Gigafactory Shanghai (Chinese: 特斯拉上海超级工厂; lit. 'Tesla Shanghai Super Factory') (also known as Giga Shanghai, or Gigafactory 3)[3] is an automobile manufacturing plant in Shanghai, China, operated by Tesla, Inc.[4] Construction of the plant began in January 2019, initial production started in October, and the first production vehicles rolled out of the factory in December 2019, less than one year after groundbreaking. The main plant currently manufactures the Model 3 and Model Y. As of July 2023, Tesla says the factory has the capacity to build over 750,000 vehicles per year and is the primary production site for Tesla vehicles exported to regions without a Gigafactory.[5] In addition to the main vehicle assembly building, a smaller building opened on the site in 2021 to assemble Superchargers.

Gigafactory Shanghai
Built2018–2019
OperatedOctober 2019 (2019-10)
LocationShanghai, China
Coordinates30°52′13″N 121°46′08″E / 30.87016656°N 121.76881044°E / 30.87016656; 121.76881044
IndustryAutomotive
Products
Employees20,000 (June 2023)[1]
Area0.865 km2 (0.334 sq mi; 214 acres)
AddressD203A, Tonghui Road No. 168, Nanhui New Town, Pudong New Area[2]
Owner(s)Tesla, Inc.

Unique among foreign automakers in China, the plant is wholly owned by Tesla and not operated as a joint venture with a Chinese company, the first time the government had allowed such an arrangement. While Tesla owns the factory, it does not own the land it is built on, as is typical in China. Tesla has land use rights with an initial term of 50 years.

History Edit

Background and land purchase (2018) Edit

Tesla Shanghai Co., Ltd., a subsidiary of the electric automaker, was formally established 8 May 2018.[6] In July 2018 Tesla CEO Elon Musk signed an agreement with the Shanghai regional government to build its third Gigafactory, and the first in China.[7] In part due to the good relationship Musk had built with the government, it was permitted to be structured as a wholly owned subsidiary of Tesla and not operated as a joint venture with a Chinese company, the first time the government had allowed such an arrangement for a foreign automaker.[8][9]: 207 

While Tesla owns the factory, it does not own the land it is built on, as is typical in China. The government granted Tesla land use rights with an initial term of 50 years. To finance the plant, Tesla received US$521 million in loans from Chinese banks at favorable interest rates,[10] and US$82 million in grant funding. The local Shanghai government granted Tesla a corporate income tax rate of 15% for 2019 through 2023, compared to the typical 25% rate in China. Having a factory in China also allows the company to avoid tariffs on vehicles imported from the U.S.[11]

In exchange for the land grant and government support, Tesla was required to spend CN¥10.85 billion in capital expenditures per (per 666.7 m2 or 7,200 sq ft) by the end of 2023, equating to a total minimum investment of CN¥14 billion (US$2 billion).[12][13] The factory is also required to generate CN¥2.23 billion of annual tax revenues starting at the end of 2023.[14]

On 8 August 2018, compulsory purchase order Shanghai [2018] No. 090 was issued by Pudong New Area Planning and Land Administration, with a closing date for objections of 14 August 2018, and finalization scheduled to occur on 20 August 2018.[15] On 26 September 2018, the bidding process for the newly acquired plots Q01-05 in the area designated as 04PD-0303 were advertised, with the restriction that the land be used for electric car manufacturing, with a minimum investment requirement.

The bidding process ran between 17‒26 October 2018, with the proviso that if there was only one bidder meeting the requirements by 11:30[clarification needed] on 17 October 2018, then the process could be closed and finalized early.[12] Tesla won the long-term lease for 86 hectares (210 acres) of land in Lingang, Shanghai on 17 October.[16][17][18]: 5:21  Tesla (Shanghai) was the only bidder, with its bid of 973 million Chinese yuan for the 50-year lease covering the 864,885-square-metre (86.5-hectare) site, with the capital coming from local Chinese banks.[19] The Shanghai Land Transfer contract No. 14 with Tesla (Shanghai) required construction work to begin within 6 months, and be completed within 30 months, with production started after 36 months, and full minimum tax revenues being paid after 60 months.[20] The Land Transfer was scheduled to occur on 12 December 2018, and limits the maximum size of above-ground buildings to 1,729,770 square metres (18,620,000 sq ft) in area [sic] with a maximum height of 30 metres (100 ft).[21] Up to 60,541 square metres (650,000 sq ft) of the area can be used for non-production office buildings.[21] Phase 1 of the project will manufacture Tesla Model 3 and Tesla Model Y cars, with a target production rate of 250,000 electric cars per year.[22] Tesla stated that it planned to eventually be able to produce 500,000 electric vehicles per year at the site.[16][17]

The public environmental impact consultation for Phase 1 of the project was opened on 24 October 2018, and scheduled to run for ten working days.[22]Capital expenditures covering the land purchase and initial design costs for Gigafactory 3 were scheduled to occur in the fourth quarter of 2018.[23] The purchase was aided by a loan from Chinese banks, and converted to a $1.4 billion loan in late 2019, also by Chinese banks.[24]

Construction and delivery (2019) Edit

Groundbreaking ceremony of phase 1, January 2019

A construction permit was granted by the Shanghai municipal government authorizing work to begin after 29 December 2018. The project contractor is China Construction Third Engineering Bureau Co., Ltd., part of China State Construction Engineering, a large state-owned construction company.[25]

The factory site is in the Lingang Industrial Zone within the Pudong district of Shanghai, with the western edge bordering the Fengxian district.

By December 2018, construction activity at the site was underway with site grading.[26] Shanghai Mayor Ying Yong visited the site on 5 December.[27][28] A subsidiary of China Minmetals was making preparations for piling foundations.[29] Shanghai Construction Group was one of the companies bidding for part of the larger construction contract.[29]

On 7 January 2019, the groundbreaking ceremony was held.[30] By March, foundation work in some areas of the large facility was in place and structure is being erected, with crews operating at the site on multiple shifts to accelerate construction.[31]

By early August 2019, the building exteriors were nearly complete, and the general assembly building was being fitted with manufacturing equipment, with a target to begin production in November.[32] The plant received its "comprehensive acceptance certificate" on 19 August.[33]

In the 3Q2019 quarterly investor call on 23 October 2019, Tesla reported that it is ahead of schedule with getting the factory into production. Moreover, it was built in just ten months, is ready for production, and was built for approximately 65% less capital expenditure per unit of manufacturing capacity than had been the Model 3 production system in the US. General assembly of the initial Tesla Model 3s was operating by October 2019,[34] with 30% of the car coming from China.[35]

Expansion (2021) Edit

In April 2021, Local reports have noted that preliminary work on the new site south of the main complex has been going on for some time. Tesla was the sole bidder for the land, and while the bidding process Gigafactory produced vehicles and the Model Y at a rate of about 450,000 cars per year, the expanded site is already being prepared for construction.[36]

A smaller building opened near the factory in 2021 builds Superchargers, with the capacity to produce 10,000 chargers per year.[37]

Expansion of Giga Shanghai was briefly halted in 2023 after the Chinese central government expressed concerns with Elon's activities at SpaceX, in particular the quickly expanding military applications of Starlink and its potential impact on global strategic defense.[38]

Production (2019-today) Edit

Giga Shanghai currently does final assembly of Model 3 vehicles which began in December 2019, with expectation to begin Model Y final assembly later in 2020. While initially, assembly is accomplished with parts and subassemblies that are shipped into the factory from the US, a major push during 2020 will be to gradually increase the "Made in China" (MIC) content in the car as Tesla China manufacturing matures.[39] As of March 2020, MIC Model Y production is slated for January 2021. Production line capacity of Giga Shanghai is aimed at 5,000 cars per week, and if achieved and sustained could result in an annual capacity of more than 250,000 vehicles.[39][unreliable source?][17] Once the factory has been fully built out and production has fully ramped, Tesla plans for the factory to reach an annual production capacity of about 500,000 vehicles for Chinese consumers.[16]

Transport truck trailer rigs moved cars out by early December 2019,[40] and the first 15 cars from the new factory were delivered on 30 December 2019, to Tesla employees.[41] The first cars to be produced at the Gigafactory and delivered to Chinese customers were delivered on 7 January 2020.[42][43] Production rate was approximately 1,000 cars per week in early 2020,[44] made by a single shift of workers[45] with a total production line capacity of 2,000 cars per week when Saturday overtime is included.[39]

The Gigafactory Shanghai was temporarily shut down for approximately two weeks by order of the government on 29 January 2020, due to the COVID-19 pandemic.[46] Production resumed 10 February, as did for suppliers and other companies around the country.[47] Several precautions were taken to prevent virus spread,[48] so preliminary plans indicate Tesla could add a second shift of production by the beginning of Q2 2020 which would increase line capacity to approximately 3,500 vehicles per week.[39] By the end of the year, it reached 8,000 vehicles per week,[49] and some of them were found to be right hand drive for export purpose[50] to Australia and New Zealand. In November 2021, total production was 56,965 vehicles and capacity was estimated to be nearing 700,000 vehicles per year, becoming the largest of the Tesla factories.[51] On 28 March 2022, Gigafactory Shanghai was again shut down, this time for 22 days due to a government lockdown in response to the 2022 Shanghai COVID-19 outbreak. It officially reopened on 19 April 2022, initially operating only one shift, with 8,000 workers sleeping at the factory, but resumed normal production near the end of May.[52]

On 12 January 2022, the China Association of Automobile Manufacturers (CAAM) announced that 310,000 new energy vehicles (NEVs) were exported from China in 2021, and that half of the total were assembled in Giga Shanghai.[53] These produced cars are mainly sold to regions such as Europe and Asia and 10 more countries around the world. The main export destination for Chinese-made NEVs was Europe. The China Association of Automobile Manufactures Data showed that the most popular option is Tesla's Model 3.[54]

See also Edit

References Edit

  1. ^ "Tesla Starts to Lay Off Some Battery Workers at China Factory". Bloomberg News. 6 July 2023. Retrieved 13 August 2023.
  2. ^ "Grant Contract for State-Owned Construction Land Use Right, dated as of October 17, 2018, by and between Shanghai Planning and Land Resource Administration Bureau, as grantor, and Tesla (Shanghai) Co., Ltd., as grantee (English translation)". www.sec.gov. 29 July 2019. Retrieved 13 August 2023.
  3. ^ Musk, Elon [@elonmusk] (25 January 2020). "Going with nomenclature of Giga [most widely understood location name] vs Giga #, so Giga Shanghai, Giga Nevada, Giga New York & Giga Berlin" (Tweet). Retrieved 26 January 2020 – via Twitter.
  4. ^ Alan Ohnsman (10 July 2018). "How Is Musk Going To Pay For Tesla's Chinese Gigafactory?". Forbes.com. from the original on 18 July 2018. Retrieved 17 July 2018.
  5. ^ "Q2 2023 Investor Update Presentation" (PDF). Tesla, Inc. 19 July 2023. p. 7. Retrieved 12 August 2023.
  6. ^ "特斯拉獨資在浦東注册成立公司" [Tesla establishes wholly-owned subsidiary in Shanghai Pudong]. 上海浦東門戶網站 發. Pudong. 15 May 2018. from the original on 23 October 2018. Retrieved 23 October 2018. 特斯拉(上海) 有限公司注册資本 1 亿元,股東為特斯拉汽車香港有限公司,公司成立日期為
  7. ^ "Tesla Plots Bold China Factory Move, Stays Silent on Cost". Bloomberg. 10 July 2018. from the original on 19 July 2018. Retrieved 19 July 2018.
  8. ^ Yuan, Li (30 November 2021). "In China, Tesla Is a Catfish, and Turns Auto Companies Into Sharks". The New York Times. Retrieved 13 August 2023.
  9. ^ Marquis, Christopher; Qiao, Kunyuan (2022). Mao and Markets: The Communist Roots of Chinese Enterprise. New Haven: Yale University Press. doi:10.2307/j.ctv3006z6k. ISBN 978-0-300-26883-6. JSTOR j.ctv3006z6k. OCLC 1348572572. S2CID 253067190.
  10. ^ "Tesla Secures $521 Million in Chinese Loans for Shanghai Production Plant". Fortune. Retrieved 13 August 2023.
  11. ^ "2018 Form 10-K". www.sec.gov. Retrieved 13 August 2023.
  12. ^ a b 包雨朦 (12 October 2018). "特斯拉上海工厂选址浮出:临港86万平方米造车用地挂牌出让" [Tesla Shanghai factory site is under tender: 860,000 square meters of car-manufacturing land for sale in Lingang]. 澎湃新闻. from the original on 18 October 2018. Retrieved 18 October 2018.
  13. ^ Shanghai Planning and Land Resources Administration (26 September 2018). "地块公告号:201813801" [Land parcel: 201813801]. from the original on 18 October 2018. Retrieved 18 October 2018. 临港重装备产业区 04PD-0303单元Q01-05地块四至范围: … 东至规划预留东海二桥控制线绿化带, 南至人民塘绿化带, 西至南奉界河绿化带, 北至老里塘河绿化带 … (平方米): 864885.0 … 出让年限50竞得价(万元): 97300.0 … 竞得人特斯拉(上海)有限公司
  14. ^ "2022 Form 10-K" (PDF). Tesla, Inc. Retrieved 12 August 2023.
  15. ^ Shanghai Planning and Land Resources Administration (8 August 2018). [Shanghai [Pudong] proposed land acquisition [2018] No. 090] (in Chinese). 上海市规划和国土资源管理局 [Pudong New Area Planning and Land Administration]. Archived from the original on 23 October 2018. Retrieved 23 October 2018.
  16. ^ a b c "Tesla inks deal for Gigafactory 3 in China". techcrunch.com. 17 October 2018. from the original on 17 October 2018. Retrieved 17 October 2018.
  17. ^ a b c "Tesla secures 210-acre land for Gigafactory 3 in China, says 'on track' with accelerated construction plan". Electrek. 17 October 2018. from the original on 18 October 2018. Retrieved 17 October 2018.
  18. ^ Chris Lister, VP of Gigafactory; Jat Dhillon, Director of Manufacturing (30 November 2018). This is Elon Musk's key to Tesla's future (video). The Verge. from the original on 1 December 2018. Retrieved 2 December 2018 – via YouTube.
  19. ^ Hancock, Tom; Ju, Sherry (18 October 2018). "Tesla pays $140m for lease on first non-US factory in Shanghai". Financial Times. from the original on 18 October 2018. Retrieved 18 October 2018.
  20. ^ Shanghai Planning and Land Resources Administration. "沪规土资(2018)出让合同第14号" [Shanghai Regulation Land Transfer (2018) Contract No. 14] (in Chinese). from the original on 23 October 2018. Retrieved 23 October 2018.
  21. ^ a b Shanghai Planning and Land Resources Administration. "沪规土资(2018)出让合同第14号 (1.0版)" [Shanghai Regulation Land Transfer (2018) Contract No. 14, Version 1.0] (contract) (in Chinese).[permanent dead link]
  22. ^ a b 上海达恩贝拉环境科技发展有限公司 (24 October 2018). [Tesla (Shanghai) Gigafactory Project (Phase 1) Environmental Impact Assessment Publicity] (in Chinese). 上海市环境保护宣传教育中心. Archived from the original on 24 October 2018. Retrieved 24 October 2018.
  23. ^ "Tesla Third Quarter 2018 Update". Tesla. 24 October 2018. p. 5. from the original on 24 October 2018. Retrieved 24 October 2018. Q4 capex projection includes the purchase of land in China and initial design and other expenditures for Gigafactory 3.
  24. ^ "Tesla to take new $1.4 billion loan from Chinese banks for Shanghai factory - sources". Reuters. 23 December 2019. from the original on 23 December 2019.
  25. ^ Alvarez, Simon (3 January 2019). "Tesla's Gigafactory 3 in China starts preparations with 6-month construction permit". Teslarati. from the original on 7 January 2019. Retrieved 6 January 2019.
  26. ^ Alvarez, Simon (17 December 2018). "Tesla Gigafactory 3 construction in China begins with rapid buildout of perimeter fence". from the original on 19 December 2018. Retrieved 19 December 2018.
  27. ^ City of Shanghai (5 December 2018). "中芯、特斯拉、积塔……应勇今天调研了这些重大投资项目!" [SMIC, Tesla and Jita … Ying Yong visited these major investment projects today!] (Press release) (in Chinese). from the original on 13 May 2019. Retrieved 5 December 2018.
  28. ^ Cheng, Evelyn (5 December 2018). "Tesla's China factory is set to begin production late next year, Shanghai government says". CNBC. from the original on 6 December 2018. Retrieved 5 December 2018.
  29. ^ a b "Hit by trade war, Tesla opens bid process to build China Gigafactory". South China Morning Post. 6 December 2018. from the original on 6 December 2018. Retrieved 17 December 2018. Shanghai Construction Group is among several firms bidding … Shanghai Baoye Group, a China Minmetals subsidiary, is preparing for the delivery of a large amount of concrete pipe piles and steel pile tips in the second half of December [2018]
  30. ^ "Tesla CEO Musk breaks ground at Shanghai Gigafactory to launch China push". 7 January 2019. from the original on 19 January 2019. Retrieved 19 January 2019.
  31. ^ Alvarez, Simon (26 March 2019). "Tesla's Gigafactory 3 buildout hits overdrive as China's workforce mobilizes 24/7". from the original on 26 March 2019. Retrieved 26 March 2019.
  32. ^ "Tesla Releases New Photo Of Gigafactory 3 In China, Drone Video Shows Massive Factory". 6 August 2019. from the original on 8 August 2019. Retrieved 10 August 2019.
  33. ^ https://www.teslarati.com/tesla-gigafactory-3-acceptance-certificate-inspection-record-time, 20 August 2019.
  34. ^ Kolodny, Lora (23 October 2019). "Tesla shares soar after crushing third-quarter earnings". CNBC. from the original on 1 November 2020. Retrieved 23 October 2019.
  35. ^ "Tesla lowers price of China Model 3 to undercut BMW and Mercedes in strategic play". TESLARATI. 3 January 2020. from the original on 3 January 2020. Retrieved 3 January 2020.
  36. ^ "Tesla Gigafactory Shanghai's new major expansion is starting". 1 April 2021. from the original on 20 November 2021. Retrieved 20 November 2021.
  37. ^ Lambert, Fred (3 February 2021). "Tesla opens its new Supercharger factory". Electrek. from the original on 11 March 2021. Retrieved 20 May 2021.
  38. ^ "Tesla China Plant Expansion in Doubt Over Starlink Concerns". Bloomberg. US. 12 January 2023. Retrieved 21 January 2023.
  39. ^ a b c d Suba, Randall (9 March 2020). "Tesla Giga Shanghai Update: Projected 2021 production, Model Y delivery schedule, Model 3 Long Range". from the original on 18 November 2020. Retrieved 10 March 2020.
  40. ^ Tesla Made-in-China Model 3 first deliveries imminent as carriers spotted leaving Gigafactory 3 9 December 2019 at the Wayback Machine, Teslarati, 8 December 2019, accessed 9 December 2019.
  41. ^ China, Tesla (29 December 2019). "Tesla will deliver the first China-made Model 3 at Gigafactory 3 plant in Shanghai TODAY. The 15 customers who are slated to get their Model 3s first are Tesla employees.pic.twitter.com/bOTeR8wjUL". @teslacn. from the original on 3 January 2020. Retrieved 30 December 2019.
  42. ^ Tesla, Inc. [@Tesla] (7 January 2020). "We just delivered our first customer cars from Gigafactory Shanghai, marking only one year from when the teams broke ground on the site" (Tweet). from the original on 11 January 2020. Retrieved 7 January 2020 – via Twitter.
  43. ^ "Tesla delivers first Chinese-made Model 3 to customers | The Star". The Toronto Star. 7 January 2020. from the original on 8 January 2020. Retrieved 23 January 2020.
  44. ^ Lambert, Fred (12 February 2020). "Tesla is going to make discontinued Model 3 Long Range RWD in China, already produced over 2,000 cars this year". Electrek. from the original on 13 February 2020. Retrieved 13 February 2020.
  45. ^ "Projected 2021 production, Model Y delivery schedule, Model 3 Long Range". TESLARATI. 9 March 2020. from the original on 18 November 2020. Retrieved 9 March 2020.
  46. ^ "Tesla says China has ordered its Shanghai factory shut down over coronavirus fears", The Verge, 29 January 2020, https://www.theverge.com/2020/1/29/21114377/tesla-coronavirus-delay-production-factory-china 2 February 2020 at the Wayback Machine
  47. ^ . www.xinhuanet.com. Xinhua News Agency. 10 February 2020. Archived from the original on 13 February 2020. Retrieved 13 February 2020.
  48. ^ Alvarez, Simon (17 March 2020). "Tesla China shares Giga Shanghai safety measures against COVID-19 virus". TESLARATI. from the original on 19 March 2020. Retrieved 17 March 2020.
  49. ^ Merano, Maria (5 January 2021). "Tesla Gigafactory Shanghai reaches 8k/week production capacity: study". from the original on 5 January 2021. Retrieved 5 January 2021.
  50. ^ Alvarez, Simon (14 January 2021). "Tesla Model 3 Right Hand Drive fleet spotted in Giga Shanghai ready for export". from the original on 26 January 2021. Retrieved 28 January 2021.
  51. ^ John, Darryn (21 December 2021). "Giga Shanghai's November 2021 production figures indicate annualized rate of 683,000 cars".
  52. ^ Lambert, Fred (8 June 2022). "Tesla Gigafactory Shanghai is going out of 'closed loop' with workers sleeping at the plant this week". Electrek. Retrieved 14 June 2022.
  53. ^ "China's new energy vehicles exports tripled in 2021, with half made by Tesla". KrASIA. 13 January 2022. Retrieved 13 January 2022.
  54. ^ Cooke, Philip (January 2020). "Gigafactory Logistics in Space and Time: Tesla's Fourth Gigafactory and Its Rivals". Sustainability. 12 (5): 2044. doi:10.3390/su12052044. ISSN 2071-1050.

External links Edit

  • Tesla GigaFactory 3 Shanghai Updates
  • Gigafactory 3 on Facebook
  • 635670279 Gigafactory 3 outline on OpenStreetMap

gigafactory, shanghai, chinese, 特斯拉上海超级工厂, tesla, shanghai, super, factory, also, known, giga, shanghai, gigafactory, automobile, manufacturing, plant, shanghai, china, operated, tesla, construction, plant, began, january, 2019, initial, production, started, o. Gigafactory Shanghai Chinese 特斯拉上海超级工厂 lit Tesla Shanghai Super Factory also known as Giga Shanghai or Gigafactory 3 3 is an automobile manufacturing plant in Shanghai China operated by Tesla Inc 4 Construction of the plant began in January 2019 initial production started in October and the first production vehicles rolled out of the factory in December 2019 less than one year after groundbreaking The main plant currently manufactures the Model 3 and Model Y As of July 2023 update Tesla says the factory has the capacity to build over 750 000 vehicles per year and is the primary production site for Tesla vehicles exported to regions without a Gigafactory 5 In addition to the main vehicle assembly building a smaller building opened on the site in 2021 to assemble Superchargers Gigafactory ShanghaiBuilt2018 2019OperatedOctober 2019 2019 10 LocationShanghai ChinaCoordinates30 52 13 N 121 46 08 E 30 87016656 N 121 76881044 E 30 87016656 121 76881044IndustryAutomotiveProductsModel 3Model YSuperchargerEmployees20 000 June 2023 1 Area0 865 km2 0 334 sq mi 214 acres AddressD203A Tonghui Road No 168 Nanhui New Town Pudong New Area 2 Owner s Tesla Inc Unique among foreign automakers in China the plant is wholly owned by Tesla and not operated as a joint venture with a Chinese company the first time the government had allowed such an arrangement While Tesla owns the factory it does not own the land it is built on as is typical in China Tesla has land use rights with an initial term of 50 years Contents 1 History 1 1 Background and land purchase 2018 1 2 Construction and delivery 2019 1 3 Expansion 2021 2 Production 2019 today 3 See also 4 References 5 External linksHistory EditBackground and land purchase 2018 Edit Tesla Shanghai Co Ltd a subsidiary of the electric automaker was formally established 8 May 2018 6 In July 2018 Tesla CEO Elon Musk signed an agreement with the Shanghai regional government to build its third Gigafactory and the first in China 7 In part due to the good relationship Musk had built with the government it was permitted to be structured as a wholly owned subsidiary of Tesla and not operated as a joint venture with a Chinese company the first time the government had allowed such an arrangement for a foreign automaker 8 9 207 While Tesla owns the factory it does not own the land it is built on as is typical in China The government granted Tesla land use rights with an initial term of 50 years To finance the plant Tesla received US 521 million in loans from Chinese banks at favorable interest rates 10 and US 82 million in grant funding The local Shanghai government granted Tesla a corporate income tax rate of 15 for 2019 through 2023 compared to the typical 25 rate in China Having a factory in China also allows the company to avoid tariffs on vehicles imported from the U S 11 In exchange for the land grant and government support Tesla was required to spend CN 10 85 billion in capital expenditures per mǔ per 666 7 m2 or 7 200 sq ft by the end of 2023 equating to a total minimum investment of CN 14 billion US 2 billion 12 13 The factory is also required to generate CN 2 23 billion of annual tax revenues starting at the end of 2023 14 On 8 August 2018 compulsory purchase order Shanghai 2018 No 090 was issued by Pudong New Area Planning and Land Administration with a closing date for objections of 14 August 2018 and finalization scheduled to occur on 20 August 2018 15 On 26 September 2018 the bidding process for the newly acquired plots Q01 05 in the area designated as 04PD 0303 were advertised with the restriction that the land be used for electric car manufacturing with a minimum investment requirement The bidding process ran between 17 26 October 2018 with the proviso that if there was only one bidder meeting the requirements by 11 30 clarification needed on 17 October 2018 then the process could be closed and finalized early 12 Tesla won the long term lease for 86 hectares 210 acres of land in Lingang Shanghai on 17 October 16 17 18 5 21 Tesla Shanghai was the only bidder with its bid of 973 million Chinese yuan for the 50 year lease covering the 864 885 square metre 86 5 hectare site with the capital coming from local Chinese banks 19 The Shanghai Land Transfer contract No 14 with Tesla Shanghai required construction work to begin within 6 months and be completed within 30 months with production started after 36 months and full minimum tax revenues being paid after 60 months 20 The Land Transfer was scheduled to occur on 12 December 2018 and limits the maximum size of above ground buildings to 1 729 770 square metres 18 620 000 sq ft in area sic with a maximum height of 30 metres 100 ft 21 Up to 60 541 square metres 650 000 sq ft of the area can be used for non production office buildings 21 Phase 1 of the project will manufacture Tesla Model 3 and Tesla Model Y cars with a target production rate of 250 000 electric cars per year 22 Tesla stated that it planned to eventually be able to produce 500 000 electric vehicles per year at the site 16 17 The public environmental impact consultation for Phase 1 of the project was opened on 24 October 2018 and scheduled to run for ten working days 22 Capital expenditures covering the land purchase and initial design costs for Gigafactory 3 were scheduled to occur in the fourth quarter of 2018 23 The purchase was aided by a loan from Chinese banks and converted to a 1 4 billion loan in late 2019 also by Chinese banks 24 Construction and delivery 2019 Edit source source source source Groundbreaking ceremony of phase 1 January 2019A construction permit was granted by the Shanghai municipal government authorizing work to begin after 29 December 2018 The project contractor is China Construction Third Engineering Bureau Co Ltd part of China State Construction Engineering a large state owned construction company 25 The factory site is in the Lingang Industrial Zone within the Pudong district of Shanghai with the western edge bordering the Fengxian district By December 2018 construction activity at the site was underway with site grading 26 Shanghai Mayor Ying Yong visited the site on 5 December 27 28 A subsidiary of China Minmetals was making preparations for piling foundations 29 Shanghai Construction Group was one of the companies bidding for part of the larger construction contract 29 On 7 January 2019 the groundbreaking ceremony was held 30 By March foundation work in some areas of the large facility was in place and structure is being erected with crews operating at the site on multiple shifts to accelerate construction 31 By early August 2019 the building exteriors were nearly complete and the general assembly building was being fitted with manufacturing equipment with a target to begin production in November 32 The plant received its comprehensive acceptance certificate on 19 August 33 In the 3Q2019 quarterly investor call on 23 October 2019 Tesla reported that it is ahead of schedule with getting the factory into production Moreover it was built in just ten months is ready for production and was built for approximately 65 less capital expenditure per unit of manufacturing capacity than had been the Model 3 production system in the US General assembly of the initial Tesla Model 3s was operating by October 2019 34 with 30 of the car coming from China 35 Expansion 2021 Edit In April 2021 Local reports have noted that preliminary work on the new site south of the main complex has been going on for some time Tesla was the sole bidder for the land and while the bidding process Gigafactory produced vehicles and the Model Y at a rate of about 450 000 cars per year the expanded site is already being prepared for construction 36 A smaller building opened near the factory in 2021 builds Superchargers with the capacity to produce 10 000 chargers per year 37 Expansion of Giga Shanghai was briefly halted in 2023 after the Chinese central government expressed concerns with Elon s activities at SpaceX in particular the quickly expanding military applications of Starlink and its potential impact on global strategic defense 38 Production 2019 today EditThis article needs to be updated The reason given is No update on Model Y production Please help update this article to reflect recent events or newly available information November 2021 Giga Shanghai currently does final assembly of Model 3 vehicles which began in December 2019 with expectation to begin Model Y final assembly later in 2020 While initially assembly is accomplished with parts and subassemblies that are shipped into the factory from the US a major push during 2020 will be to gradually increase the Made in China MIC content in the car as Tesla China manufacturing matures 39 As of March 2020 update MIC Model Y production is slated for January 2021 Production line capacity of Giga Shanghai is aimed at 5 000 cars per week and if achieved and sustained could result in an annual capacity of more than 250 000 vehicles 39 unreliable source 17 Once the factory has been fully built out and production has fully ramped Tesla plans for the factory to reach an annual production capacity of about 500 000 vehicles for Chinese consumers 16 Transport truck trailer rigs moved cars out by early December 2019 40 and the first 15 cars from the new factory were delivered on 30 December 2019 to Tesla employees 41 The first cars to be produced at the Gigafactory and delivered to Chinese customers were delivered on 7 January 2020 42 43 Production rate was approximately 1 000 cars per week in early 2020 44 made by a single shift of workers 45 with a total production line capacity of 2 000 cars per week when Saturday overtime is included 39 The Gigafactory Shanghai was temporarily shut down for approximately two weeks by order of the government on 29 January 2020 due to the COVID 19 pandemic 46 Production resumed 10 February as did for suppliers and other companies around the country 47 Several precautions were taken to prevent virus spread 48 so preliminary plans indicate Tesla could add a second shift of production by the beginning of Q2 2020 which would increase line capacity to approximately 3 500 vehicles per week 39 By the end of the year it reached 8 000 vehicles per week 49 and some of them were found to be right hand drive for export purpose 50 to Australia and New Zealand In November 2021 total production was 56 965 vehicles and capacity was estimated to be nearing 700 000 vehicles per year becoming the largest of the Tesla factories 51 On 28 March 2022 Gigafactory Shanghai was again shut down this time for 22 days due to a government lockdown in response to the 2022 Shanghai COVID 19 outbreak It officially reopened on 19 April 2022 initially operating only one shift with 8 000 workers sleeping at the factory but resumed normal production near the end of May 52 On 12 January 2022 the China Association of Automobile Manufacturers CAAM announced that 310 000 new energy vehicles NEVs were exported from China in 2021 and that half of the total were assembled in Giga Shanghai 53 These produced cars are mainly sold to regions such as Europe and Asia and 10 more countries around the world The main export destination for Chinese made NEVs was Europe The China Association of Automobile Manufactures Data showed that the most popular option is Tesla s Model 3 54 See also EditList of Tesla factoriesReferences Edit Tesla Starts to Lay Off Some Battery Workers at China Factory Bloomberg News 6 July 2023 Retrieved 13 August 2023 Grant Contract for State Owned Construction Land Use Right dated as of October 17 2018 by and between Shanghai Planning and Land Resource Administration Bureau as grantor and Tesla Shanghai Co Ltd as grantee English translation www sec gov 29 July 2019 Retrieved 13 August 2023 Musk Elon elonmusk 25 January 2020 Going with nomenclature of Giga most widely understood location name vs Giga so Giga Shanghai Giga Nevada Giga New York amp Giga Berlin Tweet Retrieved 26 January 2020 via Twitter Alan Ohnsman 10 July 2018 How Is Musk Going To Pay For Tesla s Chinese Gigafactory Forbes com Archived from the original on 18 July 2018 Retrieved 17 July 2018 Q2 2023 Investor Update Presentation PDF Tesla Inc 19 July 2023 p 7 Retrieved 12 August 2023 特斯拉獨資在浦東注册成立公司 Tesla establishes wholly owned subsidiary in Shanghai Pudong 上海浦東門戶網站 發 Pudong 15 May 2018 Archived from the original on 23 October 2018 Retrieved 23 October 2018 特斯拉 上海 有限公司注册資本 1 亿元 股東為特斯拉汽車香港有限公司 公司成立日期為 2018 年 5 月 10 日 Tesla Plots Bold China Factory Move Stays Silent on Cost Bloomberg 10 July 2018 Archived from the original on 19 July 2018 Retrieved 19 July 2018 Yuan Li 30 November 2021 In China Tesla Is a Catfish and Turns Auto Companies Into Sharks The New York Times Retrieved 13 August 2023 Marquis Christopher Qiao Kunyuan 2022 Mao and Markets The Communist Roots of Chinese Enterprise New Haven Yale University Press doi 10 2307 j ctv3006z6k ISBN 978 0 300 26883 6 JSTOR j ctv3006z6k OCLC 1348572572 S2CID 253067190 Tesla Secures 521 Million in Chinese Loans for Shanghai Production Plant Fortune Retrieved 13 August 2023 2018 Form 10 K www sec gov Retrieved 13 August 2023 a b 包雨朦 12 October 2018 特斯拉上海工厂选址浮出 临港86万平方米造车用地挂牌出让 Tesla Shanghai factory site is under tender 860 000 square meters of car manufacturing land for sale in Lingang 澎湃新闻 Archived from the original on 18 October 2018 Retrieved 18 October 2018 Shanghai Planning and Land Resources Administration 26 September 2018 地块公告号 201813801 Land parcel 201813801 Archived from the original on 18 October 2018 Retrieved 18 October 2018 临港重装备产业区 04PD 0303单元Q01 05地块 四至范围 东至规划预留东海二桥控制线绿化带 南至人民塘绿化带 西至南奉界河绿化带 北至老里塘河绿化带 平方米 864885 0 出让年限 50 竞得价 万元 97300 0 竞得人 特斯拉 上海 有限公司 2022 Form 10 K PDF Tesla Inc Retrieved 12 August 2023 Shanghai Planning and Land Resources Administration 8 August 2018 沪 浦 拟征地告 2018 第090号 Shanghai Pudong proposed land acquisition 2018 No 090 in Chinese 上海市规划和国土资源管理局 Pudong New Area Planning and Land Administration Archived from the original on 23 October 2018 Retrieved 23 October 2018 a b c Tesla inks deal for Gigafactory 3 in China techcrunch com 17 October 2018 Archived from the original on 17 October 2018 Retrieved 17 October 2018 a b c Tesla secures 210 acre land for Gigafactory 3 in China says on track with accelerated construction plan Electrek 17 October 2018 Archived from the original on 18 October 2018 Retrieved 17 October 2018 Chris Lister VP of Gigafactory Jat Dhillon Director of Manufacturing 30 November 2018 This is Elon Musk s key to Tesla s future video The Verge Archived from the original on 1 December 2018 Retrieved 2 December 2018 via YouTube Hancock Tom Ju Sherry 18 October 2018 Tesla pays 140m for lease on first non US factory in Shanghai Financial Times Archived from the original on 18 October 2018 Retrieved 18 October 2018 Shanghai Planning and Land Resources Administration 沪规土资 2018 出让合同第14号 Shanghai Regulation Land Transfer 2018 Contract No 14 in Chinese Archived from the original on 23 October 2018 Retrieved 23 October 2018 a b Shanghai Planning and Land Resources Administration 沪规土资 2018 出让合同第14号 1 0版 Shanghai Regulation Land Transfer 2018 Contract No 14 Version 1 0 contract in Chinese permanent dead link a b 上海达恩贝拉环境科技发展有限公司 24 October 2018 特斯拉上海超级工厂项目 一期 环境影响评价公示 Tesla Shanghai Gigafactory Project Phase 1 Environmental Impact Assessment Publicity in Chinese 上海市环境保护宣传教育中心 Archived from the original on 24 October 2018 Retrieved 24 October 2018 Tesla Third Quarter 2018 Update Tesla 24 October 2018 p 5 Archived from the original on 24 October 2018 Retrieved 24 October 2018 Q4 capex projection includes the purchase of land in China and initial design and other expenditures for Gigafactory 3 Tesla to take new 1 4 billion loan from Chinese banks for Shanghai factory sources Reuters 23 December 2019 Archived from the original on 23 December 2019 Alvarez Simon 3 January 2019 Tesla s Gigafactory 3 in China starts preparations with 6 month construction permit Teslarati Archived from the original on 7 January 2019 Retrieved 6 January 2019 Alvarez Simon 17 December 2018 Tesla Gigafactory 3 construction in China begins with rapid buildout of perimeter fence Archived from the original on 19 December 2018 Retrieved 19 December 2018 City of Shanghai 5 December 2018 中芯 特斯拉 积塔 应勇今天调研了这些重大投资项目 SMIC Tesla and Jita Ying Yong visited these major investment projects today Press release in Chinese Archived from the original on 13 May 2019 Retrieved 5 December 2018 Cheng Evelyn 5 December 2018 Tesla s China factory is set to begin production late next year Shanghai government says CNBC Archived from the original on 6 December 2018 Retrieved 5 December 2018 a b Hit by trade war Tesla opens bid process to build China Gigafactory South China Morning Post 6 December 2018 Archived from the original on 6 December 2018 Retrieved 17 December 2018 Shanghai Construction Group is among several firms bidding Shanghai Baoye Group a China Minmetals subsidiary is preparing for the delivery of a large amount of concrete pipe piles and steel pile tips in the second half of December 2018 Tesla CEO Musk breaks ground at Shanghai Gigafactory to launch China push 7 January 2019 Archived from the original on 19 January 2019 Retrieved 19 January 2019 Alvarez Simon 26 March 2019 Tesla s Gigafactory 3 buildout hits overdrive as China s workforce mobilizes 24 7 Archived from the original on 26 March 2019 Retrieved 26 March 2019 Tesla Releases New Photo Of Gigafactory 3 In China Drone Video Shows Massive Factory 6 August 2019 Archived from the original on 8 August 2019 Retrieved 10 August 2019 https www teslarati com tesla gigafactory 3 acceptance certificate inspection record time 20 August 2019 Kolodny Lora 23 October 2019 Tesla shares soar after crushing third quarter earnings CNBC Archived from the original on 1 November 2020 Retrieved 23 October 2019 Tesla lowers price of China Model 3 to undercut BMW and Mercedes in strategic play TESLARATI 3 January 2020 Archived from the original on 3 January 2020 Retrieved 3 January 2020 Tesla Gigafactory Shanghai s new major expansion is starting 1 April 2021 Archived from the original on 20 November 2021 Retrieved 20 November 2021 Lambert Fred 3 February 2021 Tesla opens its new Supercharger factory Electrek Archived from the original on 11 March 2021 Retrieved 20 May 2021 Tesla China Plant Expansion in Doubt Over Starlink Concerns Bloomberg US 12 January 2023 Retrieved 21 January 2023 a b c d Suba Randall 9 March 2020 Tesla Giga Shanghai Update Projected 2021 production Model Y delivery schedule Model 3 Long Range Archived from the original on 18 November 2020 Retrieved 10 March 2020 Tesla Made in China Model 3 first deliveries imminent as carriers spotted leaving Gigafactory 3 Archived 9 December 2019 at the Wayback Machine Teslarati 8 December 2019 accessed 9 December 2019 China Tesla 29 December 2019 Tesla will deliver the first China made Model 3 at Gigafactory 3 plant in Shanghai TODAY The 15 customers who are slated to get their Model 3s first are Tesla employees pic twitter com bOTeR8wjUL teslacn Archived from the original on 3 January 2020 Retrieved 30 December 2019 Tesla Inc Tesla 7 January 2020 We just delivered our first customer cars from Gigafactory Shanghai marking only one year from when the teams broke ground on the site Tweet Archived from the original on 11 January 2020 Retrieved 7 January 2020 via Twitter Tesla delivers first Chinese made Model 3 to customers The Star The Toronto Star 7 January 2020 Archived from the original on 8 January 2020 Retrieved 23 January 2020 Lambert Fred 12 February 2020 Tesla is going to make discontinued Model 3 Long Range RWD in China already produced over 2 000 cars this year Electrek Archived from the original on 13 February 2020 Retrieved 13 February 2020 Projected 2021 production Model Y delivery schedule Model 3 Long Range TESLARATI 9 March 2020 Archived from the original on 18 November 2020 Retrieved 9 March 2020 Tesla says China has ordered its Shanghai factory shut down over coronavirus fears The Verge 29 January 2020 https www theverge com 2020 1 29 21114377 tesla coronavirus delay production factory china Archived 2 February 2020 at the Wayback Machine China Focus Back to work enterprises gradually resume operation amid epidemic outbreak Xinhua English news cn www xinhuanet com Xinhua News Agency 10 February 2020 Archived from the original on 13 February 2020 Retrieved 13 February 2020 Alvarez Simon 17 March 2020 Tesla China shares Giga Shanghai safety measures against COVID 19 virus TESLARATI Archived from the original on 19 March 2020 Retrieved 17 March 2020 Merano Maria 5 January 2021 Tesla Gigafactory Shanghai reaches 8k week production capacity study Archived from the original on 5 January 2021 Retrieved 5 January 2021 Alvarez Simon 14 January 2021 Tesla Model 3 Right Hand Drive fleet spotted in Giga Shanghai ready for export Archived from the original on 26 January 2021 Retrieved 28 January 2021 John Darryn 21 December 2021 Giga Shanghai s November 2021 production figures indicate annualized rate of 683 000 cars Lambert Fred 8 June 2022 Tesla Gigafactory Shanghai is going out of closed loop with workers sleeping at the plant this week Electrek Retrieved 14 June 2022 China s new energy vehicles exports tripled in 2021 with half made by Tesla KrASIA 13 January 2022 Retrieved 13 January 2022 Cooke Philip January 2020 Gigafactory Logistics in Space and Time Tesla s Fourth Gigafactory and Its Rivals Sustainability 12 5 2044 doi 10 3390 su12052044 ISSN 2071 1050 External links EditTesla GigaFactory 3 Shanghai Updates Gigafactory 3 on Facebook 635670279 Gigafactory 3 outline on OpenStreetMap Retrieved from https en wikipedia org w index php title Gigafactory Shanghai amp oldid 1177057220, wikipedia, wiki, book, books, library,