Port Miami Tunnel

The Port of Miami Tunnel (also State Road 887) is a 4,200-foot (1,300 m)[3] bored, undersea tunnel in Miami, Florida. It consists of two parallel tunnels (one in each direction) that travel beneath Biscayne Bay, connecting the MacArthur Causeway on Watson Island with PortMiami on Dodge Island. It was built in a public–private partnership between three government entities—the Florida Department of Transportation, Miami-Dade County, and the City of Miami—and the private entity MAT Concessionaire LLC, which was in charge of designing, building, and financing the project and holds a 30-year concession to operate the tunnel.[4][5][6]

Port of Miami Tunnel
Watson Island entrance
Overview
LocationMiami, Florida
Route SR 887
StartWatson Island
EndDodge Island
Operation
Work begunMay 24, 2010 (2010-05-24)
ConstructedBouygues Construction
OpenedAugust 3, 2014 (2014-08-03)
OwnerFDOT
OperatorMAT Concessionaire, LLC
TrafficAutomotive
TollNone
Vehicles per day7000 (August 2014)[1]
Technical
Length4,200 feet (1,300 m)
No. of lanes2 (per tunnel)
Operating speed35 miles per hour[2]
Highest elevationSea level
Lowest elevation−120 feet (−37 m)[2]
Tunnel clearance15 feet (4.6 m)
Width43 feet (13 m) per tunnel
Grade5%[2]
www.portofmiamitunnel.com

State Road 887

SR 887 highlighted in black
Route information
Maintained by FDOT
Existed2014–present
Major junctions
South endPort Boulevard on Dodge Island
North end SR A1A (MacArthur Causeway) on Watson Island
Location
CountryUnited States
StateFlorida
Highway system

The project was approved after decades of planning and discussion in December 2007, but was temporarily cancelled a year later. Construction began in May 2010. The tunnel boring machine began work in November 2011 and completed the second tunnel in May 2013.[7] The tunnel was opened to traffic on August 3, 2014.[8] In the first month after opening, the tunnel averaged 7,000 vehicles per day, and nearly 16,000 vehicles now[when?] travel to the port on a typical weekday.[1]

History

The idea of a tunnel connecting the Port of Miami to Watson Island was first conceived in the 1980s as a way to reduce traffic congestion in downtown Miami. Prior to the tunnel's opening, the only route for PortMiami traffic was a two-lane drawbridge that emptied out into the streets of downtown Miami. The heavy traffic was considered detrimental to the economic growth of downtown, and a planned project to expand the port's capacity threatened to increase the volume of trucks coming through. These problems were alleviated, but not solved, by the construction of a six-lane elevated bridge, which still stands, in the early 1990s.[9] The issues would be remedied by the construction of the tunnel, allowing traffic to move between PortMiami and the MacArthur Causeway (which connects to Interstate 95 via I-395) without traveling through downtown.

Federal funding for a preliminary study into the tunnel proposal was included in the controversial 1987 highway bill which was vetoed by President Ronald Reagan, who complained that the bill was a "pork-barrel" project.[10][11] Although the veto was overridden, the tunnel proposal fell by the wayside. It was not until 2006 that the tender for the tunnel project was ready to be launched, and in December 2007 the project was approved by the City Commission.[12] However, the economic crisis resulted in a cancellation of the project in December 2008 by one of the sponsors, Babcock & Brown, and the State of Florida.[13] Despite this, in April 2009, following intense lobbying by Miami-Dade Mayor Carlos Alvarez,[14] to avoid a new tender that would delay even further the start of construction, the project was reinstated. Port director Bill Johnson has also played a key role in supporting the Port of Miami infrastructure projects,[15] as well as developing a free-trade pact with Colombia. Altogether, the port infrastructure projects had an estimated cost of around two billion dollars.[16]

Prior to 2008, the project had been estimated at a total cost of $3.1 billion USD,[17] however the revised project has an estimated cost of US$1 billion (The difference in estimates partially due to differences in previous tunnel designs).[18] Financial closing on the project was reached in October 2009.[19] Miami-Dade County was reported to have contributed $402 million, the city of Miami $50 million, and the state $650 million to build, operate and maintain it.[14] Those contributions are spread during construction and operation of the tunnel project. During construction, 90% of the funds are provided by the private sector. Of the estimated $1 billion total project cost, $607 million would go to design and construction, $195.1 million to financing, $59.6 million to insurance and maintenance during construction, $41.2 million to reserves, and $209.8 million for state development cost.[20]

Overview

 
An overview of the Port Miami Tunnel project. In this map, the areas marked in orange signify the route of the tunnel, while areas marked in blue signify associated ramps and infrastructure.

The Port of Miami Tunnel project involved the design and widening of the MacArthur Causeway by one lane in each direction leading up to the tunnel entrance, the relocation of Parrot Jungle Trail, and the reconstruction of roadways on Dodge Island. The tunnel itself has two side by side tubes carrying traffic underneath the cruise ship channel of the Government Cut shipping lane. Jacobs Engineering Group was responsible for the design of the roadways, Langan Engineering & Environmental Services was the geotechnical engineer, and Bouygues was the prime contractor for the tunnel project itself. Chosen due to their key involvement in the construction of the Channel Tunnel, a major tunnel in Europe, the selection of Bouygues was also met with controversy and protested by the Cuban exile community in Miami, due to the company's involvement with locally opposed construction projects in Cuba.[13]

The project connects the east/west Interstate 395 (I-395)/State Road 836, which terminates into State Route A1A at the Miami city limit on the MacArthur Causeway, as well as Interstate 95, directly to PortMiami.[21] The port was previously only connected to the mainland by Port Boulevard, which is accessed by crossing U.S. Route 1 (Biscayne Boulevard) and traveling through downtown.[19] The project also includes roadway improvements to the connection between I-395 and State Road 836,[22] also known as the Dolphin Expressway, at Interstate 95. The tunnel will allow heavy trucks to bypass the congested Downtown Miami area, which is considered to be especially crucial with the large increase in trade traffic expected to be created by the Deep Dredge Project and the enlargement of the Panama Canal. Projected to eventually carry 26,000 vehicles a day under Government Cut through its twin two-lane tunnels,[23] the top of the tunnels lie over 60 feet (18.3 m) below the seabed. The project created nearly 1,000 jobs as of 2011, with 70% reported as local;[24][25][26] project executives promised that many of the construction jobs would go to local contractors.[27] Along with the related Deep Dredge and Panama Canal Expansion, over 30,000 jobs are expected to be created in the long run.[28]

Before completion of the tunnel, in 2009, nearly 16,000 vehicles travelled to and from PortMiami through downtown streets each weekday. Truck traffic made up 28% (or 4,480) of this number (Source: 2009 PB Americas Traffic Study). In 2010 it was estimated that around 19,000 vehicles traveled to the port daily but that only 16% were trucks.[9] Existing truck and bus routes restricted the port's ability to grow, driving up costs for port users and presenting safety hazards. They were also thought to congest and limit redevelopment of the northern portion of Miami's Central Business District.[26]

The Port of Miami Tunnel includes providing a direct connection from the Port of Miami to highways via Watson Island to I-395 and, along with the deep dredge, keeping the Port of Miami, the county's second largest economic generator (after Miami International Airport), supporting over 11,000 jobs directly with an average salary of $50,000,[29] a competitive player in international trade.[15] The Port of Miami provides 176,000 jobs, $6.4 billion in wages and $17 billion in economic output. (Source: 2007 Port of Miami Economic Impact Study).

Public-private partnership (PPP)

 

The tunnel project is a public-private partnership (PPP or P3), designed to transfer the responsibility to design, build, finance, operate, and maintain the project to the private sector. Ten banks, BNP Paribas, Banco Bilbao Vizcaya Argentaria, RBS Citizens, N.A., Banco Santander, Bayerische Hypo, Calyon, Dexia, ING Capital, Societe Generale, and WestLB, will provide the senior debt financing for the project,[19] which totals $341.5 million.[30] The project attracted three bidding consortia. Under the concession agreement, FDOT will make milestone payments to the concessionaire (Miami Access Tunnel) during the construction period, upon the achievement of contractual milestones. 90% of Miami Access Tunnel's equity is provided by Meridiam Infrastructure Miami LLC (Luxembourg based Meridiam SARL); the remaining 10% by France's Bouygues Travaux Publics SA, operating as Dragages Concession Florida Inc.[19] The Port of Miami Tunnel Project was one of the first P3s in Florida, and the first availability-based P3 deal in the US,[31] after the Interstate 595 (I-595) renovation project in Broward County.[32]

When construction is completed, FDOT will make availability payments to the concessionaire. These payments will be contingent upon actual lane availability and service quality: if the tunnel is closed or the road is in bad condition, part or all of the payment for that period may be withheld.[30] The tunnel will be turned over to FDOT in first-class condition at the end of the contract in October 2044, thirty years after its completion.[20] Maintenance costs over this 30-year period are expected to total around $200 million.[33] Unlike many similar public-private partnerships, the tunnels will not have a toll.[19]

The originally scheduled June 2014 opening was delayed due to several mechanical problems, including leaky pipes, broken exhaust fans due to sudden vibrations, and failing bolts. The general contractor Bouygues was fined $115,000 for every day that the tunnel was not open, losing millions of dollars. The tunnel was officially opened to commercial and private traffic on August 3, 2014.

Criticism

 
Center of the tunnel traveling from MacArthur Causeway to PortMiami
 
Traveling uphill towards the PortMiami portal from MacArthur Causeway

According to the Miami Herald the financing structure of the plan is notable for the amount of financial risk taken by the builders in return for the long term concession on the tunnel.[13] Opposition to the project states that it is a waste of taxpayer money, and may become Miami's Big Dig, the nickname of a tunnel megaproject in Boston, which was a $4 billion project that ended up costing $22 billion in cost overruns. Many believe that the Port of Miami Tunnel Project will be likely to have similar cost overruns,[34] even though the Secretary of the Florida Department of Transportation (FDOT) promised that the project would finish on time and without overruns.[35] They also state that truck traffic is not a problem in Downtown, and that since 1991 car and truck traffic had reduced significantly.[36]

Downtown business owners have referred to it as the "tunnel to no where," stating that no one will use it. In 1992, 32,000 vehicles entered the port daily, a number which later dropped to nearly half that, but had once again risen to around 19,000 by 2011.[9] It has been regarded as a boondoggle project by those who oppose it, stating that the city can't afford it. In fact, the city did have difficulty providing its $50 million portion of the funding for the project.[37][38] Some believe it may create traffic problems on the MacArthur Causeway; environmentalists worry about the potentially negative impact the construction could have on the Biscayne Bay.[39] An ominous foreshadowing of cost overruns, Miami Access Tunnel requested money from a $150 million reserve fund in July 2011 for the unexpected need to grout the limestone beneath the surface so that the tunnel boring machine cuts more smoothly. This request alarmed new Miami-Dade Mayor Carlos A. Giménez when it was brought up at his first commissioners meeting as mayor on July 7.[40]

The contractor stated that they will continue without the additional requested money if FDOT denies it, but it may end up as a court case as the contractor seeks it later.[41] On July 19, the FDOT denied the request for more money to the contractor, stating that the geological issue cited was not as extensive as MAT claimed.[42]

Benefits/related projects

Although there is great speculation that the Port of Miami Tunnel project is both unnecessary and a waste of taxpayer dollars, it is expected to have positive benefits in the long run which coincide with several other related projects predicted to increase its traffic, many, such as the Port of Miami Deep Dredge Project and Panama Canal expansion, slated to be finished in 2015 and 2016, respectively. The port has gone through several expensive projects throughout its history, and many have been seen as beneficial to the economic growth of the Greater Miami area in the long run, such as in the 1950s when the deteriorating Port of Miami, then located in the mainland in downtown, was moved to its current home, the man-made Dodge Island.[43] The current port director of the Port of Miami Bill Johnson states that these new port infrastructure projects should be able to double the port's container capacity over the next decade.[44] Miami City Commissioner Marc Sarnoff stated that "This is the best public works project ever."[24] A strong trade industry is also considered to be a vital sign of a good and improving economy.[45]

Cruise traffic

 
Seven cruise ships docked at the Port of Miami

In addition to the expected increase in cargo traffic, the Port of Miami recently stated that October 2010 was its busiest October ever for cruise vacations. The port had a record 346,513 cruise passengers that October, up 29% from October 2009. This follows a record year in cruise traffic, with 4.15 million cruise passengers in the 12 months that ended in September.[46] This is partially due to the arrival of new cruise ships such as the Norwegian Epic, as well as the cruise line Costa Cruises.[47] Despite this, the Port of Miami has recently been losing cruise and cargo traffic to nearby Port Everglades in Fort Lauderdale. In 2010, Royal Caribbean Cruise Lines, which is headquartered in Miami, chose Port Everglades as home for its new cruise ships, Oasis of the Seas and Allure of the Seas,[48] currently the largest cruise ships in the world.

As for cargo traffic, truckers state that despite the longer miles, they can make more trips per day at Port Everglades. Also, they blame the port itself for this, not the Downtown traffic.[36] They state that at Port Everglades, they can make three to four runs a day, versus Port of Miami where "you're lucky if you get in two," states truck driver Alejandro Arrieta, due to waiting time at the port, which is often several hours.[9] Port Everglades also has major redevelopment plans underway that includes its own deep dredging to a 50-foot (15 m) depth;[49] they also claim to have surpassed the Port of Miami, which has long been known as the "Cruise Capital of the World" as well as the "Cargo Gateway to the Americas," in both cruise traffic and cargo tonnage handled.

Railroad access

 
The rail line being redone in November 2011

The Port of Miami was also recently awarded a federal grant as part of the Transportation Investment Generating Economic Recovery (TIGER) program to restore a connection between the Florida East Coast Railway's yard in Hialeah and the Port of Miami, directly connecting the port to rail networks across the United States,[50] as well as re-establish the port's on-dock rail capability (loading and unloading directly between ships and trains).[51] The railroad bridge connecting the Port of Miami to the mainland was damaged by Hurricane Wilma in 2005, at which time service was suspended, and the bridge remained closed for well over a decade.[52] Rail service to the port was restored by 2014.[53] The rail project is part of another element of increasing PortMiami's capacity; an inland intermodal center to be built near the airport known as Flagler Logistics Hub, which was planned to be built on 300 acres of land in Hialeah.[54]

Opposition to the railroad line returning to service included that it would be as much of a problem to downtown traffic as the container trucks and that the noise would be a disturbance to nearby residents. As with before, however, trains are occasional and reserved for specialty loads, such as oversized loads and hazardous materials, which will be banned from the tunnel.[citation needed] It was also stated that the trains, which will be able to go up to 30 mph on the newly renovated line versus the old limit of 5 mph,[55] will be able to cross Biscayne Boulevard in 90 seconds.[56] The current plan is for the line to be strictly for intermodal services, with the project including a rail yard and station at the port, however, in the future a passenger station may be added.[57]

Downtown congestion

 
Container trucks leaving the port for Interstate 95 through downtown

Another major benefit of the tunnel will be the redirecting of the large number of vehicles (nearly 16,000 daily; 2009 estimate),[58] many of them container trucks and cruise buses, that cross Biscayne Boulevard (US 1) at NW 5th Street (Port Boulevard), using level streets, such as Northeast 1st Avenue,[24] which for years were the only way to access the port.[59] Along with the capacity of the port, the amount of truck traffic could double after the completion of the numerous port projects.[44] Additionally, the Port Boulevard entrance to the port is closed at night, concentrating all truck traffic during the day. This traffic creates congestion and presents a danger to pedestrians and bicyclists. Traffic is also considered to be a harm to Miami's northern central business district, reducing its ability to grow, including Miami's new Arts & Entertainment District, valued at over $12 billion.[26]

The developers for a once planned project for the north side of downtown, known as Miami City Square, stated that the heavy truck traffic and congestion in that area was a "grave concern."[60] The Omni Community Redevelopment Agency used a $50 million loan from Wachovia to donate towards financing the tunnel construction.[61] Resorts World Miami by Genting Group and Miami World Center are two proposed major development planned for the area where congestion is a concern.[62]

Additionally, the population of Downtown Miami nearly doubled from 2000 to 2010, and is expected to increase by several thousand more in the current decade, largely due to many new high rise condo developments in the downtown area adding thousands of housing units which will benefit from having the tunnel.[18] Although traffic and port activity has declined since the early 1990s, losing some of it to the nearby Port Everglades, which overtook Port of Miami in 2007 as Florida's largest cargo port,[9] the port is likely to see a large shift in the other direction after it becomes one of few deep water ports in the United States able to handle the New Panamax ships by 2016. Within the first month of opening, it was reported that congestion in the downtown area had eased.[63]

It was estimated that 46% to 80% of the passenger vehicles, many of which are shuttle buses and taxis and make up nearly three quarters of the total port traffic will use the tunnel after it was completed.[58]

Deep Dredge/Panama Canal expansion

 
Container trucks from the Port of Miami traveling through downtown

The timing of the tunnel's construction and opening coincides with PortMiami Deep Dredge Project that will see the port dredged deeper to accommodate larger ships expected following the completion of the Panama Canal expansion, now expected to be completed in 2016 (previously 2014).[64] This will allow much larger ships, known as New Panamax, which will have a capacity of more than double that of Panamax ships to traverse the canal. This is predicted to cause a major increase in the Port of Miami's cargo traffic, which would overwhelm the intersection of Port Boulevard and Biscayne Boulevard without the tunnel. In 2009, 870,000 trucks moved cargo in and out of the port; and port officials estimate that that number will increase to around 1.4 million when larger ships start arriving.[65] In 2010, about 800,000 TEU's were moved through the port, and port director Bill Johnson said that with the right marketing to major shippers, that number should double by 2020.[66] Currently, the largest cargo ships that dock at the port have a capacity of around 4,200 TEU's (Twenty-foot Equivalent Units). After the canal expansion and port dredging, ships as large as 7,500 to 8,500 TEU's will be able to dock there.[65]

Construction

 
Preparing for construction on Watson Island (September 2010)
 
Construction on Watson Island (March 2011)

Work on the Port of Miami Tunnel project began on Watson Island and Dodge Island, including work on the MacArthur Causeway, in May 2010.[67] Groundbreaking on the construction project was unannounced and considered secret, as the groundbreaking was scheduled for June 2010,[6] but actually took place on May 24, 2010,[68] without ceremony.

The tunnel boring machine was built in Germany and had to be re-assembled in Florida after arriving in crates on the 168 metres (551 ft)[69] cargo ship Combi Dock 1[70] on Thursday, June 23, 2011,[71][72] and being assembled in the median of the causeway[73] where the construction is taking place. Both directions of the MacArthur Causeway have remained open during the assembly of the machine except for nighttime lane closures and delays on the westbound side.[74]

The machine, which weighs more than 2,500 tons, was assembled in a 65-foot (20 m) deep pit known as the launching pad located in between two concrete walls in the median of the causeway, which only left a 42-foot (13 m) cutter visible from the road.[75] According to NBC Miami, as of June 2011, 899 jobs had been created by the project, with over 70% being from the 305 area code (Miami-Dade County).[24] The construction is projected to take 47 months, with the tunnel being finished in 2014.[13] The French firm Bouygues Construction has been put in charge of operating the tunnel boring machine, which was nicknamed "Harriet" in July 2011 after a naming competition was sponsored by MAT and the FDOT, and carried out by the Girl Scout Council of Tropical Florida.[76]

The tunnel boring machine was longer than a football field at 540 feet (160 m) long,[33] and over 40 feet (12 m) in diameter. It was used to bore two side by side 43 feet (13 m) diameter tunnels, one for each direction, each 3,900 feet (1.1 km) long.[77] The tunnel boring machine itself cost $45 million and was custom built for the Port of Miami Tunnel Project by the German firm Herrenknecht.[25] No explosives are said to be used on the construction of the tunnel.[22] Drilling of the tunnel itself commenced in mid-November 2011, with the drilling machine beginning work on the Watson Island tunnel entrance.[78]

The first tunnel connecting Watson Island and the Port of Miami was completed in August 2012,[79] and the second tunnel was completed on May 9, 2013, as "Harriet" emerged back on Watson Island, where digging had commenced in 2011.[80] The roadway construction should finish for an opening on May 15, 2014.[33] The MacArthur Causeway, which currently has three traffic lanes in each direction and a sidewalk on the eastbound side, will be widened to four 12-foot (3.7 m) wide traffic lanes with a ten-foot inner and outer shoulder, as well as a six-foot sidewalk.[81]

The tunnel was officially opened to commercial and private traffic on August 3, 2014, after minor mechanical delays pushed back the originally scheduled June 2014 opening date. The general contractor Bouygues was fined $115,000 for every day that the tunnel was not open, losing millions of dollars.

Controversies

In March 2011, one of the sub contractors of Bouygues fell under criticism for the dumping of tunnel fill on sensitive wetlands on Virginia Key. They were supposed to be dumping the fill on Virginia Key on the degraded northwest side, but were found dumping it 80 to 100 yards (73.1 to 94.5 m) from the designated spot,[82] where they damaged wetlands and killed about 40 mangrove trees with a piece of equipment that got stuck.[83] The intention was that they would be allowed to put 55,000 cubic yards (42,050.5 m3) of fill there provided that they use it to build a berm to block the view of Virginia Key's sewage water treatment plant.[84] The fill that was dumped on Virginia Key was mainly rock and soil from road construction and site preparation on Watson Island and not from tunnel boring, which environmentalists object being put on Virginia Key as it may not be as clean.[75] The north point of Virginia Key is one of the last remaining undeveloped areas near the Miami downtown area and has been recently restored as it was previously used as a dumping site for the infill from the Rickenbacker Causeway, Miami Marine Stadium, and Norris Cut.[85]

One other potential infill site that was briefly suggested is an inlet located between Bicentennial Park and the American Airlines Arena on the mainland in downtown, where Miami-Dade County was conducting a study on the effects it would have.[86] This proposal was quickly retracted after public outcry due to the fact that the currently closed off waterfront lot, known as "Parcel B," is slated to soon be a long anticipated public park.[87] There has also been minor controversy over speculation that a yacht allegedly owned by Bouygues may have been bought with public money. A Bouygues spokesperson denied this claim.[88] The owner of the seaplane base on Watson Island has accused the tunnel builders of trespassing for storing equipment on his property as well as for using the road that passes through his property. FDOT and city officials said the use of the land is permitted.[89]

See also

References

  1. ^ a b Lincoff, Nina (September 24, 2014). "Port tunnel traffic grows". Miami Today. Retrieved October 16, 2014.
  2. ^ a b c Chardy, Alfonso (May 17, 2014). "Decades after conception, Miami has a port tunnel". Miami Herald. Retrieved June 6, 2014.
  3. ^ "Port of Miami Tunnel". fdotmiamidade.com. Florida Department of Transportation. Retrieved August 24, 2014.
  4. ^ "Public Private Partnership". portofmiamitunnel.com. Florida Department of Transportation. Retrieved August 24, 2014.
  5. ^ "General FAQ". portofmiamitunnel.com. Florida Department of Transportation. Retrieved August 24, 2014.
  6. ^ a b Alfonso Chardy (April 17, 2010). "Port of Miami tunnel project on track for June start". Miami Herald. Retrieved March 30, 2011.[dead link]
  7. ^ "Project History" (PDF). Florida Department of Transportation. Retrieved March 30, 2011.
  8. ^ Newland, Maggie (August 2, 2014). "Tunnel To PortMiami Opening Sunday Morning". WFOR-TV. Retrieved August 3, 2014.
  9. ^ a b c d e Erik Maza (June 2, 2010). "Port Of Miami Tunnel Project Could Be South Florida's Big Dig". Miami New Times. Retrieved April 2, 2011.
  10. ^ Pat Burson, Larry Lipman (April 1, 1987). "Fate of Miami tunnel hangs on today's Senate vote". The Palm Beach Post. Retrieved June 29, 2011.[dead link]
  11. ^ Davis, Jeff. "30 Years Ago This Week: Reagan’s 1987 Highway Bill Veto", Eno Transportation Weekly, Eno Center for Transportation, March 27, 2017.
  12. ^ Julia Neyman and Oscar Pedro Musibay (December 13, 2007). "Miami OKs Marlins' stadium, port tunnel". South Florida Business Journal. Retrieved July 12, 2011.
  13. ^ a b c d Larry Lebowitz (January 15, 2008). "Planned Miami port tunnel: Can we dig it?". Miami Herald. Retrieved January 15, 2008.[dead link]
  14. ^ a b WPLG-TV (April 16, 2009). . Archived from the original on September 26, 2011. Retrieved March 30, 2011.
  15. ^ a b Miami Dade County (July 13, 2010). . MiamiDade.gov. Archived from the original on September 5, 2010. Retrieved April 3, 2011.
  16. ^ Jose Perez Jones (March 20, 2011). "Miami needs Colombia free-trade pact". Miami Herald. Archived from the original on April 8, 2011. Retrieved April 3, 2011.
  17. ^ "Port of Miami tunnel". Critical Miami. 2005. Retrieved March 30, 2011.
  18. ^ a b "Florida DOT Mulls Bids on $1-Billion Miami Tunnel Job". Engineering News-Record. 2007. Retrieved April 3, 2011.
  19. ^ a b c d e Shelly Sigo (October 19, 2009). "Mimai Tunnel Reaches Closure". The Bond Buyer. Retrieved April 5, 2011.
  20. ^ a b . Federal Highway Administration. 2010. Archived from the original on January 17, 2011. Retrieved April 3, 2011.
  21. ^ "Port of Miami Cargo". Edward Redlich. October 14, 2010. Retrieved April 6, 2011.
  22. ^ a b Hank Tester (April 2, 2010). . NBC Miami. Archived from the original on March 13, 2012. Retrieved April 1, 2011.
  23. ^ "Video: Animation showing what the tunnel would look like". Miami Herald. January 15, 2008. Retrieved January 15, 2008.
  24. ^ a b c d Hank Tester (June 20, 2011). "Port of Miami Tunnel Dig to Get Into High Gear". NBC Miami. Retrieved June 22, 2011.
  25. ^ a b Risa Polansky (July 8, 2010). "Port of Miami tunnel project is indeed a big bore". Miami Today News. Retrieved March 30, 2011.
  26. ^ a b c Alyce Robertson (May 25, 2010). "Miami can't afford to have Port of Miami tunnel delayed". Miami Herald. Retrieved March 30, 2011.[dead link]
  27. ^ Hank Tester (September 1, 2010). "Port of Miami Tunnel Digging Up Local Jobs". NBC Miami. Retrieved April 3, 2011.
  28. ^ . TransportationNation. March 17, 2011. Archived from the original on July 27, 2011. Retrieved April 9, 2011.
  29. ^ Miami Herald Editorial (July 14, 2011). . Miami Herald. Archived from the original on August 11, 2011. Retrieved July 16, 2011.
  30. ^ a b Chrissy Mancini Nichols (March 21, 2011). "PPP Profiles:Port of Miami Tunnel". Metropolitan Planning Council. Retrieved March 31, 2011.
  31. ^ "Miami Tunnel PPP-full deal analysis". Project Finance. October 23, 2009. Retrieved April 5, 2011.
  32. ^ "Port of Miami Tunnel: Digging deep". Project Finance. November 19, 2009. Retrieved April 5, 2011.
  33. ^ a b c Ashley Hopkins (April 13, 2011). "Monster boring machine from Germany to dig Port of Miami tunnels". Miami Today. Retrieved April 13, 2011.
  34. ^ Felipe Azenha (June 2, 2010). . Transit Miami. Archived from the original on July 1, 2011. Retrieved April 2, 2011.
  35. ^ "Work on the Port of Miami tunnel gets under way". WSVN-TV. June 11, 2010. Retrieved April 4, 2011.
  36. ^ a b Erik Maza (June 3, 2010). "Port of Miami Tunnel is a waste of taxpayer money". Miami New Times. Retrieved March 31, 2011.
  37. ^ "Miami Port Tunnel threatened again as SEC orders Miami to turn over its financial books". South East Shipping News. December 12, 2009. Retrieved July 21, 2011.
  38. ^ "Letters to the Editor". Miami Herald. June 23, 2011. Retrieved July 21, 2011.[dead link]
  39. ^ Francisco Alvarado (May 24, 2011). "Five Reasons Carlos Gimenez Is The Wrong Man For The Job". Miami New Times. Retrieved May 24, 2011.
  40. ^ "New Mayor attends first commission meeting". WSVN-TV. July 7, 2011. Retrieved July 24, 2011.
  41. ^ Alfonso Chardy and Martha Brannigan (July 7, 2011). . Miami Herald. Archived from the original on August 10, 2011. Retrieved July 7, 2011.
  42. ^ Alfonso Chardy (July 19, 2011). "Florida officials deny reserve funds for Port of Miami tunnel builders". Miami Herald. Retrieved July 21, 2011.[dead link]
  43. ^ Andrew D. Melick (December 12, 2010). "How much should Seaport spend?". Miami Herald. Retrieved April 2, 2011.[dead link]
  44. ^ a b "USA: Port of Miami Deep Dredge Project to Double its Cargo Capacity". Dredging Today. November 26, 2010. Retrieved April 1, 2011.
  45. ^ Marilyn Bowden (May 26, 2011). "Outlook for small business financing is becoming brighter". Miami Today. Retrieved May 29, 2011.
  46. ^ Doreen Hemlock (December 21, 2010). . Sun Sentinel. Archived from the original on December 26, 2010. Retrieved March 31, 2011.
  47. ^ "Cruise traffic soars at Port of Miami". South Florida Business Journal. October 20, 2010. Retrieved March 31, 2011.
  48. ^ . Royal Caribbean International. 2009. Archived from the original on July 14, 2011. Retrieved April 2, 2011.
  49. ^ "Port Everglades: 300 million for Dredging in 2 billion dollar expansion plan (USA)". Dredging Today. March 3, 2010. Retrieved April 6, 2011.
  50. ^ Jeanette Sheppard, Hank Tester (July 15, 2011). "Port of Miami Rail Project Groundbreaking". NBC Miami. Retrieved July 16, 2011.
  51. ^ . Railway Age. July 13, 2011. Archived from the original on September 27, 2011. Retrieved July 16, 2011.
  52. ^ "Back to the Future: Port of Miami & Florida East Coast Railway?". MiamiDade.gov. 2010. Retrieved March 30, 2011.
  53. ^ Blake, Scott (May 7, 2014). "Seaport rail to expand again". MiamiToday News. Retrieved October 16, 2014.
  54. ^ Zachary S. Fagenson (March 10, 2011). "Million-square-foot Flagler logistics hub key piece of Miami's international trade puzzle". Miami Today News. Retrieved March 30, 2011.
  55. ^ "Port of Miami rail connection breaks ground". WSVN-TV. July 15, 2011. Retrieved July 16, 2011.
  56. ^ Ashley D. Torres (July 15, 2011). "FEC rail project starts – 800 jobs expected". South Florida Business Journal. Retrieved July 17, 2011.
  57. ^ "TIGER II Grant". Miami-Dade.gov. 2010. Retrieved April 11, 2011.
  58. ^ a b Zachary Fagenson (June 2, 2011). "Florida East Coast Rail line to haul 5% of cargo trucks from Port of Miami". Miami Today. Retrieved June 2, 2011.
  59. ^ Hank Tester (June 11, 2010). "FDT Deems Port Tunnel "Really Sexy"". NBC Miami. Retrieved April 1, 2011.
  60. ^ Yudislaidy Fernandez (July 24, 2008). "Walmart in downtown Miami? Company confirms discussions have taken place, but says no agreements have been made". Miami Today News. Retrieved April 7, 2011.
  61. ^ Jacquelyn Weiner (June 2, 2011). "Miami to ease financial pressures by refinancing some loans". Miami Today. Retrieved June 7, 2011.
  62. ^ Elaine Walker (July 31, 2011). "Genting Group is betting on Miami as future resort destination". Miami Herald. Retrieved August 1, 2011.[dead link]
  63. ^ Muiz, Andria C. (October 1, 2014). "Port Miami Tunnel marks first month of operation". Miami's Community Newspapers. Retrieved November 2, 2014.
  64. ^ Uncredited (November 26, 2010). "Port of Miami seeks funds for 'Deep Dredge' project". SandandGravel.com. Retrieved April 1, 2011.
  65. ^ a b Alfonso Chardy (August 21, 2010). "Port of Miami puts rail project on fast track". Miami Herald. Retrieved March 30, 2011.[dead link]
  66. ^ Zachary Fagenson (June 9, 2011). "Major logistics centers vital to leverage growth at Port of Miami, Miami International Airport". Miami Today. Retrieved June 8, 2011.
  67. ^ "Construction schedule". Florida Department of Transportation. 2010. Retrieved March 31, 2011.
  68. ^ Brian Hamacher (May 24, 2010). "Dig This: Port of Miami Tunnel Construction Begins". NBC Miami. Retrieved April 4, 2011.
  69. ^ "Combi Dock I (IMO: 9400473)". vesseltracker. Retrieved June 24, 2011.
  70. ^ Alfonso Chardy (June 23, 2011). "Machine to drill Port of Miami tunnel arrives". Miami Herald. Retrieved June 24, 2011.[dead link]
  71. ^ Lidia Dinkova, Alfonso Chardy (June 23, 2011). "Ship carrying tunnel boring machine to dock at Port of Miami". Miami Herald. Retrieved June 23, 2011.[dead link]
  72. ^ "Boring equipment brought for port tunnel construction". WSVN-TV. June 23, 2011. Retrieved June 23, 2011.
  73. ^ Alfonso Chardy (May 17, 2011). "Drivers hit the brakes for road construction in S. Fla". Miami Herald. Retrieved May 17, 2011.[dead link]
  74. ^ Lidia Dinkova (June 27, 2011). "Assembly of tunnel boring machine to cause MacArthur Causeway lane closures". Miami Herald. Retrieved June 27, 2011.[dead link]
  75. ^ a b Alfonso Chardy (June 20, 2011). . Miami Herald. Archived from the original on October 8, 2011. Retrieved June 22, 2011.
  76. ^ Alfonso Chardy, The Miami Herald (August 9, 2011). "Miami tunnel boring machine gets a name: Harriet". Sun Sentinel. Retrieved August 11, 2011.[permanent dead link]
  77. ^ Shani Wallis (2010). "Port of Miami Tunnel gets underway". TunnelTalk. Retrieved March 31, 2011.
  78. ^ Viglucci, Andre (November 14, 2011). "Port of Miami tunnel drilling starts". The Miami Herald. Miami, Florida. Retrieved November 29, 2011.
  79. ^ "Port of Miami Tunnel Halfway Done".
  80. ^ "PortMiami tunnel digging reaches end of the line".
  81. ^ POMT Public Affairs Program Office (June 2, 2010). (PDF). Florida Department of Transportation. Archived from the original (PDF) on September 29, 2011. Retrieved July 17, 2011.
  82. ^ Janie Campbell (March 12, 2011). "Rogue Contractor Dumps Tunnel Fill In Wetlands". NBC Miami. Retrieved March 30, 2011.
  83. ^ Miami Herald Editorial (June 25, 2011). "Don't make Virginia Key a casualty". Miami Herald. Retrieved June 25, 2011.[dead link]
  84. ^ Andres Viglucci (March 11, 2011). "Tunnel contractor makes wetland mess". Miami Herald. Retrieved March 30, 2011.[dead link]
  85. ^ "USA: Officials Propose Virginia Key Park's North Point for Dumping Site". Dredging Today. June 28, 2011. Retrieved June 29, 2011.
  86. ^ Jacquelyn Weiner (June 16, 2011). "Downtown Miami inlet a dredging dump site?". Miami Today News. Retrieved June 25, 2011.
  87. ^ Erik Bojnansky (August 4, 2011). "A Waterfront Park for All to Enjoy". Biscayne Times. Retrieved August 4, 2011.
  88. ^ Michael Miller (March 23, 2011). "Does Bouygues, Contractor On The $1 Billion Port Of Miami Tunnel, Have A $1 Million Yacht?". Miami New Times. Retrieved April 7, 2011.
  89. ^ Alfonso Chardy (July 31, 2011). "Tunnel builder accused of trespassing on seaplane base". Miami Herald. Retrieved August 1, 2011.[dead link]

External links

Route map:

KML is from Wikidata
  • Port of Miami Tunnel website
  • 2005 POM Tunnel animation video
  • Newer Tunnel animation video

port, miami, tunnel, port, miami, tunnel, also, state, road, foot, bored, undersea, tunnel, miami, florida, consists, parallel, tunnels, each, direction, that, travel, beneath, biscayne, connecting, macarthur, causeway, watson, island, with, portmiami, dodge, . The Port of Miami Tunnel also State Road 887 is a 4 200 foot 1 300 m 3 bored undersea tunnel in Miami Florida It consists of two parallel tunnels one in each direction that travel beneath Biscayne Bay connecting the MacArthur Causeway on Watson Island with PortMiami on Dodge Island It was built in a public private partnership between three government entities the Florida Department of Transportation Miami Dade County and the City of Miami and the private entity MAT Concessionaire LLC which was in charge of designing building and financing the project and holds a 30 year concession to operate the tunnel 4 5 6 Port of Miami TunnelWatson Island entranceOverviewLocationMiami FloridaRouteSR 887StartWatson IslandEndDodge IslandOperationWork begunMay 24 2010 2010 05 24 ConstructedBouygues ConstructionOpenedAugust 3 2014 2014 08 03 OwnerFDOTOperatorMAT Concessionaire LLCTrafficAutomotiveTollNoneVehicles per day7000 August 2014 1 TechnicalLength4 200 feet 1 300 m No of lanes2 per tunnel Operating speed35 miles per hour 2 Highest elevationSea levelLowest elevation 120 feet 37 m 2 Tunnel clearance15 feet 4 6 m Width43 feet 13 m per tunnelGrade5 2 www wbr portofmiamitunnel wbr comState Road 887SR 887 highlighted in blackRoute informationMaintained by FDOTExisted2014 presentMajor junctionsSouth endPort Boulevard on Dodge IslandNorth endSR A1A MacArthur Causeway on Watson IslandLocationCountryUnited StatesStateFloridaHighway systemFlorida State Highway SystemInterstate US State Former Pre 1945 Toll Scenic SR 886 SR 907The project was approved after decades of planning and discussion in December 2007 but was temporarily cancelled a year later Construction began in May 2010 The tunnel boring machine began work in November 2011 and completed the second tunnel in May 2013 7 The tunnel was opened to traffic on August 3 2014 8 In the first month after opening the tunnel averaged 7 000 vehicles per day and nearly 16 000 vehicles now when travel to the port on a typical weekday 1 Contents 1 History 2 Overview 2 1 Public private partnership PPP 2 2 Criticism 3 Benefits related projects 3 1 Cruise traffic 3 2 Railroad access 3 3 Downtown congestion 3 4 Deep Dredge Panama Canal expansion 4 Construction 4 1 Controversies 5 See also 6 References 7 External linksHistory EditThe idea of a tunnel connecting the Port of Miami to Watson Island was first conceived in the 1980s as a way to reduce traffic congestion in downtown Miami Prior to the tunnel s opening the only route for PortMiami traffic was a two lane drawbridge that emptied out into the streets of downtown Miami The heavy traffic was considered detrimental to the economic growth of downtown and a planned project to expand the port s capacity threatened to increase the volume of trucks coming through These problems were alleviated but not solved by the construction of a six lane elevated bridge which still stands in the early 1990s 9 The issues would be remedied by the construction of the tunnel allowing traffic to move between PortMiami and the MacArthur Causeway which connects to Interstate 95 via I 395 without traveling through downtown Federal funding for a preliminary study into the tunnel proposal was included in the controversial 1987 highway bill which was vetoed by President Ronald Reagan who complained that the bill was a pork barrel project 10 11 Although the veto was overridden the tunnel proposal fell by the wayside It was not until 2006 that the tender for the tunnel project was ready to be launched and in December 2007 the project was approved by the City Commission 12 However the economic crisis resulted in a cancellation of the project in December 2008 by one of the sponsors Babcock amp Brown and the State of Florida 13 Despite this in April 2009 following intense lobbying by Miami Dade Mayor Carlos Alvarez 14 to avoid a new tender that would delay even further the start of construction the project was reinstated Port director Bill Johnson has also played a key role in supporting the Port of Miami infrastructure projects 15 as well as developing a free trade pact with Colombia Altogether the port infrastructure projects had an estimated cost of around two billion dollars 16 Prior to 2008 the project had been estimated at a total cost of 3 1 billion USD 17 however the revised project has an estimated cost of US 1 billion The difference in estimates partially due to differences in previous tunnel designs 18 Financial closing on the project was reached in October 2009 19 Miami Dade County was reported to have contributed 402 million the city of Miami 50 million and the state 650 million to build operate and maintain it 14 Those contributions are spread during construction and operation of the tunnel project During construction 90 of the funds are provided by the private sector Of the estimated 1 billion total project cost 607 million would go to design and construction 195 1 million to financing 59 6 million to insurance and maintenance during construction 41 2 million to reserves and 209 8 million for state development cost 20 Overview Edit An overview of the Port Miami Tunnel project In this map the areas marked in orange signify the route of the tunnel while areas marked in blue signify associated ramps and infrastructure The Port of Miami Tunnel project involved the design and widening of the MacArthur Causeway by one lane in each direction leading up to the tunnel entrance the relocation of Parrot Jungle Trail and the reconstruction of roadways on Dodge Island The tunnel itself has two side by side tubes carrying traffic underneath the cruise ship channel of the Government Cut shipping lane Jacobs Engineering Group was responsible for the design of the roadways Langan Engineering amp Environmental Services was the geotechnical engineer and Bouygues was the prime contractor for the tunnel project itself Chosen due to their key involvement in the construction of the Channel Tunnel a major tunnel in Europe the selection of Bouygues was also met with controversy and protested by the Cuban exile community in Miami due to the company s involvement with locally opposed construction projects in Cuba 13 The project connects the east west Interstate 395 I 395 State Road 836 which terminates into State Route A1A at the Miami city limit on the MacArthur Causeway as well as Interstate 95 directly to PortMiami 21 The port was previously only connected to the mainland by Port Boulevard which is accessed by crossing U S Route 1 Biscayne Boulevard and traveling through downtown 19 The project also includes roadway improvements to the connection between I 395 and State Road 836 22 also known as the Dolphin Expressway at Interstate 95 The tunnel will allow heavy trucks to bypass the congested Downtown Miami area which is considered to be especially crucial with the large increase in trade traffic expected to be created by the Deep Dredge Project and the enlargement of the Panama Canal Projected to eventually carry 26 000 vehicles a day under Government Cut through its twin two lane tunnels 23 the top of the tunnels lie over 60 feet 18 3 m below the seabed The project created nearly 1 000 jobs as of 2011 with 70 reported as local 24 25 26 project executives promised that many of the construction jobs would go to local contractors 27 Along with the related Deep Dredge and Panama Canal Expansion over 30 000 jobs are expected to be created in the long run 28 Before completion of the tunnel in 2009 nearly 16 000 vehicles travelled to and from PortMiami through downtown streets each weekday Truck traffic made up 28 or 4 480 of this number Source 2009 PB Americas Traffic Study In 2010 it was estimated that around 19 000 vehicles traveled to the port daily but that only 16 were trucks 9 Existing truck and bus routes restricted the port s ability to grow driving up costs for port users and presenting safety hazards They were also thought to congest and limit redevelopment of the northern portion of Miami s Central Business District 26 The Port of Miami Tunnel includes providing a direct connection from the Port of Miami to highways via Watson Island to I 395 and along with the deep dredge keeping the Port of Miami the county s second largest economic generator after Miami International Airport supporting over 11 000 jobs directly with an average salary of 50 000 29 a competitive player in international trade 15 The Port of Miami provides 176 000 jobs 6 4 billion in wages and 17 billion in economic output Source 2007 Port of Miami Economic Impact Study Public private partnership PPP Edit The tunnel project is a public private partnership PPP or P3 designed to transfer the responsibility to design build finance operate and maintain the project to the private sector Ten banks BNP Paribas Banco Bilbao Vizcaya Argentaria RBS Citizens N A Banco Santander Bayerische Hypo Calyon Dexia ING Capital Societe Generale and WestLB will provide the senior debt financing for the project 19 which totals 341 5 million 30 The project attracted three bidding consortia Under the concession agreement FDOT will make milestone payments to the concessionaire Miami Access Tunnel during the construction period upon the achievement of contractual milestones 90 of Miami Access Tunnel s equity is provided by Meridiam Infrastructure Miami LLC Luxembourg based Meridiam SARL the remaining 10 by France s Bouygues Travaux Publics SA operating as Dragages Concession Florida Inc 19 The Port of Miami Tunnel Project was one of the first P3s in Florida and the first availability based P3 deal in the US 31 after the Interstate 595 I 595 renovation project in Broward County 32 When construction is completed FDOT will make availability payments to the concessionaire These payments will be contingent upon actual lane availability and service quality if the tunnel is closed or the road is in bad condition part or all of the payment for that period may be withheld 30 The tunnel will be turned over to FDOT in first class condition at the end of the contract in October 2044 thirty years after its completion 20 Maintenance costs over this 30 year period are expected to total around 200 million 33 Unlike many similar public private partnerships the tunnels will not have a toll 19 The originally scheduled June 2014 opening was delayed due to several mechanical problems including leaky pipes broken exhaust fans due to sudden vibrations and failing bolts The general contractor Bouygues was fined 115 000 for every day that the tunnel was not open losing millions of dollars The tunnel was officially opened to commercial and private traffic on August 3 2014 Criticism Edit Center of the tunnel traveling from MacArthur Causeway to PortMiami Traveling uphill towards the PortMiami portal from MacArthur Causeway According to the Miami Herald the financing structure of the plan is notable for the amount of financial risk taken by the builders in return for the long term concession on the tunnel 13 Opposition to the project states that it is a waste of taxpayer money and may become Miami s Big Dig the nickname of a tunnel megaproject in Boston which was a 4 billion project that ended up costing 22 billion in cost overruns Many believe that the Port of Miami Tunnel Project will be likely to have similar cost overruns 34 even though the Secretary of the Florida Department of Transportation FDOT promised that the project would finish on time and without overruns 35 They also state that truck traffic is not a problem in Downtown and that since 1991 car and truck traffic had reduced significantly 36 Downtown business owners have referred to it as the tunnel to no where stating that no one will use it In 1992 32 000 vehicles entered the port daily a number which later dropped to nearly half that but had once again risen to around 19 000 by 2011 9 It has been regarded as a boondoggle project by those who oppose it stating that the city can t afford it In fact the city did have difficulty providing its 50 million portion of the funding for the project 37 38 Some believe it may create traffic problems on the MacArthur Causeway environmentalists worry about the potentially negative impact the construction could have on the Biscayne Bay 39 An ominous foreshadowing of cost overruns Miami Access Tunnel requested money from a 150 million reserve fund in July 2011 for the unexpected need to grout the limestone beneath the surface so that the tunnel boring machine cuts more smoothly This request alarmed new Miami Dade Mayor Carlos A Gimenez when it was brought up at his first commissioners meeting as mayor on July 7 40 The contractor stated that they will continue without the additional requested money if FDOT denies it but it may end up as a court case as the contractor seeks it later 41 On July 19 the FDOT denied the request for more money to the contractor stating that the geological issue cited was not as extensive as MAT claimed 42 Benefits related projects EditAlthough there is great speculation that the Port of Miami Tunnel project is both unnecessary and a waste of taxpayer dollars it is expected to have positive benefits in the long run which coincide with several other related projects predicted to increase its traffic many such as the Port of Miami Deep Dredge Project and Panama Canal expansion slated to be finished in 2015 and 2016 respectively The port has gone through several expensive projects throughout its history and many have been seen as beneficial to the economic growth of the Greater Miami area in the long run such as in the 1950s when the deteriorating Port of Miami then located in the mainland in downtown was moved to its current home the man made Dodge Island 43 The current port director of the Port of Miami Bill Johnson states that these new port infrastructure projects should be able to double the port s container capacity over the next decade 44 Miami City Commissioner Marc Sarnoff stated that This is the best public works project ever 24 A strong trade industry is also considered to be a vital sign of a good and improving economy 45 Cruise traffic Edit Seven cruise ships docked at the Port of Miami In addition to the expected increase in cargo traffic the Port of Miami recently stated that October 2010 was its busiest October ever for cruise vacations The port had a record 346 513 cruise passengers that October up 29 from October 2009 This follows a record year in cruise traffic with 4 15 million cruise passengers in the 12 months that ended in September 46 This is partially due to the arrival of new cruise ships such as the Norwegian Epic as well as the cruise line Costa Cruises 47 Despite this the Port of Miami has recently been losing cruise and cargo traffic to nearby Port Everglades in Fort Lauderdale In 2010 Royal Caribbean Cruise Lines which is headquartered in Miami chose Port Everglades as home for its new cruise ships Oasis of the Seas and Allure of the Seas 48 currently the largest cruise ships in the world As for cargo traffic truckers state that despite the longer miles they can make more trips per day at Port Everglades Also they blame the port itself for this not the Downtown traffic 36 They state that at Port Everglades they can make three to four runs a day versus Port of Miami where you re lucky if you get in two states truck driver Alejandro Arrieta due to waiting time at the port which is often several hours 9 Port Everglades also has major redevelopment plans underway that includes its own deep dredging to a 50 foot 15 m depth 49 they also claim to have surpassed the Port of Miami which has long been known as the Cruise Capital of the World as well as the Cargo Gateway to the Americas in both cruise traffic and cargo tonnage handled Railroad access Edit The rail line being redone in November 2011 Further information PortMiami Railroad access The Port of Miami was also recently awarded a federal grant as part of the Transportation Investment Generating Economic Recovery TIGER program to restore a connection between the Florida East Coast Railway s yard in Hialeah and the Port of Miami directly connecting the port to rail networks across the United States 50 as well as re establish the port s on dock rail capability loading and unloading directly between ships and trains 51 The railroad bridge connecting the Port of Miami to the mainland was damaged by Hurricane Wilma in 2005 at which time service was suspended and the bridge remained closed for well over a decade 52 Rail service to the port was restored by 2014 53 The rail project is part of another element of increasing PortMiami s capacity an inland intermodal center to be built near the airport known as Flagler Logistics Hub which was planned to be built on 300 acres of land in Hialeah 54 Opposition to the railroad line returning to service included that it would be as much of a problem to downtown traffic as the container trucks and that the noise would be a disturbance to nearby residents As with before however trains are occasional and reserved for specialty loads such as oversized loads and hazardous materials which will be banned from the tunnel citation needed It was also stated that the trains which will be able to go up to 30 mph on the newly renovated line versus the old limit of 5 mph 55 will be able to cross Biscayne Boulevard in 90 seconds 56 The current plan is for the line to be strictly for intermodal services with the project including a rail yard and station at the port however in the future a passenger station may be added 57 Downtown congestion Edit Container trucks leaving the port for Interstate 95 through downtown Another major benefit of the tunnel will be the redirecting of the large number of vehicles nearly 16 000 daily 2009 estimate 58 many of them container trucks and cruise buses that cross Biscayne Boulevard US 1 at NW 5th Street Port Boulevard using level streets such as Northeast 1st Avenue 24 which for years were the only way to access the port 59 Along with the capacity of the port the amount of truck traffic could double after the completion of the numerous port projects 44 Additionally the Port Boulevard entrance to the port is closed at night concentrating all truck traffic during the day This traffic creates congestion and presents a danger to pedestrians and bicyclists Traffic is also considered to be a harm to Miami s northern central business district reducing its ability to grow including Miami s new Arts amp Entertainment District valued at over 12 billion 26 The developers for a once planned project for the north side of downtown known as Miami City Square stated that the heavy truck traffic and congestion in that area was a grave concern 60 The Omni Community Redevelopment Agency used a 50 million loan from Wachovia to donate towards financing the tunnel construction 61 Resorts World Miami by Genting Group and Miami World Center are two proposed major development planned for the area where congestion is a concern 62 Additionally the population of Downtown Miami nearly doubled from 2000 to 2010 and is expected to increase by several thousand more in the current decade largely due to many new high rise condo developments in the downtown area adding thousands of housing units which will benefit from having the tunnel 18 Although traffic and port activity has declined since the early 1990s losing some of it to the nearby Port Everglades which overtook Port of Miami in 2007 as Florida s largest cargo port 9 the port is likely to see a large shift in the other direction after it becomes one of few deep water ports in the United States able to handle the New Panamax ships by 2016 Within the first month of opening it was reported that congestion in the downtown area had eased 63 It was estimated that 46 to 80 of the passenger vehicles many of which are shuttle buses and taxis and make up nearly three quarters of the total port traffic will use the tunnel after it was completed 58 Deep Dredge Panama Canal expansion Edit Container trucks from the Port of Miami traveling through downtown Further information PortMiami Deep Dredge Project The timing of the tunnel s construction and opening coincides with PortMiami Deep Dredge Project that will see the port dredged deeper to accommodate larger ships expected following the completion of the Panama Canal expansion now expected to be completed in 2016 previously 2014 64 This will allow much larger ships known as New Panamax which will have a capacity of more than double that of Panamax ships to traverse the canal This is predicted to cause a major increase in the Port of Miami s cargo traffic which would overwhelm the intersection of Port Boulevard and Biscayne Boulevard without the tunnel In 2009 870 000 trucks moved cargo in and out of the port and port officials estimate that that number will increase to around 1 4 million when larger ships start arriving 65 In 2010 about 800 000 TEU s were moved through the port and port director Bill Johnson said that with the right marketing to major shippers that number should double by 2020 66 Currently the largest cargo ships that dock at the port have a capacity of around 4 200 TEU s Twenty foot Equivalent Units After the canal expansion and port dredging ships as large as 7 500 to 8 500 TEU s will be able to dock there 65 Construction Edit Preparing for construction on Watson Island September 2010 Construction on Watson Island March 2011 Work on the Port of Miami Tunnel project began on Watson Island and Dodge Island including work on the MacArthur Causeway in May 2010 67 Groundbreaking on the construction project was unannounced and considered secret as the groundbreaking was scheduled for June 2010 6 but actually took place on May 24 2010 68 without ceremony The tunnel boring machine was built in Germany and had to be re assembled in Florida after arriving in crates on the 168 metres 551 ft 69 cargo ship Combi Dock 1 70 on Thursday June 23 2011 71 72 and being assembled in the median of the causeway 73 where the construction is taking place Both directions of the MacArthur Causeway have remained open during the assembly of the machine except for nighttime lane closures and delays on the westbound side 74 The machine which weighs more than 2 500 tons was assembled in a 65 foot 20 m deep pit known as the launching pad located in between two concrete walls in the median of the causeway which only left a 42 foot 13 m cutter visible from the road 75 According to NBC Miami as of June 2011 899 jobs had been created by the project with over 70 being from the 305 area code Miami Dade County 24 The construction is projected to take 47 months with the tunnel being finished in 2014 13 The French firm Bouygues Construction has been put in charge of operating the tunnel boring machine which was nicknamed Harriet in July 2011 after a naming competition was sponsored by MAT and the FDOT and carried out by the Girl Scout Council of Tropical Florida 76 The tunnel boring machine was longer than a football field at 540 feet 160 m long 33 and over 40 feet 12 m in diameter It was used to bore two side by side 43 feet 13 m diameter tunnels one for each direction each 3 900 feet 1 1 km long 77 The tunnel boring machine itself cost 45 million and was custom built for the Port of Miami Tunnel Project by the German firm Herrenknecht 25 No explosives are said to be used on the construction of the tunnel 22 Drilling of the tunnel itself commenced in mid November 2011 with the drilling machine beginning work on the Watson Island tunnel entrance 78 The first tunnel connecting Watson Island and the Port of Miami was completed in August 2012 79 and the second tunnel was completed on May 9 2013 as Harriet emerged back on Watson Island where digging had commenced in 2011 80 The roadway construction should finish for an opening on May 15 2014 33 The MacArthur Causeway which currently has three traffic lanes in each direction and a sidewalk on the eastbound side will be widened to four 12 foot 3 7 m wide traffic lanes with a ten foot inner and outer shoulder as well as a six foot sidewalk 81 The tunnel was officially opened to commercial and private traffic on August 3 2014 after minor mechanical delays pushed back the originally scheduled June 2014 opening date The general contractor Bouygues was fined 115 000 for every day that the tunnel was not open losing millions of dollars Controversies Edit In March 2011 one of the sub contractors of Bouygues fell under criticism for the dumping of tunnel fill on sensitive wetlands on Virginia Key They were supposed to be dumping the fill on Virginia Key on the degraded northwest side but were found dumping it 80 to 100 yards 73 1 to 94 5 m from the designated spot 82 where they damaged wetlands and killed about 40 mangrove trees with a piece of equipment that got stuck 83 The intention was that they would be allowed to put 55 000 cubic yards 42 050 5 m3 of fill there provided that they use it to build a berm to block the view of Virginia Key s sewage water treatment plant 84 The fill that was dumped on Virginia Key was mainly rock and soil from road construction and site preparation on Watson Island and not from tunnel boring which environmentalists object being put on Virginia Key as it may not be as clean 75 The north point of Virginia Key is one of the last remaining undeveloped areas near the Miami downtown area and has been recently restored as it was previously used as a dumping site for the infill from the Rickenbacker Causeway Miami Marine Stadium and Norris Cut 85 One other potential infill site that was briefly suggested is an inlet located between Bicentennial Park and the American Airlines Arena on the mainland in downtown where Miami Dade County was conducting a study on the effects it would have 86 This proposal was quickly retracted after public outcry due to the fact that the currently closed off waterfront lot known as Parcel B is slated to soon be a long anticipated public park 87 There has also been minor controversy over speculation that a yacht allegedly owned by Bouygues may have been bought with public money A Bouygues spokesperson denied this claim 88 The owner of the seaplane base on Watson Island has accused the tunnel builders of trespassing for storing equipment on his property as well as for using the road that passes through his property FDOT and city officials said the use of the land is permitted 89 See also Edit Transportation portalPort of Miami Deep Dredge Project New Panamax Panama Canal expansion project Transportation in South FloridaReferences Edit a b Lincoff Nina September 24 2014 Port tunnel traffic grows Miami Today Retrieved October 16 2014 a b c Chardy Alfonso May 17 2014 Decades after conception Miami has a port tunnel Miami Herald Retrieved June 6 2014 Port of Miami Tunnel fdotmiamidade com Florida Department of Transportation Retrieved August 24 2014 Public Private Partnership portofmiamitunnel com Florida Department of Transportation Retrieved August 24 2014 General FAQ portofmiamitunnel com Florida Department of Transportation Retrieved August 24 2014 a b Alfonso Chardy April 17 2010 Port of Miami tunnel project on track for June start Miami Herald Retrieved March 30 2011 dead link Project History PDF Florida Department of Transportation Retrieved March 30 2011 Newland Maggie August 2 2014 Tunnel To PortMiami Opening Sunday Morning WFOR TV Retrieved August 3 2014 a b c d e Erik Maza June 2 2010 Port Of Miami Tunnel Project Could Be South Florida s Big Dig Miami New Times Retrieved April 2 2011 Pat Burson Larry Lipman April 1 1987 Fate of Miami tunnel hangs on today s Senate vote The Palm Beach Post Retrieved June 29 2011 dead link Davis Jeff 30 Years Ago This Week Reagan s 1987 Highway Bill Veto Eno Transportation Weekly Eno Center for Transportation March 27 2017 Julia Neyman and Oscar Pedro Musibay December 13 2007 Miami OKs Marlins stadium port tunnel South Florida Business Journal Retrieved July 12 2011 a b c d Larry Lebowitz January 15 2008 Planned Miami port tunnel Can we dig it Miami Herald Retrieved January 15 2008 dead link a b WPLG TV April 16 2009 Port Of Miami Tunnel Project Revived Archived from the original on September 26 2011 Retrieved March 30 2011 a b Miami Dade County July 13 2010 City County team up to secure federal funding for Port of Miami Deep Dredge Project MiamiDade gov Archived from the original on September 5 2010 Retrieved April 3 2011 Jose Perez Jones March 20 2011 Miami needs Colombia free trade pact Miami Herald Archived from the original on April 8 2011 Retrieved April 3 2011 Port of Miami tunnel Critical Miami 2005 Retrieved March 30 2011 a b Florida DOT Mulls Bids on 1 Billion Miami Tunnel Job Engineering News Record 2007 Retrieved April 3 2011 a b c d e Shelly Sigo October 19 2009 Mimai Tunnel Reaches Closure The Bond Buyer Retrieved April 5 2011 a b Case Studies Port of Miami Tunnel Federal Highway Administration 2010 Archived from the original on January 17 2011 Retrieved April 3 2011 Port of Miami Cargo Edward Redlich October 14 2010 Retrieved April 6 2011 a b Hank Tester April 2 2010 Actual Work Spotted at Port Tunnel Project NBC Miami Archived from the original on March 13 2012 Retrieved April 1 2011 Video Animation showing what the tunnel would look like Miami Herald January 15 2008 Retrieved January 15 2008 a b c d Hank Tester June 20 2011 Port of Miami Tunnel Dig to Get Into High Gear NBC Miami Retrieved June 22 2011 a b Risa Polansky July 8 2010 Port of Miami tunnel project is indeed a big bore Miami Today News Retrieved March 30 2011 a b c Alyce Robertson May 25 2010 Miami can t afford to have Port of Miami tunnel delayed Miami Herald Retrieved March 30 2011 dead link Hank Tester September 1 2010 Port of Miami Tunnel Digging Up Local Jobs NBC Miami Retrieved April 3 2011 A Man A Plan A Tunnel TransportationNation March 17 2011 Archived from the original on July 27 2011 Retrieved April 9 2011 Miami Herald Editorial July 14 2011 Ready to rake in the big bucks Miami Herald Archived from the original on August 11 2011 Retrieved July 16 2011 a b Chrissy Mancini Nichols March 21 2011 PPP Profiles Port of Miami Tunnel Metropolitan Planning Council Retrieved March 31 2011 Miami Tunnel PPP full deal analysis Project Finance October 23 2009 Retrieved April 5 2011 Port of Miami Tunnel Digging deep Project Finance November 19 2009 Retrieved April 5 2011 a b c Ashley Hopkins April 13 2011 Monster boring machine from Germany to dig Port of Miami tunnels Miami Today Retrieved April 13 2011 Felipe Azenha June 2 2010 Is the Port of Miami Tunnel Our Big Dig or OurTunnel to Nowhere Transit Miami Archived from the original on July 1 2011 Retrieved April 2 2011 Work on the Port of Miami tunnel gets under way WSVN TV June 11 2010 Retrieved April 4 2011 a b Erik Maza June 3 2010 Port of Miami Tunnel is a waste of taxpayer money Miami New Times Retrieved March 31 2011 Miami Port Tunnel threatened again as SEC orders Miami to turn over its financial books South East Shipping News December 12 2009 Retrieved July 21 2011 Letters to the Editor Miami Herald June 23 2011 Retrieved July 21 2011 dead link Francisco Alvarado May 24 2011 Five Reasons Carlos Gimenez Is The Wrong Man For The Job Miami New Times Retrieved May 24 2011 New Mayor attends first commission meeting WSVN TV July 7 2011 Retrieved July 24 2011 Alfonso Chardy and Martha Brannigan July 7 2011 Firm building Miami tunnel seeks more money months before starting to drill Miami Herald Archived from the original on August 10 2011 Retrieved July 7 2011 Alfonso Chardy July 19 2011 Florida officials deny reserve funds for Port of Miami tunnel builders Miami Herald Retrieved July 21 2011 dead link Andrew D Melick December 12 2010 How much should Seaport spend Miami Herald Retrieved April 2 2011 dead link a b USA Port of Miami Deep Dredge Project to Double its Cargo Capacity Dredging Today November 26 2010 Retrieved April 1 2011 Marilyn Bowden May 26 2011 Outlook for small business financing is becoming brighter Miami Today Retrieved May 29 2011 Doreen Hemlock December 21 2010 Port of Miami had busiest October ever for cruises Sun Sentinel Archived from the original on December 26 2010 Retrieved March 31 2011 Cruise traffic soars at Port of Miami South Florida Business Journal October 20 2010 Retrieved March 31 2011 Royal Caribbean Announces Allure Of The Seas Inaugural Season Royal Caribbean International 2009 Archived from the original on July 14 2011 Retrieved April 2 2011 Port Everglades 300 million for Dredging in 2 billion dollar expansion plan USA Dredging Today March 3 2010 Retrieved April 6 2011 Jeanette Sheppard Hank Tester July 15 2011 Port of Miami Rail Project Groundbreaking NBC Miami Retrieved July 16 2011 Miami port rail link construction set Railway Age July 13 2011 Archived from the original on September 27 2011 Retrieved July 16 2011 Back to the Future Port of Miami amp Florida East Coast Railway MiamiDade gov 2010 Retrieved March 30 2011 Blake Scott May 7 2014 Seaport rail to expand again MiamiToday News Retrieved October 16 2014 Zachary S Fagenson March 10 2011 Million square foot Flagler logistics hub key piece of Miami s international trade puzzle Miami Today News Retrieved March 30 2011 Port of Miami rail connection breaks ground WSVN TV July 15 2011 Retrieved July 16 2011 Ashley D Torres July 15 2011 FEC rail project starts 800 jobs expected South Florida Business Journal Retrieved July 17 2011 TIGER II Grant Miami Dade gov 2010 Retrieved April 11 2011 a b Zachary Fagenson June 2 2011 Florida East Coast Rail line to haul 5 of cargo trucks from Port of Miami Miami Today Retrieved June 2 2011 Hank Tester June 11 2010 FDT Deems Port Tunnel Really Sexy NBC Miami Retrieved April 1 2011 Yudislaidy Fernandez July 24 2008 Walmart in downtown Miami Company confirms discussions have taken place but says no agreements have been made Miami Today News Retrieved April 7 2011 Jacquelyn Weiner June 2 2011 Miami to ease financial pressures by refinancing some loans Miami Today Retrieved June 7 2011 Elaine Walker July 31 2011 Genting Group is betting on Miami as future resort destination Miami Herald Retrieved August 1 2011 dead link Muiz Andria C October 1 2014 Port Miami Tunnel marks first month of operation Miami s Community Newspapers Retrieved November 2 2014 Uncredited November 26 2010 Port of Miami seeks funds for Deep Dredge project SandandGravel com Retrieved April 1 2011 a b Alfonso Chardy August 21 2010 Port of Miami puts rail project on fast track Miami Herald Retrieved March 30 2011 dead link Zachary Fagenson June 9 2011 Major logistics centers vital to leverage growth at Port of Miami Miami International Airport Miami Today Retrieved June 8 2011 Construction schedule Florida Department of Transportation 2010 Retrieved March 31 2011 Brian Hamacher May 24 2010 Dig This Port of Miami Tunnel Construction Begins NBC Miami Retrieved April 4 2011 Combi Dock I IMO 9400473 vesseltracker Retrieved June 24 2011 Alfonso Chardy June 23 2011 Machine to drill Port of Miami tunnel arrives Miami Herald Retrieved June 24 2011 dead link Lidia Dinkova Alfonso Chardy June 23 2011 Ship carrying tunnel boring machine to dock at Port of Miami Miami Herald Retrieved June 23 2011 dead link Boring equipment brought for port tunnel construction WSVN TV June 23 2011 Retrieved June 23 2011 Alfonso Chardy May 17 2011 Drivers hit the brakes for road construction in S Fla Miami Herald Retrieved May 17 2011 dead link Lidia Dinkova June 27 2011 Assembly of tunnel boring machine to cause MacArthur Causeway lane closures Miami Herald Retrieved June 27 2011 dead link a b Alfonso Chardy June 20 2011 A giant step for Port of Miami tunnel construction Miami Herald Archived from the original on October 8 2011 Retrieved June 22 2011 Alfonso Chardy The Miami Herald August 9 2011 Miami tunnel boring machine gets a name Harriet Sun Sentinel Retrieved August 11 2011 permanent dead link Shani Wallis 2010 Port of Miami Tunnel gets underway TunnelTalk Retrieved March 31 2011 Viglucci Andre November 14 2011 Port of Miami tunnel drilling starts The Miami Herald Miami Florida Retrieved November 29 2011 Port of Miami Tunnel Halfway Done PortMiami tunnel digging reaches end of the line POMT Public Affairs Program Office June 2 2010 Technical Fact Sheet PDF Florida Department of Transportation Archived from the original PDF on September 29 2011 Retrieved July 17 2011 Janie Campbell March 12 2011 Rogue Contractor Dumps Tunnel Fill In Wetlands NBC Miami Retrieved March 30 2011 Miami Herald Editorial June 25 2011 Don t make Virginia Key a casualty Miami Herald Retrieved June 25 2011 dead link Andres Viglucci March 11 2011 Tunnel contractor makes wetland mess Miami Herald Retrieved March 30 2011 dead link USA Officials Propose Virginia Key Park s North Point for Dumping Site Dredging Today June 28 2011 Retrieved June 29 2011 Jacquelyn Weiner June 16 2011 Downtown Miami inlet a dredging dump site Miami Today News Retrieved June 25 2011 Erik Bojnansky August 4 2011 A Waterfront Park for All to Enjoy Biscayne Times Retrieved August 4 2011 Michael Miller March 23 2011 Does Bouygues Contractor On The 1 Billion Port Of Miami Tunnel Have A 1 Million Yacht Miami New Times Retrieved April 7 2011 Alfonso Chardy July 31 2011 Tunnel builder accused of trespassing on seaplane base Miami Herald Retrieved August 1 2011 dead link External links EditRoute map KML file edit help Template Attached KML Port Miami TunnelKML is from Wikidata Wikimedia Commons has media related to Port of Miami Tunnel Port of Miami Tunnel website 2005 POM Tunnel animation video Newer Tunnel animation video Retrieved from https en wikipedia org w index php title Port Miami Tunnel amp oldid 1106038689, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.