fbpx
Wikipedia

Urban Ring Project (MBTA)

The Urban Ring was a proposed project of the Massachusetts Bay Transportation Authority and the Massachusetts Department of Transportation, to develop new public transportation routes that would provide improved circumferential connections among many existing transit lines that project radially from downtown Boston.[1] The Urban Ring Corridor is located roughly one to two miles from downtown Boston, passing through the Massachusetts cities of Boston, Chelsea, Everett, Medford, Somerville, Cambridge, and Brookline.[1] The project was expected to convert 41,500 car trips to transit trips daily.[2]

MBTA Urban Ring
ParentMassachusetts Bay Transportation Authority
FoundedSuspended, but partial implementation of some segments is proceeding
Headquarters10 Park Plaza, Boston, MA 02116
LocaleBoston, Massachusetts
Service areaBoston, Chelsea, Everett, Medford, Somerville, Cambridge, and Brookline
Service typeBus rapid transit
Routes1 circumferential, with 2 major spurs
Stations31 proposed
Daily ridership282,000–293,000 passengers per day in 2025 (estimated)
Fuel typeDiesel
OperatorMBTA
Websitewww.massdot.state.ma.us/theurbanring/

The Major Investment Study split the project into three phases, the first of which (enhanced bus service) was partially implemented. The planning of Phase 2 was suspended in January 2010 because MBTA and the Commonwealth of Massachusetts have insufficient funding to build a substantial portion of that phase (projected to cost $2.4 billion).[2][3] As of 2019, some interim bus service improvements have been implemented or are underway, in the absence of major funding.

Background Edit

Transportation advocates in Boston have complained that rail transit riders cannot travel from one outlying area to another without first traveling to the downtown hub stations, changing lines, and traveling outbound again. Some of the radial transit lines, notably the Green Line, are so overcrowded that service is very slow and limited in capacity because of rush-hour "crush loads". There are several crosstown bus lines, such as the #1, #66, CT1, CT2, and CT3 routes, but they are slow, unreliable, and subject to bus bunching because they must operate in mixed street traffic.[4]

A circumferential rapid transit line was proposed by the City of Boston as early as 1923, and circumferential transit has been studied as early as 1972, in the Boston Transportation Planning Review.[5] Detailed proposals were not studied until the late 1990s.[6]

Project proposal Edit

The proposed project has three phases. The first phase has been partially implemented. Phase 1, as it is commonly called, involves expanding "crosstown" bus lines serving the entire corridor and "express commuter" lines connecting to suburban locations. Phase 2 would create six overlapping bus rapid transit lines forming a complete ring around downtown Boston. Phase 3 includes the implementation of rail service on the most heavily traveled portion of the ring, from Assembly Square in southeastern Somerville to Nubian Square in the Roxbury neighborhood of Boston, via East Cambridge.

Phase 1 Edit

Phase 1, as recommended in the 2001 Major Investment Study, was to add interim service within 5 years while planning and construction took place for further phases. The three existing crosstown (CT) bus routes would have been modified, and eight additional crosstown routes added. Two express commuter (EC) routes would also have been added to provide radial service to portions of the corridor. (A third route, EC3, was dropped from consideration due to low projected ridership.) Phase 1 was to cost $98.5 million, primarily for acquisition of 100 new buses and expansion of bus garages. Because of the limited construction scope, it did not require further environmental review.[7]

Route Terminals Via
CT4 Ruggles JFK/UMass Dudley Square and Uphams Corner
CT5 Logan Airport terminals Sullivan Square Chelsea and Everett
CT6 Bellingham Square Kendall/MIT Community College and Lechmere
CT7 Kendall/MIT Franklin Park Zoo Kenmore, Ruggles, and Dudley Square
CT8 Sullivan Square Longwood Medical Area Union Square, University Park, Lower Cambridgeport, and Boston University
CT9 Kenmore Harvard Boston University and Allston Landing
CT10 Kenmore JFK/UMass Longwood Medical Area, MFA, Ruggles, Washington St/Silver Line, City Hospital, BU Medical Area, Newmarket/South Bay, Andrew
CT11 Longwood Medical Area Fields Corner station MFA, BU Medical, and Uphams Corner
EC1 Anderson/Woburn University Park Sullivan Square and Lechmere
EC2 Riverside Lechmere Newton Corner, Allston Landing, Central Square, and Kendall Square
EC3 Route 9 Natick Kenmore Wellesley Hills, Riverside, Newton Corner, and Longwood Medical Area

Phase 2 Edit

Draft EIR Edit

 
Map of the proposed Phase 2 system
 
MBTA-owned right of way along Ruggles Street, which would have been used for the Urban Ring busway

The MBTA filed the Draft Environmental Impact Report (DEIR) for Phase 2 with the Massachusetts Environmental Policy Act (MEPA) Office on November 30, 2004.[8] In its FY2005-10 and draft FY2006-11 Capital Improvement Plans, the MBTA has not budgeted any money for the Urban Ring project, beyond supporting the EIR process.[9]

Phase 2[10] would convert and expand five of the "crosstown" lines (CT2, CT3, CT4, CT5, and CT8) into bus rapid transit lines that overlap and form a complete ring around the urban core.

  • BRT 1: Airport Station to Kendall Square via Wellington, Assembly Square, Sullivan Square, and Lechmere
  • BRT 2: Logan Airport Terminals to Wellington with local service to Chelsea and Everett
  • BRT 3: Wellington to Kendall via Gilman Square, Union Square Somerville, and Lechmere
  • BRT 5: Lechmere to Ruggles via Kendall, Grand Junction/MIT, BU Bridge, Kenmore/Yawkey/Fenway, and Huntington Avenue
  • BRT 6: Commonwealth Ave at Boston University Central to UMass Boston via Ruggles, Melnea Cass Blvd, Uphams Corner
  • BRT 7: Longwood Medical Area to Mystic Mall via South Boston, World Trade Center, Ted Williams Tunnel, and Downtown Chelsea

BRT connections with the commuter rail lines would be improved by expanding the following existing stations:

The following new Commuter Rail stations would be created:

The new BRT lines would make additional connections at other commuter rail stops, rapid transit stops, and bus hubs.

Some parts of the BRT system would run in mixed traffic, including through the Ted Williams Tunnel and to the terminals at Logan International Airport. Dedicated lanes would be provided for certain portions, including:

Ridership was estimated at 106,000 passengers per day in 2010; capital cost was estimated at $500 million.

2008 revised draft EIR Edit

The revised route of the ring had the following stops:[11]

Station BRT routes Existing connections City / Neighborhood
Logan International Airport 2 Boston / East Boston
Airport 1, 2, 7 Boston / East Boston
Griffin Way 1, 2, 7 Chelsea
Downtown Chelsea 1, 2, 7 Chelsea
Mystic Mall 1, 7 Chelsea
Everett 1, 2 Everett
Wellington 1, 2 Medford
Assembly Square 1, 2 Somerville / Assembly Square
Sullivan Square 1, 2, 5 Boston / Charlestown
Inner Belt Road 1, 5 Somerville / Inner Belt
Lechmere 1, 5 Cambridge / East Cambridge
First Street 1, 5 Cambridge / East Cambridge
Binney Street 1, 5 Cambridge / East Cambridge
Broadway 1 Cambridge / Tech Square
Kendall/MIT 1, 5 Cambridge / Kendall Square
Massachusetts Ave / MIT 5 Cambridge / MIT campus
Cambridgeport 5 Cambridge / Cambridgeport
BU Bridge 5, 6 (at Boston University Central) Boston / Boston University campus
Yawkey 5, 6, 7 Boston / Fenway–Kenmore
Fenway 5, 6, 7 Boston / Fenway-Kenmore
LMA 5, 6, 7 Boston (Longwood Medical Area)
Ruggles 5, 6, 7 Boston / Roxbury
Washington Street 6, 7 Boston / Roxbury
Dudley Square 7 Boston / Roxbury
Crosstown Center 6, 7 Boston / Roxbury
BU Medical Center 7 Boston / BU Medical Center campus
Broadway 7 Boston / South Boston
A Street 7 Boston / South Boston
World Trade Center 7 Boston / Seaport
 
Construction of the Silver Line Gateway busway - the only part of the Urban Ring to enter construction - in Chelsea in 2015

Logan International Airport, Broadway, and Dudley Square were to be on short spurs, each served by only one route. There were to be two major spurs, both served only by the BRT 6 route. One was to JFK/UMass station, splitting from the main route near Crosstown Center with intermediate stations at Newmarket and Edward Everett Square. The other spur would run to Harvard station via Allston, with several possible alignments. Potential intermediate stations on different alignments included West Station, Cambridge Street, North Harvard Street, and Brighton Mills; all alignments included a Barrys Corner stop. A commuter rail platform was to be added at Sullivan Square to serve the Haverhill Line and Newburyport/Rockport Line.

An interim surface routing was proposed, with multiple stops in the Longwood Medical Area, while the tunnel would be under construction. The capital cost for this version of the plan was estimated at $2.2 billion, with a projected daily ridership of 170,000. Approximately 53% of the route was either in a bus-only lane, dedicated busway, or tunnel.[12] This was increased from the previous plan for Phase 2, to improve travel times. As a result of the implementation of Phase 2, ridership growth on the Red, Orange, Blue, and Green lines would be slowed, but Commuter Rail ridership boosted. The Urban Ring would have a higher collective ridership than the Orange Line, Blue Line, or the entire Commuter Rail system.[12]

Phase 3 Edit

Phase 3[13] would add a rail line on the most heavily traveled portion of the corridor, from Assembly Square in Somerville to Lechmere, Kendall Station, crossing Massachusetts Avenue near MIT, and connecting at Longwood Medical Area, Ruggles, and Nubian Square. The exact alignment would be determined through further environmental review, and included possible stops in Union Square Somerville, Cambridgeport and/or Kenmore Square, and a possible new tunnel under the Charles River.

There were three alternatives being considered for Phase 3, which differed from the alternatives described in the Major Investment Study (MIS) and Draft Environmental Impact Review (DEIR). Employment growth projections have also changed since those documents were written. The three proposed options for what type of rail service to build were:

  • A light rail branch of the Green Line, mostly on the surface
  • A light rail branch of the Green Line, entirely subway
  • A heavy rail branch of the Orange Line, entirely subway

Estimated ridership is 282,000–293,000 passengers per day in 2025; about 47,000 would be diverted from cars, and most of the rest would be diverted from trips on congested radial lines, reducing the need to travel through downtown Boston.

Partial implementation Edit

Since the suspension of the overall project, a segment of the original route was constructed, completing in 2018. The "Silver Line Gateway" service (route SL3) has commenced, connecting Downtown and South Boston to the inner-core city of Chelsea, with an intermediate stop serving Logan Airport. The route is a mix of dedicated right-of-way and shared street traffic segments, using articulated buses.

See also Edit

References Edit

  1. ^ a b eot Urban Ring Notice
  2. ^ a b , Executive Office of transportation, Commonwealth of Massachusetts, January 2009 (archived 2011)
  3. ^ Mullan, Jeffery B. (January 22, 2010). (PDF). Massachusetts Executive Office of Energy and Environmental Affairs. Archived from the original (PDF) on March 23, 2020. Retrieved October 31, 2019.
  4. ^ "As MBTA Issues Continue, Advocates Push for Transportation Funding Bill". NBC Boston. Retrieved 2020-03-04.
  5. ^ "Circumferential Transit Report". Boston Transportation Planning Review. Commonwealth of Massachusetts. October 1972. Retrieved 2014-02-11.
  6. ^ Central Transportation Planning Staff (15 November 1993). . National Transportation Library. Archived from the original on 5 October 2013. Retrieved 24 January 2013.
  7. ^ "Attachment 2: Detailed Descriptions, Plans, and Schedule of the Proposed Project by Phase". (PDF). Massachusetts Bay Transportation Authority. July 2001. pp. 1–6. Archived from the original (PDF) on November 8, 2001.
  8. ^ , MBTA. (archived 2006)
  9. ^ "MBTA Financials", MBTA. Also cf. , MBTA, (archived 2005)
  10. ^ Sources for this section: The official project brochure and Phase 2 Draft EIR.
  11. ^ (PDF). Massachusetts Executive Office of Transportation. November 2008. Archived from the original (PDF) on May 14, 2017.
  12. ^ a b Sempra Energy
  13. ^ Source: Official project brochure.

External links Edit

  • Massachusetts DoT Website for the Urban Ring Project 2013-01-26 at the Wayback Machine
  • Phase 2 plans 2013-07-28 at the Wayback Machine
  • GRAND JUNCTION FEASIBILITY REVIEW, December 22, 2016, City of Cambridge

urban, ring, project, mbta, this, article, needs, updated, please, help, update, this, article, reflect, recent, events, newly, available, information, 2019, urban, ring, proposed, project, massachusetts, transportation, authority, massachusetts, department, t. This article needs to be updated Please help update this article to reflect recent events or newly available information May 2019 The Urban Ring was a proposed project of the Massachusetts Bay Transportation Authority and the Massachusetts Department of Transportation to develop new public transportation routes that would provide improved circumferential connections among many existing transit lines that project radially from downtown Boston 1 The Urban Ring Corridor is located roughly one to two miles from downtown Boston passing through the Massachusetts cities of Boston Chelsea Everett Medford Somerville Cambridge and Brookline 1 The project was expected to convert 41 500 car trips to transit trips daily 2 MBTA Urban RingParentMassachusetts Bay Transportation AuthorityFoundedSuspended but partial implementation of some segments is proceedingHeadquarters10 Park Plaza Boston MA 02116LocaleBoston MassachusettsService areaBoston Chelsea Everett Medford Somerville Cambridge and BrooklineService typeBus rapid transitRoutes1 circumferential with 2 major spursStations31 proposedDaily ridership282 000 293 000 passengers per day in 2025 estimated Fuel typeDieselOperatorMBTAWebsitewww wbr massdot wbr state wbr ma wbr us wbr theurbanring wbr The Major Investment Study split the project into three phases the first of which enhanced bus service was partially implemented The planning of Phase 2 was suspended in January 2010 because MBTA and the Commonwealth of Massachusetts have insufficient funding to build a substantial portion of that phase projected to cost 2 4 billion 2 3 As of 2019 update some interim bus service improvements have been implemented or are underway in the absence of major funding Contents 1 Background 2 Project proposal 3 Phase 1 4 Phase 2 4 1 Draft EIR 4 2 2008 revised draft EIR 5 Phase 3 6 Partial implementation 7 See also 8 References 9 External linksBackground EditTransportation advocates in Boston have complained that rail transit riders cannot travel from one outlying area to another without first traveling to the downtown hub stations changing lines and traveling outbound again Some of the radial transit lines notably the Green Line are so overcrowded that service is very slow and limited in capacity because of rush hour crush loads There are several crosstown bus lines such as the 1 66 CT1 CT2 and CT3 routes but they are slow unreliable and subject to bus bunching because they must operate in mixed street traffic 4 A circumferential rapid transit line was proposed by the City of Boston as early as 1923 and circumferential transit has been studied as early as 1972 in the Boston Transportation Planning Review 5 Detailed proposals were not studied until the late 1990s 6 Project proposal EditThe proposed project has three phases The first phase has been partially implemented Phase 1 as it is commonly called involves expanding crosstown bus lines serving the entire corridor and express commuter lines connecting to suburban locations Phase 2 would create six overlapping bus rapid transit lines forming a complete ring around downtown Boston Phase 3 includes the implementation of rail service on the most heavily traveled portion of the ring from Assembly Square in southeastern Somerville to Nubian Square in the Roxbury neighborhood of Boston via East Cambridge Phase 1 EditPhase 1 as recommended in the 2001 Major Investment Study was to add interim service within 5 years while planning and construction took place for further phases The three existing crosstown CT bus routes would have been modified and eight additional crosstown routes added Two express commuter EC routes would also have been added to provide radial service to portions of the corridor A third route EC3 was dropped from consideration due to low projected ridership Phase 1 was to cost 98 5 million primarily for acquisition of 100 new buses and expansion of bus garages Because of the limited construction scope it did not require further environmental review 7 Route Terminals ViaCT4 Ruggles JFK UMass Dudley Square and Uphams CornerCT5 Logan Airport terminals Sullivan Square Chelsea and EverettCT6 Bellingham Square Kendall MIT Community College and LechmereCT7 Kendall MIT Franklin Park Zoo Kenmore Ruggles and Dudley SquareCT8 Sullivan Square Longwood Medical Area Union Square University Park Lower Cambridgeport and Boston UniversityCT9 Kenmore Harvard Boston University and Allston LandingCT10 Kenmore JFK UMass Longwood Medical Area MFA Ruggles Washington St Silver Line City Hospital BU Medical Area Newmarket South Bay AndrewCT11 Longwood Medical Area Fields Corner station MFA BU Medical and Uphams CornerEC1 Anderson Woburn University Park Sullivan Square and LechmereEC2 Riverside Lechmere Newton Corner Allston Landing Central Square and Kendall SquareEC3 Route 9 Natick Kenmore Wellesley Hills Riverside Newton Corner and Longwood Medical AreaPhase 2 EditDraft EIR Edit nbsp Map of the proposed Phase 2 system nbsp MBTA owned right of way along Ruggles Street which would have been used for the Urban Ring buswayThe MBTA filed the Draft Environmental Impact Report DEIR for Phase 2 with the Massachusetts Environmental Policy Act MEPA Office on November 30 2004 8 In its FY2005 10 and draft FY2006 11 Capital Improvement Plans the MBTA has not budgeted any money for the Urban Ring project beyond supporting the EIR process 9 Phase 2 10 would convert and expand five of the crosstown lines CT2 CT3 CT4 CT5 and CT8 into bus rapid transit lines that overlap and form a complete ring around the urban core BRT 1 Airport Station to Kendall Square via Wellington Assembly Square Sullivan Square and Lechmere BRT 2 Logan Airport Terminals to Wellington with local service to Chelsea and Everett BRT 3 Wellington to Kendall via Gilman Square Union Square Somerville and Lechmere BRT 5 Lechmere to Ruggles via Kendall Grand Junction MIT BU Bridge Kenmore Yawkey Fenway and Huntington Avenue BRT 6 Commonwealth Ave at Boston University Central to UMass Boston via Ruggles Melnea Cass Blvd Uphams Corner BRT 7 Longwood Medical Area to Mystic Mall via South Boston World Trade Center Ted Williams Tunnel and Downtown ChelseaBRT connections with the commuter rail lines would be improved by expanding the following existing stations Downtown Chelsea Newburyport Rockport Line Yawkey Framingham Worcester Line project initiated construction scheduled for completion in 2014 Ruggles inbound platform for Northeast corridor The following new Commuter Rail stations would be created Sullivan Square near junction of Newburyport Rockport and Haverhill Reading Lines Gilman Square Lowell Line Union Square Fitchburg Line The new BRT lines would make additional connections at other commuter rail stops rapid transit stops and bus hubs Some parts of the BRT system would run in mixed traffic including through the Ted Williams Tunnel and to the terminals at Logan International Airport Dedicated lanes would be provided for certain portions including The Grand Junction Railroad right of way which runs through the campus of the Massachusetts Institute of Technology and crosses the Charles River under the Boston University Bridge Railroad right of way in Somerville connecting with Lechmere Portions from East Boston to Chelsea Melnea Cass Boulevard connecting the Silver Orange and Green Lines E Branch The Haul Road in South BostonRidership was estimated at 106 000 passengers per day in 2010 capital cost was estimated at 500 million 2008 revised draft EIR Edit The revised route of the ring had the following stops 11 Station BRT routes Existing connections City NeighborhoodLogan International Airport 2 Silver Line Boston East BostonAirport 1 2 7 Blue Line Boston East BostonGriffin Way 1 2 7 ChelseaDowntown Chelsea 1 2 7 Newburyport Rockport Line ChelseaMystic Mall 1 7 ChelseaEverett 1 2 EverettWellington 1 2 Orange Line MedfordAssembly Square 1 2 Somerville Assembly SquareSullivan Square 1 2 5 Orange Line Boston CharlestownInner Belt Road 1 5 Somerville Inner BeltLechmere 1 5 Green Line Cambridge East CambridgeFirst Street 1 5 Cambridge East CambridgeBinney Street 1 5 Cambridge East CambridgeBroadway 1 Cambridge Tech SquareKendall MIT 1 5 Red Line Cambridge Kendall SquareMassachusetts Ave MIT 5 Cambridge MIT campusCambridgeport 5 Cambridge CambridgeportBU Bridge 5 6 Green Line B branch at Boston University Central Boston Boston University campusYawkey 5 6 7 Framingham Worcester Line Boston Fenway KenmoreFenway 5 6 7 Green Line D branch Boston Fenway KenmoreLMA 5 6 7 Boston Longwood Medical Area Ruggles 5 6 7 Orange Line Providence Stoughton Line Needham Line Franklin Foxboro Line Boston RoxburyWashington Street 6 7 Silver Line Boston RoxburyDudley Square 7 Silver Line Boston RoxburyCrosstown Center 6 7 Boston RoxburyBU Medical Center 7 Boston BU Medical Center campusBroadway 7 Red Line Boston South BostonA Street 7 Boston South BostonWorld Trade Center 7 Silver Line Boston Seaport nbsp Construction of the Silver Line Gateway busway the only part of the Urban Ring to enter construction in Chelsea in 2015Logan International Airport Broadway and Dudley Square were to be on short spurs each served by only one route There were to be two major spurs both served only by the BRT 6 route One was to JFK UMass station splitting from the main route near Crosstown Center with intermediate stations at Newmarket and Edward Everett Square The other spur would run to Harvard station via Allston with several possible alignments Potential intermediate stations on different alignments included West Station Cambridge Street North Harvard Street and Brighton Mills all alignments included a Barrys Corner stop A commuter rail platform was to be added at Sullivan Square to serve the Haverhill Line and Newburyport Rockport Line An interim surface routing was proposed with multiple stops in the Longwood Medical Area while the tunnel would be under construction The capital cost for this version of the plan was estimated at 2 2 billion with a projected daily ridership of 170 000 Approximately 53 of the route was either in a bus only lane dedicated busway or tunnel 12 This was increased from the previous plan for Phase 2 to improve travel times As a result of the implementation of Phase 2 ridership growth on the Red Orange Blue and Green lines would be slowed but Commuter Rail ridership boosted The Urban Ring would have a higher collective ridership than the Orange Line Blue Line or the entire Commuter Rail system 12 Phase 3 EditPhase 3 13 would add a rail line on the most heavily traveled portion of the corridor from Assembly Square in Somerville to Lechmere Kendall Station crossing Massachusetts Avenue near MIT and connecting at Longwood Medical Area Ruggles and Nubian Square The exact alignment would be determined through further environmental review and included possible stops in Union Square Somerville Cambridgeport and or Kenmore Square and a possible new tunnel under the Charles River There were three alternatives being considered for Phase 3 which differed from the alternatives described in the Major Investment Study MIS and Draft Environmental Impact Review DEIR Employment growth projections have also changed since those documents were written The three proposed options for what type of rail service to build were A light rail branch of the Green Line mostly on the surface A light rail branch of the Green Line entirely subway A heavy rail branch of the Orange Line entirely subwayEstimated ridership is 282 000 293 000 passengers per day in 2025 about 47 000 would be diverted from cars and most of the rest would be diverted from trips on congested radial lines reducing the need to travel through downtown Boston Partial implementation EditMain article Silver Line MBTA Extension to Chelsea Since the suspension of the overall project a segment of the original route was constructed completing in 2018 The Silver Line Gateway service route SL3 has commenced connecting Downtown and South Boston to the inner core city of Chelsea with an intermediate stop serving Logan Airport The route is a mix of dedicated right of way and shared street traffic segments using articulated buses See also EditInterstate 695 Massachusetts a 1960s proposed but cancelled highway involving many of the same communities Mid City Transitway in Chicago ILReferences Edit a b eot Urban Ring Notice a b Urban Ring Phase 2 Fact Sheet Executive Office of transportation Commonwealth of Massachusetts January 2009 archived 2011 Mullan Jeffery B January 22 2010 Re Urban Ring Phase 2 EOEEA 12565 PDF Massachusetts Executive Office of Energy and Environmental Affairs Archived from the original PDF on March 23 2020 Retrieved October 31 2019 As MBTA Issues Continue Advocates Push for Transportation Funding Bill NBC Boston Retrieved 2020 03 04 Circumferential Transit Report Boston Transportation Planning Review Commonwealth of Massachusetts October 1972 Retrieved 2014 02 11 Central Transportation Planning Staff 15 November 1993 The Transportation Plan for the Boston Region Volume 2 National Transportation Library Archived from the original on 5 October 2013 Retrieved 24 January 2013 Attachment 2 Detailed Descriptions Plans and Schedule of the Proposed Project by Phase Circumferential Transit Improvements in the Urban Ring Corridor Expanded Environmental Notification Form ENF PDF Massachusetts Bay Transportation Authority July 2001 pp 1 6 Archived from the original PDF on November 8 2001 Urban Ring Documents Library MBTA archived 2006 MBTA Financials MBTA Also cf Inside the T Capital Investment Program The FY06 FY10 Capital Investment Program MBTA archived 2005 Sources for this section The official project brochure and Phase 2 Draft EIR The Urban Ring Phase 2 Revised Draft Environmental Impact Report Statement PDF Massachusetts Executive Office of Transportation November 2008 Archived from the original PDF on May 14 2017 a b Sempra Energy Source Official project brochure External links EditMassachusetts DoT Website for the Urban Ring Project Archived 2013 01 26 at the Wayback Machine Phase 2 plans Archived 2013 07 28 at the Wayback Machine GRAND JUNCTION FEASIBILITY REVIEW December 22 2016 City of Cambridge Retrieved from https en wikipedia org w index php title Urban Ring Project MBTA amp oldid 1175824393, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.