernized to cope with increasing numbers of passengers In the initial phase of its capacity expansion program completed in 1999 the line s seven four car second generation trains were commissioned providing an increased train capacity of 1 358 passengers while the original two car trains capable of holding 748 passengers were transformed into three car trains with room for 1 122 64 As part of the second phase of expansion twelve new trains made in Japan by Kinki Sharyo and Nippon Sharyo were purchased in 2005 and were introduced in December 2006 providing a capacity of 1 388 passengers 29 65 71 72 The fourth generation trains ordered in 2017 with Japanese funding for the south extension to replace the first generation trains 73 74 75 76 were delayed in deployment due to the need to rectify factory defects in the roofs of the units that went undetected prior to delivery due to the inability to conduct factory inspections during the COVID 19 pandemic 77 Rectification works were conducted with costs shouldered by the manufacturer The new train sets entered revenue service on July 20 2023 78 Prior to 1999 the first generation trains were notorious for its lack of air conditioning relying instead on forced air roof ventilation for cooling 79 This however resulted in hot and stuffy rides Although the entry of the second generation trains in 1999 marked the introduction of air conditioned trains in the line the problem was fully addressed after a preparatory rehabilitation program completed in 2001 allowed the installation of air conditioners to the older rolling stock in 2004 80 81 82 LRMC has also built an in house laboratory for production manufacturing fabrication and repair of train parts that are no longer available in the market 83 The Passenger Assist Railway Display System a passenger information system powered by LCD screens installed near the ceiling of the train that shows news advertisements current train location arrivals and station layouts are already installed in the third generation trains along with the trains of Line 2 and the first generation trains of Line 3 As of the 4th quarter of 2023 these units were discreetly removed and prior to removal were no longer operating Rolling stock of LRT Line 1 nbsp First generation LRTA 1000 class 1984 nbsp Second generation LRTA 1100 class 1999 nbsp Third generation LRTA 1200 class 2006 nbsp Fourth generation LRTA 13000 class 2023 Depot edit The line maintains an at grade depot in Baclaran Pasay It serves as the center of the operations and maintenance of the line It is connected to the mainline through a spur line Before its expansion the depot had a capacity of 145 light rail vehicles and an area of 6 4 hectares 16 acres 84 It was expanded to an area of 10 6 hectares 26 acres to accommodate 197 vehicles with Shimizu Corporation and First Balfour implementing the project 85 Expansion works were completed after the depot was inaugurated on February 23 2022 86 A satellite depot is being constructed in Zapote as part of the line s south extension project When completed the satellite depot will handle 72 light rail vehicles 85 Other infrastructure editSignalling edit nbsp Alstom Atlas 100 signal lights Throughout its history the line used different signalling systems The line currently uses the Alstom Atlas 100 solution based on ETCS Level 1 The original signalling system used in the LRT Line 1 was based on fixed block and relay type trackside systems Trains had an automatic train stop system that activates if the train passes by a red signal or over speeding Based on a procurement plan published by the Light Rail Transit Authority most of the signalling equipment including track circuits were supplied by ACEC 8 In 2007 as part of a capacity expansion project the signalling system was replaced with a signalling and train control system based on automatic train protection ATP and automatic train supervision ATS using Siemens technology The ATP system monitors the speed of the trains while the ATS system directs train operations Prior to the 2022 upgrade the signalling system was designed to operate at a headway of 112 seconds 5 87 Aside from the ATP and ATS systems its subsystems include train detection through axle counters and microprocessor based interlocking 87 The signalling system was again upgraded as part of the line s south extension Alstom was awarded a contract in February 2016 to supply the signalling and communications systems for the line 7 Alstom supplied the Atlas 100 solution based on ETCS Level 1 The testing and commissioning phase of the upgraded signalling system started in November 2021 and was completed on February 1 2022 6 Tracks edit nbsp nbsp twinblock ties employed on the Direct fixation tracks left and Ballast tracks right The tracks have three types ballasted slab tracks and concrete plinth Ballasted sections are found in the original 13 95 kilometer 8 67 mile section from Baclaran to Monumento while slab tracks are found in the north extension and the newer Cavite extension uses concrete plinths like the MRT 3 and LRT 2 For the ballasted and ballastless tracks the rails are supported by twin block concrete railroad ties and have a track center distance of 3 2 meters 10 feet 87 88 The tracks in the original 13 95 kilometer 8 67 mile line consist of 50 kilogram per meter 100 pound per yard rails designed to the EB 50T rail profile while the tracks in the future extension line consist of 54 kilogram per meter 110 pound per yard rails designed to the UIC 54 rail profile 9 Due to the deterioration of the rail tracks in the original line speed restrictions were implemented in 2011 except for the north extension 70 In 2012 a contract to replace 23 kilometers 14 miles of rails was awarded to the joint venture of Oriental and Motolite Marketing Corporation Korail Erin Marty Fabricators Company Inc and Jorgman Construction and Development Corporation 89 However there were delays in the project implementation until February 2014 when the then Department of Transportation and Communications issued a notice to proceed for the joint venture 90 The first phase of the replacement started in 2014 91 while the rails at Monumento station were replaced in March 2015 92 The first phase of the rail replacement was completed in December 2015 51 The second and final phase of replacement works commenced in August 2016 by the Light Rail Manila Corporation 51 which contracted Joratech 93 to replace 26 kilometers 16 miles of rails 51 and was completed in 2017 94 This was intended to increase the operating speed from 40 kilometers per hour 25 miles per hour to 60 kilometers per hour 37 miles per hour and was achieved on April 5 2021 70 Extensions editSouth extension edit nbsp Construction of the Cavite Extension Project viaduct along Ninoy Aquino Avenue in July 2021 nbsp The girder launcher along Radial Road 1 approaching Roxas Boulevard in November 2021 nbsp Construction of Manuyo Uno station viaduct along C 5 Road Extension in April 2023 nbsp Construction of Manila Line 1 south extension depot Manuyo Uno station along C 5 Road Extension in April 2023 Plans for an extension to the province of Cavite were pitched as early as 1999 with the original plan being the MRT Line 6 which was identified in the Metro Manila Urban Transportation Integration Study Master Plan by the Japan International Cooperation Agency in 1999 This would have constructed a 12 to 15 kilometer elevated railway from Baclaran to Imus with extensions leading to Cavite City 10 0 km Dasmarinas 14 5 km Airport Sucat 9 0 km and Alabang 12 0 km 95 96 However the project never materialized The extension was first approved by the National Economic and Development Authority in 2000 while the Implementing Agreement for the project was approved in 2002 to be undertaken by SNC Lavalin as a public private partnership project 97 98 The proposal however was subsequently terminated in 2006 99 In the same year the government worked with International Finance Corporation White amp Case Halcrow and other consultants to conduct an open market invitation to tender for the extension and for a 40 year concession to run the extended line 99 100 However the project was shelved months before Gloria Macapagal Arroyo would end her term as President 101 The project was subsequently re approved by President Benigno Aquino III in March 2012 again as a public private partnership project 102 with construction expected to start by 2014 However a myriad of problems caused the project to be delayed right of way issues and the initial failed bidding of the line s privatization in 2013 Subsequently the Light Rail Manila Corporation LRMC was awarded the concession by 2014 before the line was privatized on September 12 2015 The issues were resolved in 2016 and on May 4 2017 the 11 7 kilometer 7 3 mile South Extension Project also known as the Cavite Extension Project broke ground 103 104 When completed it would be the third rail line extending outside the Metro Manila area after the east extension of Line 2 and the construction of Line 7 105 The project is divided in two phases Phase 1 covers five stations from Redemptorist to Dr Santos while Phase 2 covers the remaining three stations from Las Pinas to Niog 11 The two phase project would be implemented in a hybrid funding scheme which combines the funds from the Japanese official development assistance and LRMC the private proponent 106 Civil works on the extension began on May 7 2019 107 The project pegged at 64 billion has suffered cost overruns due to construction delays caused by the COVID 19 pandemic and pending right of way issues of the extension s second phase 108 The line would be extended from Paranaque southwards connecting Las Pinas and Bacoor to the Mega Manila railway network It would involve the construction of eight stations Redemptorist Manila International Airport Asia World Ninoy Aquino Dr Santos Las Pinas Zapote Niog and another two planned stations Manuyo Uno and Talaba the construction of three intermodal facilities one satellite depot located at Zapote and mass upgrades to the existing Baclaran depot The construction of the extension line is being built using a full span launching method renowned as one of the fastest methods of construction for bridges and elevated viaducts that cuts time and total land space needed for construction As the first railway line to utilize the new construction method a total of 203 pi girders were used for the construction of the extension s first phase 109 the last of which was laid on February 7 2022 110 The project is expected to cater more than 800 000 passengers daily once completed 103 104 The LRMC partnered with Bouygues Construction for the civil works 111 Alstom for the installation of the signalling and communication systems 7 and the RATP Dev Transdev Asia 112 for the overall engineering procurement consultation construction and assistance services for the project In August 2023 businessman Manny Villar bared plans to take over the extension project noting the difficulty of LRMC extending the line to Cavite due to right of way issues A portion of the extension will pass by Villar s properties in Las Pinas and according to Villar right of way acquisition will not be a problem He also plans to further extend the line into Cavite province should the unsolicited proposal be approved 113 On December 19 2023 the first test run along the extension was successfully conducted using an LRTA 1100 class train 114 As of November 11 2023 update the project is 94 1 complete Phase 1 of the extension is expected to be operational by the fourth quarter of 2024 115 with full operations by 2027 116 The Light Rail Manila Corporation stated that the LRT1 Cavite Extension Phase 1 was 97 complete as of March 2024 the Redemptorist Station Asia World Station Ninoy Aquino Station and Dr Santos Station were 93 3 83 88 and 94 1 finished respectively 117 Incidents and accidents editRizal Day bombings edit Main article Rizal Day bombings On December 30 2000 during the Rizal Day a 1000 class LRV train Car number 1037 was involved in the Rizal Day bombings at Blumentritt station The attack on the line killed some 22 people and injured hundreds Eight members of both Jemaah Islamiyah and the Moro Islamic Liberation Front MILF which include Hambal Asia s most wanted man and Fathur Rahman al Ghozi were charged with plotting and masterminding the attacks in 2003 some three years after the attacks Three suspects were put on trial 118 119 with al Ghozi receiving 17 years in prison due to the illegal possession of explosives Al Ghozi later died in a firefight after attempting to escape from prison Other incidents edit This section needs to be updated Please help update this article to reflect recent events or newly available information September 2023 On January 3 2008 a fire blazed at a shopping mall in Baclaran Due to the smoke the Baclaran station was temporarily closed A provisional service was implemented between EDSA and Monumento at the time the north extension was not opened yet with southbound trains still proceeding towards Baclaran to only serve as a turnback siding 120 The station remained closed the following day 121 until it was reopened a few days later citation needed On August 11 2008 a fire blazed in a mall near the Baclaran station The station was closed to the public until the station was reopened on August 13 122 On December 8 2008 a train encountered a glitch while approaching Carriedo station 123 On February 18 2011 two trains 1G and 3G collided near Fernando Poe Jr station in Quezon City at the reversing tracks around a kilometer away to the east There were no passengers on board when the incident happened The cause of the collision is yet to be determined whether due to driver error or technical malfunction 124 On April 15 2011 a door malfunction disrupted the operations of Line 1 at Blumentritt station 125 On June 21 2011 at 8 00 AM a train suffered a short circuit in one of its electrical components at Libertad station On the same day at 2 23 PM a power cable was hit by lightning disrupting the line s operations for three hours 126 On August 30 2012 at 5 50 AM a woman committed suicide after jumping in front of an approaching train at EDSA station Operations were disrupted until operations resumed at 9 40 AM 127 On December 21 2012 a train stalled at the Monumento station 128 On November 14 2014 a signaling fault at Fernando Poe Jr station limited the operations between Monumento and Baclaran stations The situation normalized at 3 57 PM 129 On May 23 2015 thousands of passengers were stranded after two trains 1G and 3G collided near the Monumento station A train driver was hurt after the impact caused his head to slam into the dashboard of the train 130 The accident later revealed to be caused by power fluctuation that affected the signalling system forced passengers to alight from the station until services was restored around 1 pm at the same day 131 On March 10 2016 a 1G train car door was left open while running between Central Terminal and Pedro Gil stations The problem was fixed at the Pedro Gil station 132 On March 22 2016 the doors of a 1G train car at the Central Terminal station failed to open leaving passengers trapped inside the train 133 134 On September 26 2016 a faulty door in a 1G train car suddenly slammed shut in less than a second No one was injured 135 On November 6 2017 a man s leg got stuck when a train door closed at the Gil Puyat station The man was dragged at the platform when the train was moving leaving the man with severe injuries The man was then sent to a nearby hospital where he was confined in an intensive care unit According to a report a number of trains particularly the 1000 class 1G trains do not have sensors that detects an object between doors 136 On November 27 2017 an 1100 class 2G train door malfunctioned after a passenger forcibly opened it at Vito Cruz station causing the sensor to malfunction The train continued its journey with the door left open and a passenger recorded this incident on camera 137 On February 20 2018 at around 6 00am a train at R Papa station unloaded 120 passengers after the air pressure gauge inside the train malfunctioned The operations returned to normal 30 minutes later 138 On July 21 2018 at around 6 00 AM a contact wire sparked near Libertad station A provisional service between Fernando Poe Jr and United Nations stations was implemented Normal operations resumed at 2 59 PM after the cable was fixed 139 On September 26 2018 a faulty 1G train door was unable to open at the Balintawak station A passenger pushed the door open and was able to disembark The next passenger pushed the door but it abruptly closed on him but managed to get through 140 On October 3 2019 a mechanical problem limited the LRT 1 operations between Monumento and Baclaran stations The operations returned to normal at 1 50 AM 141 On November 6 2020 a 1G train car emitted smoke at Gil Puyat station at 2 00 PM due to a catenary fault Passengers were evacuated and the line implemented a provisional service from Balintawak to Central Terminal and vice versa 142 The situation normalized at 8 00 PM 143 On April 4 2022 a train suffered a glitch at Tayuman station causing a speed restriction of 25 kilometers per hour 16 miles per hour Operations normalized at 7 34 AM 144 On February 17 2023 operations were limited between Fernando Poe Jr and Gil Puyat due to electrical problems 145 On April 14 2023 at 10 17 AM a speed restriction of 25 kilometers per hour 16 miles per hour was put in place in the whole train line due to the reported fault of the affected LRV 146 At 10 25 AM the operations stop in whole line due to the fault of affected train at Bambang station northbound 147 and the line implemented a provisional service from Baclaran to Central Terminal and vice versa at 10 52 AM 148 Operations normalized from Baclaran to Fernando Poe Jr and vice versa at 11 01 AM 149 References edit a b c Abadilla Emmie V April 12 2023 10 regional airports up for sale Bautista Manila Bulletin Retrieved April 13 2023 Manila Timeline LRT MRT a b Calonzo Andreo C October 22 2010 DOTC LRT Line 1 s Roosevelt Station now open GMA News Online Retrieved August 13 2021 Section VI 3 Drawings PDF Part 2 Employer s Requirements LRT Line 1 4th Generation Rolling Stock Report Department of Transportation Philippines October 16 2015 p 3 Archived from the original PDF on December 27 2021 Retrieved February 26 2022 a b c Department of Transportation and Communications Light Rail Transit Authority June 4 2012 MANILA LRT1 EXTENSION OPERATIONS AND MAINTENANCE PROJECT PDF Public Private Partnership Center Report Retrieved June 7 2020 a b officialLRT1 February 1 2022 LRMC completes upgrade of LRT 1 signalling system Light Rail Manila Corporation Retrieved February 2 2022 a href Template Cite web html title Template Cite web cite web a CS1 maint numeric names authors list link a b c Alstom to supply an integrated metro solution to Manila Alstom com February 12 2016 a b PROCUREMENT PLAN 2007 SIGNALLING SPARE PARTS IMPORTED ITEMS PDF Light Rail Transit Authority Archived from the original PDF on April 30 2006 Retrieved March 13 2022 a b c BIDDING DOCUMENTS Part 2 for Procurement of New Rolling Stock LRV 4th Generation PDF LRT 1 South Cavite Extension Project Report Department of Transportation Philippines 2015 pp 98 103 121 126 148 149 Archived from the original PDF on December 16 2021 Retrieved December 16 2021 Marasigan Lorenz S January 28 2021 New trains for LRT 1 arrive in PHL BusinessMirror Retrieved July 13 2021 a b Balinbin Arjay L January 18 2021 LRT 1 Cavite Extension more than halfway complete Transport dep t says BusinessWorld Retrieved August 7 2021 a b c d e f Japan International Cooperation Agency 2004 Metro Manila LRT Line 1 Capacity Expansion Project PDF Report Retrieved December 4 2021 Lines 1 and 2 Route Map Light Rail Transit Authority Archived from the original on May 28 2014 Retrieved June 10 2014 Government urged to construct LRT station in Bagong Barrio Press release Caloocan City Public Information Office November 3 2008 Archived from the original on August 4 2010 Retrieved August 13 2021 LRT 1 Train Service Hours Light Rail Manila Corporation August 26 2020 Retrieved March 28 2022 LRMC releases LRT 1 train schedule for 2022 Holy Week Manila Standard April 6 2022 Retrieved April 6 2022 Grecia Leandre December 21 2021 Here are the LRT 1 LRT 2 MRT 3 schedules for Christmas 2021 Top Gear Philippines Retrieved March 28 2022 a b c d e Satre Gary L June 1998 The Metro Manila LRT System A Historical Perspective PDF Japan Railway amp Transport Review Vol 16 EJRCF Retrieved June 11 2019 a b c Light rail transit rides high Elevated route is designed to clear snarled traffic below Engineering News Record McGraw Hill Education January 20 1983 p 54 a b LRTA History Light Rail Transit Authority Archived from the original on June 9 2019 Retrieved April 19 2019 Provision of Travelway Space for Urban Public Transport in Developing Countries UN HABITAT 1993 ISBN 9789211312201 Retrieved June 15 2019 The LRT Line 1 System The Green Line Light Rail Transit Authority July 14 2014 Archived from the original on July 14 2014 Retrieved July 14 2014 Rimmer Peter J 2013 Rikisha to Rapid Transit Urban Public Transport Systems and Policy in Southeast Asia Elsevier pp 190 191 ISBN 9781483150529 Marcelo Ellen S August 29 1996 P2 77 B LRT I contract awarded Marubeni ABB group wins Manila Bulletin Villegas Paul N September 24 1996 LRTA Marubeni Corp sign P1 94 B pact to expand LRT 1 Business World a b LRT to get facelift with new modernization program says administrator The Philippine Star April 9 2000 Retrieved April 8 2022 Abadilla Emmie V August 1 2000 LRT operations revert to gov t Metro contract expires Manila Bulletin a b Japan International Cooperation Agency 2012 Ex Post Evaluation of Japanese ODA Loan Project LRT Line 1 Capacity Expansion Project II PDF Report Retrieved December 4 2021 a b PGMA Japan PM inaugurate 3G trains Press release Light Rail Transit Authority December 7 2006 Archived from the original on July 8 2008 Retrieved April 6 2022 MRTC gets support on Edsa MRT 3 phase 2 project The Philippine Star February 24 2003 Retrieved February 6 2022 Laude Pete September 15 2008 Caloocan wants LRT station in Bagong Barrio The Philippine Star Retrieved November 11 2023 Laude Pete Botial Jerry November 4 2008 Caloocan residents want additional LRT station The Philippine Star Retrieved November 11 2023 Lectura Lenie December 22 2010 Feasibility study for P1 2 B LRT Malvar station ready Business Mirror Archived from the original on March 9 2012 Retrieved August 13 2021 a b Project Updates The LRT Line 1 North Extension Project Light Rail Transit Authority Archived from the original on September 28 2011 Retrieved February 6 2022 History of MRT3 Retrieved November 11 2023 LRT 1 North Extension First Balfour Retrieved November 10 2021 CHAPTER 5 PROJECT IMPLEMENTATION PLAN PDF PREPARATORY STUDY FOR LRT LINE 2 EXTENSION PROJECT FINAL REPORT Report October 2011 Retrieved February 6 2022 Ronda Rainier Allan February 11 2010 LRT trains can run on MRT to solve overloading woes The Philippine Star Retrieved February 6 2022 Burgonio TJ Montecillo Paolo February 26 2010 Metro rail loop finally finished Philippine Daily Inquirer Archived from the original on February 27 2010 Retrieved February 6 2022 LRT opens Balintawak station ABS CBN News March 22 2010 Retrieved August 13 2021 Ayala San Miguel Meralco 21 others interested in MRT 3 LRT 1 ABS CBN News April 14 2011 Retrieved February 18 2022 DOTC chief de Jesus resigns ABS CBN News June 1 2011 Retrieved February 18 2022 Montecillo Paolo G July 13 2011 DOTC reviews MRT LRT central station project Philippine Daily Inquirer Retrieved February 18 2022 LRT 1 Cavite extension bidding a failure Rappler August 29 2013 Retrieved February 26 2022 Japan s Sumitomo joins Pangilinan Ayala consortium for LRT 1 ABS CBN News May 29 2020 Retrieved May 29 2020 DOTC awards LRT 1 Cavex PPP starts bid for LRT 2 O amp M Official Gazette of the Republic of the Philippines September 13 2014 Retrieved December 4 2021 PPP contract signed for Manila LRT 1 project InfraPPP October 6 2014 Archived from the original on January 24 2021 Retrieved December 4 2021 P65B Manila Cavite Transit Project Underway Social Patrol Archived from the original on May 5 2017 Retrieved May 8 2017 Light Rail Manila Corp inks operation and maintenance contract with French firm RATP Dev for the LRT1 extension project France in the Philippines and in Micronesia Embassy of France in Manila Archived from the original on February 5 2018 Retrieved February 4 2018 Philippines Manila LRT 1 Cavite Extension PDF International Finance Corporation Archived from the original PDF on February 4 2018 Retrieved February 4 2018 a b c d officialLRT1 August 31 2016 LRMC commences 26 km rail replacement in LRT 1 Light Rail Manila Corporation Retrieved November 10 2021 a href Template Cite web html title Template Cite web cite web a CS1 maint numeric names authors list link Marasigan Lorenz S April 19 2017 LRMC signs P980 million deal with First Balfour for repair of LRT 1 BusinessMirror Retrieved November 10 2021 Camus Miguel R November 17 2018 P650 M rehab of LRT1 power system set Philippine Daily Inquirer Retrieved November 10 2021 LRMC spending P1B to rehabilitate old trains of LRT 1 Interaksyon June 8 2017 Retrieved February 26 2022 Camus Miguel R February 23 2018 LRMC signs P450 M deal for train rehab upgrade Inquirer net Wala pong limit sa diameter ng wheels Kaugnay naman po ng bagahe hanggang 2 feet x 2 feet po ang maximum dimension na pinapayagan sa LRT 2 Twitter Retrieved May 15 2022 GMANews TV SOPHIA DEDACE November 18 2009 Bikes trains and fewer cars with LRT s Bike O2 project GMA News Online Retrieved May 15 2022 LRT1 Customer Advisory March 9 2022 Retrieved March 9 2022 Salamat Marya October 14 2014 Best to keep LRT1 run by public servants consumer groups Bulatlat Retrieved March 25 2022 Martin Sammy January 11 2012 Light rail transit sets new ridership record The Manila Times Retrieved January 9 2022 via PressReader a b Mercurio Richmond September 23 2018 LRT 1 posts record 14 63 million ridership in August Marsigan Lorenz S May 24 2018 LRMC sees LRT 1 passengers increasing by 75 in 2021 BusinessMirror Light Rail Manila Corporation officialLRT1 May 23 2023 Hi The minute interval is not the train s arrival at the station but the interval of the train that departs at the end line The train arrival will depend on your location which is every 5 6 minutes in every station Thank you for your understanding Ingat po sa biyahe Tweet Retrieved June 1 2023 via Twitter a b The Line 1 Capacity Expansion Project Phase I Light Rail Transit Authority Archived from the original on May 17 2006 Retrieved April 7 2006 a b Light Rail Transit Authority Manila Philippines Light Rail Vehicle Kinki Sharyo Archived from the original on July 17 2011 Retrieved March 8 2010 MANILA LINE 1 LRV www caf net Retrieved December 9 2023 Cahiles Gerg December 30 2019 How the Rizal Day bombings changed the PH s security landscape CNN Philippines Retrieved December 16 2021 Razon Evangeline M June 1998 The Manila LRT System PDF Japan Railway and Transport Review 16 38 39 Retrieved December 15 2009 Otaki Tsutomu 2007 The Commissioning In Case of a Project in Manila PDF KS World 14 Kinki Sharyo 12 13 Archived from the original PDF on September 28 2011 Retrieved January 15 2010 a b c officiallrt1 April 4 2021 LRMC increases LRT 1 speed to 60kph Light Rail Manila Corporation Retrieved April 25 2021 a href Template Cite web html title Template Cite web cite web a CS1 maint numeric names authors list link 3rd Generation LRV Mock Up on Display Light Rail Transit Authority March 9 2006 Archived from the original on April 24 2006 Retrieved April 7 2006 Olchondra Riza T December 7 2006 3G trains to serve LRTA riders Dec 11 More comfortable safer rides assured for commuter Philippine Daily Inquirer Archived from the original on February 22 2013 Retrieved February 7 2010 CAF and Mitsubishi win LRV contract in Manila Railway PRO November 21 2017 Retrieved February 20 2022 Camus Miguel R November 21 2017 LRT 1 to get new train cars from Japan s Mitsubishi Inquirer net CAF awarded Manila rolling stock contract Metro Report International November 20 2017 Retrieved June 7 2020 CAF TO SUPPLY 30 LRVS TO MANILA THE PHILIPPINES Construcciones y Auxiliar de Ferrocarriles Retrieved May 19 2019 Arcangel Xianne February 17 2023 Nearly all train cars delivered for LRT 1 Cavite Extension defective says DOTr official CNN Philippines Archived from the original on February 18 2023 Retrieved February 23 2023 Recuenco Aaron July 19 2023 New state of the art train sets await LRT 1 riders starting July 20 Manila Bulletin Retrieved July 19 2023 Ronda Rainier Allan August 15 2003 No more sweaty LRT rides The Philippine Star Retrieved November 11 2023 The Line 1 Rehabilitation I Project Phase 3 Rolling Stock Rehabilitation Light Rail Transit Authority Archived from the original on May 22 2013 Retrieved January 19 2010 Varella Benjie September 26 2003 Line 1 to have all air conditioned trains by April The Manila Times Archived from the original on April 15 2005 Retrieved April 7 2006 LRT Line 1 Capacity Expansion Project Phase II Package B Light Rail Transit Authority Archived from the original on May 22 2013 Retrieved June 11 2014 officiallrt1 April 23 2021 LRMC and DOST MIRDC ink knowledge sharing partnership on rail technology Light Rail Manila Corporation Retrieved April 12 2022 a href Template Cite news html title Template Cite news cite news a CS1 maint numeric names authors list link Construction works launched for LRT 1 Cavite extension Railway Pro May 10 2019 Archived from the original on December 13 2021 Retrieved December 13 2021 a b LRT Line 1 Expansion of Existing Depot at Baclaran First Balfour Retrieved December 3 2021 Argosino Faith February 23 2022 Baclaran Depot of LRT 1 Cavite Extension project completed Manila Bulletin Retrieved February 23 2022 a b c Japan International Cooperation Agency Oriental Consultants Co Ltd ALMEC Corporation Katahira amp Engineers International Tonichi Engineering Consultants Inc July 2013 LRT LINE 1 CAVITE EXTENSION PROJECT PDF STUDY ON RAILWAY STRATEGY FOR ENHANCEMENT OF RAILWAY NETWORK SYSTEM IN METRO MANILA OF THE REPUBLIC OF THE PHILIPPINES FINAL REPORT Report Vol 1 Archived PDF from the original on December 27 2021 Retrieved January 13 2022 Japan International Cooperation Agency Oriental Consultants Co Ltd ALMEC Corporation Katahira amp Engineers International Tonichi Engineering Consultants Inc July 2013 APPENDICES PDF STUDY ON RAILWAY STRATEGY FOR ENHANCEMENT OF RAILWAY NETWORK SYSTEM IN METRO MANILA OF THE REPUBLIC OF THE PHILIPPINES FINAL REPORT LRT LINE 1 CAVITE EXTENSION PROJECT Report Vol 1 Retrieved January 13 2022 Amendatory and Restated Contract PDF Project No 2 Systematic Replacement of Gantry Anchor Bolts of I RT 1 Revenue Line Department of Transportation and Communications Archived from the original PDF on January 26 2022 Retrieved April 19 2022 LRT 1 rail supplier targets to complete contract in November Manila Bulletin February 11 2015 Retrieved April 8 2022 via Yahoo News Philippines Replacement of LRT 1 worn out steel rails to start next month Manila Bulletin November 13 2014 Retrieved February 25 2022 via Yahoo News Philippines Locsin Joel March 7 2015 LOOK LRT 1 tracks replaced at Monumento station GMA News Retrieved April 8 2022 Systematic Rail Replacement 26 458 lm LRT1 Mainline Tracks Joratech Retrieved April 24 2022 Cordero Ted February 1 2018 LRMC to raise LRT1 train speed to 60 kph GMA News Retrieved February 25 2022 METRO MANILA URBAN TRANSPORTATION INTEGRATION STUDY FINAL REPORT SUMMARY PDF Japan International Corporation Agency March 5 1999 Retrieved July 17 2023 METRO MANILA URBAN TRANSPORTATION INTEGRATION STUDY TECHNICAL REPORT NO 7 TRANSPORTATION PROJECT REVIEW PDF Japan International Corporation Agency 1999 Retrieved July 17 2023 Valencia L B April 1 2002 850 M LRT EXTENSION TO CAVITE STARTS IN NOVEMBER Manila Bulletin Archived from the original on February 19 2022 Retrieved February 19 2022 Valencia L B September 15 2004 LRT1 Extension Expected to Start Construction by 2005 Manila Bulletin Archived from the original on April 15 2005 Retrieved February 14 2022 via Light Rail Transit Authority a b Transaction Overview PDF MANILA LRT LINE 1 SOUTH EXTENSION PROJECT Light Rail Transit Authority 2006 Archived from the original PDF on July 20 2007 Retrieved February 14 2022 INVITATION TO SUBMIT EXPRESSIONS OF INTEREST AND CALL FOR REGISTRATION PDF MANILA LRT LINE 1 SOUTH EXTENSION PROJECT Light Rail Transit Authority 2006 Archived from the original PDF on February 21 2007 Retrieved February 14 2022 Montecillo Paolo February 25 2010 Arroyo wants LRT 1 extended to Cavite Philippine Daily Inquirer Archived from the original on February 27 2010 Retrieved February 14 2022 Ang Dean March 23 2012 Government approves LRT Line 1 Cavite Extension Project AutoIndustriya com Retrieved November 11 2023 a b Barrow Keith May 4 2017 Manila breaks ground on LRT 1 Cavite extension International Railway Journal Simmons Boardman Publishing Retrieved May 4 2017 a b Cordero John Ted May 4 2017 DOTr LRMC break ground for LRT 1 Cavite extension project GMA News Online Retrieved May 5 2017 LRT Line 1 Cavite Extension and Operation amp Maintenance ppp gov ph Public Private Partnership Center Retrieved July 6 2021 Cordero Ted July 4 2018 Tugade says LRT1 Cavite extension to be completed in 2021 GMA News Online Retrieved July 8 2018 Orellana Faye May 7 2019 Construction of LRT 1 Cavite extension begins Philippine Daily Inquirer Retrieved July 20 2021 Abadilla Emmie V April 13 2023 Phase1 LRT 1 Cavite Extension extension cost balloons due to delays Manila Bulletin Retrieved November 11 2023 LRT 1 Cavite Extension moves closer to completion celebrates new milestone NationBuilder PH Archived from the original on February 5 2022 Retrieved February 5 2022 Dela Cruz Raymond Carl February 7 2022 LRMC contractor complete LRT 1 Cavite Extension viaduct Philippine News Agency Retrieved February 14 2022 LRT 1 Cavite Extension features world class construction technology Wheels ph October 1 2020 Manila RATP Dev Cabuag VG August 17 2023 Villar PAVI wants to extendLRT 1 up to Silang in Cavite BusinessMirror Retrieved November 11 2023 Yu Lance Spencer December 20 2023 FAST FACTS What s the LRT 1 Cavite Extension Rappler Retrieved December 20 2023 Rosel Trixee November 11 2023 Progress rate of LRT 1 extension construction now at 94 Manila Bulletin Retrieved November 11 2023 Dumlao Abadilla Doris March 15 2022 LRT 1 Cavite extension gears up for 2024 start of operations INQUIRER net Retrieved March 15 2022 Cordero Ted March 6 2024 Phase 1 of LRT1 Cavite extension now 97 complete LRMC Retrieved March 7 2024 Tubeza Philip July 8 2003 Terrorist raps filed vs Asia s most wanted man Inquirer Philippine Daily Inquirer Archived from the original on December 6 2003 DOJ Indicts Asia s Most Wanted Terrorist in 2000 LRT Bombing Department of Justice Republic of the Philippines July 7 2003 Archived from the original on July 25 2008 Baclaran fire disrupts LRT operations GMA News and Public Affairs January 3 2008 Retrieved November 1 2021 LRT closes Baclaran station again GMA News and Public Affairs January 4 2008 Retrieved November 1 2021 LRT Baclaran terminal resumes operation mall fire under control GMA News and Public Affairs August 13 2008 Retrieved November 1 2021 Dedace Sophia December 8 2008 LRT Line 1 trips disrupted report GMA News GMA News and Public Affairs Retrieved November 1 2021 Castro Doland February 18 2011 2 LRT trains collide ABS CBN News Quezon City Metro Manila ABS CBN News and Current Affairs Archived from the original on May 26 2020 Retrieved May 26 2021 Door problem disrupts LRT operations anew GMA News and Public Affairs April 15 2011 Retrieved November 1 2021 Lightning disrupts LRT 1 operations for 3 hours GMA News and Public Affairs June 21 2011 Retrieved November 1 2021 Cayabyab Zhander August 30 2012 Woman commits suicide inside LRT station ABS CBN News Retrieved November 10 2021 Glitch disrupts LRT 1 operations in Monumento GMA News and Public Affairs December 21 2012 Retrieved November 1 2021 Glitch isolates LRT 1 s Roosevelt station GMA News and Public Affairs November 14 2014 Retrieved November 1 2021 Gonzales Yuji Vincent May 23 2015 2 LRT trains collide due to technical glitch at least 1 hurt INQUIRER net South Caloocan Metro Manila Archived from the original on February 4 2016 Retrieved May 26 2021 Palma Paola May 23 2015 Minor collision disrupts LRT operation Saturday CNN Philippines Metro Manila Archived from the original on January 1 2016 Retrieved May 26 2021 LRT 1 train travels two stations with door open CNN Philippines March 11 2016 Archived from the original on March 18 2016 Retrieved October 30 2021 Bajo Ramil Galupo Rey March 23 2016 LRT passengers trapped as LRT doors fail to open The Philippine Star Retrieved October 30 2021 People Trapped inside LRT and One Passed Out Because the Door Won t Open YouTube video Archived from the original on December 14 2021 Yee Jovic September 28 2016 LRT 1 door slams shut on passengers no one hurt Philippine Daily Inquirer Retrieved October 30 2021 Bajo Anna Felicia November 7 2017 Man ends up in ICU after foot got stuck in moving LRT train s door GMA News Retrieved October 30 2021 Bacungan VJ November 28 2017 WATCH LRT 1 train runs with open door CNN Philippines Archived from the original on October 30 2021 Retrieved October 30 2021 Pascual Jekki Aquino Lyza Reyes Isay February 20 2018 LRT 1 MRT nagkaaberya nagpababa ng mga pasahero ABS CBN News Retrieved June 1 2021 Mga pasahero ng LRT 1 pinababa matapos magka aberya ABS CBN News in Filipino July 21 2018 Retrieved November 1 2021 YOU SHALL NOT PASS Malfunctioning train door closes by itself makes disembarking a challenge for commuters Coconuts Manila September 28 2018 Retrieved October 30 2021 Galvez Daphne October 3 2019 Glitch stalls LRT 1 s Monumento Roosevelt operations Philippine Daily Inquirer Retrieved May 26 2021 Marquez Consuelo November 6 2020 LRT 1 train catches fire in Pasay management limits train ops INQUIRER net Retrieved April 25 2021 Marquez Consuelo November 6 2020 LRT 1 resumes regular operations after technical woes at Gil Puyat Station INQUIRER net Retrieved May 26 2021 LRT1 ops temporarily affected by train glitch normal ops resumed LRMC GMA News April 4 2022 Retrieved May 5 2022 Cua Aric John Sy February 17 2023 LRT 1 operations limited after electrical problems The Manila Times Retrieved February 17 2023 25kph speed restriction has been put in place from Baclaran to Roosevelt Twitter April 14 2023 Retrieved April 14 2023 A stop for safety has been put in place from Baclaran to Roosevelt Twitter April 14 2023 Retrieved April 14 2023 Limited operations of LRT 1 Twitter April 14 2023 Retrieved April 14 2023 Resumed operations Twitter April 14 2023 Retrieved April 14 2023 External links edit nbsp Media related to LRT Line 1 Metro Manila at Wikimedia Commons The LRT Line 1 System Light Rail Manila Corporation Retrieved from https en wikipedia org w index php title LRT Line 1 Metro Manila amp oldid 1217673751, wikipedia, wiki, book, books, library,