North–South Commuter Railway

The North–South Commuter Railway (NSCR), also known as the Clark–Calamba Railway, is a 147-kilometer (91-mile) urban rail transit system under construction in the island of Luzon, Philippines. Running from New Clark City in Capas to Calamba, Laguna with 36 stations and four services, the railway was designed to improve connectivity within the Greater Manila Area and will be integrated with the railway network in the region.[5][6][7]

North–South Commuter Railway
Construction of the railway in Balagtas, Bulacan
Overview
StatusUnder construction
OwnerDepartment of Transportation
LocaleCentral Luzon, Metro Manila, Calabarzon
Termini
Stations36
Websitewww.nscr.com.ph
Service
TypeCommuter rail
Airport rail link
SystemPNR North Main Line (Tutuban–Malolos)
PNR South Main Line (Tutuban–Calamba)
Services4
Operator(s)Philippine National Railways
Depot(s)Malanday[a]
Mabalacat
Banlic
Rolling stockVarious, see rolling stock
History
Planned opening2025 (partial)
2029 (full)[b]
Technical
Line length147 km (91 mi)
Number of tracksDouble-track[c]
CharacterElevated[d]
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Loading gauge4,150 mm × 3,000 mm (13 ft 7 in × 9 ft 10 in)[1]
Minimum radiusMainline: 260–400 m (850–1,310 ft)[1]
Depot: 92–100 m (302–328 ft)[1]
Electrification1,500 V DC overhead lines[1]
Operating speed120–160 km/h (70–100 mph)[e]
SignallingETCS Level 2[f]
Highest elevation130 m (430 ft) at Clark International Airport station
Maximum incline25
Average inter-station distance4.11 km (2.55 mi)
Route map

New Clark City
Mabalacat Depot
Clark International Airport
Quitangil River
Clark
Abacan River
Angeles
Sindalan Creek
San Fernando
San Fernando River
Apalit
Calumpit
Malolos
Malolos South
Guiguinto
Guiguinto River
Balagtas
Santol River
Bocaue River
Bocaue
Tabing-Ilog
Igulot River
Marilao
Marilao River
Meycauayan
Meycauayan River
Valenzuela Depot
Valenzuela Polo
Malabon
Caloocan
Solis
Tutuban
Blumentritt
España
Estero de Valencia
Santa Mesa
Paco
Buendia
Estero de Tripa de Gallina
EDSA
Estero de Tripa de Gallina
Nichols
FTI
 MMS 
Bicutan
 MMS 
Sucat
Sucat River
Alabang
Bayanan Creek
Poblacion River
Muntinlupa
Magdaong River
Tunasan River
San Isidro River
San Pedro
Pacita
Biñan
Biñan River
Silang-Sta. Rosa River
Santa Rosa
Cabuyao River
Cabuyao
Gulod
Cabuyao River
Mamatid
Banlic
Banlic Depot
Calamba

Originally planned in the 1990s, the railway project has had a tumultuous history, being repeatedly halted and restarted due to various reasons.[8] The first proposal was the 32-kilometer (20-mile) "Manila–Clark rapid railway" with Spain in the 1990s that was discontinued after disagreements on funding,[8][9] and during the 2000s, the NorthRail project with China that was discontinued in 2011 due to allegations of overpricing.[10][11][12] The current railway line began development in 2013.[13] The project's initial phase was approved in 2015,[14] and construction began in 2019.[15]

Expected to cost ₱873.62 billion,[16] the line is the most expensive railway transportation project in the country. The entire system is expected to be completed by 2029.[17] Upon its completion, the railway will supersede the existing PNR Metro Commuter Line.

History

Background

 
The Ferrocarril de Manila a Dagupan operated trains to and from Manila

During the Spanish and American colonial periods, the Manila Railway Company, later the Manila Railroad Company (MRR), operated various local trains between Manila and its neighboring provinces. By the 1920s, trains ran from Tutuban to Naic in Cavite, Pagsanjan in Laguna, Montalban in Rizal, and Bulacan.[18] The network was heavily damaged in the Battle of Manila during World War II,[19] but was mostly reestablished after the war.[20]

MRR would be succeeded by the Philippine National Railways (PNR) on June 20, 1964.[21] On April 6, 1970, PNR inaugurated the Metro Manila Commuter Service, which started at Manila North Harbor and ended in Biñan station in Laguna.[22] After numerous expansions, the commuter service served thousands of daily riders in its system and had an expansive network in and out of Metro Manila.[23] In 1978, at the request of the Philippine government, the Japan International Cooperation Agency (JICA) conducted a study on the electrification of the commuter service.[24] The plan was made to keep up with the increasing demand for transportation in the region. It called for the replacement of the diesel-run trains and the electrification of the PNR commuter line. Two experts from the Japanese National Railways were sent to conduct the study.[24]

Services north of Manila started to decline in the 1980s. However, commuter services were briefly extended to Malolos starting in 1990 under the Metrotren project but later ceased in 1997.[25] Since then, railway services have been mostly confined to the south, with the contemporary Metro Commuter Line being predominantly aligned to the South Main Line.[26]

Manila–Clark rapid railway system

During the 1990s, President Fidel Ramos signed a memorandum of agreement with Juan Carlos I of Spain for the construction of a railway line from Manila to Clark in September 1994.[8] This would be known as the Manila–Clark rapid railway system. On August 24, 1995, North Luzon Railways Corporation (NLRC) was formed as a subsidiary of Bases Conversion and Development Authority (BCDA).[8] The NLRC then entered into an engineering, procurement and construction contract with the Spanish Railways Corporation on February 7, 1996, but the contract was later terminated on August 14, 1998, after the parties disagreed on the source of funding for the project.[8]

In September 1999, the National Economic and Development Authority (NEDA) approved the railway project, with the initial phase covering a segment from Caloocan to Calumpit. The source of funding was to be the Obuchi Fund from the Japan Bank for International Cooperation (JBIC).[8] Pre-construction activities such as right-of-way clearing and relocation of affected informal settlers began, but a presidential directive later halted the clearing activities and the JBIC loan was not granted.[8]

NorthRail

 
Abandoned NorthRail columns in Malolos, Bulacan that have since been demolished.

Under the presidency of Gloria Macapagal Arroyo, a successor to the Manila–Clark rapid railway system, the NorthRail project, an 80-kilometer (50-mile) rail line,[27] was conceived. On September 14, 2002, a memorandum of understanding was signed by NorthRail and China National Machinery and Equipment Group (CNMEG) for the project.[8] It was later approved on August 5, 2003.[8] The project was estimated to cost around US$500 million, and the funding was to be covered by a US$400 million loan from the Export–Import Bank of China, and the rest to be shouldered by the government through BCDA and NLRC.[8][9][28]

The project involved the upgrading of the existing single track to an elevated dual-track system, converting the rail gauge from narrow gauge to standard gauge, and linking Manila to Malolos in Bulacan and further on to Angeles City, Clark Special Economic Zone and Clark International Airport.[8] The first phase of the project covered the Caloocan to Malolos segment, which spans 32 kilometers (20 miles).[28] Before construction could start, the Philippine Senate raised concerns about alleged corruption in the project. Senator Franklin Drilon commissioned a study from the University of the Philippines, which recommended the cancellation of the railway's construction, citing anomalies in the bidding process and the Buyer Credit Loan Agreement (BCLA) with Exim China.[8] Despite the controversy, preparatory construction began in early November 2006. Civil and design works started in October 2007. Due to delays in the construction work, it was soon renegotiated with the Chinese government. Construction temporarily continued in January 2009 with the support of the North Luzon Railways Corporation.[8]

However, the NorthRail project would be formally cancelled in March 2011, due to persisting legal issues and allegations of overpricing and corruption.[9][12][10] Nonetheless, on September 2011, the government expressed its interest to restart the project with Interior and Local Government Secretary Mar Roxas stating that China was open to reconfiguring the project.[29][12] NEDA Director-General Arsenio Balisacan also stated that NorthRail would resume within the term of President Benigno Aquino III,[30] but despite the announcement the NorthRail project was permanently scrapped and replaced with the NSCR project,[31] although the Philippine government was still obligated to pay the corresponding loans. In March 2012, the Philippine Supreme Court authorized a lower court to hear the case for voiding the contract. Instead of paying the US$184 million owed by the government in 2012, the Department of Finance was to pay the Export-Import Bank of China four installments of US$46 million from September 2012 onwards.[30] On November 6, 2017, DOTr, BCDA, and North Luzon Railways reached an out-of-court settlement with Sinomach (formerly CNMEG), resolving the five-year dispute. It saved the government ₱5 billion in potential payment of claims to Sinomach, and hundreds of millions of pesos in legal fees and arbitration costs.[27]

Development

With the termination of the NorthRail project, the Department of Transportation and Communications considered restarting the project by commissioning a feasibility study by CPCS Transcom Ltd. of Canada. Part of the study examined having a Malolos–Tutuban–Calamba–Los Baños commuter line.[31][32] The feasibility study was still ongoing when the NEDA included the North–South Commuter Railway in the Metro Manila Dream Plan, which it approved in 2014.[33]

The plan for the NSCR, a component of the North–South Railway Project,[34] included the 37-kilometer (23-mile) NSCR Phase 1, an electrified narrow gauge[35] commuter railway from Tutuban to Malolos and funded through overseas development assistance; and the second phase which included the reconstruction of the Tutuban–Calamba commuter line and the rehabilitation of long-haul services with an extension up to Matnog, Sorsogon and a branch line from Calamba to Batangas. It was to be funded through a public–private partnership (PPP) scheme.[34][36][37]

On February 16, 2015, the NEDA board, chaired by President Benigno Aquino III, approved the NSCR Phase 1 project.[36][38] After President Aquino met with Japanese Prime Minister Shinzo Abe in Japan in June 2015, Abe expressed his commitment to fund the project. On November 19, 2015, representatives of both countries exchanged notes on the project in the presence of Abe and Aquino.[14] JICA was chosen by the Japanese government to look into financing the project, and on November 27, seven months before Aquino would end his term, JICA and the Department of Finance signed a loan agreement worth ₱97.3 billion ($1.99 billion) for the financing of the first phase.[39][40][41]

The succeeding administration included the project under the Build! Build! Build! Infrastructure Program.[42] In addition, numerous changes to the project were made. The railway's gauge was changed to standard gauge,[43] and the railway was extended to New Clark City. In addition, the PPP scheme for the south commuter line was abandoned in favor of overseas development assistance from Japan.[44] On June 25, 2017, transportation secretary Arthur Tugade announced the new name for the project and unveiled the locations of the first five stations during a press tour of the old PNR line.[45]

On January 21, 2019, a loan agreement worth ₱80.47 billion (US$1.54 billion) for the North–South Commuter Railway Extension Project (NSCR-Ex), which includes the PNR Clark 2 and Calamba sections, was signed by JICA and the Department of Finance (DOF).[46] Another loan agreement worth ₱66.6 billion (US$1.3 billion) for the NSCR-Ex project was signed on July 11 by the Asian Development Bank (ADB) and DOF.[47] JICA would finance the electrical and mechanical systems as well as the trains for the PNR Clark 2 and Calamba sections, while ADB would finance the civil works.[48]

The loan for the civil works of PNR Calamba, worth ₱227 billion (US$4.3 billion), was approved by the ADB on June 9, 2022.[49] The loan agreement was signed by President Rodrigo Duterte and ADB on June 16.[50] Two more loan agreements were signed on February 9, 2023, during the working visit of President Bongbong Marcos in Japan.[51]

Construction

 
Construction of PNR Clark 1 in Meycauayan, Bulacan in March 2022
 
Construction of PNR Clark 2 in Mabalacat, Pampanga in October 2022

Pre-construction works such as clearing of the right of way started on January 5, 2018.[71] The North–South Commuter Railway is being built in three phases and divided into two primary sections:

  • PNR Clark — This is the northern section of the NSCR. Construction was divided into two phases. PNR Clark 1 involves the 38-kilometer (24-mile) Tutuban–Malolos railway, while PNR Clark 2 involves the 53-kilometer (33-mile) Malolos–Clark railway. The 91-kilometer (57-mile) railway line, when fully completed, will run from Tutuban station in Manila to New Clark City station within the Clark Freeport and Special Economic Zone, with a link to Clark International Airport.[72][73]
  • PNR Calamba — Also known as PNR Clark Phase 3,[74] PNR Calamba is the southern section of the NSCR. It involves the reconstruction of the existing Metro Commuter Line as an electrified standard gauge railway with elevated, at-grade, and depressed sections.[75][76] The 56-kilometer (35-mile) railway will run from Solis station in Manila to Calamba station in Laguna.

The groundbreaking of PNR Clark 1 was held on February 15, 2019, and construction started after.[15] Meanwhile, the groundbreaking of PNR Clark 2 was held on September 18, 2021.[48] PNR Clark is expected to start partial operations in October 2022, with full operations in 2024.[77] As of December 2021, PNR Clark 1 is 51.3% complete, while PNR Clark 2 is 32% complete as of September 2021.[78][79]

Construction of PNR Calamba is set to begin by 2022, with partial operations slated by 2025[80] and full operations by March 2029.[17]

Route

The North–South Commuter Railway will comprise two sections corresponding to the Philippine National Railways' old main lines. The first is the 91-kilometer (57-mile)[81] fully-elevated PNR Clark which is being built over the mostly-defunct North Main Line in northern Metro Manila and Central Luzon.[82][83] The construction of PNR Clark is further subdivided into two sections: the 38-kilometer (24-mile) PNR Clark 1 between Tutuban and Malolos, and the 53-kilometer (33-mile) PNR Clark 2 from Malolos to New Clark City.[84] The second component is the 56-kilometer (35-mile)[81] PNR Calamba which will use the existing PNR Metro Commuter Line right of way between Tutuban and Calamba, which were historically parts of the South Main Line and will have elevated, at-grade and depressed sections.[75]

Services

There are four classes of services on this line. The following are:[85]

  • Commuter is the basic commuter rail service and has the least priority. It stops at all stations within its route. There are three routes planned for this class; Tutuban–New Clark City, Tutuban–Calamba, and Clark International Airport–Calamba. The maximum speed for this service will be 120 kilometers per hour (75 miles per hour) for the entire line.
  • Commuter Express is the limited-stop service for the line, succeeding the Commex service during the Metrotren era in the early 2000s. Although it will run faster than regular commuter trains, it will still use the same routes and rolling stock.
  • The Airport Limited Express is the temporary designation for the planned airport rail link and limited express service between Clark International Airport and Alabang station. As the flagship NSCR service, it will use dedicated rolling stock complete with intercity-grade amenities plus baggage space for people arriving from the airport. It will have a maximum speed of 160 kilometers per hour (100 miles per hour) along the NSCR North. As of January 2022, the final name for the service is yet to be determined.
  • Subway through-service is the proposed augmentation between the NSCR and the Metro Manila Subway. It will serve the southernmost areas of Metro Manila and neighboring Laguna, branching from the subway line at FTI station while the remainder of the line will go towards the direction of NAIA Terminal 3 in Pasay. It will use the Subway trainsets instead of the NSCR ones, although both are from the Sustina family.

Stations

Proposed train stations and services[86][85][87]
Phase Station Services Transfers Location
Commuter Commuter express Limited express Through service to/from
Metro Manila Subway[85]
NCC–Tutuban CIA–Calamba Tutuban–Calamba NCC–Tutuban CIA–Calamba Tutuban–Calamba
PNR Clark 2 New Clark City none Capas, Tarlac
Clark International Airport   Clark International Airport Mabalacat, Pampanga
Clark none
Angeles Angeles, Pampanga
San Fernando San Fernando, Pampanga
Apalit Apalit, Pampanga
Calumpit Calumpit, Bulacan
Malolos Malolos, Bulacan
PNR Clark 1
Malolos South
Guiguinto Guiguinto, Bulacan
Tuktukan
Balagtas Balagtas, Bulacan
Bocaue Bocaue, Bulacan
Tabing Ilog Marilao, Bulacan
Marilao
Meycauayan Meycauayan, Bulacan
Valenzuela Valenzuela
Valenzuela Polo
Malabon Malabon
Caloocan Caloocan
Solis Manila
Tutuban   Tutuban
PNR Calamba Blumentritt   Blumentritt
España none
Santa Mesa   Pureza
Paco none
Buendia Makati
EDSA 3 Magallanes
Senate[88][89] None Taguig
FTI  MMS 
   16  TITX
Bicutan  MMS 
   25  Bicutan
Parañaque
Sucat PNR Bicol
   25  Sucat
Muntinlupa
Alabang none
Muntinlupa
San Pedro San Pedro, Laguna
Pacita
Biñan Biñan
Santa Rosa Santa Rosa, Laguna
Cabuyao Cabuyao, Laguna
Banlic PNR Bicol Calamba, Laguna
Calamba none
Stations in italics will open in 2030.

Extensions and additional stations

The Metro Manila Dream Plan proposed a 38-kilometer (24-mile) branch line that will split in Angeles City. The line will have 12 stations and shall end in Tarlac City.[90] The study also proposed a 47-kilometer (29-mile) extension of the NSCR to Batangas City.[90] This will be built parallel to the PNR South Long Haul project which was approved in 2017, with the line being a single-track, standard gauge line without electrification, and will be built at-grade similar to the present PNR network.[91] The PNR has also requested for a feasibility study for a commuter line connecting Tarlac City and San Jose, Nueva Ecija in 2019. The length of the line and the number of stations will be determined once a proposal has been submitted.[92] Another proposed southward extension to Pansol in Calamba, Laguna was proposed by a 2019 JICA report.[93]

The North–South Commuter Railway will also have provisions for infill stations: Malabon, Valenzuela Polo, Tabing Ilog, Tuktukan, and Malolos South.[85]

Infrastructure

NSCR will be the first commuter rail system in the country to be mostly grade-separated. Trains are designed to run on 1,435 mm (4 ft 8+12 in) standard gauge tracks at a design speed of 120 kilometers per hour (75 miles per hour) for regular trains and 160 kilometers per hour (99 miles per hour) for airport express trains.

Station layout

All stations will have a standard layout, with a concourse level and a platform level. The stations are designed to adhere to both Philippine and Japanese standards.[85] Stations will either have island platforms or side platforms with platform screen doors. The stations are designed to be barrier-free, and trains shall have spaces for passengers using wheelchairs. Historical stations will be preserved.[94] All stations will have access to intermodal facilities.[85] The FTI station in particular will be connected to the Taguig Integrated Terminal Exchange.[95]

Rolling stock

The North–South Commuter Railway will have two types of rolling stock: commuter trains and airport express trains. With the exception of wheelchair spaces, the commuter trains will have a capacity of 2,242 passengers. The express trains, on the other hand, will have a capacity of 392 passengers.[96] A total of 464 electric multiple unit traincars have been procured to operate on the line, with 104 of these being the 8-car EM10000 class trainsets to be built by the Japan Transport Engineering Company (J-TREC), successor to the Tokyu Car Corporation that provided rolling stock to the Philippines from 1955 to 1976. The trainsets were previously named as the Sustina Commuter at the time of purchase, and are based on JR East commuter stock such as the E233 series but adapted to standard gauge.[g] The trains are also designed to be interoperable with the Metro Manila Subway.[97] The trainsets have been designated as the EM10000 class in October 2021.[98] The first batch of the commuter trains arrived on November 21, 2021.[99] The bidding for an order for 304 more commuter cars in a separate contract was opened in September 2020, with the joint venture of Japan Transport Engineering Company and Sumitomo Corporation winning the contract on January 14, 2022.[100] The first EM10000 class train was unveiled on March 18, 2022[101] and the contract for the 304 cars was signed by the DOTr, Sumitomo, and J-TREC on the same day. The deliveries of the 304 cars are set to be completed by September 2028.[102]

The 56 airport express trainsets, meanwhile, are being procured as of 2019.[103][104] On February 26, 2021, a suggested preliminary design based on the E259 and E353 series was published.[96] On May 10, the Department of Transportation later announced it will acquire the airport express trainsets from Japanese manufacturers.[105] After several months of delays and rescheduling, three bidders have submitted their designs: Kawasaki Heavy Industries and Sojitz joint venture, Marubeni and Stadler Rail, and Mitsubishi and Construcciones y Auxiliar de Ferrocarriles (CAF).[106][h] The contract is expected to be awarded in the last quarter of 2022.[needs update][107]

Rolling stock Commuter trains[85][108][1] Airport express trains[96][109]
Image  
Year Batch 1: Fiscal 2022
Batch 2: 2025–2028[102]
TBD
Manufacturer J-TREC TBD[i]
Model EM10000 class (first batch)
TBD (second batch)
TBD
Number to be built First batch: 104 cars (13 sets)
Second batch: 304 cars (38 sets)
56 cars (7 sets)
Order no. CP 03 (first batch)
CP NS-02 (second batch)
CP NS-03
Formation 8 cars per trainset
Car length 20 m (65 ft 7 in)
Width 2.95 m (9 ft 8 in)
Pantograph lockdown height 4.15 m (13 ft 7 in)
Floor height 1.13–1.15 m (3 ft 8 in – 3 ft 9 in)
Body material Lightweight stainless steel Aluminum alloy and stainless steel
Tare weight 270 t (600,000 lb) 315 t (694,000 lb)
Axle load 16 t (35,000 lb)
Capacity Leading car: 266 standing, 45 seated
Intermediate car: 285 standing, 54 seated
Leading car: 40 seated
Intermediate car: 52 seated
PWD seating: 8 wheelchair spaces
Seat layout Rapid transit-style longitudinal seating Airline-style open coach seating
Doors per side 4 2
Traction control IGBTVVVF (first batch)
Hybrid SiCVVVF (second batch)
Hybrid SiCVVVF
Traction power 1,500 V DC overhead catenary
Pantograph type 1 single-arm pantograph Toyo Denki 2 single-arm pantographs, outward facing
Top speed 120 km/h (75 mph) ≥170 km/h (110 mph)
Train configuration TcM–M–T–T–M–M–Tc Tc–M–M–M–M–M–M–Tc
Other features Toilets, luggage racks
Status First batch: Under construction/delivery[99]
Second batch: Ordered; to be built[102]
To be ordered

Signalling

Initially, the PNR Clark 1 section of the line was set to use a communications-based train control (CBTC) system.[108] The line will instead use a signalling system based on ETCS Level 2. The subsystems consist of automatic train control (ATC), automatic train protection (ATP), automatic train supervision (ATS), train detection through track circuits, and computer-based interlocking, with provisions for automatic train operation (ATO).[110]

For Phase 1 between Tutuban and Malolos, Hitachi's Italian subsidiary Hitachi Rail STS will be the provider of ETCS Level 2 equipment as part of a contract package covering electrical and mechanical systems, and track works.[2] For Phase 2 between and the NSCR South, Alstom will use its Atlas 200 system for Level 2 signalling.[4]

Tracks

The line will feature an Elastic Sleeper Direct Fasten (ESDF) type ballastless track with concrete sleepers in the mainline and plastic/fiber-reinforced foam urethane railroad ties on turnouts in the mainline and depot.[110] Continuous welded rails will be employed on the mainline, while jointed rails with fishplates will be employed in the depot. 60-kilogram-per-meter (120-pound-per-yard) rails will be employed in the mainline while rails built to the JIS 50N rail profile will be used in the depot.[110]

See also

Footnotes

  1. ^ Main depot
  2. ^ The project will be implemented in three phases which will have their own opening dates.
  3. ^ May use quadruple-track at stations.
  4. ^ May be through viaduct or embankment. Also includes an at-grade section between EDSA and FTI stations and an underground section around Clark International Airport station.
  5. ^ Up to 120 kilometers per hour (75 miles per hour) for commuter trains while 160 kilometers per hour (100 miles per hour) for airport express trains.
  6. ^ Hitachi Rail STS will supply ETCS Level 2 equipment along Phase 1 between Tutuban and Malolos,[2] while Alstom's Atlas 200 was selected for the Malolos–Clark and NSCR South segments.[3][4]
  7. ^ The E233 series and other Japanese commuter trainsets run on 1,067 mm (3 ft 6 in) narrow gauge tracks.
  8. ^ Mitsubishi and CAF are currently manufacturing the LRTA 13000 class light rail vehicles for the LRT Line 1.
  9. ^ Three bidders have submitted their designs: Kawasaki Railcar, Marubeni, and Mitsubishi.[106]

References

  1. ^ a b c d e PART 2 - EMPLOYER'S REQUIREMENTS from BIDDING DOCUMENTS FOR PROCUREMENT OF PACKAGE CP NS-02: ROLLING STOCK - COMMUTER TRAINSETS (PDF) (Report). Vol. 2 of 3. Philippine National Railways. September 2020. (PDF) from the original on January 4, 2022. Retrieved January 4, 2022.
  2. ^ a b c Balinbin, Arjay L. (November 14, 2022). "Malolos-Tutuban rail contract bagged by Japan's Hitachi Rail". BusinessWorld. Retrieved November 22, 2022.
  3. ^ a b Department of Transportation (February 2, 2023). "Notice of Award" (PDF). Department of Transportation (Philippines). Retrieved February 8, 2023.
  4. ^ a b "Alstom-led consortium to provide integrated railway system for the Philippines' North-South Commuter Railway Extension Project". Alstom. March 6, 2022. Retrieved March 7, 2022.
  5. ^ (PDF) (Report). Japan International Cooperation Agency. September 2014. Archived from the original (PDF) on October 11, 2014.
  6. ^ Camus, Miguel R. (February 16, 2019). "DOTr plans to integrate new railway lines". business.inquirer.net. from the original on February 16, 2019. Retrieved February 16, 2019.
  7. ^ Pateña, Aerol John (April 30, 2019). "DOTr awards contract to DMCI Consortium for PNR North Phase 1 Project". Philippine News Agency. from the original on November 11, 2020. Retrieved May 27, 2021.
  8. ^ a b c d e f g h i j k l m "Off track: Northrail timeline". ABS-CBN News. July 15, 2008. from the original on February 17, 2019. Retrieved February 17, 2019.
  9. ^ a b c Inquirer, Philippine Daily (January 17, 2019). "WHAT WENT BEFORE: The Northrail Project". newsinfo.inquirer.net. from the original on February 14, 2019. Retrieved February 16, 2019.
  10. ^ a b . The PCIJ Blog. September 9, 2005. Archived from the original on August 12, 2014. Retrieved July 29, 2014.
  11. ^ Nicolas, Jino (November 6, 2017). "Northrail dispute settled". BusinessWorld. from the original on June 26, 2021. Retrieved June 26, 2021.
  12. ^ a b c "Philippines: China-funded Northrail project derailed". Financial Times. from the original on August 17, 2018. Retrieved February 17, 2019.
  13. ^ "DOTC eyes elevated railway from Malolos to Los Banos". ABS-CBN News. July 22, 2013. from the original on August 22, 2015. Retrieved April 23, 2019.
  14. ^ a b "Japan Commits JPY241.991 Billion ODA For North-South Commuter Railway Project (Malolos - Tutuban)". www.ph.emb-japan.go.jp (Embassy of Japan in the Philippines). November 19, 2015. from the original on December 24, 2020. Retrieved December 24, 2020.
  15. ^ a b Mercurio, Richmond (February 16, 2019). "Construction of North-South Commuter Railway kicks off". Philstar.com. from the original on September 1, 2021. Retrieved September 1, 2021.
  16. ^ Dela Cruz, Raymond Carl (August 11, 2022). "DOTr assures North-South Commuter Railway on-time completion". Philippine News Agency. Retrieved November 30, 2022.
  17. ^ a b c d e f "4 North-South Railway contracts awarded". PortCalls Asia. October 6, 2022. Retrieved October 6, 2022.
  18. ^ Orbon, Glenn; Dungca, Joana (2015). "The Philippine Railway System". Movement Systems.
  19. ^ Gamble, Adrian (March 10, 2017). "Manila's Long-Lost 'Tranvias' Once the Envy of Asia". skyrisecities.com. Skyrise Cities. from the original on June 21, 2020. Retrieved June 21, 2020.
  20. ^ "Chapter I: Present Conditions". Report of Survey of the Manila Railroad Company and the Preliminary Survey of Railroads for Mindanao (Report). Chicago: De Leuw, Cather & Company. 1951. pp. 1–12.
  21. ^ "Republic Act No. 4156 | GOVPH". Official Gazette of the Republic of the Philippines. from the original on January 3, 2022. Retrieved January 3, 2022.
  22. ^ "Carmona's Commuter Train". Times Journal. April 1973. from the original on July 13, 2021. Retrieved July 23, 2020.
  23. ^ . Philippine National Railways (February 27, 2009). Archived from the original on February 27, 2009. Retrieved November 4, 2011.
  24. ^ a b "REPORT ON STUDY OF THE ELECTRIFICATION OF THE PNR COMMUTER SERVICE" (PDF). Japanese International Cooperation Agency (JICA). December 1978. (PDF) from the original on May 22, 2021. Retrieved February 15, 2021.
  25. ^ "Metrotren Inaugural". Manila Chronicle. May 11, 1990. from the original on July 13, 2021. Retrieved May 6, 2021.
  26. ^ "Corporate Profile". Philippine National Railways. from the original on January 3, 2022. Retrieved January 3, 2022. The PNR currently operates in the Manila metropolitan area and the provinces of Laguna, Quezon, Camarines Sur and Albay. In the past, the PNR also used to serve the provinces of Bulacan, Pampanga, Tarlac, Nueva Ecija, Pangasinan and La Union on the North Main Line, and Batangas on the South Main Line.
  27. ^ a b Paz, Chrisee Dela (November 6, 2017). "PH gov't ends dispute with China's Sinomach over Northrail project". Rappler. from the original on November 25, 2018. Retrieved February 16, 2019.
  28. ^ a b . Malaya. April 6, 2004. Archived from the original on May 9, 2010 – via lrta.gov.ph.
  29. ^ Bordadora, Norman (September 2, 2011). "China open to reconfiguring NorthRail project, says Roxas". newsinfo.inquirer.net. from the original on April 1, 2019. Retrieved February 16, 2019.
  30. ^ a b Basa, Mick (August 21, 2014). . Rappler. Archived from the original on February 18, 2019. Retrieved February 17, 2019.
  31. ^ a b "DOTC eyes elevated railway from Malolos to Los Banos". ABS-CBN News. July 22, 2013. from the original on August 22, 2015. Retrieved April 23, 2019.
  32. ^ . Archived from the original on January 2, 2014. Retrieved January 1, 2014.
  33. ^ (PDF) (Report). Japan International Cooperation Agency. September 2014. Archived from the original (PDF) on October 11, 2014.
  34. ^ a b "New north-south commuter railway set". www.officialgazette.gov.ph. December 1, 2015. from the original on July 2, 2021. Retrieved December 24, 2020.
  35. ^ "Bidders line up for Philippines North-South line". International Railway Journal. August 20, 2015. from the original on May 17, 2021. Retrieved May 17, 2021.
  36. ^ a b "P287-B North-South Railway project eyed for 2020 operation". PPP Center. February 18, 2015. from the original on July 2, 2021. Retrieved December 24, 2020.
  37. ^ "PNR lines up new railway project for PPP". Philstar.com. Retrieved November 3, 2021.
  38. ^ "NEDA Board approves six transport infra projects". www.officialgazette.gov.ph. February 16, 2015. from the original on July 2, 2021. Retrieved December 25, 2020.
  39. ^ Camus, Miguel (January 29, 2016). "PH, Japan seal P97-B commuter rail project". Philippine Daily Inquirer. from the original on December 24, 2020. Retrieved December 24, 2020.
  40. ^ Diangson, Louie (January 29, 2016). "PH, Japan signs deal for the Php97 billion commuter railway". www.yugatech.com. from the original on December 24, 2020. Retrieved December 24, 2020.
  41. ^ Dela Paz, Chrisee (November 28, 2015). . rappler.com. Archived from the original on November 25, 2018. Retrieved December 25, 2020.
  42. ^ "Tugade: PNR Clark, Calamba trains to arrive in December 2021". Philippine Information Agency. from the original on June 26, 2021. Retrieved June 26, 2021.
  43. ^ "Philippines adopts standard gauge for new lines". International Railway Journal. August 9, 2016. from the original on April 23, 2021. Retrieved May 17, 2021.
  44. ^ Dela Paz, Chrisee (November 17, 2016). . Rappler. Archived from the original on November 21, 2016. Retrieved May 25, 2022.
  45. ^ Dela Paz, Chrisee (June 25, 2017). "17 stations of Manila–Clark railway announced". Rappler. from the original on March 22, 2019. Retrieved February 17, 2019.
  46. ^ Padin, Mary Grace (January 23, 2019). "Gov't secures P98.7 billion JICA loans for railway, flood control". The Philippine Star. from the original on November 26, 2020. Retrieved February 3, 2022.
  47. ^ Parrocha, Azer (July 11, 2019). "PRRD orders DOTr to hasten completion of Malolos-Clark Railway". Philippine News Agency. from the original on July 11, 2019. Retrieved February 3, 2022.
  48. ^ a b "NSCR Extension Project starts construction". The Manila Times. September 27, 2021. Retrieved May 24, 2022.
  49. ^ de Vera, Ben O. (June 9, 2022). "ADB OKs $4.3B loan for Manila-Calamba railway project". Philippine Daily Inquirer. Retrieved June 9, 2022.
  50. ^ Pinlac, Beatrice (June 17, 2022). "PH, ADB ink $4.3B loan agreement for South Commuter Railway project". Philippine Daily Inquirer. Retrieved June 17, 2022.
  51. ^ Cordero, Ted (February 9, 2023). "PH, Japan ink ¥400-B loan deals for North-South railway, extension projects". GMA Integrated News. Retrieved February 22, 2023.
  52. ^ "DMCI, Japanese partner bag P54-B contract for North-South Commuter Railway project". GMA News Online. May 21, 2019. from the original on May 28, 2019. Retrieved May 28, 2019.
  53. ^ "Viaduct contract awarded for Philippines' NSCR". International Railway Journal. December 22, 2020. from the original on May 17, 2021. Retrieved May 17, 2021.
  54. ^ "Overview". Sumitomo Mitsui Construction. Retrieved May 25, 2022.
  55. ^ "NORTH-SOUTH COMMUTER RAILWAY PROJECT (MALOLOS-TUTUBAN) N1CP04: ELECTRICAL AND MECHANICAL SYSTEMS AND TRACKWORKS". Department of Transportation (Philippines). August 25, 2021. Retrieved November 5, 2021.
  56. ^ Procurement Service – Philippine Government Electronic Procurement System (October 13, 2022). "General Bid Bulletin No. 4 - Responses to Clarifications" (PDF). Retrieved February 21, 2023.
  57. ^ Manuel, Pilar (September 21, 2020). "Megawide, 2 Korean firms secure construction for part of Malolos-Clark Railway". CNN Philippines. from the original on October 18, 2020. Retrieved May 5, 2021.
  58. ^ Loyola, James A. (September 21, 2020). "Megawide, Korean partners win P28-B railway project". Manila Bulletin. from the original on July 2, 2021. Retrieved May 5, 2021.
  59. ^ "Contracts Worth $1.7 Billion Awarded for ADB-Funded Malolos–Clark Railway Project". Asian Development Bank. October 8, 2020. from the original on January 3, 2022. Retrieved January 3, 2022.
  60. ^ "Philippines awards North-South Commuter Railway contracts". International Railway Journal. August 4, 2020. from the original on May 17, 2021. Retrieved May 17, 2021.
  61. ^ a b Rosales, Elijah Felice (February 21, 2023). "DOTr awards contract for P40 billion NSCR line". Philstar. Retrieved February 21, 2023.
  62. ^ Department of Transportation (February 17, 2023). "Notice of Contract Award: Malolos to Clark Railway Project (Blumentritt Extension) - Package CP S-01" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  63. ^ Department of Transportation (February 17, 2023). "Notice of Contract Award: South Commuter Railway Project - Package CP S-02" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  64. ^ Department of Transportation (February 20, 2023). "Notice of Contract Award: South Commuter Railway Project - Package CP S-03B" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  65. ^ Department of Transportation (September 23, 2022). "Notice of Contract Award: South Commuter Railway Project - Package CP S-04" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  66. ^ Department of Transportation (September 23, 2022). "Notice of Contract Award: South Commuter Railway Project - Package CP S-05" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  67. ^ Department of Transportation (September 23, 2022). "Notice of Contract Award: South Commuter Railway Project - Package CP S-06" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  68. ^ Department of Transportation (September 23, 2022). "Notice of Contract Award: South Commuter Railway Project - Package CP S-07" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  69. ^ Department of Transportation (January 14, 2022). "Notice of Award of Contract Package NS-02: Rolling Stock – Commuter Trainsets" (PDF). Procurement Service – Philippine Government Electronic Procurement System. Retrieved February 21, 2023.
  70. ^ Balinbin, Arjay (March 9, 2022). "Japan's J-Trec-Sumitomo JV bags new trainset contract for gov't railways". BusinessWorld. Retrieved February 21, 2023.
  71. ^ Pateña, Aerol John (January 6, 2018). "Preps begin for Phase 1 of PNR Clark railway project". Philippine News Agency. from the original on June 26, 2021. Retrieved June 26, 2021.
  72. ^ Dela Paz, Chrisee. "17 stations of Manila–Clark Railway revealed". Rappler. from the original on March 22, 2019. Retrieved June 25, 2017.
  73. ^ Aning, Jerome (June 25, 2017). "DOTr leads marking of Manila–Clark railway's 5 future stations". Philippine Daily Inquirer. from the original on June 12, 2018. Retrieved June 25, 2017.
  74. ^ "DOTr - TUGADE: PNR CLARK, CALAMBA TRAINS TO ARRIVE IN DECEMBER 2021". dotr.gov.ph. from the original on June 2, 2021. Retrieved July 13, 2021.
  75. ^ a b Dela Paz, Chrissie (September 13, 2017). "NEDA Board approves Manila subway, longest railway". Rappler. from the original on September 14, 2017. Retrieved September 15, 2017.
  76. ^ Leyco, Chino S. (September 13, 2017). . Manila Bulletin. Archived from the original on September 14, 2017. Retrieved September 15, 2017.
  77. ^ "Completion of PNR Clark Phase 1, 2 on track". Philippine News Agency. March 8, 2021. from the original on March 8, 2021. Retrieved March 9, 2021.
  78. ^ Gines, Ben Jr. (December 2, 2021). "PNR phase 1 on track for 2022 completion". The Manila Times. from the original on December 2, 2021. Retrieved January 3, 2022.
  79. ^ "LOOK: PNR Clark phase 2 train will run from Malolos to Clark in 30 minutes | Coconuts". Coconuts Manila. September 21, 2021. from the original on September 23, 2021. Retrieved January 3, 2022.
  80. ^ Balinbin, Arjay L. (December 1, 2021). "Construction progress for PNR Clark Phase 1 Balagtas, Bocaue stations exceeds 23%". BusinessWorld Online. from the original on December 1, 2021. Retrieved January 3, 2022.
  81. ^ a b "Civil works start for Metro Manila-Bulacan railway segment". www.pna.gov.ph. from the original on June 3, 2020. Retrieved January 22, 2020.
  82. ^ "Project_Details – BUILD". build.gov.ph. from the original on August 14, 2020. Retrieved April 27, 2019.
  83. ^ "Project Details – Build". Build.gov.ph. June 1, 2018. Retrieved January 9, 2020.[permanent dead link]
  84. ^ "PH, Japan sign P78-b loan for Luzon railway network". Manila Standard. from the original on November 25, 2018. Retrieved February 17, 2019.
  85. ^ a b c d e f g Department of Transportation The Republic of the Philippines (October 2018). "FEASIBILITY STUDY ON THE NORTH SOUTH RAILWAY PROJECT-SOUTH LINE (COMMUTER)(NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT) IN THE REPUBLIC OF THE PHILIPPINES" (PDF). jica.go.jp. (PDF) from the original on April 11, 2021. Retrieved April 26, 2019.
  86. ^ "Railways Sector". www.dotr.gov.ph. Department of Transportation (Philippines). from the original on May 26, 2021. Retrieved June 10, 2021.
  87. ^ "Chapter 6" (PDF). Route Plan and Railways System. Study on railway strategy for Clark-metro Manila for the greater capital region in the Republic of the Philippines: final report. (Report). Vol. II. Japan International Cooperation Agency. June 2013. Retrieved September 11, 2021.
  88. ^ "Philippines: South Commuter Railway Project". Asian Development Bank. May 2022. Retrieved October 20, 2022.
  89. ^ Invitation for Bids, PB21-036-5 (PDF). South Commuter Railway Project for Package Number CP S-03a: Building and Civil Engineering Works for approximately 7.9 kms of at Grade and Viaduct Railway Track Structure including Elevated Station at Buendia and at Grade Stations at EDSA and Senate (Report). March 22, 2021. Retrieved October 20, 2022.
  90. ^ a b "Roadmap for Transport Infrastructure Development for Metro Manila and its Surrounding Areas (Region III and Region IV-A)" (PDF). Japan International Cooperation Agency. March 30, 2014. (PDF) from the original on June 27, 2020. Retrieved May 7, 2020.
  91. ^ Dela Paz, Chrisee (September 13, 2017). "NEDA Board approves Metro Manila Subway". Rappler. from the original on September 14, 2017. Retrieved September 14, 2017.
  92. ^ Villanueva, Joann (January 22, 2019). "PNR asks for feasibility of Cabanatuan-Makati line". Philippine News Agency. from the original on November 5, 2020. Retrieved August 2, 2020.
  93. ^ National Economic and Development Authority (August 2019). FOLLOW-UP SURVEY ON ROADMAP FOR TRANSPORT INFRASTRUCTURE DEVELOPMENT FOR GREATER CAPITAL REGION (GCR) (PDF) (Report). Vol. JR 19-003. Japan International Cooperation Agency.
  94. ^ INQUIRER.net. "PNR to preserve old train stations in Bulacan". newsinfo.inquirer.net. from the original on July 27, 2020. Retrieved April 18, 2020.
  95. ^ Pateña, Aerol John (January 18, 2018). "Taguig integrated terminal to ease traffic on EDSA". Philippine News Agency. from the original on January 3, 2022. Retrieved January 3, 2022.
  96. ^ a b c BIDDING DOCUMENTS FOR PROCUREMENT OF PACKAGE CP NS-03: ROLLING STOCK - LIMITED EXPRESS TRAINSETS (PDF) (Report). Vol. 2 of 3. Philippine National Railways. February 2021. (PDF) from the original on August 21, 2021. Retrieved August 19, 2021.
  97. ^ Balinbin, Arjay L. (July 21, 2021). "North-South rail, subway trains to start arriving in December". BusinessWorld. from the original on July 21, 2021. Retrieved July 23, 2021.
  98. ^ マニラ南北線EM10011Mとマニラ南北線EM10011Lが株式会社総合車両製作所(J-TREC)から陸送!【令和3年(西暦2021年)10月18日月曜日】 [Manila North-South Line EM10011M and Manila North-South Line EM10011L being shipped by land from [the] Japan Transport Engineering Company (J-TREC)! (Monday, October 18, 2021)] (YouTube) (in Japanese). October 18, 2021. Retrieved October 19, 2021.
  99. ^ a b "First 8-car trainset for PNR Clark Phase 1 arrives in PH". ABS-CBN News. November 21, 2021. from the original on November 21, 2021. Retrieved November 22, 2021.
  100. ^ "Notice of Award of Contract Package NS-02: Rolling Stock – Commuter Trainsets" (PDF). Department of Transportation (Philippines). January 14, 2022. Retrieved January 22, 2022.
  101. ^ Abadilla, Emmie V. (March 18, 2022). "PH's 1st electric multiple train set unveiled". Manila Bulletin. Retrieved March 20, 2022.
  102. ^ a b c "Order Received to Supply 304 for the Philippines' North-South Commuter Railway Extension Project". Sumitomo Corporation. March 18, 2022. from the original on March 20, 2022. Retrieved March 20, 2022.
  103. ^ "1 local, 5 foreign firms bid for P50.8-B PNR Clark Phase 2". GMA News. October 16, 2019. from the original on February 15, 2020. Retrieved February 15, 2020.
  104. ^ Environmental Impact Assessment (PDF). Proposed Multitranche Financing Facility Republic of the Philippines: South Commuter Railway Project (Report). Department of Transportation (Philippines) and the Asian Development Bank. July 1, 2020. (PDF) from the original on May 17, 2021. Retrieved May 17, 2021.
  105. ^ "Philippines: Philippines to engage Japanese manufacturers for NSCR Express trainsets". International Union of Railways. May 10, 2021. from the original on May 17, 2021. Retrieved May 17, 2021.
  106. ^ a b LIVE: Bid Opening for the Contract Package NS-03 - Limited Express Rolling Stock (16:9 720p) (Facebook Live). Department of Transportation (Philippines). October 15, 2021. Retrieved October 16, 2021.
  107. ^ PTS Technical Talks - May 19, 2022 (16:9 1080p) (YouTube). Philippine Tunneling Society. May 19, 2022.
  108. ^ a b BIDDING DOCUMENTS FOR THE PROCUREMENT OF PACKAGE CP03: ROLLING STOCK (Report). Vol. 2 of 3. Department of Transportation (Philippines). July 2018. from the original on January 4, 2022. Retrieved January 4, 2022.
  109. ^ Valdez, Denise (July 17, 2019). "DoTr, Japan firms ink P12-B contract for train cars". BusinessWorld. from the original on April 14, 2021. Retrieved April 14, 2021.
  110. ^ a b c "PART 2 Employer's Requirements" (PDF). The Malolos–Clark Railway Project and the North South Railway Project-South Line (Commuter) PACKAGE CP NS-01: E&M SYSTEMS AND TRACK WORKS. Department of Transportation (Philippines). March 2021. (PDF) from the original on March 13, 2022. Retrieved March 13, 2022.

north, south, commuter, railway, this, article, about, philippine, rail, line, other, uses, north, south, railway, nscr, also, known, clark, calamba, railway, kilometer, mile, urban, rail, transit, system, under, construction, island, luzon, philippines, runni. This article is about the Philippine rail line For other uses see North South Railway The North South Commuter Railway NSCR also known as the Clark Calamba Railway is a 147 kilometer 91 mile urban rail transit system under construction in the island of Luzon Philippines Running from New Clark City in Capas to Calamba Laguna with 36 stations and four services the railway was designed to improve connectivity within the Greater Manila Area and will be integrated with the railway network in the region 5 6 7 North South Commuter RailwayConstruction of the railway in Balagtas BulacanOverviewStatusUnder constructionOwnerDepartment of TransportationLocaleCentral Luzon Metro Manila CalabarzonTerminiNew Clark CityCalambaStations36Websitewww wbr nscr wbr com wbr phServiceTypeCommuter railAirport rail linkSystemPNR North Main Line Tutuban Malolos PNR South Main Line Tutuban Calamba Services4Operator s Philippine National RailwaysDepot s Malanday a MabalacatBanlicRolling stockVarious see rolling stockHistoryPlanned opening2025 partial 2029 full b TechnicalLine length147 km 91 mi Number of tracksDouble track c CharacterElevated d Track gauge1 435 mm 4 ft 8 1 2 in standard gaugeLoading gauge4 150 mm 3 000 mm 13 ft 7 in 9 ft 10 in 1 Minimum radiusMainline 260 400 m 850 1 310 ft 1 Depot 92 100 m 302 328 ft 1 Electrification1 500 V DC overhead lines 1 Operating speed120 160 km h 70 100 mph e SignallingETCS Level 2 f Highest elevation130 m 430 ft at Clark International Airport stationMaximum incline25 Average inter station distance4 11 km 2 55 mi Route mapNew Clark CityMabalacat DepotClark International AirportQuitangil RiverClarkAbacan RiverClarkAngeles CityAngelesAngeles CitySan FernandoSindalan CreekSan FernandoSan Fernando RiverSan FernandoApalitApalitApalitCalumpitPampanga RiverCalumpitAngat RiverCalumpitMalolosMalolosMalolos SouthMalolosGuiguintoGuiguintoGuiguinto RiverGuiguintoBalagtasBalagtasSantol RiverBalagtasBocaueBocaue RiverBocaueBocaueMarilaoTabing IlogIgulot RiverMarilaoMarilao RiverMarilaoMeycauayanMeycauayanMeycauayan RiverMeycauayanValenzuelaValenzuelaValenzuela DepotValenzuela PoloTullahan RiverValenzuelaMalabonMalabonMalabonCaloocanCaloocanCaloocanManilaSolisTutubanBlumentrittEspana 8Estero de ValenciaSanta MesaPasig RiverPacoManilaMakatiBuendiaEstero de Tripa de GallinaEDSA 3Makati Estero de Tripa de Gallina TaguigNicholsAsia World East Valenzuela FTI MMS TaguigParanaqueBicutan MMS ParanaqueMuntinlupaSucatSucat RiverMangangate RiverAlabangBayanan CreekPoblacion RiverMuntinlupaMagdaong RiverMuntinlupa Tunasan River San PedroSan Isidro RiverSan PedroPacitaSan PedroBinanBinanBinan RiverBinanSanta RosaSilang Sta Rosa RiverSanta RosaSanta RosaCabuyaoCabuyao RiverCabuyaoGulodCabuyao RiverMamatidCabuyaoCalambaBanlicBanlic DepotSan Cristobal RiverSan Juan RiverCalambaThis diagram viewtalkeditOriginally planned in the 1990s the railway project has had a tumultuous history being repeatedly halted and restarted due to various reasons 8 The first proposal was the 32 kilometer 20 mile Manila Clark rapid railway with Spain in the 1990s that was discontinued after disagreements on funding 8 9 and during the 2000s the NorthRail project with China that was discontinued in 2011 due to allegations of overpricing 10 11 12 The current railway line began development in 2013 13 The project s initial phase was approved in 2015 14 and construction began in 2019 15 Expected to cost 873 62 billion 16 the line is the most expensive railway transportation project in the country The entire system is expected to be completed by 2029 17 Upon its completion the railway will supersede the existing PNR Metro Commuter Line Contents 1 History 1 1 Background 1 1 1 Manila Clark rapid railway system 1 1 2 NorthRail 1 2 Development 1 3 Construction 2 Route 2 1 Services 2 2 Stations 2 3 Extensions and additional stations 3 Infrastructure 3 1 Station layout 3 2 Rolling stock 3 3 Signalling 3 4 Tracks 4 See also 5 Footnotes 6 ReferencesHistory EditBackground Edit The Ferrocarril de Manila a Dagupan operated trains to and from Manila See also PNR Metro Commuter Line History During the Spanish and American colonial periods the Manila Railway Company later the Manila Railroad Company MRR operated various local trains between Manila and its neighboring provinces By the 1920s trains ran from Tutuban to Naic in Cavite Pagsanjan in Laguna Montalban in Rizal and Bulacan 18 The network was heavily damaged in the Battle of Manila during World War II 19 but was mostly reestablished after the war 20 MRR would be succeeded by the Philippine National Railways PNR on June 20 1964 21 On April 6 1970 PNR inaugurated the Metro Manila Commuter Service which started at Manila North Harbor and ended in Binan station in Laguna 22 After numerous expansions the commuter service served thousands of daily riders in its system and had an expansive network in and out of Metro Manila 23 In 1978 at the request of the Philippine government the Japan International Cooperation Agency JICA conducted a study on the electrification of the commuter service 24 The plan was made to keep up with the increasing demand for transportation in the region It called for the replacement of the diesel run trains and the electrification of the PNR commuter line Two experts from the Japanese National Railways were sent to conduct the study 24 Services north of Manila started to decline in the 1980s However commuter services were briefly extended to Malolos starting in 1990 under the Metrotren project but later ceased in 1997 25 Since then railway services have been mostly confined to the south with the contemporary Metro Commuter Line being predominantly aligned to the South Main Line 26 Manila Clark rapid railway system Edit During the 1990s President Fidel Ramos signed a memorandum of agreement with Juan Carlos I of Spain for the construction of a railway line from Manila to Clark in September 1994 8 This would be known as the Manila Clark rapid railway system On August 24 1995 North Luzon Railways Corporation NLRC was formed as a subsidiary of Bases Conversion and Development Authority BCDA 8 The NLRC then entered into an engineering procurement and construction contract with the Spanish Railways Corporation on February 7 1996 but the contract was later terminated on August 14 1998 after the parties disagreed on the source of funding for the project 8 In September 1999 the National Economic and Development Authority NEDA approved the railway project with the initial phase covering a segment from Caloocan to Calumpit The source of funding was to be the Obuchi Fund from the Japan Bank for International Cooperation JBIC 8 Pre construction activities such as right of way clearing and relocation of affected informal settlers began but a presidential directive later halted the clearing activities and the JBIC loan was not granted 8 NorthRail Edit Abandoned NorthRail columns in Malolos Bulacan that have since been demolished Under the presidency of Gloria Macapagal Arroyo a successor to the Manila Clark rapid railway system the NorthRail project an 80 kilometer 50 mile rail line 27 was conceived On September 14 2002 a memorandum of understanding was signed by NorthRail and China National Machinery and Equipment Group CNMEG for the project 8 It was later approved on August 5 2003 8 The project was estimated to cost around US 500 million and the funding was to be covered by a US 400 million loan from the Export Import Bank of China and the rest to be shouldered by the government through BCDA and NLRC 8 9 28 The project involved the upgrading of the existing single track to an elevated dual track system converting the rail gauge from narrow gauge to standard gauge and linking Manila to Malolos in Bulacan and further on to Angeles City Clark Special Economic Zone and Clark International Airport 8 The first phase of the project covered the Caloocan to Malolos segment which spans 32 kilometers 20 miles 28 Before construction could start the Philippine Senate raised concerns about alleged corruption in the project Senator Franklin Drilon commissioned a study from the University of the Philippines which recommended the cancellation of the railway s construction citing anomalies in the bidding process and the Buyer Credit Loan Agreement BCLA with Exim China 8 Despite the controversy preparatory construction began in early November 2006 Civil and design works started in October 2007 Due to delays in the construction work it was soon renegotiated with the Chinese government Construction temporarily continued in January 2009 with the support of the North Luzon Railways Corporation 8 However the NorthRail project would be formally cancelled in March 2011 due to persisting legal issues and allegations of overpricing and corruption 9 12 10 Nonetheless on September 2011 the government expressed its interest to restart the project with Interior and Local Government Secretary Mar Roxas stating that China was open to reconfiguring the project 29 12 NEDA Director General Arsenio Balisacan also stated that NorthRail would resume within the term of President Benigno Aquino III 30 but despite the announcement the NorthRail project was permanently scrapped and replaced with the NSCR project 31 although the Philippine government was still obligated to pay the corresponding loans In March 2012 the Philippine Supreme Court authorized a lower court to hear the case for voiding the contract Instead of paying the US 184 million owed by the government in 2012 the Department of Finance was to pay the Export Import Bank of China four installments of US 46 million from September 2012 onwards 30 On November 6 2017 DOTr BCDA and North Luzon Railways reached an out of court settlement with Sinomach formerly CNMEG resolving the five year dispute It saved the government 5 billion in potential payment of claims to Sinomach and hundreds of millions of pesos in legal fees and arbitration costs 27 Development Edit See also Build Build Build and Metro Manila Dream Plan With the termination of the NorthRail project the Department of Transportation and Communications considered restarting the project by commissioning a feasibility study by CPCS Transcom Ltd of Canada Part of the study examined having a Malolos Tutuban Calamba Los Banos commuter line 31 32 The feasibility study was still ongoing when the NEDA included the North South Commuter Railway in the Metro Manila Dream Plan which it approved in 2014 33 The plan for the NSCR a component of the North South Railway Project 34 included the 37 kilometer 23 mile NSCR Phase 1 an electrified narrow gauge 35 commuter railway from Tutuban to Malolos and funded through overseas development assistance and the second phase which included the reconstruction of the Tutuban Calamba commuter line and the rehabilitation of long haul services with an extension up to Matnog Sorsogon and a branch line from Calamba to Batangas It was to be funded through a public private partnership PPP scheme 34 36 37 On February 16 2015 the NEDA board chaired by President Benigno Aquino III approved the NSCR Phase 1 project 36 38 After President Aquino met with Japanese Prime Minister Shinzo Abe in Japan in June 2015 Abe expressed his commitment to fund the project On November 19 2015 representatives of both countries exchanged notes on the project in the presence of Abe and Aquino 14 JICA was chosen by the Japanese government to look into financing the project and on November 27 seven months before Aquino would end his term JICA and the Department of Finance signed a loan agreement worth 97 3 billion 1 99 billion for the financing of the first phase 39 40 41 The succeeding administration included the project under the Build Build Build Infrastructure Program 42 In addition numerous changes to the project were made The railway s gauge was changed to standard gauge 43 and the railway was extended to New Clark City In addition the PPP scheme for the south commuter line was abandoned in favor of overseas development assistance from Japan 44 On June 25 2017 transportation secretary Arthur Tugade announced the new name for the project and unveiled the locations of the first five stations during a press tour of the old PNR line 45 On January 21 2019 a loan agreement worth 80 47 billion US 1 54 billion for the North South Commuter Railway Extension Project NSCR Ex which includes the PNR Clark 2 and Calamba sections was signed by JICA and the Department of Finance DOF 46 Another loan agreement worth 66 6 billion US 1 3 billion for the NSCR Ex project was signed on July 11 by the Asian Development Bank ADB and DOF 47 JICA would finance the electrical and mechanical systems as well as the trains for the PNR Clark 2 and Calamba sections while ADB would finance the civil works 48 The loan for the civil works of PNR Calamba worth 227 billion US 4 3 billion was approved by the ADB on June 9 2022 49 The loan agreement was signed by President Rodrigo Duterte and ADB on June 16 50 Two more loan agreements were signed on February 9 2023 during the working visit of President Bongbong Marcos in Japan 51 Construction Edit List of contractors Contract package Scope of work Contractors Date awarded NotesTutuban Malolos railwayCP 01 Construction of Solis Bocaue section Taisei Corporation DMCI Holdings May 2019 52 VSL International a subsidiary of Bouygues was appointed as the subcontractor for the construction of the viaduct 53 CP 02 Construction of Bocaue Malolos section Sumitomo Mitsui Construction 54 December 2018CP 03 Rolling stock for Tutuban Malolos railway J TREC July 2019CP 04 55 Electrical and mechanical E amp M systems Hitachi Rail STS November 2022 2 CP 05 Construction of Tutuban Solis section TBD Ongoing bidding 56 Malolos Clark railwayN 01 Construction of Malolos San Simon section Megawide Construction Corporation Hyundai Engineering amp Construction Dong ah Geological Engineering Company September 2020 57 58 N 02 Construction of San Simon Mexico section Acciona Daelim Industrial October 2020 59 N 03 Construction of Mexico Clark Mabalacat section Italian Thai Development Public Company LimitedN 04 Construction of Clark Mabalacat Clark International Airport section EEI Corporation Acciona August 2020 60 N 05 Construction of 33 hectare 82 acre depot and main operations control center in Mabalacat POSCOS 01 Construction of Solis Blumentritt section Blumentritt extension PT Adhi Karya PT PP February 2023 61 62 Manila Calamba South Commuter railwayS 02 Construction of Blumentritt Paco section DMCI Holdings Acciona February 2023 61 63 S 03a Construction of Paco Senate section TBD Ongoing biddingS 03b Construction of Senate FTI section and tunneling works to MMSP Senate station Leighton Contractors Asia First Balfour February 2023 64 S 03c Construction of FTI Sucat section TBD Ongoing biddingS 04 Construction of Sucat San Pedro section Hyundai Engineering amp Construction Dong ah Geological Engineering Company September 2022 17 65 S 05 Construction of San Pedro Cabuyao section September 2022 17 66 S 06 Construction of Cabuyao Calamba section September 2022 17 67 S 07 Construction of Banlic depot Lotte Engineering amp Construction Gulermak EEI Corporation September 2022 17 68 Other associated contractsNS 01 Electrical and mechanical E amp M systems for Malolos Clark and Manila Calamba railways Mitsubishi Alstom Colas Rail February 2023 3 NS 02 Commuter rolling stock for Malolos Clark and Manila Calamba railways J TREC January 2022 69 70 NS 03 Limited express trains TBD Ongoing bidding Construction of PNR Clark 1 in Meycauayan Bulacan in March 2022 Construction of PNR Clark 2 in Mabalacat Pampanga in October 2022 Pre construction works such as clearing of the right of way started on January 5 2018 71 The North South Commuter Railway is being built in three phases and divided into two primary sections PNR Clark This is the northern section of the NSCR Construction was divided into two phases PNR Clark 1 involves the 38 kilometer 24 mile Tutuban Malolos railway while PNR Clark 2 involves the 53 kilometer 33 mile Malolos Clark railway The 91 kilometer 57 mile railway line when fully completed will run from Tutuban station in Manila to New Clark City station within the Clark Freeport and Special Economic Zone with a link to Clark International Airport 72 73 PNR Calamba Also known as PNR Clark Phase 3 74 PNR Calamba is the southern section of the NSCR It involves the reconstruction of the existing Metro Commuter Line as an electrified standard gauge railway with elevated at grade and depressed sections 75 76 The 56 kilometer 35 mile railway will run from Solis station in Manila to Calamba station in Laguna The groundbreaking of PNR Clark 1 was held on February 15 2019 and construction started after 15 Meanwhile the groundbreaking of PNR Clark 2 was held on September 18 2021 48 PNR Clark is expected to start partial operations in October 2022 with full operations in 2024 77 As of December 2021 update PNR Clark 1 is 51 3 complete while PNR Clark 2 is 32 complete as of September 2021 update 78 79 Construction of PNR Calamba is set to begin by 2022 with partial operations slated by 2025 80 and full operations by March 2029 17 Route EditThe North South Commuter Railway will comprise two sections corresponding to the Philippine National Railways old main lines The first is the 91 kilometer 57 mile 81 fully elevated PNR Clark which is being built over the mostly defunct North Main Line in northern Metro Manila and Central Luzon 82 83 The construction of PNR Clark is further subdivided into two sections the 38 kilometer 24 mile PNR Clark 1 between Tutuban and Malolos and the 53 kilometer 33 mile PNR Clark 2 from Malolos to New Clark City 84 The second component is the 56 kilometer 35 mile 81 PNR Calamba which will use the existing PNR Metro Commuter Line right of way between Tutuban and Calamba which were historically parts of the South Main Line and will have elevated at grade and depressed sections 75 Services Edit There are four classes of services on this line The following are 85 Commuter is the basic commuter rail service and has the least priority It stops at all stations within its route There are three routes planned for this class Tutuban New Clark City Tutuban Calamba and Clark International Airport Calamba The maximum speed for this service will be 120 kilometers per hour 75 miles per hour for the entire line Commuter Express is the limited stop service for the line succeeding the Commex service during the Metrotren era in the early 2000s Although it will run faster than regular commuter trains it will still use the same routes and rolling stock The Airport Limited Express is the temporary designation for the planned airport rail link and limited express service between Clark International Airport and Alabang station As the flagship NSCR service it will use dedicated rolling stock complete with intercity grade amenities plus baggage space for people arriving from the airport It will have a maximum speed of 160 kilometers per hour 100 miles per hour along the NSCR North As of January 2022 update the final name for the service is yet to be determined Subway through service is the proposed augmentation between the NSCR and the Metro Manila Subway It will serve the southernmost areas of Metro Manila and neighboring Laguna branching from the subway line at FTI station while the remainder of the line will go towards the direction of NAIA Terminal 3 in Pasay It will use the Subway trainsets instead of the NSCR ones although both are from the Sustina family Stations Edit Proposed train stations and services 86 85 87 Phase Station Services Transfers LocationCommuter Commuter express Limited express Through service to fromMetro Manila Subway 85 NCC Tutuban CIA Calamba Tutuban Calamba NCC Tutuban CIA Calamba Tutuban CalambaPNR Clark 2 New Clark City none Capas TarlacClark International Airport Clark International Airport Mabalacat PampangaClark noneAngeles Angeles PampangaSan Fernando San Fernando PampangaApalit Apalit PampangaCalumpit Calumpit BulacanMalolos Malolos BulacanPNR Clark 1Malolos South Guiguinto Guiguinto BulacanTuktukan Balagtas Balagtas BulacanBocaue Bocaue BulacanTabing Ilog Marilao BulacanMarilao Meycauayan Meycauayan BulacanValenzuela ValenzuelaValenzuela Polo Malabon MalabonCaloocan CaloocanSolis ManilaTutuban TutubanPNR Calamba Blumentritt BlumentrittEspana noneSanta Mesa PurezaPaco noneBuendia MakatiEDSA 3 MagallanesSenate 88 89 None TaguigFTI MMS 16 TITXBicutan MMS 25 Bicutan ParanaqueSucat PNR Bicol 25 Sucat MuntinlupaAlabang noneMuntinlupa San Pedro San Pedro LagunaPacita Binan BinanSanta Rosa Santa Rosa LagunaCabuyao Cabuyao LagunaBanlic PNR Bicol Calamba LagunaCalamba noneStations in italics will open in 2030 Extensions and additional stations Edit The Metro Manila Dream Plan proposed a 38 kilometer 24 mile branch line that will split in Angeles City The line will have 12 stations and shall end in Tarlac City 90 The study also proposed a 47 kilometer 29 mile extension of the NSCR to Batangas City 90 This will be built parallel to the PNR South Long Haul project which was approved in 2017 with the line being a single track standard gauge line without electrification and will be built at grade similar to the present PNR network 91 The PNR has also requested for a feasibility study for a commuter line connecting Tarlac City and San Jose Nueva Ecija in 2019 The length of the line and the number of stations will be determined once a proposal has been submitted 92 Another proposed southward extension to Pansol in Calamba Laguna was proposed by a 2019 JICA report 93 The North South Commuter Railway will also have provisions for infill stations Malabon Valenzuela Polo Tabing Ilog Tuktukan and Malolos South 85 Infrastructure EditNSCR will be the first commuter rail system in the country to be mostly grade separated Trains are designed to run on 1 435 mm 4 ft 8 1 2 in standard gauge tracks at a design speed of 120 kilometers per hour 75 miles per hour for regular trains and 160 kilometers per hour 99 miles per hour for airport express trains Station layout Edit All stations will have a standard layout with a concourse level and a platform level The stations are designed to adhere to both Philippine and Japanese standards 85 Stations will either have island platforms or side platforms with platform screen doors The stations are designed to be barrier free and trains shall have spaces for passengers using wheelchairs Historical stations will be preserved 94 All stations will have access to intermodal facilities 85 The FTI station in particular will be connected to the Taguig Integrated Terminal Exchange 95 Rolling stock Edit See also List of Philippine National Railways rolling stock Future The North South Commuter Railway will have two types of rolling stock commuter trains and airport express trains With the exception of wheelchair spaces the commuter trains will have a capacity of 2 242 passengers The express trains on the other hand will have a capacity of 392 passengers 96 A total of 464 electric multiple unit traincars have been procured to operate on the line with 104 of these being the 8 car EM10000 class trainsets to be built by the Japan Transport Engineering Company J TREC successor to the Tokyu Car Corporation that provided rolling stock to the Philippines from 1955 to 1976 The trainsets were previously named as the Sustina Commuter at the time of purchase and are based on JR East commuter stock such as the E233 series but adapted to standard gauge g The trains are also designed to be interoperable with the Metro Manila Subway 97 The trainsets have been designated as the EM10000 class in October 2021 98 The first batch of the commuter trains arrived on November 21 2021 99 The bidding for an order for 304 more commuter cars in a separate contract was opened in September 2020 with the joint venture of Japan Transport Engineering Company and Sumitomo Corporation winning the contract on January 14 2022 100 The first EM10000 class train was unveiled on March 18 2022 101 and the contract for the 304 cars was signed by the DOTr Sumitomo and J TREC on the same day The deliveries of the 304 cars are set to be completed by September 2028 102 The 56 airport express trainsets meanwhile are being procured as of 2019 103 104 On February 26 2021 a suggested preliminary design based on the E259 and E353 series was published 96 On May 10 the Department of Transportation later announced it will acquire the airport express trainsets from Japanese manufacturers 105 After several months of delays and rescheduling three bidders have submitted their designs Kawasaki Heavy Industries and Sojitz joint venture Marubeni and Stadler Rail and Mitsubishi and Construcciones y Auxiliar de Ferrocarriles CAF 106 h The contract is expected to be awarded in the last quarter of 2022 needs update 107 Rolling stock Commuter trains 85 108 1 Airport express trains 96 109 Image Year Batch 1 Fiscal 2022Batch 2 2025 2028 102 TBDManufacturer J TREC TBD i Model EM10000 class first batch TBD second batch TBDNumber to be built First batch 104 cars 13 sets Second batch 304 cars 38 sets 56 cars 7 sets Order no CP 03 first batch CP NS 02 second batch CP NS 03Formation 8 cars per trainsetCar length 20 m 65 ft 7 in Width 2 95 m 9 ft 8 in Pantograph lockdown height 4 15 m 13 ft 7 in Floor height 1 13 1 15 m 3 ft 8 in 3 ft 9 in Body material Lightweight stainless steel Aluminum alloy and stainless steelTare weight 270 t 600 000 lb 315 t 694 000 lb Axle load 16 t 35 000 lb Capacity Leading car 266 standing 45 seatedIntermediate car 285 standing 54 seated Leading car 40 seatedIntermediate car 52 seatedPWD seating 8 wheelchair spacesSeat layout Rapid transit style longitudinal seating Airline style open coach seatingDoors per side 4 2Traction control IGBT VVVF first batch Hybrid SiC VVVF second batch Hybrid SiC VVVFTraction power 1 500 V DC overhead catenaryPantograph type 1 single arm pantograph Toyo Denki 2 single arm pantographs outward facingTop speed 120 km h 75 mph 170 km h 110 mph Train configuration Tc M M T T M M Tc Tc M M M M M M TcOther features Toilets luggage racksStatus First batch Under construction delivery 99 Second batch Ordered to be built 102 To be orderedSignalling Edit Initially the PNR Clark 1 section of the line was set to use a communications based train control CBTC system 108 The line will instead use a signalling system based on ETCS Level 2 The subsystems consist of automatic train control ATC automatic train protection ATP automatic train supervision ATS train detection through track circuits and computer based interlocking with provisions for automatic train operation ATO 110 For Phase 1 between Tutuban and Malolos Hitachi s Italian subsidiary Hitachi Rail STS will be the provider of ETCS Level 2 equipment as part of a contract package covering electrical and mechanical systems and track works 2 For Phase 2 between and the NSCR South Alstom will use its Atlas 200 system for Level 2 signalling 4 Tracks Edit The line will feature an Elastic Sleeper Direct Fasten ESDF type ballastless track with concrete sleepers in the mainline and plastic fiber reinforced foam urethane railroad ties on turnouts in the mainline and depot 110 Continuous welded rails will be employed on the mainline while jointed rails with fishplates will be employed in the depot 60 kilogram per meter 120 pound per yard rails will be employed in the mainline while rails built to the JIS 50N rail profile will be used in the depot 110 See also EditPhilippine National Railways Department of Transportation DOTr Transportation in the Philippines Rail transportation in the Greater Manila AreaFootnotes Edit Main depot The project will be implemented in three phases which will have their own opening dates May use quadruple track at stations May be through viaduct or embankment Also includes an at grade section between EDSA and FTI stations and an underground section around Clark International Airport station Up to 120 kilometers per hour 75 miles per hour for commuter trains while 160 kilometers per hour 100 miles per hour for airport express trains Hitachi Rail STS will supply ETCS Level 2 equipment along Phase 1 between Tutuban and Malolos 2 while Alstom s Atlas 200 was selected for the Malolos Clark and NSCR South segments 3 4 The E233 series and other Japanese commuter trainsets run on 1 067 mm 3 ft 6 in narrow gauge tracks Mitsubishi and CAF are currently manufacturing the LRTA 13000 class light rail vehicles for the LRT Line 1 Three bidders have submitted their designs Kawasaki Railcar Marubeni and Mitsubishi 106 References Edit a b c d e PART 2 EMPLOYER S REQUIREMENTS from BIDDING DOCUMENTS FOR PROCUREMENT OF PACKAGE CP NS 02 ROLLING STOCK COMMUTER TRAINSETS PDF Report Vol 2 of 3 Philippine National Railways September 2020 Archived PDF from the original on January 4 2022 Retrieved January 4 2022 a b c Balinbin Arjay L November 14 2022 Malolos Tutuban rail contract bagged by Japan s Hitachi Rail BusinessWorld Retrieved November 22 2022 a b Department of Transportation February 2 2023 Notice of Award PDF Department of Transportation Philippines Retrieved February 8 2023 a b Alstom led consortium to provide integrated railway system for the Philippines North South Commuter Railway Extension Project Alstom March 6 2022 Retrieved March 7 2022 Main Points of the Roadmap PDF Report Japan International Cooperation Agency September 2014 Archived from the original PDF on October 11 2014 Camus Miguel R February 16 2019 DOTr plans to integrate new railway lines business inquirer net Archived from the original on February 16 2019 Retrieved February 16 2019 Patena Aerol John April 30 2019 DOTr awards contract to DMCI Consortium for PNR North Phase 1 Project Philippine News Agency Archived from the original on November 11 2020 Retrieved May 27 2021 a b c d e f g h i j k l m Off track Northrail timeline ABS CBN News July 15 2008 Archived from the original on February 17 2019 Retrieved February 17 2019 a b c Inquirer Philippine Daily January 17 2019 WHAT WENT BEFORE The Northrail Project newsinfo inquirer net Archived from the original on February 14 2019 Retrieved February 16 2019 a b U P study finds North Rail contract illegal disadvantageous to government The PCIJ Blog September 9 2005 Archived from the original on August 12 2014 Retrieved July 29 2014 Nicolas Jino November 6 2017 Northrail dispute settled BusinessWorld Archived from the original on June 26 2021 Retrieved June 26 2021 a b c Philippines China funded Northrail project derailed Financial Times Archived from the original on August 17 2018 Retrieved February 17 2019 DOTC eyes elevated railway from Malolos to Los Banos ABS CBN News July 22 2013 Archived from the original on August 22 2015 Retrieved April 23 2019 a b Japan Commits JPY241 991 Billion ODA For North South Commuter Railway Project Malolos Tutuban www ph emb japan go jp Embassy of Japan in the Philippines November 19 2015 Archived from the original on December 24 2020 Retrieved December 24 2020 a b Mercurio Richmond February 16 2019 Construction of North South Commuter Railway kicks off Philstar com Archived from the original on September 1 2021 Retrieved September 1 2021 Dela Cruz Raymond Carl August 11 2022 DOTr assures North South Commuter Railway on time completion Philippine News Agency Retrieved November 30 2022 a b c d e f 4 North South Railway contracts awarded PortCalls Asia October 6 2022 Retrieved October 6 2022 Orbon Glenn Dungca Joana 2015 The Philippine Railway System Movement Systems Gamble Adrian March 10 2017 Manila s Long Lost Tranvias Once the Envy of Asia skyrisecities com Skyrise Cities Archived from the original on June 21 2020 Retrieved June 21 2020 Chapter I Present Conditions Report of Survey of the Manila Railroad Company and the Preliminary Survey of Railroads for Mindanao Report Chicago De Leuw Cather amp Company 1951 pp 1 12 Republic Act No 4156 GOVPH Official Gazette of the Republic of the Philippines Archived from the original on January 3 2022 Retrieved January 3 2022 Carmona s Commuter Train Times Journal April 1973 Archived from the original on July 13 2021 Retrieved July 23 2020 Brief history of PNR Philippine National Railways February 27 2009 Archived from the original on February 27 2009 Retrieved November 4 2011 a b REPORT ON STUDY OF THE ELECTRIFICATION OF THE PNR COMMUTER SERVICE PDF Japanese International Cooperation Agency JICA December 1978 Archived PDF from the original on May 22 2021 Retrieved February 15 2021 Metrotren Inaugural Manila Chronicle May 11 1990 Archived from the original on July 13 2021 Retrieved May 6 2021 Corporate Profile Philippine National Railways Archived from the original on January 3 2022 Retrieved January 3 2022 The PNR currently operates in the Manila metropolitan area and the provinces of Laguna Quezon Camarines Sur and Albay In the past the PNR also used to serve the provinces of Bulacan Pampanga Tarlac Nueva Ecija Pangasinan and La Union on the North Main Line and Batangas on the South Main Line a b Paz Chrisee Dela November 6 2017 PH gov t ends dispute with China s Sinomach over Northrail project Rappler Archived from the original on November 25 2018 Retrieved February 16 2019 a b RP China break ground for Manila Ilocos railway Malaya April 6 2004 Archived from the original on May 9 2010 via lrta gov ph Bordadora Norman September 2 2011 China open to reconfiguring NorthRail project says Roxas newsinfo inquirer net Archived from the original on April 1 2019 Retrieved February 16 2019 a b Basa Mick August 21 2014 Northrail project up for NEDA ICC approval soon Rappler Archived from the original on February 18 2019 Retrieved February 17 2019 a b DOTC eyes elevated railway from Malolos to Los Banos ABS CBN News July 22 2013 Archived from the original on August 22 2015 Retrieved April 23 2019 Govt eyes elevated rail project in Luzon Manila Standard Today Archived from the original on January 2 2014 Retrieved January 1 2014 Main Points of the Roadmap PDF Report Japan International Cooperation Agency September 2014 Archived from the original PDF on October 11 2014 a b New north south commuter railway set www officialgazette gov ph December 1 2015 Archived from the original on July 2 2021 Retrieved December 24 2020 Bidders line up for Philippines North South line International Railway Journal August 20 2015 Archived from the original on May 17 2021 Retrieved May 17 2021 a b P287 B North South Railway project eyed for 2020 operation PPP Center February 18 2015 Archived from the original on July 2 2021 Retrieved December 24 2020 PNR lines up new railway project for PPP Philstar com Retrieved November 3 2021 NEDA Board approves six transport infra projects www officialgazette gov ph February 16 2015 Archived from the original on July 2 2021 Retrieved December 25 2020 Camus Miguel January 29 2016 PH Japan seal P97 B commuter rail project Philippine Daily Inquirer Archived from the original on December 24 2020 Retrieved December 24 2020 Diangson Louie January 29 2016 PH Japan signs deal for the Php97 billion commuter railway www yugatech com Archived from the original on December 24 2020 Retrieved December 24 2020 Dela Paz Chrisee November 28 2015 PH Japan sign 1 99B loan for North South commuter railway rappler com Archived from the original on November 25 2018 Retrieved December 25 2020 Tugade PNR Clark Calamba trains to arrive in December 2021 Philippine Information Agency Archived from the original on June 26 2021 Retrieved June 26 2021 Philippines adopts standard gauge for new lines International Railway Journal August 9 2016 Archived from the original on April 23 2021 Retrieved May 17 2021 Dela Paz Chrisee November 17 2016 Duterte gov t calls off auction for South Line of North South Railway Rappler Archived from the original on November 21 2016 Retrieved May 25 2022 Dela Paz Chrisee June 25 2017 17 stations of Manila Clark railway announced Rappler Archived from the original on March 22 2019 Retrieved February 17 2019 Padin Mary Grace January 23 2019 Gov t secures P98 7 billion JICA loans for railway flood control The Philippine Star Archived from the original on November 26 2020 Retrieved February 3 2022 Parrocha Azer July 11 2019 PRRD orders DOTr to hasten completion of Malolos Clark Railway Philippine News Agency Archived from the original on July 11 2019 Retrieved February 3 2022 a b NSCR Extension Project starts construction The Manila Times September 27 2021 Retrieved May 24 2022 de Vera Ben O June 9 2022 ADB OKs 4 3B loan for Manila Calamba railway project Philippine Daily Inquirer Retrieved June 9 2022 Pinlac Beatrice June 17 2022 PH ADB ink 4 3B loan agreement for South Commuter Railway project Philippine Daily Inquirer Retrieved June 17 2022 Cordero Ted February 9 2023 PH Japan ink 400 B loan deals for North South railway extension projects GMA Integrated News Retrieved February 22 2023 DMCI Japanese partner bag P54 B contract for North South Commuter Railway project GMA News Online May 21 2019 Archived from the original on May 28 2019 Retrieved May 28 2019 Viaduct contract awarded for Philippines NSCR International Railway Journal December 22 2020 Archived from the original on May 17 2021 Retrieved May 17 2021 Overview Sumitomo Mitsui Construction Retrieved May 25 2022 NORTH SOUTH COMMUTER RAILWAY PROJECT MALOLOS TUTUBAN N1CP04 ELECTRICAL AND MECHANICAL SYSTEMS AND TRACKWORKS Department of Transportation Philippines August 25 2021 Retrieved November 5 2021 Procurement Service Philippine Government Electronic Procurement System October 13 2022 General Bid Bulletin No 4 Responses to Clarifications PDF Retrieved February 21 2023 Manuel Pilar September 21 2020 Megawide 2 Korean firms secure construction for part of Malolos Clark Railway CNN Philippines Archived from the original on October 18 2020 Retrieved May 5 2021 Loyola James A September 21 2020 Megawide Korean partners win P28 B railway project Manila Bulletin Archived from the original on July 2 2021 Retrieved May 5 2021 Contracts Worth 1 7 Billion Awarded for ADB Funded Malolos Clark Railway Project Asian Development Bank October 8 2020 Archived from the original on January 3 2022 Retrieved January 3 2022 Philippines awards North South Commuter Railway contracts International Railway Journal August 4 2020 Archived from the original on May 17 2021 Retrieved May 17 2021 a b Rosales Elijah Felice February 21 2023 DOTr awards contract for P40 billion NSCR line Philstar Retrieved February 21 2023 Department of Transportation February 17 2023 Notice of Contract Award Malolos to Clark Railway Project Blumentritt Extension Package CP S 01 PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation February 17 2023 Notice of Contract Award South Commuter Railway Project Package CP S 02 PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation February 20 2023 Notice of Contract Award South Commuter Railway Project Package CP S 03B PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation September 23 2022 Notice of Contract Award South Commuter Railway Project Package CP S 04 PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation September 23 2022 Notice of Contract Award South Commuter Railway Project Package CP S 05 PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation September 23 2022 Notice of Contract Award South Commuter Railway Project Package CP S 06 PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation September 23 2022 Notice of Contract Award South Commuter Railway Project Package CP S 07 PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Department of Transportation January 14 2022 Notice of Award of Contract Package NS 02 Rolling Stock Commuter Trainsets PDF Procurement Service Philippine Government Electronic Procurement System Retrieved February 21 2023 Balinbin Arjay March 9 2022 Japan s J Trec Sumitomo JV bags new trainset contract for gov t railways BusinessWorld Retrieved February 21 2023 Patena Aerol John January 6 2018 Preps begin for Phase 1 of PNR Clark railway project Philippine News Agency Archived from the original on June 26 2021 Retrieved June 26 2021 Dela Paz Chrisee 17 stations of Manila Clark Railway revealed Rappler Archived from the original on March 22 2019 Retrieved June 25 2017 Aning Jerome June 25 2017 DOTr leads marking of Manila Clark railway s 5 future stations Philippine Daily Inquirer Archived from the original on June 12 2018 Retrieved June 25 2017 DOTr TUGADE PNR CLARK CALAMBA TRAINS TO ARRIVE IN DECEMBER 2021 dotr gov ph Archived from the original on June 2 2021 Retrieved July 13 2021 a b Dela Paz Chrissie September 13 2017 NEDA Board approves Manila subway longest railway Rappler Archived from the original on September 14 2017 Retrieved September 15 2017 Leyco Chino S September 13 2017 NEDA Board approves big infra projects Manila Bulletin Archived from the original on September 14 2017 Retrieved September 15 2017 Completion of PNR Clark Phase 1 2 on track Philippine News Agency March 8 2021 Archived from the original on March 8 2021 Retrieved March 9 2021 Gines Ben Jr December 2 2021 PNR phase 1 on track for 2022 completion The Manila Times Archived from the original on December 2 2021 Retrieved January 3 2022 LOOK PNR Clark phase 2 train will run from Malolos to Clark in 30 minutes Coconuts Coconuts Manila September 21 2021 Archived from the original on September 23 2021 Retrieved January 3 2022 Balinbin Arjay L December 1 2021 Construction progress for PNR Clark Phase 1 Balagtas Bocaue stations exceeds 23 BusinessWorld Online Archived from the original on December 1 2021 Retrieved January 3 2022 a b Civil works start for Metro Manila Bulacan railway segment www pna gov ph Archived from the original on June 3 2020 Retrieved January 22 2020 Project Details BUILD build gov ph Archived from the original on August 14 2020 Retrieved April 27 2019 Project Details Build Build gov ph June 1 2018 Retrieved January 9 2020 permanent dead link PH Japan sign P78 b loan for Luzon railway network Manila Standard Archived from the original on November 25 2018 Retrieved February 17 2019 a b c d e f g Department of Transportation The Republic of the Philippines October 2018 FEASIBILITY STUDY ON THE NORTH SOUTH RAILWAY PROJECT SOUTH LINE COMMUTER NORTH SOUTH COMMUTER RAILWAY EXTENSION PROJECT IN THE REPUBLIC OF THE PHILIPPINES PDF jica go jp Archived PDF from the original on April 11 2021 Retrieved April 26 2019 Railways Sector www dotr gov ph Department of Transportation Philippines Archived from the original on May 26 2021 Retrieved June 10 2021 Chapter 6 PDF Route Plan and Railways System Study on railway strategy for Clark metro Manila for the greater capital region in the Republic of the Philippines final report Report Vol II Japan International Cooperation Agency June 2013 Retrieved September 11 2021 Philippines South Commuter Railway Project Asian Development Bank May 2022 Retrieved October 20 2022 Invitation for Bids PB21 036 5 PDF South Commuter Railway Project for Package Number CP S 03a Building and Civil Engineering Works for approximately 7 9 kms of at Grade and Viaduct Railway Track Structure including Elevated Station at Buendia and at Grade Stations at EDSA and Senate Report March 22 2021 Retrieved October 20 2022 a b Roadmap for Transport Infrastructure Development for Metro Manila and its Surrounding Areas Region III and Region IV A PDF Japan International Cooperation Agency March 30 2014 Archived PDF from the original on June 27 2020 Retrieved May 7 2020 Dela Paz Chrisee September 13 2017 NEDA Board approves Metro Manila Subway Rappler Archived from the original on September 14 2017 Retrieved September 14 2017 Villanueva Joann January 22 2019 PNR asks for feasibility of Cabanatuan Makati line Philippine News Agency Archived from the original on November 5 2020 Retrieved August 2 2020 National Economic and Development Authority August 2019 FOLLOW UP SURVEY ON ROADMAP FOR TRANSPORT INFRASTRUCTURE DEVELOPMENT FOR GREATER CAPITAL REGION GCR PDF Report Vol JR 19 003 Japan International Cooperation Agency INQUIRER net PNR to preserve old train stations in Bulacan newsinfo inquirer net Archived from the original on July 27 2020 Retrieved April 18 2020 Patena Aerol John January 18 2018 Taguig integrated terminal to ease traffic on EDSA Philippine News Agency Archived from the original on January 3 2022 Retrieved January 3 2022 a b c BIDDING DOCUMENTS FOR PROCUREMENT OF PACKAGE CP NS 03 ROLLING STOCK LIMITED EXPRESS TRAINSETS PDF Report Vol 2 of 3 Philippine National Railways February 2021 Archived PDF from the original on August 21 2021 Retrieved August 19 2021 Balinbin Arjay L July 21 2021 North South rail subway trains to start arriving in December BusinessWorld Archived from the original on July 21 2021 Retrieved July 23 2021 マニラ南北線EM10011Mとマニラ南北線EM10011Lが株式会社総合車両製作所 J TREC から陸送 令和3年 西暦2021年 10月18日月曜日 Manila North South Line EM10011M and Manila North South Line EM10011L being shipped by land from the Japan Transport Engineering Company J TREC Monday October 18 2021 YouTube in Japanese October 18 2021 Retrieved October 19 2021 a b First 8 car trainset for PNR Clark Phase 1 arrives in PH ABS CBN News November 21 2021 Archived from the original on November 21 2021 Retrieved November 22 2021 Notice of Award of Contract Package NS 02 Rolling Stock Commuter Trainsets PDF Department of Transportation Philippines January 14 2022 Retrieved January 22 2022 Abadilla Emmie V March 18 2022 PH s 1st electric multiple train set unveiled Manila Bulletin Retrieved March 20 2022 a b c Order Received to Supply 304 for the Philippines North South Commuter Railway Extension Project Sumitomo Corporation March 18 2022 Archived from the original on March 20 2022 Retrieved March 20 2022 1 local 5 foreign firms bid for P50 8 B PNR Clark Phase 2 GMA News October 16 2019 Archived from the original on February 15 2020 Retrieved February 15 2020 Environmental Impact Assessment PDF Proposed Multitranche Financing Facility Republic of the Philippines South Commuter Railway Project Report Department of Transportation Philippines and the Asian Development Bank July 1 2020 Archived PDF from the original on May 17 2021 Retrieved May 17 2021 Philippines Philippines to engage Japanese manufacturers for NSCR Express trainsets International Union of Railways May 10 2021 Archived from the original on May 17 2021 Retrieved May 17 2021 a b LIVE Bid Opening for the Contract Package NS 03 Limited Express Rolling Stock 16 9 720p Facebook Live Department of Transportation Philippines October 15 2021 Retrieved October 16 2021 PTS Technical Talks May 19 2022 16 9 1080p YouTube Philippine Tunneling Society May 19 2022 a b BIDDING DOCUMENTS FOR THE PROCUREMENT OF PACKAGE CP03 ROLLING STOCK Report Vol 2 of 3 Department of Transportation Philippines July 2018 Archived from the original on January 4 2022 Retrieved January 4 2022 Valdez Denise July 17 2019 DoTr Japan firms ink P12 B contract for train cars BusinessWorld Archived from the original on April 14 2021 Retrieved April 14 2021 a b c PART 2 Employer s Requirements PDF The Malolos Clark Railway Project and the North South Railway Project South Line Commuter PACKAGE CP NS 01 E amp M SYSTEMS AND TRACK WORKS Department of Transportation Philippines March 2021 Archived PDF from the original on March 13 2022 Retrieved March 13 2022 Retrieved from https en wikipedia org w index php title North South Commuter Railway amp oldid 1150613586, wikipedia, wiki, book, books, library,