East Side Access (ESA) is a public works project in New York City that extended the Long Island Rail Road (LIRR) two miles from its Main Line in Queens to the new Grand Central Madison station under Grand Central Terminal on Manhattan's East Side. The Metropolitan Transportation Authority (MTA) project was originally scheduled to open in 2009 but was delayed by more than a decade. The new station and tunnels opened with limited service to Jamaica station in Queens on January 25, 2023, and full service began on February 27, 2023. The estimated cost of the project rose nearly threefold from US$3.5 billion to US$11.1 billion as of April 2018, making it one of the world's most expensive underground rail-construction projects.

East Side Access
Interactive map
  Red and   blue: new tunnels.
  Green: existing 63rd Street Tunnel.
Points denote new stations.
Overview
StatusFull service
OwnerMetropolitan Transportation Authority
LocaleNew York City
Termini
Stations2
WebsiteOfficial website
Service
TypeCommuter rail
SystemLong Island Rail Road
ServicesCity Terminal Zone
Operator(s)MTA Long Island Rail Road
Ridership162,000 daily (projected)
History
CommencedSeptember 2007 (2007-09)
OpenedJanuary 25, 2023 (2023-01-25)[1]
Technical
Line length2 mi (3.2 km)
Track length6.1 mi (9.8 km)
Number of tracks2–8
CharacterUnderground
Track gauge4 ft 8+12 in (1,435 mm) standard gauge
ElectrificationThird rail750 V DC
Route map

East Side Access route
Other routes

The new LIRR terminal contains eight tracks and four platforms in a two-level station 100 feet (30.5 m) below street level. It was built in conjunction with several other LIRR expansion projects, including an additional track along parts of the Main Line. The project was intended to remove or reduce the need for subway transfers for a large number of riders with jobs on the east side of Manhattan. Previously, the only Manhattan stop for trains from Long Island was Penn Station, on the west side of the island.

East Side Access was based on transit plans from the 1950s, though an LIRR terminal on Manhattan's East Side was first proposed in 1963. The planned LIRR line was included in the 1968 Program for Action of transit improvements in the New York City area. Lack of funds prevented the construction of any part of the connection other than the 63rd Street Tunnel under the East River. Plans for the LIRR connection were revived in the late 1990s. The project received federal funding in 2006, and construction began the following year. The tunnels on the Manhattan side were dug from 2007 to 2011, and the connecting tunnels on the Queens side were completed in 2012. Afterward, work began on other facilities related to the line, such as new platforms at Grand Central, ventilation and ancillary buildings, communication and utility systems, and supporting rail infrastructure in Queens. The project's completion was delayed several times during construction.

History edit

Origins edit

The East Side Access project was based on regional planning proposals that were first brought up in the 1950s.[2]: 18 (PDF p. 21)  In March 1954, the New York City Transit Authority (NYCTA) issued a $658 million construction program. The proposal included a tunnel for the Second Avenue Subway, which would cross the East River between 76th Street in Manhattan and Astoria in Queens before continuing onto the Long Island Rail Road (LIRR)'s Main Line in Queens.[3] The 76th Street tunnel proposal resurfaced in 1963, though the location of the tunnel was changed several times thereafter.[4] In 1965, the NYCTA finally decided to build the subway tunnel at 63rd Street.[5]

The first proposals to bring LIRR service to a terminal in eastern Midtown Manhattan arose in 1963.[2]: 17 (PDF p. 20)  To facilitate planning for this terminal, a third track was added to the plans for the 63rd Street subway tunnel in April 1966. The track would serve LIRR trains to east Midtown, alleviating train traffic into Penn Station on Manhattan's west side while integrating the LIRR with the subway.[6] A fourth track was added to the plans in August 1966 after it was determined that LIRR trains would be too large to run on subway tracks. This amendment increased the number of LIRR tracks to two, and provided segregated tracks for the LIRR and the subway.[7]

In February 1968, the NYCTA's parent company, the Metropolitan Transportation Authority (MTA), released the Program for Action, which proposed numerous improvements to subway, railway, and airport service in the New York metropolitan area. The plan included a new LIRR terminal at a proposed Metropolitan Transportation Center at Third Avenue and 48th Street in East Midtown. It also included connections to Grand Central Terminal, with a new northern entrance leading to the center, and the Second Avenue Subway, among other transit services.[8]: 5 [9] The new LIRR line was to branch off from existing lines in Sunnyside, Queens, and enter Manhattan using the new two-level 63rd Street Tunnel. The upper level was to be used by the New York City Subway's 63rd Street lines and the lower level was to be used by the LIRR.[9] According to renderings of the transportation center, the mezzanine would be placed above four island platforms and eight tracks, which would be split evenly across two levels,[8]: 48–49  similar to the present terminal under Grand Central.[10][11]

 
A ventilation tower for the 63rd Street Tunnel

Construction on the project began in 1969.[2]: 17 (PDF p. 20)  Four 38-foot-square (12 m) prefabricated sections of the 63rd Street Tunnel were constructed under the East River, the first of which was delivered in May 1971.[12] That first section was lowered into place on August 29, 1971,[13] and the last section was lowered on March 14, 1972.[14] The double-deck, 3,140-foot (960 m)[15] tunnel under the East River was "holed through" on October 10, 1972, with the separate sections of tunnels being connected.[16] The estimated cost of the project was $341 million, and the MTA applied for $227 million in Federal funds.[17]

Plans to build the Manhattan terminal in the Turtle Bay neighborhood were opposed by residents who feared it would change the neighborhood and bring traffic congestion;[18] they suggested it be built at Grand Central instead.[19] MTA officials countered that there were too many rail lines at Grand Central, and that adding the LIRR would further strain the Lexington Avenue Line. If it were on Third Avenue, passengers would have been more inclined to use the Second Avenue Subway, which was partially under construction at the time.[18] On April 16, 1973, a Federal directive directed New York State to consider expanding and modernizing Grand Central before building the new terminal under Third Avenue.[17]

Preliminary planning for the Metropolitan Transportation Center had been completed by January 1975.[2]: 17 (PDF p. 20) [20] Due to continued opposition to the Transportation Center, a "Grand Central Alternative" was published in September 1976. It called for the LIRR to use Grand Central Terminal's lower level instead.[2]: 18 (PDF p. 21)  In 1977, the MTA's board of directors voted to use Grand Central as the terminal for the proposed LIRR route.[21]

Plans stalled edit

Due to the 1975 New York City fiscal crisis, the LIRR project was canceled long before the tunnel was completed. The New York Times noted that the lower level of the 63rd Street Tunnel was still under construction by 1976, even though "officials knew that the tunnel would never be used."[22] Richard Ravitch, the MTA chairman, said that to stop the work was impossible or so costly as to make it impractical subsequent to the construction of the subway portion."[22] The lower level of the 63rd Street Tunnel was completed along with the upper subway level.[2]: 17 (PDF p. 20) [22] The western end of the tunnel lay dormant under Second Avenue at 63rd Street for three decades. By the time that construction on the LIRR tunnel level stopped, the tunnel was built for a distance of 8,600 feet (2,600 m). The 8,600-foot "tunnel to nowhere" was completed "largely for structural reasons — to support the subway tunnel above."[22]

The 63rd Street subway line and LIRR tunnel were completed as far as 29th Street in Long Island City, Queens, with the subway level of the tunnel opening in 1989. The LIRR tunnel remained unused beneath the subway tracks.[23] In 1994, work began to extend the 63rd Street subway tunnel east to connect to the Queens Boulevard subway line; the LIRR tunnel was also extended east, under 41st Avenue in Queens to the west side of Northern Boulevard in Queens.[24][25] The subway connector was opened to full-time F train service in December 2001.[26][27]

Plans revived edit

Plans were made in 1995 to bring LIRR service to East Midtown,[28]: 3  although MTA officials declared that the LIRR East Side connection would not be completed within the next generation. In 1997, U.S. Senator Al D'Amato started asking for federal money to connect the LIRR to Grand Central. New York Governor George Pataki had previously proposed completing the project, but D'Amato's support increased the likelihood that construction would actually begin. At the time, if everything went favorably, the LIRR link could open by 2010.[29] By that time, the LIRR was the busiest commuter railroad in the United States, with an average of 269,400 passengers each weekday in 1999.[2]: 4 (PDF p.7)  As of 1998, there were almost 1.77 million jobs in Manhattan, including an increasing number of white-collar "office" jobs in East Midtown.[2]: 7 (PDF p.10)  Penn Station on the West Side was operating at capacity due to a complex track interlocking and limited capacity in the East River Tunnels.[2]: 8 (PDF p.11) 

In 1999, the MTA proposed a $17 billion five-year capital budget. This budget included a $1.6 billion LIRR connection to Grand Central, as well as several subway extensions.[30] The project's final environmental impact assessment (FEIS) was released in March 2001.[31]: 1 [a] The FEIS reviewed two key options for bringing LIRR service to Grand Central. The first option was to connect the tunnels to the existing lower level at Grand Central, while the second option was to build an entirely new station underneath it. The MTA ultimately recommended the second option because it was cheaper and less disruptive to Metro-North service.[31]: 4 [28]: 4  After reviewing the FEIS for two months, the Federal Transit Administration (FTA) gave the project a favorable "Record of Decision"—i.e., approved it.[28]: 3 [31]

 
East Side Access Project Information Center

After the September 11, 2001, attacks, the MTA said it would accelerate the construction of East Side Access. LIRR president Kenneth J. Bauer said, "The incident of September 11 shows the importance of East Side Access to a greater degree. If something happened at the East River tunnel, you wouldn't be able to run trains to Penn Station."[32] The MTA and Governor Pataki supported East Side Access and the Second Avenue Subway, both of which involved building new railroad infrastructure on the East Side.[33] In 2002, Congress allocated $132 million for infrastructure projects in New York State, including $14.7 million for East Side Access.[34] A final design for the project was approved in 2002, and the first properties for it were acquired in 2003.[28]: 4 

In 2004, some business owners in Midtown announced their opposition to a proposed 16-story ventilation building at 50th Street east of Madison Avenue. They said that the building would cause pollution and that it could be vulnerable to terrorist attacks.[35] Catholic Archbishop Cardinal Edward Egan of the Roman Catholic Archdiocese of New York worried about the effect on St. Patrick's Cathedral, which faced Fifth Avenue with its back on Madison Avenue north of 50th Street.[36] At first, MTA officials held fast to their plans,[37] but after continued opposition, they reduced the size of the building and moved the structure's cooling towers.[38]

Construction progress edit

Funding for MTA capital projects such as East Side Access, the Second Avenue Subway, and the 7 Subway Extension were included in the Rebuild and Renew Transportation Bond Act of 2005. As part of this act, the state would take on $2.9 billion in debt to issue bonds to fund these projects.[39] Voters ultimately approved the bond issue by a margin of 55% to 44%.[40] The federal government committed to provide $2.6 billion to help build the project by signing a full funding grant agreement in December 2006.[41][42] The construction contract for a 1-mile (1.6 km) tunnel in Manhattan westward and southward from the dormant lower level of the 63rd Street Tunnel to the new 100-foot-deep (30 m) station beneath Grand Central Terminal was awarded in July 2006. The contract went to Dragados/Judlau, a joint American–Spanish venture whose American headquarters were in College Point, Queens, close to the East Side Access site.[43][44]: 10  The total contract award was $428 million[26][43][44]: 10  and used two large tunnel boring machines.[26] After Hurricane Sandy flooded the East River Tunnels between Queens and Penn Station in 2012, officials prioritized the construction of East Side Access so that LIRR trains could be diverted to Grand Central, allowing the East River Tunnels to be renovated.[11]

Manhattan side edit

 
A tunnel cavern deep under Park Avenue, to the north of the new LIRR station, which now houses a switch

Work on the Manhattan side included building a new 8-track train station with storage tracks extending to 38th Street.[45]: 1 (PDF p. 2) [28]: 3  North of the station, the tunnels would connect to the 63rd Street Tunnel's lower level.[45]: 1 (PDF p. 2) [28]: 2  The new station would be housed in two gigantic caverns blasted out of the Manhattan schist rock formation under the station.[46][45]: 3 (PDF p. 4)  A three-level structure was being built in each cavern, with one 1,020-foot-long (310 m) train platform and two tracks each on the top and bottom levels. A passenger concourse was being constructed between each cavern's upper and lower levels.[28]: 3 [10] An upper-level concourse, accessed by a series of stairs, elevators, and escalators,[47] would replace ten tracks on the west side of Metro-North's Madison Yard.[48]: 3  The cavern structure is located under the Park Avenue Viaduct, which surrounds Grand Central Terminal, while the storage tracks are located under the Park Avenue Tunnel, which is located south of Grand Central Terminal.[45]: 6 (PDF p. 7) 

 
Construction of the station's upper concourse in the Grand Central Terminal's Madison Yard in May 2014. Two of the yard's tracks were kept in service during construction to bring in equipment and remove debris.
 
50th Street Commons pocket park

The track connections from the new station to the 63rd Street Tunnel were excavated using tunnel boring machines.[49] The first machine was delivered in May 2007.[26] Dragados/Judlau created a launch chamber for the tunnel boring machines under Second Avenue at 63rd Street in Manhattan using a controlled drill-and-blast method, then assembled and launched each 640-ton machine.[50] The first tunnel boring machine was launched westbound then southbound from the 63rd Street Tunnel in September 2007, and it reached Grand Central Terminal in July 2008.[51] The second machine began boring a parallel tunnel in December 2007 and had completed its tunnel at 37th Street on September 30, 2008.[50][52] Geocomp Corporation was hired to monitor the boring, using a battery of instruments to record vibration, ground settlement and any tilting or drift suffered by the tunnel boring machines. The instruments include inclinometers, extensometers, seismographs, observation wells, dynamic strain gauges, tilt meters and automated motorized total stations with prismatic targets.[53] The tunnel boring machines bored an average of 50 feet (15 meters) per day. Cross-connections between the tunnels were created under Park Avenue, between 49th and 51st Streets, by controlled drill-and-blast. The work began in mid-July 2008 and required between six and eight months to complete.[51]

In April 2008, the MTA awarded Dragados/Judlau another contract. The $506 million contract was for excavating caverns for the three-level platform structures, mezzanine, escalators, passageways, and track crossovers.[44]: 12  The MTA gave Gramercy Group Inc. the $38.9 million contract to reconfigure part of Madison Yard in March 2009.[44]: 14  In September 2009, the MTA awarded Yonkers Contracting Company a $40.8 million contract to demolish a building at 47 East 44th Street and construct a ventilation plant & concourse entrance on the building site, along with constructing a station entrance at an existing office tower at 245 Park Avenue (at East 46th Street).[44]: 16  Smaller contracts for electrical installations and structural repairs were also awarded in 2008.[44]: 16, 18  In 2010, the New York City Business Integrity Commission found that a subcontractor for the East Side Access project was involved with an organized crime family. The subcontractor, who had been hired to haul away the dirt from the excavation process, was replaced.[54]

In July 2011, after the tunnel boring machines finished drilling through the Grand Central station box, they were left in place under 38th Street and Park Avenue, as it was more economical than disassembling them in Queens and selling them for scrap, which could have added $9 million to the project's final cost.[55] The next step in construction was to make cast-in-place concrete sections to create the tunnel lining.[56] Each tunnel was 22 feet (7 meters) in diameter, with an average depth of 140 feet (43 m) beneath street level.[57]

In September 2014, the MTA opened a 2,400-square-foot (220 m2) pocket park, at 48 East 50th Street between Madison and Park Avenues, created along with a $97 million ventilation facility at that location. The pocket park, known as 50th Street Commons, has a capacity of 100 people standing, or 40 people sitting down.[58] The park, containing abundant greenery along a granite backdrop with tables and chairs,[59] was meant to reduce noise pollution from the ventilation facility, which also served as an emergency exit.[60][61]

 
Tracks being laid in the 63rd Street Tunnel

On October 26, 2015, a 1,920-square-foot (178 m2) seating area in Grand Central Terminal's lower-level dining concourse was closed in order to build structural framework that would allow for the construction of stairways and escalators between the concourse and new LIRR station. This was deemed a major milestone in the construction of East Side Access by Dr. Michael Horodniceanu, President of MTA Capital Construction.[62] On November 10, 2015, a groundbreaking ceremony was held to celebrate the emergence of the project into Grand Central Terminal.[63]

On January 27, 2016, the final major contract for the construction of East Side Access was awarded to Tutor Perini Corporation. The contract was for the construction of four railroad platforms and eight tracks for the new Grand Central Terminal.[64] The first tracks inside the 63rd Street Tunnel were laid in September 2017.[65] The pre-cast platforms inside Grand Central Terminal were completed in May 2018, followed by the completion of the tracks in August 2018. The MTA also started installing escalators between the lower concourse and the platform mezzanine. Beginning in April 2018, the MTA began conducting site tours of the project; it had given 35 tours by September 2018.[66]: 26  In advance of the planned deconstruction of 270 Park Avenue above East Side Access,[67] the MTA and 270 Park Avenue's owner JPMorgan Chase signed an agreement in July 2019, in which JPMorgan agreed to ensure that the deconstruction of 270 Park Avenue would not disrupt the timeline of East Side Access.[68]: 22 

Queens side edit

 
Construction site in Queens, nicknamed the "Q-tip," where tunnels under the Sunnyside Yard were launched and the connection under Northern Boulevard to the 63rd Street Tunnel was made

Previous work extending subway service through the upper level of the 63rd Street Tunnel to lines in Queens also extended the lower level to a point west of Northern Boulevard, across from the Sunnyside Yard.[69] Work in Queens included extending the tunnel under Northern Boulevard and boring four tunnels under Sunnyside Yard. This was a particularly delicate and expensive task because of the elevated BMT Astoria Line and the underground IND Queens Boulevard Line directly above. The existing tunnel bellmouth west of Northern Boulevard was expanded to serve as the staging area for the Manhattan work, bringing in workers, equipment and supplies, and bringing out the muck and debris from excavation.[70][71] A temporary narrow-gauge railway and a conveyor belt system were constructed behind the tunnel boring machines (TBMs) and through the 63rd Street Tunnels to the Queens bellmouth.[56] Due to its shape, the Queens work site was nicknamed the "Q-tip".[72]

Pile Foundation Construction Company built an $83 million cut structure, which extends the tracks under Northern Boulevard into the Sunnyside Yard. It created an area that served as the launch chamber for soft-bore Queens tunnels that would connect the 63rd Street line to the main LIRR branches, and an interlocking and emergency exit and venting facility. The cut was then covered with a deck.[73] In August 2009, Perini Corp. was awarded a $144 million contract to reconfigure the Harold Interlocking railway junction, increasing its capacity to accommodate trains bound for Grand Central Terminal, and to construct new yard lead tracks to allow trains to enter the storage yards.[44]: 24  Smaller contracts for structural work, environmental monitoring, and data measurement were also awarded.[44]: 21–23  Some Amtrak buildings in Sunnyside Yard were demolished to make room for the East Side Access portals in Queens.[44]: 24 

In September 2009, the MTA awarded Granite-Traylor-Frontiere Joint Venture a $659.2 million contract to use two custom-built 500-ton slurry TBMs to create the tunnels connecting the LIRR Main Line and the Port Washington Branch to the 63rd Street Tunnel under 41st Avenue.[44]: 23 [74] The four tunnels, with precast concrete liners, total 2 miles (3.2 km) in length.[75] The contract included a $58 million option to dig three tunnel pits and three emergency shafts and to complete an open cut.[44]: 23 [74] The TBMs, which could dig through several types of earth, were the first such machines to be used in the New York City area.[74]

The two TBMs began digging on the Queens side in April 2011.[76] On December 22, 2011, breakthrough was achieved in Tunnel "A" of the four Queens tunnel drives from the 63rd Street Tunnel bellmouth.[71] By July 25, 2012, all four Queens tunnel drives were complete.[49] In April 2014, contracts were awarded for the final modifications for the tunnels, as well as for communication systems.[77]

 
Rail laying for the Amtrak westbound bypass tunnel in Queens

The project also added two bypass tunnels for Amtrak trains within Harold Interlocking. While eastbound Amtrak trains to New England would be able to go through the interlocking without crossing the paths of East Side Access trains, westbound Amtrak trains to Penn Station would use tracks that intersected East Side Access tracks. East Side Access trains to Grand Central came from the east and would diverge to the northwest while Amtrak trains to Penn Station came from the north and would continue west, so the final environmental impact statement called for a bypass for westbound trains.[78] Around $295 million was allocated for the bypass in 2011,[79][80] and work on this project started in 2013.[81] However, by October 2015, the tunnels were behind schedule because Amtrak and the MTA could not cooperate on track access schedules.[82] These delays ultimately raised construction costs by almost $1 billion as of April 2018,[83] and in a report that month, the MTA attributed the delays to a lack of cooperation on Amtrak's part.[84]: 27–31  The work at Harold Interlocking also included the installation of a microprocessor-based signal system, replacing the old track circuit-based signal system.[85][86]

In July 2018, workers started realigning tracks to make way for the construction of the Queens tunnel portal, which was the final major contract not underway at the time.[87] The realignment of the three westbound Main Line and Port Washington Branch tracks, as well as the construction of a new eastbound Main Line track to replace an existing track, were completed by the end of summer 2018.[66]: 26  The last major construction contract—$60 million to move tracks in Harold Interlocking and build a tunnel portal structure for Tunnel B/C—was awarded to Skanska in October 2018.[88][89] Work on the tunnel structure was expected to run from mid-2019 to mid-2021.[90][91] Work on the Midday Storage Yard also progressed, and by 2019, tracks were being laid in the storage yard.[68]: 14–18, 23  The portal for Tunnel B/C was completed by early 2021,[92] and the yard was 99 percent complete by that May.[93]: 9 

Final work and opening edit

By May 2021, finishes were being placed in the station; the third rail, signals, and other right-of-way equipment were being tested.[93]: 9–10  On October 31, 2021, Governor Kathy Hochul rode the first passenger test train through the East Side Access tunnels to Grand Central Terminal.[94][95] In May 2022, MTA chairman Janno Lieber announced that the project was still scheduled for completion by the end of the year, and Hochul announced that the new station would be named "Grand Central Madison".[96][97] More extensive tests of operation and safety features (e.g., the positive train control system) were underway and were expected to be completed by the end of 2022.[98]

By late 2022, there were concerns that the project's completion could be delayed to March 2023.[99] At the time, the MTA had not yet activated the Advanced Civil Speed Enforcement System, which would automatically activate the brakes of oversized trains that attempted to enter the tunnels.[99][100] In addition, mass-transit ridership declined significantly following the onset of the COVID-19 pandemic in early 2020, and the LIRR's passenger numbers had not completely recovered more than two years later. Large amounts of office space in Midtown Manhattan were still vacant, although MTA officials expressed optimism that the completion of East Side Access would attract office workers back to Midtown.[101] The LIRR received operational control of the Grand Central Madison station on December 9, 2022, upon which the station and tracks became subject to Federal Railroad Administration regulations.[102][103] The Grand Central Madison station remained unopened two weeks later; MTA chairman Janno Lieber attributed the delays to a single ventilation fan that could not exhaust enough air.[104][105]

At the end of December 2022, the MTA postponed the station's opening to January 2023.[106][107] Early the next month, Lieber indicated that the station's opening could be postponed further to February 2023.[108][109] Non-revenue shuttle trains began running on January 11, 2023,[110] and the FRA said on January 19 that the LIRR had finished installing ACSES equipment in the tunnels.[111] On the evening of January 23, 2023, it was announced that the station would open on January 25;[112][113] the station opened as scheduled on that date, with the first train leaving Jamaica at 10:45 a.m.[114] The initial "Grand Central Direct" service ran only between Jamaica and Grand Central Madison, with trains alternatively skipping or serving all intermediate stops.[115][116] On February 8, 2023, the MTA announced that it would implement full service on February 27, with 296 daily trains operating to or from Grand Central Madison.[117]

Route edit

 
Starting point for the four Queens tunnels under Sunnyside Yard. The top three tunnels (Tunnels A, B/C, and D, from left to right) will connect to the LIRR Main Line, while the bottom tunnel will connect to storage and maintenance tracks.

Extending between Sunnyside Yard in Queens and Grand Central Terminal in Manhattan, the East Side Access project created an LIRR branch from its Main Line through new track connections at Harold Interlocking within Sunnyside Yard, and through the lower level of the existing 63rd Street Tunnel under the East River. A storage yard adjacent to Sunnyside Yard is also being built, connecting to the 63rd Street Tunnel via a loop. In Manhattan new tunnels begin at the western end of the 63rd Street Tunnel at Second Avenue, curving south under Park Avenue and entering a new LIRR terminal beneath Grand Central.[118] Excluding storage tunnels, the project is about 4 miles (6.4 km) long, consisting of 5,500 ft (1,700 m) of new route in Queens, 8,600 ft (2,600 m) of preexisting route under the 63rd Street Tunnel, and 7,200 ft (2,200 m) of new route in Manhattan.[119]: 8 

On the Queens side, four tunnels merge into two tracks and enter the lower level of the 63rd Street Tunnel. Three of them (Tunnels A, B/C, and D) connect to the busy Harold Interlocking, splitting off the Main Line. A fourth tunnel on a lower level connects to the Midday Storage Yard.[71] The Midday Storage Yard, located to the northwest of the existing Sunnyside Yard, comprises 33 acres (13 ha) and will contain 24 storage tracks once completed.[120] Tutor Perini is constructing the $291 million yard just south of the existing Harold Interlocking.[121]

The line fans out into a bi-level station under Grand Central Terminal with eight tracks, four on each level.[10] South of the station, the four tracks on each level merge into two 1,700-foot-long (520 m) storage tracks, with one in each cavern on each level. These storage tracks, which extend under Park Avenue south to 38th Street, are long enough to store one 1,020-foot-long (310 m), 12-car train. The storage tracks were not part of the original proposal, as they were added in a 2008 modification to the plans for East Side Access.[122]

The project also included the construction of several ventilation plants. One is located at 44th Street, near the Yale Club of New York City, while another is located at 50th Street east of Madison Avenue.[48]: 11 [123] Ventilation facilities are also located on Park Avenue at 38th Street and at 55th Street, as well as on 63rd Street at York Avenue and at 2nd Avenue.[123]

Station edit

 
Platform of the new terminal

The new LIRR terminal at Grand Central, located 14 stories below ground, has 350,000 square feet (33,000 m2) with four platforms and eight tracks, plus a new retail and dining concourse with 25 retail spaces. There are two caverns containing one platform and two tracks on each of two levels; a mezzanine is located between the two platform levels.[10][11] The LIRR terminal is accessed via stairwells, 22 elevators, and 47 escalators connecting to the existing food court at the lower level of Grand Central. The number of elevators in this terminal exceeds the 19 escalators in the remainder of the LIRR system combined.[47]

The MTA originally planned to build and open additional entrances at 44th, 45th, 47th, and 48th Streets.[28]: 3 [56][124]: 5  The station connects to existing entrances at Grand Central North. The LIRR station also contains entrances at 335 Madison Avenue, near the southeast corner with 44th Street; at 270 Park Avenue and 280 Park Avenue near 47th and 48th–49th Streets, respectively; and at 347 Madison Avenue, on the east side of the avenue at 45th Street. An entrance on 46th Street between Lexington and Park Avenue was also built, connecting with Grand Central North.[124]: 5–6  The MTA later announced its intent to defer construction of an entrance at 48th Street because the owner of 415 Madison Avenue wanted to undertake a major construction project on the site.[124]: 7  The MTA also connected the new station to the existing 47th Street cross-passage.[28]: 3 [56] The escalators are up to 180 feet (55 m) long and descend more than 90 feet (27 m). The escalators and elevators are among the few privately operated escalators and elevators in the entire MTA system.[47]

Service changes edit

Trains to Grand Central run 20 hours a day.[125] In 2015, plans called for 24 trains per hour to run to Grand Central during peak morning hours, with an estimated 162,000 passenger trips to and from Grand Central on an average weekday.[56][46][126]

Bilevel rail cars, such as the LIRR's DM30AC and C3 fleet, cannot serve Grand Central because their loading gauge is too large for the tunnel.[127]: 10–11 [128] Although M3 electric multiple units can fit in the 63rd Street Tunnel, the fleet is not compatible with the new line's safety and signaling systems. As a result, when East Side Access opened, about 22 percent of the LIRR's fleet was unable to serve Grand Central Madison.[129]

Timetable overhaul edit

In anticipation of the completion of East Side Access and related projects, in 2022, the MTA overhauled LIRR timetables for the first time in more than 30 years.[130] On June 2, 2022, the MTA released draft timetables[131][132] that LIRR president Catherine Rinaldi pronounced "revolutionary", saying, "In one stroke, we are increasing service by 40%."[131] The public was invited to comment on the proposed changes at a virtual public meeting on July 13, 2022;[131] after hundreds of people registered to speak, two more such meetings were added.[133] These meetings notwithstanding, MTA officials said in December that the late-June draft would be implemented when Grand Central Madison opened for full service.[134]

The revised timetables proposed a substantial increase in reverse-peak and off-peak service on most branches. This included half-hourly off-peak service on the Main Line to and from Ronkonkoma (increased from hourly) and hourly off-peak service on the West Hempstead Branch (increased from bihourly). Additionally, due to the simultaneous completion of the Main Line Third Track project, reverse-peak service gaps of over 90 minutes along the Main Line were eliminated.[b][130][136] Additionally, most branches received service to both Manhattan terminals, with a considerable increase in the total number of trains to and from Manhattan during peak hours.[131][136] The inconsistent service patterns of most branches were also restructured into simpler patterns with western zones (closer to New York City) and eastern zones (away from New York City).[137] The draft timetables called for more evenly spaced trains.[131][138]

The timetables were also designed to accommodate repairs to the East River Tunnels to Penn Station following damage from Hurricane Sandy in 2012. The reduction of tunnel capacity (from four to three operational tunnels) during renovation, resulting in the need to share additional track space with Amtrak and NJ Transit, was cited as a reason for reduction in service to Penn Station in the draft timetables. As of 2022, renovation work was expected to begin no earlier than 2024 and take about three years to complete.[139]

Critical reception edit

These changes have met generally positive reception for introducing additional flexibility to peak commuters, especially those traveling to the East Side, and facilitating the development of job centers on Long Island for reverse commuters.[140] In the June 2022 MTA board meeting, chairman Janno Lieber described increased reverse-peak service as having a "potential boom to Long Island's economy".[141]

Some proposed service changes were not well received.[138][140] The new timetables have been criticized for greatly reducing the amount of through service to Atlantic Terminal and not sufficiently augmenting peak service,[131][138] with some stations even seeing a slight reduction in peak service.[c] Additionally, reconfiguration of the track layout of Jamaica station will require Brooklyn-bound riders to perform up-and-over transfers to a new Platform F; this has been criticized as being much less convenient than cross-platform transfers, especially for disabled customers.[141][142] Riders have also criticized the elimination of timed connections at Jamaica, which will no longer be built into the schedule; the MTA claims that this change will reduce delays and allow more trains to run.[d][130] Some have stated that poorly-timed connections, especially to and from Brooklyn shuttles,[143][144] could lengthen their daily commutes by over 20 minutes.[144] Diesel branches[e] are also not slated to see considerably increased service, as noted by one blogger.[137] Despite this backlash, Lieber urged customers to "give it a chance" and declared that the MTA was "making no apologies" for the proposed service plan.[141]

On September 28, 2022, following backlash from customers, the MTA announced the restoration of three express trains serving Penn Station on the Port Washington Branch, which were initially cut from the draft timetables.[145] The February 2023 timetables were likewise met with mixed reception, with some commuters anticipating newfound flexibility, and others criticizing the MTA for not responding to community feedback on the draft timetables.[146] In particular, riders on the Oyster Bay Branch (a diesel-only branch) expressed concerns that the new schedules had eliminated direct transfers at the Jamaica station, thereby lengthening their commutes.[147]

Implementation of changes edit

A shuttle service, Grand Central Direct, operated between Grand Central Madison and Jamaica between January 25 and February 26, 2023. Grand Central Direct trains ran hourly during rush hours in the peak direction stopping at Woodside. Midday and weekend trains operated half-hourly, with one train making stops at Kew Gardens, Forest Hills, and Woodside, and one train running nonstop between Jamaica and Grand Central. On weekdays, the first train left Jamaica at 6:17 a.m., with the last train leaving Grand Central at 8:04 p.m.. Trains ran on weekends between 7 a.m. and 10 p.m.[1]

On February 8, 2023, the MTA announced that new timetables featuring full service to Grand Central Madison would come into effect on February 27, which were largely unchanged from the draft timetables released in June 2022.[146] Full service was implemented as scheduled on February 27, 2023.[148][149] After full service was implemented, many riders reported that their trains were delayed and overcrowded.[150][151] In particular, almost all commuters traveling to or from Brooklyn—who constituted 8 to 12 percent of morning rush-hour riders—had to transfer at Jamaica. These commuters reported that the new schedules either did not give them enough time to transfer, or forced them to wait for long periods.[150] In addition, although the MTA had predicted that 40 percent of riders would travel to Grand Central Madison, only 30 percent ended up doing so.[152] In response to these complaints, the MTA added trips and lengthened existing trains to and from Brooklyn,[153][154] and they also lengthened trains to and from Penn Station.[151] By November 2023, about two out of five LIRR commuters to Manhattan were traveling through Grand Central Madison.[155]

Impact edit

A primary goal of the project was to reduce travel time for LIRR passengers traveling to the East Side of Manhattan. The MTA expected passengers to save about 40 minutes during a typical round trip by using Grand Central Madison instead of Penn Station.[115][156] Shortly after Grand Central Madison opened, a reporter for Gothamist wrote that transferring from there to the Grand Central–42nd Street station on the IRT Lexington Avenue Line (4, ​5, ​6, and <6> trains) took 10 to 12 minutes on foot via escalators, roughly the same amount of time it took to travel from 34th Street–Penn Station to Grand Central–42nd Street using the IRT Broadway–Seventh Avenue Line and 42nd Street Shuttle.[157] The project was expected to add passengers on the already overcrowded IRT Lexington Avenue Line and on surface bus routes on the East Side; but to reduce the load on rush-hour E train service between Pennsylvania Station and Midtown East and 7 train service across the East River.[158]

In April 2023, the MTA detailed the effects of the opening of the station on subway ridership. Many fewer people traveled on the subway between the East Side and Penn Station: 31 percent fewer weekday trips between Grand Central and Penn Station, a 34 percent decline on the E train between the East 53rd Street corridor and Penn Station, and 42nd Street Shuttle ridership declined as well. But ridership on the subway from Grand Central to Upper Manhattan increased by 10 percent and ridership from Grand Central to Union Square, by 18 percent.[159]

LIRR customer satisfaction, which stood at 81 percent before East Side Access opened, decreased to 68 percent by May 2023, in part because of the loss of direct service to Atlantic Terminal and the discontinuation of timed transfers at Jamaica, an MTA study found.[160] In particular, satisfaction among Atlantic Branch riders had been halved, from 82 percent to 41 percent.[160][161]

Controversies edit

Costs and construction delays edit

The project's estimated cost has increased from $3.5 billion when first proposed[162] to $4.3 billion in 1999,[162][163][164] $5.3 billion in 2003,[83] $6.3 billion in 2004,[162][163][83][165] $7.2 billion in 2008,[83][50] $8.4 billion in 2012,[162][163][166] and either $9.7 billion[83] or $10.8 billion in 2014.[158][162] By 2017, the projected cost was either $12 billion[167] or $10.2 billion,[168] making it the most expensive construction project of its type in the world by either measure.[168][167] The MTA budgeted a total of $10.178 billion to the project over five 5-year capital programs, up to and including the 2015–2019 capital program. Of these, 27% are federal funds and the other 73% are local funds. As of November 2017, the MTA had spent $7.397 billion of the available funding.[169]: 40  As of April 2018, the project was expected to cost $11.1 billion, an increase from a previous estimate of $10.2 billion.[168][83][170] The project had $10.3 billion in funding, which allowed construction to continue through 2020.[11] The state legislature had to approve an additional $798 million to allow construction to be completed, but this had not been approved by late 2019.[171]

 
West cavern, seen in January 2014
 
Cavern in January 2013

The completion date for the project has also been pushed back multiple times. Once planned to be operational by 2009 at a cost of $4.3 billion,[172][158] East Side Access was then rescheduled to open in 2017,[173] 2016,[174] 2018,[175] 2019,[165] September 2023,[176] and then either December 2023[177] or late 2023.[65] However, by April 2018, the MTA was looking to start passenger service in December 2022, at an estimated cost of $11.1 billion.[168][83][84]: 36  As of July 2020, the MTA had a "target revenue service" date of May 2022 (whereupon construction would be essentially complete), while the line was planned to open to the public in December 2022.[119]: 13  The timeline was only slightly delayed due to the COVID-19 pandemic in New York City.[119]: 18  The opening was ultimately postponed to January 25, 2023.[115]

In 2012, the United States Department of Transportation (USDOT)'s Inspector General announced that it wanted an audit done on the project, after the USDOT learned of the fourteen-year delay in the completion date and the more-than-100% cost increase.[178][166] In 2015, the USDOT's Deputy Principal Assistant Inspector General for Auditing and Evaluation, Joseph W. Come, testified before the United States House Committee on Oversight and Government Reform's Subcommittee on Transportation and Public Assets. Come said that several New York City transportation projects also experienced significant delays and cost overruns. This was due to a variety of factors, such as fraud, poor management, and a lack of oversight.[179]

The New York Times reported in 2017 that the project was slated to become the most expensive of its kind in the world. With an estimated cost of $12 billion, or about $3.5 billion per mile ($2.2 billion per kilometer) of new tunnel, the East Side Access tunnels were seven times as expensive as comparable railroad tunnels in other countries.[167][170] Over the years, the projected cost of East Side Access had risen by billions of dollars due to unnecessary expenses. Contractors for the MTA were paid more than those working in other cities, even though that provided no construction benefits. Planning for East Side Access cost more than $2 billion, and planning for MTA projects in general also made up more of the cost than in other cities' projects. In addition, politicians and trade unions had forced the MTA to hire more workers than were needed. In 2010, an accountant had found that the project was hiring 200 extra workers, at a cost of $1,000 per worker per day, for no apparent reason.[167] The bidding process for MTA construction contracts also raised costs because, in some cases, only one or two contractors would bid on a project.[167][83] Similar construction projects in New York City, such as the Second Avenue Subway and 7 Subway Extension, had been more expensive than comparable projects elsewhere for the same reasons, even though other cities' transit systems faced similar, or greater, problems compared to the MTA.[167] Other delays were attributed to the fact that dozens of contracts, some of which conflicted with each other, were bid out separately. Cost increases also occurred due to changing the design while construction was underway; ordering components that were the wrong size; failing to cooperate with other transit agencies in Sunnyside Yard; and making infeasible construction-timeline estimates.[83]

In a bid to lower costs and reduce delays, in September 2018, the LIRR hired Arthur R. Troup, who previously held senior positions with Atlanta's and Washington, D.C.'s rapid transit systems, to lead the East Side Access project.[180][181]

Incidents and accidents edit

Several major accidents occurred during construction, and East Side Access has been cited for numerous safety violations.[182] In late 2011, a construction worker died after a tunnel collapsed.[182][183] In October 2014, a contractor who was digging wells on the Queens side accidentally punctured the subway tunnel underneath, grazing an F train with passengers inside.[184][185]

Associated projects edit

Arch Street Yard and Shop Facility edit

 
The Arch Street Yard and Shop, as visible from the 7 train window
 
The yards as visible from 21 st.
 
Street entrance

The Arch Street Yard and Shop is in Long Island City, near the Hunterspoint Avenue station.[186]: 249  The yard itself has been in use since at least 1910.[187] The Arch Street Facility includes tracks that were built on the right-of-way of the LIRR's former North Shore Branch. Although the branch formerly extended west to what is now the Gantry Plaza State Park on the East River shoreline,[186]: 252  the Arch Street Facility's storage tracks only extend as far as 11th Street, several blocks away from the river.[186]: 255 

The LIRR planned a maintenance facility in the yard as part of the East Side Access project.[188] The building was completed in either December 2004[189]: 4  or June 2005.[186]: 252  The $80.4 million facility was built using a mix of federal and non-federal funds.[189]: 4  The LIRR had built the Arch Street Facility in advance so it could test its then-new M7 cars. When the MTA planned the facility in 2002, it had anticipated that East Side Access would open in 2011 and that the Arch Street Shop could be used to maintain the LIRR fleet. It was thought that the Hillside Facility would not be able to maintain the expanded LIRR fleet on its own. However, after the East Side Access project was repeatedly delayed, the Arch Street Facility was ultimately leased and licensed for other uses.[189]: 5 

Just south of the Arch Street Yard, the Montauk Cutoff connected the Main Line to the Montauk Branch until it was decommissioned in 2015.[190] As part of East Side Access, a portion of the cutoff was demolished to make room for the Midday Storage Yard.[191][121]

New Sunnyside station edit

A new LIRR train station in Sunnyside on the west side of Queens Boulevard and Skillman Avenue[192][193]: 20–21  along the Northeast Corridor (which the LIRR uses to get into Pennsylvania Station) has been proposed, which would provide one-stop access for area residents to Midtown Manhattan.[194] The station would have two side platforms and one island platform, all of which would be able to accommodate 12-car trains.[193]: 20–21  In its 2015–2019 capital program, the MTA had budgeted $76.5 million for the construction of such a station [195] with a proposed start date in January 2021,[196] but then delayed any work until after the completion of East Side Access.[197]

Capacity increase edit

The East Side Access project, along with several readiness-improvement projects, will allow the LIRR to run 24 more twelve-car trains during rush hours. This will boost its rush-hour passenger capacity from 300,000 to 425,000 daily commuters, a 45% increase.[11]

Main Line third track edit

 
A bridge, built in October 2017 to accommodate a third track on the Main Line

Related to the MTA's East Side Access project is its long-planned widening of the two-track LIRR Main Line by adding a third track.[198][199] Completion of Main Line third track construction was assumed during East Side Access project planning and referenced in the original East Side Access environmental impact statement as necessary to support service level increases caused by adding service to and from Grand Central.[200] The MTA has said that it considers the Main Line third track an "essential" project to support East Side Access,[201] and that the Main Line third track will "complement the East Side Access megaproject, which is doubling the LIRR's capacity into Manhattan."[199]

The third track's construction was deferred indefinitely by the MTA in 2008 due to budget constraints.[198][202] In January 2016, Governor Cuomo and the MTA announced plans to restart construction of the Main Line third track.[198][199] In December 2017, the LIRR awarded a contract for the project to the consortium 3rd Track Constructors for $1.8 billion.[203][204][205] A groundbreaking ceremony for the third track project was held on September 5, 2018.[206][207] The third track opened in several phases[208] and was completed by October 2022.[209][210]

Readiness projects edit

Five "readiness projects" are also under construction across the LIRR system to handle the expanded peak-hour service planned when East Side Access opens. Together, they are expected to cost $495 million.[211][212][213]

The largest of these projects is at Jamaica station, where the MTA is re-configuring track layouts, installing high-speed switches, and adding a new Platform F for the Atlantic Branch.[214] The changes will allow the Atlantic Branch to function as a high-frequency shuttle service to Atlantic Terminal, and most trains from Long Island will proceed to either Long Island City station, Penn Station, or Grand Central via the Main Line.[215] The first phase of the project, including the new platform, was completed in 2021 at a cost of $380 million.[216]

Another project will add train storage capacity at two LIRR stations. A 1,700-foot (520 m) siding near Massapequa station on the Babylon Branch will be used to store trains that originate or terminate at the station, enabling more peak-hour service to and from Penn Station/Grand Central. It was originally planned for completion in April 2019,[213] though was delayed until June 2021.[217]: 57  The MTA is also extending Track 2 on the Port Washington Branch, which ends as a pocket track east of Great Neck station, eastward by 1,200 feet (370 m) so it can store two trainsets. Additionally, a new bridge was built at Colonial Road near the station; it opened in May 2016 and replaced a 114-year-old span.[218][219][220][221][222] The construction of the pocket track was originally scheduled for completion in December 2018 at a total cost of $45.2 million.[213] However, the completion date was pushed back several times;[223]: 60  as of November 2021, a tentative completion date of August 2022 was announced.[217]: 59  Following another delay,[224] construction of the extended pocket track was completed in December 2022.[225]

Finally, the MTA planned to expand two yards. The MTA expanded the rail yard along the Main Line/Ronkonkoma Branch next to Ronkonkoma station, increasing the number of tracks in the yard from 12 to 23.[226] The project was budgeted for $128 million.[213][227] Construction started in July 2017[228] and the expanded yard went into service in late 2020.[217]: 62 [223]: 62  Additionally, the Port Washington Yard, next to Port Washington station on the Port Washington Branch, was planned to be expanded to store two more ten-car trains. As of 2017, construction was scheduled to begin in late 2020 or early 2021 at a cost of $500,000.[213][229] However, this project met significant community opposition, primarily because of proposed reduction of parking spaces near the station.[230] As of September 2022, the MTA has not come to an agreement with the Town of North Hempstead,[223]: 65  resulting in the project being postponed indefinitely.[145][217]: 61 

New railcars edit

 
M9 railcars, which are being purchased before the opening of East Side Access

The LIRR also purchased up to 160 M9 cars to handle the increased passenger traffic expected with the opening of East Side Access. They are being paid for with federal grant money attached to the project.[231][11] Although the MTA had ordered the M9s as early as 2013, the contract was delayed several times.[129] As of June 2022, the delivery of M9s was almost three years behind schedule, reportedly due to supply chain issues and labor shortages. Only 132 of 202 cars in the base order have yet been delivered,[232][233] and the additional 160 M9As did not arrive before the opening of East Side Access.[234]: 35  The MTA thus reintroduced about 100 of the older M3 cars (which first entered service the mid-1980s) to provide the advertised additional service.[129][235] The M3s are slated to remain in service at least until the remaining M9s for fleet expansion are delivered.[235]

Penn Station Access edit

Redirecting LIRR trains from Penn Station to Grand Central Terminal frees up tracks and platforms at Penn. This new capacity, as well as track connections resulting from the East Side Access project, allows Metro-North Railroad trains on the New Haven Line to run to Penn Station via Amtrak's Hell Gate Bridge. Four new local Metro-North stations in the Bronx are planned as part of this project, at Co-op City, Morris Park, Parkchester, and Hunts Point. The MTA is constructing a second connection from the Metro-North's Hudson Line to Penn Station using Amtrak's West Side Line in Manhattan.[236] The Penn Station Access project will provide direct rides from Connecticut, Westchester County, the Lower Hudson Valley, and the Bronx to West Midtown; ease reverse-commuting from Manhattan and the Bronx to Westchester County, the Lower Hudson Valley, and Connecticut; and provide transportation service to areas of the Bronx without direct subway service.[237] In December 2021, it was announced that the project would be completed in 2027,[238] several years later than initially proposed.[239]

See also edit

KML is from Wikidata

Notes edit

  1. ^ For the full FEIS, see:
    • "East Side Access Final Environmental Impact Statement: Overview". mta.info. Metropolitan Transportation Authority. March 6, 2001. Retrieved February 2, 2018.
  2. ^ This includes the Main Line west of Hicksville and the Oyster Bay, Port Jefferson, and Ronkonkoma Branches. Prior to the opening of the third track, reverse-peak service was severely limited by the need to utilize both Main Line tracks in the peak direction during the busiest period of rush hour.[135]
  3. ^ This includes various stations on different branches,[137] as well as Penn Station, which will be served by 10 fewer AM peak trains.[131]
  4. ^ Until 2022, several trains going in the same direction have been scheduled to arrive at Jamaica at the same time, a system through which passengers had quick cross-platform transfers to reach their desired branch. Under the new system, connections will not be timed, requiring riders to wait an arbitrary amount of time for the next train to their destination.
  5. ^ The Oyster Bay Branch, Port Jefferson Branch east of Huntington, Montauk Branch east of Babylon, and Main Line east of Ronkonkoma

References edit

  1. ^ a b "Introducing special Grand Central Direct service". Metropolitan Transportation Authority. Retrieved January 23, 2022.
  2. ^ a b c d e f g h i "Chapter 1: Purpose and Need". East Side Access Environmental Impact Statement (PDF). MTA Capital Construction. March 2001. (PDF) from the original on March 4, 2016. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  3. ^ "Improvements That Are Planned for Subways" (PDF). The New York Times. March 24, 1954. from the original on August 8, 2022. Retrieved February 8, 2016.
  4. ^ Bennett, Charles G. (May 25, 1963). "61st St. Tunnel to Queens Sped" (PDF). The New York Times. p. 1. from the original on May 7, 2022. Retrieved October 20, 2011.
  5. ^ Bennett, Charles G. (January 15, 1965). "63d Street Tube Approved By City; Hearing Heated" (PDF). The New York Times. p. 1. from the original on May 7, 2022. Retrieved October 20, 2011.
  6. ^ "L.I.R.R. Will Run In Queens Tunnel; 3d Track In 63d St. Tube To Provide East Side Outlet" (PDF). The New York Times. April 28, 1966. ISSN 0362-4331. from the original on May 7, 2022. Retrieved February 1, 2018.
  7. ^ "Tunnel From Queens to 63d St. To Have 4 Tracks Instead of 3" (PDF). The New York Times. August 12, 1966. ISSN 0362-4331. from the original on May 7, 2022. Retrieved February 1, 2018.
  8. ^ a b "Full text of "Metropolitan transportation, a program for action. Report to Nelson A. Rockefeller, Governor of New York."". Internet Archive. November 7, 1967. Retrieved October 1, 2015.
  9. ^ a b * Bennett, Charles G. (February 29, 1968). "Transportation Funding Would Have 4 Sources; Plan's Financing Would Be Varied" (PDF). The New York Times. from the original on May 7, 2022. Retrieved October 11, 2015.
    • Witkin, Richard (February 29, 1968). "$2.9-Billion Transit Plan For New York Area Links Subways, Rails, Airports; 2-Phase Proposal Program By Governor Calls For $1.6-Billion In First 10 Years 2-Phase Proposal For Transit Given" (PDF). The New York Times. from the original on May 7, 2022. Retrieved October 11, 2015.
  10. ^ a b c d Dobnik, Verena (November 4, 2015). "Massive East Side Access Project Rolling On Under Grand Central". nbcnewyork.com. from the original on December 1, 2019. Retrieved January 19, 2016.
  11. ^ a b c d e f "East Side Access transforming the LIRR". Herald Community Newspapers. August 21, 2018. from the original on August 13, 2021. Retrieved September 23, 2018.
  12. ^ "Harbor Welcome Is Given Tube for Queens Subway". The New York Times. May 19, 1971. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 3, 2018.
  13. ^ Prial, Frank J. (August 30, 1971). "First Section of 63d St. Tunnel Lowered to Bottom of East River". The New York Times. ISSN 0362-4331. from the original on February 3, 2018. Retrieved December 25, 2016 – via The New York Times Archive.
  14. ^ Prial, Frank J. (March 14, 1972). "City's First Subway Tunnel in 40 Years Cut Through". The New York Times. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 3, 2018.
  15. ^ "To Break Ground For 63rd St., East River Tunnel" (PDF). New York Leader-Observer. November 20, 1969. p. 8. (PDF) from the original on December 16, 2018. Retrieved July 29, 2016 – via Fultonhistory.com.
  16. ^ "Governor Rockefeller and Mayor Lindsay Attend 'Holing Through' of 63d St. Tunnel". The New York Times. October 11, 1972. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 3, 2018.
  17. ^ a b Tolchin, Martin (June 7, 1973). "Grand Central Is Favored Over a 3d Ave. Terminal". The New York Times. ISSN 0362-4331. from the original on September 28, 2017. Retrieved December 25, 2016 – via The New York Times Archive.
  18. ^ a b Prial, Frank J. (July 8, 1973). "Turtle Bay Residents, Fighting M .T .A. Rail Plan, Heartened by Killing of Proposed Bridge Over Sound". The New York Times. ISSN 0362-4331. from the original on September 28, 2017. Retrieved December 25, 2016 – via The New York Times Archive.
  19. ^ Tolchin, Martin (June 15, 1973). "A 3d Ave Rail Terminal Foreseen by U.S. Official". The New York Times. from the original on September 28, 2017. Retrieved September 28, 2017.
  20. ^ Burks, Edward C. (1975). "L.I.R.R. Terminal Delayed by M.T.A." The New York Times. ISSN 0362-4331. from the original on February 5, 2018. Retrieved February 4, 2018.
  21. ^ "GRAND CENTRAL GETS VOTE AS L.I.R.R. SITE". The New York Times. July 9, 1977. from the original on December 25, 2018. Retrieved December 24, 2018.
  22. ^ a b c d Andelman, David A. (October 11, 1980). "Tunnel Project, Five Years Old, Won't Be Used". The New York Times. p. 25. from the original on July 22, 2018. Retrieved October 20, 2011.
  23. ^ Lorch, Donatella (October 29, 1989). "The 'Subway to Nowhere' Now Goes Somewhere". The New York Times. from the original on December 18, 2021. Retrieved October 20, 2011.
  24. ^ . October 19, 2002. Archived from the original on October 19, 2002. Retrieved September 18, 2016.
  25. ^ Silano, Louis G.; Shanbhag, Radmas (July 2000). "The Final Connection". Civil Engineering. Vol. 86, no. 7. pp. 56–61.
  26. ^ a b c d Neuman, William (May 11, 2007). "Awaiting Rock-Eating Beast, L.I.R.R. Tunnel Is Poised to Finish Trip to Grand Central". The New York Times. from the original on February 4, 2018. Retrieved February 3, 2018.
  27. ^ Kershaw, Sarah (December 17, 2001). "V Train Begins Service Today, Giving Queens Commuters Another Option". The New York Times. from the original on January 7, 2017. Retrieved February 3, 2018.
  28. ^ a b c d e f g h i "Appendix B: Upper Level Loop Analysis". East Side Access Modification to Environmental Impact Statement (PDF). MTA Capital Construction. April 2006. (PDF) from the original on August 25, 2014. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  29. ^ Perez-Pena, Richard (February 16, 1997). "Proposed L.I.R.R. Link To Grand Central Gains". The New York Times. from the original on February 3, 2018. Retrieved February 3, 2018.
  30. ^ Lueck, Thomas J. (September 26, 1999). "M.T.A. to Propose Spending Billions on Rail Expansion". The New York Times. from the original on February 3, 2018. Retrieved February 3, 2018.
  31. ^ a b c Record of Decisions (PDF). United States Department of Transportation; Federal Transit Administration; Metropolitan Transportation Authority. May 21, 2001. (PDF) from the original on May 20, 2017. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  32. ^ Ain, Stewart (December 23, 2001). "Pushing to Speed Up East Side Rail Link". The New York Times. ISSN 0362-4331. from the original on February 4, 2018. Retrieved February 3, 2018.
  33. ^ Luo, Michael (November 26, 2003). "Weighing Transit Possibilities, New Study Follows the Money". The New York Times. ISSN 0362-4331. from the original on February 4, 2018. Retrieved February 3, 2018.
  34. ^ Associated Press (February 4, 2002). "NY received $132 million under bin" (PDF). Salamanca Press. p. 5. (PDF) from the original on May 7, 2022. Retrieved July 29, 2016 – via Fultonhistory.com.
  35. ^ Urbina, Ian (November 20, 2004). "Plan to Connect L.I.R.R. to Grand Central Hits Snag". The New York Times. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 3, 2018.
  36. ^ Yates, Maura (February 10, 2005). "East Side Access Draws Opponents". The New York Sun. from the original on October 31, 2010. Retrieved January 9, 2010.
  37. ^ Chan, Sewell (March 30, 2005). "M.T.A. Continues to Favor Plan for a Midtown Ventilation Tower". The New York Times. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 3, 2018.
  38. ^ Chan, Sewell (December 7, 2005). "M.T.A. Scales Back Midtown Ventilation Project". The New York Times. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 3, 2018.
  39. ^ Chan, Sewell (October 25, 2005). "Stakes High for M.T.A. and City in Vote on $2.9 Billion Bond Act". The New York Times. ISSN 0362-4331. from the original on February 4, 2018. Retrieved February 3, 2018.
  40. ^ (PDF). New York State Board of Elections. November 8, 2008. Archived from the original (PDF) on December 3, 2018. Retrieved February 3, 2018.
  41. ^ (Press release). U.S. Department of Transportation. December 18, 2006. Archived from the original on January 3, 2007. Retrieved January 18, 2007.
  42. ^ L.I.R.R. Access to Grand Central. The New York Times (video). October 1, 2006. from the original on February 3, 2018. Retrieved February 3, 2018.
  43. ^ a b Cuza, Bobby (July 12, 2006). "MTA Takes Major Step Towards Completing East Side Access Plan". NY1.
  44. ^ a b c d e f g h i j k "East Side Access Quarterly Report Q3 2009" (PDF). Metropolitan Transportation Authority. September 2009. p. 16. (PDF) from the original on June 27, 2016. Retrieved February 5, 2018.
  45. ^ a b c d Sarkar, Subal; Mukherjee, Amitabha; Benslimane, Aomar (2004). "Rock Tunnelling with TBMs on the East Side Access Project a New Perspective". International Conference on Case Histories in Geotechnical Engineering. Vol. 13. Missouri University of Science and Technology. from the original on February 4, 2018. Retrieved February 3, 2018.
  46. ^ a b Harshbarger, Rebecca (November 4, 2015). "350-million-year-old rock pulverized for new rail tunnels". am New York. from the original on February 3, 2018. Retrieved February 2, 2018.
  47. ^ a b c Mann, Ted (April 26, 2012). "MTA Focuses on Ups, Downs". The Wall Street Journal. from the original on January 10, 2021. Retrieved August 5, 2016.
  48. ^ a b "Chapter 1: Purpose and Need". East Side Access Modification to Environmental Impact Statement (PDF). MTA Capital Construction. April 2006. (PDF) from the original on March 4, 2016. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  49. ^ a b "MTA Completes Tunnel Boring On East Side Access". CBS New York. July 26, 2012. from the original on February 3, 2018. Retrieved February 3, 2018.
  50. ^ a b c Neuman, William (July 18, 2008). "A 640-Ton Machine Drills a Long Island Rail Road Tunnel to Grand Central". The New York Times. ISSN 0362-4331. from the original on February 3, 2018. Retrieved February 4, 2018.
  51. ^ a b "East Side Access Tunnel Boring Machine Reaches Grand Central Terminal" (Press release). Metropolitan Transportation Authority. July 2, 2008. from the original on December 22, 2015. Retrieved January 9, 2010.
  52. ^ "MTA ESA Progress Map" April 8, 2014, at the Wayback Machine. Metropolitan Transportation Authority. Retrieved October 9, 2008.
  53. ^ "Geocomp Corporation Brochure" February 2, 2014, at the Wayback Machine (PDF). Geocomp Corporation.
  54. ^ Rashbaum, William K. (May 19, 2010). "M.T.A. Tunnel Job Loses Dirt Hauler Over Mob Ties". The New York Times. ISSN 0362-4331. from the original on February 5, 2018. Retrieved February 4, 2018.
  55. ^ Grynbaum, Michael M. (July 24, 2011). "Deep Below Park Avenue, a 200-Ton Drill at Rest". The New York Times. ISSN 0362-4331. from the original on February 20, 2017. Retrieved July 5, 2016.
  56. ^ a b c d e Ocean, Justin (November 4, 2015). "Inside the Massive New Rail Tunnels Beneath NYC's Grand Central". Bloomberg.com. from the original on February 4, 2018. Retrieved February 2, 2018.
  57. ^ (PDF). Metropolitan Transportation Authority. Archived from the original (PDF) on April 8, 2014. Retrieved April 7, 2014.
  58. ^ "50th Street Commons Pocket Park Opens as Part of East Side Access". Metropolitan Transportation Authority. September 16, 2014. from the original on September 19, 2014. Retrieved September 16, 2014.
  59. ^ "MTA opens "pocket park" on 50th Street". Newsday. September 17, 2014. from the original on September 17, 2014. Retrieved September 17, 2014.
  60. ^ "MTA Inaugurates New Pocket Park 'Oasis' in Midtown New York". Inhabitat New York City. September 17, 2014. from the original on September 19, 2014. Retrieved September 17, 2014.
  61. ^ . Gothamist. Archived from the original on September 19, 2014. Retrieved September 17, 2014.
  62. ^ "MTA | news | Milestone for East Side Access: Workers to Break Through Lower Level Floor To Build Housing for Escalators and Stairways to Future LIRR Concourse". www.mta.info. from the original on February 24, 2016. Retrieved February 17, 2016.
  63. ^ (PDF). mta.info. Metropolitan Transportation Authority. December 14, 2015. Archived from the original (PDF) on February 25, 2016. Retrieved February 17, 2016.
  64. ^ "MTA OK's contract for East Side Access". TimesLedger. from the original on February 14, 2016. Retrieved February 17, 2016.
  65. ^ a b "MTA starts laying track for long-awaited East Side access for LIRR commuters". Spectrum News NY1. September 25, 2017. from the original on February 3, 2018. Retrieved February 2, 2018.
  66. ^ a b "Capital Program Oversight Committee Meeting – September 2018" (PDF). mta.info. Metropolitan Transportation Authority. September 24, 2018. (PDF) from the original on September 23, 2018. Retrieved September 23, 2018.
  67. ^ Bagli, Charles V. (February 21, 2018). "Out With the Old Building, in With the New for JPMorgan Chase". The New York Times. ISSN 0362-4331. from the original on August 9, 2021. Retrieved February 22, 2018.
  68. ^ a b "Capital Program Oversight Committee Meeting" (PDF). Metropolitan Transportation Authority. July 22, 2019. (PDF) from the original on July 19, 2019. Retrieved January 19, 2019.
  69. ^ Final Environmental Impact Statement for the 63rd Street Line Connection to the Queens Boulevard Line. Queens, New York, New York: Metropolitan Transportation Authority, United States Department of Transportation, Federal Transit Administration. June 1992. from the original on June 18, 2017. Retrieved July 23, 2016.
  70. ^ Nasri, V.; Lee, W.S.; Rice, J. (2004). "Comparison of the predicted behavior of the Manhattan TBM launch shaft with the observed data, East Side Access Project, New York". North American Tunneling. Taylor & Francis. pp. 537–544. ISBN 978-1-4398-3375-9. from the original on May 22, 2020. Retrieved July 23, 2016.
  71. ^ a b c Metropolitan Transportation Authority. East Side Access 1/24/2012 Update. from the original on April 10, 2013. Retrieved May 8, 2012 – via YouTube.
  72. ^ "Risk Assessment Overview: ESA Queens Tunneling Program" (PDF). mta.info. MTA Capital Construction. September 26, 2011. p. 11. (PDF) from the original on November 7, 2016. Retrieved February 2, 2018.
  73. ^ "New York's Subway System Finally Starting Major Expansion" May 9, 2008, at the Wayback Machine. newyork.construction.com. May 2006 issue.
  74. ^ a b c "East Side Access – Queens Bored Tunnels & Structures". Engineering News-Record. June 1, 2010. from the original on July 12, 2019. Retrieved February 6, 2018.
  75. ^ . Construction Equipment. September 30, 2009. Archived from the original on December 25, 2009. Retrieved October 9, 2009.
  76. ^ . NY1. March 18, 2011. Archived from the original on August 25, 2011. Retrieved March 19, 2011.
  77. ^ Castillo, Alfonso (April 16, 2014). "MTA: Two key East Side Access contracts awarded". Newspaper. Newsday. from the original on April 22, 2014. Retrieved April 21, 2014.
  78. ^ "28". East Side Access in New York, Queens, and Bronx Counties, New York, and Nassau and Suffolk Counties, New York: Environmental Impact Statement (PDF). MTA Capital Construction. March 2001. p. 47. (PDF) from the original on March 15, 2018. Retrieved March 15, 2018. {{cite book}}: |work= ignored (help)
  79. ^ Colvin, Jill (May 9, 2011). . DNAinfo.com. Archived from the original on May 13, 2011. Retrieved May 13, 2011.
  80. ^ "New York Gets $354.4 Million For High-Speed Rail Projects". CBS New York. May 9, 2011. from the original on March 15, 2018. Retrieved March 15, 2018.
  81. ^ "East Side Access trackwork to speed LIRR and Amtrak trains". Railway Track & Structures. July 18, 2013. from the original on March 15, 2018. Retrieved March 15, 2018.
  82. ^ Castillo, Alfonso A. (October 3, 2015). "MTA 'megaproject' challenged by Amtrak". Newsday. from the original on March 15, 2018. Retrieved March 15, 2018.
  83. ^ a b c d e f g h i Castillo, Alfonso A. (April 15, 2018). "East Side Access price tag now stands at $11.2B". Newsday. from the original on April 15, 2018. Retrieved April 16, 2018.
  84. ^ a b "Capital Program Oversight Committee Meeting" (PDF). Metropolitan Transportation Authority. April 23, 2018. (PDF) from the original on April 21, 2018. Retrieved April 20, 2018.
  85. ^ Castillo, Alfonso A. (March 1, 2018). "MTA: Another snag for East Side Access project". Newsday. from the original on April 16, 2018. Retrieved April 16, 2018.
  86. ^ "LIRR to test upgraded signal system for East Side Access project. For Railroad Career Professionals". Progressive Railroading. April 5, 2018. from the original on April 16, 2018. Retrieved April 16, 2018.
  87. ^ "LIRR relocates tracks for Grand Central tunnel". Newsday. July 19, 2018. from the original on September 23, 2018. Retrieved September 23, 2018.
  88. ^ "Press Release – MTA Headquarters – MTA Awards Final Major Construction Contract for East Side Access". Metropolitan Transportation Authority. October 31, 2018. from the original on November 6, 2018. Retrieved November 6, 2018.
  89. ^ "EAST SIDE ACCESS: Bringing Long Island Rail Road Service to the East Side of Manhattan LIRR Committee Report" (PDF). Metropolitan Transportation Authority. November 13, 2018. (PDF) from the original on April 24, 2019. Retrieved November 20, 2018.
  90. ^ "Skanska Awarded Final Heavy Civil Contract for East Side Access". Tunnel Business Magazine. January 10, 2019. from the original on January 12, 2019. Retrieved January 12, 2019.
  91. ^ Walker, Ameena (January 11, 2019). "New $60M contract will bring delayed East Side Access closer to completion". Curbed NY. from the original on January 11, 2019. Retrieved January 12, 2019.
  92. ^ . A Modern LI. March 18, 2021. Archived from the original on November 14, 2022. Retrieved November 14, 2022.
  93. ^ a b "Capital Program Oversight Committee Meeting May 2021". Metropolitan Transportation Authority. May 26, 2021. from the original on May 26, 2021. Retrieved May 26, 2021.
  94. ^ Duggan, Kevin (October 31, 2021). "Test run: Hochul takes first LIRR ride to Grand Central a year ahead of East Side Access completion | amNewYork". www.amny.com. from the original on November 1, 2021. Retrieved November 1, 2021.
  95. ^ Fan, Christina (October 31, 2021). "East Side Access One Step Closer For Long Islanders As MTA Unveils 350,000 Square-Foot Terminal At Grand Central". CBS New York – Breaking News, Sports, Weather, Traffic And The Best of NY. from the original on November 1, 2021. Retrieved November 1, 2021.
  96. ^ Siff, Andrew; Vazquez, Jennifer (May 31, 2022). "East Side Access Terminal Gets New Name 'Grand Central Madison'". NBC New York. Retrieved May 31, 2022.
  97. ^ Duggan, Kevin (May 31, 2022). "East Side Access project, renamed 'Grand Central Madison,' will increase LIRR service by 40%, Hochul says". amNewYork. from the original on June 3, 2022. Retrieved May 31, 2022.
  98. ^ Stabile, Tom (May 11, 2022). "MTA Chugs Toward Finish Line In East Side Access Marathon". Engineering News-Record. from the original on August 8, 2022. Retrieved July 12, 2022.
  99. ^ a b Nessen, Stephen (November 8, 2022). "Key safety approval could delay MTA's long-stalled East Side Access project". Gothamist. Retrieved November 9, 2022.
  100. ^ Worrell, Carolina (October 24, 2022). "LIRR Seeks 'Temporary Relief' From FRA's Hazard Detectors Requirements". Railway Age. Retrieved November 9, 2022.
  101. ^ Hallum, Mark (November 9, 2022). "Grand Central-Long Island Connection Opening Amid Slumping Commuter Numbers". Commercial Observer. Retrieved November 10, 2022.
  102. ^ Brachfeld, Ben (December 11, 2022). "LIRR assumes operational control of Grand Central Madison, but still no opening date". amNewYork. Retrieved December 12, 2022.
  103. ^ Yanes, Darwin (December 11, 2022). "LIRR takes operational control of Grand Central Madison, MTA says". Newsday. Retrieved December 12, 2022.
  104. ^ Sanderson, Bill (December 21, 2022). "Balky ventilation fan last hurdle keeping LIRR trains from Grand Central". New York Daily News. Retrieved December 25, 2022.
  105. ^ Castillo, Alfonso A. (December 21, 2022). "MTA chairman Janno Lieber: East Side Access opening held up by exhaust fan". Newsday. Retrieved December 25, 2022.
  106. ^ Siff, Andrew (December 29, 2022). "Grand Central Madison Won't Open in 2022 – Here's Target Date for NYC's New LIRR Stop". NBC New York. Retrieved December 30, 2022.
  107. ^ Chayes, Matthew (December 29, 2022). "Grand Central Madison will not open in 2022, MTA says". Newsday. Retrieved December 30, 2022.
  108. ^ Castillo, Alfonso A. (January 11, 2023). "Deadline for connecting LIRR to Grand Central still not certain, transit chief says". Newsday. Retrieved January 12, 2023.
  109. ^ Nessen, Stephen (January 11, 2023). "MTA's East Side Access project delayed again due to vent problems". Gothamist. Retrieved January 12, 2023.
  110. ^ Nessen, Stephen (January 18, 2023). "Grand Central Madison is closed, but the MTA is running empty trains there anyway". Gothamist. Retrieved January 24, 2023.
  111. ^ Castillo, Alfonso A. (January 20, 2023). "Feds approve LIRR safety system for East Side Access". Newsday. Retrieved January 24, 2023.
  112. ^ Castillo, Alfonso A. (January 24, 2023). "LIRR Grand Central Madison service to begin on Wednesday". Newsday. Retrieved January 24, 2023.
  113. ^ Siff, Andrew (January 23, 2023). "NYC's New LIRR Stop at Grand Central Madison Set to Open This Week – What to Know". NBC New York. Retrieved January 24, 2023.
  114. ^ Castillo, Alfonso A. (January 24, 2023). "Grand Central Madison opens Wednesday, culmination of $11.1 billion East Side Access project". Newsday. Retrieved January 26, 2023.
  115. ^ a b c Ley, Ana (January 25, 2023). "L.I.R.R. Service to Grand Central Begins Today at Long Last". The New York Times. ISSN 0362-4331. Retrieved January 25, 2023.
  116. ^ Brachfeld, Ben (January 24, 2023). "FINALLY! Grand Central Madison station opens after decades of planning and construction". amNewYork. Retrieved January 27, 2023.
  117. ^ Simko-Bednarski, Evan (February 8, 2023). "Full LIRR service starting at Grand Central Terminal on Feb. 27". New York Daily News. Retrieved February 8, 2023.
  118. ^ "Capital Programs East Side Access". web.mta.info. Metropolitan Transportation Authority. from the original on February 3, 2018. Retrieved February 3, 2018.
  119. ^ a b c "Capital Program Oversight Committee Meeting". Metropolitan Transportation Authority. July 22, 2020. from the original on July 21, 2020. Retrieved July 21, 2020.
  120. ^ "East Side Access Newsletter" (PDF). nyc.gov. Winter 2018. p. 2. (PDF) from the original on September 26, 2018. Retrieved September 26, 2018.
  121. ^ a b Lancaster, Maggie (May 2, 2017). . Railway Track and Structures. Archived from the original on May 2, 2017. Retrieved February 5, 2018.
  122. ^ "MTA LIRR East Side Access Technical Memorandum Assessing Design Refinement: Tail Tracks Ventilation Plenum and Grate" (PDF). Metropolitan Transportation Authority. February 2008. p. 1. (PDF) from the original on August 22, 2014. Retrieved February 5, 2018.
  123. ^ a b "MTA awards contract for LIRR-Grand Central tunnel ventilation facility". New York Post. September 24, 2012. from the original on February 4, 2018. Retrieved February 3, 2018.
  124. ^ a b c "MTA LIRR East Side Access Environmental Re-Evaluation Consultation Form Review" (PDF). Metropolitan Transportation Authority. May 4, 2018. (PDF) from the original on February 7, 2019. Retrieved February 5, 2019.
  125. ^ "City Terminal − Grand Central". Metropolitan Transportation Authority. Retrieved February 27, 2022.
  126. ^ "ESA Facts & Figures" (PDF). mta.info. Metropolitan Transportation Authority. November 2, 2015. (PDF) from the original on February 25, 2016. Retrieved February 17, 2016.
  127. ^ "Chapter 28: Comments and Responses on the Draft Environmental Impact Statement". East Side Access Environmental Impact Statement (PDF). MTA Capital Construction. March 2001. (PDF) from the original on March 15, 2018. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  128. ^ Penner, Larry (January 6, 2020). "The Real Co$ts of LIRR East Side Access to Grand Central Terminal". Long Island Weekly. from the original on July 9, 2021. Retrieved June 14, 2022.
  129. ^ a b c "More than 20% of LIRR trains can't run in Grand Central Madison tunnel". Gothamist. March 14, 2023. Retrieved March 20, 2023.
  130. ^ a b c "Governor Hochul Announces New Long Island Rail Road Terminal in Midtown Manhattan Will Be Named Grand Central Madison". governor.ny.gov. May 31, 2022. from the original on June 3, 2022. Retrieved June 14, 2022.
  131. ^ a b c d e f g Castillo, Alfonso A. (June 3, 2022). "LIRR's issues Grand Central Madison draft timetables, with some critics". Newsday. from the original on June 12, 2022. Retrieved June 14, 2022.
  132. ^ "LIRR to Grand Central: Draft Schedules". mta.info. June 2, 2022. from the original on June 11, 2022. Retrieved June 14, 2022.
  133. ^ "LIRR Announces Additional Virtual Public Meetings On Proposed Schedule Changes". Port Washington News. August 4, 2022. Retrieved February 21, 2023.
  134. ^ Hoogensen, Finn (December 19, 2022). "LIRR to offer direct train between Grand Central Madison and Jamaica, Queens". PIX11. Retrieved December 22, 2022.
  135. ^ "Project Benefits". amodernli.com. from the original on July 27, 2021. Retrieved June 14, 2022.
  136. ^ a b Hoogensen, Finn (June 2, 2022). "Grand Central Madison: LIRR releases draft timetables for new terminal". PIX 11. Retrieved June 14, 2022.
  137. ^ a b c "East Side Access service plan proposes measly peak service increases". thelirrtoday.com. June 9, 2022. from the original on June 9, 2022. Retrieved June 14, 2022.
  138. ^ a b c Geberer, Ranaan (June 6, 2022). "LIRR's new Manhattan terminal means more trains from Brooklyn, but most will be Jamaica shuttles". Brooklyn Daily Eagle. from the original on June 14, 2022. Retrieved June 14, 2022.
  139. ^ Castillo, Alfonso A. (October 28, 2022). "Sandy-damaged tunnel repairs haven't begun, limiting LIRR service to Penn Station". Newsday. Retrieved October 30, 2022.
  140. ^ a b Genn, Adina (June 7, 2022). "East Side Access touted as economic game changer for LI". Long Island Business News. from the original on June 9, 2022. Retrieved June 14, 2022.
  141. ^ a b c Castillo, Alfonso A. (June 29, 2022). "MTA chairman making no 'apologies' for East Side Access plan". Newsday. from the original on June 29, 2022. Retrieved June 30, 2022.
  142. ^ "PCAC Press Release on LIRR East Side Access Proposed Service Plans: Calls For More Public Meetings and Participation Opportunities for Commuters" (Press release). Permanent Citizens Advisory Committee to the MTA. June 21, 2022. from the original on July 14, 2022. Retrieved June 30, 2022.
  143. ^ Castillo, Alfonso A. (May 25, 2019). "New amenitites coming to Jamaica station, but it might be bad marriage for Brooklyn". Newsday. from the original on June 14, 2022. Retrieved June 14, 2022.
  144. ^ a b Castillo, Alfonso A. (June 18, 2022). "LIRR commuters not pleased with proposed changes". Newsday. from the original on June 18, 2022. Retrieved June 18, 2022.
  145. ^ a b Kaplan, Anna M. (September 28, 2022). "Important LIRR Commuter Update: Express Trains Have Been Saved". nysenate.gov. Retrieved October 1, 2022.
  146. ^ a b Castillo, Alfonso A. (February 24, 2023). "LIRR riders await new Grand Central service with enthusiasm, trepidation". Newsday. Retrieved February 27, 2023.
  147. ^ Gusoff, Carolyn (February 24, 2023). "Frustrated Long Island Rail Road riders say new schedule will make commutes longer, less convenient". CBS News. Retrieved March 20, 2023.
  148. ^ "LIRR full service begins Monday, 2/27, at Grand Central Madison; train schedules to change". ABC7 New York. February 27, 2023. Retrieved February 27, 2023.
  149. ^ Castillo, Alfonso A. (February 26, 2023). "East Side Access completed, LIRR riders get full service to Grand Central Madison Monday". Newsday. Retrieved February 27, 2023.
  150. ^ a b Ley, Ana (March 3, 2023). "A Mad Dash as Commuters Deal With New L.I.R.R. Service". The New York Times. ISSN 0362-4331. Retrieved March 18, 2023.
  151. ^ a b Charles, Charline (March 2, 2023). "LIRR commuters complain of overcrowding, delays, after Grand Central Madison launch". PIX11. Retrieved March 18, 2023.
  152. ^ "LIRR making adjustments first week of full Grand Central Madison service". ABC7 New York. March 3, 2023. Retrieved March 18, 2023.
  153. ^ Brachfeld, Ben (March 5, 2023). "MTA adds more LIRR trains in Brooklyn, retools schedule amid chaotic rollout". amNewYork. Retrieved March 18, 2023.
  154. ^ "MTA adjusts LIRR Brooklyn schedule following unpopular East Side Access schedule changes". News 12 - The Bronx. March 6, 2023. Retrieved March 18, 2023.
  155. ^ Dias, John (November 1, 2023). "Long Island Rail Road seeing more commuters shift to Grand Central Madison following service changes". CBS New York. Retrieved January 15, 2024.
  156. ^ "Everything to know about Grand Central Madison". Crain's New York Business. January 25, 2023. Retrieved January 27, 2023.
  157. ^ Nessen, Stephen (January 26, 2023). "Grand Central Madison, 15 stories underground, saves LIRR riders little time compared to Penn Station commute". Gothamist. Retrieved January 27, 2023.
  158. ^ a b c Donohue, Pete (January 27, 2014). "MTA walks back targets on East Side Access yet again, completion now not expected until 2023". New York Daily News. from the original on March 5, 2014. Retrieved March 5, 2014.
  159. ^ "New York City Transit Key Performance Metrics April 2023". mta.info. Metropolitan Transportation Authority. April 21, 2023. Retrieved April 21, 2023.
  160. ^ a b Castillo, Alfonso A. (July 17, 2023). "LIRR rider satisfaction plummets after Grand Central Madison opening". Newsday. Retrieved July 18, 2023.
  161. ^ "LIRR satisfaction numbers dip in response to Grand Central Madison rollout". News 12 - Long Island. July 18, 2023. Retrieved July 18, 2023.
  162. ^ a b c d e Penner, Larry (February 26, 2016). "East Side Access wastes time and money". TimesLedger. from the original on February 5, 2018. Retrieved February 4, 2018.
  163. ^ a b c Hawkins, Andrew J. (November 5, 2015). "Inside New York City's East Side Access, the biggest transportation project in America". The Verge. from the original on February 4, 2018. Retrieved February 4, 2018.
  164. ^ . TimesLedger. Archived from the original on February 5, 2018. Retrieved February 4, 2018.
  165. ^ a b Taylor, Alan (February 22, 2013). "The Tunnels of NYC's East Side Access Project". The Atlantic. from the original on January 6, 2015. Retrieved February 4, 2018.
  166. ^ a b Moynihan, Colin (May 21, 2012). "L.I.R.R. East Side Access Plan to Need More Time and Money". The New York Times. ISSN 0362-4331. from the original on February 5, 2018. Retrieved February 4, 2018.
  167. ^ a b c d e f Rosenthal, Brian M. (December 28, 2017). "The Most Expensive Mile of Subway Track on Earth". The New York Times. ISSN 0362-4331. from the original on December 29, 2017. Retrieved December 29, 2017.
  168. ^ a b c d Siff, Andrew (April 16, 2018). "MTA Megaproject to Cost Almost $1B More Than Prior Estimate". NBC New York. from the original on April 17, 2018. Retrieved April 16, 2018.
  169. ^ (PDF). mta.info. Metropolitan Transportation Authority. December 11, 2017. Archived from the original (PDF) on February 5, 2018. Retrieved February 4, 2018.
  170. ^ a b "As Cost of Train Link Passes $11 Billion, M.T.A.'s Credibility Shrinks". The New York Times. April 25, 2018. from the original on October 4, 2018. Retrieved October 4, 2018.
  171. ^ Guse, Clayton (September 19, 2019). "MTA seeks another $798 million to finish East Side Access project long plagued by delays and rising costs". New York Daily News. from the original on July 21, 2020. Retrieved July 21, 2020.
  172. ^ Penner, Larry (May 27, 2021). "Digging deeper on the (very deep) East Side Access project". Empire Center for Public Policy. from the original on August 8, 2022. Retrieved June 1, 2022.
  173. ^ Donohue, Pete (July 21, 2009). "Second Avenue Subway Setback: New Hurdles Will Likely Push Phase One Completion from 2015 to 2017". Daily News. Retrieved January 9, 2010.
  174. ^ Redwine, Tina (July 7, 2011). . NY1. Archived from the original on July 10, 2011. Retrieved July 8, 2011.
  175. ^ Shutack, Jackie. . FiOS1. Archived from the original on July 9, 2014. Retrieved January 10, 2012 – via YouTube.
  176. ^ Castillo, Alfonso A. (January 27, 2014). "East Side Access completion date extended – again". Newsday. from the original on March 21, 2014. Retrieved March 5, 2014. The MTA's monumental East Side Access project to link the Long Island Rail Road to Grand Central Terminal could carry a price tag $2.6 billion over budget and not be completed until 2023, four years behind schedule, according to a new report.
  177. ^ "MTA and LIRR East Side Access cost and schedule continue to change". Metro US. August 10, 2017. from the original on February 4, 2018. Retrieved February 4, 2018.
  178. ^ Redwine, Tina (May 21, 2012). . NY1. Archived from the original on May 23, 2012. Retrieved May 24, 2012.
  179. ^ Come, Joseph W. (June 8, 2015). "Oversight of Major Transportation Projects: Opportunities To Apply Lessons Learned" (PDF). United States Department of Transportation. (PDF) from the original on June 12, 2017. Retrieved February 4, 2018.
  180. ^ Castillo, Alfonso A. (September 25, 2018). "New boss tagged for LIRR East Side Access project". Newsday. from the original on September 27, 2018. Retrieved September 27, 2018.
  181. ^ "MTA taps Troup for ESA". Railway Age. September 25, 2018. from the original on September 27, 2018. Retrieved September 27, 2018.
  182. ^ a b Kates, Brian (November 18, 2011). "Young sandhog dies in tunnel collapse". NY Daily News. from the original on February 4, 2018. Retrieved February 4, 2018.
  183. ^ Grynbaum, Michael M.; Haughney, Christine (November 19, 2011). "Sandhog Killed in Railroad Tunnel Accident". The New York Times. from the original on December 5, 2018. Retrieved December 5, 2018.
  184. ^ "MTA battling 'stupidity' on the East Side Access project". ABC7 New York. November 18, 2014. from the original on December 5, 2018. Retrieved December 5, 2018.
  185. ^ Donohue, Pete; Rosenberg, Eli; Otis, Ginger Adams (October 30, 2014). "Drill bit blunder in MTA's East Side Access project nearly cuts into occupied F train in Queens". nydailynews.com. from the original on December 5, 2018. Retrieved December 5, 2018.
  186. ^ a b c d "Transit and Railroad Yards: Queens". Inventory of Decking Opportunities Over Transportation Properties (PDF). New York City Department of City Planning. September 2008. (PDF) from the original on February 28, 2017. Retrieved February 5, 2018.
  187. ^ Correal, Annie (December 6, 2015). "In Long Island City, Now Arriving in No Man's Land". The New York Times. from the original on February 6, 2018. Retrieved February 5, 2018.
  188. ^ "Chapter 17: Construction and Construction Management". East Side Access Environmental Impact Statement (PDF). MTA Capital Construction. March 2001. (PDF) from the original on February 6, 2018. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  189. ^ a b c DiNapoli, Thomas P. (December 2017). "Utilization of the Arch Street Yard and Shop Facility" (PDF). New York State Office of the State Comptroller. (PDF) from the original on February 6, 2018. Retrieved February 5, 2018.
  190. ^ Kensinger, Nathan (December 3, 2015). "In Long Island City, a Community Seeks to Reclaim an Urban Wilderness". Curbed NY. from the original on February 7, 2018. Retrieved February 5, 2018.
  191. ^ "Capital Program Oversight Committee Meeting" (PDF). mta.info. Metropolitan Transportation Authority. April 17, 2017. pp. 65–66. (PDF) from the original on February 6, 2018. Retrieved August 31, 2017.
  192. ^ "East Side Access". Congresswoman Carolyn Maloney. from the original on February 6, 2018. Retrieved February 5, 2018.
  193. ^ a b "Chapter 2: Project Alternatives". East Side Access Environmental Impact Statement (PDF). MTA Capital Construction. March 2001. (PDF) from the original on February 6, 2018. Retrieved February 2, 2018. {{cite book}}: |work= ignored (help)
  194. ^ Vandam, Jeff (February 4, 2007). "An Enclave at Once Snug and Inclusive". The New York Times. from the original on April 11, 2011. Retrieved February 14, 2008. When the Long Island Rail Road's East Side Access project is completed in 2013, its trains, too, will go to Grand Central. Sunnyside's new station in the system will create a nonstop commute to Midtown.
  195. ^ "MTA Capital Program 2015–2019" (PDF). mta.info. Metropolitan Transportation Authority. July 31, 2017. p. 164. (PDF) from the original on January 10, 2021. Retrieved February 5, 2018.
  196. ^ "ESA RI: Sunnyside Station". mta.info. Metropolitan Transportation Authority. from the original on September 7, 2017. Retrieved February 5, 2018.
  197. ^ Stefan Revenboer (October 24, 2022). "The new Grand Central LIRR service will bypass Sunnyside, Queens". New York News.
  198. ^ a b c Fitzsimmons, Emma G. (January 5, 2016). "Cuomo Revives Long-Stalled Plan to Add Track to L.I.R.R." The New York Times. p. A18. from the original on January 7, 2016. Retrieved January 7, 2016.
  199. ^ a b c "LIRR Main Line Expansion Will Ease Commuting and Attract Businesses and Jobs" (Press release). Metropolitan Transportation Authority. January 5, 2016. from the original on January 19, 2016. Retrieved January 19, 2016.
  200. ^ 2013 Long Island Index Special Analysis: How the Long Island Rail Road Could Shape the Next Economy (PDF) (Report). 2013. (PDF) from the original on February 22, 2016. Retrieved January 19, 2016.
  201. ^ "Main Line Corridor Improvements Project Presentation" (PDF). Metropolitan Transportation Authority. (PDF) from the original on January 25, 2016. Retrieved January 7, 2016.
  202. ^ Nardiello, Carolyn (September 16, 2008). "Third-Track Plan Isn't Dead, L.I.R.R. Insists". The New York Times. from the original on April 19, 2015. Retrieved January 19, 2016.
  203. ^ Berger, Paul (December 13, 2017). "MTA Awards $1.8 Billion Contract to Expand Long Island Rail Road". The Wall Street Journal. from the original on January 25, 2018. Retrieved January 25, 2018.
  204. ^ Castillo, Alfonso A. (December 13, 2017). "MTA approves $1.9B contract to design, build LIRR 3rd track". Newsday. from the original on January 26, 2018. Retrieved January 25, 2018.
  205. ^ Klar, Rebecca (December 20, 2017). "MTA approves $1.8B contract for third track project". The Island Now. from the original on January 26, 2018. Retrieved January 25, 2018.
  206. ^ "LIRR Third Track Project Moving Forward Despite Concerns Of Residents". CBS New York. September 5, 2018. from the original on September 6, 2018. Retrieved September 6, 2018.
  207. ^ Rivoli, Dan (September 5, 2018). "Cuomo continues infrastructure tour with Long Island Rail Road groundbreaking". New York Daily News. from the original on September 6, 2018. Retrieved September 6, 2018.
  208. ^ "LIRR unveils 1st section of new express lane track". Yahoo! Sports. August 15, 2022. Retrieved August 15, 2022.
  209. ^ Duggan, Kevin (October 3, 2022). "'Third' time's the charm: MTA finishes $2.5 billion LIRR Third Track project". amNewYork. Retrieved October 15, 2022.
  210. ^ "LIRR Completes Third Track Project". Railway Age. October 4, 2022. Retrieved October 15, 2022.
  211. ^ Anuta, Joe; Newman, Philip (June 5, 2013). . TimesLedger. TimesLedger Newspapers. Archived from the original on May 25, 2018. Retrieved May 24, 2018.
  212. ^ "MTA Capital Program Oversight Meeting" (PDF). mta.info. Metropolitan Transportation Authority. January 2013. p. 8. (PDF) from the original on October 25, 2017. Retrieved May 24, 2018.
  213. ^ a b c
east, side, access, public, works, project, york, city, that, extended, long, island, rail, road, lirr, miles, from, main, line, queens, grand, central, madison, station, under, grand, central, terminal, manhattan, east, side, metropolitan, transportation, aut. East Side Access ESA is a public works project in New York City that extended the Long Island Rail Road LIRR two miles from its Main Line in Queens to the new Grand Central Madison station under Grand Central Terminal on Manhattan s East Side The Metropolitan Transportation Authority MTA project was originally scheduled to open in 2009 but was delayed by more than a decade The new station and tunnels opened with limited service to Jamaica station in Queens on January 25 2023 and full service began on February 27 2023 The estimated cost of the project rose nearly threefold from US 3 5 billion to US 11 1 billion as of April 2018 update making it one of the world s most expensive underground rail construction projects East Side AccessInteractive map Red and blue new tunnels Green existing 63rd Street Tunnel Points denote new stations OverviewStatusFull serviceOwnerMetropolitan Transportation AuthorityLocaleNew York CityTerminiSunnyside Yard Harold Interlocking Queens Grand Central Madison Manhattan Stations2WebsiteOfficial websiteServiceTypeCommuter railSystemLong Island Rail RoadServicesCity Terminal ZoneOperator s MTA Long Island Rail RoadRidership162 000 daily projected HistoryCommencedSeptember 2007 2007 09 OpenedJanuary 25 2023 2023 01 25 1 TechnicalLine length2 mi 3 2 km Track length6 1 mi 9 8 km Number of tracks2 8CharacterUndergroundTrack gauge4 ft 8 1 2 in 1 435 mm standard gaugeElectrificationThird rail 750 V DCRoute mapLegendEast River Northeast Corridorto BostonLIRR Main Lineto Greenport63rd Street SubwaySunnyside YardMetro North main line Harold Interlocking63rd Street Subway 63rd Street TunnelMidday Storage YardSunnysideArch Street YardHunterspoint AvenueGrand Central Montauk Branchto MontaukLong Island CityNEC amp LIRRto Penn Station East River TunnelsEast Side Access routeOther routesThis diagram viewtalkeditThe new LIRR terminal contains eight tracks and four platforms in a two level station 100 feet 30 5 m below street level It was built in conjunction with several other LIRR expansion projects including an additional track along parts of the Main Line The project was intended to remove or reduce the need for subway transfers for a large number of riders with jobs on the east side of Manhattan Previously the only Manhattan stop for trains from Long Island was Penn Station on the west side of the island East Side Access was based on transit plans from the 1950s though an LIRR terminal on Manhattan s East Side was first proposed in 1963 The planned LIRR line was included in the 1968 Program for Action of transit improvements in the New York City area Lack of funds prevented the construction of any part of the connection other than the 63rd Street Tunnel under the East River Plans for the LIRR connection were revived in the late 1990s The project received federal funding in 2006 and construction began the following year The tunnels on the Manhattan side were dug from 2007 to 2011 and the connecting tunnels on the Queens side were completed in 2012 Afterward work began on other facilities related to the line such as new platforms at Grand Central ventilation and ancillary buildings communication and utility systems and supporting rail infrastructure in Queens The project s completion was delayed several times during construction Contents 1 History 1 1 Origins 1 2 Plans stalled 1 3 Plans revived 1 4 Construction progress 1 4 1 Manhattan side 1 4 2 Queens side 1 5 Final work and opening 2 Route 3 Station 4 Service changes 4 1 Timetable overhaul 4 1 1 Critical reception 4 2 Implementation of changes 5 Impact 6 Controversies 6 1 Costs and construction delays 6 2 Incidents and accidents 7 Associated projects 7 1 Arch Street Yard and Shop Facility 7 2 New Sunnyside station 7 3 Capacity increase 7 3 1 Main Line third track 7 3 2 Readiness projects 7 4 New railcars 7 5 Penn Station Access 8 See also 9 Notes 10 References 11 External linksHistory editOrigins edit The East Side Access project was based on regional planning proposals that were first brought up in the 1950s 2 18 PDF p 21 In March 1954 the New York City Transit Authority NYCTA issued a 658 million construction program The proposal included a tunnel for the Second Avenue Subway which would cross the East River between 76th Street in Manhattan and Astoria in Queens before continuing onto the Long Island Rail Road LIRR s Main Line in Queens 3 The 76th Street tunnel proposal resurfaced in 1963 though the location of the tunnel was changed several times thereafter 4 In 1965 the NYCTA finally decided to build the subway tunnel at 63rd Street 5 The first proposals to bring LIRR service to a terminal in eastern Midtown Manhattan arose in 1963 2 17 PDF p 20 To facilitate planning for this terminal a third track was added to the plans for the 63rd Street subway tunnel in April 1966 The track would serve LIRR trains to east Midtown alleviating train traffic into Penn Station on Manhattan s west side while integrating the LIRR with the subway 6 A fourth track was added to the plans in August 1966 after it was determined that LIRR trains would be too large to run on subway tracks This amendment increased the number of LIRR tracks to two and provided segregated tracks for the LIRR and the subway 7 In February 1968 the NYCTA s parent company the Metropolitan Transportation Authority MTA released the Program for Action which proposed numerous improvements to subway railway and airport service in the New York metropolitan area The plan included a new LIRR terminal at a proposed Metropolitan Transportation Center at Third Avenue and 48th Street in East Midtown It also included connections to Grand Central Terminal with a new northern entrance leading to the center and the Second Avenue Subway among other transit services 8 5 9 The new LIRR line was to branch off from existing lines in Sunnyside Queens and enter Manhattan using the new two level 63rd Street Tunnel The upper level was to be used by the New York City Subway s 63rd Street lines and the lower level was to be used by the LIRR 9 According to renderings of the transportation center the mezzanine would be placed above four island platforms and eight tracks which would be split evenly across two levels 8 48 49 similar to the present terminal under Grand Central 10 11 nbsp A ventilation tower for the 63rd Street TunnelConstruction on the project began in 1969 2 17 PDF p 20 Four 38 foot square 12 m prefabricated sections of the 63rd Street Tunnel were constructed under the East River the first of which was delivered in May 1971 12 That first section was lowered into place on August 29 1971 13 and the last section was lowered on March 14 1972 14 The double deck 3 140 foot 960 m 15 tunnel under the East River was holed through on October 10 1972 with the separate sections of tunnels being connected 16 The estimated cost of the project was 341 million and the MTA applied for 227 million in Federal funds 17 Plans to build the Manhattan terminal in the Turtle Bay neighborhood were opposed by residents who feared it would change the neighborhood and bring traffic congestion 18 they suggested it be built at Grand Central instead 19 MTA officials countered that there were too many rail lines at Grand Central and that adding the LIRR would further strain the Lexington Avenue Line If it were on Third Avenue passengers would have been more inclined to use the Second Avenue Subway which was partially under construction at the time 18 On April 16 1973 a Federal directive directed New York State to consider expanding and modernizing Grand Central before building the new terminal under Third Avenue 17 Preliminary planning for the Metropolitan Transportation Center had been completed by January 1975 2 17 PDF p 20 20 Due to continued opposition to the Transportation Center a Grand Central Alternative was published in September 1976 It called for the LIRR to use Grand Central Terminal s lower level instead 2 18 PDF p 21 In 1977 the MTA s board of directors voted to use Grand Central as the terminal for the proposed LIRR route 21 Plans stalled edit Due to the 1975 New York City fiscal crisis the LIRR project was canceled long before the tunnel was completed The New York Times noted that the lower level of the 63rd Street Tunnel was still under construction by 1976 even though officials knew that the tunnel would never be used 22 Richard Ravitch the MTA chairman said that to stop the work was impossible or so costly as to make it impractical subsequent to the construction of the subway portion 22 The lower level of the 63rd Street Tunnel was completed along with the upper subway level 2 17 PDF p 20 22 The western end of the tunnel lay dormant under Second Avenue at 63rd Street for three decades By the time that construction on the LIRR tunnel level stopped the tunnel was built for a distance of 8 600 feet 2 600 m The 8 600 foot tunnel to nowhere was completed largely for structural reasons to support the subway tunnel above 22 The 63rd Street subway line and LIRR tunnel were completed as far as 29th Street in Long Island City Queens with the subway level of the tunnel opening in 1989 The LIRR tunnel remained unused beneath the subway tracks 23 In 1994 work began to extend the 63rd Street subway tunnel east to connect to the Queens Boulevard subway line the LIRR tunnel was also extended east under 41st Avenue in Queens to the west side of Northern Boulevard in Queens 24 25 The subway connector was opened to full time F train service in December 2001 26 27 Plans revived edit Plans were made in 1995 to bring LIRR service to East Midtown 28 3 although MTA officials declared that the LIRR East Side connection would not be completed within the next generation In 1997 U S Senator Al D Amato started asking for federal money to connect the LIRR to Grand Central New York Governor George Pataki had previously proposed completing the project but D Amato s support increased the likelihood that construction would actually begin At the time if everything went favorably the LIRR link could open by 2010 29 By that time the LIRR was the busiest commuter railroad in the United States with an average of 269 400 passengers each weekday in 1999 2 4 PDF p 7 As of 1998 there were almost 1 77 million jobs in Manhattan including an increasing number of white collar office jobs in East Midtown 2 7 PDF p 10 Penn Station on the West Side was operating at capacity due to a complex track interlocking and limited capacity in the East River Tunnels 2 8 PDF p 11 In 1999 the MTA proposed a 17 billion five year capital budget This budget included a 1 6 billion LIRR connection to Grand Central as well as several subway extensions 30 The project s final environmental impact assessment FEIS was released in March 2001 31 1 a The FEIS reviewed two key options for bringing LIRR service to Grand Central The first option was to connect the tunnels to the existing lower level at Grand Central while the second option was to build an entirely new station underneath it The MTA ultimately recommended the second option because it was cheaper and less disruptive to Metro North service 31 4 28 4 After reviewing the FEIS for two months the Federal Transit Administration FTA gave the project a favorable Record of Decision i e approved it 28 3 31 nbsp East Side Access Project Information CenterAfter the September 11 2001 attacks the MTA said it would accelerate the construction of East Side Access LIRR president Kenneth J Bauer said The incident of September 11 shows the importance of East Side Access to a greater degree If something happened at the East River tunnel you wouldn t be able to run trains to Penn Station 32 The MTA and Governor Pataki supported East Side Access and the Second Avenue Subway both of which involved building new railroad infrastructure on the East Side 33 In 2002 Congress allocated 132 million for infrastructure projects in New York State including 14 7 million for East Side Access 34 A final design for the project was approved in 2002 and the first properties for it were acquired in 2003 28 4 In 2004 some business owners in Midtown announced their opposition to a proposed 16 story ventilation building at 50th Street east of Madison Avenue They said that the building would cause pollution and that it could be vulnerable to terrorist attacks 35 Catholic Archbishop Cardinal Edward Egan of the Roman Catholic Archdiocese of New York worried about the effect on St Patrick s Cathedral which faced Fifth Avenue with its back on Madison Avenue north of 50th Street 36 At first MTA officials held fast to their plans 37 but after continued opposition they reduced the size of the building and moved the structure s cooling towers 38 Construction progress edit Funding for MTA capital projects such as East Side Access the Second Avenue Subway and the 7 Subway Extension were included in the Rebuild and Renew Transportation Bond Act of 2005 As part of this act the state would take on 2 9 billion in debt to issue bonds to fund these projects 39 Voters ultimately approved the bond issue by a margin of 55 to 44 40 The federal government committed to provide 2 6 billion to help build the project by signing a full funding grant agreement in December 2006 41 42 The construction contract for a 1 mile 1 6 km tunnel in Manhattan westward and southward from the dormant lower level of the 63rd Street Tunnel to the new 100 foot deep 30 m station beneath Grand Central Terminal was awarded in July 2006 The contract went to Dragados Judlau a joint American Spanish venture whose American headquarters were in College Point Queens close to the East Side Access site 43 44 10 The total contract award was 428 million 26 43 44 10 and used two large tunnel boring machines 26 After Hurricane Sandy flooded the East River Tunnels between Queens and Penn Station in 2012 officials prioritized the construction of East Side Access so that LIRR trains could be diverted to Grand Central allowing the East River Tunnels to be renovated 11 Manhattan side edit nbsp A tunnel cavern deep under Park Avenue to the north of the new LIRR station which now houses a switchWork on the Manhattan side included building a new 8 track train station with storage tracks extending to 38th Street 45 1 PDF p 2 28 3 North of the station the tunnels would connect to the 63rd Street Tunnel s lower level 45 1 PDF p 2 28 2 The new station would be housed in two gigantic caverns blasted out of the Manhattan schist rock formation under the station 46 45 3 PDF p 4 A three level structure was being built in each cavern with one 1 020 foot long 310 m train platform and two tracks each on the top and bottom levels A passenger concourse was being constructed between each cavern s upper and lower levels 28 3 10 An upper level concourse accessed by a series of stairs elevators and escalators 47 would replace ten tracks on the west side of Metro North s Madison Yard 48 3 The cavern structure is located under the Park Avenue Viaduct which surrounds Grand Central Terminal while the storage tracks are located under the Park Avenue Tunnel which is located south of Grand Central Terminal 45 6 PDF p 7 nbsp Construction of the station s upper concourse in the Grand Central Terminal s Madison Yard in May 2014 Two of the yard s tracks were kept in service during construction to bring in equipment and remove debris nbsp 50th Street Commons pocket parkThe track connections from the new station to the 63rd Street Tunnel were excavated using tunnel boring machines 49 The first machine was delivered in May 2007 26 Dragados Judlau created a launch chamber for the tunnel boring machines under Second Avenue at 63rd Street in Manhattan using a controlled drill and blast method then assembled and launched each 640 ton machine 50 The first tunnel boring machine was launched westbound then southbound from the 63rd Street Tunnel in September 2007 and it reached Grand Central Terminal in July 2008 51 The second machine began boring a parallel tunnel in December 2007 and had completed its tunnel at 37th Street on September 30 2008 50 52 Geocomp Corporation was hired to monitor the boring using a battery of instruments to record vibration ground settlement and any tilting or drift suffered by the tunnel boring machines The instruments include inclinometers extensometers seismographs observation wells dynamic strain gauges tilt meters and automated motorized total stations with prismatic targets 53 The tunnel boring machines bored an average of 50 feet 15 meters per day Cross connections between the tunnels were created under Park Avenue between 49th and 51st Streets by controlled drill and blast The work began in mid July 2008 and required between six and eight months to complete 51 In April 2008 the MTA awarded Dragados Judlau another contract The 506 million contract was for excavating caverns for the three level platform structures mezzanine escalators passageways and track crossovers 44 12 The MTA gave Gramercy Group Inc the 38 9 million contract to reconfigure part of Madison Yard in March 2009 44 14 In September 2009 the MTA awarded Yonkers Contracting Company a 40 8 million contract to demolish a building at 47 East 44th Street and construct a ventilation plant amp concourse entrance on the building site along with constructing a station entrance at an existing office tower at 245 Park Avenue at East 46th Street 44 16 Smaller contracts for electrical installations and structural repairs were also awarded in 2008 44 16 18 In 2010 the New York City Business Integrity Commission found that a subcontractor for the East Side Access project was involved with an organized crime family The subcontractor who had been hired to haul away the dirt from the excavation process was replaced 54 In July 2011 after the tunnel boring machines finished drilling through the Grand Central station box they were left in place under 38th Street and Park Avenue as it was more economical than disassembling them in Queens and selling them for scrap which could have added 9 million to the project s final cost 55 The next step in construction was to make cast in place concrete sections to create the tunnel lining 56 Each tunnel was 22 feet 7 meters in diameter with an average depth of 140 feet 43 m beneath street level 57 In September 2014 the MTA opened a 2 400 square foot 220 m2 pocket park at 48 East 50th Street between Madison and Park Avenues created along with a 97 million ventilation facility at that location The pocket park known as 50th Street Commons has a capacity of 100 people standing or 40 people sitting down 58 The park containing abundant greenery along a granite backdrop with tables and chairs 59 was meant to reduce noise pollution from the ventilation facility which also served as an emergency exit 60 61 nbsp Tracks being laid in the 63rd Street TunnelOn October 26 2015 a 1 920 square foot 178 m2 seating area in Grand Central Terminal s lower level dining concourse was closed in order to build structural framework that would allow for the construction of stairways and escalators between the concourse and new LIRR station This was deemed a major milestone in the construction of East Side Access by Dr Michael Horodniceanu President of MTA Capital Construction 62 On November 10 2015 a groundbreaking ceremony was held to celebrate the emergence of the project into Grand Central Terminal 63 On January 27 2016 the final major contract for the construction of East Side Access was awarded to Tutor Perini Corporation The contract was for the construction of four railroad platforms and eight tracks for the new Grand Central Terminal 64 The first tracks inside the 63rd Street Tunnel were laid in September 2017 65 The pre cast platforms inside Grand Central Terminal were completed in May 2018 followed by the completion of the tracks in August 2018 The MTA also started installing escalators between the lower concourse and the platform mezzanine Beginning in April 2018 the MTA began conducting site tours of the project it had given 35 tours by September 2018 66 26 In advance of the planned deconstruction of 270 Park Avenue above East Side Access 67 the MTA and 270 Park Avenue s owner JPMorgan Chase signed an agreement in July 2019 in which JPMorgan agreed to ensure that the deconstruction of 270 Park Avenue would not disrupt the timeline of East Side Access 68 22 Queens side edit nbsp Construction site in Queens nicknamed the Q tip where tunnels under the Sunnyside Yard were launched and the connection under Northern Boulevard to the 63rd Street Tunnel was madePrevious work extending subway service through the upper level of the 63rd Street Tunnel to lines in Queens also extended the lower level to a point west of Northern Boulevard across from the Sunnyside Yard 69 Work in Queens included extending the tunnel under Northern Boulevard and boring four tunnels under Sunnyside Yard This was a particularly delicate and expensive task because of the elevated BMT Astoria Line and the underground IND Queens Boulevard Line directly above The existing tunnel bellmouth west of Northern Boulevard was expanded to serve as the staging area for the Manhattan work bringing in workers equipment and supplies and bringing out the muck and debris from excavation 70 71 A temporary narrow gauge railway and a conveyor belt system were constructed behind the tunnel boring machines TBMs and through the 63rd Street Tunnels to the Queens bellmouth 56 Due to its shape the Queens work site was nicknamed the Q tip 72 Pile Foundation Construction Company built an 83 million cut structure which extends the tracks under Northern Boulevard into the Sunnyside Yard It created an area that served as the launch chamber for soft bore Queens tunnels that would connect the 63rd Street line to the main LIRR branches and an interlocking and emergency exit and venting facility The cut was then covered with a deck 73 In August 2009 Perini Corp was awarded a 144 million contract to reconfigure the Harold Interlocking railway junction increasing its capacity to accommodate trains bound for Grand Central Terminal and to construct new yard lead tracks to allow trains to enter the storage yards 44 24 Smaller contracts for structural work environmental monitoring and data measurement were also awarded 44 21 23 Some Amtrak buildings in Sunnyside Yard were demolished to make room for the East Side Access portals in Queens 44 24 In September 2009 the MTA awarded Granite Traylor Frontiere Joint Venture a 659 2 million contract to use two custom built 500 ton slurry TBMs to create the tunnels connecting the LIRR Main Line and the Port Washington Branch to the 63rd Street Tunnel under 41st Avenue 44 23 74 The four tunnels with precast concrete liners total 2 miles 3 2 km in length 75 The contract included a 58 million option to dig three tunnel pits and three emergency shafts and to complete an open cut 44 23 74 The TBMs which could dig through several types of earth were the first such machines to be used in the New York City area 74 The two TBMs began digging on the Queens side in April 2011 76 On December 22 2011 breakthrough was achieved in Tunnel A of the four Queens tunnel drives from the 63rd Street Tunnel bellmouth 71 By July 25 2012 all four Queens tunnel drives were complete 49 In April 2014 contracts were awarded for the final modifications for the tunnels as well as for communication systems 77 nbsp Rail laying for the Amtrak westbound bypass tunnel in QueensThe project also added two bypass tunnels for Amtrak trains within Harold Interlocking While eastbound Amtrak trains to New England would be able to go through the interlocking without crossing the paths of East Side Access trains westbound Amtrak trains to Penn Station would use tracks that intersected East Side Access tracks East Side Access trains to Grand Central came from the east and would diverge to the northwest while Amtrak trains to Penn Station came from the north and would continue west so the final environmental impact statement called for a bypass for westbound trains 78 Around 295 million was allocated for the bypass in 2011 79 80 and work on this project started in 2013 81 However by October 2015 the tunnels were behind schedule because Amtrak and the MTA could not cooperate on track access schedules 82 These delays ultimately raised construction costs by almost 1 billion as of April 2018 83 and in a report that month the MTA attributed the delays to a lack of cooperation on Amtrak s part 84 27 31 The work at Harold Interlocking also included the installation of a microprocessor based signal system replacing the old track circuit based signal system 85 86 In July 2018 workers started realigning tracks to make way for the construction of the Queens tunnel portal which was the final major contract not underway at the time 87 The realignment of the three westbound Main Line and Port Washington Branch tracks as well as the construction of a new eastbound Main Line track to replace an existing track were completed by the end of summer 2018 66 26 The last major construction contract 60 million to move tracks in Harold Interlocking and build a tunnel portal structure for Tunnel B C was awarded to Skanska in October 2018 88 89 Work on the tunnel structure was expected to run from mid 2019 to mid 2021 90 91 Work on the Midday Storage Yard also progressed and by 2019 tracks were being laid in the storage yard 68 14 18 23 The portal for Tunnel B C was completed by early 2021 92 and the yard was 99 percent complete by that May 93 9 Final work and opening edit By May 2021 finishes were being placed in the station the third rail signals and other right of way equipment were being tested 93 9 10 On October 31 2021 Governor Kathy Hochul rode the first passenger test train through the East Side Access tunnels to Grand Central Terminal 94 95 In May 2022 MTA chairman Janno Lieber announced that the project was still scheduled for completion by the end of the year and Hochul announced that the new station would be named Grand Central Madison 96 97 More extensive tests of operation and safety features e g the positive train control system were underway and were expected to be completed by the end of 2022 98 By late 2022 there were concerns that the project s completion could be delayed to March 2023 99 At the time the MTA had not yet activated the Advanced Civil Speed Enforcement System which would automatically activate the brakes of oversized trains that attempted to enter the tunnels 99 100 In addition mass transit ridership declined significantly following the onset of the COVID 19 pandemic in early 2020 and the LIRR s passenger numbers had not completely recovered more than two years later Large amounts of office space in Midtown Manhattan were still vacant although MTA officials expressed optimism that the completion of East Side Access would attract office workers back to Midtown 101 The LIRR received operational control of the Grand Central Madison station on December 9 2022 upon which the station and tracks became subject to Federal Railroad Administration regulations 102 103 The Grand Central Madison station remained unopened two weeks later MTA chairman Janno Lieber attributed the delays to a single ventilation fan that could not exhaust enough air 104 105 At the end of December 2022 the MTA postponed the station s opening to January 2023 106 107 Early the next month Lieber indicated that the station s opening could be postponed further to February 2023 108 109 Non revenue shuttle trains began running on January 11 2023 110 and the FRA said on January 19 that the LIRR had finished installing ACSES equipment in the tunnels 111 On the evening of January 23 2023 it was announced that the station would open on January 25 112 113 the station opened as scheduled on that date with the first train leaving Jamaica at 10 45 a m 114 The initial Grand Central Direct service ran only between Jamaica and Grand Central Madison with trains alternatively skipping or serving all intermediate stops 115 116 On February 8 2023 the MTA announced that it would implement full service on February 27 with 296 daily trains operating to or from Grand Central Madison 117 Route edit nbsp Starting point for the four Queens tunnels under Sunnyside Yard The top three tunnels Tunnels A B C and D from left to right will connect to the LIRR Main Line while the bottom tunnel will connect to storage and maintenance tracks Extending between Sunnyside Yard in Queens and Grand Central Terminal in Manhattan the East Side Access project created an LIRR branch from its Main Line through new track connections at Harold Interlocking within Sunnyside Yard and through the lower level of the existing 63rd Street Tunnel under the East River A storage yard adjacent to Sunnyside Yard is also being built connecting to the 63rd Street Tunnel via a loop In Manhattan new tunnels begin at the western end of the 63rd Street Tunnel at Second Avenue curving south under Park Avenue and entering a new LIRR terminal beneath Grand Central 118 Excluding storage tunnels the project is about 4 miles 6 4 km long consisting of 5 500 ft 1 700 m of new route in Queens 8 600 ft 2 600 m of preexisting route under the 63rd Street Tunnel and 7 200 ft 2 200 m of new route in Manhattan 119 8 On the Queens side four tunnels merge into two tracks and enter the lower level of the 63rd Street Tunnel Three of them Tunnels A B C and D connect to the busy Harold Interlocking splitting off the Main Line A fourth tunnel on a lower level connects to the Midday Storage Yard 71 The Midday Storage Yard located to the northwest of the existing Sunnyside Yard comprises 33 acres 13 ha and will contain 24 storage tracks once completed 120 Tutor Perini is constructing the 291 million yard just south of the existing Harold Interlocking 121 The line fans out into a bi level station under Grand Central Terminal with eight tracks four on each level 10 South of the station the four tracks on each level merge into two 1 700 foot long 520 m storage tracks with one in each cavern on each level These storage tracks which extend under Park Avenue south to 38th Street are long enough to store one 1 020 foot long 310 m 12 car train The storage tracks were not part of the original proposal as they were added in a 2008 modification to the plans for East Side Access 122 The project also included the construction of several ventilation plants One is located at 44th Street near the Yale Club of New York City while another is located at 50th Street east of Madison Avenue 48 11 123 Ventilation facilities are also located on Park Avenue at 38th Street and at 55th Street as well as on 63rd Street at York Avenue and at 2nd Avenue 123 Station editMain article Grand Central Madison station nbsp Platform of the new terminalThe new LIRR terminal at Grand Central located 14 stories below ground has 350 000 square feet 33 000 m2 with four platforms and eight tracks plus a new retail and dining concourse with 25 retail spaces There are two caverns containing one platform and two tracks on each of two levels a mezzanine is located between the two platform levels 10 11 The LIRR terminal is accessed via stairwells 22 elevators and 47 escalators connecting to the existing food court at the lower level of Grand Central The number of elevators in this terminal exceeds the 19 escalators in the remainder of the LIRR system combined 47 The MTA originally planned to build and open additional entrances at 44th 45th 47th and 48th Streets 28 3 56 124 5 The station connects to existing entrances at Grand Central North The LIRR station also contains entrances at 335 Madison Avenue near the southeast corner with 44th Street at 270 Park Avenue and 280 Park Avenue near 47th and 48th 49th Streets respectively and at 347 Madison Avenue on the east side of the avenue at 45th Street An entrance on 46th Street between Lexington and Park Avenue was also built connecting with Grand Central North 124 5 6 The MTA later announced its intent to defer construction of an entrance at 48th Street because the owner of 415 Madison Avenue wanted to undertake a major construction project on the site 124 7 The MTA also connected the new station to the existing 47th Street cross passage 28 3 56 The escalators are up to 180 feet 55 m long and descend more than 90 feet 27 m The escalators and elevators are among the few privately operated escalators and elevators in the entire MTA system 47 Service changes editTrains to Grand Central run 20 hours a day 125 In 2015 update plans called for 24 trains per hour to run to Grand Central during peak morning hours with an estimated 162 000 passenger trips to and from Grand Central on an average weekday 56 46 126 Bilevel rail cars such as the LIRR s DM30AC and C3 fleet cannot serve Grand Central because their loading gauge is too large for the tunnel 127 10 11 128 Although M3 electric multiple units can fit in the 63rd Street Tunnel the fleet is not compatible with the new line s safety and signaling systems As a result when East Side Access opened about 22 percent of the LIRR s fleet was unable to serve Grand Central Madison 129 Timetable overhaul edit In anticipation of the completion of East Side Access and related projects in 2022 the MTA overhauled LIRR timetables for the first time in more than 30 years 130 On June 2 2022 the MTA released draft timetables 131 132 that LIRR president Catherine Rinaldi pronounced revolutionary saying In one stroke we are increasing service by 40 131 The public was invited to comment on the proposed changes at a virtual public meeting on July 13 2022 131 after hundreds of people registered to speak two more such meetings were added 133 These meetings notwithstanding MTA officials said in December that the late June draft would be implemented when Grand Central Madison opened for full service 134 The revised timetables proposed a substantial increase in reverse peak and off peak service on most branches This included half hourly off peak service on the Main Line to and from Ronkonkoma increased from hourly and hourly off peak service on the West Hempstead Branch increased from bihourly Additionally due to the simultaneous completion of the Main Line Third Track project reverse peak service gaps of over 90 minutes along the Main Line were eliminated b 130 136 Additionally most branches received service to both Manhattan terminals with a considerable increase in the total number of trains to and from Manhattan during peak hours 131 136 The inconsistent service patterns of most branches were also restructured into simpler patterns with western zones closer to New York City and eastern zones away from New York City 137 The draft timetables called for more evenly spaced trains 131 138 The timetables were also designed to accommodate repairs to the East River Tunnels to Penn Station following damage from Hurricane Sandy in 2012 The reduction of tunnel capacity from four to three operational tunnels during renovation resulting in the need to share additional track space with Amtrak and NJ Transit was cited as a reason for reduction in service to Penn Station in the draft timetables As of 2022 update renovation work was expected to begin no earlier than 2024 and take about three years to complete 139 Critical reception edit These changes have met generally positive reception for introducing additional flexibility to peak commuters especially those traveling to the East Side and facilitating the development of job centers on Long Island for reverse commuters 140 In the June 2022 MTA board meeting chairman Janno Lieber described increased reverse peak service as having a potential boom to Long Island s economy 141 Some proposed service changes were not well received 138 140 The new timetables have been criticized for greatly reducing the amount of through service to Atlantic Terminal and not sufficiently augmenting peak service 131 138 with some stations even seeing a slight reduction in peak service c Additionally reconfiguration of the track layout of Jamaica station will require Brooklyn bound riders to perform up and over transfers to a new Platform F this has been criticized as being much less convenient than cross platform transfers especially for disabled customers 141 142 Riders have also criticized the elimination of timed connections at Jamaica which will no longer be built into the schedule the MTA claims that this change will reduce delays and allow more trains to run d 130 Some have stated that poorly timed connections especially to and from Brooklyn shuttles 143 144 could lengthen their daily commutes by over 20 minutes 144 Diesel branches e are also not slated to see considerably increased service as noted by one blogger 137 Despite this backlash Lieber urged customers to give it a chance and declared that the MTA was making no apologies for the proposed service plan 141 On September 28 2022 following backlash from customers the MTA announced the restoration of three express trains serving Penn Station on the Port Washington Branch which were initially cut from the draft timetables 145 The February 2023 timetables were likewise met with mixed reception with some commuters anticipating newfound flexibility and others criticizing the MTA for not responding to community feedback on the draft timetables 146 In particular riders on the Oyster Bay Branch a diesel only branch expressed concerns that the new schedules had eliminated direct transfers at the Jamaica station thereby lengthening their commutes 147 Implementation of changes edit A shuttle service Grand Central Direct operated between Grand Central Madison and Jamaica between January 25 and February 26 2023 Grand Central Direct trains ran hourly during rush hours in the peak direction stopping at Woodside Midday and weekend trains operated half hourly with one train making stops at Kew Gardens Forest Hills and Woodside and one train running nonstop between Jamaica and Grand Central On weekdays the first train left Jamaica at 6 17 a m with the last train leaving Grand Central at 8 04 p m Trains ran on weekends between 7 a m and 10 p m 1 On February 8 2023 the MTA announced that new timetables featuring full service to Grand Central Madison would come into effect on February 27 which were largely unchanged from the draft timetables released in June 2022 146 Full service was implemented as scheduled on February 27 2023 148 149 After full service was implemented many riders reported that their trains were delayed and overcrowded 150 151 In particular almost all commuters traveling to or from Brooklyn who constituted 8 to 12 percent of morning rush hour riders had to transfer at Jamaica These commuters reported that the new schedules either did not give them enough time to transfer or forced them to wait for long periods 150 In addition although the MTA had predicted that 40 percent of riders would travel to Grand Central Madison only 30 percent ended up doing so 152 In response to these complaints the MTA added trips and lengthened existing trains to and from Brooklyn 153 154 and they also lengthened trains to and from Penn Station 151 By November 2023 about two out of five LIRR commuters to Manhattan were traveling through Grand Central Madison 155 Impact editA primary goal of the project was to reduce travel time for LIRR passengers traveling to the East Side of Manhattan The MTA expected passengers to save about 40 minutes during a typical round trip by using Grand Central Madison instead of Penn Station 115 156 Shortly after Grand Central Madison opened a reporter for Gothamist wrote that transferring from there to the Grand Central 42nd Street station on the IRT Lexington Avenue Line 4 5 6 and lt 6 gt trains took 10 to 12 minutes on foot via escalators roughly the same amount of time it took to travel from 34th Street Penn Station to Grand Central 42nd Street using the IRT Broadway Seventh Avenue Line and 42nd Street Shuttle 157 The project was expected to add passengers on the already overcrowded IRT Lexington Avenue Line and on surface bus routes on the East Side but to reduce the load on rush hour E train service between Pennsylvania Station and Midtown East and 7 train service across the East River 158 In April 2023 the MTA detailed the effects of the opening of the station on subway ridership Many fewer people traveled on the subway between the East Side and Penn Station 31 percent fewer weekday trips between Grand Central and Penn Station a 34 percent decline on the E train between the East 53rd Street corridor and Penn Station and 42nd Street Shuttle ridership declined as well But ridership on the subway from Grand Central to Upper Manhattan increased by 10 percent and ridership from Grand Central to Union Square by 18 percent 159 LIRR customer satisfaction which stood at 81 percent before East Side Access opened decreased to 68 percent by May 2023 in part because of the loss of direct service to Atlantic Terminal and the discontinuation of timed transfers at Jamaica an MTA study found 160 In particular satisfaction among Atlantic Branch riders had been halved from 82 percent to 41 percent 160 161 Controversies editCosts and construction delays edit The project s estimated cost has increased from 3 5 billion when first proposed 162 to 4 3 billion in 1999 162 163 164 5 3 billion in 2003 83 6 3 billion in 2004 162 163 83 165 7 2 billion in 2008 83 50 8 4 billion in 2012 162 163 166 and either 9 7 billion 83 or 10 8 billion in 2014 158 162 By 2017 the projected cost was either 12 billion 167 or 10 2 billion 168 making it the most expensive construction project of its type in the world by either measure 168 167 The MTA budgeted a total of 10 178 billion to the project over five 5 year capital programs up to and including the 2015 2019 capital program Of these 27 are federal funds and the other 73 are local funds As of November 2017 update the MTA had spent 7 397 billion of the available funding 169 40 As of April 2018 update the project was expected to cost 11 1 billion an increase from a previous estimate of 10 2 billion 168 83 170 The project had 10 3 billion in funding which allowed construction to continue through 2020 11 The state legislature had to approve an additional 798 million to allow construction to be completed but this had not been approved by late 2019 171 nbsp West cavern seen in January 2014 nbsp Cavern in January 2013The completion date for the project has also been pushed back multiple times Once planned to be operational by 2009 at a cost of 4 3 billion 172 158 East Side Access was then rescheduled to open in 2017 173 2016 174 2018 175 2019 165 September 2023 176 and then either December 2023 177 or late 2023 65 However by April 2018 update the MTA was looking to start passenger service in December 2022 at an estimated cost of 11 1 billion 168 83 84 36 As of July 2020 update the MTA had a target revenue service date of May 2022 whereupon construction would be essentially complete while the line was planned to open to the public in December 2022 119 13 The timeline was only slightly delayed due to the COVID 19 pandemic in New York City 119 18 The opening was ultimately postponed to January 25 2023 115 In 2012 the United States Department of Transportation USDOT s Inspector General announced that it wanted an audit done on the project after the USDOT learned of the fourteen year delay in the completion date and the more than 100 cost increase 178 166 In 2015 the USDOT s Deputy Principal Assistant Inspector General for Auditing and Evaluation Joseph W Come testified before the United States House Committee on Oversight and Government Reform s Subcommittee on Transportation and Public Assets Come said that several New York City transportation projects also experienced significant delays and cost overruns This was due to a variety of factors such as fraud poor management and a lack of oversight 179 The New York Times reported in 2017 that the project was slated to become the most expensive of its kind in the world With an estimated cost of 12 billion or about 3 5 billion per mile 2 2 billion per kilometer of new tunnel the East Side Access tunnels were seven times as expensive as comparable railroad tunnels in other countries 167 170 Over the years the projected cost of East Side Access had risen by billions of dollars due to unnecessary expenses Contractors for the MTA were paid more than those working in other cities even though that provided no construction benefits Planning for East Side Access cost more than 2 billion and planning for MTA projects in general also made up more of the cost than in other cities projects In addition politicians and trade unions had forced the MTA to hire more workers than were needed In 2010 an accountant had found that the project was hiring 200 extra workers at a cost of 1 000 per worker per day for no apparent reason 167 The bidding process for MTA construction contracts also raised costs because in some cases only one or two contractors would bid on a project 167 83 Similar construction projects in New York City such as the Second Avenue Subway and 7 Subway Extension had been more expensive than comparable projects elsewhere for the same reasons even though other cities transit systems faced similar or greater problems compared to the MTA 167 Other delays were attributed to the fact that dozens of contracts some of which conflicted with each other were bid out separately Cost increases also occurred due to changing the design while construction was underway ordering components that were the wrong size failing to cooperate with other transit agencies in Sunnyside Yard and making infeasible construction timeline estimates 83 In a bid to lower costs and reduce delays in September 2018 the LIRR hired Arthur R Troup who previously held senior positions with Atlanta s and Washington D C s rapid transit systems to lead the East Side Access project 180 181 Incidents and accidents edit Several major accidents occurred during construction and East Side Access has been cited for numerous safety violations 182 In late 2011 a construction worker died after a tunnel collapsed 182 183 In October 2014 a contractor who was digging wells on the Queens side accidentally punctured the subway tunnel underneath grazing an F train with passengers inside 184 185 Associated projects editArch Street Yard and Shop Facility edit nbsp The Arch Street Yard and Shop as visible from the 7 train window nbsp The yards as visible from 21 st nbsp Street entranceThe Arch Street Yard and Shop is in Long Island City near the Hunterspoint Avenue station 186 249 The yard itself has been in use since at least 1910 187 The Arch Street Facility includes tracks that were built on the right of way of the LIRR s former North Shore Branch Although the branch formerly extended west to what is now the Gantry Plaza State Park on the East River shoreline 186 252 the Arch Street Facility s storage tracks only extend as far as 11th Street several blocks away from the river 186 255 The LIRR planned a maintenance facility in the yard as part of the East Side Access project 188 The building was completed in either December 2004 189 4 or June 2005 186 252 The 80 4 million facility was built using a mix of federal and non federal funds 189 4 The LIRR had built the Arch Street Facility in advance so it could test its then new M7 cars When the MTA planned the facility in 2002 it had anticipated that East Side Access would open in 2011 and that the Arch Street Shop could be used to maintain the LIRR fleet It was thought that the Hillside Facility would not be able to maintain the expanded LIRR fleet on its own However after the East Side Access project was repeatedly delayed the Arch Street Facility was ultimately leased and licensed for other uses 189 5 Just south of the Arch Street Yard the Montauk Cutoff connected the Main Line to the Montauk Branch until it was decommissioned in 2015 190 As part of East Side Access a portion of the cutoff was demolished to make room for the Midday Storage Yard 191 121 New Sunnyside station edit Main article Sunnyside station New York City A new LIRR train station in Sunnyside on the west side of Queens Boulevard and Skillman Avenue 192 193 20 21 along the Northeast Corridor which the LIRR uses to get into Pennsylvania Station has been proposed which would provide one stop access for area residents to Midtown Manhattan 194 The station would have two side platforms and one island platform all of which would be able to accommodate 12 car trains 193 20 21 In its 2015 2019 capital program the MTA had budgeted 76 5 million for the construction of such a station 195 with a proposed start date in January 2021 196 but then delayed any work until after the completion of East Side Access 197 Capacity increase edit The East Side Access project along with several readiness improvement projects will allow the LIRR to run 24 more twelve car trains during rush hours This will boost its rush hour passenger capacity from 300 000 to 425 000 daily commuters a 45 increase 11 Main Line third track edit nbsp A bridge built in October 2017 to accommodate a third track on the Main LineMain article Main Line Long Island Rail Road Third track between Floral Park and Hicksville Related to the MTA s East Side Access project is its long planned widening of the two track LIRR Main Line by adding a third track 198 199 Completion of Main Line third track construction was assumed during East Side Access project planning and referenced in the original East Side Access environmental impact statement as necessary to support service level increases caused by adding service to and from Grand Central 200 The MTA has said that it considers the Main Line third track an essential project to support East Side Access 201 and that the Main Line third track will complement the East Side Access megaproject which is doubling the LIRR s capacity into Manhattan 199 The third track s construction was deferred indefinitely by the MTA in 2008 due to budget constraints 198 202 In January 2016 Governor Cuomo and the MTA announced plans to restart construction of the Main Line third track 198 199 In December 2017 the LIRR awarded a contract for the project to the consortium 3rd Track Constructors for 1 8 billion 203 204 205 A groundbreaking ceremony for the third track project was held on September 5 2018 206 207 The third track opened in several phases 208 and was completed by October 2022 209 210 Readiness projects edit Five readiness projects are also under construction across the LIRR system to handle the expanded peak hour service planned when East Side Access opens Together they are expected to cost 495 million 211 212 213 The largest of these projects is at Jamaica station where the MTA is re configuring track layouts installing high speed switches and adding a new Platform F for the Atlantic Branch 214 The changes will allow the Atlantic Branch to function as a high frequency shuttle service to Atlantic Terminal and most trains from Long Island will proceed to either Long Island City station Penn Station or Grand Central via the Main Line 215 The first phase of the project including the new platform was completed in 2021 at a cost of 380 million 216 Another project will add train storage capacity at two LIRR stations A 1 700 foot 520 m siding near Massapequa station on the Babylon Branch will be used to store trains that originate or terminate at the station enabling more peak hour service to and from Penn Station Grand Central It was originally planned for completion in April 2019 213 though was delayed until June 2021 217 57 The MTA is also extending Track 2 on the Port Washington Branch which ends as a pocket track east of Great Neck station eastward by 1 200 feet 370 m so it can store two trainsets Additionally a new bridge was built at Colonial Road near the station it opened in May 2016 and replaced a 114 year old span 218 219 220 221 222 The construction of the pocket track was originally scheduled for completion in December 2018 at a total cost of 45 2 million 213 However the completion date was pushed back several times 223 60 as of November 2021 update a tentative completion date of August 2022 was announced 217 59 Following another delay 224 construction of the extended pocket track was completed in December 2022 225 Finally the MTA planned to expand two yards The MTA expanded the rail yard along the Main Line Ronkonkoma Branch next to Ronkonkoma station increasing the number of tracks in the yard from 12 to 23 226 The project was budgeted for 128 million 213 227 Construction started in July 2017 228 and the expanded yard went into service in late 2020 217 62 223 62 Additionally the Port Washington Yard next to Port Washington station on the Port Washington Branch was planned to be expanded to store two more ten car trains As of 2017 update construction was scheduled to begin in late 2020 or early 2021 at a cost of 500 000 213 229 However this project met significant community opposition primarily because of proposed reduction of parking spaces near the station 230 As of September 2022 update the MTA has not come to an agreement with the Town of North Hempstead 223 65 resulting in the project being postponed indefinitely 145 217 61 New railcars edit nbsp M9 railcars which are being purchased before the opening of East Side AccessThe LIRR also purchased up to 160 M9 cars to handle the increased passenger traffic expected with the opening of East Side Access They are being paid for with federal grant money attached to the project 231 11 Although the MTA had ordered the M9s as early as 2013 the contract was delayed several times 129 As of June 2022 the delivery of M9s was almost three years behind schedule reportedly due to supply chain issues and labor shortages Only 132 of 202 cars in the base order have yet been delivered 232 233 and the additional 160 M9As did not arrive before the opening of East Side Access 234 35 The MTA thus reintroduced about 100 of the older M3 cars which first entered service the mid 1980s to provide the advertised additional service 129 235 The M3s are slated to remain in service at least until the remaining M9s for fleet expansion are delivered 235 Penn Station Access edit Main article Penn Station Access Redirecting LIRR trains from Penn Station to Grand Central Terminal frees up tracks and platforms at Penn This new capacity as well as track connections resulting from the East Side Access project allows Metro North Railroad trains on the New Haven Line to run to Penn Station via Amtrak s Hell Gate Bridge Four new local Metro North stations in the Bronx are planned as part of this project at Co op City Morris Park Parkchester and Hunts Point The MTA is constructing a second connection from the Metro North s Hudson Line to Penn Station using Amtrak s West Side Line in Manhattan 236 The Penn Station Access project will provide direct rides from Connecticut Westchester County the Lower Hudson Valley and the Bronx to West Midtown ease reverse commuting from Manhattan and the Bronx to Westchester County the Lower Hudson Valley and Connecticut and provide transportation service to areas of the Bronx without direct subway service 237 In December 2021 it was announced that the project would be completed in 2027 238 several years later than initially proposed 239 See also editKML file edit help Template Attached KML East Side AccessKML is from Wikidata Center City Commuter Connection a similar tunnel opened in Philadelphia in 1984 to connect two previously separate rail terminals Fulton Center another MTA Capital Construction project Gateway Program Northeast Corridor a proposed railroad expansion project on the west side of Manhattan History of Grand Central Terminal more details about the history of Grand Central Terminal Lower Manhattan Jamaica JFK Transportation Project a formerly proposed LIRR project North South Rail Link a set of proposals for a similar project in Boston Second Avenue Subway another MTA Capital Construction project whose Phase I entered service on January 1 2017 7 Subway Extension a completed MTA Capital Construction projectPortals nbsp New York City nbsp TrainsNotes edit For the full FEIS see East Side Access Final Environmental Impact Statement Overview mta info Metropolitan Transportation Authority March 6 2001 Retrieved February 2 2018 This includes the Main Line west of Hicksville and the Oyster Bay Port Jefferson and Ronkonkoma Branches Prior to the opening of the third track reverse peak service was severely limited by the need to utilize both Main Line tracks in the peak direction during the busiest period of rush hour 135 This includes various stations on different branches 137 as well as Penn Station which will be served by 10 fewer AM peak trains 131 Until 2022 several trains going in the same direction have been scheduled to arrive at Jamaica at the same time a system through which passengers had quick cross platform transfers to reach their desired branch Under the new system connections will not be timed requiring riders to wait an arbitrary amount of time for the next train to their destination The Oyster Bay Branch Port Jefferson Branch east of Huntington Montauk Branch east of Babylon and Main Line east of RonkonkomaReferences edit a b Introducing special Grand Central Direct service Metropolitan Transportation Authority Retrieved January 23 2022 a b c d e f g h i Chapter 1 Purpose and Need East Side Access Environmental Impact Statement PDF MTA Capital Construction March 2001 Archived PDF from the original on March 4 2016 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help Improvements That Are Planned for Subways PDF The New York Times March 24 1954 Archived from the original on August 8 2022 Retrieved February 8 2016 Bennett Charles G May 25 1963 61st St Tunnel to Queens Sped PDF The New York Times p 1 Archived from the original on May 7 2022 Retrieved October 20 2011 Bennett Charles G January 15 1965 63d Street Tube Approved By City Hearing Heated PDF The New York Times p 1 Archived from the original on May 7 2022 Retrieved October 20 2011 L I R R Will Run In Queens Tunnel 3d Track In 63d St Tube To Provide East Side Outlet PDF The New York Times April 28 1966 ISSN 0362 4331 Archived from the original on May 7 2022 Retrieved February 1 2018 Tunnel From Queens to 63d St To Have 4 Tracks Instead of 3 PDF The New York Times August 12 1966 ISSN 0362 4331 Archived from the original on May 7 2022 Retrieved February 1 2018 a b Full text of Metropolitan transportation a program for action Report to Nelson A Rockefeller Governor of New York Internet Archive November 7 1967 Retrieved October 1 2015 a b Bennett Charles G February 29 1968 Transportation Funding Would Have 4 Sources Plan s Financing Would Be Varied PDF The New York Times Archived from the original on May 7 2022 Retrieved October 11 2015 Witkin Richard February 29 1968 2 9 Billion Transit Plan For New York Area Links Subways Rails Airports 2 Phase Proposal Program By Governor Calls For 1 6 Billion In First 10 Years 2 Phase Proposal For Transit Given PDF The New York Times Archived from the original on May 7 2022 Retrieved October 11 2015 a b c d Dobnik Verena November 4 2015 Massive East Side Access Project Rolling On Under Grand Central nbcnewyork com Archived from the original on December 1 2019 Retrieved January 19 2016 a b c d e f East Side Access transforming the LIRR Herald Community Newspapers August 21 2018 Archived from the original on August 13 2021 Retrieved September 23 2018 Harbor Welcome Is Given Tube for Queens Subway The New York Times May 19 1971 ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 3 2018 Prial Frank J August 30 1971 First Section of 63d St Tunnel Lowered to Bottom of East River The New York Times ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved December 25 2016 via The New York Times Archive Prial Frank J March 14 1972 City s First Subway Tunnel in 40 Years Cut Through The New York Times ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 3 2018 To Break Ground For 63rd St East River Tunnel PDF New York Leader Observer November 20 1969 p 8 Archived PDF from the original on December 16 2018 Retrieved July 29 2016 via Fultonhistory com Governor Rockefeller and Mayor Lindsay Attend Holing Through of 63d St Tunnel The New York Times October 11 1972 ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 3 2018 a b Tolchin Martin June 7 1973 Grand Central Is Favored Over a 3d Ave Terminal The New York Times ISSN 0362 4331 Archived from the original on September 28 2017 Retrieved December 25 2016 via The New York Times Archive a b Prial Frank J July 8 1973 Turtle Bay Residents Fighting M T A Rail Plan Heartened by Killing of Proposed Bridge Over Sound The New York Times ISSN 0362 4331 Archived from the original on September 28 2017 Retrieved December 25 2016 via The New York Times Archive Tolchin Martin June 15 1973 A 3d Ave Rail Terminal Foreseen by U S Official The New York Times Archived from the original on September 28 2017 Retrieved September 28 2017 Burks Edward C 1975 L I R R Terminal Delayed by M T A The New York Times ISSN 0362 4331 Archived from the original on February 5 2018 Retrieved February 4 2018 GRAND CENTRAL GETS VOTE AS L I R R SITE The New York Times July 9 1977 Archived from the original on December 25 2018 Retrieved December 24 2018 a b c d Andelman David A October 11 1980 Tunnel Project Five Years Old Won t Be Used The New York Times p 25 Archived from the original on July 22 2018 Retrieved October 20 2011 Lorch Donatella October 29 1989 The Subway to Nowhere Now Goes Somewhere The New York Times Archived from the original on December 18 2021 Retrieved October 20 2011 About NYC Transit History October 19 2002 Archived from the original on October 19 2002 Retrieved September 18 2016 Silano Louis G Shanbhag Radmas July 2000 The Final Connection Civil Engineering Vol 86 no 7 pp 56 61 a b c d Neuman William May 11 2007 Awaiting Rock Eating Beast L I R R Tunnel Is Poised to Finish Trip to Grand Central The New York Times Archived from the original on February 4 2018 Retrieved February 3 2018 Kershaw Sarah December 17 2001 V Train Begins Service Today Giving Queens Commuters Another Option The New York Times Archived from the original on January 7 2017 Retrieved February 3 2018 a b c d e f g h i Appendix B Upper Level Loop Analysis East Side Access Modification to Environmental Impact Statement PDF MTA Capital Construction April 2006 Archived PDF from the original on August 25 2014 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help Perez Pena Richard February 16 1997 Proposed L I R R Link To Grand Central Gains The New York Times Archived from the original on February 3 2018 Retrieved February 3 2018 Lueck Thomas J September 26 1999 M T A to Propose Spending Billions on Rail Expansion The New York Times Archived from the original on February 3 2018 Retrieved February 3 2018 a b c Record of Decisions PDF United States Department of Transportation Federal Transit Administration Metropolitan Transportation Authority May 21 2001 Archived PDF from the original on May 20 2017 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help Ain Stewart December 23 2001 Pushing to Speed Up East Side Rail Link The New York Times ISSN 0362 4331 Archived from the original on February 4 2018 Retrieved February 3 2018 Luo Michael November 26 2003 Weighing Transit Possibilities New Study Follows the Money The New York Times ISSN 0362 4331 Archived from the original on February 4 2018 Retrieved February 3 2018 Associated Press February 4 2002 NY received 132 million under bin PDF Salamanca Press p 5 Archived PDF from the original on May 7 2022 Retrieved July 29 2016 via Fultonhistory com Urbina Ian November 20 2004 Plan to Connect L I R R to Grand Central Hits Snag The New York Times ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 3 2018 Yates Maura February 10 2005 East Side Access Draws Opponents The New York Sun Archived from the original on October 31 2010 Retrieved January 9 2010 Chan Sewell March 30 2005 M T A Continues to Favor Plan for a Midtown Ventilation Tower The New York Times ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 3 2018 Chan Sewell December 7 2005 M T A Scales Back Midtown Ventilation Project The New York Times ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 3 2018 Chan Sewell October 25 2005 Stakes High for M T A and City in Vote on 2 9 Billion Bond Act The New York Times ISSN 0362 4331 Archived from the original on February 4 2018 Retrieved February 3 2018 General Election Proposal Number Two A Proposition Rebuild And Renew New York Transportation Bond Act Of 2005 PDF New York State Board of Elections November 8 2008 Archived from the original PDF on December 3 2018 Retrieved February 3 2018 U S Transportation Secretary Signs Record 2 6 Billion Agreement To Fund New Tunnel Network To Give Long Island Commuters Direct Access to Grand Central Station Press release U S Department of Transportation December 18 2006 Archived from the original on January 3 2007 Retrieved January 18 2007 L I R R Access to Grand Central The New York Times video October 1 2006 Archived from the original on February 3 2018 Retrieved February 3 2018 a b Cuza Bobby July 12 2006 MTA Takes Major Step Towards Completing East Side Access Plan NY1 a b c d e f g h i j k East Side Access Quarterly Report Q3 2009 PDF Metropolitan Transportation Authority September 2009 p 16 Archived PDF from the original on June 27 2016 Retrieved February 5 2018 a b c d Sarkar Subal Mukherjee Amitabha Benslimane Aomar 2004 Rock Tunnelling with TBMs on the East Side Access Project a New Perspective International Conference on Case Histories in Geotechnical Engineering Vol 13 Missouri University of Science and Technology Archived from the original on February 4 2018 Retrieved February 3 2018 a b Harshbarger Rebecca November 4 2015 350 million year old rock pulverized for new rail tunnels am New York Archived from the original on February 3 2018 Retrieved February 2 2018 a b c Mann Ted April 26 2012 MTA Focuses on Ups Downs The Wall Street Journal Archived from the original on January 10 2021 Retrieved August 5 2016 a b Chapter 1 Purpose and Need East Side Access Modification to Environmental Impact Statement PDF MTA Capital Construction April 2006 Archived PDF from the original on March 4 2016 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help a b MTA Completes Tunnel Boring On East Side Access CBS New York July 26 2012 Archived from the original on February 3 2018 Retrieved February 3 2018 a b c Neuman William July 18 2008 A 640 Ton Machine Drills a Long Island Rail Road Tunnel to Grand Central The New York Times ISSN 0362 4331 Archived from the original on February 3 2018 Retrieved February 4 2018 a b East Side Access Tunnel Boring Machine Reaches Grand Central Terminal Press release Metropolitan Transportation Authority July 2 2008 Archived from the original on December 22 2015 Retrieved January 9 2010 MTA ESA Progress Map Archived April 8 2014 at the Wayback Machine Metropolitan Transportation Authority Retrieved October 9 2008 Geocomp Corporation Brochure Archived February 2 2014 at the Wayback Machine PDF Geocomp Corporation Rashbaum William K May 19 2010 M T A Tunnel Job Loses Dirt Hauler Over Mob Ties The New York Times ISSN 0362 4331 Archived from the original on February 5 2018 Retrieved February 4 2018 Grynbaum Michael M July 24 2011 Deep Below Park Avenue a 200 Ton Drill at Rest The New York Times ISSN 0362 4331 Archived from the original on February 20 2017 Retrieved July 5 2016 a b c d e Ocean Justin November 4 2015 Inside the Massive New Rail Tunnels Beneath NYC s Grand Central Bloomberg com Archived from the original on February 4 2018 Retrieved February 2 2018 MANHATTAN TUNNELS EXCAVATION PDF Metropolitan Transportation Authority Archived from the original PDF on April 8 2014 Retrieved April 7 2014 50th Street Commons Pocket Park Opens as Part of East Side Access Metropolitan Transportation Authority September 16 2014 Archived from the original on September 19 2014 Retrieved September 16 2014 MTA opens pocket park on 50th Street Newsday September 17 2014 Archived from the original on September 17 2014 Retrieved September 17 2014 MTA Inaugurates New Pocket Park Oasis in Midtown New York Inhabitat New York City September 17 2014 Archived from the original on September 19 2014 Retrieved September 17 2014 Photos MTA Opens Adorable Pocket Park On East 50th Street Gothamist Gothamist Archived from the original on September 19 2014 Retrieved September 17 2014 MTA news Milestone for East Side Access Workers to Break Through Lower Level Floor To Build Housing for Escalators and Stairways to Future LIRR Concourse www mta info Archived from the original on February 24 2016 Retrieved February 17 2016 Long Island Committee Meeting December 2015 PDF mta info Metropolitan Transportation Authority December 14 2015 Archived from the original PDF on February 25 2016 Retrieved February 17 2016 MTA OK s contract for East Side Access TimesLedger Archived from the original on February 14 2016 Retrieved February 17 2016 a b MTA starts laying track for long awaited East Side access for LIRR commuters Spectrum News NY1 September 25 2017 Archived from the original on February 3 2018 Retrieved February 2 2018 a b Capital Program Oversight Committee Meeting September 2018 PDF mta info Metropolitan Transportation Authority September 24 2018 Archived PDF from the original on September 23 2018 Retrieved September 23 2018 Bagli Charles V February 21 2018 Out With the Old Building in With the New for JPMorgan Chase The New York Times ISSN 0362 4331 Archived from the original on August 9 2021 Retrieved February 22 2018 a b Capital Program Oversight Committee Meeting PDF Metropolitan Transportation Authority July 22 2019 Archived PDF from the original on July 19 2019 Retrieved January 19 2019 Final Environmental Impact Statement for the 63rd Street Line Connection to the Queens Boulevard Line Queens New York New York Metropolitan Transportation Authority United States Department of Transportation Federal Transit Administration June 1992 Archived from the original on June 18 2017 Retrieved July 23 2016 Nasri V Lee W S Rice J 2004 Comparison of the predicted behavior of the Manhattan TBM launch shaft with the observed data East Side Access Project New York North American Tunneling Taylor amp Francis pp 537 544 ISBN 978 1 4398 3375 9 Archived from the original on May 22 2020 Retrieved July 23 2016 a b c Metropolitan Transportation Authority East Side Access 1 24 2012 Update Archived from the original on April 10 2013 Retrieved May 8 2012 via YouTube Risk Assessment Overview ESA Queens Tunneling Program PDF mta info MTA Capital Construction September 26 2011 p 11 Archived PDF from the original on November 7 2016 Retrieved February 2 2018 New York s Subway System Finally Starting Major Expansion Archived May 9 2008 at the Wayback Machine newyork construction com May 2006 issue a b c East Side Access Queens Bored Tunnels amp Structures Engineering News Record June 1 2010 Archived from the original on July 12 2019 Retrieved February 6 2018 Granite Traylor Frontier Kemper Venture Awarded 659 Million for Queens Bored Tunnels and Structures Construction Equipment September 30 2009 Archived from the original on December 25 2009 Retrieved October 9 2009 MTA Officials Dedicate Tunnel Boring Machines NY1 March 18 2011 Archived from the original on August 25 2011 Retrieved March 19 2011 Castillo Alfonso April 16 2014 MTA Two key East Side Access contracts awarded Newspaper Newsday Archived from the original on April 22 2014 Retrieved April 21 2014 28 East Side Access in New York Queens and Bronx Counties New York and Nassau and Suffolk Counties New York Environmental Impact Statement PDF MTA Capital Construction March 2001 p 47 Archived PDF from the original on March 15 2018 Retrieved March 15 2018 a href Template Cite book html title Template Cite book cite book a work ignored help Colvin Jill May 9 2011 New York Awarded 350 Million for High Speed Rail Projects DNAinfo com Archived from the original on May 13 2011 Retrieved May 13 2011 New York Gets 354 4 Million For High Speed Rail Projects CBS New York May 9 2011 Archived from the original on March 15 2018 Retrieved March 15 2018 East Side Access trackwork to speed LIRR and Amtrak trains Railway Track amp Structures July 18 2013 Archived from the original on March 15 2018 Retrieved March 15 2018 Castillo Alfonso A October 3 2015 MTA megaproject challenged by Amtrak Newsday Archived from the original on March 15 2018 Retrieved March 15 2018 a b c d e f g h i Castillo Alfonso A April 15 2018 East Side Access price tag now stands at 11 2B Newsday Archived from the original on April 15 2018 Retrieved April 16 2018 a b Capital Program Oversight Committee Meeting PDF Metropolitan Transportation Authority April 23 2018 Archived PDF from the original on April 21 2018 Retrieved April 20 2018 Castillo Alfonso A March 1 2018 MTA Another snag for East Side Access project Newsday Archived from the original on April 16 2018 Retrieved April 16 2018 LIRR to test upgraded signal system for East Side Access project For Railroad Career Professionals Progressive Railroading April 5 2018 Archived from the original on April 16 2018 Retrieved April 16 2018 LIRR relocates tracks for Grand Central tunnel Newsday July 19 2018 Archived from the original on September 23 2018 Retrieved September 23 2018 Press Release MTA Headquarters MTA Awards Final Major Construction Contract for East Side Access Metropolitan Transportation Authority October 31 2018 Archived from the original on November 6 2018 Retrieved November 6 2018 EAST SIDE ACCESS Bringing Long Island Rail Road Service to the East Side of Manhattan LIRR Committee Report PDF Metropolitan Transportation Authority November 13 2018 Archived PDF from the original on April 24 2019 Retrieved November 20 2018 Skanska Awarded Final Heavy Civil Contract for East Side Access Tunnel Business Magazine January 10 2019 Archived from the original on January 12 2019 Retrieved January 12 2019 Walker Ameena January 11 2019 New 60M contract will bring delayed East Side Access closer to completion Curbed NY Archived from the original on January 11 2019 Retrieved January 12 2019 East Side Access Approach Structure Selected as a Top Project by RT amp S A Modern LI March 18 2021 Archived from the original on November 14 2022 Retrieved November 14 2022 a b Capital Program Oversight Committee Meeting May 2021 Metropolitan Transportation Authority May 26 2021 Archived from the original on May 26 2021 Retrieved May 26 2021 Duggan Kevin October 31 2021 Test run Hochul takes first LIRR ride to Grand Central a year ahead of East Side Access completion amNewYork www amny com Archived from the original on November 1 2021 Retrieved November 1 2021 Fan Christina October 31 2021 East Side Access One Step Closer For Long Islanders As MTA Unveils 350 000 Square Foot Terminal At Grand Central CBS New York Breaking News Sports Weather Traffic And The Best of NY Archived from the original on November 1 2021 Retrieved November 1 2021 Siff Andrew Vazquez Jennifer May 31 2022 East Side Access Terminal Gets New Name Grand Central Madison NBC New York Retrieved May 31 2022 Duggan Kevin May 31 2022 East Side Access project renamed Grand Central Madison will increase LIRR service by 40 Hochul says amNewYork Archived from the original on June 3 2022 Retrieved May 31 2022 Stabile Tom May 11 2022 MTA Chugs Toward Finish Line In East Side Access Marathon Engineering News Record Archived from the original on August 8 2022 Retrieved July 12 2022 a b Nessen Stephen November 8 2022 Key safety approval could delay MTA s long stalled East Side Access project Gothamist Retrieved November 9 2022 Worrell Carolina October 24 2022 LIRR Seeks Temporary Relief From FRA s Hazard Detectors Requirements Railway Age Retrieved November 9 2022 Hallum Mark November 9 2022 Grand Central Long Island Connection Opening Amid Slumping Commuter Numbers Commercial Observer Retrieved November 10 2022 Brachfeld Ben December 11 2022 LIRR assumes operational control of Grand Central Madison but still no opening date amNewYork Retrieved December 12 2022 Yanes Darwin December 11 2022 LIRR takes operational control of Grand Central Madison MTA says Newsday Retrieved December 12 2022 Sanderson Bill December 21 2022 Balky ventilation fan last hurdle keeping LIRR trains from Grand Central New York Daily News Retrieved December 25 2022 Castillo Alfonso A December 21 2022 MTA chairman Janno Lieber East Side Access opening held up by exhaust fan Newsday Retrieved December 25 2022 Siff Andrew December 29 2022 Grand Central Madison Won t Open in 2022 Here s Target Date for NYC s New LIRR Stop NBC New York Retrieved December 30 2022 Chayes Matthew December 29 2022 Grand Central Madison will not open in 2022 MTA says Newsday Retrieved December 30 2022 Castillo Alfonso A January 11 2023 Deadline for connecting LIRR to Grand Central still not certain transit chief says Newsday Retrieved January 12 2023 Nessen Stephen January 11 2023 MTA s East Side Access project delayed again due to vent problems Gothamist Retrieved January 12 2023 Nessen Stephen January 18 2023 Grand Central Madison is closed but the MTA is running empty trains there anyway Gothamist Retrieved January 24 2023 Castillo Alfonso A January 20 2023 Feds approve LIRR safety system for East Side Access Newsday Retrieved January 24 2023 Castillo Alfonso A January 24 2023 LIRR Grand Central Madison service to begin on Wednesday Newsday Retrieved January 24 2023 Siff Andrew January 23 2023 NYC s New LIRR Stop at Grand Central Madison Set to Open This Week What to Know NBC New York Retrieved January 24 2023 Castillo Alfonso A January 24 2023 Grand Central Madison opens Wednesday culmination of 11 1 billion East Side Access project Newsday Retrieved January 26 2023 a b c Ley Ana January 25 2023 L I R R Service to Grand Central Begins Today at Long Last The New York Times ISSN 0362 4331 Retrieved January 25 2023 Brachfeld Ben January 24 2023 FINALLY Grand Central Madison station opens after decades of planning and construction amNewYork Retrieved January 27 2023 Simko Bednarski Evan February 8 2023 Full LIRR service starting at Grand Central Terminal on Feb 27 New York Daily News Retrieved February 8 2023 Capital Programs East Side Access web mta info Metropolitan Transportation Authority Archived from the original on February 3 2018 Retrieved February 3 2018 a b c Capital Program Oversight Committee Meeting Metropolitan Transportation Authority July 22 2020 Archived from the original on July 21 2020 Retrieved July 21 2020 East Side Access Newsletter PDF nyc gov Winter 2018 p 2 Archived PDF from the original on September 26 2018 Retrieved September 26 2018 a b Lancaster Maggie May 2 2017 MTA awards Tutor Perini 291 5 million contract for the Mid Day Storage Yard project Railway Track and Structures Archived from the original on May 2 2017 Retrieved February 5 2018 MTA LIRR East Side Access Technical Memorandum Assessing Design Refinement Tail Tracks Ventilation Plenum and Grate PDF Metropolitan Transportation Authority February 2008 p 1 Archived PDF from the original on August 22 2014 Retrieved February 5 2018 a b MTA awards contract for LIRR Grand Central tunnel ventilation facility New York Post September 24 2012 Archived from the original on February 4 2018 Retrieved February 3 2018 a b c MTA LIRR East Side Access Environmental Re Evaluation Consultation Form Review PDF Metropolitan Transportation Authority May 4 2018 Archived PDF from the original on February 7 2019 Retrieved February 5 2019 City Terminal Grand Central Metropolitan Transportation Authority Retrieved February 27 2022 ESA Facts amp Figures PDF mta info Metropolitan Transportation Authority November 2 2015 Archived PDF from the original on February 25 2016 Retrieved February 17 2016 Chapter 28 Comments and Responses on the Draft Environmental Impact Statement East Side Access Environmental Impact Statement PDF MTA Capital Construction March 2001 Archived PDF from the original on March 15 2018 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help Penner Larry January 6 2020 The Real Co ts of LIRR East Side Access to Grand Central Terminal Long Island Weekly Archived from the original on July 9 2021 Retrieved June 14 2022 a b c More than 20 of LIRR trains can t run in Grand Central Madison tunnel Gothamist March 14 2023 Retrieved March 20 2023 a b c Governor Hochul Announces New Long Island Rail Road Terminal in Midtown Manhattan Will Be Named Grand Central Madison governor ny gov May 31 2022 Archived from the original on June 3 2022 Retrieved June 14 2022 a b c d e f g Castillo Alfonso A June 3 2022 LIRR s issues Grand Central Madison draft timetables with some critics Newsday Archived from the original on June 12 2022 Retrieved June 14 2022 LIRR to Grand Central Draft Schedules mta info June 2 2022 Archived from the original on June 11 2022 Retrieved June 14 2022 LIRR Announces Additional Virtual Public Meetings On Proposed Schedule Changes Port Washington News August 4 2022 Retrieved February 21 2023 Hoogensen Finn December 19 2022 LIRR to offer direct train between Grand Central Madison and Jamaica Queens PIX11 Retrieved December 22 2022 Project Benefits amodernli com Archived from the original on July 27 2021 Retrieved June 14 2022 a b Hoogensen Finn June 2 2022 Grand Central Madison LIRR releases draft timetables for new terminal PIX 11 Retrieved June 14 2022 a b c East Side Access service plan proposes measly peak service increases thelirrtoday com June 9 2022 Archived from the original on June 9 2022 Retrieved June 14 2022 a b c Geberer Ranaan June 6 2022 LIRR s new Manhattan terminal means more trains from Brooklyn but most will be Jamaica shuttles Brooklyn Daily Eagle Archived from the original on June 14 2022 Retrieved June 14 2022 Castillo Alfonso A October 28 2022 Sandy damaged tunnel repairs haven t begun limiting LIRR service to Penn Station Newsday Retrieved October 30 2022 a b Genn Adina June 7 2022 East Side Access touted as economic game changer for LI Long Island Business News Archived from the original on June 9 2022 Retrieved June 14 2022 a b c Castillo Alfonso A June 29 2022 MTA chairman making no apologies for East Side Access plan Newsday Archived from the original on June 29 2022 Retrieved June 30 2022 PCAC Press Release on LIRR East Side Access Proposed Service Plans Calls For More Public Meetings and Participation Opportunities for Commuters Press release Permanent Citizens Advisory Committee to the MTA June 21 2022 Archived from the original on July 14 2022 Retrieved June 30 2022 Castillo Alfonso A May 25 2019 New amenitites coming to Jamaica station but it might be bad marriage for Brooklyn Newsday Archived from the original on June 14 2022 Retrieved June 14 2022 a b Castillo Alfonso A June 18 2022 LIRR commuters not pleased with proposed changes Newsday Archived from the original on June 18 2022 Retrieved June 18 2022 a b Kaplan Anna M September 28 2022 Important LIRR Commuter Update Express Trains Have Been Saved nysenate gov Retrieved October 1 2022 a b Castillo Alfonso A February 24 2023 LIRR riders await new Grand Central service with enthusiasm trepidation Newsday Retrieved February 27 2023 Gusoff Carolyn February 24 2023 Frustrated Long Island Rail Road riders say new schedule will make commutes longer less convenient CBS News Retrieved March 20 2023 LIRR full service begins Monday 2 27 at Grand Central Madison train schedules to change ABC7 New York February 27 2023 Retrieved February 27 2023 Castillo Alfonso A February 26 2023 East Side Access completed LIRR riders get full service to Grand Central Madison Monday Newsday Retrieved February 27 2023 a b Ley Ana March 3 2023 A Mad Dash as Commuters Deal With New L I R R Service The New York Times ISSN 0362 4331 Retrieved March 18 2023 a b Charles Charline March 2 2023 LIRR commuters complain of overcrowding delays after Grand Central Madison launch PIX11 Retrieved March 18 2023 LIRR making adjustments first week of full Grand Central Madison service ABC7 New York March 3 2023 Retrieved March 18 2023 Brachfeld Ben March 5 2023 MTA adds more LIRR trains in Brooklyn retools schedule amid chaotic rollout amNewYork Retrieved March 18 2023 MTA adjusts LIRR Brooklyn schedule following unpopular East Side Access schedule changes News 12 The Bronx March 6 2023 Retrieved March 18 2023 Dias John November 1 2023 Long Island Rail Road seeing more commuters shift to Grand Central Madison following service changes CBS New York Retrieved January 15 2024 Everything to know about Grand Central Madison Crain s New York Business January 25 2023 Retrieved January 27 2023 Nessen Stephen January 26 2023 Grand Central Madison 15 stories underground saves LIRR riders little time compared to Penn Station commute Gothamist Retrieved January 27 2023 a b c Donohue Pete January 27 2014 MTA walks back targets on East Side Access yet again completion now not expected until 2023 New York Daily News Archived from the original on March 5 2014 Retrieved March 5 2014 New York City Transit Key Performance Metrics April 2023 mta info Metropolitan Transportation Authority April 21 2023 Retrieved April 21 2023 a b Castillo Alfonso A July 17 2023 LIRR rider satisfaction plummets after Grand Central Madison opening Newsday Retrieved July 18 2023 LIRR satisfaction numbers dip in response to Grand Central Madison rollout News 12 Long Island July 18 2023 Retrieved July 18 2023 a b c d e Penner Larry February 26 2016 East Side Access wastes time and money TimesLedger Archived from the original on February 5 2018 Retrieved February 4 2018 a b c Hawkins Andrew J November 5 2015 Inside New York City s East Side Access the biggest transportation project in America The Verge Archived from the original on February 4 2018 Retrieved February 4 2018 East Side Access wastes time and money TimesLedger Archived from the original on February 5 2018 Retrieved February 4 2018 a b Taylor Alan February 22 2013 The Tunnels of NYC s East Side Access Project The Atlantic Archived from the original on January 6 2015 Retrieved February 4 2018 a b Moynihan Colin May 21 2012 L I R R East Side Access Plan to Need More Time and Money The New York Times ISSN 0362 4331 Archived from the original on February 5 2018 Retrieved February 4 2018 a b c d e f Rosenthal Brian M December 28 2017 The Most Expensive Mile of Subway Track on Earth The New York Times ISSN 0362 4331 Archived from the original on December 29 2017 Retrieved December 29 2017 a b c d Siff Andrew April 16 2018 MTA Megaproject to Cost Almost 1B More Than Prior Estimate NBC New York Archived from the original on April 17 2018 Retrieved April 16 2018 Metro North Railroad and Long Island Rail Road Committee Meeting PDF mta info Metropolitan Transportation Authority December 11 2017 Archived from the original PDF on February 5 2018 Retrieved February 4 2018 a b As Cost of Train Link Passes 11 Billion M T A s Credibility Shrinks The New York Times April 25 2018 Archived from the original on October 4 2018 Retrieved October 4 2018 Guse Clayton September 19 2019 MTA seeks another 798 million to finish East Side Access project long plagued by delays and rising costs New York Daily News Archived from the original on July 21 2020 Retrieved July 21 2020 Penner Larry May 27 2021 Digging deeper on the very deep East Side Access project Empire Center for Public Policy Archived from the original on August 8 2022 Retrieved June 1 2022 Donohue Pete July 21 2009 Second Avenue Subway Setback New Hurdles Will Likely Push Phase One Completion from 2015 to 2017 Daily News Retrieved January 9 2010 Redwine Tina July 7 2011 NY1 Exclusive East Side LIRR Terminal under Construction for 2016 NY1 Archived from the original on July 10 2011 Retrieved July 8 2011 Shutack Jackie LIRR Grand Central Tunnel Project Delayed until 2018 FiOS1 Archived from the original on July 9 2014 Retrieved January 10 2012 via YouTube Castillo Alfonso A January 27 2014 East Side Access completion date extended again Newsday Archived from the original on March 21 2014 Retrieved March 5 2014 The MTA s monumental East Side Access project to link the Long Island Rail Road to Grand Central Terminal could carry a price tag 2 6 billion over budget and not be completed until 2023 four years behind schedule according to a new report MTA and LIRR East Side Access cost and schedule continue to change Metro US August 10 2017 Archived from the original on February 4 2018 Retrieved February 4 2018 Redwine Tina May 21 2012 Feds Audit East Side Access Project as MTA Stands by New Completion Date NY1 Archived from the original on May 23 2012 Retrieved May 24 2012 Come Joseph W June 8 2015 Oversight of Major Transportation Projects Opportunities To Apply Lessons Learned PDF United States Department of Transportation Archived PDF from the original on June 12 2017 Retrieved February 4 2018 Castillo Alfonso A September 25 2018 New boss tagged for LIRR East Side Access project Newsday Archived from the original on September 27 2018 Retrieved September 27 2018 MTA taps Troup for ESA Railway Age September 25 2018 Archived from the original on September 27 2018 Retrieved September 27 2018 a b Kates Brian November 18 2011 Young sandhog dies in tunnel collapse NY Daily News Archived from the original on February 4 2018 Retrieved February 4 2018 Grynbaum Michael M Haughney Christine November 19 2011 Sandhog Killed in Railroad Tunnel Accident The New York Times Archived from the original on December 5 2018 Retrieved December 5 2018 MTA battling stupidity on the East Side Access project ABC7 New York November 18 2014 Archived from the original on December 5 2018 Retrieved December 5 2018 Donohue Pete Rosenberg Eli Otis Ginger Adams October 30 2014 Drill bit blunder in MTA s East Side Access project nearly cuts into occupied F train in Queens nydailynews com Archived from the original on December 5 2018 Retrieved December 5 2018 a b c d Transit and Railroad Yards Queens Inventory of Decking Opportunities Over Transportation Properties PDF New York City Department of City Planning September 2008 Archived PDF from the original on February 28 2017 Retrieved February 5 2018 Correal Annie December 6 2015 In Long Island City Now Arriving in No Man s Land The New York Times Archived from the original on February 6 2018 Retrieved February 5 2018 Chapter 17 Construction and Construction Management East Side Access Environmental Impact Statement PDF MTA Capital Construction March 2001 Archived PDF from the original on February 6 2018 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help a b c DiNapoli Thomas P December 2017 Utilization of the Arch Street Yard and Shop Facility PDF New York State Office of the State Comptroller Archived PDF from the original on February 6 2018 Retrieved February 5 2018 Kensinger Nathan December 3 2015 In Long Island City a Community Seeks to Reclaim an Urban Wilderness Curbed NY Archived from the original on February 7 2018 Retrieved February 5 2018 Capital Program Oversight Committee Meeting PDF mta info Metropolitan Transportation Authority April 17 2017 pp 65 66 Archived PDF from the original on February 6 2018 Retrieved August 31 2017 East Side Access Congresswoman Carolyn Maloney Archived from the original on February 6 2018 Retrieved February 5 2018 a b Chapter 2 Project Alternatives East Side Access Environmental Impact Statement PDF MTA Capital Construction March 2001 Archived PDF from the original on February 6 2018 Retrieved February 2 2018 a href Template Cite book html title Template Cite book cite book a work ignored help Vandam Jeff February 4 2007 An Enclave at Once Snug and Inclusive The New York Times Archived from the original on April 11 2011 Retrieved February 14 2008 When the Long Island Rail Road s East Side Access project is completed in 2013 its trains too will go to Grand Central Sunnyside s new station in the system will create a nonstop commute to Midtown MTA Capital Program 2015 2019 PDF mta info Metropolitan Transportation Authority July 31 2017 p 164 Archived PDF from the original on January 10 2021 Retrieved February 5 2018 ESA RI Sunnyside Station mta info Metropolitan Transportation Authority Archived from the original on September 7 2017 Retrieved February 5 2018 Stefan Revenboer October 24 2022 The new Grand Central LIRR service will bypass Sunnyside Queens New York News a b c Fitzsimmons Emma G January 5 2016 Cuomo Revives Long Stalled Plan to Add Track to L I R R The New York Times p A18 Archived from the original on January 7 2016 Retrieved January 7 2016 a b c LIRR Main Line Expansion Will Ease Commuting and Attract Businesses and Jobs Press release Metropolitan Transportation Authority January 5 2016 Archived from the original on January 19 2016 Retrieved January 19 2016 2013 Long Island Index Special Analysis How the Long Island Rail Road Could Shape the Next Economy PDF Report 2013 Archived PDF from the original on February 22 2016 Retrieved January 19 2016 Main Line Corridor Improvements Project Presentation PDF Metropolitan Transportation Authority Archived PDF from the original on January 25 2016 Retrieved January 7 2016 Nardiello Carolyn September 16 2008 Third Track Plan Isn t Dead L I R R Insists The New York Times Archived from the original on April 19 2015 Retrieved January 19 2016 Berger Paul December 13 2017 MTA Awards 1 8 Billion Contract to Expand Long Island Rail Road The Wall Street Journal Archived from the original on January 25 2018 Retrieved January 25 2018 Castillo Alfonso A December 13 2017 MTA approves 1 9B contract to design build LIRR 3rd track Newsday Archived from the original on January 26 2018 Retrieved January 25 2018 Klar Rebecca December 20 2017 MTA approves 1 8B contract for third track project The Island Now Archived from the original on January 26 2018 Retrieved January 25 2018 LIRR Third Track Project Moving Forward Despite Concerns Of Residents CBS New York September 5 2018 Archived from the original on September 6 2018 Retrieved September 6 2018 Rivoli Dan September 5 2018 Cuomo continues infrastructure tour with Long Island Rail Road groundbreaking New York Daily News Archived from the original on September 6 2018 Retrieved September 6 2018 LIRR unveils 1st section of new express lane track Yahoo Sports August 15 2022 Retrieved August 15 2022 Duggan Kevin October 3 2022 Third time s the charm MTA finishes 2 5 billion LIRR Third Track project amNewYork Retrieved October 15 2022 LIRR Completes Third Track Project Railway Age October 4 2022 Retrieved October 15 2022 Anuta Joe Newman Philip June 5 2013 Queens Tomorrow LIRR headed to Grand Central TimesLedger TimesLedger Newspapers Archived from the original on May 25 2018 Retrieved May 24 2018 MTA Capital Program Oversight Meeting PDF mta info Metropolitan Transportation Authority January 2013 p 8 Archived PDF from the original on October 25 2017 Retrieved May 24 2018 a b c s, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.