Kandadji Dam

The Kandadji Dam, is a large multipurpose dam under construction on the Niger River. The site is situated near the small town of Kandadji, Tillabéri Department, Tillabéri Region, Niger, 180 km northwest of the capital Niamey.[2] It is being built by the Haut Commissariat à l'Aménagement de la Vallée du Niger (High Commission for Niger Valley), a public body under the Primer Minister's Office.

Kandadji Dam
Location of Kandadji Dam in Niger
LocationTillabéri Department, Niger
Coordinates14°36′32″N 0°59′14″E / 14.6089°N 0.9872°E / 14.6089; 0.9872
Construction beganMarch 2019
Opening date2025 (est.)
Construction cost€1.2 billion
Operator(s)Haut Commissariat à l'Aménagement de la Vallée du Niger (High Commission for Niger Valley)
Dam and spillways
ImpoundsNiger River
Height28 m (92 ft)[1]
Length8,780 metres (9,600 yd)[1]
Spillway capacity3,150 m3 (111,000 cu ft)[1]
Reservoir
Total capacity1,596,000 megalitres (1,294,000 acre⋅ft)[1]
Surface area282 km2 (109 sq mi)[1]
Maximum water depth5.67 m (18.6 ft)[1]
Power Station
Commission date2025 (est.)
Turbines4
Installed capacity130 MW (170,000 hp)

The dam will generate hydropower and is control the flow of the Niger River, holding water during the dry season to maintain a minimum flow and making downstream irrigation possible. The project is formally named the Kandadji Programme for Ecosystem Regeneration and Niger River Development (Programme Kandadji de Régénération des Ecosystèmes et de Mise en Valeur du Fleuve Niger).

History edit

The project was first proposed in the 1970s, when a larger dam had been considered. In 1998 the African Development Bank approved funding for a feasibility study that was conducted by the German consulting firm Lahmeyer. Under the study, an environmental and social diagnosis and an initial environmental and social assessment were conducted. The findings were presented in 2002. In August 2002 the government decided by Decree to go ahead with the project, which was from that time called the Kandadji Ecosystems Regeneration and Niger Valley Development Programme. Subsequently, a detailed assessment of environmental and social impact, including a Population Resettlement Plan and a Local Development Plan, was conducted. The Local Development Plan was designed to facilitate the economic transition of displaced persons in order to restore their standard of living or even enhance it, beyond mere resettlement. The final design of the dam was prepared with financing from the Islamic Development Bank, and that of a 2,000 hectares (4,900 acres) irrigation project with financing from the West African Development Bank.[3] In 2005 and 2006 consultations were undertaken as part of the environmental and social assessment, which included participants from the World Wide Fund for Nature and International Union for Conservation of Nature.[4] According to one source, construction of the dam was begun in August 2008. In April 2009 a workshop on benefit sharing from dams in West Africa was held in Niamey organized by the Niger Basin Authority, the International Institute for Environment and Development and the International Union for Conservation of Nature. The workshop recommended to improve the communication towards the people affected by the dam and to pay particular attention to legal processes related to resettlement, and to continue to reflect on a future management structure to equitably share the benefits of the dam.[5] In November 2009 a process to select consultants to accompany the resettlement has been initiated.[6]

According to the World Bank, the entire Kandadji Program will be implemented in three phases:

  • Phase I, which started in 2009 and is expected to be completed in 2016, comprises the Kandadji dam and its reservoir, the hydro-mechanical equipment for the 18 gates, economic and local community development, and implementation of environmental and social mitigation measures for resettled people;
  • Phase II comprises construction of the hydropower plant, transmission lines, road, irrigated agricultural development, and expanded local and community development in the reservoir area and downstream, and
  • Phase III focuses on the development of irrigated agriculture and the scaling-up of the economy and local community development of the region (including fisheries, livestock, agribusiness and trade.[7]

Construction of the dam itself was contracted to Russian company Zarubezhvodstroy, which signed the construction contract in September 2010.[8] Construction of the dam was relaunched at a ceremony on 23 May 2011, following the election of President Mahamadou Issoufou.[9][10][11][12] The Kandaji Dam is the first object being constructed by a Russian company in Niger.[13] In May 2011, the Director General of Zarubezhvodstroy, OJSC E.V. Gudzenchuk, announced "For the first time a Russian company is involved in building such a large project in West Africa at the expense of foreign investors. Zarubezhvodstroy has vast experience in the field that would allow us to meet the challenges with confidence and with great professionalism."[13]

Plans were announced in June 2011 to relocate 5383 individuals and 770 families who will be displaced by the dam.[14]

Construction of the dam was begun in August 2008.[15] The first brick of the dam was laid by the President of Niger, Mamadou Tandja.[16] In 2008, the dam itself was expected to be completed in 2013.[16] By 2012, the completion date had moved to September 2015.[17] Construction has been slower than expected, with interruptions due to financing problems; as of 2019, completion is expected in 2025.[18] Construction works were 12% complete as of September 2019.[19]

Technical features edit

The earth dyke dam will be 8.4 km dam long, creating a reservoir of 1.6 billion m3 and a regulated discharge of 120 m3/s (3.8 km3/year) in Niamey. The hydroelectric plant will have a capacity of 130 megawatt, and a 132 kilovolt high voltage line will be built over 188 km to Niamey. Irrigation development will consist of a first phase of 6,000 hectares mainly for the benefit of resettled communities, with a medium-term target in 2034 of 45,000 hectares out of an irrigable potential of 122,000 hectares.[20]

Benefits edit

The project is a very high-profile project for Niger. According to the Prime Minister at the time of initiating construction, Seyni Oumarou, "no other development project will have sparked so much long term interest or such high expectations". The expected benefits include increased agricultural production and hydropower generation. Niger imports almost half of its electricity consumption of 440 million kilowatt-hours (1.6×109 MJ) (2007) from neighboring Nigeria, which itself suffers frequent power cuts. The plant would increase installed capacity in Niger from 240 Megawatt (MW) in 2007 to 370 MW (+55%).[21] Other expected benefits are related to "drinking water supply, sanitation, improved flood recession cropping, grazing and fishery".[22]

Financial costs edit

The financial costs of the broader project, including the infrastructure for irrigation and drinking water supply, were estimated at US$670 million by one source in 2007.[23] Another source mentions US$942 million in 2011.[10] The contract to build the dam itself, however, is apparently only worth Euro 130 million.[8] According to the World Bank, the Kandadji Program (Phase I and Phase II) is expected to cost US$785 million.[7]

Financing edit

Financing comes from ten sources: the African Development Bank, the Islamic Development Bank, the West African Development Bank, the Saudi Fund for Development, the Kuwait Fund for Arab Economic Development, the OPEC Fund for International Development, the Arab Bank for Economic Development in Africa, the Bank for Investment and Development of the Economic Community of West African States (ECOWAS), the French Development Agency (AFD) and the Government of Niger.[8]

Specific amounts are as follows, as far as known:

Financing for the hydropower station itself is due to come from a public-private partnership.[16][24]

Environmental, social and downstream impact edit

Negative social impacts include the resettlement of almost 35,000 people from 15 villages, loss of infrastructure (a national road, boreholes, clinics, schools, mosques, slaughterhouses, markets and grain mills) and loss of about 7,000 ha of agricultural land. According to a 2007 report by UNEP's Dams and Development Project, which itself was a follow-up activity to a report by the World Commission on Dams, the Kandadji project "serves as a useful example of the projection and estimation of social effects, which appears to have been widely encompassing, covering both negative impacts and benefits". These impacts were "projected at an early stage in project planning, enabling issues and potential impacts to be addressed in subsequent planning phases".[28]

The project is expected to improve the river's ecology, which has suffered from a 30% decline in river flows since the 1970s.[29] The dam would regulate flows. According to press reports from Nigeria, the project would reduce the river flow to Nigeria by at least 10 percent, thus jeopardizing power production from two existing dams in Nigeria and meaning a "colossal loss (...) to the agricultural capacity of (Nigerian) states that border the River Niger".[30] However, according to the 2008 environmental assessment of the project, the "modifications of the quantities of water flowing into the Niger River as a result of the Kandadji dam will be minimal in Nigeria". The average loss through evaporation and modification of the Niger River water flows in Nigeria will be low (2.3% at Jebba) and there will be positive impacts by improving the minimum water level in Nigeria.[31]

Developments edit

In August 2023 Afrik21.africa reported that China Gezhouba Group Company (CGGC), the then engineering, procurement and construction (EPC) contractor had suspend construction work on the project, following the 2023 Nigerien coup d'état. The resultant economic sanctions imposed by the European Union, the World Bank and ECOWAS made it impossible for CGGC to pay its subcontractors and its workers. Construction may resume if and when those sanctions are lifted.[32]

See also edit

References edit

  1. ^ a b c d e f "Programme Kandadji de Régénération des Écosystèmes et de Mise en valeur de la vallée du Niger. Detailed Environmental and Social Impact Assessment" (PDF). Tecsult Limited. November 2006. p. 5. Retrieved 29 April 2013.
  2. ^ Kandadji, Niger Page[permanent dead link]. Falling Rain.com. Retrieved 2009-02-01
  3. ^ Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED POPULATION RESETTLEMENT PLAN, EXECUTIVE SUMMARY, February 2008, p. 1-2
  4. ^ Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT, EXECUTIVE SUMMARY, January 2008, p. 12
  5. ^ IUCN:Les acteurs échangent sur le partage des bénéfices et la gestion des réservoirs, 6 May 2009
  6. ^ Niger seeks relocation consultants for 125-MW Kandadji, 20 November 2009
  7. ^ a b c "The Kandadji Program in the Sahel" (PDF). World Bank. Retrieved 29 April 2013.
  8. ^ a b c "News". Zarubezhvodstroy. 23 May 2011. Retrieved 29 April 2013.
  9. ^ Le président du Niger lance la construction d’un barrage hydro-électrique. PANA Press, 2011-05-24
  10. ^ a b Russian firm starts work on Niger hydro dam. Abdoulaye Massalatchi Reuters – Tue, May 24, 2011
  11. ^ Présentation du Barrage de Kandadji
  12. ^ "Africa Intelligence: exclusive news on Africa". Africa Intelligence. Retrieved 2022-01-06.
  13. ^ a b "Kandaji Dam: History". Zarubezhvodstroy» OJSC. Retrieved July 18, 2012.
  14. ^ Les riverains du barrage de Kandadji seront déplacés et indemnisés - Afriquinfos
  15. ^ Niger / AfD Bank Group President receives Niger’s Finance and Economy Minister. African Press Organization (APO). October 10, 2008/
  16. ^ a b c ReutersAlertNet:Niger begins building dam for food, electricity, 4 August 2008
  17. ^ "Niger Criticizes Russian Company Over Delays on Hydropower Dam". Bloomberg. 2 March 2012. Retrieved 29 April 2013.
  18. ^ "Niger : nouveau coup de pouce de la BAD pour la construction d'un barrage à Kandadji". La Tribune (in French). 24 May 2019. Retrieved 2020-04-12.
  19. ^ "Niger : les travaux du barrage de Kandadji confiés à une entreprise chinoise évoluent à la grande satisfaction des autorités - Xinhua | Actualités Chine & Afrique". french.xinhuanet.com. Retrieved 2020-04-12.
  20. ^ Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED POPULATION RESETTLEMENT PLAN, EXECUTIVE SUMMARY, February 2008, p. 3-4
  21. ^ U.S. Energy Information Administration:http://tonto.eia.doe.gov/country/country_energy_data.cfm?fips=NG Niger Energy Profile, accessed on January 10, 2009
  22. ^ a b AfricanManager:Saudi Fund grants US$20 million to Niger for Kandadji dam, 9 January 2010
  23. ^ Reuters:Niger says secures $236 mln Islamic funding for dam, 3 December 2007
  24. ^ a b "African bank funds Niger's 125-MW Kandadji Dam, ecosystems". HydroWorld.com. Retrieved July 19, 2012.
  25. ^ OFID:Commitments in 2008, accessed on January 9, 2010
  26. ^ African Development Bank:Niger: US$62 Million ADF Funding for the development of Niger Valley Ecosystems, 31 October 2008
  27. ^ AFD. "Equipping the Kandadji Dam Hydropower Plant". AFD. Retrieved 15 June 2022.
  28. ^ UNEP:DAMS AND DEVELOPMENT PROJECT, COMPENDIUM ON RELEVANT PRACTICES, Social Impact Assessment of Affected People, Final Report, August 2007, p. x, accessed on January 10, 2009
  29. ^ Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED POPULATION RESETTLEMENT PLAN, EXECUTIVE SUMMARY, February 2008, p. 2
  30. ^ BusinessdayOnline:New dam on River Niger: Why it is crucial Nigeria responds, 8 January 2009, by Martin Ayankola
  31. ^ Republic of Niger, Prime Minister’s Office, High Commission for Niger Valley / African Development Bank:"KANDADJI" ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME (KERNVDP), DETAILED ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT, EXECUTIVE SUMMARY, January 2008, p. 11
  32. ^ Jean Marie Takouleu (18 August 2023). "Niger: Following the coup, CGGC suspends construction of the Kandadji dam". Paris, France. Retrieved 20 August 2023.

Further sources edit

  • Multi-purpose Projects: Kandadji Dam Niger. Lahmeyer International (2008). (Link broken)
  • Assessment of the environmental impacts of the Kandadji dam project: an energy choice identified under the National Energy and Sustainable Development Program. Hassane Kimba / Nigerian Association of Environmental Impact Assessment Professionals. AJEAM-RAGEE Volume 5 April 2003; 46-54 (Link broken)
  • Haut Commissariat au Barrage de Kandadji (official site)[permanent dead link]. Republique du Niger: Cabinet du Premier Ministre. Retrieved 2009-02-01. (Link broken)
  • Niger - Evaluation de l'effet du barrage de Kandadji sur les pêcheries du fleuve Niger. Un rapport préparé pour le projet assistance a l'Autorité du Barrage de Kandadji (ABK); Document de travail 1. (French) Welcomme, R.L., / FAO, Rome (Italy). Fisheries Dept., 1981, 7 p. Report No: FAO-FI—TCP/NER/0103(MA)
  • Jamie Skinner:Niger: Tough questions posed by the Kandadji dam development, International Institute for Environment and Development, 19 April 2013

kandadji, large, multipurpose, under, construction, niger, river, site, situated, near, small, town, kandadji, tillabéri, department, tillabéri, region, niger, northwest, capital, niamey, being, built, haut, commissariat, aménagement, vallée, niger, high, comm. The Kandadji Dam is a large multipurpose dam under construction on the Niger River The site is situated near the small town of Kandadji Tillaberi Department Tillaberi Region Niger 180 km northwest of the capital Niamey 2 It is being built by the Haut Commissariat a l Amenagement de la Vallee du Niger High Commission for Niger Valley a public body under the Primer Minister s Office Kandadji DamLocation of Kandadji Dam in NigerLocationTillaberi Department NigerCoordinates14 36 32 N 0 59 14 E 14 6089 N 0 9872 E 14 6089 0 9872Construction beganMarch 2019Opening date2025 est Construction cost 1 2 billionOperator s Haut Commissariat a l Amenagement de la Vallee du Niger High Commission for Niger Valley Dam and spillwaysImpoundsNiger RiverHeight28 m 92 ft 1 Length8 780 metres 9 600 yd 1 Spillway capacity3 150 m3 111 000 cu ft 1 ReservoirTotal capacity1 596 000 megalitres 1 294 000 acre ft 1 Surface area282 km2 109 sq mi 1 Maximum water depth5 67 m 18 6 ft 1 Power StationCommission date2025 est Turbines4Installed capacity130 MW 170 000 hp The dam will generate hydropower and is control the flow of the Niger River holding water during the dry season to maintain a minimum flow and making downstream irrigation possible The project is formally named the Kandadji Programme for Ecosystem Regeneration and Niger River Development Programme Kandadji de Regeneration des Ecosystemes et de Mise en Valeur du Fleuve Niger Contents 1 History 2 Technical features 3 Benefits 4 Financial costs 5 Financing 6 Environmental social and downstream impact 7 Developments 8 See also 9 References 10 Further sourcesHistory editThe project was first proposed in the 1970s when a larger dam had been considered In 1998 the African Development Bank approved funding for a feasibility study that was conducted by the German consulting firm Lahmeyer Under the study an environmental and social diagnosis and an initial environmental and social assessment were conducted The findings were presented in 2002 In August 2002 the government decided by Decree to go ahead with the project which was from that time called the Kandadji Ecosystems Regeneration and Niger Valley Development Programme Subsequently a detailed assessment of environmental and social impact including a Population Resettlement Plan and a Local Development Plan was conducted The Local Development Plan was designed to facilitate the economic transition of displaced persons in order to restore their standard of living or even enhance it beyond mere resettlement The final design of the dam was prepared with financing from the Islamic Development Bank and that of a 2 000 hectares 4 900 acres irrigation project with financing from the West African Development Bank 3 In 2005 and 2006 consultations were undertaken as part of the environmental and social assessment which included participants from the World Wide Fund for Nature and International Union for Conservation of Nature 4 According to one source construction of the dam was begun in August 2008 In April 2009 a workshop on benefit sharing from dams in West Africa was held in Niamey organized by the Niger Basin Authority the International Institute for Environment and Development and the International Union for Conservation of Nature The workshop recommended to improve the communication towards the people affected by the dam and to pay particular attention to legal processes related to resettlement and to continue to reflect on a future management structure to equitably share the benefits of the dam 5 In November 2009 a process to select consultants to accompany the resettlement has been initiated 6 According to the World Bank the entire Kandadji Program will be implemented in three phases Phase I which started in 2009 and is expected to be completed in 2016 comprises the Kandadji dam and its reservoir the hydro mechanical equipment for the 18 gates economic and local community development and implementation of environmental and social mitigation measures for resettled people Phase II comprises construction of the hydropower plant transmission lines road irrigated agricultural development and expanded local and community development in the reservoir area and downstream and Phase III focuses on the development of irrigated agriculture and the scaling up of the economy and local community development of the region including fisheries livestock agribusiness and trade 7 Construction of the dam itself was contracted to Russian company Zarubezhvodstroy which signed the construction contract in September 2010 8 Construction of the dam was relaunched at a ceremony on 23 May 2011 following the election of President Mahamadou Issoufou 9 10 11 12 The Kandaji Dam is the first object being constructed by a Russian company in Niger 13 In May 2011 the Director General of Zarubezhvodstroy OJSC E V Gudzenchuk announced For the first time a Russian company is involved in building such a large project in West Africa at the expense of foreign investors Zarubezhvodstroy has vast experience in the field that would allow us to meet the challenges with confidence and with great professionalism 13 Plans were announced in June 2011 to relocate 5383 individuals and 770 families who will be displaced by the dam 14 Construction of the dam was begun in August 2008 15 The first brick of the dam was laid by the President of Niger Mamadou Tandja 16 In 2008 the dam itself was expected to be completed in 2013 16 By 2012 the completion date had moved to September 2015 17 Construction has been slower than expected with interruptions due to financing problems as of 2019 completion is expected in 2025 18 Construction works were 12 complete as of September 2019 19 Technical features editThe earth dyke dam will be 8 4 km dam long creating a reservoir of 1 6 billion m3 and a regulated discharge of 120 m3 s 3 8 km3 year in Niamey The hydroelectric plant will have a capacity of 130 megawatt and a 132 kilovolt high voltage line will be built over 188 km to Niamey Irrigation development will consist of a first phase of 6 000 hectares mainly for the benefit of resettled communities with a medium term target in 2034 of 45 000 hectares out of an irrigable potential of 122 000 hectares 20 Benefits editThe project is a very high profile project for Niger According to the Prime Minister at the time of initiating construction Seyni Oumarou no other development project will have sparked so much long term interest or such high expectations The expected benefits include increased agricultural production and hydropower generation Niger imports almost half of its electricity consumption of 440 million kilowatt hours 1 6 109 MJ 2007 from neighboring Nigeria which itself suffers frequent power cuts The plant would increase installed capacity in Niger from 240 Megawatt MW in 2007 to 370 MW 55 21 Other expected benefits are related to drinking water supply sanitation improved flood recession cropping grazing and fishery 22 Financial costs editThe financial costs of the broader project including the infrastructure for irrigation and drinking water supply were estimated at US 670 million by one source in 2007 23 Another source mentions US 942 million in 2011 10 The contract to build the dam itself however is apparently only worth Euro 130 million 8 According to the World Bank the Kandadji Program Phase I and Phase II is expected to cost US 785 million 7 Financing editFinancing comes from ten sources the African Development Bank the Islamic Development Bank the West African Development Bank the Saudi Fund for Development the Kuwait Fund for Arab Economic Development the OPEC Fund for International Development the Arab Bank for Economic Development in Africa the Bank for Investment and Development of the Economic Community of West African States ECOWAS the French Development Agency AFD and the Government of Niger 8 Specific amounts are as follows as far as known US 236 million was pledged by the Islamic Development Bank 24 US 15 million was pledged by the OPEC Fund for International Development in February 2009 25 US 62 million were approved in October 2008 by the African Development Bank through a combined loan and grant 26 US 20 million were approved in January 2010 by the Saudi Development Fund 22 US 200 million from the World Bank 7 EUR50 million from the French Development Agency 27 Financing for the hydropower station itself is due to come from a public private partnership 16 24 Environmental social and downstream impact editNegative social impacts include the resettlement of almost 35 000 people from 15 villages loss of infrastructure a national road boreholes clinics schools mosques slaughterhouses markets and grain mills and loss of about 7 000 ha of agricultural land According to a 2007 report by UNEP s Dams and Development Project which itself was a follow up activity to a report by the World Commission on Dams the Kandadji project serves as a useful example of the projection and estimation of social effects which appears to have been widely encompassing covering both negative impacts and benefits These impacts were projected at an early stage in project planning enabling issues and potential impacts to be addressed in subsequent planning phases 28 The project is expected to improve the river s ecology which has suffered from a 30 decline in river flows since the 1970s 29 The dam would regulate flows According to press reports from Nigeria the project would reduce the river flow to Nigeria by at least 10 percent thus jeopardizing power production from two existing dams in Nigeria and meaning a colossal loss to the agricultural capacity of Nigerian states that border the River Niger 30 However according to the 2008 environmental assessment of the project the modifications of the quantities of water flowing into the Niger River as a result of the Kandadji dam will be minimal in Nigeria The average loss through evaporation and modification of the Niger River water flows in Nigeria will be low 2 3 at Jebba and there will be positive impacts by improving the minimum water level in Nigeria 31 Developments editIn August 2023 Afrik21 africa reported that China Gezhouba Group Company CGGC the then engineering procurement and construction EPC contractor had suspend construction work on the project following the 2023 Nigerien coup d etat The resultant economic sanctions imposed by the European Union the World Bank and ECOWAS made it impossible for CGGC to pay its subcontractors and its workers Construction may resume if and when those sanctions are lifted 32 See also editKenie Hydroelectric Power StationReferences edit a b c d e f Programme Kandadji de Regeneration des Ecosystemes et de Mise en valeur de la vallee du Niger Detailed Environmental and Social Impact Assessment PDF Tecsult Limited November 2006 p 5 Retrieved 29 April 2013 Kandadji Niger Page permanent dead link Falling Rain com Retrieved 2009 02 01 Republic of Niger Prime Minister s Office High Commission for Niger Valley African Development Bank KANDADJI ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME KERNVDP DETAILED POPULATION RESETTLEMENT PLAN EXECUTIVE SUMMARY February 2008 p 1 2 Republic of Niger Prime Minister s Office High Commission for Niger Valley African Development Bank KANDADJI ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME KERNVDP DETAILED ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT EXECUTIVE SUMMARY January 2008 p 12 IUCN Les acteurs echangent sur le partage des benefices et la gestion des reservoirs 6 May 2009 Niger seeks relocation consultants for 125 MW Kandadji 20 November 2009 a b c The Kandadji Program in the Sahel PDF World Bank Retrieved 29 April 2013 a b c News Zarubezhvodstroy 23 May 2011 Retrieved 29 April 2013 Le president du Niger lance la construction d un barrage hydro electrique PANA Press 2011 05 24 a b Russian firm starts work on Niger hydro dam Abdoulaye Massalatchi Reuters Tue May 24 2011 Presentation du Barrage de Kandadji Africa Intelligence exclusive news on Africa Africa Intelligence Retrieved 2022 01 06 a b Kandaji Dam History Zarubezhvodstroy OJSC Retrieved July 18 2012 Les riverains du barrage de Kandadji seront deplaces et indemnises Afriquinfos Niger AfD Bank Group President receives Niger s Finance and Economy Minister African Press Organization APO October 10 2008 a b c ReutersAlertNet Niger begins building dam for food electricity 4 August 2008 Niger Criticizes Russian Company Over Delays on Hydropower Dam Bloomberg 2 March 2012 Retrieved 29 April 2013 Niger nouveau coup de pouce de la BAD pour la construction d un barrage a Kandadji La Tribune in French 24 May 2019 Retrieved 2020 04 12 Niger les travaux du barrage de Kandadji confies a une entreprise chinoise evoluent a la grande satisfaction des autorites Xinhua Actualites Chine amp Afrique french xinhuanet com Retrieved 2020 04 12 Republic of Niger Prime Minister s Office High Commission for Niger Valley African Development Bank KANDADJI ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME KERNVDP DETAILED POPULATION RESETTLEMENT PLAN EXECUTIVE SUMMARY February 2008 p 3 4 U S Energy Information Administration http tonto eia doe gov country country energy data cfm fips NG Niger Energy Profile accessed on January 10 2009 a b AfricanManager Saudi Fund grants US 20 million to Niger for Kandadji dam 9 January 2010 Reuters Niger says secures 236 mln Islamic funding for dam 3 December 2007 a b African bank funds Niger s 125 MW Kandadji Dam ecosystems HydroWorld com Retrieved July 19 2012 OFID Commitments in 2008 accessed on January 9 2010 African Development Bank Niger US 62 Million ADF Funding for the development of Niger Valley Ecosystems 31 October 2008 AFD Equipping the Kandadji Dam Hydropower Plant AFD Retrieved 15 June 2022 UNEP DAMS AND DEVELOPMENT PROJECT COMPENDIUM ON RELEVANT PRACTICES Social Impact Assessment of Affected People Final Report August 2007 p x accessed on January 10 2009 Republic of Niger Prime Minister s Office High Commission for Niger Valley African Development Bank KANDADJI ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME KERNVDP DETAILED POPULATION RESETTLEMENT PLAN EXECUTIVE SUMMARY February 2008 p 2 BusinessdayOnline New dam on River Niger Why it is crucial Nigeria responds 8 January 2009 by Martin Ayankola Republic of Niger Prime Minister s Office High Commission for Niger Valley African Development Bank KANDADJI ECOSYSTEMS REGENERATION AND NIGER VALLEY DEVELOPMENT PROGRAMME KERNVDP DETAILED ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT EXECUTIVE SUMMARY January 2008 p 11 Jean Marie Takouleu 18 August 2023 Niger Following the coup CGGC suspends construction of the Kandadji dam Paris France Retrieved 20 August 2023 Further sources editMulti purpose Projects Kandadji Dam Niger Lahmeyer International 2008 Link broken Assessment of the environmental impacts of the Kandadji dam project an energy choice identified under the National Energy and Sustainable Development Program Hassane Kimba Nigerian Association of Environmental Impact Assessment Professionals AJEAM RAGEE Volume 5 April 2003 46 54 Link broken Haut Commissariat au Barrage de Kandadji official site permanent dead link Republique du Niger Cabinet du Premier Ministre Retrieved 2009 02 01 Link broken Niger Evaluation de l effet du barrage de Kandadji sur les pecheries du fleuve Niger Un rapport prepare pour le projet assistance a l Autorite du Barrage de Kandadji ABK Document de travail 1 French Welcomme R L FAO Rome Italy Fisheries Dept 1981 7 p Report No FAO FI TCP NER 0103 MA Jamie Skinner Niger Tough questions posed by the Kandadji dam development International Institute for Environment and Development 19 April 2013 nbsp Water portal nbsp Renewable energy portal Retrieved from https en wikipedia org w index php title Kandadji Dam amp oldid 1185601030, wikipedia, wiki, book, books, library,