fbpx
Wikipedia

Kolkata Metro Line 4

The Kolkata Metro Line 4 or the Yellow Line, also known as the Noapara - Barasat Line of the Kolkata Metro in India is a 16.876 km (10.486 mi)[1] long metro route from Noapara to Barasat in North 24 Parganas, which is under construction. It is being built by RVNL, Senbo & ITD.[3] It will run mostly underground viaducts. The track will be elevated until Jessore Road Station and then go underground towards Barasat metro station. It will have an interchange station at the NSCBI Airport with Kolkata Metro Line 6.

Kolkata Metro Line 4

Noapara - Barasat
Under construction elevated railway of Kolkata Metro Line 4 or Yellow Line near Bagjola canal
Overview
StatusUnder construction
OwnerMetro Railway, Kolkata
Locale Kolkata Metropolitan Area, India
Termini
Connecting linesBlue Line Orange Line
Stations10
Service
TypeRapid transit
SystemKolkata Metro
Operator(s)Metro Railway, Kolkata
Depot(s)Noapara Depot
Airport Depot
Barasat Depot
Technical
Line length18.13 kilometres (11.27 mi)

6.87 kilometres (4.27 mi) (Under Construction)

11.26 kilometres (7.00 mi) (Planned))[1]
Number of tracks2
Track gauge5 ft 6 in (1,676 mm) broad gauge
Electrification750 V DC[2] using third rail
Operating speed80 km/h (designed)
Route map

(Click to expand)

Stations edit

The stations of this corridor are:

Line 4 (Yellow Line)
No. Station Name Location Phase Opening Connections Layout Coordinates Notes
English Bengali
1 Noapara নোয়াপাড়া Noapara 1 10 July 2013
  •   (operational)
    •   34C Bus Stand
    •   Health Care More Bus Stop
    •   Gharui Paschimpara Bus Stop
Elevated
2 Dum Dum Cantonment দমদম ক্যান্টনমেন্ট Dum Dum Cantonment Under Construction
3 Jessore Road যশোর রোড NSCB International Airport (Gate No. 1)
  •   H.M.V. Gate Bus Stop
    •   Airport Gate No. 1 Bus Stop
At grade Previously suburban rail used to operate in this line
4 Jai Hind জয় হিন্দ NSCB International Airport
  •   (under construction)
    •   Airport AC Bus Stand
    •   Airport Gate No. 1 Bus Stop
    •   Airport Gate No. 2 Bus Stop
    •   Airport Gate No. 2.5 Bus Stop
    •   Airport Gate No. 3 Bus Stop
Underground
5 Birati বিরাটি Birati 2
  •   Birati More Bus Stop
  •   Gouripur Bus Stand
6 Michael Nagar মাইকেল নগর Michael Nagar
  •   Bankra Bus Stop
  •   Bankra Madni Nagar Bus Stop
7 New Barrackpore নিউ ব্যারাকপুর New Barrackpore
  •   B.T. College Bus Stand
  •   Sukanta Nagar Bus Stop
8 Madhyamgram মধ্যমগ্রাম Madhyamgram 3 Planned
9 Hridaypur হৃদয়পুর Hridaypur
10 Barasat বারাসাত Barasat

Progress of Dum Dum Cantonment metro station edit

 
Dum Dum Cantonment metro station

An amount of Rs 227 crore contract to build this station along with a mostly at-grade 2.16 km (1.34 mi) section from the Bagjola Canal to the existing ramp of the Airport Circular Railway track was awarded to Senbo Engineering Limited all the way back in June 2011. Since then, the station’s civil structure has been built, but work for the at-grade track section could not be started due to land acquisition issues along the line’s proposed alignment. But the rehabilitation work has completed in 2020, and the work is going smoothly. Recently girders were placed over Eastern Railway tracks. The metro station is set to be operational by 2024.

Project development edit

The project will be completed in three phases. The first phase of work from Noapara to Biman Bandar is under progress. In the second phase work from Biman Bandar to New Barrackpore will be done and in the last phase from New Barrackpore to Barasat work will be done. But the development work from New Barrackpore to Barasat got struck for the last eight years since it was sanctioned because of encroachments[4] and the Airport Authority of India objected the elevated stretches from New Barrackpore to Barasat. Later, after objections from AAI, a decision was taken to convert this into an underground stretch. On 29 June 2019 sanction for material modification for underground construction at an additional cost of 1,615 crore (US$200 million) was sent to Railway Board by Metro. For this underground tunneling AAI has agreed to shift their fuel tanks, buildings and cables and the project is expected to be started from 2020.[5]

Construction of an underground integrated station for Line 6 and line 4 has begun at NSCBI Airport land just 150 metres (492 ft) away from the terminal building.

'The development of New Barrackpore to Barasat was supposed to go elevated to cut down the expenses, but the stretch was in doubt due to huge encroachment problem. But in February 2021, Prime Minister Narendra Modi gave his nod to construct this stretch underground, giving respite to thousands of families who were supposed to be evicted for the development of the elevated stretch.[6] In order to lower the cost of the underground work, latest technology TBM will not be used, instead old technology of cut and cover method will be used for metro.[7]

Line 4 has been divided into three phases now.

  • Phase 1: Noapara - Biman Bandar (under construction)
  • Phase 2: Biman Bandar - New Barrackpore (construction has been started, tender floated by RVNL to carry out construction work)
  • Phase 3: New Barrackpore - Barasat (construction to begin soon)

See also edit

References edit

  1. ^ a b "New System Map of Kolkata Metro".
  2. ^ "CAF to supply Kolkata metro trains".
  3. ^ "Senbo Engg wins ₹532 crore underground civil contracts for Kolkata Metro Line 4 | Metro Rail Today". Metro Rail Today: Gateway to Rail & Metro Industry. Retrieved 12 April 2023.
  4. ^ Gupta, Jayanta (23 July 2019). "Kolkata: Metro to run below surface after airport". The Times of India. Retrieved 25 March 2020.
  5. ^ "Metro to run below surface after airport". Times of India. 26 July 2019.
  6. ^ "PM nod for underground Metro averts eviction". www.telegraphindia.com. Retrieved 14 March 2021.
  7. ^ "Senbo Engg wins ₹532 crore underground civil contracts for Kolkata Metro Line 4 | Metro Rail Today". Metro Rail Today: Gateway to Rail & Metro Industry. Retrieved 12 April 2023.

kolkata, metro, line, yellow, line, also, known, noapara, barasat, line, kolkata, metro, india, long, metro, route, from, noapara, barasat, north, parganas, which, under, construction, being, built, rvnl, senbo, will, mostly, underground, viaducts, track, will. The Kolkata Metro Line 4 or the Yellow Line also known as the Noapara Barasat Line of the Kolkata Metro in India is a 16 876 km 10 486 mi 1 long metro route from Noapara to Barasat in North 24 Parganas which is under construction It is being built by RVNL Senbo amp ITD 3 It will run mostly underground viaducts The track will be elevated until Jessore Road Station and then go underground towards Barasat metro station It will have an interchange station at the NSCBI Airport with Kolkata Metro Line 6 Kolkata Metro Line 4 Noapara BarasatUnder construction elevated railway of Kolkata Metro Line 4 or Yellow Line near Bagjola canalOverviewStatusUnder constructionOwnerMetro Railway KolkataLocaleKolkata Metropolitan Area IndiaTerminiNoapara south Barasat north Connecting linesBlue Line Orange LineStations10ServiceTypeRapid transitSystemKolkata MetroOperator s Metro Railway KolkataDepot s Noapara DepotAirport DepotBarasat DepotTechnicalLine length18 13 kilometres 11 27 mi 6 87 kilometres 4 27 mi Under Construction 11 26 kilometres 7 00 mi Planned 1 Number of tracks2Track gauge5 ft 6 in 1 676 mm broad gaugeElectrification750 V DC 2 using third railOperating speed80 km h designed Route map Click to expand Contents 1 Stations 2 Progress of Dum Dum Cantonment metro station 3 Project development 4 See also 5 ReferencesStations editThe stations of this corridor are Line 4 Yellow Line No Station Name Location Phase Opening Connections Layout Coordinates Notes English Bengali 1 Noapara ন য প ড Noapara 1 10 July 2013 nbsp operational nbsp 34C Bus Stand nbsp Health Care More Bus Stop nbsp Gharui Paschimpara Bus Stop Elevated 2 Dum Dum Cantonment দমদম ক য ন টনম ন ট Dum Dum Cantonment Under Construction nbsp Dum Dum Cantonment nbsp 30D Bus Stand nbsp Auto Stand to Nagerbazar 3 Jessore Road যশ র র ড NSCB International Airport Gate No 1 nbsp H M V Gate Bus Stop nbsp Airport Gate No 1 Bus Stop At grade Previously suburban rail used to operate in this line 4 Jai Hind জয হ ন দ NSCB International Airport nbsp under construction nbsp Airport AC Bus Stand nbsp Airport Gate No 1 Bus Stop nbsp Airport Gate No 2 Bus Stop nbsp Airport Gate No 2 5 Bus Stop nbsp Airport Gate No 3 Bus Stop Underground 5 Birati ব র ট Birati 2 nbsp Birati More Bus Stop nbsp Gouripur Bus Stand 6 Michael Nagar ম ইক ল নগর Michael Nagar nbsp Bankra Bus Stop nbsp Bankra Madni Nagar Bus Stop 7 New Barrackpore ন উ ব য র কপ র New Barrackpore nbsp B T College Bus Stand nbsp Sukanta Nagar Bus Stop 8 Madhyamgram মধ যমগ র ম Madhyamgram 3 Planned nbsp Madhyamgram nbsp Kalibari Madhyamgram Bus Stop 9 Hridaypur হ দয প র Hridaypur nbsp Hridaypur 10 Barasat ব র স ত Barasat nbsp Barasat Junction nbsp Barasat Champadali Bus TerminalProgress of Dum Dum Cantonment metro station edit nbsp Dum Dum Cantonment metro station An amount of Rs 227 crore contract to build this station along with a mostly at grade 2 16 km 1 34 mi section from the Bagjola Canal to the existing ramp of the Airport Circular Railway track was awarded to Senbo Engineering Limited all the way back in June 2011 Since then the station s civil structure has been built but work for the at grade track section could not be started due to land acquisition issues along the line s proposed alignment But the rehabilitation work has completed in 2020 and the work is going smoothly Recently girders were placed over Eastern Railway tracks The metro station is set to be operational by 2024 Project development editThe project will be completed in three phases The first phase of work from Noapara to Biman Bandar is under progress In the second phase work from Biman Bandar to New Barrackpore will be done and in the last phase from New Barrackpore to Barasat work will be done But the development work from New Barrackpore to Barasat got struck for the last eight years since it was sanctioned because of encroachments 4 and the Airport Authority of India objected the elevated stretches from New Barrackpore to Barasat Later after objections from AAI a decision was taken to convert this into an underground stretch On 29 June 2019 sanction for material modification for underground construction at an additional cost of 1 615 crore US 200 million was sent to Railway Board by Metro For this underground tunneling AAI has agreed to shift their fuel tanks buildings and cables and the project is expected to be started from 2020 5 Construction of an underground integrated station for Line 6 and line 4 has begun at NSCBI Airport land just 150 metres 492 ft away from the terminal building The development of New Barrackpore to Barasat was supposed to go elevated to cut down the expenses but the stretch was in doubt due to huge encroachment problem But in February 2021 Prime Minister Narendra Modi gave his nod to construct this stretch underground giving respite to thousands of families who were supposed to be evicted for the development of the elevated stretch 6 In order to lower the cost of the underground work latest technology TBM will not be used instead old technology of cut and cover method will be used for metro 7 Line 4 has been divided into three phases now Phase 1 Noapara Biman Bandar under construction Phase 2 Biman Bandar New Barrackpore construction has been started tender floated by RVNL to carry out construction work Phase 3 New Barrackpore Barasat construction to begin soon See also editList of Kolkata metro stations Kolkata Metro Rolling Stock List of rapid transit systems Trams in Kolkata Kolkata Lightrail Kolkata Monorail Kolkata Suburban RailwayReferences edit a b New System Map of Kolkata Metro CAF to supply Kolkata metro trains Senbo Engg wins 532 crore underground civil contracts for Kolkata Metro Line 4 Metro Rail Today Metro Rail Today Gateway to Rail amp Metro Industry Retrieved 12 April 2023 Gupta Jayanta 23 July 2019 Kolkata Metro to run below surface after airport The Times of India Retrieved 25 March 2020 Metro to run below surface after airport Times of India 26 July 2019 PM nod for underground Metro averts eviction www telegraphindia com Retrieved 14 March 2021 Senbo Engg wins 532 crore underground civil contracts for Kolkata Metro Line 4 Metro Rail Today Metro Rail Today Gateway to Rail amp Metro Industry Retrieved 12 April 2023 Retrieved from https en wikipedia org w index php title Kolkata Metro Line 4 amp oldid 1221854630, wikipedia, wiki, book, books, library,