The Olympic Dam mine is a large poly-metallic underground mine located in South Australia, 550 km (340 mi) NNW of Adelaide. It is the fourth largest copper deposit and the largest known single deposit of uranium in the world. Copper is the largest contributor to total revenue, accounting for approximately 70% of the mine's revenue, with the remaining 25% from uranium, and around 5% from silver and gold.[1] BHP has owned and operated the mine since 2005. The mine was previously owned by Western Mining Corporation.

Olympic Dam mine
Clarke and Robinson shafts (centre)
Location
Olympic Dam
Location in Australia
LocationOlympic Dam
StateSouth Australia
CountryAustralia
Coordinates30°26′24″S 136°52′23″E / 30.44000°S 136.87306°E / -30.44000; 136.87306
Production
Productscopper
uranium oxide
gold
silver
TypeUnderground
History
Discovered1975
Opened1988
Owner
CompanyBHP
Year of acquisition2005

Since it opened in 1988, an extensive underground mine, an integrated metallurgical processing plant and expansive open-air tailings storage facilities have been constructed. The adjacent Olympic Dam mining centre and the nearby township of Roxby Downs service the mine and accommodate its workforce. Daily flights to and from Adelaide are provided via the Olympic Dam Airport.

BHP planned to expand the mine by establishing a new open cut pit and building extensive supporting infrastructure. In 2012 the expansion was postponed indefinitely pending investigation of a "new and cheaper design".[2]

Scale of production Edit

As of 2013, Olympic Dam is the second largest uranium-producing mine in the world, having produced 4,100 tonnes (4,000 long tons; 4,500 short tons) of uranium metal in the financial year ending June 2013. The only larger producer is the McArthur River uranium mine in Canada.[3] Given the energy density of uranium, this quantity is equal to a heating value of 820 TWh (equivalent to 705.5 megatonnes of TNT (2,952 PJ)) at a CANDU-typical burnup of 200 MWhthermal/kg.[4] Other reactor types which require uranium enrichment will recover slightly different amounts of heat from this amount of uranium. For comparison to get the same amount of heat energy by burning coal (energy density ranging from 24 to 35 MJ/kg) one would need between 84.34 megatonnes (83,010,000 long tons; 92,970,000 short tons) and 123 megatonnes (121,000,000 long tons; 136,000,000 short tons) of coal depending on grade. The largest coal mine in the world, North Antelope Rochelle Mine in Wyoming, produced 85.3 megatonnes (84,000,000 long tons; 94,000,000 short tons) of coal in 2019 at a grade of 3,800 kilojoules per kilogram (1,600 BTU/lb) equivalent to roughly 3.24×1011 megajoules (9.0×1010 kWh) of heat energy.

History Edit

 
Olympic Dam phreatic stage diagram of the volcanogenic uranium deposit.

In 1979 a joint venture partnership was established between Western Mining Corporation and BP Minerals with the intention of establishing the mine. Three years later, the Roxby Downs (Indenture Ratification) Act 1982 was signed, creating a legal framework for the development to proceed. The first shaft was constructed that year, and named the Whenan Shaft after Ted Whenan, one of the exploration drillers who discovered the ore body. The new municipality of Roxby Downs was also established in 1982, as an intended service centre and community hub for the mine workers and their families. In 1983, the mine's first Environmental Impact Statement was approved, authorising copper production of up to 150,000 tonnes per annum. Over a decade would pass before this production target was achieved.

In 1987, a decline entrance to the mine was created, and the Olympic Dam Special Mining Lease was connected to the South Australian electricity grid. The mine was officially opened the following year, and the first shipments of copper cathodes and uranium oxide were made. Roxby Downs township was officially opened, and the town's newspaper, the Roxby Downs Sun commenced publication. In 1989, the Olympic Dam refinery produced its first gold and silver bars.[5]

In 1993, Western Mining Corporation bought BP's 49% shareholding and assumed total control of the project.[6] Several stages of expansion occurred around this time and production increased. In 1986, the mine's target production had been set at 45,000 tonnes of copper per annum. In 1992, output reached 66,000 tonnes, then 84,000 in 1995.

The mine's first major expansion was announced in 1996 with the objective of producing 200,000 tonnes per annum once complete. A second Environmental Impact Statement was approved, allowing the mine to expand production up to 350,000 tonnes of copper per annum.

In 1998 the mine poured its 500th bar of gold. Two years later the mine produced 200,000 tonnes of copper in a year for the first time. Optimisation efforts increased output to 235,000 tonnes per annum in 2002.[5]

BHP made a successful bid for Western Mining Corporation in March 2005 and the offer was accepted by the Australian Competition & Consumer Commission in April.[7] BHP Billiton was not the only resources company to express interest in the project. Xstrata had made prior takeover bids in late 2004,[8] and French state-run nuclear industrial company Areva had entered into what were rumoured to be partnership discussions with WMC Resources in February.[9]

After the acquisition, BHP began to plan what would become a proposed $30 billion expansion project, involving the excavation of a new open cut mine within the existing Special Mining Lease. The expansion plan was expected to be a boon to the South Australian economy- forecast to generate an estimated 23,000 direct and indirect jobs. Major new infrastructure would need to be constructed to facilitate the expansion, including a new airport at Olympic Dam, a rail link, a seawater desalination plant at Point Lowly, a barge-landing facility near Port Augusta and a worker village near Andamooka.

The company's access to the Government of South Australia was enhanced by the formation of the Olympic Dam Task Force in 2006, which has since served as a single entry-point for the company's interactions with the state.[10] BHP also began to develop relationships with scientific and academic institutions with the objective of facilitating relevant technical, environmental and policy research.

Research sponsorship and partnerships Edit

Academic research related to the Olympic Dam mine and funded by BHP Billiton has been undertaken by at least four major South Australian institutions since the take-over. Works have included producing a projection of future skill requirements for Olympic Dam by Flinders University,[11] research into novel "liquid mining" techniques conducted by a team at the South Australian Museum,[12] numerous studies at the Environment Institute and Institute for Mineral and Energy Resources (IMER) at the University of Adelaide and numerous more at the Ian Wark Research Institute at the University of South Australia.[13]

In 2008, the Ian Wark Research Institute entered a research partnership with BHP. The company committed to provide $500,000 per annum for five consecutive years for research programs. The institute's annual report that year referred to BHP Billiton as having had a representative on their advisory board for "many years".[14] In 2012, the Institute for Mineral and Energy Resources at the University of Adelaide was awarded over $2.5 million as part of the Australian Research Council's Industrial Transformation Program. Funds were to be spent over six years during the establishment of a research hub for advancing copper-uranium production. BHP Billiton partnered with IMER on the project and is providing $2.5 million in cash plus additional in-kind contributions.[15]

BHP executives have also held numerous board memberships within academic institutions since the Olympic Dam take-over. Andrew Shook, general manager of BHP Billiton's Uranium Customer Sector Group, held a position on the advisory board of the Ian Wark Research Institute from 2009 to 2011, and Robert Sumner held a position as an adjunct senior research fellow there for the same period.[13][16][17] John England, the vice president of technology, Uranium Customer Sector Group at BHP Billiton, was appointed to the advisory board of IMER from its establishment in 2009 until 2014. President of Uranium Dean Dalla Valle also held a position on the IMER advisory board in 2009 to 2010[18] and another on the board of the South Australian Museum from 2011 to 2012. Vice President Sustainability at BHP Billiton, Carl Binning, has held a position on the Board of the Environment Institute since at least 2011.[19] He ceased working for BHP Billiton in 2012 but continues to hold his board position.

Industry associations Edit

BHP Olympic Dam is a member of the World Nuclear Association,[20] whose mission is "to promote a wider understanding of nuclear energy among key international influencers by producing authoritative information, developing common industry positions, and contributing to the energy debate."[21] BHP Billiton is also a full member of the Minerals Council of Australia's Uranium Forum, where the interests of the Olympic Dam project are represented.[22]

Sponsorships Edit

BHP sponsors a variety of events and organisations. Some are directly linked to the company's uranium portfolio, which is exclusively represented by the Olympic Dam mine. In 2016, BHP Billiton was the major sponsor of the Australian Radiation Protection Society's (ARPS) 2016 Conference, held in Adelaide.[23] Tours of the Olympic Dam mine have also been offered to delegates of uranium and mining industry conferences held in South Australia.[24]

Proposed expansion Edit

At the time of the BHP takeover, WMC Resources was investigating ways to expand the mine, including considering constructing a prospective seawater desalination plant at Port Bonython (Point Lowly).[25]

In 2008, BHP completed a pre-feasibility study into the expansion of the mine's operations, with the first step of expansion scheduled for completion by late 2013. In December 2008, South Australia's Premier Mike Rann revealed advice from BHP that the project would proceed as an open-cut operation.[26]

While being welcomed at the time by state and federal governments as a major boost to the economy, the proposed expansion of mining operations also attracted considerable criticism. In 2007, BHP Billiton attracted public attention for delaying the release of its environmental impact statement for the Olympic Dam expansion, and for the company's response to inconsistencies in the scope and configuration of the proposed expansion.[27]

In May 2009, the company released an extensive environmental impact statement for public comment. It revealed the detailed plans for the proposed construction and its future operation. Among the project's new infrastructure requirements were: a desalination plant at Point Lowly (Port Bonython), a rail link to Pimba, a worker accommodation village between Olympic Dam and Andamooka and a barge landing facility near Port Augusta.[28]

In May 2011, the company released a Supplementary Environmental Impact Statement in response to the 4,197 submissions received during a 14-week public comment period.[29]

On 10 October 2011, state and federal government approvals for the mine expansion were granted.[30]

Seawater desalination at Point Lowly Edit

 
The Point Lowly cuttlefish aggregation may be impacted by Olympic Dam desalination plant brine.

Seawater desalination had been considered by Western Mining Corporation as early as 1997,[31] but at that time it was considered to be neither economically nor environmentally viable. By 2005, Western Mining Corporation had revisited the possibility of seawater desalination from upper Spencer Gulf. A pre-feasibility study was underway at the time of the BHP Billiton takeover, and was completed by the project's new owners.

In order to meet the project's increasing demand for water, the BHP Billiton expansion plan proposed to construct a large-scale reverse osmosis seawater desalination plant at Point Lowly in upper Spencer Gulf. The water would then be pumped over 300 km north to the Olympic Dam mine site and Roxby Downs township. The proposed plant's location remains controversial due to the proximity of the proposed brine discharge to critical breeding habitat for the Giant Australian Cuttlefish, which are sensitive to increases in ocean salinity.[32]

In August 2009, a South Australian parliamentary committee recommended that BHP Billiton investigate alternative locations for the proposed plant after concluding that brine could harm the marine ecology of upper Spencer Gulf.[33]

In 2010 and 2011, three petitions (signed by a total of 910 South Australians) were tabled in the Parliament of South Australia calling for the relocation of the proposed desalination plant, so that it would discharge brine into an oceanic environment rather than into Spencer Gulf.[34]

 
Kevin Buzzacott

In February 2012, Arabana elder Kevin Buzzacott legally challenged the Commonwealth Environment Minister Tony Burke's environmental approval of the Olympic Dam mine expansion. Buzzacott was represented by the Environmental Defenders' Office and appeared in the Federal Court in Adelaide on 3 and 4 April 2012.[35] His case was dismissed on 20 April 2012.[36] An appeal of the judge's decision in 2013 was also unsuccessful.[37]

In July 2012, more than 400 people joined the "Lizard's Revenge" protest at the Olympic Dam site. The anti-nuclear activists, including Buzzacott, protested against the mine expansion and the uranium industry. They say the company and the government have put short-term economic gain ahead of environmental and health concerns. Organiser Nectaria Calan said police harassed protesters, demanding identification and controlling access to and from their campsite.[38]

The original development of the mine also attracted public opposition from Australia's anti-nuclear movement. Hundreds of arrests occurred at and around the mine site during a variety of actions and demonstrations in 1983 and 1984.[39] The protesters alleged that they had been provoked by police and that they had been unfairly represented as the antagonists in various media reports.[40]

In August 2012, BHP Billiton announced that the expansion was being postponed indefinitely pending investigation of a "new and cheaper design".[2] The South Australian Mineral Resources and Energy Minister, Tom Koutsantonis in response to this announcement stated "they will be developed (and) it will bring a great deal of prosperity." However the Premier, Jay Weatherill, warned BHP "given that this is the second time they have disappointed South Australians, there can be no doubt that this community permission will come at a (greater) cost" next time.[41] Eight months later, the service town of Roxby Downs was reportedly "in a slump".[42]

In December 2013, the federal government expressed its support for the revival of the Olympic Dam expansion project. The announcements were made in the wake of news that General Motors Holden would be ceasing its car production operations in South Australia in 2017.[43] Members of South Australia's business community believe that the state's future prosperity should not be dependent on the Olympic Dam expansion proceeding and have expressed the need for Government to support a diversified economy.[44]

In September 2014, environmental approval was received for heap-leaching trials to commence at the mine in an effort to reduce processing costs.[45]

In 2015, the Olympic Dam mine's workforce began a staged contraction in company-wide efforts to reduce operating costs. A review of the workforce was announced in January.[46] Since the review commenced, 50 contractor positions were shed in March and 140 jobs were lost in June. A spokesperson from BHP Billiton told Australian Mining:

"All areas of our business, including labour productivity, are being examined. A review is currently progressing in our operational areas and we expect there will be further workforce reductions".[47]

Operations Edit

 
Monument at the discovery hole of Olympic Dam, RD1
 
Chalcopyrite-rich ore specimen from Olympic Dam

Underground mine Edit

The Olympic Dam mine works an extremely large iron oxide copper gold deposit with estimated reserves of 2.95 billion tonnes of ore grading 1.2% copper, 0.04% uranium, .5 g/t of gold and 6 g/t of silver.[48]

The deposit was originally discovered by Western Mining Corporation in 1975 near Roxby Downs Sheep Station and production officially commenced in 1988. It now belongs to BHP, which acquired WMC Resources in 2005. The mine currently operates by an underground mining method called sublevel open stoping, using modern and highly productive mining equipment. The March 2005 mine production rate is an annualised 9.1 million tonnes making it one of Australia's larger mines. 2005 metal production is thought to be in excess of 220,000 tonnes of copper, 4500 tonnes of uranium oxide, plus gold and silver. The copper and uranium oxide are exported through Port Adelaide. Most of the mine workers live in the nearby towns of Roxby Downs and Andamooka. Regular flights between Adelaide and the Olympic Dam Airport serve the mine project.

 
Yellowcake

Uranium production Edit

The production of uranium at Olympic dam accounts for approximately 25% of the mine's revenue. Since 2013, Olympic Dam has been Australia's largest producer of uranium oxide or 'yellowcake'.[49]

Annual U3O8 production at Olympic Dam
Year Tonnes U3O8
2006-07
3,474
2007-08
4,115
2008-09
3,974
2009-10
2,258
2010-11
4,012
2011-12
3,853
2012-13
4,064
2013-14
3,988
2014-15
3,144
2015-16
4,363
2016-17
3,661

Electricity supply Edit

The Olympic Dam mine is South Australia's single largest consumer of electricity, and is connected (at 275kV) at end of the grid via Port Augusta.[50] In 2009, BHP Billiton defined its typical annual electricity consumption as 870,000 MWh[51] (or 125 MW).[52] In 2015, BHP requested a more reliable grid connection.[53] The 2016 storm and heatwaves disrupted production and caused financial losses,[52][54] and the state started initiatives to increase grid reliability.[52] The mine has ordered 210MW wind power and 110MW solar for 2022.[55]

Water supply Edit

The Olympic Dam mine uses 35 megalitres of Great Artesian Basin water each day, making it the largest industrial user of underground water in the southern hemisphere.[56] Water is pumped along an underground pipeline from two bore fields which are located 110 km and 200 km to the north of the mine.[57] The salty bore water requires desalination before it is used. Contaminated water from mining operations is passed through a series of sealed ponds where it evaporates.[57] 3 megalitres of the 35 megalitres extracted daily is supplied to the township of Roxby Downs. Water usage has increased significantly since the 1990s. In 1995, the Olympic Dam project, including the Roxby Downs township, consumed an average of 14.3 megalitres of water daily.[58]

The high use of artesian water as a result of mine operations threatens areas of high ecological significance. In particular, the pumping of water from the bore fields has been linked to observations of reductions in flow or drying out in nearby mound springs.[59] As mound springs are the only permanent source of water in the arid interior of South Australia a delicate yet intricate ecological balance has been established[60] with prolonged isolation causing the existence of many rare and endemic species.[61]

Air pollution Edit

Airborne pollution emissions from the Olympic Dam processing facility are reported annually to the National Pollution Inventory. Emissions exceeding 500 tonnes per annum as of 2013 are (from largest to smallest): particulate matter (10 um), oxides of nitrogen, sulfur dioxide and carbon monoxide.[62]

Public sector support Edit

 
Paul Heithersay, Olympic Dam Task Force CE

In 2006, the Government of South Australia established the Olympic Dam Task Force to assist BHP Billiton with their mine expansion plans. Paul Heithersay is the task force's Chief Executive and as of 2015 also serves as Deputy Chief Executive for the Department of State Development. Current and former senior public servants who have also worked on the Olympic Dam project as employees of BHP Billiton or Western Mining Corporation include Richard Yeeles and Kym Winter-Dewhirst.

See also Edit

References Edit

  1. ^ http://www.aph.gov.au/parliamentary_business/committees/house_of_representatives_committees?url=jsct/8august2006/subs2/sub34_1.pdf[bare URL PDF]
  2. ^ a b "BHP shelves Olympic Dam as profit falls a third". Australia: ABC News. 22 August 2012.
  3. ^ "The 10 biggest uranium mines in the world – Mining Technology". mining-technology.com. 3 November 2013. Retrieved 14 July 2015.
  4. ^ http://www.unene.ca/essentialcandu/pdf/21%20-%20In-core%20FM.pdf[bare URL PDF]
  5. ^ a b Olympic Dam Expansion 2011 (PDF). BHP Billiton. 2011. pp. 29–31.
  6. ^ Lewis, Chris. "Expansion at Olympic Dam" (PDF). International Atomic Energy Association. Western Mining Corporation. Retrieved 14 August 2015.
  7. ^ "ACCC approves BHP acquisition of WMC". The Sydney Morning Herald. 19 April 2005. Retrieved 7 June 2015.
  8. ^ "WMC rejects new Xstrata takeover bid". Australian Broadcasting Corporation. 23 November 2004. Retrieved 7 June 2015.
  9. ^ "French company eyes Olympic Dam". Australian Broadcasting Corporation. 25 February 2005. Retrieved 7 June 2015.
  10. ^ . minerals.dmitre.sa.gov.au. Archived from the original on 8 June 2015. Retrieved 1 June 2015.
  11. ^ "BHP Olympic Dam expansion project – Projection of future skill requirements". National Institute of Labour Studies. Flinders University. Retrieved 3 August 2015.
  12. ^ "South Australian Museum – Liquid Mining: Olympic Dam in a Test Tube". samuseum.sa.gov.au. Retrieved 3 August 2015.
  13. ^ a b "Ian Wark Research Institute Annual Report 2010" (PDF). University of South Australia. Retrieved 4 August 2015.
  14. ^ "Ian Wark Research Institute Annual Report 2008" (PDF). University of South Australia. Retrieved 4 August 2015.
  15. ^ . Institute for Mineral & Energy Research. University of Adelaide. 2012. Archived from the original on 19 October 2014. Retrieved 9 October 2014.
  16. ^ "Ian Wark Research Institute Annual Report 2009" (PDF). University of South Australia. Retrieved 4 August 2015.
  17. ^ "Ian Wark Research Institute Annual Report 2011" (PDF). University of South Australia. Retrieved 4 August 2015.
  18. ^ (PDF). University of Adelaide. Archived from the original (PDF) on 3 March 2016. Retrieved 4 August 2015.
  19. ^ (PDF). University of Adelaide. Archived from the original (PDF) on 21 March 2015. Retrieved 4 August 2015.
  20. ^ "World Nuclear Association Membership – World Nuclear Association". world-nuclear.org. Retrieved 29 May 2016.
  21. ^ "Mission – World Nuclear Association". world-nuclear.org. Retrieved 29 May 2016.
  22. ^ "Resources | Australia's Uranium Industry | Uranium Forum Members". minerals.org.au. Retrieved 29 May 2016.
  23. ^ "ARPS Conference 2016". Australian Radiation Protection Society. Retrieved 1 September 2016.
  24. ^ "Uranium – Uranium 2016". uranium.ausimm.com.au. Retrieved 1 September 2016.
  25. ^ "A Water Supply for Regional South Australia: Reducing Reliance on the River Murray – Feasibility Assessment Report" (PDF).
  26. ^ $7bn BHP Billiton mine giant to go ahead: Mike Rann[permanent dead link]
  27. ^ Uranium mining and the question of corporate social responsibility
  28. ^ BHP Billiton Environmental Impact Statement released for Olympic Dam expansion PM 1 May 2009
  29. ^ (PDF). bhpbilliton.com. Archived from the original (PDF) on 14 July 2015. Retrieved 10 July 2015.
  30. ^ "Huge Olympic Dam mine expansion wins federal nod". Australia: ABC News. 10 October 2011. Retrieved 10 October 2011.
  31. ^ "ASSESSMENT OF THE ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED EXPANSION OF THE OLYMPIC DAM OPERATIONS AT ROXBY DOWNS" (PDF). Environment Australia. 1 November 1997. Retrieved 17 August 2015.
  32. ^ Schliebs, Mark "Fears remain that safeguards won't save giant cuttlefish" The Australian 2011-10-11.
  33. ^ "Pt Lowly unsuitable for BHP desalination plant". Mining Australia. Retrieved 5 August 2015.
  34. ^ "Tabled Papers and Petitions". Parliament of South Australia. Retrieved 2 August 2015.
  35. ^ "Elder Kevin Buzzacott challenges decision to expand Olympic Dam" The Advertiser (2012-04-03)
  36. ^ Friends of the Earth Adelaide "Legal challenge of federal approval of the Olympic Dam expansion continues" 5 March 2015 at the Wayback Machine Retrieved 2013-11-27.
  37. ^ The Australian "Aboriginal elder loses bid to block $30bn Olympic Dam mine expansion" (2013-10-08)
  38. ^ Sarah Martin (16 July 2012). "Police accused over Olympic Dam protest". The Australian.
  39. ^ "Roxby Downs mine protest winds down". The Canberra Times. 4 September 1983. p. 3. Retrieved 25 July 2015.
  40. ^ "'Inaccurate' reports about Roxby Downs". The Canberra Times. 4 September 1984. p. 10. Retrieved 25 July 2015.
  41. ^ = "BHP Billiton's decision won't be covered by tax hike says SA Premier Jay Weatherill" News.com.au 2012-08-23. =
  42. ^ Kurmelovs, Royce (16 April 2013). "Australia: Is this the beginning of the end for mining boom?". The Foreign Report. Retrieved 7 August 2015.
  43. ^ Maher, Sid & Shanahan, Dennis "Tony Abbott's push for Olympic Dam revival" The Australian, 2013-12-24. Accessed 2013-12-26.
  44. ^ Mather, Joanna "Olympic Dam no SA panacea: business leaders" Australian Financial Review, 2013-12-24.
  45. ^ "Olympic Dam expansion hinges on new heap leach process". Mining Australia. Retrieved 5 August 2015.
  46. ^ "BHP cut jobs at Olympic Dam". Mining Australia. Retrieved 5 August 2015.
  47. ^ "More job cuts likely at Olympic Dam". Mining Australia. Retrieved 5 August 2015.
  48. ^ (PDF). ethesis.helsinki.fi. 2012. Archived from the original (PDF) on 9 April 2011. Retrieved 4 July 2013.
  49. ^ . world-nuclear.org. Archived from the original on 9 November 2014. Retrieved 4 August 2015.
  50. ^ 2012 South Australian Electricity Report. Australian Energy Market Operator. 2012. p. 12.
  51. ^ Olympic Dam Draft Environmental Impact Statement 2009 (PDF). BHP Billiton. 2009. p. 377.
  52. ^ a b c Paul, Sonali (4 August 2017). "BHP presses for cheaper power ahead of Olympic Dam mine expansion". Reuters. Retrieved 11 October 2017.
  53. ^ Network capability
  54. ^ Luke, Griffiths (21 February 2017). "Mining giant BHP reveals it has taken a $137 million hit because of recent power outages at its Olympic Dam operations". The Advertiser (Adelaide).
  55. ^ Parkinson, Giles (13 October 2021). "BHP signs landmark renewable energy deal for huge Olympic Dam mine". RenewEconomy.
  56. ^ . Archived from the original on 13 February 2008. Retrieved 9 April 2015.
  57. ^ a b Pigram, John J. (2007). Australia's Water Resources: From use to management. Collingwood, Victoria: CSIRO Publishing. p. 112. ISBN 9780643094420.
  58. ^ Lewis, Chris. "Expansion at Olympic Dam" (PDF). Western Mining Corporation. Retrieved 17 August 2015.
  59. ^ Mudd, G. (2000). "Mound springs of the Great Artesian Basin in South Australia: a case study from Olympic Dam" (PDF). Environmental Geology. 39 (5): 463–476. doi:10.1007/s002540050452. S2CID 54687235. Retrieved 30 November 2012.
  60. ^ Keane, D, 1997, The Sustainability of Use of Groundwater from the Great Artesian Basin, with Particular Reference to the South-Western Edge of the Basin and Impact on the Mound Springs, Environmental Engineering, RMIT, 76 p.
  61. ^ Kinhill, 1997, Olympic Dam Expansion Project Environmental Impact Statement, Prepared for WMC (Olympic Dam Corporation) Pty Ltd by Kinhill Engineers Pty Ltd, May 1997, 500 p.
  62. ^ "2012/2013 report for BHP BILLITON OLYMPIC DAM CORPORATION PTY LTD, BHP Billiton Olympic Dam – Roxby Downs, SA". National Pollution Inventory. Australian Government. Retrieved 24 February 2015.

External links Edit

  • South Australian History 3 July 2007 at the Wayback Machine
  • Infomine Minesites
  • BHP Billiton
  • Social and Ecological Impact of Water Extraction for a Copper-Uranium Mine
  • Olympic Dam Project on mining-technology.com

olympic, mine, large, poly, metallic, underground, mine, located, south, australia, adelaide, fourth, largest, copper, deposit, largest, known, single, deposit, uranium, world, copper, largest, contributor, total, revenue, accounting, approximately, mine, reve. The Olympic Dam mine is a large poly metallic underground mine located in South Australia 550 km 340 mi NNW of Adelaide It is the fourth largest copper deposit and the largest known single deposit of uranium in the world Copper is the largest contributor to total revenue accounting for approximately 70 of the mine s revenue with the remaining 25 from uranium and around 5 from silver and gold 1 BHP has owned and operated the mine since 2005 The mine was previously owned by Western Mining Corporation Olympic Dam mineClarke and Robinson shafts centre LocationOlympic DamLocation in AustraliaLocationOlympic DamStateSouth AustraliaCountryAustraliaCoordinates30 26 24 S 136 52 23 E 30 44000 S 136 87306 E 30 44000 136 87306ProductionProductscopperuranium oxidegoldsilverTypeUndergroundHistoryDiscovered1975Opened1988OwnerCompanyBHPYear of acquisition2005Since it opened in 1988 an extensive underground mine an integrated metallurgical processing plant and expansive open air tailings storage facilities have been constructed The adjacent Olympic Dam mining centre and the nearby township of Roxby Downs service the mine and accommodate its workforce Daily flights to and from Adelaide are provided via the Olympic Dam Airport BHP planned to expand the mine by establishing a new open cut pit and building extensive supporting infrastructure In 2012 the expansion was postponed indefinitely pending investigation of a new and cheaper design 2 Contents 1 Scale of production 2 History 3 Research sponsorship and partnerships 4 Industry associations 5 Sponsorships 6 Proposed expansion 7 Seawater desalination at Point Lowly 8 Operations 8 1 Underground mine 8 2 Uranium production 8 3 Electricity supply 8 4 Water supply 8 5 Air pollution 8 6 Public sector support 9 See also 10 References 11 External linksScale of production EditAs of 2013 Olympic Dam is the second largest uranium producing mine in the world having produced 4 100 tonnes 4 000 long tons 4 500 short tons of uranium metal in the financial year ending June 2013 The only larger producer is the McArthur River uranium mine in Canada 3 Given the energy density of uranium this quantity is equal to a heating value of 820 TWh equivalent to 705 5 megatonnes of TNT 2 952 PJ at a CANDU typical burnup of 200 MWhthermal kg 4 Other reactor types which require uranium enrichment will recover slightly different amounts of heat from this amount of uranium For comparison to get the same amount of heat energy by burning coal energy density ranging from 24 to 35 MJ kg one would need between 84 34 megatonnes 83 010 000 long tons 92 970 000 short tons and 123 megatonnes 121 000 000 long tons 136 000 000 short tons of coal depending on grade The largest coal mine in the world North Antelope Rochelle Mine in Wyoming produced 85 3 megatonnes 84 000 000 long tons 94 000 000 short tons of coal in 2019 at a grade of 3 800 kilojoules per kilogram 1 600 BTU lb equivalent to roughly 3 24 1011 megajoules 9 0 1010 kWh of heat energy History Edit nbsp Olympic Dam phreatic stage diagram of the volcanogenic uranium deposit In 1979 a joint venture partnership was established between Western Mining Corporation and BP Minerals with the intention of establishing the mine Three years later the Roxby Downs Indenture Ratification Act 1982 was signed creating a legal framework for the development to proceed The first shaft was constructed that year and named the Whenan Shaft after Ted Whenan one of the exploration drillers who discovered the ore body The new municipality of Roxby Downs was also established in 1982 as an intended service centre and community hub for the mine workers and their families In 1983 the mine s first Environmental Impact Statement was approved authorising copper production of up to 150 000 tonnes per annum Over a decade would pass before this production target was achieved In 1987 a decline entrance to the mine was created and the Olympic Dam Special Mining Lease was connected to the South Australian electricity grid The mine was officially opened the following year and the first shipments of copper cathodes and uranium oxide were made Roxby Downs township was officially opened and the town s newspaper the Roxby Downs Sun commenced publication In 1989 the Olympic Dam refinery produced its first gold and silver bars 5 In 1993 Western Mining Corporation bought BP s 49 shareholding and assumed total control of the project 6 Several stages of expansion occurred around this time and production increased In 1986 the mine s target production had been set at 45 000 tonnes of copper per annum In 1992 output reached 66 000 tonnes then 84 000 in 1995 The mine s first major expansion was announced in 1996 with the objective of producing 200 000 tonnes per annum once complete A second Environmental Impact Statement was approved allowing the mine to expand production up to 350 000 tonnes of copper per annum In 1998 the mine poured its 500th bar of gold Two years later the mine produced 200 000 tonnes of copper in a year for the first time Optimisation efforts increased output to 235 000 tonnes per annum in 2002 5 BHP made a successful bid for Western Mining Corporation in March 2005 and the offer was accepted by the Australian Competition amp Consumer Commission in April 7 BHP Billiton was not the only resources company to express interest in the project Xstrata had made prior takeover bids in late 2004 8 and French state run nuclear industrial company Areva had entered into what were rumoured to be partnership discussions with WMC Resources in February 9 After the acquisition BHP began to plan what would become a proposed 30 billion expansion project involving the excavation of a new open cut mine within the existing Special Mining Lease The expansion plan was expected to be a boon to the South Australian economy forecast to generate an estimated 23 000 direct and indirect jobs Major new infrastructure would need to be constructed to facilitate the expansion including a new airport at Olympic Dam a rail link a seawater desalination plant at Point Lowly a barge landing facility near Port Augusta and a worker village near Andamooka The company s access to the Government of South Australia was enhanced by the formation of the Olympic Dam Task Force in 2006 which has since served as a single entry point for the company s interactions with the state 10 BHP also began to develop relationships with scientific and academic institutions with the objective of facilitating relevant technical environmental and policy research Research sponsorship and partnerships EditAcademic research related to the Olympic Dam mine and funded by BHP Billiton has been undertaken by at least four major South Australian institutions since the take over Works have included producing a projection of future skill requirements for Olympic Dam by Flinders University 11 research into novel liquid mining techniques conducted by a team at the South Australian Museum 12 numerous studies at the Environment Institute and Institute for Mineral and Energy Resources IMER at the University of Adelaide and numerous more at the Ian Wark Research Institute at the University of South Australia 13 In 2008 the Ian Wark Research Institute entered a research partnership with BHP The company committed to provide 500 000 per annum for five consecutive years for research programs The institute s annual report that year referred to BHP Billiton as having had a representative on their advisory board for many years 14 In 2012 the Institute for Mineral and Energy Resources at the University of Adelaide was awarded over 2 5 million as part of the Australian Research Council s Industrial Transformation Program Funds were to be spent over six years during the establishment of a research hub for advancing copper uranium production BHP Billiton partnered with IMER on the project and is providing 2 5 million in cash plus additional in kind contributions 15 BHP executives have also held numerous board memberships within academic institutions since the Olympic Dam take over Andrew Shook general manager of BHP Billiton s Uranium Customer Sector Group held a position on the advisory board of the Ian Wark Research Institute from 2009 to 2011 and Robert Sumner held a position as an adjunct senior research fellow there for the same period 13 16 17 John England the vice president of technology Uranium Customer Sector Group at BHP Billiton was appointed to the advisory board of IMER from its establishment in 2009 until 2014 President of Uranium Dean Dalla Valle also held a position on the IMER advisory board in 2009 to 2010 18 and another on the board of the South Australian Museum from 2011 to 2012 Vice President Sustainability at BHP Billiton Carl Binning has held a position on the Board of the Environment Institute since at least 2011 19 He ceased working for BHP Billiton in 2012 but continues to hold his board position Industry associations EditBHP Olympic Dam is a member of the World Nuclear Association 20 whose mission is to promote a wider understanding of nuclear energy among key international influencers by producing authoritative information developing common industry positions and contributing to the energy debate 21 BHP Billiton is also a full member of the Minerals Council of Australia s Uranium Forum where the interests of the Olympic Dam project are represented 22 Sponsorships EditBHP sponsors a variety of events and organisations Some are directly linked to the company s uranium portfolio which is exclusively represented by the Olympic Dam mine In 2016 BHP Billiton was the major sponsor of the Australian Radiation Protection Society s ARPS 2016 Conference held in Adelaide 23 Tours of the Olympic Dam mine have also been offered to delegates of uranium and mining industry conferences held in South Australia 24 Proposed expansion EditAt the time of the BHP takeover WMC Resources was investigating ways to expand the mine including considering constructing a prospective seawater desalination plant at Port Bonython Point Lowly 25 In 2008 BHP completed a pre feasibility study into the expansion of the mine s operations with the first step of expansion scheduled for completion by late 2013 In December 2008 South Australia s Premier Mike Rann revealed advice from BHP that the project would proceed as an open cut operation 26 While being welcomed at the time by state and federal governments as a major boost to the economy the proposed expansion of mining operations also attracted considerable criticism In 2007 BHP Billiton attracted public attention for delaying the release of its environmental impact statement for the Olympic Dam expansion and for the company s response to inconsistencies in the scope and configuration of the proposed expansion 27 In May 2009 the company released an extensive environmental impact statement for public comment It revealed the detailed plans for the proposed construction and its future operation Among the project s new infrastructure requirements were a desalination plant at Point Lowly Port Bonython a rail link to Pimba a worker accommodation village between Olympic Dam and Andamooka and a barge landing facility near Port Augusta 28 In May 2011 the company released a Supplementary Environmental Impact Statement in response to the 4 197 submissions received during a 14 week public comment period 29 On 10 October 2011 state and federal government approvals for the mine expansion were granted 30 Seawater desalination at Point Lowly Edit nbsp The Point Lowly cuttlefish aggregation may be impacted by Olympic Dam desalination plant brine Seawater desalination had been considered by Western Mining Corporation as early as 1997 31 but at that time it was considered to be neither economically nor environmentally viable By 2005 Western Mining Corporation had revisited the possibility of seawater desalination from upper Spencer Gulf A pre feasibility study was underway at the time of the BHP Billiton takeover and was completed by the project s new owners In order to meet the project s increasing demand for water the BHP Billiton expansion plan proposed to construct a large scale reverse osmosis seawater desalination plant at Point Lowly in upper Spencer Gulf The water would then be pumped over 300 km north to the Olympic Dam mine site and Roxby Downs township The proposed plant s location remains controversial due to the proximity of the proposed brine discharge to critical breeding habitat for the Giant Australian Cuttlefish which are sensitive to increases in ocean salinity 32 In August 2009 a South Australian parliamentary committee recommended that BHP Billiton investigate alternative locations for the proposed plant after concluding that brine could harm the marine ecology of upper Spencer Gulf 33 In 2010 and 2011 three petitions signed by a total of 910 South Australians were tabled in the Parliament of South Australia calling for the relocation of the proposed desalination plant so that it would discharge brine into an oceanic environment rather than into Spencer Gulf 34 nbsp Kevin BuzzacottIn February 2012 Arabana elder Kevin Buzzacott legally challenged the Commonwealth Environment Minister Tony Burke s environmental approval of the Olympic Dam mine expansion Buzzacott was represented by the Environmental Defenders Office and appeared in the Federal Court in Adelaide on 3 and 4 April 2012 35 His case was dismissed on 20 April 2012 36 An appeal of the judge s decision in 2013 was also unsuccessful 37 In July 2012 more than 400 people joined the Lizard s Revenge protest at the Olympic Dam site The anti nuclear activists including Buzzacott protested against the mine expansion and the uranium industry They say the company and the government have put short term economic gain ahead of environmental and health concerns Organiser Nectaria Calan said police harassed protesters demanding identification and controlling access to and from their campsite 38 The original development of the mine also attracted public opposition from Australia s anti nuclear movement Hundreds of arrests occurred at and around the mine site during a variety of actions and demonstrations in 1983 and 1984 39 The protesters alleged that they had been provoked by police and that they had been unfairly represented as the antagonists in various media reports 40 In August 2012 BHP Billiton announced that the expansion was being postponed indefinitely pending investigation of a new and cheaper design 2 The South Australian Mineral Resources and Energy Minister Tom Koutsantonis in response to this announcement stated they will be developed and it will bring a great deal of prosperity However the Premier Jay Weatherill warned BHP given that this is the second time they have disappointed South Australians there can be no doubt that this community permission will come at a greater cost next time 41 Eight months later the service town of Roxby Downs was reportedly in a slump 42 In December 2013 the federal government expressed its support for the revival of the Olympic Dam expansion project The announcements were made in the wake of news that General Motors Holden would be ceasing its car production operations in South Australia in 2017 43 Members of South Australia s business community believe that the state s future prosperity should not be dependent on the Olympic Dam expansion proceeding and have expressed the need for Government to support a diversified economy 44 In September 2014 environmental approval was received for heap leaching trials to commence at the mine in an effort to reduce processing costs 45 In 2015 the Olympic Dam mine s workforce began a staged contraction in company wide efforts to reduce operating costs A review of the workforce was announced in January 46 Since the review commenced 50 contractor positions were shed in March and 140 jobs were lost in June A spokesperson from BHP Billiton told Australian Mining All areas of our business including labour productivity are being examined A review is currently progressing in our operational areas and we expect there will be further workforce reductions 47 Operations Edit nbsp Monument at the discovery hole of Olympic Dam RD1 nbsp Chalcopyrite rich ore specimen from Olympic DamUnderground mine Edit The Olympic Dam mine works an extremely large iron oxide copper gold deposit with estimated reserves of 2 95 billion tonnes of ore grading 1 2 copper 0 04 uranium 5 g t of gold and 6 g t of silver 48 The deposit was originally discovered by Western Mining Corporation in 1975 near Roxby Downs Sheep Station and production officially commenced in 1988 It now belongs to BHP which acquired WMC Resources in 2005 The mine currently operates by an underground mining method called sublevel open stoping using modern and highly productive mining equipment The March 2005 mine production rate is an annualised 9 1 million tonnes making it one of Australia s larger mines 2005 metal production is thought to be in excess of 220 000 tonnes of copper 4500 tonnes of uranium oxide plus gold and silver The copper and uranium oxide are exported through Port Adelaide Most of the mine workers live in the nearby towns of Roxby Downs and Andamooka Regular flights between Adelaide and the Olympic Dam Airport serve the mine project nbsp YellowcakeUranium production Edit The production of uranium at Olympic dam accounts for approximately 25 of the mine s revenue Since 2013 Olympic Dam has been Australia s largest producer of uranium oxide or yellowcake 49 Annual U3O8 production at Olympic Dam Year Tonnes U3O82006 07 3 4742007 08 4 1152008 09 3 9742009 10 2 2582010 11 4 0122011 12 3 8532012 13 4 0642013 14 3 9882014 15 3 1442015 16 4 3632016 17 3 661Electricity supply Edit The Olympic Dam mine is South Australia s single largest consumer of electricity and is connected at 275kV at end of the grid via Port Augusta 50 In 2009 BHP Billiton defined its typical annual electricity consumption as 870 000 MWh 51 or 125 MW 52 In 2015 BHP requested a more reliable grid connection 53 The 2016 storm and heatwaves disrupted production and caused financial losses 52 54 and the state started initiatives to increase grid reliability 52 The mine has ordered 210MW wind power and 110MW solar for 2022 55 Water supply Edit The Olympic Dam mine uses 35 megalitres of Great Artesian Basin water each day making it the largest industrial user of underground water in the southern hemisphere 56 Water is pumped along an underground pipeline from two bore fields which are located 110 km and 200 km to the north of the mine 57 The salty bore water requires desalination before it is used Contaminated water from mining operations is passed through a series of sealed ponds where it evaporates 57 3 megalitres of the 35 megalitres extracted daily is supplied to the township of Roxby Downs Water usage has increased significantly since the 1990s In 1995 the Olympic Dam project including the Roxby Downs township consumed an average of 14 3 megalitres of water daily 58 The high use of artesian water as a result of mine operations threatens areas of high ecological significance In particular the pumping of water from the bore fields has been linked to observations of reductions in flow or drying out in nearby mound springs 59 As mound springs are the only permanent source of water in the arid interior of South Australia a delicate yet intricate ecological balance has been established 60 with prolonged isolation causing the existence of many rare and endemic species 61 Air pollution Edit Airborne pollution emissions from the Olympic Dam processing facility are reported annually to the National Pollution Inventory Emissions exceeding 500 tonnes per annum as of 2013 are from largest to smallest particulate matter 10 um oxides of nitrogen sulfur dioxide and carbon monoxide 62 Public sector support Edit nbsp Paul Heithersay Olympic Dam Task Force CEIn 2006 the Government of South Australia established the Olympic Dam Task Force to assist BHP Billiton with their mine expansion plans Paul Heithersay is the task force s Chief Executive and as of 2015 also serves as Deputy Chief Executive for the Department of State Development Current and former senior public servants who have also worked on the Olympic Dam project as employees of BHP Billiton or Western Mining Corporation include Richard Yeeles and Kym Winter Dewhirst See also Edit nbsp South Australia portalIan Duncan Arvi Parbo Hugh Morgan List of Australian inquiries into uranium mining Uranium mining in Australia Uranium ore depositsReferences Edit http www aph gov au parliamentary business committees house of representatives committees url jsct 8august2006 subs2 sub34 1 pdf bare URL PDF a b BHP shelves Olympic Dam as profit falls a third Australia ABC News 22 August 2012 The 10 biggest uranium mines in the world Mining Technology mining technology com 3 November 2013 Retrieved 14 July 2015 http www unene ca essentialcandu pdf 21 20 20In core 20FM pdf bare URL PDF a b Olympic Dam Expansion 2011 PDF BHP Billiton 2011 pp 29 31 Lewis Chris Expansion at Olympic Dam PDF International Atomic Energy Association Western Mining Corporation Retrieved 14 August 2015 ACCC approves BHP acquisition of WMC The Sydney Morning Herald 19 April 2005 Retrieved 7 June 2015 WMC rejects new Xstrata takeover bid Australian Broadcasting Corporation 23 November 2004 Retrieved 7 June 2015 French company eyes Olympic Dam Australian Broadcasting Corporation 25 February 2005 Retrieved 7 June 2015 Minerals Olympic Dam Task Force minerals dmitre sa gov au Archived from the original on 8 June 2015 Retrieved 1 June 2015 BHP Olympic Dam expansion project Projection of future skill requirements National Institute of Labour Studies Flinders University Retrieved 3 August 2015 South Australian Museum Liquid Mining Olympic Dam in a Test Tube samuseum sa gov au Retrieved 3 August 2015 a b Ian Wark Research Institute Annual Report 2010 PDF University of South Australia Retrieved 4 August 2015 Ian Wark Research Institute Annual Report 2008 PDF University of South Australia Retrieved 4 August 2015 Industrial transformation research hub for IMER Institute for Mineral amp Energy Research University of Adelaide 2012 Archived from the original on 19 October 2014 Retrieved 9 October 2014 Ian Wark Research Institute Annual Report 2009 PDF University of South Australia Retrieved 4 August 2015 Ian Wark Research Institute Annual Report 2011 PDF University of South Australia Retrieved 4 August 2015 Institute for Mineral and Energy Resources Inaugural Report 2009 2010 PDF University of Adelaide Archived from the original PDF on 3 March 2016 Retrieved 4 August 2015 Environment Institute Annual Report 2011 PDF University of Adelaide Archived from the original PDF on 21 March 2015 Retrieved 4 August 2015 World Nuclear Association Membership World Nuclear Association world nuclear org Retrieved 29 May 2016 Mission World Nuclear Association world nuclear org Retrieved 29 May 2016 Resources Australia s Uranium Industry Uranium Forum Members minerals org au Retrieved 29 May 2016 ARPS Conference 2016 Australian Radiation Protection Society Retrieved 1 September 2016 Uranium Uranium 2016 uranium ausimm com au Retrieved 1 September 2016 A Water Supply for Regional South Australia Reducing Reliance on the River Murray Feasibility Assessment Report PDF 7bn BHP Billiton mine giant to go ahead Mike Rann permanent dead link Uranium mining and the question of corporate social responsibility BHP Billiton Environmental Impact Statement released for Olympic Dam expansion PM 1 May 2009 404 Not Found PDF bhpbilliton com Archived from the original PDF on 14 July 2015 Retrieved 10 July 2015 Huge Olympic Dam mine expansion wins federal nod Australia ABC News 10 October 2011 Retrieved 10 October 2011 ASSESSMENT OF THE ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED EXPANSION OF THE OLYMPIC DAM OPERATIONS AT ROXBY DOWNS PDF Environment Australia 1 November 1997 Retrieved 17 August 2015 Schliebs Mark Fears remain that safeguards won t save giant cuttlefish The Australian 2011 10 11 Pt Lowly unsuitable for BHP desalination plant Mining Australia Retrieved 5 August 2015 Tabled Papers and Petitions Parliament of South Australia Retrieved 2 August 2015 Elder Kevin Buzzacott challenges decision to expand Olympic Dam The Advertiser 2012 04 03 Friends of the Earth Adelaide Legal challenge of federal approval of the Olympic Dam expansion continues Archived 5 March 2015 at the Wayback Machine Retrieved 2013 11 27 The Australian Aboriginal elder loses bid to block 30bn Olympic Dam mine expansion 2013 10 08 Sarah Martin 16 July 2012 Police accused over Olympic Dam protest The Australian Roxby Downs mine protest winds down The Canberra Times 4 September 1983 p 3 Retrieved 25 July 2015 Inaccurate reports about Roxby Downs The Canberra Times 4 September 1984 p 10 Retrieved 25 July 2015 BHP Billiton s decision won t be covered by tax hike says SA Premier Jay Weatherill News com au 2012 08 23 Kurmelovs Royce 16 April 2013 Australia Is this the beginning of the end for mining boom The Foreign Report Retrieved 7 August 2015 Maher Sid amp Shanahan Dennis Tony Abbott s push for Olympic Dam revival The Australian 2013 12 24 Accessed 2013 12 26 Mather Joanna Olympic Dam no SA panacea business leaders Australian Financial Review 2013 12 24 Olympic Dam expansion hinges on new heap leach process Mining Australia Retrieved 5 August 2015 BHP cut jobs at Olympic Dam Mining Australia Retrieved 5 August 2015 More job cuts likely at Olympic Dam Mining Australia Retrieved 5 August 2015 Iron oxide deposits in the world PDF ethesis helsinki fi 2012 Archived from the original PDF on 9 April 2011 Retrieved 4 July 2013 Australia s Uranium Mines world nuclear org Archived from the original on 9 November 2014 Retrieved 4 August 2015 2012 South Australian Electricity Report Australian Energy Market Operator 2012 p 12 Olympic Dam Draft Environmental Impact Statement 2009 PDF BHP Billiton 2009 p 377 a b c Paul Sonali 4 August 2017 BHP presses for cheaper power ahead of Olympic Dam mine expansion Reuters Retrieved 11 October 2017 Network capability Luke Griffiths 21 February 2017 Mining giant BHP reveals it has taken a 137 million hit because of recent power outages at its Olympic Dam operations The Advertiser Adelaide Parkinson Giles 13 October 2021 BHP signs landmark renewable energy deal for huge Olympic Dam mine RenewEconomy Indigenous nuclear campaigner wins national environment award Archived from the original on 13 February 2008 Retrieved 9 April 2015 a b Pigram John J 2007 Australia s Water Resources From use to management Collingwood Victoria CSIRO Publishing p 112 ISBN 9780643094420 Lewis Chris Expansion at Olympic Dam PDF Western Mining Corporation Retrieved 17 August 2015 Mudd G 2000 Mound springs of the Great Artesian Basin in South Australia a case study from Olympic Dam PDF Environmental Geology 39 5 463 476 doi 10 1007 s002540050452 S2CID 54687235 Retrieved 30 November 2012 Keane D 1997 The Sustainability of Use of Groundwater from the Great Artesian Basin with Particular Reference to the South Western Edge of the Basin and Impact on the Mound Springs Environmental Engineering RMIT 76 p Kinhill 1997 Olympic Dam Expansion Project Environmental Impact Statement Prepared for WMC Olympic Dam Corporation Pty Ltd by Kinhill Engineers Pty Ltd May 1997 500 p 2012 2013 report for BHP BILLITON OLYMPIC DAM CORPORATION PTY LTD BHP Billiton Olympic Dam Roxby Downs SA National Pollution Inventory Australian Government Retrieved 24 February 2015 External links EditSouth Australian History Archived 3 July 2007 at the Wayback Machine Infomine Minesites BHP Billiton Social and Ecological Impact of Water Extraction for a Copper Uranium Mine Olympic Dam Project on mining technology com Retrieved from https en wikipedia org w index php title Olympic Dam mine amp oldid 1157164357, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.