fbpx
Wikipedia

Trans Mountain pipeline

The Trans Mountain Pipeline System, or simply the Trans Mountain Pipeline (TMPL), is a multiple product pipeline system that carries crude and refined products from Edmonton, Alberta, to the coast of British Columbia, Canada.[1][2]

Trans Mountain Pipeline (TMPL)
Trans Mountain pipeline route from Edmonton to Burnaby
Location
CountryCanada
ProvinceAlberta and British Columbia
FromEdmonton, Alberta
ToBurnaby, British Columbia
General information
Typemultiple product pipelines: crude oil, refined petroleum products such as jet fuel, gasoline, diesel[1]
StatusGovernment of Canada
OwnerTrans Mountain Corporation (TMC) (Canada Development Investment Corporation)
Commissioned1951
Technical information
Length1,150 km (710 mi)
Diameter610 mm (24 in)

The corporation was created in 1951, construction began in 1952, and operations commenced in 1953. It is the only pipeline to run between these two areas.

The construction of a second pipeline between Hinton, Alberta, and Hargreaves, British Columbia, running adjacent to the existing line, was completed in 2008.[3]

In 2013, a project to twin the existing Trans Mountain pipeline—the Trans Mountain Expansion Project—was proposed to the Canadian National Energy Board.[4] The project was 75% complete, as of January 2023.[5] The expansion, which runs roughly parallel to the existing pipeline, will increase capacity from 300,000 barrels per day (48,000 m3/d) to 890,000 barrels per day (141,000 m3/d).

Since it was first proposed in 2013, this Trans Mountain Expansion Project has attracted controversy due to its potential environmental impact, having faced legal challenges, as well as protests from environmentalists and First Nations groups. A Supreme Court decision on July 2, 2020, that rejected the appeals made by First Nations and environmental groups, "[brought] an end to the years-long legal challenge".[6]

On August 31, 2018, the Government of Canada purchased the pipeline for $4.5 billion from Kinder Morgan through the creation of the Trans Mountain Corporation (TMC), in order to "keep the project alive".[7] TMC is a Crown corporation, a subsidiary of the Canada Development Investment Corporation (CDEV).[8] Until the purchase by CDEV, the Trans Mountain Pipeline was owned by the Houston, Texas-based pipeline operator's Canadian division.

History edit

In February 1947, large oil deposits were discovered near Leduc, Alberta. The idea for a pipeline from Alberta to British Columbia quickly emerged, driven by the growing demand for oil both in Asia and on the west coast of Canada and the United States. The US military was also interested in developing this infrastructure so that oil could be accessed more easily for military use.[citation needed]

On March 21, 1951, the Trans Mountain Pipeline Company Trans Mountain was created when the Canadian Parliament granted the company a charter under a special act of Parliament.[9] The proposal for the pipeline was immediately submitted to the Board of Transport Commissioners and was approved. Construction began in February 1952 and the final section was welded in place near Aldergrove, British Columbia, on October 17, 1952.[9]

According to a 2019 JWN Energy series—Inside Canada's Pipeline Industry—by former editor of Oilweek, Gordon Jaremko, both the Board approval and the construction of the 1,150-kilometre (710 mi) pipeline were sped up as concerns about the Korean War mounted. The governments considered the TMPL to be a strategic way of reducing reliance on oil tankers, made vulnerable under threats of potential attack on the west coast of North America.[10]

Canadian Bechtel Ltd. was responsible for engineering, design, and construction of the project. Ownership of the company was split between Canadian Bechtel Ltd. and Standard Oil.[clarification needed]

In August 1953, crude oil from Edmonton, Alberta, began flowing to refineries in the Vancouver area and the northwestern U.S. through TNPL.[10]

The total cost of TMPL was $93 million, according to then Premier of British Columbia W. A. C. Bennett at the opening ceremony.[11][12]

Prior to 1983, the only product TMPL carried was crude oil to supply refineries in the Vancouver area and to the state of Washington.[1]

Shift from single- to multiple products pipelines (1983-) edit

In 1983, Trans Mountain began experiments to shift from single- to multiple-product pipelines to increase efficiency and to become more competitive.[1] By 1985, TMPL regularly carried refined-products 820 kilometres (510 mi) from Edmonton to Kamloops, British Columbia. This had extended to Vancouver by 1993.[1]

A 1993 report said that the TMPL was the "only major system in the world" at that time, transporting both crude oil and refined petroleum products" in a single pipeline.[13][1]

By 1998, TMPL made regular shipments to Vancouver of refined petroleum products "including jet fuel, gasoline (unleaded and premium unleaded), diesel (regular sulfur, low sulfur, and low temperature), methyl tertiary butyl ether (MTBE), and crude-oil (light sweet, light sour, and heavy)".[1]

In 2004, Kinder Morgan began the process to add a second pipeline, running parallel to the first, for the portion running between Hinton, Alberta, and Hargreaves, British Columbia. This required two more pumping stations – the Wolf Pump Station, near Niton Junction, Alberta, and the Chappel Pump Station, near Pyramid Creek Falls Provincial Park, British Columbia. This increased capacity by 40,000 barrels per day (6,400 m3/d), (from 260,000 to 300,000 barrels per day (41,000 to 48,000 m3/d)).[3]

TMPL and oil refineries edit

Shell, Petro-Canada and Imperial closed refineries in British Columbia in the 1990s and expanded their refineries in the Edmonton area following the TMPL construction.[14] TMPL had the capacity to carry refined products, as well as crude oil via the batch system.[14] According to a 2016 Oil Sands Magazine article, this resulted in the conversion of existing refineries along the TMPL route into storage and distribution facilities and terminals.[14] In 1983, Kamloops' Royalite Refinery, was shutdown.[14] In 1993, two refineries were closed—Shell's in North Burnaby—a large Vancouver neighbourhood—and Petro-Canada's in Port Coquitlam—27 km (17 mi) east of Vancouver—were closed.[14] In 1995, Imperial Oil closed their refinery in Port Moody—a city that is part of the Metro Vancouver Regional District.[14]

Spill history edit

As of 2017, TMPL had reported approximately 84 spills to Canada's National Energy Board since 1961.[15][16] Although a majority occurred at contained zones such as pumping stations, and a majority were below the mandatory reporting threshold of 1.5 cubic metres, there were some significant spill events.

In Abbotsford in 2005, a ruptured pipeline dumped 210 m3 (1,300 bbl) of crude oil. The company attributed the accident to activity on a neighbouring property.[17] In 2007, in Burnaby, a contractor working on a sewage project for the City of Burnaby ruptured a pipeline, causing spillage of 224–234 m3 (1,410–1,470 bbl) of crude oil. Some of it flowed into Burrard Inlet via the Burnaby storm sewer system. Most of it was recovered. Eleven houses were sprayed with oil, and about 225–250 residents were evacuated or left voluntarily. Cleanup took more than a year.[18][19][20][21] In 2009, in Burnaby 305 m3 (1,920 bbl) of crude oil were released from a tank at the Trans Mountain Burnaby Terminal. Most of it flowed into a containment area.[22] In Sumas in 2012 90 m3 (570 bbl) of light crude oil leaked from a Sumas Mountain holding tank. All of it flowed into a containment area.[23] In 2020, in Sumas, 190.0 m3 (1,195 bbl) of light crude leaked from small pipe connected to mainline. Trans Mountain reported on June 14 that the spill was contained on the property and that groundwater was monitored for contamination.[24]

Trans Mountain Expansion Project edit

On June 18, 2013, Kinder Morgan filed an application with the Canadian National Energy Board pursuant to Part III of the National Energy Board Act[4] to build a second pipeline under the Trans Mountain Pipeline Expansion Project.[25] The second pipeline was to run roughly parallel to the existing pipeline, between Edmonton and Burnaby, (east of Vancouver) and to be used to transport diluted bitumen, also known as dilbit. The additional pipeline requires 12 new pumping stations. The proposed expansion, with 980 kilometres (610 mi) of pipe, would increase the system's capacity from 300,000 barrels per day (48,000 m3/d) to 890,000 barrels per day (141,000 m3/d). In 2016, the cost of completing the connection between Strathcona County, Alberta, and Burnaby, British Columbia was estimated at $6.8 billion in 2013.[26]

 
Trans Mountain Pipeline, in green, with other Canadian Energy Regulator managed pipelines.

Kinder Morgan had the support at that time of several large petroleum industry customers for this expansion, (BP Canada Energy Trading Co., Canadian Natural Resources, Canadian Oil Sands Ltd., Cenovus Energy Inc., Devon Canada Corp., Husky Energy Marketing Inc., Imperial Oil Ltd., Nexen Marketing Inc., Statoil Canada Ltd., Suncor Energy Marketing Inc., Suncor Energy Products Partnership, Tesoro Refining & Marketing Co, and Total E&P Canada Ltd).[27]

In 2016, B.C. stated it did not support Trans Mountain, partly because Kinder Morgan has not provided enough information about its proposed spill prevention and spill clean-up program.[28] On November 29, 2016, Canada's federal cabinet approved the expansion project, announcing that the approval was "subject to 157 binding conditions that will address potential Indigenous, socio-economic and environmental impacts, including project engineering, safety and emergency preparedness."[29]

On January 11, 2017, B.C. Premier Christy Clark announced British Columbia's support for the expansion of the Trans Mountain pipeline, saying the project met her government's five conditions for approval and includes a revenue-sharing agreement worth up to $1 billion.[30]

In 2018, the federal government created the Crown corporation, the Trans Mountain Corporation (TMC) when it bought the pipeline from the Houston-based Kinder Morgan for C$4.5 billion.[7][31] The purchase had been announced by the federal government in May 2018. At that time, the government said it would seek outside investors to complete the expansion. These investors would also be indemnified for any delays induced by provincial or municipal governments.

In 2020, three insurance companies that had previously supported the project withdrew their support, including Zurich Insurance Group, the leading insurer. The company that is advancing the project says that it still has enough insurance coverage.[32]

By February 2020, the assessment for the completion of the project was estimated at $12.6 billion, an increase of the previous estimate of $7.4 billion.[31] The cost increase was the result of rising costs of "labour, steel, and land".[33]

In a September 2020 interview with the Canadian Press, TMC's CEO Ian Anderson said that the expansion was on schedule despite the $5.2-billion increase in its cost.[34] Anderson cited other challenges to construction including the COVID-19 pandemic, the slump in the demand for fuel, which contributes to the slump in the price of oil,[35] and the ongoing protests by opponents to the expansion.[34]

By February 2022, the Crown corporation that owned Trans Mountain, TMC, said that costs had increased by 70%, from $12.6 billion to $21.4 billion.[7] Faced with the federal government's costly COVID-19 response, Finance Minister Chrystia Freeland, said this new funding for the pipeline was not part of the federal government's commitment.[7] The status of the company changed to a non-agent Crown corporation on April 29, 2022, which meant that it was able to access financing from third-party lenders.[5] In March 2023, it was announced that the cost has again increased to $30.9 billion.[36]

As of April 2022, construction had reached the half-way mark.[37] The company said in their November 29, 2022 third quarter report that expansion would be mechanically complete by the third quarter of 2023 and the commercial service would be operational in the fourth quarter of 2023.[38][5]

According to a January 11, 2023 statement from the company, more than 700 kilometres (430 mi) of pipe was already in place representing 75% of the entire project.[5]

Debate edit

The expansion project has faced criticism, particularly from environmentalists and First Nations groups. To reach the terminus, tankers have to pass through a very narrow channel of shallow water from the open sea, still putting leaks at risk due to vehicle crashes.[39] Environmentalists have expressed concern about the heightened risk of an oil spill in the Burrard Inlet resulting from the expansion, which entails the obstruction of 30% of the inlet and a seven-fold increase in tanker traffic, according to Stand.earth, formerly ForestEthics.[40]

Those who support the pipeline say that it will create jobs and that it has a lower risk of spilling oil than transporting oil by rail, which pipeline proponents say would otherwise have to be used.[41]

A 2014 study by Simon Fraser University claimed that Kinder Morgan overestimated the economic benefits of the pipeline expansion.[42] From 2008 through 2018, Western Canadian Select (WCS), Canada's benchmark for heavy crude oil sold at an average discount of US$17 against the benchmark for light oil, West Texas Intermediate (WTI). This widened to a record US$50 in the fall of 2018 with the price of WCS hitting a record low of less than US$14 a barrel.[43][44]

Despite federal government approval, seven Federal Court challenges were filed by the municipalities of Vancouver and Burnaby, and the Tsleil-Waututh, Squamish, Kwantlen, and Coldwater First Nations.[45] In November 2017, Minister of Natural Resources Jim Carr stated that the federal government had sent a letter in support of a dispute resolution process to the National Energy Board to expedite any future disputes over provincial or municipal permits impeding the expansion. BC Environmental Minister George Heyman accused the federal government of interfering with an independent review of the project, arguing that "it's both a highly unusual and a highly troubling intrusion on a province's right to enforce its own permits, its own regulations and the interests of its own citizens".[46][47]

On January 30, 2018, the B.C. government proposed a restriction on increases to the amount of diluted bitumen that can be imported into the province from Alberta, until the completion of studies on whether potential spillage could be mitigated. The province also announced an intent to consult with local communities and First Nations among others. Alberta premier Rachel Notley criticized the proposal as being a stalling tactic on Trans Mountain expansion, explaining that "the B.C. government has every right to consult on whatever it pleases with its citizens. It does not have the right to rewrite our constitution and assume powers for itself that it does not have." On February 6, 2018, Notley ordered the Alberta Gaming and Liquor Commission to cease future imports of British Columbia wine as a retaliatory sanction over these moves.[48][49] The wine sanctions were lifted on February 22, 2018.[50]

On April 8, 2018, Kinder Morgan suspended "non-essential" activities relating to the pipeline, as the company did not want to "put [its] shareholders at risk on the remaining project spend". The company stated that it would attempt to reach agreements on a funding plan with stakeholders by May 31.[51] On April 16, 2018, the Alberta government introduced the Preserving Canada's Economic Prosperity Act, which would give the Minister of Energy power to regulate the export of crude oil, natural gas, or refined fuel from Alberta. The bill could be used to effectively ban the export of Alberta gas to British Columbia. As such, B.C. Attorney General David Eby threatened to sue Alberta over the proposed bill, as he considered it unconstitutional, and stated that it could have a further impact on gasoline prices in the province.[52][53][54]

On May 29, 2018, the Canadian federal government announced its intent to acquire the Trans Mountain Pipeline from Kinder Morgan for $4.5 billion. The government does not intend to remain the permanent owner of the pipeline, as it plans to seek outside investors to finance the twinning project. If the government cannot find a buyer before the consummation of the purchase, it will carry out the purchase via a crown corporation, and operate it in the meantime. The eventual owner will be indemnified by the government for any delays or hindrances to the project that result from legal actions by provincial or municipal governments. The government will also have the option to cover costs or purchase the pipeline back if the new owner is unable to complete the project due to legal pressure, or, despite reasonable efforts, cannot complete the project by an established deadline.[55][56]

Critics[who?] of the expansion argued[where?] that this proposed purchase was a taxpayer-funded bailout of the project. B.C. Premier John Horgan stated that the sale would not affect the provincial government's ongoing efforts to block the pipeline expansion, stating that "rather than go to the court to determine jurisdictions, they're making financial decisions that affect taxpayers and they'll have to be accountable for that". Stewart Phillip, president of the Union of British Columbia Indian Chiefs, stated that the union was "absolutely shocked and appalled that Canada is willingly investing taxpayers' money in such a highly controversial fossil fuel expansion project".[57]

On August 30, 2018, Kinder Morgan Canada's shareholders voted to approve the sale of the pipeline to the federal government.[58] However, the same day, the Federal Court of Appeal overturned the government's approval of the expansion project, citing that it did not sufficiently fulfill its constitutional duties to consult local First Nations groups,[59][60] and because it lacked an environmental assessment of increased tanker traffic on orcas in the Salish Sea[61] off the BC coast.[62] On August 31, Trudeau said the federal government remained committed to the pipeline expansion project in spite of this setback.[63][64] In response to the approval being overturned, Premier Rachel Notley announced that Alberta would pull out of the national carbon price and called for an appeal to the Supreme Court of Canada of the federal court's August 30 decision.[64]

Protests edit

The expansion project faced opposition from civic governments, First Nations, environmentally concerned citizens, and others. In September 2012, Tsleil-Waututh leaders had hoped to shut down the project altogether.[65]

In November 2014, opponents of the pipeline expansion camped in Burnaby Mountain Park to block pipeline construction crews, and over 100 were arrested.[34] Members of the Squamish and Tsleil-Waututh First Nations of British Columbia paddled canoes on the waters of Burrard Inlet, in North Vancouver, to Kinder Morgan's Burnaby Terminal for a ceremony to protest the expansion of the Trans Mountain pipeline.[65] In a 2020 Global News interview, with the pipeline expansion work underway again, Grand Chief Stewart Phillip, president of the Union of BC Indian Chiefs, said that he expected that there would be more "Burnaby Mountain-style" protests.[34]

Protests took place in Vancouver to stop work on the pipeline on September 19, 2017.

 
A protester holds a sign that says "No Consent No Pipeline" at a rally in 2017
 
Burnaby Mayor Derek Corrigan addresses the crowd, at the STOP KINDER MORGAN protest rally

Burnaby Mayor Derek Corrigan addressed the crowd at a Stop Kinder Morgan protest rally in Burnaby Mountain Park. By 2018, rallies opposing the projects had been organized across Canada. Organizations including LeadNow and the Dogwood Initiative have also opposed the project and organized protests.[66][67]

The RCMP contained the protests on Burnaby Mountain.

In July 2018 activists blocked an oil tanker from the Ironworkers Memorial Bridge in Vancouver.[68]

In September 2021 a treetop camp in the Brunette River Conservation Area was dismantled by RCMP following a court injunction. The protest camp had been occupied by protesters since December 2020, and a leader of the protest claimed further actions would be planned.[69]

Secwépemc opposition edit

According to Aboriginal Peoples Television Network, since 2013 Secwépemc community members, primarily women, have been defending their traditional land (known as Secwepemcul’ecw) against the proposed expansion of the pipeline, asserting that the expansion was approved without sufficient consultation. The expansion would cross 518 km of Secwépemc territory. The land defenders (as they call themselves; some media refers to them as protesters and activists) are concerned about the damage to the land and water the pipeline passes through, in particular the disruption of salmon populations, violation of the Declaration on the Rights of Indigenous Peoples, and violation of traditional Secwépemc law, founded by the Okanagan Shuswap Confederacy. Their claim is that the First Nation band governments only have jurisdiction through Canadian law on their reserves, whereas traditional Secwépemc leadership retains sovereignty over Secwepemcul’ecw.[70]

Since July 2018, a Secwépemc protest camp has been occupied just outside of Blue River, British Columbia, where there are plans to drill under the river.[71] That camp, established by a group known as the Tiny House Warriors, is located near a planned "work camp" (referred to by Indigenous dissenters as a "man camp" because of the predominance of men in the demographics of pipeline workers).[72] The establishment of the camp led Kúkpi7 (Chief) Rosanne Casimir of Tk’emlúps te Secwépemc First Nation (TteS), along with Chief Shelly Loring of Simpcw First Nation to issue a joint statement asking the Tiny House Warriors to stand down, claiming it was the Warriors violating Secwépemc law.[73]

In early September 2020, protester Loralie Dick chained herself to the TMX worksite in Kamloops before being arrested by the RCMP for violating a B.C. Supreme Court injunction from 2018 that barred land defenders from blocking work.[71][73]

In early October 2020, a protest camp was set up along the Thompson River, along the proposed route of the expansion. One of the residents of the Thompson River camp was Secwépemc matriarch Miranda Dick, who told reporters there were an average of 20 people at the camp as of October 5th. At the time it was set up, Kúkpi7 Casimir said she had no issue with the protest camp, so long as health and safety guidelines were followed.[74] On October 9, in response to TMX workers being seen surveying in preparation to drill under the river, the camp was moved directly in the way of the expansion. On October 10, the Secwépemc delivered a cease and desist notice to TMX for the second time.[75] On October 11 it was moved again due to a chemical leak in the river. By October 15, the RCMP had begun arresting people connected to the camp, including Hereditary Chief Segwses, Loralie Dick, April Thomas, Billie Pierre and Romilly Cavanaugh.[71] In February 2020, Segwses and his daughter gave themselves up for arrest for participating in the 2020 Canadian pipeline and railway protests, in order to prevent the RCMP from snuffing a sacred fire as well as to prevent the escalation of a confrontation.[75]

On October 17, 2020, Dick cut her hair in ceremony before the gates of the expansion project. Soon after the ceremony, she and four other women were arrested by RCMP officers.[70] One was arrested without charges, while the other four are set to appear in court in January 2021.[71] In a statement released the following day, TteS Kúkpi7 Rosanne Casimir thanked the RCMP for maintaining peace and order and stated that she and the elected council did not endorse the protesters. TteS is one of several First Nations bands that have signed agreements with Trans Mountain. Casimir's statement asserted that the council "[had] not sold or ceded or given anything away" but that "[they had] upheld [their] jurisdictional rights."[76]

Phase III consultations (November 2018-) edit

In response to the Federal Court's overturning the federal authorization of Trans Mountain, the Canadian Government "reinitiated Phase III consultations" with Natural Resources Canada as lead and Justice Frank Iacobucci appointed by the government to oversee consultations. An NEB panel heard three weeks of Indigenous traditional testimony with 117 Indigenous groups impacted by the pipeline, beginning on November 19,[61] with sessions in Calgary, Victoria and Nanaimo.[77]

The Trudeau government restricted the Phase III hearings in terms of time and scope.[61] The government gave the NEB a "tight timeline" with a final report due on February 22, 2019.[61] The hearings are also restricted by the NEB panel to investigate "new information" as it relates to the impact of increased oil tanker traffic to and from the Westridge Marine Terminal in Burrard Inlet, Burnaby to Canada's 12-nautical-mile territorial waters. The environmental concern in this area includes the Salish Sea's southern resident killer whales' (SRKW) prime Chinook salmon feeding ground. By November 2018, there were only 74 SRKW left.[61] Noise and pollution from marine vessels along with the diminishing stocks of salmon – their prime source of food – have contributed to the whales' declining numbers.[61]

Hearings in the form of pipeline roundtable meetings with Trans Mountain representative and indigenous groups took place in Calgary in November, and in Kamloops and Nanaimo in December, with the summary expected in January.[62][77]

Government of Canada June 18, 2019 approval of TMX edit

On June 18, 2019, the federal government through the Governor in Council (GIC) confirmed the approval of federally-owned TMX project. The twinned pipeline will have the capacity to carry almost 1 million bpd from Alberta to the coast of British Columbia.[78] The National Energy Board, Prime Minister Justin Trudeau and his cabinet agreed that the TMX was in the "national interest" as it would add "tens of billions of dollars" to government revenue as well as sustaining thousands of jobs.[78] Both the NEB and the federal government acknowledged that there was a possibility that TMX could "damage the environment and marine life", but the benefits outweighed the risks.[78]

Prime Minister Trudeau said that the revenue from TMC, which was estimated at $500 million annually just in federal corporate taxes, would be invested in "unspecified clean energy projects".[78][4][79]

In their letter sent to both Trans Mountain and the lawyers representing the Tsleil-Waututh Nation, the NEB wrote that within the context of "substantial" and "significant" interest and participation on the part of Indigenous peoples and the general public, including the August 30, 2018 decision in Tsleil-Waututh Nation v. Canada,[80] the NEB's regulatory oversight processes for the next phases of the Trans Mountain Expansion Project "lifecycle", which include "detailed route approvals", such as potential "routing and non-routing", would include a public comment period.[80]

SCC 2020 decisions dismissing appeals challenging TMX edit

By December 2019, the legal basis of the expansion was challenged in Canada's Federal Court of Appeal as politicians, environmentalists and some Indigenous groups returned to the courts and pressed the issue of Aboriginal title.[81] Some Indigenous groups, such as the Kehewin Cree Nation, T'Sou-ke Nation, Frog Lake First Nation, Scia'new First Nation, Simpcw First Nation, Pellt'iq't First Nation and Squiala First Nation formed the Western Indigenous Pipeline Group (WIPG) and have sanctioned the project for ownership stakes. Others, like the Coldwater Indian Band, have unsettled issues. These issues include disputes over the compensation from the institution of the first pipeline right-of-way in the 1950s, as well as future water supply risks that they would assume.

In February 2020, a Federal Court of Appeal denied the request by environment and Indigenous groups to "consider whether there had been sufficient consultation".[6]

A March 5, 2020 Supreme Court March, "decided not to hear five challenges from environment and Indigenous groups".[6]

On July 2, 2020, the Supreme Court of Canada rejected appeals by the Squamish Nation, Tsleil-Waututh Nation, and Coldwater Indian Band and others challenging federal approval of the Trans Mountain pipeline expansion project, "bringing an end to the years-long legal challenge".[6]

See also edit

Notes edit

References edit

  1. ^ a b c d e f g Baum, Judy S.; Marzocco, Ken E.; Hansen, Larry I. (October 5, 1998). "Batching, treating keys to moving refined products in crude-oil line". Oil&Gas Journal. 96 (40): 49. Use of a crude-oil pipeline to transport refined petroleum products can be successful and cost-effective, as the experience of one western Canadian pipeline makes clear Via Gale and Wikipedia Library
  2. ^ "Who We Are". Trans Mountain. n.d. Retrieved January 13, 2022.
  3. ^ a b "Trans Mountain Anchor Loop". Transmountain. from the original on June 16, 2016. Retrieved January 12, 2023.
  4. ^ a b c Government of Canada (June 18, 2019), "The Government of Canada has approved the Trans Mountain Expansion Project", National Energy Board (NEB), retrieved June 19, 2019
  5. ^ a b c d Franklin, Michael (January 12, 2023). "Trans Mountain expansion on track, despite comments from Alberta premier". CTV News. Calgary. Retrieved January 12, 2023.
  6. ^ a b c d "Supreme Court dismisses First Nations' challenge against Trans Mountain pipeline". CBC News. July 2, 2020. Retrieved January 12, 2022.
  7. ^ a b c d Carmichael, Kevin (February 18, 2022). "Chrystia Freeland closes the door on new funding for Trans Mountain as project costs surge". Financial Post. Retrieved January 12, 2023. Construction costs have surged by some 70 per cent
  8. ^ Website of TMC
  9. ^ a b "Our History". Trans Mountain. n.d. Retrieved January 15, 2023.
  10. ^ a b Jaremko, Gordon (March 19, 2019). "Canada's history of pipeline challenges is longer than you might think". JWN Energy. Retrieved January 16, 2023.
  11. ^ Richard Finnie (director) (June 20, 2010) [1953]. Oil across the Rockies Part 1 (video) (video). Richard Finnie of Canadian Bechtel Limited. Event occurs at 9 min 42 sec. Retrieved January 16, 2023 – via YouTube.
  12. ^ Richard Finnie (director) (June 20, 2010) [1953]. Oil across the Rockies Part 4 (video) (video). Richard Finnie of Canadian Bechtel Limited. Event occurs at 9.44 min. Retrieved January 16, 2023 – via YouTube.
  13. ^ Mortimer, D. (1993). Receipt Piping Hydraulic Study private report prepared for Petro-Canada, Burrard Products Terminal, Port Moody, B.C. (Report).
  14. ^ a b c d e f "Why Vancouver Desperately Needs A New Oil Refinery Investing". Oil Sands Magazine. March 3, 2016. Retrieved January 16, 2023.
  15. ^ "Spill History". www.transmountain.com. June 27, 2017.
  16. ^ (PDF). Transmountain. August 31, 2016. Archived from the original (PDF) on December 21, 2016. Retrieved December 8, 2016.
  17. ^ "Abbotsford - Sumas Facility: Ward Road Spill". Transmountain. from the original on December 1, 2016. Retrieved December 1, 2016.
  18. ^ "Westridge 2007 spill". Transmountain. from the original on December 1, 2016. Retrieved December 1, 2016.
  19. ^ "Pipeline Investigation Report P07H0040". Transportation Safety Board of Canada. December 23, 2008. from the original on June 13, 2017. Retrieved June 1, 2017.
  20. ^ Granger, Grant (July 21, 2017). "The day oil rained down on Burnaby".
  21. ^ "3 companies plead guilty to Burnaby oil spill - CBC News".
  22. ^ "Burnaby Tank 82 2009 Spill". Transmountain. from the original on December 1, 2016. Retrieved December 1, 2016.
  23. ^ "Abbotsford - Sumas Facility: Tank 121 2012 Spill". Transmountain. from the original on December 1, 2016. Retrieved December 1, 2016.
  24. ^ "Trans Mountain Pipeline spill in Abbotsford estimated at up to 190,000 litres of crude oil". CBC News. June 14, 2020. Retrieved June 15, 2020.
  25. ^ "About Us". Trans Mountain. from the original on September 28, 2015. Retrieved September 27, 2015.
  26. ^ . Trans Mountain. 2013. Archived from the original on April 23, 2016. Retrieved May 16, 2016.
  27. ^ "Expansion Project". www.transmountain.com. June 21, 2017. Retrieved January 23, 2021.
  28. ^ "Trans Mountain pipeline expansion not supported by B.C. government". Transmountain. CBC News. January 11, 2016. from the original on December 7, 2016. Retrieved December 8, 2016.
  29. ^ "Government of Canada announces pipeline plan that will protect the environment and grow the economy" (Press release). Government of Canada. November 29, 2016. from the original on December 1, 2016. Retrieved December 8, 2016.
  30. ^ "B.C. approves Trans Mountain pipeline expansion - The Star". The Toronto Star. January 11, 2017.
  31. ^ a b "TMX cost balloons to $12.6B". Global News. February 7, 2020. Retrieved January 12, 2023.
  32. ^ Rosane, Olivia (July 23, 2020). "Trans Mountain Pipeline's Lead Insurer Zurich Drops Coverage". Ecowatch. Retrieved July 24, 2020.
  33. ^ Crawford, Tiffany (February 7, 2020). "Cost of Trans Mountain pipeline expansion project in B.C. soars". Vancouver Sun. Retrieved January 12, 2023.
  34. ^ a b c d Healing, Dan (September 15, 2020). "Trans Mountain pipeline expansion on schedule, on budget: CEO". Global News via Canadian Press. Retrieved October 26, 2020.
  35. ^ Luz, Andres Guerra (October 21, 2020). "Oil Prices Slump on US Fuel Supply Build". Bloomberg Rigzone. Retrieved October 26, 2020.
  36. ^ "Trans Mountain pipeline expansion costs surge 44% to $30.9 billion". financialpost.com. Retrieved March 13, 2023.
  37. ^ "Trans Mountain says expansion project is now 50% complete". April 19, 2022.
  38. ^ "Trans Mountain Corporation Releases Third Quarter 2022 Results". Trans Mountain. November 29, 2022. Retrieved January 12, 2023.
  39. ^ "What the Trans Mountain pipeline will mean for B.C.'s coast". The Globe and Mail. 2017. Retrieved August 30, 2018.
  40. ^ "Trans Mountain Pipeline: The truth about construction" (PDF). Stand.earth. Vancouver, British Columbia. September 2019. Retrieved October 26, 2020.
  41. ^ "Pipelines much safer than shipping oil by rail, Fraser Institute (a private organization funded by the Koch Brothers) study says". Financial Post. from the original on December 2, 2016. Retrieved December 1, 2016.
  42. ^ "Kinder Morgan's Trans Mountain pipeline benefits questioned". CBC News. November 10, 2014. from the original on December 4, 2016. Retrieved May 16, 2016.
  43. ^ Lundy, Matt (November 27, 2018). "Why Alberta's latest oil-price plunge is unprecedented". The Globe and Mail. Retrieved December 28, 2018.
  44. ^ Brusstar, Dan; Putnam, Bluford (December 21, 2015). "U.S. Oil Exports Could Narrow WTI-Brent Spread - CME Group". from the original on July 16, 2016. Retrieved January 8, 2019.
  45. ^ Hoekstra, Gordon (November 26, 2016). "Yes could still be no as Kinder Morgan awaits Trudeau's nod on its multibillion-dollar pipeline expansion". The Vancouver Sun. from the original on December 9, 2016. Retrieved December 8, 2016.
  46. ^ "B.C. slams Ottawa's defence of Trans Mountain pipeline expansion". The Globe and Mail. Retrieved February 9, 2018.
  47. ^ "'No province can impinge on the national interest', federal minister says as pipeline feud simmers". CBC News. Retrieved February 9, 2018.
  48. ^ "B.C. creates more uncertainty for Trans Mountain with bitumen restriction". CBC News. Retrieved February 9, 2018.
  49. ^ "B.C. not backing down on fight against pipeline expansion despite Alberta's threats". CBC News. Retrieved February 9, 2018.
  50. ^ "Cheers! B.C. wine industry celebrates end of Alberta ban". CBC News. Retrieved April 18, 2018.
  51. ^ "Alberta demands 'concrete action' from Ottawa to get Trans Mountain pipeline moving". CBC News. Retrieved April 18, 2018.
  52. ^ "Alberta unveils bill that could wreak havoc on B.C. gas prices in trade war". CBC News. Retrieved April 18, 2018.
  53. ^ "New law would allow Alberta to restrict flow of oil and gas as Trans Mountain battle escalates". Financial Post. April 16, 2018. Retrieved April 18, 2018.
  54. ^ "Alberta premier 'prepared to turn off the taps' now that legislation approved". Edmonton Journal. May 17, 2018. Retrieved August 30, 2018.
  55. ^ "Liberals to buy Trans Mountain pipeline for $4.5B to ensure expansion is built". CBC News. Retrieved May 30, 2018.
  56. ^ "Ottawa is buying Trans Mountain. What does that mean? A guide". The Globe and Mail. Retrieved May 29, 2018.
  57. ^ Weichel, Andrew (May 29, 2018). "B.C. premier, Indigenous groups respond to Trans Mountain purchase". CTV News British Columbia. Retrieved May 30, 2018.
  58. ^ "Kinder Morgan Canada shareholders vote to sell Trans Mountain pipeline to Ottawa with project in limbo". CBC News. Retrieved August 30, 2018.
  59. ^ "Federal Court of Appeal quashes construction approvals for Trans Mountain, leaving project in limbo". CBC News. Retrieved August 30, 2018.
  60. ^ "Trans Mountain pipeline approval quashed by court". Financial Post. August 30, 2018. Retrieved August 30, 2018.
  61. ^ a b c d e f Hunter, Justine (November 8, 2018). "Limited public access to new hearings on the Trans Mountain pipeline project". The Globe and Mail. Victoria. Retrieved January 8, 2019.
  62. ^ a b Tarasko, Mike (November 20, 2018). "New Trans Mountain hearings begin in Calgary". My McMurray. Calgary. Retrieved January 7, 2019.
  63. ^ "Trudeau committed to building Trans Mountain despite new legal challenges". CBC News. Retrieved September 7, 2018.
  64. ^ a b "Prime Minister says Ottawa still committed to build Trans Mountain pipeline expansion". August 31, 2018. Retrieved September 7, 2018.
  65. ^ a b Keller, James (May 2, 2014). "B.C. First Nation launches legal challenge over Kinder Morgan pipeline". Canadian Televisions News. from the original on May 8, 2014.
  66. ^ Azpiri, Jon (April 25, 2018). "Summer jobs controversy reheats over posting calling to 'stop the Kinder Morgan pipeline'". Global News. Retrieved July 18, 2018.
  67. ^ The Canadian Press (June 4, 2018). "Rallies planned across Canada to protest Kinder Morgan buyout". News 1130. Retrieved July 18, 2018.
  68. ^ "Pipeline protesters block Trans Mountain oil tanker from Ironworkers Memorial Bridge". July 3, 2018. Retrieved September 7, 2018.
  69. ^ Hernandez, Jon (September 28, 2021). "Treetop camp protesting Trans Mountain pipeline dismantled". CBC News. Retrieved October 7, 2021.
  70. ^ a b Kilawna, Kelsie (October 24, 2020). "Secwépemc Matriarch cuts off her hair in defense of her lands and waters". APTN National News. Retrieved October 26, 2020.
  71. ^ a b c d Laferte, Boston (October 23, 2020). "Secwepemc set up new camp in hopes of halting TMX construction, leads to five arrests". The Martlet. Retrieved October 26, 2020.
  72. ^ Brake, Justin (July 19, 2018). "Tiny House Warriors establish new village to resist pipeline, assert Secwepemc sovereignty". APTN National News. Retrieved October 26, 2020.
  73. ^ a b Rothenburger, Mel (October 24, 2020). "ROTHENBURGER: Protests and arrests were played out in a familiar script". CFJC Today. Retrieved October 26, 2020.
  74. ^ Sperling, Jill (October 5, 2020). "Camp set up near Mission Flats Road in protest of Trans Mountain pipeline expansion project". CFJC Today. Retrieved October 26, 2020.
  75. ^ a b "5 arrested after standing in way of Trans Mountain pipeline construction in B.C. Interior". CBC News. October 16, 2020. Retrieved October 26, 2020.
  76. ^ Kergin, Brendan (October 18, 2020). "Tk'emlups te Secwepemc leadership releases statement on TMX arrests". Castanet.net. from the original on October 23, 2020. Retrieved October 26, 2020.
  77. ^ a b Verenca, Tereza (December 10, 2018). "Three arrested as judge consults with Indigenous groups about Trans Mountain project". Burnaby Now. Retrieved January 7, 2019.
  78. ^ a b c d Tasker, John Paul (June 18, 2019). "Trudeau cabinet approves Trans Mountain expansion project". CBC News. Retrieved January 12, 2023. Federal officials say construction of the $7.4 billion pipeline is likely to begin in 2019
  79. ^ "Orders In Council", Government of Canada, no. 2019–0820, June 18, 2019, retrieved June 19, 2019
  80. ^ a b "Trans Mountain Expansion Project Order in Council P.C. 2019-0820 Project update: Letter from NEB to Trans Mountain and Tsleil-Waututh Nation", National Energy Board (NEB), Calgary, Alberta, June 18, 2019, retrieved June 19, 2019
  81. ^ Kestler-D'Amours, Jillian; O'Toole, Megan (December 5, 2019). "Nations divided: mapping Canada's pipeline battle". Al Jazeera website. Retrieved December 5, 2019.

External links edit

  • Oil Across the Rockies - Documentary of the building of the pipeline.
  • The Building of Trans Mountain: Canada's First Oil Pipeline Across the Rockies - Book about the building of the pipeline.

trans, mountain, pipeline, trans, mountain, redirects, here, other, uses, trans, mountain, disambiguation, trans, mountain, pipeline, system, simply, trans, mountain, pipeline, tmpl, multiple, product, pipeline, system, that, carries, crude, refined, products,. Trans Mountain redirects here For other uses see Trans mountain disambiguation The Trans Mountain Pipeline System or simply the Trans Mountain Pipeline TMPL is a multiple product pipeline system that carries crude and refined products from Edmonton Alberta to the coast of British Columbia Canada 1 2 Trans Mountain Pipeline TMPL Trans Mountain pipeline route from Edmonton to BurnabyLocationCountryCanadaProvinceAlberta and British ColumbiaFromEdmonton AlbertaToBurnaby British ColumbiaGeneral informationTypemultiple product pipelines crude oil refined petroleum products such as jet fuel gasoline diesel 1 StatusGovernment of CanadaOwnerTrans Mountain Corporation TMC Canada Development Investment Corporation Commissioned1951Technical informationLength1 150 km 710 mi Diameter610 mm 24 in The corporation was created in 1951 construction began in 1952 and operations commenced in 1953 It is the only pipeline to run between these two areas The construction of a second pipeline between Hinton Alberta and Hargreaves British Columbia running adjacent to the existing line was completed in 2008 3 In 2013 a project to twin the existing Trans Mountain pipeline the Trans Mountain Expansion Project was proposed to the Canadian National Energy Board 4 The project was 75 complete as of January 2023 5 The expansion which runs roughly parallel to the existing pipeline will increase capacity from 300 000 barrels per day 48 000 m3 d to 890 000 barrels per day 141 000 m3 d Since it was first proposed in 2013 this Trans Mountain Expansion Project has attracted controversy due to its potential environmental impact having faced legal challenges as well as protests from environmentalists and First Nations groups A Supreme Court decision on July 2 2020 that rejected the appeals made by First Nations and environmental groups brought an end to the years long legal challenge 6 On August 31 2018 the Government of Canada purchased the pipeline for 4 5 billion from Kinder Morgan through the creation of the Trans Mountain Corporation TMC in order to keep the project alive 7 TMC is a Crown corporation a subsidiary of the Canada Development Investment Corporation CDEV 8 Until the purchase by CDEV the Trans Mountain Pipeline was owned by the Houston Texas based pipeline operator s Canadian division Contents 1 History 1 1 Shift from single to multiple products pipelines 1983 1 2 TMPL and oil refineries 1 3 Spill history 2 Trans Mountain Expansion Project 2 1 Debate 2 2 Protests 2 2 1 Secwepemc opposition 2 3 Phase III consultations November 2018 2 4 Government of Canada June 18 2019 approval of TMX 2 5 SCC 2020 decisions dismissing appeals challenging TMX 3 See also 4 Notes 5 References 6 External linksHistory editIn February 1947 large oil deposits were discovered near Leduc Alberta The idea for a pipeline from Alberta to British Columbia quickly emerged driven by the growing demand for oil both in Asia and on the west coast of Canada and the United States The US military was also interested in developing this infrastructure so that oil could be accessed more easily for military use citation needed On March 21 1951 the Trans Mountain Pipeline Company Trans Mountain was created when the Canadian Parliament granted the company a charter under a special act of Parliament 9 The proposal for the pipeline was immediately submitted to the Board of Transport Commissioners and was approved Construction began in February 1952 and the final section was welded in place near Aldergrove British Columbia on October 17 1952 9 According to a 2019 JWN Energy series Inside Canada s Pipeline Industry by former editor of Oilweek Gordon Jaremko both the Board approval and the construction of the 1 150 kilometre 710 mi pipeline were sped up as concerns about the Korean War mounted The governments considered the TMPL to be a strategic way of reducing reliance on oil tankers made vulnerable under threats of potential attack on the west coast of North America 10 Canadian Bechtel Ltd was responsible for engineering design and construction of the project Ownership of the company was split between Canadian Bechtel Ltd and Standard Oil clarification needed In August 1953 crude oil from Edmonton Alberta began flowing to refineries in the Vancouver area and the northwestern U S through TNPL 10 The total cost of TMPL was 93 million according to then Premier of British Columbia W A C Bennett at the opening ceremony 11 12 Prior to 1983 the only product TMPL carried was crude oil to supply refineries in the Vancouver area and to the state of Washington 1 Shift from single to multiple products pipelines 1983 edit In 1983 Trans Mountain began experiments to shift from single to multiple product pipelines to increase efficiency and to become more competitive 1 By 1985 TMPL regularly carried refined products 820 kilometres 510 mi from Edmonton to Kamloops British Columbia This had extended to Vancouver by 1993 1 A 1993 report said that the TMPL was the only major system in the world at that time transporting both crude oil and refined petroleum products in a single pipeline 13 1 By 1998 TMPL made regular shipments to Vancouver of refined petroleum products including jet fuel gasoline unleaded and premium unleaded diesel regular sulfur low sulfur and low temperature methyl tertiary butyl ether MTBE and crude oil light sweet light sour and heavy 1 In 2004 Kinder Morgan began the process to add a second pipeline running parallel to the first for the portion running between Hinton Alberta and Hargreaves British Columbia This required two more pumping stations the Wolf Pump Station near Niton Junction Alberta and the Chappel Pump Station near Pyramid Creek Falls Provincial Park British Columbia This increased capacity by 40 000 barrels per day 6 400 m3 d from 260 000 to 300 000 barrels per day 41 000 to 48 000 m3 d 3 TMPL and oil refineries edit Shell Petro Canada and Imperial closed refineries in British Columbia in the 1990s and expanded their refineries in the Edmonton area following the TMPL construction 14 TMPL had the capacity to carry refined products as well as crude oil via the batch system 14 According to a 2016 Oil Sands Magazine article this resulted in the conversion of existing refineries along the TMPL route into storage and distribution facilities and terminals 14 In 1983 Kamloops Royalite Refinery was shutdown 14 In 1993 two refineries were closed Shell s in North Burnaby a large Vancouver neighbourhood and Petro Canada s in Port Coquitlam 27 km 17 mi east of Vancouver were closed 14 In 1995 Imperial Oil closed their refinery in Port Moody a city that is part of the Metro Vancouver Regional District 14 Spill history edit As of 2017 update TMPL had reported approximately 84 spills to Canada s National Energy Board since 1961 15 16 Although a majority occurred at contained zones such as pumping stations and a majority were below the mandatory reporting threshold of 1 5 cubic metres there were some significant spill events In Abbotsford in 2005 a ruptured pipeline dumped 210 m3 1 300 bbl of crude oil The company attributed the accident to activity on a neighbouring property 17 In 2007 in Burnaby a contractor working on a sewage project for the City of Burnaby ruptured a pipeline causing spillage of 224 234 m3 1 410 1 470 bbl of crude oil Some of it flowed into Burrard Inlet via the Burnaby storm sewer system Most of it was recovered Eleven houses were sprayed with oil and about 225 250 residents were evacuated or left voluntarily Cleanup took more than a year 18 19 20 21 In 2009 in Burnaby 305 m3 1 920 bbl of crude oil were released from a tank at the Trans Mountain Burnaby Terminal Most of it flowed into a containment area 22 In Sumas in 2012 90 m3 570 bbl of light crude oil leaked from a Sumas Mountain holding tank All of it flowed into a containment area 23 In 2020 in Sumas 190 0 m3 1 195 bbl of light crude leaked from small pipe connected to mainline Trans Mountain reported on June 14 that the spill was contained on the property and that groundwater was monitored for contamination 24 Trans Mountain Expansion Project editOn June 18 2013 Kinder Morgan filed an application with the Canadian National Energy Board pursuant to Part III of the National Energy Board Act 4 to build a second pipeline under the Trans Mountain Pipeline Expansion Project 25 The second pipeline was to run roughly parallel to the existing pipeline between Edmonton and Burnaby east of Vancouver and to be used to transport diluted bitumen also known as dilbit The additional pipeline requires 12 new pumping stations The proposed expansion with 980 kilometres 610 mi of pipe would increase the system s capacity from 300 000 barrels per day 48 000 m3 d to 890 000 barrels per day 141 000 m3 d In 2016 the cost of completing the connection between Strathcona County Alberta and Burnaby British Columbia was estimated at 6 8 billion in 2013 26 nbsp Trans Mountain Pipeline in green with other Canadian Energy Regulator managed pipelines Kinder Morgan had the support at that time of several large petroleum industry customers for this expansion BP Canada Energy Trading Co Canadian Natural Resources Canadian Oil Sands Ltd Cenovus Energy Inc Devon Canada Corp Husky Energy Marketing Inc Imperial Oil Ltd Nexen Marketing Inc Statoil Canada Ltd Suncor Energy Marketing Inc Suncor Energy Products Partnership Tesoro Refining amp Marketing Co and Total E amp P Canada Ltd 27 In 2016 B C stated it did not support Trans Mountain partly because Kinder Morgan has not provided enough information about its proposed spill prevention and spill clean up program 28 On November 29 2016 Canada s federal cabinet approved the expansion project announcing that the approval was subject to 157 binding conditions that will address potential Indigenous socio economic and environmental impacts including project engineering safety and emergency preparedness 29 On January 11 2017 B C Premier Christy Clark announced British Columbia s support for the expansion of the Trans Mountain pipeline saying the project met her government s five conditions for approval and includes a revenue sharing agreement worth up to 1 billion 30 In 2018 the federal government created the Crown corporation the Trans Mountain Corporation TMC when it bought the pipeline from the Houston based Kinder Morgan for C 4 5 billion 7 31 The purchase had been announced by the federal government in May 2018 At that time the government said it would seek outside investors to complete the expansion These investors would also be indemnified for any delays induced by provincial or municipal governments In 2020 three insurance companies that had previously supported the project withdrew their support including Zurich Insurance Group the leading insurer The company that is advancing the project says that it still has enough insurance coverage 32 By February 2020 the assessment for the completion of the project was estimated at 12 6 billion an increase of the previous estimate of 7 4 billion 31 The cost increase was the result of rising costs of labour steel and land 33 In a September 2020 interview with the Canadian Press TMC s CEO Ian Anderson said that the expansion was on schedule despite the 5 2 billion increase in its cost 34 Anderson cited other challenges to construction including the COVID 19 pandemic the slump in the demand for fuel which contributes to the slump in the price of oil 35 and the ongoing protests by opponents to the expansion 34 By February 2022 the Crown corporation that owned Trans Mountain TMC said that costs had increased by 70 from 12 6 billion to 21 4 billion 7 Faced with the federal government s costly COVID 19 response Finance Minister Chrystia Freeland said this new funding for the pipeline was not part of the federal government s commitment 7 The status of the company changed to a non agent Crown corporation on April 29 2022 which meant that it was able to access financing from third party lenders 5 In March 2023 it was announced that the cost has again increased to 30 9 billion 36 As of April 2022 construction had reached the half way mark 37 The company said in their November 29 2022 third quarter report that expansion would be mechanically complete by the third quarter of 2023 and the commercial service would be operational in the fourth quarter of 2023 38 5 According to a January 11 2023 statement from the company more than 700 kilometres 430 mi of pipe was already in place representing 75 of the entire project 5 Debate edit The expansion project has faced criticism particularly from environmentalists and First Nations groups To reach the terminus tankers have to pass through a very narrow channel of shallow water from the open sea still putting leaks at risk due to vehicle crashes 39 Environmentalists have expressed concern about the heightened risk of an oil spill in the Burrard Inlet resulting from the expansion which entails the obstruction of 30 of the inlet and a seven fold increase in tanker traffic according to Stand earth formerly ForestEthics 40 Those who support the pipeline say that it will create jobs and that it has a lower risk of spilling oil than transporting oil by rail which pipeline proponents say would otherwise have to be used 41 A 2014 study by Simon Fraser University claimed that Kinder Morgan overestimated the economic benefits of the pipeline expansion 42 From 2008 through 2018 Western Canadian Select WCS Canada s benchmark for heavy crude oil sold at an average discount of US 17 against the benchmark for light oil West Texas Intermediate WTI This widened to a record US 50 in the fall of 2018 with the price of WCS hitting a record low of less than US 14 a barrel 43 44 Despite federal government approval seven Federal Court challenges were filed by the municipalities of Vancouver and Burnaby and the Tsleil Waututh Squamish Kwantlen and Coldwater First Nations 45 In November 2017 Minister of Natural Resources Jim Carr stated that the federal government had sent a letter in support of a dispute resolution process to the National Energy Board to expedite any future disputes over provincial or municipal permits impeding the expansion BC Environmental Minister George Heyman accused the federal government of interfering with an independent review of the project arguing that it s both a highly unusual and a highly troubling intrusion on a province s right to enforce its own permits its own regulations and the interests of its own citizens 46 47 On January 30 2018 the B C government proposed a restriction on increases to the amount of diluted bitumen that can be imported into the province from Alberta until the completion of studies on whether potential spillage could be mitigated The province also announced an intent to consult with local communities and First Nations among others Alberta premier Rachel Notley criticized the proposal as being a stalling tactic on Trans Mountain expansion explaining that the B C government has every right to consult on whatever it pleases with its citizens It does not have the right to rewrite our constitution and assume powers for itself that it does not have On February 6 2018 Notley ordered the Alberta Gaming and Liquor Commission to cease future imports of British Columbia wine as a retaliatory sanction over these moves 48 49 The wine sanctions were lifted on February 22 2018 50 On April 8 2018 Kinder Morgan suspended non essential activities relating to the pipeline as the company did not want to put its shareholders at risk on the remaining project spend The company stated that it would attempt to reach agreements on a funding plan with stakeholders by May 31 51 On April 16 2018 the Alberta government introduced the Preserving Canada s Economic Prosperity Act which would give the Minister of Energy power to regulate the export of crude oil natural gas or refined fuel from Alberta The bill could be used to effectively ban the export of Alberta gas to British Columbia As such B C Attorney General David Eby threatened to sue Alberta over the proposed bill as he considered it unconstitutional and stated that it could have a further impact on gasoline prices in the province 52 53 54 On May 29 2018 the Canadian federal government announced its intent to acquire the Trans Mountain Pipeline from Kinder Morgan for 4 5 billion The government does not intend to remain the permanent owner of the pipeline as it plans to seek outside investors to finance the twinning project If the government cannot find a buyer before the consummation of the purchase it will carry out the purchase via a crown corporation and operate it in the meantime The eventual owner will be indemnified by the government for any delays or hindrances to the project that result from legal actions by provincial or municipal governments The government will also have the option to cover costs or purchase the pipeline back if the new owner is unable to complete the project due to legal pressure or despite reasonable efforts cannot complete the project by an established deadline 55 56 Critics who of the expansion argued where that this proposed purchase was a taxpayer funded bailout of the project B C Premier John Horgan stated that the sale would not affect the provincial government s ongoing efforts to block the pipeline expansion stating that rather than go to the court to determine jurisdictions they re making financial decisions that affect taxpayers and they ll have to be accountable for that Stewart Phillip president of the Union of British Columbia Indian Chiefs stated that the union was absolutely shocked and appalled that Canada is willingly investing taxpayers money in such a highly controversial fossil fuel expansion project 57 On August 30 2018 Kinder Morgan Canada s shareholders voted to approve the sale of the pipeline to the federal government 58 However the same day the Federal Court of Appeal overturned the government s approval of the expansion project citing that it did not sufficiently fulfill its constitutional duties to consult local First Nations groups 59 60 and because it lacked an environmental assessment of increased tanker traffic on orcas in the Salish Sea 61 off the BC coast 62 On August 31 Trudeau said the federal government remained committed to the pipeline expansion project in spite of this setback 63 64 In response to the approval being overturned Premier Rachel Notley announced that Alberta would pull out of the national carbon price and called for an appeal to the Supreme Court of Canada of the federal court s August 30 decision 64 Protests edit The expansion project faced opposition from civic governments First Nations environmentally concerned citizens and others In September 2012 Tsleil Waututh leaders had hoped to shut down the project altogether 65 In November 2014 opponents of the pipeline expansion camped in Burnaby Mountain Park to block pipeline construction crews and over 100 were arrested 34 Members of the Squamish and Tsleil Waututh First Nations of British Columbia paddled canoes on the waters of Burrard Inlet in North Vancouver to Kinder Morgan s Burnaby Terminal for a ceremony to protest the expansion of the Trans Mountain pipeline 65 In a 2020 Global News interview with the pipeline expansion work underway again Grand Chief Stewart Phillip president of the Union of BC Indian Chiefs said that he expected that there would be more Burnaby Mountain style protests 34 Protests took place in Vancouver to stop work on the pipeline on September 19 2017 nbsp A protester holds a sign that says No Consent No Pipeline at a rally in 2017 nbsp Burnaby Mayor Derek Corrigan addresses the crowd at the STOP KINDER MORGAN protest rallyBurnaby Mayor Derek Corrigan addressed the crowd at a Stop Kinder Morgan protest rally in Burnaby Mountain Park By 2018 rallies opposing the projects had been organized across Canada Organizations including LeadNow and the Dogwood Initiative have also opposed the project and organized protests 66 67 The RCMP contained the protests on Burnaby Mountain In July 2018 activists blocked an oil tanker from the Ironworkers Memorial Bridge in Vancouver 68 In September 2021 a treetop camp in the Brunette River Conservation Area was dismantled by RCMP following a court injunction The protest camp had been occupied by protesters since December 2020 and a leader of the protest claimed further actions would be planned 69 Secwepemc opposition edit According to Aboriginal Peoples Television Network since 2013 Secwepemc community members primarily women have been defending their traditional land known as Secwepemcul ecw against the proposed expansion of the pipeline asserting that the expansion was approved without sufficient consultation The expansion would cross 518 km of Secwepemc territory The land defenders as they call themselves some media refers to them as protesters and activists are concerned about the damage to the land and water the pipeline passes through in particular the disruption of salmon populations violation of the Declaration on the Rights of Indigenous Peoples and violation of traditional Secwepemc law founded by the Okanagan Shuswap Confederacy Their claim is that the First Nation band governments only have jurisdiction through Canadian law on their reserves whereas traditional Secwepemc leadership retains sovereignty over Secwepemcul ecw 70 Since July 2018 a Secwepemc protest camp has been occupied just outside of Blue River British Columbia where there are plans to drill under the river 71 That camp established by a group known as the Tiny House Warriors is located near a planned work camp referred to by Indigenous dissenters as a man camp because of the predominance of men in the demographics of pipeline workers 72 The establishment of the camp led Kukpi7 Chief Rosanne Casimir of Tk emlups te Secwepemc First Nation TteS along with Chief Shelly Loring of Simpcw First Nation to issue a joint statement asking the Tiny House Warriors to stand down claiming it was the Warriors violating Secwepemc law 73 In early September 2020 protester Loralie Dick chained herself to the TMX worksite in Kamloops before being arrested by the RCMP for violating a B C Supreme Court injunction from 2018 that barred land defenders from blocking work 71 73 In early October 2020 a protest camp was set up along the Thompson River along the proposed route of the expansion One of the residents of the Thompson River camp was Secwepemc matriarch Miranda Dick who told reporters there were an average of 20 people at the camp as of October 5th At the time it was set up Kukpi7 Casimir said she had no issue with the protest camp so long as health and safety guidelines were followed 74 On October 9 in response to TMX workers being seen surveying in preparation to drill under the river the camp was moved directly in the way of the expansion On October 10 the Secwepemc delivered a cease and desist notice to TMX for the second time 75 On October 11 it was moved again due to a chemical leak in the river By October 15 the RCMP had begun arresting people connected to the camp including Hereditary Chief Segwses Loralie Dick April Thomas Billie Pierre and Romilly Cavanaugh 71 In February 2020 Segwses and his daughter gave themselves up for arrest for participating in the 2020 Canadian pipeline and railway protests in order to prevent the RCMP from snuffing a sacred fire as well as to prevent the escalation of a confrontation 75 On October 17 2020 Dick cut her hair in ceremony before the gates of the expansion project Soon after the ceremony she and four other women were arrested by RCMP officers 70 One was arrested without charges while the other four are set to appear in court in January 2021 71 In a statement released the following day TteS Kukpi7 Rosanne Casimir thanked the RCMP for maintaining peace and order and stated that she and the elected council did not endorse the protesters TteS is one of several First Nations bands that have signed agreements with Trans Mountain Casimir s statement asserted that the council had not sold or ceded or given anything away but that they had upheld their jurisdictional rights 76 Phase III consultations November 2018 edit In response to the Federal Court s overturning the federal authorization of Trans Mountain the Canadian Government reinitiated Phase III consultations with Natural Resources Canada as lead and Justice Frank Iacobucci appointed by the government to oversee consultations An NEB panel heard three weeks of Indigenous traditional testimony with 117 Indigenous groups impacted by the pipeline beginning on November 19 61 with sessions in Calgary Victoria and Nanaimo 77 The Trudeau government restricted the Phase III hearings in terms of time and scope 61 The government gave the NEB a tight timeline with a final report due on February 22 2019 61 The hearings are also restricted by the NEB panel to investigate new information as it relates to the impact of increased oil tanker traffic to and from the Westridge Marine Terminal in Burrard Inlet Burnaby to Canada s 12 nautical mile territorial waters The environmental concern in this area includes the Salish Sea s southern resident killer whales SRKW prime Chinook salmon feeding ground By November 2018 there were only 74 SRKW left 61 Noise and pollution from marine vessels along with the diminishing stocks of salmon their prime source of food have contributed to the whales declining numbers 61 Hearings in the form of pipeline roundtable meetings with Trans Mountain representative and indigenous groups took place in Calgary in November and in Kamloops and Nanaimo in December with the summary expected in January 62 77 Government of Canada June 18 2019 approval of TMX edit On June 18 2019 the federal government through the Governor in Council GIC confirmed the approval of federally owned TMX project The twinned pipeline will have the capacity to carry almost 1 million bpd from Alberta to the coast of British Columbia 78 The National Energy Board Prime Minister Justin Trudeau and his cabinet agreed that the TMX was in the national interest as it would add tens of billions of dollars to government revenue as well as sustaining thousands of jobs 78 Both the NEB and the federal government acknowledged that there was a possibility that TMX could damage the environment and marine life but the benefits outweighed the risks 78 Prime Minister Trudeau said that the revenue from TMC which was estimated at 500 million annually just in federal corporate taxes would be invested in unspecified clean energy projects 78 4 79 In their letter sent to both Trans Mountain and the lawyers representing the Tsleil Waututh Nation the NEB wrote that within the context of substantial and significant interest and participation on the part of Indigenous peoples and the general public including the August 30 2018 decision in Tsleil Waututh Nation v Canada 80 the NEB s regulatory oversight processes for the next phases of the Trans Mountain Expansion Project lifecycle which include detailed route approvals such as potential routing and non routing would include a public comment period 80 SCC 2020 decisions dismissing appeals challenging TMX edit By December 2019 the legal basis of the expansion was challenged in Canada s Federal Court of Appeal as politicians environmentalists and some Indigenous groups returned to the courts and pressed the issue of Aboriginal title 81 Some Indigenous groups such as the Kehewin Cree Nation T Sou ke Nation Frog Lake First Nation Scia new First Nation Simpcw First Nation Pellt iq t First Nation and Squiala First Nation formed the Western Indigenous Pipeline Group WIPG and have sanctioned the project for ownership stakes Others like the Coldwater Indian Band have unsettled issues These issues include disputes over the compensation from the institution of the first pipeline right of way in the 1950s as well as future water supply risks that they would assume In February 2020 a Federal Court of Appeal denied the request by environment and Indigenous groups to consider whether there had been sufficient consultation 6 A March 5 2020 Supreme Court March decided not to hear five challenges from environment and Indigenous groups 6 On July 2 2020 the Supreme Court of Canada rejected appeals by the Squamish Nation Tsleil Waututh Nation and Coldwater Indian Band and others challenging federal approval of the Trans Mountain pipeline expansion project bringing an end to the years long legal challenge 6 See also editEagle Spirit Pipeline Northern Gateway PipelineNotes editReferences edit a b c d e f g Baum Judy S Marzocco Ken E Hansen Larry I October 5 1998 Batching treating keys to moving refined products in crude oil line Oil amp Gas Journal 96 40 49 Use of a crude oil pipeline to transport refined petroleum products can be successful and cost effective as the experience of one western Canadian pipeline makes clear Via Gale and Wikipedia Library Who We Are Trans Mountain n d Retrieved January 13 2022 a b Trans Mountain Anchor Loop Transmountain Archived from the original on June 16 2016 Retrieved January 12 2023 a b c Government of Canada June 18 2019 The Government of Canada has approved the Trans Mountain Expansion Project National Energy Board NEB retrieved June 19 2019 a b c d Franklin Michael January 12 2023 Trans Mountain expansion on track despite comments from Alberta premier CTV News Calgary Retrieved January 12 2023 a b c d Supreme Court dismisses First Nations challenge against Trans Mountain pipeline CBC News July 2 2020 Retrieved January 12 2022 a b c d Carmichael Kevin February 18 2022 Chrystia Freeland closes the door on new funding for Trans Mountain as project costs surge Financial Post Retrieved January 12 2023 Construction costs have surged by some 70 per cent Website of TMC a b Our History Trans Mountain n d Retrieved January 15 2023 a b Jaremko Gordon March 19 2019 Canada s history of pipeline challenges is longer than you might think JWN Energy Retrieved January 16 2023 Richard Finnie director June 20 2010 1953 Oil across the Rockies Part 1 video video Richard Finnie of Canadian Bechtel Limited Event occurs at 9 min 42 sec Retrieved January 16 2023 via YouTube Richard Finnie director June 20 2010 1953 Oil across the Rockies Part 4 video video Richard Finnie of Canadian Bechtel Limited Event occurs at 9 44 min Retrieved January 16 2023 via YouTube Mortimer D 1993 Receipt Piping Hydraulic Study private report prepared for Petro Canada Burrard Products Terminal Port Moody B C Report a b c d e f Why Vancouver Desperately Needs A New Oil Refinery Investing Oil Sands Magazine March 3 2016 Retrieved January 16 2023 Spill History www transmountain com June 27 2017 Releases Reported by Trans Mountain 1961 2016 PDF Transmountain August 31 2016 Archived from the original PDF on December 21 2016 Retrieved December 8 2016 Abbotsford Sumas Facility Ward Road Spill Transmountain Archived from the original on December 1 2016 Retrieved December 1 2016 Westridge 2007 spill Transmountain Archived from the original on December 1 2016 Retrieved December 1 2016 Pipeline Investigation Report P07H0040 Transportation Safety Board of Canada December 23 2008 Archived from the original on June 13 2017 Retrieved June 1 2017 Granger Grant July 21 2017 The day oil rained down on Burnaby 3 companies plead guilty to Burnaby oil spill CBC News Burnaby Tank 82 2009 Spill Transmountain Archived from the original on December 1 2016 Retrieved December 1 2016 Abbotsford Sumas Facility Tank 121 2012 Spill Transmountain Archived from the original on December 1 2016 Retrieved December 1 2016 Trans Mountain Pipeline spill in Abbotsford estimated at up to 190 000 litres of crude oil CBC News June 14 2020 Retrieved June 15 2020 About Us Trans Mountain Archived from the original on September 28 2015 Retrieved September 27 2015 Trans Mountain Proposed Expansion Trans Mountain 2013 Archived from the original on April 23 2016 Retrieved May 16 2016 Expansion Project www transmountain com June 21 2017 Retrieved January 23 2021 Trans Mountain pipeline expansion not supported by B C government Transmountain CBC News January 11 2016 Archived from the original on December 7 2016 Retrieved December 8 2016 Government of Canada announces pipeline plan that will protect the environment and grow the economy Press release Government of Canada November 29 2016 Archived from the original on December 1 2016 Retrieved December 8 2016 B C approves Trans Mountain pipeline expansion The Star The Toronto Star January 11 2017 a b TMX cost balloons to 12 6B Global News February 7 2020 Retrieved January 12 2023 Rosane Olivia July 23 2020 Trans Mountain Pipeline s Lead Insurer Zurich Drops Coverage Ecowatch Retrieved July 24 2020 Crawford Tiffany February 7 2020 Cost of Trans Mountain pipeline expansion project in B C soars Vancouver Sun Retrieved January 12 2023 a b c d Healing Dan September 15 2020 Trans Mountain pipeline expansion on schedule on budget CEO Global News via Canadian Press Retrieved October 26 2020 Luz Andres Guerra October 21 2020 Oil Prices Slump on US Fuel Supply Build Bloomberg Rigzone Retrieved October 26 2020 Trans Mountain pipeline expansion costs surge 44 to 30 9 billion financialpost com Retrieved March 13 2023 Trans Mountain says expansion project is now 50 complete April 19 2022 Trans Mountain Corporation Releases Third Quarter 2022 Results Trans Mountain November 29 2022 Retrieved January 12 2023 What the Trans Mountain pipeline will mean for B C s coast The Globe and Mail 2017 Retrieved August 30 2018 Trans Mountain Pipeline The truth about construction PDF Stand earth Vancouver British Columbia September 2019 Retrieved October 26 2020 Pipelines much safer than shipping oil by rail Fraser Institute a private organization funded by the Koch Brothers study says Financial Post Archived from the original on December 2 2016 Retrieved December 1 2016 Kinder Morgan s Trans Mountain pipeline benefits questioned CBC News November 10 2014 Archived from the original on December 4 2016 Retrieved May 16 2016 Lundy Matt November 27 2018 Why Alberta s latest oil price plunge is unprecedented The Globe and Mail Retrieved December 28 2018 Brusstar Dan Putnam Bluford December 21 2015 U S Oil Exports Could Narrow WTI Brent Spread CME Group Archived from the original on July 16 2016 Retrieved January 8 2019 Hoekstra Gordon November 26 2016 Yes could still be no as Kinder Morgan awaits Trudeau s nod on its multibillion dollar pipeline expansion The Vancouver Sun Archived from the original on December 9 2016 Retrieved December 8 2016 B C slams Ottawa s defence of Trans Mountain pipeline expansion The Globe and Mail Retrieved February 9 2018 No province can impinge on the national interest federal minister says as pipeline feud simmers CBC News Retrieved February 9 2018 B C creates more uncertainty for Trans Mountain with bitumen restriction CBC News Retrieved February 9 2018 B C not backing down on fight against pipeline expansion despite Alberta s threats CBC News Retrieved February 9 2018 Cheers B C wine industry celebrates end of Alberta ban CBC News Retrieved April 18 2018 Alberta demands concrete action from Ottawa to get Trans Mountain pipeline moving CBC News Retrieved April 18 2018 Alberta unveils bill that could wreak havoc on B C gas prices in trade war CBC News Retrieved April 18 2018 New law would allow Alberta to restrict flow of oil and gas as Trans Mountain battle escalates Financial Post April 16 2018 Retrieved April 18 2018 Alberta premier prepared to turn off the taps now that legislation approved Edmonton Journal May 17 2018 Retrieved August 30 2018 Liberals to buy Trans Mountain pipeline for 4 5B to ensure expansion is built CBC News Retrieved May 30 2018 Ottawa is buying Trans Mountain What does that mean A guide The Globe and Mail Retrieved May 29 2018 Weichel Andrew May 29 2018 B C premier Indigenous groups respond to Trans Mountain purchase CTV News British Columbia Retrieved May 30 2018 Kinder Morgan Canada shareholders vote to sell Trans Mountain pipeline to Ottawa with project in limbo CBC News Retrieved August 30 2018 Federal Court of Appeal quashes construction approvals for Trans Mountain leaving project in limbo CBC News Retrieved August 30 2018 Trans Mountain pipeline approval quashed by court Financial Post August 30 2018 Retrieved August 30 2018 a b c d e f Hunter Justine November 8 2018 Limited public access to new hearings on the Trans Mountain pipeline project The Globe and Mail Victoria Retrieved January 8 2019 a b Tarasko Mike November 20 2018 New Trans Mountain hearings begin in Calgary My McMurray Calgary Retrieved January 7 2019 Trudeau committed to building Trans Mountain despite new legal challenges CBC News Retrieved September 7 2018 a b Prime Minister says Ottawa still committed to build Trans Mountain pipeline expansion August 31 2018 Retrieved September 7 2018 a b Keller James May 2 2014 B C First Nation launches legal challenge over Kinder Morgan pipeline Canadian Televisions News Archived from the original on May 8 2014 Azpiri Jon April 25 2018 Summer jobs controversy reheats over posting calling to stop the Kinder Morgan pipeline Global News Retrieved July 18 2018 The Canadian Press June 4 2018 Rallies planned across Canada to protest Kinder Morgan buyout News 1130 Retrieved July 18 2018 Pipeline protesters block Trans Mountain oil tanker from Ironworkers Memorial Bridge July 3 2018 Retrieved September 7 2018 Hernandez Jon September 28 2021 Treetop camp protesting Trans Mountain pipeline dismantled CBC News Retrieved October 7 2021 a b Kilawna Kelsie October 24 2020 Secwepemc Matriarch cuts off her hair in defense of her lands and waters APTN National News Retrieved October 26 2020 a b c d Laferte Boston October 23 2020 Secwepemc set up new camp in hopes of halting TMX construction leads to five arrests The Martlet Retrieved October 26 2020 Brake Justin July 19 2018 Tiny House Warriors establish new village to resist pipeline assert Secwepemc sovereignty APTN National News Retrieved October 26 2020 a b Rothenburger Mel October 24 2020 ROTHENBURGER Protests and arrests were played out in a familiar script CFJC Today Retrieved October 26 2020 Sperling Jill October 5 2020 Camp set up near Mission Flats Road in protest of Trans Mountain pipeline expansion project CFJC Today Retrieved October 26 2020 a b 5 arrested after standing in way of Trans Mountain pipeline construction in B C Interior CBC News October 16 2020 Retrieved October 26 2020 Kergin Brendan October 18 2020 Tk emlups te Secwepemc leadership releases statement on TMX arrests Castanet net Archived from the original on October 23 2020 Retrieved October 26 2020 a b Verenca Tereza December 10 2018 Three arrested as judge consults with Indigenous groups about Trans Mountain project Burnaby Now Retrieved January 7 2019 a b c d Tasker John Paul June 18 2019 Trudeau cabinet approves Trans Mountain expansion project CBC News Retrieved January 12 2023 Federal officials say construction of the 7 4 billion pipeline is likely to begin in 2019 Orders In Council Government of Canada no 2019 0820 June 18 2019 retrieved June 19 2019 a b Trans Mountain Expansion Project Order in Council P C 2019 0820 Project update Letter from NEB to Trans Mountain and Tsleil Waututh Nation National Energy Board NEB Calgary Alberta June 18 2019 retrieved June 19 2019 Kestler D Amours Jillian O Toole Megan December 5 2019 Nations divided mapping Canada s pipeline battle Al Jazeera website Retrieved December 5 2019 External links editOil Across the Rockies Documentary of the building of the pipeline The Building of Trans Mountain Canada s First Oil Pipeline Across the Rockies Book about the building of the pipeline Retrieved from https en wikipedia org w index php title Trans Mountain pipeline amp oldid 1177995498, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.