fbpx
Wikipedia

Pickering Nuclear Generating Station

Pickering Nuclear Generating Station is a Canadian nuclear power station located on the north shore of Lake Ontario in Pickering, Ontario. It is one of the oldest nuclear power stations in the world and Canada's third-largest, consisting of eight CANDU reactors. Since 2003, two of these units have been defueled and the remaining six produce about 16% of Ontario's power and employ 3,000 workers.[3]

Pickering Nuclear Generating Station
Unit 4 Facing east with the large vacuum building and water tower in the background
CountryCanada
LocationPickering, Durham Region, Ontario
Coordinates43°48′42″N 79°03′57″W / 43.81167°N 79.06583°W / 43.81167; -79.06583Coordinates: 43°48′42″N 79°03′57″W / 43.81167°N 79.06583°W / 43.81167; -79.06583
StatusOperational
Construction beganUnit 1: June 1, 1966
Unit 2: September 1, 1966
Unit 3: December 1, 1967
Unit 4: May 1, 1968
Unit 5: November 1, 1974
Unit 6: October 1, 1975
Unit 7: March 1, 1976
Unit 8: September 1, 1976
Commission dateUnit 1: July 29, 1971
Unit 2: December 30, 1971
Unit 3: June 1, 1972
Unit 4 June 17, 1973
Unit 5: May 10, 1983
Unit 6: February 1, 1984
Unit 7: January 1, 1985
Unit 8: February 28, 1986 [1]
Decommission date28 May 2007 (A2)
31 Oct 2008 (A3)
Construction cost$716 million CAD (A station)
$3.84 billion CAD (B station)
Owner(s)Ontario Power Generation (OPG)
Operator(s)Ontario Power Generation (OPG)
Employees3000+
Nuclear power station
Reactor typeCANDU-500
Reactor supplierAECL
Cooling sourceLake Ontario
Thermal capacity6 × 1744 MWth
Power generation
Units operational2 × 515 MWe (NET A 1–4)
2 × 516 MWe (NET B 6–8)
1 × 522 MWe (NET B 7)
1 x 530 MWe (NET B 5)
Make and model2 × CANDU 500A
4 × CANDU 500B
Units decommissioned2 × 515 MW
Nameplate capacity3114 MW
Capacity factor73.85% (lifetime)
87.07% (2019)
Annual net output23,600 GW·h (2019) [2]
929,244 GW·h (lifetime)
External links
WebsitePickering Nuclear
CommonsRelated media on Commons

Located at the Pickering station until October 2019 was a single 1.8 MWe wind turbine named the OPG 7 commemorative turbine. The turbine was dismantled in stages during October 2019 [4]

Reactor codification

The reactors can be classified as follows:

PICKERING A

  • PICKERING A 1
  • PICKERING A 2 (Safe Shutdown state, defuelled)
  • PICKERING A 3 (Safe Shutdown state, defuelled)
  • PICKERING A 4

PICKERING B

  • PICKERING B 5
  • PICKERING B 6
  • PICKERING B 7
  • PICKERING B 8

Construction

The site was once Squires Beach located west of Duffins Creek. The facility was constructed in stages between 1965 and 1986[5] by the provincial Crown corporation, Ontario Hydro, with significant completion of Station A scheduled for 1971.[6] In April 1999, Ontario Hydro was split into five component Crown corporations with Ontario Power Generation (OPG) taking over all electricity generating stations.[7] OPG continues to operate the Pickering station.[8]

Operation

The Pickering station is a large multi-unit nuclear facility, comprising six operating CANDU nuclear reactors with a total output of 3,114 MW when all units are on line, and two non-operating units with a total output of 1,030 MW currently shut down in safe storage.[8] The facility is connected to the North American power grid via numerous 230 kV and 500 kV transmission lines.[9]

The facility was operated as two distinct stations, Pickering A (Units 1 to 4) and Pickering B (Units 5 to 8) until 2011.[10] While primarily administrative in nature, the division was not wholly artificial, as there are some distinct differences in design between the two groups of stations. (Example: The Pickering A units employ a moderator dump as a shutdown mechanism,[11] a feature not found in Pickering B, which instead uses what is called an over-poisoned reaction guaranteed shutdown.[12]) There are, however, a number of systems and structures in common between the two stations; the most notable of these is the shared vacuum building, a negative pressure containment system.[13] The operation of Pickering A and B was unified in 2010,[14] to reduce costs now that Pickering A Units 2 and 3 are shut down in safe storage.

Electrical Output

The graph represents the annual electricity generation at the site (A and B combined) in TWh.

As of the end of 2021, the total lifetime output of the facility was 929.24 TWh.

Partial shutdown

On December 31, 1997 the four Pickering A reactors were shut down by Ontario Hydro and placed in lay up, suspending work on upgrades to the shutdown system. Ontario Hydro committed to restarting the units, but the project underwent long delays and large cost over-runs.

Premier Mike Harris asked former federal energy Minister Jake Epp to study and make recommendations on the problems with the Pickering restart. The review panel was established in May 2003.

Unit 4 was refurbished and then restarted in Sept. 2003. The election of the Ontario Liberal Party in October 2003 delayed action on the Epp report. In late 2003, the new government fired the top three executives of OPG for botching the Unit 4 restoration, which was years late and millions of dollars over budget.[15]

Mr. Epp and the Pickering A Review Panel released their report in December 2003,[16] which acknowledged the large cost over-runs and delays, attributing blame to bad management. The Epp Review estimated the cost of restarting the remaining three reactors at $3 – 4 billion and supported the continuation of the project.

The government of Dalton McGuinty appointed Epp to the Ontario Power Generation Review headed by John Manley to examine the future role of Ontario Power Generation (OPG) in the province's electricity market, examine its corporate and management structure, and decide whether the public utility should proceed with refurbishing three more nuclear reactors at the Pickering nuclear power plant. The report recommended proceeding with the restart of Pickering “A” reactors 1, 2, and 3, sequentially. The report argued that the restart of units 2 and 3 would be contingent on whether “OPG will be able to succeed at the Unit 1 project."[17]

The McGuinty government accepted the OPG Review Committee's recommendation and allowed the refurbishment and restart of reactor 1, which still underwent cost over-runs and delays.[citation needed]

The anti-nuclear group Sierra Club of Canada criticized the 2004 OPG Review Committee report for not attributing any blame to the problems of nuclear technology, noting that there were no energy or environmental experts appointed to the panel.[18]

Numerous changes in executive-level staff and project management strategy were made for the follow-on project to refurbish Unit 1. The experience of refurbishing Pickering A Unit 1 was significantly different from Unit 4, with a much tighter adherence to schedule and budget.[citation needed] In August 2005, the OPG Board of Directors announced that Units 2 and 3 would not be refurbished due to specific technical and cost risks surrounding the material condition of these two units. Unit 1 was returned to service in November 2005, providing 542 MW of generating capacity for Ontario's electricity system.[citation needed]

 
The Pickering Nuclear Generating Station, viewed from the west. All eight reactors are visible, from 2.5km to 3.25km away.

Costs

Construction Costs

Ontario Hydro estimated the construction cost for the four Pickering "A" units at $508 million in 1965. Actual cost was $716 million (in 1971 dollars). The 1974 estimated cost for the four Pickering "B" units was $1.585 billion. Final cost was $3.846 billion (1986 dollars).[19]

Refurbishment Costs

According to Ontario's FAO, the cost for refurbishing Pickering A units deviated significantly from projections.[20]
- Pickering Unit 4 was slated to cost $460 million and ultimately ended up costing $1.25 billion.
- Pickering Unit 1 was slated to cost $210 million and ultimately ended up costing $1.00 billion.

However, the figure presented by the FAO for Unit 1 doesn't align with that provided by Ontario Energy Minister, Dwight Duncan, who indicated that Pickering Unit 1 would cost $900 million, putting the completed project much closer to budget.[21] This is supported by OPG stating that the project was completed on time and on budget.[22]

Waste

The used nuclear fuel and some refurbishment waste generated by the plant sits on-site at the Pickering Waste Management Facility. All operational low and intermediate-level waste is transported to OPG's Western Waste Management Facility at the Bruce nuclear site near Kincardine, Ontario. OPG has proposed the construction and operation of a deep geologic repository for the long-term storage of low and intermediate level waste on lands adjacent to the Western Waste Management Facility.[23] The Nuclear Waste Management Organization is currently seeking a site for a potential repository for the used fuel from all Canadian nuclear reactors.

Records

- On October 7, 1994, Pickering Unit 7 set the world record for continuous runtime at 894 days, a record that stood for 22 years. It was surpassed by Heysham 2 unit 8 in 2016, a facility located in the UK, owned by EDF.[24] This was subsequently surpassed by OPG's Darlington plant with Unit 1 running 1,106 consecutive days.[25]
- In 2019, Pickering set a site capacity factor record of 87.07%, producing 23.6TWh and putting it roughly on-par with the much newer Darlington and Bruce facilities.[2]

Future

In January 2016, the Province of Ontario approved plans to pursue continued operation of the Pickering Nuclear Generating Station to 2026.[26]

OPG will work with the Ministry of Energy, the Independent Electricity System Operator and the Ontario Energy Board to pursue continued operation of the Pickering Station to 2024. All six units would operate until 2024; two units would then shut down and four units would operate to 2026.[27] Extending Pickering's operation will ensure a reliable, clean source of base load electricity during refurbishment of the Darlington Nuclear Generating Station and the initial Bruce Nuclear refurbishments.[28]

Any plan to extend Pickering's life requires approval from the Canadian Nuclear Safety Commission (CNSC). OPG is currently working on a licence application to the CNSC for approval in 2018.

After operation of Pickering concludes, OPG will begin the longer term decommissioning process as refurbishment will not be pursued. The first step in the long term decommissioning process is to layup the reactors and place them into safe storage. Pickering staff will have future employment opportunities placing the Pickering units in a safe storage state, at the Darlington refurbishment and operations, or at the potential new build at Darlington.

OPG has begun planning for the station's end of commercial operations including the potential repurposing of the Pickering site location.[29]

OPG will proceed with a detailed planning phase for the mid-life refurbishment of the Darlington Nuclear Generating Station east of Toronto, with construction expected to start in 2016. The business decision to move forward with an investment in Darlington came after initial studies on the plant's condition operating performance returned positive results.

In January 2016, the Province of Ontario announced its decision to proceed with refurbishment of Darlington.[26]

In September 2022, The Province of Ontario announced its support for the continued operation of the Pickering Nuclear plant beyond its previously set closure date. Simultaniously, the province also announced its support for a refurbishment of Pickering B to allow for an additional 30 years of operation which would provide long-term stability to Ontario's electricity grid, and ensure a continued supply of cobalt-60 of which Pickering currently supplies 10% of all cobalt-60 used worldwide.[30]

Incidents

A serious incident occurred on 1 August 1983. Pressure tube G16 in the Pickering A Unit 2 reactor developed a 2 metre long split. The reactor was safely shut down and the damage investigated. The cause was found to be the mis-location of annulus gas spacer springs which allowed the hot pressure tube to sag and touch the inside of the cold calandria tube leading to hydrogen enrichment of the cooler areas. This created a series of small cracks which linked up and caused the long rupture. There was some local fuel damage and the reactor was safely shut down by the operators with no increase in radioactive emissions. The eventual resolution was Large Scale Fuel Channel Replacement and all the pressure tubes were replaced in all Pickering A reactors. The new pressure tubes were supported by an improved design of the annulus gas spacer springs. Since then, careful monitoring of the location of the annulus gas spacer rings has been a significant part of routine reactor inspections.[31]

On December 10, 1994 there was a loss of coolant accident. It is said to be the most serious accident in Canadian history (June 2001) by The Standing Senate Committee on Energy, the Environment and Natural Resources. The Emergency Core Cooling System was used to prevent a meltdown.[32][33]

On March 14, 2011, there was a leak of 73 cubic metres of demineralized water into Lake Ontario from a failed pump seal. There was negligible risk to the public according to the Canadian Nuclear Safety Commission.[34]

2020 nuclear incident alert

On January 12, 2020 at 7:24 a.m. ET, an emergency alert was issued via Alert Ready on all radio stations, television stations, television providers, and wireless networks in the province of Ontario, containing an advisory of an unspecified "incident" that had been reported and was being addressed at the plant. The alert stated that no immediate action was required for those within 10 kilometres (6.2 mi) of the plant. Approximately 40 minutes later, OPG issued a statement via Twitter that the alert had been sent in error, and a second emergency alert was issued at around 9:10 a.m. with a similar message cancelling the previous alert.[35][36]

Solicitor General Sylvia Jones stated that the alert was accidentally issued during a "routine training exercise" by Ontario's emergency operations centre. The incident prompted criticism from government officials, including MPP Peter Tabuns, Pickering mayor Dave Ryan, and Toronto mayor John Tory.[37]

The false alarm also prompted renewed interest in preparedness for actual nuclear accidents: OPG reported a surge in the sales of potassium iodide kits via its "Prepare to Be Safe" website between January 12 and 13, increasing from its monthly average of 100 to 200, to over 32,000. The website is applicable for those who live within 50 kilometres (31 mi) of the plant; per Canadian Nuclear Safety Commission (CNSC) requirements, OPG is required to distribute these pills to all residences within 10 kilometres (6.2 mi) of a nuclear facility.[38][39][40]

See also

References

  1. ^ . Archived from the original on 2020-03-12. Retrieved 2020-09-09.
  2. ^ a b "Our story > Pickering Nuclear celebrates record-setting year". OPG. 2020-01-30. from the original on 2020-06-09. Retrieved 2021-11-29.
  3. ^ Shah, Maryam (2013-06-22). "Future of Pickering nuclear plant a hot topic in Durham Region". Toronto Sun. from the original on 2016-08-16. Retrieved 2014-07-02.
  4. ^ "Removal of Pickering wind turbine – Sept. 30 to Nov. 8, 2019". OPG. 2019-09-27. from the original on 2020-06-09. Retrieved 2021-11-29.
  5. ^ "Better Never than Late: The Climate Fall-Out of Ontario's Nuclear Electricity Plan" (PDF). Greenpeace Canada. October 2008.
  6. ^ "it seems like only yesterday this was a farmer's field". Canadian Champion (Milton, ON). 1967-04-05. p. 5. from the original on 2020-03-21.
  7. ^ "A look at the long, complicated history of Ontario hydro". YorkRegion.com. 2017-03-09. from the original on 2020-11-12. Retrieved 2020-05-13.
  8. ^ a b "Pickering Nuclear Generating Station". OPG. from the original on 2021-04-23. Retrieved 2021-11-29.
  9. ^ "Pickering-Ajax-Whitby Sub-region Integrated Regional Resource Plan - Appendices" (PDF). 2016-06-30. (PDF) from the original on 2019-02-24.
  10. ^ McClearn, Matthew; Baum, Kathryn Blaze (16 January 2020). "Ontario government supports OPG proposal to operate Pickering nuclear station past planned 2024 closing". The Globe and Mail. from the original on 18 January 2020. Retrieved 13 May 2020.
  11. ^ "The Use of Rod-Based Guaranteed Shutdown State in CANDU Reactors". Canadian Nuclear Safety Commission. 2016-04-08. from the original on 2021-11-20. Retrieved 2021-11-29.
  12. ^ Urjan, R. (2010). "Rod-Based Guaranteed Shutdown States (RBGSS) implementation at Pickering B (IAEA-TECDOC--1650)". International Atomic Energy Agency (IAEA). from the original on 2020-06-09. Retrieved 2021-11-29.
  13. ^ "Pickering Nuclear Generating Station". Canadian Nuclear Safety Commission. 3 February 2014. from the original on 2021-11-18. Retrieved 2021-11-29.
  14. ^ "EB-2013-0321 - Decision with Reasons" (PDF). Ontario Energy Board. 2014-11-20. (PDF) from the original on 2020-12-16.
  15. ^ Luciw, Roma (12 August 2005). "OPG cancels Pickering repairs". The Globe and Mail. from the original on 9 June 2020. Retrieved 13 May 2020.
  16. ^ "Report Of The Pickering "A" Review Panel" (PDF). December 2003. (PDF) from the original on 2020-06-09.
  17. ^ Manley, J.; Epp, J.; Godsoe, P.C. (2004-03-15). Transforming Ontario's Power Generation Company (Report). The Ontario Power Generation Review Committee. p. 47 – via INIS.
  18. ^ . Sierra Club of Canada. 2004-03-17. Archived from the original on 16 April 2004.
  19. ^ (PDF). www.pembinafoundation.org. Archived from the original (PDF) on 4 April 2017. Retrieved 19 April 2022.
  20. ^ "Nuclear Refurbishment - An Assessment of the Financial Risks of the Nuclear Refurbishment Plan" (PDF). FAO - Financial Accountability Office of Ontario. Fall 2017. (PDF) from the original on 2021-01-26.
  21. ^ "Ontario government gives thumbs up to Pickering A1 restart". Nuclear Engineering International. 2004-07-26. from the original on 2020-09-05. Retrieved 2022-06-08.
  22. ^ "OPG Moves to Planning Phase of Darlington Refurbishment". Cision Canada. 2010-02-16. Retrieved 2022-06-08.
  23. ^ "Deep Geologic Repository". OPG. Retrieved 2011-04-11.
  24. ^ Larson, Aaron (2016-09-21). "New Record: Nuclear Power Plant Online for 940 Continuous Days". PowerMagazine. from the original on 2021-10-09. Retrieved 2021-11-29.
  25. ^ "Darlington's Unit 1 heads into planned outage after record-breaking run". OPG. 2021-02-05. from the original on 2022-01-13. Retrieved 2022-01-13.
  26. ^ a b . news.ontario.ca. 2016-01-11. Archived from the original on 2016-04-14.
  27. ^ "Pickering Nuclear Generating Station". Ontario Power Generation. from the original on 2016-07-11. Retrieved 2016-06-28.
  28. ^ . Canada's Ministry of Energy. Archived from the original on 2016-07-09. Retrieved 2016-06-28.
  29. ^ . Ontario Power Generation. Archived from the original on 2016-07-18.
  30. ^ "Ontario extends Pickering operations : Energy & Environment - World Nuclear News".
  31. ^ "EXAMINATION OF THE PRESSURE TUBE RUPTURE AT PICKERING NGS 'A' UNIT 2, FUEL CHANNEL G16" (PDF). (PDF) from the original on 2013-10-05. Retrieved 2013-07-21.
  32. ^ "Nuclear Threat in the Eastern Mediterranean" David H. Martin, June 2000, Page 10 (or page 17 of 106) 2014-10-13 at the Wayback Machine
  33. ^ ""Pickering A Shutdown and Rehabilitation: A Brief History" page 4 (or page 11 of 51)" (PDF). (PDF) from the original on 2019-02-03. Retrieved 2019-02-03.
  34. ^ "Pickering Nuclear plant reports water leak, CBC News, March 16 2011". from the original on 2012-04-30. Retrieved 2012-04-25.
  35. ^ "Ontario government apologizes for alert about Pickering nuclear plant incident sent 'in error'". CBC News. 2020-01-12. from the original on 2020-01-12. Retrieved 2020-01-12.
  36. ^ "Pickering Nuclear Generating Station emergency alert issued in error, OPG says". Global News. from the original on 2020-01-12. Retrieved 2020-01-12.
  37. ^ Austen, Ian (2020-01-12). "Ontario Warned of a Nuclear 'Emergency,' Then Said Never Mind". The New York Times. ISSN 0362-4331. from the original on 2020-01-12. Retrieved 2020-01-12.
  38. ^ "Iodide pills protect you in a nuclear disaster. So, why didn't more people have them before the Pickering scare?". Toronto Star. 20 January 2020. from the original on 2020-01-20. Retrieved 2020-01-21.
  39. ^ "Orders for potassium iodide pills surge after false alarm at Pickering nuclear power plant". Toronto Star. 14 January 2020. from the original on 2020-01-15. Retrieved 2020-01-21.
  40. ^ "Over 32,000 potassium iodide pills ordered in 2 days after Pickering nuclear power plant alert error". CBC News. January 14, 2020. from the original on January 16, 2020. Retrieved January 20, 2020.

External links

  • Ontario Power Generation
  • Google maps satellite image

pickering, nuclear, generating, station, canadian, nuclear, power, station, located, north, shore, lake, ontario, pickering, ontario, oldest, nuclear, power, stations, world, canada, third, largest, consisting, eight, candu, reactors, since, 2003, these, units. Pickering Nuclear Generating Station is a Canadian nuclear power station located on the north shore of Lake Ontario in Pickering Ontario It is one of the oldest nuclear power stations in the world and Canada s third largest consisting of eight CANDU reactors Since 2003 two of these units have been defueled and the remaining six produce about 16 of Ontario s power and employ 3 000 workers 3 Pickering Nuclear Generating StationUnit 4 Facing east with the large vacuum building and water tower in the backgroundCountryCanadaLocationPickering Durham Region OntarioCoordinates43 48 42 N 79 03 57 W 43 81167 N 79 06583 W 43 81167 79 06583 Coordinates 43 48 42 N 79 03 57 W 43 81167 N 79 06583 W 43 81167 79 06583StatusOperationalConstruction beganUnit 1 June 1 1966Unit 2 September 1 1966Unit 3 December 1 1967Unit 4 May 1 1968Unit 5 November 1 1974Unit 6 October 1 1975Unit 7 March 1 1976Unit 8 September 1 1976Commission dateUnit 1 July 29 1971Unit 2 December 30 1971Unit 3 June 1 1972Unit 4 June 17 1973Unit 5 May 10 1983Unit 6 February 1 1984Unit 7 January 1 1985Unit 8 February 28 1986 1 Decommission date28 May 2007 A2 31 Oct 2008 A3 Construction cost 716 million CAD A station 3 84 billion CAD B station Owner s Ontario Power Generation OPG Operator s Ontario Power Generation OPG Employees3000 Nuclear power stationReactor typeCANDU 500Reactor supplierAECLCooling sourceLake OntarioThermal capacity6 1744 MWthPower generationUnits operational2 515 MWe NET A 1 4 2 516 MWe NET B 6 8 1 522 MWe NET B 7 1 x 530 MWe NET B 5 Make and model2 CANDU 500A4 CANDU 500BUnits decommissioned2 515 MWNameplate capacity3114 MWCapacity factor73 85 lifetime 87 07 2019 Annual net output23 600 GW h 2019 2 929 244 GW h lifetime External linksWebsitePickering NuclearCommonsRelated media on Commons edit on Wikidata Located at the Pickering station until October 2019 was a single 1 8 MWe wind turbine named the OPG 7 commemorative turbine The turbine was dismantled in stages during October 2019 4 Contents 1 Reactor codification 2 Construction 3 Operation 4 Electrical Output 5 Partial shutdown 6 Costs 6 1 Construction Costs 6 2 Refurbishment Costs 7 Waste 8 Records 9 Future 10 Incidents 10 1 2020 nuclear incident alert 11 See also 12 References 13 External linksReactor codification EditThe reactors can be classified as follows PICKERING A PICKERING A 1 PICKERING A 2 Safe Shutdown state defuelled PICKERING A 3 Safe Shutdown state defuelled PICKERING A 4PICKERING B PICKERING B 5 PICKERING B 6 PICKERING B 7 PICKERING B 8Construction EditThe site was once Squires Beach located west of Duffins Creek The facility was constructed in stages between 1965 and 1986 5 by the provincial Crown corporation Ontario Hydro with significant completion of Station A scheduled for 1971 6 In April 1999 Ontario Hydro was split into five component Crown corporations with Ontario Power Generation OPG taking over all electricity generating stations 7 OPG continues to operate the Pickering station 8 Operation EditThe Pickering station is a large multi unit nuclear facility comprising six operating CANDU nuclear reactors with a total output of 3 114 MW when all units are on line and two non operating units with a total output of 1 030 MW currently shut down in safe storage 8 The facility is connected to the North American power grid via numerous 230 kV and 500 kV transmission lines 9 The facility was operated as two distinct stations Pickering A Units 1 to 4 and Pickering B Units 5 to 8 until 2011 10 While primarily administrative in nature the division was not wholly artificial as there are some distinct differences in design between the two groups of stations Example The Pickering A units employ a moderator dump as a shutdown mechanism 11 a feature not found in Pickering B which instead uses what is called an over poisoned reaction guaranteed shutdown 12 There are however a number of systems and structures in common between the two stations the most notable of these is the shared vacuum building a negative pressure containment system 13 The operation of Pickering A and B was unified in 2010 14 to reduce costs now that Pickering A Units 2 and 3 are shut down in safe storage Electrical Output EditThe graph represents the annual electricity generation at the site A and B combined in TWh As of the end of 2021 the total lifetime output of the facility was 929 24 TWh Partial shutdown EditOn December 31 1997 the four Pickering A reactors were shut down by Ontario Hydro and placed in lay up suspending work on upgrades to the shutdown system Ontario Hydro committed to restarting the units but the project underwent long delays and large cost over runs Premier Mike Harris asked former federal energy Minister Jake Epp to study and make recommendations on the problems with the Pickering restart The review panel was established in May 2003 Unit 4 was refurbished and then restarted in Sept 2003 The election of the Ontario Liberal Party in October 2003 delayed action on the Epp report In late 2003 the new government fired the top three executives of OPG for botching the Unit 4 restoration which was years late and millions of dollars over budget 15 Mr Epp and the Pickering A Review Panel released their report in December 2003 16 which acknowledged the large cost over runs and delays attributing blame to bad management The Epp Review estimated the cost of restarting the remaining three reactors at 3 4 billion and supported the continuation of the project The government of Dalton McGuinty appointed Epp to the Ontario Power Generation Review headed by John Manley to examine the future role of Ontario Power Generation OPG in the province s electricity market examine its corporate and management structure and decide whether the public utility should proceed with refurbishing three more nuclear reactors at the Pickering nuclear power plant The report recommended proceeding with the restart of Pickering A reactors 1 2 and 3 sequentially The report argued that the restart of units 2 and 3 would be contingent on whether OPG will be able to succeed at the Unit 1 project 17 The McGuinty government accepted the OPG Review Committee s recommendation and allowed the refurbishment and restart of reactor 1 which still underwent cost over runs and delays citation needed The anti nuclear group Sierra Club of Canada criticized the 2004 OPG Review Committee report for not attributing any blame to the problems of nuclear technology noting that there were no energy or environmental experts appointed to the panel 18 Numerous changes in executive level staff and project management strategy were made for the follow on project to refurbish Unit 1 The experience of refurbishing Pickering A Unit 1 was significantly different from Unit 4 with a much tighter adherence to schedule and budget citation needed In August 2005 the OPG Board of Directors announced that Units 2 and 3 would not be refurbished due to specific technical and cost risks surrounding the material condition of these two units Unit 1 was returned to service in November 2005 providing 542 MW of generating capacity for Ontario s electricity system citation needed The Pickering Nuclear Generating Station viewed from the west All eight reactors are visible from 2 5km to 3 25km away Costs EditConstruction Costs Edit Ontario Hydro estimated the construction cost for the four Pickering A units at 508 million in 1965 Actual cost was 716 million in 1971 dollars The 1974 estimated cost for the four Pickering B units was 1 585 billion Final cost was 3 846 billion 1986 dollars 19 Refurbishment Costs Edit According to Ontario s FAO the cost for refurbishing Pickering A units deviated significantly from projections 20 Pickering Unit 4 was slated to cost 460 million and ultimately ended up costing 1 25 billion Pickering Unit 1 was slated to cost 210 million and ultimately ended up costing 1 00 billion However the figure presented by the FAO for Unit 1 doesn t align with that provided by Ontario Energy Minister Dwight Duncan who indicated that Pickering Unit 1 would cost 900 million putting the completed project much closer to budget 21 This is supported by OPG stating that the project was completed on time and on budget 22 Waste EditThe used nuclear fuel and some refurbishment waste generated by the plant sits on site at the Pickering Waste Management Facility All operational low and intermediate level waste is transported to OPG s Western Waste Management Facility at the Bruce nuclear site near Kincardine Ontario OPG has proposed the construction and operation of a deep geologic repository for the long term storage of low and intermediate level waste on lands adjacent to the Western Waste Management Facility 23 The Nuclear Waste Management Organization is currently seeking a site for a potential repository for the used fuel from all Canadian nuclear reactors Records Edit On October 7 1994 Pickering Unit 7 set the world record for continuous runtime at 894 days a record that stood for 22 years It was surpassed by Heysham 2 unit 8 in 2016 a facility located in the UK owned by EDF 24 This was subsequently surpassed by OPG s Darlington plant with Unit 1 running 1 106 consecutive days 25 In 2019 Pickering set a site capacity factor record of 87 07 producing 23 6TWh and putting it roughly on par with the much newer Darlington and Bruce facilities 2 Future EditIn January 2016 the Province of Ontario approved plans to pursue continued operation of the Pickering Nuclear Generating Station to 2026 26 OPG will work with the Ministry of Energy the Independent Electricity System Operator and the Ontario Energy Board to pursue continued operation of the Pickering Station to 2024 All six units would operate until 2024 two units would then shut down and four units would operate to 2026 27 Extending Pickering s operation will ensure a reliable clean source of base load electricity during refurbishment of the Darlington Nuclear Generating Station and the initial Bruce Nuclear refurbishments 28 Any plan to extend Pickering s life requires approval from the Canadian Nuclear Safety Commission CNSC OPG is currently working on a licence application to the CNSC for approval in 2018 After operation of Pickering concludes OPG will begin the longer term decommissioning process as refurbishment will not be pursued The first step in the long term decommissioning process is to layup the reactors and place them into safe storage Pickering staff will have future employment opportunities placing the Pickering units in a safe storage state at the Darlington refurbishment and operations or at the potential new build at Darlington OPG has begun planning for the station s end of commercial operations including the potential repurposing of the Pickering site location 29 OPG will proceed with a detailed planning phase for the mid life refurbishment of the Darlington Nuclear Generating Station east of Toronto with construction expected to start in 2016 The business decision to move forward with an investment in Darlington came after initial studies on the plant s condition operating performance returned positive results In January 2016 the Province of Ontario announced its decision to proceed with refurbishment of Darlington 26 In September 2022 The Province of Ontario announced its support for the continued operation of the Pickering Nuclear plant beyond its previously set closure date Simultaniously the province also announced its support for a refurbishment of Pickering B to allow for an additional 30 years of operation which would provide long term stability to Ontario s electricity grid and ensure a continued supply of cobalt 60 of which Pickering currently supplies 10 of all cobalt 60 used worldwide 30 Incidents EditA serious incident occurred on 1 August 1983 Pressure tube G16 in the Pickering A Unit 2 reactor developed a 2 metre long split The reactor was safely shut down and the damage investigated The cause was found to be the mis location of annulus gas spacer springs which allowed the hot pressure tube to sag and touch the inside of the cold calandria tube leading to hydrogen enrichment of the cooler areas This created a series of small cracks which linked up and caused the long rupture There was some local fuel damage and the reactor was safely shut down by the operators with no increase in radioactive emissions The eventual resolution was Large Scale Fuel Channel Replacement and all the pressure tubes were replaced in all Pickering A reactors The new pressure tubes were supported by an improved design of the annulus gas spacer springs Since then careful monitoring of the location of the annulus gas spacer rings has been a significant part of routine reactor inspections 31 On December 10 1994 there was a loss of coolant accident It is said to be the most serious accident in Canadian history June 2001 by The Standing Senate Committee on Energy the Environment and Natural Resources The Emergency Core Cooling System was used to prevent a meltdown 32 33 On March 14 2011 there was a leak of 73 cubic metres of demineralized water into Lake Ontario from a failed pump seal There was negligible risk to the public according to the Canadian Nuclear Safety Commission 34 2020 nuclear incident alert Edit Main article Alert Ready False alarms On January 12 2020 at 7 24 a m ET an emergency alert was issued via Alert Ready on all radio stations television stations television providers and wireless networks in the province of Ontario containing an advisory of an unspecified incident that had been reported and was being addressed at the plant The alert stated that no immediate action was required for those within 10 kilometres 6 2 mi of the plant Approximately 40 minutes later OPG issued a statement via Twitter that the alert had been sent in error and a second emergency alert was issued at around 9 10 a m with a similar message cancelling the previous alert 35 36 Solicitor General Sylvia Jones stated that the alert was accidentally issued during a routine training exercise by Ontario s emergency operations centre The incident prompted criticism from government officials including MPP Peter Tabuns Pickering mayor Dave Ryan and Toronto mayor John Tory 37 The false alarm also prompted renewed interest in preparedness for actual nuclear accidents OPG reported a surge in the sales of potassium iodide kits via its Prepare to Be Safe website between January 12 and 13 increasing from its monthly average of 100 to 200 to over 32 000 The website is applicable for those who live within 50 kilometres 31 mi of the plant per Canadian Nuclear Safety Commission CNSC requirements OPG is required to distribute these pills to all residences within 10 kilometres 6 2 mi of a nuclear facility 38 39 40 See also Edit Ontario portal Energy portal Nuclear technology portalList of largest power stations in Canada List of nuclear reactors in Canada Nuclear power in Canada Darlington Nuclear Generating Station Bruce Nuclear Generating Station Point Lepreau Nuclear Generating Station Fitzpatrick Nuclear Generating Station Nine Mile Point Nuclear Generating Station Frenchman s BayReferences Edit Preliminary Decommissioning Plan Pickering Generating Stations A amp B Archived from the original on 2020 03 12 Retrieved 2020 09 09 a b Our story gt Pickering Nuclear celebrates record setting year OPG 2020 01 30 Archived from the original on 2020 06 09 Retrieved 2021 11 29 Shah Maryam 2013 06 22 Future of Pickering nuclear plant a hot topic in Durham Region Toronto Sun Archived from the original on 2016 08 16 Retrieved 2014 07 02 Removal of Pickering wind turbine Sept 30 to Nov 8 2019 OPG 2019 09 27 Archived from the original on 2020 06 09 Retrieved 2021 11 29 Better Never than Late The Climate Fall Out of Ontario s Nuclear Electricity Plan PDF Greenpeace Canada October 2008 it seems like only yesterday this was a farmer s field Canadian Champion Milton ON 1967 04 05 p 5 Archived from the original on 2020 03 21 A look at the long complicated history of Ontario hydro YorkRegion com 2017 03 09 Archived from the original on 2020 11 12 Retrieved 2020 05 13 a b Pickering Nuclear Generating Station OPG Archived from the original on 2021 04 23 Retrieved 2021 11 29 Pickering Ajax Whitby Sub region Integrated Regional Resource Plan Appendices PDF 2016 06 30 Archived PDF from the original on 2019 02 24 McClearn Matthew Baum Kathryn Blaze 16 January 2020 Ontario government supports OPG proposal to operate Pickering nuclear station past planned 2024 closing The Globe and Mail Archived from the original on 18 January 2020 Retrieved 13 May 2020 The Use of Rod Based Guaranteed Shutdown State in CANDU Reactors Canadian Nuclear Safety Commission 2016 04 08 Archived from the original on 2021 11 20 Retrieved 2021 11 29 Urjan R 2010 Rod Based Guaranteed Shutdown States RBGSS implementation at Pickering B IAEA TECDOC 1650 International Atomic Energy Agency IAEA Archived from the original on 2020 06 09 Retrieved 2021 11 29 Pickering Nuclear Generating Station Canadian Nuclear Safety Commission 3 February 2014 Archived from the original on 2021 11 18 Retrieved 2021 11 29 EB 2013 0321 Decision with Reasons PDF Ontario Energy Board 2014 11 20 Archived PDF from the original on 2020 12 16 Luciw Roma 12 August 2005 OPG cancels Pickering repairs The Globe and Mail Archived from the original on 9 June 2020 Retrieved 13 May 2020 Report Of The Pickering A Review Panel PDF December 2003 Archived PDF from the original on 2020 06 09 Manley J Epp J Godsoe P C 2004 03 15 Transforming Ontario s Power Generation Company Report The Ontario Power Generation Review Committee p 47 via INIS Manley Expected to Support Pickering Nuclear Boondoggle Sierra Club of Canada 2004 03 17 Archived from the original on 16 April 2004 Appendix 2 Ontario s Nuclear Generating Facilities A History and Estimate of Unit Lifetimes and Refurbishment Costs PDF www pembinafoundation org Archived from the original PDF on 4 April 2017 Retrieved 19 April 2022 Nuclear Refurbishment An Assessment of the Financial Risks of the Nuclear Refurbishment Plan PDF FAO Financial Accountability Office of Ontario Fall 2017 Archived PDF from the original on 2021 01 26 Ontario government gives thumbs up to Pickering A1 restart Nuclear Engineering International 2004 07 26 Archived from the original on 2020 09 05 Retrieved 2022 06 08 OPG Moves to Planning Phase of Darlington Refurbishment Cision Canada 2010 02 16 Retrieved 2022 06 08 Deep Geologic Repository OPG Retrieved 2011 04 11 Larson Aaron 2016 09 21 New Record Nuclear Power Plant Online for 940 Continuous Days PowerMagazine Archived from the original on 2021 10 09 Retrieved 2021 11 29 Darlington s Unit 1 heads into planned outage after record breaking run OPG 2021 02 05 Archived from the original on 2022 01 13 Retrieved 2022 01 13 a b Ontario Moving Forward with Nuclear Refurbishment at Darlington and Pursuing Continued Operations at Pickering to 2024 news ontario ca 2016 01 11 Archived from the original on 2016 04 14 Pickering Nuclear Generating Station Ontario Power Generation Archived from the original on 2016 07 11 Retrieved 2016 06 28 Ontario s Long Term Energy Plan Canada s Ministry of Energy Archived from the original on 2016 07 09 Retrieved 2016 06 28 Repurposing Pickering Ontario Power Generation Archived from the original on 2016 07 18 Ontario extends Pickering operations Energy amp Environment World Nuclear News EXAMINATION OF THE PRESSURE TUBE RUPTURE AT PICKERING NGS A UNIT 2 FUEL CHANNEL G16 PDF Archived PDF from the original on 2013 10 05 Retrieved 2013 07 21 Nuclear Threat in the Eastern Mediterranean David H Martin June 2000 Page 10 or page 17 of 106 Archived 2014 10 13 at the Wayback Machine Pickering A Shutdown and Rehabilitation A Brief History page 4 or page 11 of 51 PDF Archived PDF from the original on 2019 02 03 Retrieved 2019 02 03 Pickering Nuclear plant reports water leak CBC News March 16 2011 Archived from the original on 2012 04 30 Retrieved 2012 04 25 Ontario government apologizes for alert about Pickering nuclear plant incident sent in error CBC News 2020 01 12 Archived from the original on 2020 01 12 Retrieved 2020 01 12 Pickering Nuclear Generating Station emergency alert issued in error OPG says Global News Archived from the original on 2020 01 12 Retrieved 2020 01 12 Austen Ian 2020 01 12 Ontario Warned of a Nuclear Emergency Then Said Never Mind The New York Times ISSN 0362 4331 Archived from the original on 2020 01 12 Retrieved 2020 01 12 Iodide pills protect you in a nuclear disaster So why didn t more people have them before the Pickering scare Toronto Star 20 January 2020 Archived from the original on 2020 01 20 Retrieved 2020 01 21 Orders for potassium iodide pills surge after false alarm at Pickering nuclear power plant Toronto Star 14 January 2020 Archived from the original on 2020 01 15 Retrieved 2020 01 21 Over 32 000 potassium iodide pills ordered in 2 days after Pickering nuclear power plant alert error CBC News January 14 2020 Archived from the original on January 16 2020 Retrieved January 20 2020 External links Edit Wikimedia Commons has media related to Pickering Nuclear Generating Station Ontario Power Generation Google maps satellite image Retrieved from https en wikipedia org w index php title Pickering Nuclear Generating Station amp oldid 1118745280, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.