fbpx
Wikipedia

Electricity sector in Argentina

The electricity sector in Argentina constitutes the third largest power market in Latin America.[citation needed] It relies mostly on thermal generation (60% of installed capacity) and hydropower generation (36%). The prevailing natural gas-fired thermal generation is at risk due to the uncertainty about future gas supply.

Electricity sector of Argentina
Data
Electricity coverage (2016)100% (total);[1] (LAC total average in 2016: 98.2%) [1]
Installed capacity (2020)41,951 MW
Share of fossil energy60.5%
Share of renewable energy33%
GHG emissions from electricity generation (2011)67.32 Mt CO2
Average electricity use (2014)3,050 kWh per capita
Distribution losses (2014)3.3%; (LAC average in 2005: 13.6%)
Consumption by sector
(% of total)
Residential41%
Industrial45%
Commercial and public sector13%
Tariffs and financing
Average residential tariff
(US$/kW·h, 2004)
0.0380; (LAC average in 2005: 0.115)
Average industrial tariff
(US$/kW·h, 2006)
0.0386 (LAC average in 2005: 0.107)
Services
Sector unbundlingYes
Share of private sector in generation75%
Share of private sector in transmission0%
Share of private sector in distribution75%
Competitive supply to large usersYes
Competitive supply to residential usersNo
Institutions
No. of service providersDominating 3 distributors:
Responsibility for transmissionTransener
Responsibility for regulationNational agency (ENRE) and provincial agencies
Responsibility for policy-settingEnergy Secretariat
Responsibility for the environmentSecretariat of Environment and Sustainable Development
Electricity sector lawYes (1991)
Renewable energy lawYes (1998, modified in 2007)
CDM transactions related to the electricity sector3 registered CDM projects; 673,650 t CO2e annual emissions reductions

Faced with rising electricity demand (over 6% annually) and declining reserve margins, the government of Argentina is in the process of commissioning large projects, both in the generation and transmission sectors. To keep up with rising demand, it is estimated that about 1,000 MW of new generation capacity are needed each year. An important number of these projects are being financed by the government through trust funds, while independent private initiative is still limited as it has not fully recovered yet from the effects of the 2002 Argentine economic crisis.

The electricity sector was unbundled in generation, transmission and distribution by the reforms carried out in the early 1990s. Generation occurs in a competitive and mostly liberalized market in which 75% of the generation capacity is owned by private utilities. In contrast, the transmission and distribution sectors are highly regulated and much less competitive than generation.

Electricity supply and demand edit

Installed capacity by source in Argentina (2020)[2]
 Fossil (oil, gas, coal): 24,549 MW (61.3%)Hydroelectric powerRenewable (wind, solar): 2,903 MW (7.3%)Nuclear: 1,755 MW (4.4%)
  •   Fossil (oil, gas, coal): 24,549 MW (61.3%)
  •   Hydro: 10,812 MW (27.0%)
  •   Renewable (wind, solar): 2,903 MW (7.3%)
  •   Nuclear: 1,755 MW (4.4%)

Generation edit

Thermal plants fueled by natural gas (CCGT) are the leading source of electricity generation in Argentina. Argentina generates electricity using thermal power plants based on fossil fuels (60%), hydroelectric plants (36%), and nuclear plants (3%), while wind and solar power accounted for less than 1%. Installed nominal capacity in 2019 was 38,922 MW.[3] However, this scenario of gas dominance is likely to undergo changes due to gas exhaustion derived from the existing "bottlenecks" in exploration and production (E+P) and pipeline capacity. Gas output dropped for the first time in 2005 (-1.4%) and gas reserves dropped to ten years of consumption by the end of 2004 (down from an average of 30 years in the 1980s).[4] Today, gas reserves are 43% lower than in 2000.[5] This situation is further aggravated by the uncertainty surrounding the gas deals with Bolivia and the plans to build new regional pipeline connections. Total generation in 2005 was 96.65 TW·h. In 2015, the Atucha II Nuclear Power Plant reached 100% power, increasing the percentage of nuclear power in Argentina from 7% to 10%.[6]

 
Argentina electricity supply by year

The generators are divided into eight regions: Cuyo (CUY), Comahue (COM), Northwest (NOA), Center (CEN), Buenos Aires/Gran Buenos Aires (GBA-BAS), Littoral (LIT), Northeast (NEA) and Patagonia (PAT).

Installed capacity in the wholesale market as of December 2020:[7]

Technology Installed
capacity (MW)
%
Thermal Combined Cycle 13,120 31.3
Gas Turbine 6,298 15.0
Steam Turbine 4,254 10.1
Diesel engine 1,693 4.0
Total Thermal 25,365 60.5
Pumped Storage 974 2.3
Nuclear 1,755 4.2
Renewable Hydropower 10,370 24.5
Onshore wind 2,623 6.3
Solar photovoltaic 759 1.8
Landfill gas 21.9 0.1
Biogases from anaerobic fermantation 28.5 0.1
Total Renewable 13,802.4 33.0
Total 41,951 100

The above table does not consider off-grid installed capacity nor distributed generation (small biogas/biomass facilities, rooftop solar panels, etc.)

While CAMESSA categorises hydropower larger than 50MW as non-renewable, the renewable classification of large hydropower is in line with international standars and how other countries classify their hydropower as renewable energy. Pumped storage is considered as non-renewable due to its consumption of electricity from the grid.

Imports and exports edit

In 2005, Argentina imported 6.38 TW·h of electricity while it exported 3.49 TW·h.[8] Net energy imports thus were about 3% of consumption.

Argentina also imports electricity from Paraguay, produced by the jointly built Yaciretá Dam. On 18 September 2006 Paraguay agreed to settling its debt of $11,000,000,000 owed to Argentina for the construction of Yaciretá by paying in electricity, at the rate of 8,000 GWh per year for 40 years.

Demand edit

Electricity demand in Argentina has steadily grown since 1991, with just a temporary decline caused by the economic crisis of 2001-2002[9] that has been followed by a quick recovery (6%-8% annual increase) in the last five years,[10] partially due to economic recovery. In 2005, the country consumed 94.3 TW·h of electricity, which corresponds to 2,368 kWh per capita. Residential consumption accounted for 29% of the total, while industrial, and commercial and public represented 43% and 26% respectively.[8]

Demand and supply projections edit

Argentina currently faces a tight supply/demand scenario as reserve margins have declined from above 30% in 2001 to less than 10%. This fact, together with the deterioration in distribution companies services (i.e. cables, transformers, etc.), has the potential to endanger supply. To sustain a 6-8% annual increase in demand, it is estimated that the system should incorporate about 1,000 MW of generation capacity each year.[11]

Transmission and distribution edit

In Argentina, there are two main wide area synchronous grids systems, SADI (Sistema Argentino de Interconexión, Argentine Interconnected System) in the North and center-South of the country, and SIP (Sistema de Interconexión Patagónico, Patagonian Interconnected System) in the South. Both systems are integrated since March 2006.[12] The electricity market in the SADI area is managed by the MEM (Mercado Eléctrico Mayorista).

Access to electricity edit

Total electricity coverage in Argentina was close to 100% of the population in 2016.[1] However, access to electricity is more deficient in certain rural areas. The Renewable Energy in the Rural Market Project (PERMER) in 2012 was one of several programs being implemented to enlarge electricity coverage in rural areas.[13] (See World Bank projects below).

Service quality edit

Interruption frequency and duration edit

Interruption frequency and duration are considerably below the averages for the LAC region. In 2002, the average number of interruptions per subscriber was 5.15, while duration of interruptions per subscriber was 5.25 hours. The weighted averages for LAC were 13 interruptions and 14 hours respectively.[14]

Distribution and transmission losses edit

Distribution losses in 2005 were 13.6%, down from 17% a decade before.[14] In 2014, losses were about 3.3%.[3]

Responsibilities in the Electricity Sector edit

Policy and regulation edit

The Energy Secretariat (SENER) is responsible for policy setting, while the National Electricity Regulator (ENRE) is the independent entity within the Energy Secretariat responsible for applying the regulatory framework established by Law 26,046 of 1991. ENRE is in charge of regulation and overall supervision of the sector under federal control. Provincial regulators regulate the rest of the utilities. ENRE and the provincial regulators set tariffs and supervise compliance of regulated transmission and distribution entities with safety, quality, technical and environmental standards. CAMMESA (Compañía Administradora del Mercado Mayorista Eléctrico) is the administrator of the wholesale electricity market. Its main functions include the operation and dispatch of generation and price calculation in the spot market, the real-time operation of the electricity system and the administration of the commercial transactions in the electricity market.[10]

The Electric Power Federal Council (CFEE), created in 1960, plays a very important role in the sector as well. It is the administrator of funds that specifically target electricity operations (i.e. National Fund for Electric Power, see Recent developments below) and is also an adviser to the National and the Provincial Governments in issues relating to the power industry, public and private energy services, priorities in the execution of new projects and studies, concessions and authorizations, and electricity tariffs and prices. It is also an adviser for legislative modifications in the power industry.[15]

The Argentine power sector is one of the most competitive and deregulated in South America. However, the fact that the Energy Secretariat has veto power over CAMMESA has the potential to alter the functioning of the competitive market. The functions of generation, transmission, and distribution are open to the private sector, but there are restrictions on cross-ownership between these three functions. Argentine law guarantees access to the grid in order to create a competitive environment and to allow generators to serve customers anywhere in the country.[9]

Generation edit

Private and state-owned companies carry out generation in a competitive, mostly liberalized electricity market, with 75% of total installed capacity in private hands. The share in public hands corresponds to nuclear generation and to the two bi-national hydropower plants: Yacyretá (Argentina-Paraguay) and Salto Grande (Argentina-Uruguay). The generation sector is highly fragmented with more than ten large companies, all of them providing less than 15% of the system's total capacity.[8] Power generators sell their electricity in the wholesale market operated by the CAMMESA.[9]

Transmission and distribution edit

The transmission and distribution sectors are highly regulated and less competitive than generation. In transmission, the Compañía Nacional de Transporte Energético en Alta Tension (Transener) operates the national electricity transmission grid under a long-term agreement with the Argentine government. In the distribution sector, three private companies, Edenor (Empresa Distribuidora y Comercializadora Norte), Edesur (Electricidad Distribuidora Sur) and Edelap (Empresa de Electricidad de la Plata), dominate a market with 75% control by private firms.[9]

Other important distribution companies at the provincial level are:

  • Public provincial: EPEC (Empresa Provincial de Energía de Córdoba), EPESFI (Empresa Provincial de Energía de Santa Fé)
  • Private provincial: ESJ ( Energía San Juan), EDET (Empresa de Distribución Eléctrica de Tucumán): EDEN (Empresa Distribuidora de Energía Norte), EDEA (Empresa Distribuidora de Energía Atlántica), EDES (Empresa Distribuidora de Energía Sur)

Renewable energy resources edit

 
Argentina renewable electricity production by year

The National Promotion Direction (DNPROM) within the Energy Secretariat (SENER) is responsible for the design of programs and actions conducive to the development of renewable energies (through the ) and energy efficiency (through the ) initiatives.[9] Complementarily, the Secretariat for the Environment and Natural Resources (SEMARNAT) is responsible for environmental policy and the preservation of renewable and non-renewable resources.[12]

The most important legal instruments for the promotion of renewable energy are Law 25,019 from 1998 and Law 26,190 from 2007. The 1998 law, known as the "National Wind and Solar Energy Rules", declared wind and solar generation of national interest and introduced a mechanism that established an additional payment per generated kWh which, in 1998, meant a 40% premium over market price. It also granted certain tax exemptions for a period of 15 years from the law's promulgation.[10] The 2007 Law complemented the previous one, declaring of national interest the generation of electricity from any renewable source intended to deliver a public service. This law also set an 8% target for renewable energy consumption in the period of 10 years and mandated the creation of a trust fund whose resources will be allocated to pay a premium for electricity produced from renewable sources.

Hydropower edit

At the end of 2021 Argentina was the 21st country in the world in terms of installed hydroelectric power (11.3 GW). [16]

Argentina's hydroelectric potential is being exploited only partially. While the identified potential is 170,000 GW·h/year, in 2006 hydroelectric production amounted just to 42,360 GW·h.[12] There are also untapped mini-hydropower resources, whose potential is estimated at 1.81% of overall electricity production (in contrast with its current 0.88%).[17]

(For a comprehensive list of plants see Hydroelectric power stations in Argentina.)

Wind edit

At the end of 2021 Argentina was the 26th country in the world in terms of installed wind energy (3.2 GW). [18]

As of 2020 Argentina had an installed wind energy capacity of 1.6 GW, with 931 MW installed in 2019 alone.[19] Electricity production from onshore wind power in Argentina has increased from 1.41 TWh in 2018 to 9.42 TWh in 2020.[20]

The technical potential for offshore wind in Argentina has been estimated to amount to 2.5 TW, but no offshore turbines have been built so far.[21]

The Argentine Patagonia region has a very large wind potential. The Chubut Wind Power Regional Center (CREE) estimated the theoretical potential for the region at 500 GW of electricity generation. However, this large potential is still largely unexploited. One of the reasons for this underdevelopment is that existing tariffs and incentives do not make wind power development attractive enough yet. However, the main deterrent to wind power development in the region has been the lack of transmission lines that connect the Patagonia region with the National Interconnected System.[22] The completion of the Choele-Choel-Puerto Madryn high voltage line, the first section of Línea Patagónica under the framework of the Plan Federal de Transporte de Energía Eléctrica, eliminated this bottleneck in March 2006.[23]

Nevertheless, wind power has increased significantly in Argentina during the last decade. Total operating wind power capacity in 2005 was 26.6 MW, shared by 13 plants. This is still only about 0.05% of the theoretical potential of wind energy in Argentina. In 2007, the distribution of number plants and total capacity was:[17]

Of the 13 plants, only three have been commissioned after the year 2000, with the remaining 10 built during the 1990s.[17]

(See for Argentina).

Solar edit

At the end of 2021 Argentina was the 43rd country in the world in terms of installed solar energy (1.0 GW). [24]

Solar power is only present in remote areas. Just 81 MW·h were generated in 2005, less than 0.1% of total electricity production.[25] In 2012 the first of four 5 MW stages of Cañada Honda was completed, as part of a plan to install 117 MW of renewable energy.[26]

History of the electricity sector edit

The reforms of 1991/92 edit

Prior to 1991, the electricity sector in Argentina was vertically integrated. The sector experienced a serious crisis in the summers of 1988/1989, primarily due to the lack of maintenance of the country's thermal power plants (50% were unavailable).[27] Shortly after the crisis, the government of Carlos Menem introduced a new legal framework for the electricity sector through Law 24,065, which included the following elements: vertical and horizontal unbundling of generation, transmission and distribution; opening up of all segments to the private sector; and separation of the regulatory function from policy setting. As a result of the new law, there was substantial private investment which, together with the public power plants that started production in the 1990s, transformed a situation of power shortage and low quality into one of abundance and reliability at lower prices.[28]

ENRE (Electricity National Regulatory Entity) was created in 1992. The Wholesale Electricity Market (MEM), which covers up to 93% of total demand corresponding to the Argentine Interconnected System (SADI), was also created in 1992. The remaining 7% share of the demand corresponds to Patagonia, which had its own interconnected market, the Patagonian Wholesale Electricity Market MEMSP), now interconnected with the MEM. CAMMESA (Wholesale Electricity Market Administration Company) was also created that year and assigned the responsibilities of coordinating dispatch operations, setting wholesale prices and administrating economic transactions performed through the Argentine Interconnected System.[27]

The reforms implemented in the 1990s led to high investment, which allowed for a 75% increase in generation capacity, resulting in the decrease of prices in the wholesale market from US$40/MW·h in 1992 to US$23/MW·h in 2001. However, the reforms failed to deliver the necessary increase in transmission capacity. Only one relevant project, the addition of the 1,300 km high voltage line between Comahue and Buenos Aires, was built in the 1990s. Distribution networks were also renovated and expanded, which resulted in efficiency and quality improvements.[29]

Tariff freeze edit

As a response to the 2001 economic crisis, electricity tariffs were converted to the Argentine peso and frozen in January 2002 through the Public Emergency and Exchange Regime Law. Together with high inflation (see Economy of Argentina) and the devaluation of the peso, many companies in the sector had to deal with high levels of debt in foreign currency under a scenario in which their revenues remained stable while their costs increased. This situation has led to severe underinvestment and unavailability to keep up with an increasing demand, factors that contributed to the 2003-2004 energy crisis.[29] Since 2003, the government has been in the process of introducing modifications that allow for tariff increases. Industrial and commercial consumers' tariffs have already been raised (near 100% in nominal terms and 50% in real terms), but residential tariffs still remain the same.

Creation of Enarsa edit

In 2004, President Néstor Kirchner created Energía Argentina Sociedad Anónima (Enarsa), a company managed by the national state of Argentina for the exploitation and commercialization of petroleum and natural gas, but also the generation, transmission and trade of electricity. Through the creation of Enarsa, the state will regain a relevant place in the energy market that was largely privatized during the 1990s.

Energy Plus and Gas Plus programs edit

In September 2006, SENER launched the Energy Plus (Energía Plus) program with the objective of increasing generation capacity and meeting the rising demand for electricity. The program applies for consumption levels above those for 2005. CAMMESA requires all large users (above 300 kW) to contract the difference between their current demand and their demand in the year 2005 in the Energy Plus market. In this new de-regulated market, only energy produced from new generation plants will be traded. The aim of the program is twofold. In one hand, it seeks to guarantee supply to residential consumers, public entities, and small and medium enterprises. On the other hand, it aims at encouraging self-generation by the industrial sector and electricity cogeneration.[28]

In March 2008, the government approved Resolution 24/2008, which created a new natural gas market called "Gas Plus" to encourage private investment in natural gas exploration and production. The Gas Plus regime applies to new discoveries and to "tight gas" fields. The price of the new gas, whose commercialization will be restricted to the domestic market, will not be subject to the conditions established in the "Agreement with Natural Gas Producers 2007-2011" but will be based on costs and a reasonable profit. Experts believe that, if the Gas Plus regime is successful, it could stimulate new investments in electricity generation plants under the Energy Plus regime as it could ensure fuel supply to the new plants.[30]

The National Program for the Rational and Efficient Use of Energy (PRONUREE) edit

In December 2007, the government launched the National Program for the Rational and Efficient Use of Energy (PRONUREE, Decree 140/2007). This decree declared the rational and efficient use of energy to be in the national interest and is also part of the energy sector strategy to counter supply/demand imbalance. The PRONUREE, under the responsibility of the Secretariat of Energy, aims to be a vehicle for improving energy efficiency in the energy-consuming sectors and acknowledges that energy efficiency needs to be promoted with a long-term commitment and vision. It also acknowledges the connection between energy efficiency and sustainable development, including the reduction of greenhouse gas emissions. The program also recognizes the need for individual behavioral changes to be promoted with an educational strategy, with the public sector setting the example by assuming a leadership role in the implementation of energy conservation measures in its facilities.[31]

The PRONUREE includes short- and long-term measures aimed at improving the energy efficiency in the industrial, commercial, transport, residential and service sectors and public buildings. It also supports educational programs on energy efficiency, enhanced regulations to expand cogeneration activities; labeling of equipment and appliances that use energy; improvements to the energy efficiency regulations; and broader utilization of the Clean Development Mechanism (CDM) to support the development of energy efficiency projects.[31] The objective of the program is to reduce electricity consumption by 6%.[32]

One of the first activities defined under PRONUREE is the national program to phase out incandescent bulbs by 2011 in Argentina. The program, financed by the government, aims to replace incandescent bulbs with energy efficient compact fluorescent lamps (CFLs) in all households connected to the electricity grid and selected public buildings. The program, which has initially undergone a pilot phase and expects to replace 5 million incandescent lamps in the next six months,[33] foresees the distribution of 25 million lamps overall.[34] Staff from the distribution companies will visit each household to replace the incandescent lamps and to inform residential users on the advantages of replacing the bulbs and of the efficient use of energy in general.[33]

Recent tariff increases, 2008 edit

In Argentina, retail tariffs for the distribution utilities in the Metropolitan Area of Buenos Aires and La Plata city (i.e. Edenor, Edesur and Edelap) are regulated by the national regulatory agency (ENRE) while provincial utilities are regulated by local regulators. While the utilities under ENRE's jurisdiction had not been allowed to raise residential tariffs since they were frozen in 2002 as a result of the Emergency and Exchange Regime Law, some provincial regulators had recently approved additional charges to residential tariffs. In particular, the Public Service Regulatory Agency in the Province of Córdoba (ERSeP) agreed in February 2008[35] to a 17.4% additional charge to residential customers. Likewise, Santa Fé approved increases between 10% and 20%;[36] Mendoza between 0 and 5% below 300 kWh and between 10% and 27% above 300 kWh;[37][38] Jujuy between 22% and 29% and Tucumán between 10% and 24%.[39] Other provinces (i.e. San Juan, Chaco, Formosa, Corrientes, La Pampa, Neuqen, Río Negro and Entre Ríos) are expected to raise tariffs in the near future.[39]

Recently, in August 2008, after a 7-year tariff freeze, residential electricity tariffs in the Buenos Aires metropolitan area (served by the Edenor, Edesur and Edelap utilities) have been increased by 10-30% for households that consume more than 650 kWh every two months. For consumption between 651 kWh and 800 kWh, the increase will be 10%; on the other end, for users over 1,201 kWh, the increase amounts to 30%. The increase impacts around 24% of all Edenor, Edesur and Edelap customers (1,600,000 households). For commercial and industrial users the increase will be 10%.[40]

At the end of August 2008, ENRE also approved increases in transmission tariffs in the 17%-47% range.[41] The increase granted by ENRE was below the increase determined by the Energy Secretariat for some transmission companies (e.g. Transener, Transba, Distrocuyo and Transnoa. Some of them (i.e. Transener, Transba), will most likely challenge ENRE's decision.[42] An overall tariff revision is still pending and has been put off until February 2009.[43]

Tariffs, cost recovery and subsidies edit

Tariffs edit

Electricity tariffs in Argentina are well below the LAC average. In 2004, the average residential tariff was US$0.0380 per kWh, very similar to the average industrial tariff, which was US$0.0386 per kWh in 2003. Weighted averages for LAC were US$0.115 per kWh for residential consumers and US$0.107 per kWh for industrial customers.[14] (See History of the electricity sector for more information on the evolution of tariffs).

Subsidies edit

See Fund for the Electric Development of the Interior (FEDEI) below.

Investment and financing edit

In 1991, the Government of Argentina created the National Fund for Electric Power (FNEE, Fondo Nacional de la Energía Eléctrica), to be funded by a share of the petrol tax and a surcharge on sales from the wholesale market. This Fund, which is administered by CFEE (Electric Power Federal Council), provides funding to the following other funds at the shares indicated:[44]

  • 47.4%: Subsidiary Fund for Regional Tariff Compensation to Final Users (FCT), for homogenization of tariffs across the country (this created a de facto subsidy for those consumers in the areas with higher electricity costs)
  • 31.6%: Fund for the Electric Development of the Interior (FEDEI), for generation, transmission and rural and urban distribution works. Most funds have been directed to rural electrification
  • 19.75%: Fiduciary Fund for Federal Electricity Transmission(FFTEF) (created in 2000), for co-financing or projects in electricity transmission.
  • 1.26%: Wind Energy Fund (created in 2002), for the development of wind energy,

In addition, CAMMESA, the administrator of the wholesale electricity market, had projected that by 2007 the country's energy demand would require an additional capacity of 1,600 MW. Faced with the need for specific investments but also with a lack of private investment, the Energy Secretariat (SENER) enacted Resolutions 712 and 826 in 2004, which created FONINVEMEM, the Fund for the Investment Needed to Increase the Supply of Electricity in the Wholesale Market. The Fund, which sought to encourage participation from creditors of the wholesale market, invited those creditors, mainly generation companies, to participate with their credit in the creation of the Fund itself.[45]

Ongoing projects edit

There are several projects that are part of the government's response to the predicted electricity shortages. If all those plans are completed as expected, the capacity requirements for the next few years will be met.

Thermal power edit

Two new CCGT plants, the José de San Martín Thermoelectric and Manuel Belgrano Thermoelectric, of 830 MW each, are under construction and expected to start full operations at the beginning of 2009. Endesa, Total S.A., AES Corporation, Petrobras, EDF and Duke Energy are the main shareholders in the plants. Both plants, which have been financed through the FONINVEMEM (total investment amounts up to US$1,097 million), are expected to start full operations at the beginning of 2009.[46]

In addition, the Planning Ministry announced in July 2007 the commissioning of five new thermal plants with a total capacity of 1.6 GW and an overall investment of US$3,250 million. These dual-generation turbine (gas or fuel oil) plants, which are expected to start operations in 2008, will be located in Ensenada (540 MW), Necochea (270 MW), Campana (540 MW), Santa Fe (125 MW) and Córdoba (125 MW).[47] Finally, Enarsa has recently launched bidding for eleven small and transportable generation units (15-30 MW each) and for other three larger generation units (50-100 MW) to be installed on barges. These new units, whose base price is still unknown, will add between 400 and 500 MW of new generation capacity.[48]

Nuclear power edit

In 2006, the Argentine government launched a plan to boost nuclear energy. The Atucha II nuclear power plant, whose construction started in 1981, was to be completed and to add 750 MW of generation capacity by 2010. The plant started producing power in June 2014. In addition, the Embalse nuclear power plant, with 648 MW of generation capacity, was to be refurbished to extend its operational life beyond 2011.[49]

Hydropower edit

 
The Yacyretá dam. It is planned to increase its height to increase the electricity generation capacity in Argentina and Paraguay.

On the hydropower side, the Yacyretá dam's reservoir was elevated by 7 m to the height of 83 m as contemplated in its original design, which increased its capacity from 1,700 to 3,100 MW. This will lead to a 60% increase in its electricity output (from 11,450 GW·h to 18,500 GW·h).[10] The reservoir rise was complete in February 2011 despite a serious controversy regarding the resettlement of people.[50][51][52] Additionally, in 2006, bidding for the expansion of Yacyretá with the construction of a new 3-turbine plant in the Añá Cuá arm of the Paraná River was announced by the Government. This expansion, to be finalized in 2010, would add 300 MW of new generation capacity.[53]

Transmission edit

In regard to transmission, the Federal Plan for Transport of Electric Energy at 500 kV is under implementation under the umbrella of the FFTEF (Fondo Fiduciario para el Transporte Eléctrico Federal).[10] The main lines of the plan (Línea Patagónica, Línea Minera, Yacyretá, Puerto Madryn – Pico Truncado, NEA-NOA, Comahue – Cuyo, Pico Truncado – Río Turbio – Río Gallegos) are already built or currently under construction. The lines built between 2007 and 2009 will add 4,813 new kilometers of high voltage transmission capacity.[23][54]

In addition, the Federal Plan for Transport of Electric Energy II, defined in 2003 and updated in 2006, has the objective of addressing the constraints faced by the regional transmission networks in the period up to 2010. This complementary plan has prioritized the necessary works according to their ability to address short-term demand issues. 109 of the 240 works identified in 2003 were considered of high priority and have already been completed or are under execution. Initially, investment for high priority works was estimated at US$376 million, while estimated investment for the rest of the works totaled US$882.2 million. However, this budget is under revision due to the increasing costs of materials such as steel and aluminum and of labor.[10]

Summary of private participation in the electricity sector edit

Prior to 1991, the electricity sector in Argentina was vertically integrated. The new legal framework for the electricity sector included: vertical and horizontal unbundling of generation, transmission and distribution; opening up of all segments to the private sector; and separation of the regulatory function from policy setting.

Currently, private and state-owned companies carry out generation in a completive, mostly liberalized electricity market, with 75% of total installed capacity in private hands. The publicly owned share corresponds to nuclear generation and to the two bi-national hydropower plants: Yacyretá (Argentina-Paraguay) and Salto Grande (Argentina-Uruguay). On the other hand, the transmission and distribution sectors are highly regulated and less competitive than generation. In transmission, the Compañía Nacional de Transporte Energético en Alta Tension (Transener) operates the national electricity transmission grid, while in the distribution sector, three private companies, Edenor (Empresa Distribuidora y Comercializadora Norte), Edesur (Electricidad Distribuidora Sur) and Edelap (Empresa de Electricidad de la Plata), dominate a market with 75% control by private firms.

Activity Private participation (%)
Generation 75% of installed capacity
Transmission 100%
Distribution 75% of clients

Electricity and the Environment edit

Responsibility for the environment edit

The holds responsibility for the environment in Argentina.

Greenhouse gas emissions edit

OLADE (Organización Latinoamericana de Energía) estimated that CO2 emissions from electricity production in 2003 were 20.5 million tons of CO2, which represents 17% of total emissions for the energy sector.[55] In 2011, according to the International Energy Agency, the actual CO2 emissions from electricity generation were 67.32 million metric tons, a share of 36.7% of the countries' total CO2 emissions from fuel combustion.[56]

CDM projects in electricity edit

As of August 2007, there are only three energy-related registered CDM projects in Argentina, with expected total emissions reductions of 673,650 tons of CO2e per year.[57] Of the three projects, only one is large-scale: the 10.56 MW Antonio Morán wind power plant in the Patagonia region. Production of electricity from biomass waste in the Aceitera General Deheza and methane recovery and electricity generation from the Norte III-B landfill are the two small-scale existing projects.

External assistance edit

World Bank edit

The only active energy project financed by the World Bank in Argentina is the Renewable Energy in the Rural Market Project (PERMER). This project has the objective of guaranteeing access to electricity to 1.8 million people (314,000 households) and to 6,000 public services (schools, hospitals, etc.) located far from electricity distribution centers. Electrification of this dispersed market will be mostly carried out through the installation of solar photovoltaic systems, but also through other technologies such as micro-hydraulic turbines, wind and, eventually, diesel generators.[13] The project, which started in 1999 and is expected to end in December 2008, has received a US$10 million grant from GEF and a US$30 million loan from the World Bank.[58] The Argentine Energy Secretariat has recently presented an Energy Efficiency project to the GEF. The objective of the project is to improve energy use, reducing its costs to consumers and contributing to the sustainability of the energy sector in the long term. A reduction in greenhouse gas emissions is also sought.[59]

Inter-American Development Bank edit

In November 2006, the Inter-American Development Bank approved a $580 million loan for the construction of a new 760-mile transmission line in northern Argentina that will connect separate grids in the northeastern and northwestern parts of the country, the Norte Grande Electricity Transmission Program.

Andean Development Corporation (CAF) edit

In 2006, Argentina received financing from CAF (Andean Development Corporation) for two electricity projects: the Electricity Interconection Comahue-Cuyo (US$200 million) and the Electricity Interconnection Rincón Santa María-Rodríguez (US$300 million), two of the high voltage transmission lines included in the Federal Transportation Plan.[60] In the same year, Argentina also borrowed US$210 million from CAF for a program that aims at repairing the country's hydroelectric infrastructure.

In June 2007, CAF approved a US$45 million loan to the Buenos Aires province for partial financing of the electricity transport capacity in the North of the province.[61]

Sources edit

  • Cámara Argentina de la Construcción, 2006. La construcción como herramienta del crecimiento continuado. Sector eléctrico. Evaluación de las inversiones necesarias para el sector eléctrico nacional en el mediano plazo. Consultor: Dr. Ing. Alberto del Rosso.
  • Coordinación de Energías Renovables, 2006.
  • Oxford Analytica, 2006. Argentina: Energy issues threaten sustained growth
  • Secretaria de Energía, 2006. .
  • Secretaría de Energía, 2007.

See also edit

Notes edit

  1. ^ a b c "World Bank: Access to Electricity (% of total population)". World Bank.
  2. ^ Potencia Instalada Energía Eléctrica
  3. ^ a b "Monthly Report - Main variables of the month - April 2019" (PDF). CAMMESA. p. 11.
  4. ^ Oxford Analytica 2006
  5. ^ Econométrica
  6. ^ "Atucha 2 reaches 100% rated power - World Nuclear News".
  7. ^ "www.cammesa.com". www.cammesa.com. Retrieved 18 February 2021.
  8. ^ a b c Secretaría de Energía 2006
  9. ^ a b c d e . Archived from the original on 26 August 2007. Retrieved 24 September 2007.
  10. ^ a b c d e f Cámara Argentina de la Construcción 2006
  11. ^ El País
  12. ^ a b c Coordinación de Energías Renovables 2006
  13. ^ a b . Archived from the original on 30 November 2012. Retrieved 30 November 2012.
  14. ^ a b c Benchmarking data of the electricity distribution sector in Latin America and Caribbean Region 1995-2005
  15. ^ . Archived from the original on 12 October 2007. Retrieved 28 September 2007.
  16. ^ "RENEWABLE CAPACITY STATISTICS 2022" (PDF). IRENA. Retrieved 19 May 2022.
  17. ^ a b c Coordinación de Energías Renovables 29 July 2007 at the Wayback Machine
  18. ^ "RENEWABLE CAPACITY STATISTICS 2022" (PDF). IRENA. Retrieved 19 May 2022.
  19. ^ "Renewable Energy for Argentina | ABO Wind".
  20. ^ "'Dark horse Argentina could challenge Brazil in South America's offshore wind race' | Recharge". 7 September 2021.
  21. ^ "'Dark horse Argentina could challenge Brazil in South America's offshore wind race' | Recharge". 7 September 2021.
  22. ^ Instituto Nacional de Tecnología Industrial
  23. ^ a b Public works news
  24. ^ "RENEWABLE CAPACITY STATISTICS 2022" (PDF). IRENA. Retrieved 19 May 2022.
  25. ^ SENER 2007
  26. ^ Parque Solar Fotovoltaico Cañada Honda
  27. ^ a b La Energía Eléctrica en la República Argentina
  28. ^ a b ENRE
  29. ^ a b (PDF). Archived from the original (PDF) on 3 March 2016. Retrieved 27 April 2019.
  30. ^ Resolution 24/2008 Secretariat of Energy
  31. ^ a b Decree 140/2007
  32. ^ La Nación 5 January 2008
  33. ^ a b La Nación 4 March 2008
  34. ^ La Nación 15 March 2008
  35. ^ (PDF). Archived from the original (PDF) on 19 February 2009. Retrieved 18 April 2008.
  36. ^ . Archived from the original on 26 June 2008. Retrieved 18 April 2008.
  37. ^ . Archived from the original on 10 July 2011. Retrieved 18 April 2008.
  38. ^ . Archived from the original on 29 July 2007. Retrieved 18 April 2008.
  39. ^ a b Urgente 24
  40. ^ Resolution ENRE 356/08
  41. ^ Resolutions ENRE 327, 328/08
  42. ^ Diario Clarín,16th Aug 2008
  43. ^ Resolutions Energy Secretariat 864, 865, 866/08
  44. ^ Electric Power Federal Council (CFEE)[permanent dead link]
  45. ^ Cámara de Diputados
  46. ^ . Archived from the original on 14 December 2007. Retrieved 24 September 2007.
  47. ^ . Archived from the original on 7 July 2011. Retrieved 24 September 2007.
  48. ^
  49. ^ . Archived from the original on 17 November 2007. Retrieved 24 September 2007.
  50. ^ Kerr, Juliette (25 February 2011). . Global Insight. Archived from the original on 13 March 2012. Retrieved 3 March 2011.
  51. ^ Udall, Lori. (PDF). World Commission on Dams. Archived from the original (PDF) on 13 June 2010. Retrieved 3 March 2011.
  52. ^ "Argentina, Paraguay celebrate Yacyreta dam completion" ((Google cache)). ADPnews. 28 February 2011. Retrieved 3 March 2011.[permanent dead link]
  53. ^ Na Nación
  54. ^ . Archived from the original on 7 February 2007. Retrieved 24 September 2007.
  55. ^ OLADE 28 September 2007 at the Wayback Machine
  56. ^ "Argentina - CO2 emissions". index mundi. Retrieved 20 April 2016.
  57. ^ UNFCCC
  58. ^ World Bank
  59. ^ . Archived from the original on 29 July 2007. Retrieved 24 September 2007.
  60. ^ CAF(a)
  61. ^ . Archived from the original on 2 October 2007. Retrieved 24 September 2007.

External links edit

Public entities edit

  • Electric Power Federal Council (CFEE)
  • Administrator of the Wholesale Electricity Market (CAMMESA)
  • National Electricity Regulator (ENRE)

Electricity distributors edit

  • Edenor
  • Edesur
  • Edelap
  • Federación Argentina de Cooperativas de Electricidad y Otros Servicios Públicos Limitada

External partners edit

  • List of World Bank projects in Argentina

Other edit

  • La Energía Eléctrica en la República Argentina
  • Early History of the electricity sector in Argentina
  • (in Spanish)

electricity, sector, argentina, this, article, require, cleanup, meet, wikipedia, quality, standards, specific, problem, inline, external, links, please, help, improve, this, article, june, 2019, learn, when, remove, this, template, message, electricity, secto. This article may require cleanup to meet Wikipedia s quality standards The specific problem is inline external links Please help improve this article if you can June 2019 Learn how and when to remove this template message The electricity sector in Argentina constitutes the third largest power market in Latin America citation needed It relies mostly on thermal generation 60 of installed capacity and hydropower generation 36 The prevailing natural gas fired thermal generation is at risk due to the uncertainty about future gas supply Electricity sector of ArgentinaDataElectricity coverage 2016 100 total 1 LAC total average in 2016 98 2 1 Installed capacity 2020 41 951 MWShare of fossil energy60 5 Share of renewable energy33 GHG emissions from electricity generation 2011 67 32 Mt CO2Average electricity use 2014 3 050 kWh per capitaDistribution losses 2014 3 3 LAC average in 2005 13 6 Consumption by sector of total Residential41 Industrial45 Commercial and public sector13 Tariffs and financingAverage residential tariff US kW h 2004 0 0380 LAC average in 2005 0 115 Average industrial tariff US kW h 2006 0 0386 LAC average in 2005 0 107 ServicesSector unbundlingYesShare of private sector in generation75 Share of private sector in transmission0 Share of private sector in distribution75 Competitive supply to large usersYesCompetitive supply to residential usersNoInstitutionsNo of service providersDominating 3 distributors EdenorEdesurEdelapResponsibility for transmissionTransenerResponsibility for regulationNational agency ENRE and provincial agenciesResponsibility for policy settingEnergy SecretariatResponsibility for the environmentSecretariat of Environment and Sustainable DevelopmentElectricity sector lawYes 1991 Renewable energy lawYes 1998 modified in 2007 CDM transactions related to the electricity sector3 registered CDM projects 673 650 t CO2e annual emissions reductionsFaced with rising electricity demand over 6 annually and declining reserve margins the government of Argentina is in the process of commissioning large projects both in the generation and transmission sectors To keep up with rising demand it is estimated that about 1 000 MW of new generation capacity are needed each year An important number of these projects are being financed by the government through trust funds while independent private initiative is still limited as it has not fully recovered yet from the effects of the 2002 Argentine economic crisis The electricity sector was unbundled in generation transmission and distribution by the reforms carried out in the early 1990s Generation occurs in a competitive and mostly liberalized market in which 75 of the generation capacity is owned by private utilities In contrast the transmission and distribution sectors are highly regulated and much less competitive than generation Contents 1 Electricity supply and demand 1 1 Generation 1 2 Imports and exports 1 3 Demand 1 4 Demand and supply projections 2 Transmission and distribution 3 Access to electricity 4 Service quality 4 1 Interruption frequency and duration 4 2 Distribution and transmission losses 5 Responsibilities in the Electricity Sector 5 1 Policy and regulation 5 2 Generation 5 3 Transmission and distribution 6 Renewable energy resources 6 1 Hydropower 6 2 Wind 6 3 Solar 7 History of the electricity sector 7 1 The reforms of 1991 92 7 2 Tariff freeze 7 3 Creation of Enarsa 7 4 Energy Plus and Gas Plus programs 7 5 The National Program for the Rational and Efficient Use of Energy PRONUREE 7 6 Recent tariff increases 2008 8 Tariffs cost recovery and subsidies 8 1 Tariffs 8 2 Subsidies 9 Investment and financing 9 1 Ongoing projects 9 1 1 Thermal power 9 1 2 Nuclear power 9 1 3 Hydropower 9 1 4 Transmission 10 Summary of private participation in the electricity sector 11 Electricity and the Environment 11 1 Responsibility for the environment 11 2 Greenhouse gas emissions 11 3 CDM projects in electricity 12 External assistance 12 1 World Bank 12 2 Inter American Development Bank 12 3 Andean Development Corporation CAF 13 Sources 14 See also 15 Notes 16 External links 16 1 Public entities 16 2 Electricity distributors 16 3 External partners 16 4 OtherElectricity supply and demand editInstalled capacity by source in Argentina 2020 2 nbsp Fossil oil gas coal 24 549 MW 61 3 Hydro 10 812 MW 27 0 Renewable wind solar 2 903 MW 7 3 Nuclear 1 755 MW 4 4 Generation edit See also Category Hydroelectric power stations in Argentina Category Nuclear power stations in Argentina and List of power stations in ArgentinaThermal plants fueled by natural gas CCGT are the leading source of electricity generation in Argentina Argentina generates electricity using thermal power plants based on fossil fuels 60 hydroelectric plants 36 and nuclear plants 3 while wind and solar power accounted for less than 1 Installed nominal capacity in 2019 was 38 922 MW 3 However this scenario of gas dominance is likely to undergo changes due to gas exhaustion derived from the existing bottlenecks in exploration and production E P and pipeline capacity Gas output dropped for the first time in 2005 1 4 and gas reserves dropped to ten years of consumption by the end of 2004 down from an average of 30 years in the 1980s 4 Today gas reserves are 43 lower than in 2000 5 This situation is further aggravated by the uncertainty surrounding the gas deals with Bolivia and the plans to build new regional pipeline connections Total generation in 2005 was 96 65 TW h In 2015 the Atucha II Nuclear Power Plant reached 100 power increasing the percentage of nuclear power in Argentina from 7 to 10 6 nbsp Argentina electricity supply by yearThe generators are divided into eight regions Cuyo CUY Comahue COM Northwest NOA Center CEN Buenos Aires Gran Buenos Aires GBA BAS Littoral LIT Northeast NEA and Patagonia PAT Installed capacity in the wholesale market as of December 2020 7 Technology Installedcapacity MW Thermal Combined Cycle 13 120 31 3Gas Turbine 6 298 15 0Steam Turbine 4 254 10 1Diesel engine 1 693 4 0Total Thermal 25 365 60 5Pumped Storage 974 2 3Nuclear 1 755 4 2Renewable Hydropower 10 370 24 5Onshore wind 2 623 6 3Solar photovoltaic 759 1 8Landfill gas 21 9 0 1Biogases from anaerobic fermantation 28 5 0 1Total Renewable 13 802 4 33 0Total 41 951 100The above table does not consider off grid installed capacity nor distributed generation small biogas biomass facilities rooftop solar panels etc While CAMESSA categorises hydropower larger than 50MW as non renewable the renewable classification of large hydropower is in line with international standars and how other countries classify their hydropower as renewable energy Pumped storage is considered as non renewable due to its consumption of electricity from the grid Imports and exports edit In 2005 Argentina imported 6 38 TW h of electricity while it exported 3 49 TW h 8 Net energy imports thus were about 3 of consumption Argentina also imports electricity from Paraguay produced by the jointly built Yacireta Dam On 18 September 2006 Paraguay agreed to settling its debt of 11 000 000 000 owed to Argentina for the construction of Yacireta by paying in electricity at the rate of 8 000 GWh per year for 40 years Demand edit Electricity demand in Argentina has steadily grown since 1991 with just a temporary decline caused by the economic crisis of 2001 2002 9 that has been followed by a quick recovery 6 8 annual increase in the last five years 10 partially due to economic recovery In 2005 the country consumed 94 3 TW h of electricity which corresponds to 2 368 kWh per capita Residential consumption accounted for 29 of the total while industrial and commercial and public represented 43 and 26 respectively 8 Demand and supply projections edit Argentina currently faces a tight supply demand scenario as reserve margins have declined from above 30 in 2001 to less than 10 This fact together with the deterioration in distribution companies services i e cables transformers etc has the potential to endanger supply To sustain a 6 8 annual increase in demand it is estimated that the system should incorporate about 1 000 MW of generation capacity each year 11 Transmission and distribution editMain article Argentine Interconnection System In Argentina there are two main wide area synchronous grids systems SADI Sistema Argentino de Interconexion Argentine Interconnected System in the North and center South of the country and SIP Sistema de Interconexion Patagonico Patagonian Interconnected System in the South Both systems are integrated since March 2006 12 The electricity market in the SADI area is managed by the MEM Mercado Electrico Mayorista Access to electricity editTotal electricity coverage in Argentina was close to 100 of the population in 2016 1 However access to electricity is more deficient in certain rural areas The Renewable Energy in the Rural Market Project PERMER in 2012 was one of several programs being implemented to enlarge electricity coverage in rural areas 13 See World Bank projects below Service quality editInterruption frequency and duration edit Interruption frequency and duration are considerably below the averages for the LAC region In 2002 the average number of interruptions per subscriber was 5 15 while duration of interruptions per subscriber was 5 25 hours The weighted averages for LAC were 13 interruptions and 14 hours respectively 14 Distribution and transmission losses edit Distribution losses in 2005 were 13 6 down from 17 a decade before 14 In 2014 losses were about 3 3 3 Responsibilities in the Electricity Sector editPolicy and regulation edit The Energy Secretariat SENER is responsible for policy setting while the National Electricity Regulator ENRE is the independent entity within the Energy Secretariat responsible for applying the regulatory framework established by Law 26 046 of 1991 ENRE is in charge of regulation and overall supervision of the sector under federal control Provincial regulators regulate the rest of the utilities ENRE and the provincial regulators set tariffs and supervise compliance of regulated transmission and distribution entities with safety quality technical and environmental standards CAMMESA Compania Administradora del Mercado Mayorista Electrico is the administrator of the wholesale electricity market Its main functions include the operation and dispatch of generation and price calculation in the spot market the real time operation of the electricity system and the administration of the commercial transactions in the electricity market 10 The Electric Power Federal Council CFEE created in 1960 plays a very important role in the sector as well It is the administrator of funds that specifically target electricity operations i e National Fund for Electric Power see Recent developments below and is also an adviser to the National and the Provincial Governments in issues relating to the power industry public and private energy services priorities in the execution of new projects and studies concessions and authorizations and electricity tariffs and prices It is also an adviser for legislative modifications in the power industry 15 The Argentine power sector is one of the most competitive and deregulated in South America However the fact that the Energy Secretariat has veto power over CAMMESA has the potential to alter the functioning of the competitive market The functions of generation transmission and distribution are open to the private sector but there are restrictions on cross ownership between these three functions Argentine law guarantees access to the grid in order to create a competitive environment and to allow generators to serve customers anywhere in the country 9 Generation edit Private and state owned companies carry out generation in a competitive mostly liberalized electricity market with 75 of total installed capacity in private hands The share in public hands corresponds to nuclear generation and to the two bi national hydropower plants Yacyreta Argentina Paraguay and Salto Grande Argentina Uruguay The generation sector is highly fragmented with more than ten large companies all of them providing less than 15 of the system s total capacity 8 Power generators sell their electricity in the wholesale market operated by the CAMMESA 9 Transmission and distribution edit The transmission and distribution sectors are highly regulated and less competitive than generation In transmission the Compania Nacional de Transporte Energetico en Alta Tension Transener operates the national electricity transmission grid under a long term agreement with the Argentine government In the distribution sector three private companies Edenor Empresa Distribuidora y Comercializadora Norte Edesur Electricidad Distribuidora Sur and Edelap Empresa de Electricidad de la Plata dominate a market with 75 control by private firms 9 Other important distribution companies at the provincial level are Public provincial EPEC Empresa Provincial de Energia de Cordoba EPESFI Empresa Provincial de Energia de Santa Fe Private provincial ESJ Energia San Juan EDET Empresa de Distribucion Electrica de Tucuman EDEN Empresa Distribuidora de Energia Norte EDEA Empresa Distribuidora de Energia Atlantica EDES Empresa Distribuidora de Energia Sur Renewable energy resources edit nbsp Argentina renewable electricity production by yearThe National Promotion Direction DNPROM within the Energy Secretariat SENER is responsible for the design of programs and actions conducive to the development of renewable energies through the Renewable Energy Coordination and energy efficiency through the Energy Efficiency Coordination initiatives 9 Complementarily the Secretariat for the Environment and Natural Resources SEMARNAT is responsible for environmental policy and the preservation of renewable and non renewable resources 12 The most important legal instruments for the promotion of renewable energy are Law 25 019 from 1998 and Law 26 190 from 2007 The 1998 law known as the National Wind and Solar Energy Rules declared wind and solar generation of national interest and introduced a mechanism that established an additional payment per generated kWh which in 1998 meant a 40 premium over market price It also granted certain tax exemptions for a period of 15 years from the law s promulgation 10 The 2007 Law complemented the previous one declaring of national interest the generation of electricity from any renewable source intended to deliver a public service This law also set an 8 target for renewable energy consumption in the period of 10 years and mandated the creation of a trust fund whose resources will be allocated to pay a premium for electricity produced from renewable sources Hydropower edit At the end of 2021 Argentina was the 21st country in the world in terms of installed hydroelectric power 11 3 GW 16 Argentina s hydroelectric potential is being exploited only partially While the identified potential is 170 000 GW h year in 2006 hydroelectric production amounted just to 42 360 GW h 12 There are also untapped mini hydropower resources whose potential is estimated at 1 81 of overall electricity production in contrast with its current 0 88 17 For a comprehensive list of plants see Hydroelectric power stations in Argentina Wind edit At the end of 2021 Argentina was the 26th country in the world in terms of installed wind energy 3 2 GW 18 As of 2020 Argentina had an installed wind energy capacity of 1 6 GW with 931 MW installed in 2019 alone 19 Electricity production from onshore wind power in Argentina has increased from 1 41 TWh in 2018 to 9 42 TWh in 2020 20 The technical potential for offshore wind in Argentina has been estimated to amount to 2 5 TW but no offshore turbines have been built so far 21 The Argentine Patagonia region has a very large wind potential The Chubut Wind Power Regional Center CREE estimated the theoretical potential for the region at 500 GW of electricity generation However this large potential is still largely unexploited One of the reasons for this underdevelopment is that existing tariffs and incentives do not make wind power development attractive enough yet However the main deterrent to wind power development in the region has been the lack of transmission lines that connect the Patagonia region with the National Interconnected System 22 The completion of the Choele Choel Puerto Madryn high voltage line the first section of Linea Patagonica under the framework of the Plan Federal de Transporte de Energia Electrica eliminated this bottleneck in March 2006 23 Nevertheless wind power has increased significantly in Argentina during the last decade Total operating wind power capacity in 2005 was 26 6 MW shared by 13 plants This is still only about 0 05 of the theoretical potential of wind energy in Argentina In 2007 the distribution of number plants and total capacity was 17 Buenos Aires Province 6 plants 6 100 kW Chubut Province 4 plants 17 460 kW Santa Cruz Province 1 plant 2 400 kW La Pampa Province 1 plant 1 800 kW Neuquen Province 1 plant 400 kWOf the 13 plants only three have been commissioned after the year 2000 with the remaining 10 built during the 1990s 17 See Wind power regime map for Argentina Solar edit At the end of 2021 Argentina was the 43rd country in the world in terms of installed solar energy 1 0 GW 24 Solar power is only present in remote areas Just 81 MW h were generated in 2005 less than 0 1 of total electricity production 25 In 2012 the first of four 5 MW stages of Canada Honda was completed as part of a plan to install 117 MW of renewable energy 26 History of the electricity sector editThe reforms of 1991 92 edit Prior to 1991 the electricity sector in Argentina was vertically integrated The sector experienced a serious crisis in the summers of 1988 1989 primarily due to the lack of maintenance of the country s thermal power plants 50 were unavailable 27 Shortly after the crisis the government of Carlos Menem introduced a new legal framework for the electricity sector through Law 24 065 which included the following elements vertical and horizontal unbundling of generation transmission and distribution opening up of all segments to the private sector and separation of the regulatory function from policy setting As a result of the new law there was substantial private investment which together with the public power plants that started production in the 1990s transformed a situation of power shortage and low quality into one of abundance and reliability at lower prices 28 ENRE Electricity National Regulatory Entity was created in 1992 The Wholesale Electricity Market MEM which covers up to 93 of total demand corresponding to the Argentine Interconnected System SADI was also created in 1992 The remaining 7 share of the demand corresponds to Patagonia which had its own interconnected market the Patagonian Wholesale Electricity Market MEMSP now interconnected with the MEM CAMMESA Wholesale Electricity Market Administration Company was also created that year and assigned the responsibilities of coordinating dispatch operations setting wholesale prices and administrating economic transactions performed through the Argentine Interconnected System 27 The reforms implemented in the 1990s led to high investment which allowed for a 75 increase in generation capacity resulting in the decrease of prices in the wholesale market from US 40 MW h in 1992 to US 23 MW h in 2001 However the reforms failed to deliver the necessary increase in transmission capacity Only one relevant project the addition of the 1 300 km high voltage line between Comahue and Buenos Aires was built in the 1990s Distribution networks were also renovated and expanded which resulted in efficiency and quality improvements 29 Tariff freeze edit As a response to the 2001 economic crisis electricity tariffs were converted to the Argentine peso and frozen in January 2002 through the Public Emergency and Exchange Regime Law Together with high inflation see Economy of Argentina and the devaluation of the peso many companies in the sector had to deal with high levels of debt in foreign currency under a scenario in which their revenues remained stable while their costs increased This situation has led to severe underinvestment and unavailability to keep up with an increasing demand factors that contributed to the 2003 2004 energy crisis 29 Since 2003 the government has been in the process of introducing modifications that allow for tariff increases Industrial and commercial consumers tariffs have already been raised near 100 in nominal terms and 50 in real terms but residential tariffs still remain the same Creation of Enarsa edit In 2004 President Nestor Kirchner created Energia Argentina Sociedad Anonima Enarsa a company managed by the national state of Argentina for the exploitation and commercialization of petroleum and natural gas but also the generation transmission and trade of electricity Through the creation of Enarsa the state will regain a relevant place in the energy market that was largely privatized during the 1990s Energy Plus and Gas Plus programs edit In September 2006 SENER launched the Energy Plus Energia Plus program with the objective of increasing generation capacity and meeting the rising demand for electricity The program applies for consumption levels above those for 2005 CAMMESA requires all large users above 300 kW to contract the difference between their current demand and their demand in the year 2005 in the Energy Plus market In this new de regulated market only energy produced from new generation plants will be traded The aim of the program is twofold In one hand it seeks to guarantee supply to residential consumers public entities and small and medium enterprises On the other hand it aims at encouraging self generation by the industrial sector and electricity cogeneration 28 In March 2008 the government approved Resolution 24 2008 which created a new natural gas market called Gas Plus to encourage private investment in natural gas exploration and production The Gas Plus regime applies to new discoveries and to tight gas fields The price of the new gas whose commercialization will be restricted to the domestic market will not be subject to the conditions established in the Agreement with Natural Gas Producers 2007 2011 but will be based on costs and a reasonable profit Experts believe that if the Gas Plus regime is successful it could stimulate new investments in electricity generation plants under the Energy Plus regime as it could ensure fuel supply to the new plants 30 The National Program for the Rational and Efficient Use of Energy PRONUREE edit In December 2007 the government launched the National Program for the Rational and Efficient Use of Energy PRONUREE Decree 140 2007 This decree declared the rational and efficient use of energy to be in the national interest and is also part of the energy sector strategy to counter supply demand imbalance The PRONUREE under the responsibility of the Secretariat of Energy aims to be a vehicle for improving energy efficiency in the energy consuming sectors and acknowledges that energy efficiency needs to be promoted with a long term commitment and vision It also acknowledges the connection between energy efficiency and sustainable development including the reduction of greenhouse gas emissions The program also recognizes the need for individual behavioral changes to be promoted with an educational strategy with the public sector setting the example by assuming a leadership role in the implementation of energy conservation measures in its facilities 31 The PRONUREE includes short and long term measures aimed at improving the energy efficiency in the industrial commercial transport residential and service sectors and public buildings It also supports educational programs on energy efficiency enhanced regulations to expand cogeneration activities labeling of equipment and appliances that use energy improvements to the energy efficiency regulations and broader utilization of the Clean Development Mechanism CDM to support the development of energy efficiency projects 31 The objective of the program is to reduce electricity consumption by 6 32 One of the first activities defined under PRONUREE is the national program to phase out incandescent bulbs by 2011 in Argentina The program financed by the government aims to replace incandescent bulbs with energy efficient compact fluorescent lamps CFLs in all households connected to the electricity grid and selected public buildings The program which has initially undergone a pilot phase and expects to replace 5 million incandescent lamps in the next six months 33 foresees the distribution of 25 million lamps overall 34 Staff from the distribution companies will visit each household to replace the incandescent lamps and to inform residential users on the advantages of replacing the bulbs and of the efficient use of energy in general 33 Recent tariff increases 2008 edit In Argentina retail tariffs for the distribution utilities in the Metropolitan Area of Buenos Aires and La Plata city i e Edenor Edesur and Edelap are regulated by the national regulatory agency ENRE while provincial utilities are regulated by local regulators While the utilities under ENRE s jurisdiction had not been allowed to raise residential tariffs since they were frozen in 2002 as a result of the Emergency and Exchange Regime Law some provincial regulators had recently approved additional charges to residential tariffs In particular the Public Service Regulatory Agency in the Province of Cordoba ERSeP agreed in February 2008 35 to a 17 4 additional charge to residential customers Likewise Santa Fe approved increases between 10 and 20 36 Mendoza between 0 and 5 below 300 kWh and between 10 and 27 above 300 kWh 37 38 Jujuy between 22 and 29 and Tucuman between 10 and 24 39 Other provinces i e San Juan Chaco Formosa Corrientes La Pampa Neuqen Rio Negro and Entre Rios are expected to raise tariffs in the near future 39 Recently in August 2008 after a 7 year tariff freeze residential electricity tariffs in the Buenos Aires metropolitan area served by the Edenor Edesur and Edelap utilities have been increased by 10 30 for households that consume more than 650 kWh every two months For consumption between 651 kWh and 800 kWh the increase will be 10 on the other end for users over 1 201 kWh the increase amounts to 30 The increase impacts around 24 of all Edenor Edesur and Edelap customers 1 600 000 households For commercial and industrial users the increase will be 10 40 At the end of August 2008 ENRE also approved increases in transmission tariffs in the 17 47 range 41 The increase granted by ENRE was below the increase determined by the Energy Secretariat for some transmission companies e g Transener Transba Distrocuyo and Transnoa Some of them i e Transener Transba will most likely challenge ENRE s decision 42 An overall tariff revision is still pending and has been put off until February 2009 43 Tariffs cost recovery and subsidies editTariffs edit Electricity tariffs in Argentina are well below the LAC average In 2004 the average residential tariff was US 0 0380 per kWh very similar to the average industrial tariff which was US 0 0386 per kWh in 2003 Weighted averages for LAC were US 0 115 per kWh for residential consumers and US 0 107 per kWh for industrial customers 14 See History of the electricity sector for more information on the evolution of tariffs Subsidies edit See Fund for the Electric Development of the Interior FEDEI below Investment and financing editIn 1991 the Government of Argentina created the National Fund for Electric Power FNEE Fondo Nacional de la Energia Electrica to be funded by a share of the petrol tax and a surcharge on sales from the wholesale market This Fund which is administered by CFEE Electric Power Federal Council provides funding to the following other funds at the shares indicated 44 47 4 Subsidiary Fund for Regional Tariff Compensation to Final Users FCT for homogenization of tariffs across the country this created a de facto subsidy for those consumers in the areas with higher electricity costs 31 6 Fund for the Electric Development of the Interior FEDEI for generation transmission and rural and urban distribution works Most funds have been directed to rural electrification 19 75 Fiduciary Fund for Federal Electricity Transmission FFTEF created in 2000 for co financing or projects in electricity transmission 1 26 Wind Energy Fund created in 2002 for the development of wind energy In addition CAMMESA the administrator of the wholesale electricity market had projected that by 2007 the country s energy demand would require an additional capacity of 1 600 MW Faced with the need for specific investments but also with a lack of private investment the Energy Secretariat SENER enacted Resolutions 712 and 826 in 2004 which created FONINVEMEM the Fund for the Investment Needed to Increase the Supply of Electricity in the Wholesale Market The Fund which sought to encourage participation from creditors of the wholesale market invited those creditors mainly generation companies to participate with their credit in the creation of the Fund itself 45 Ongoing projects edit There are several projects that are part of the government s response to the predicted electricity shortages If all those plans are completed as expected the capacity requirements for the next few years will be met Thermal power edit Two new CCGT plants the Jose de San Martin Thermoelectric and Manuel Belgrano Thermoelectric of 830 MW each are under construction and expected to start full operations at the beginning of 2009 Endesa Total S A AES Corporation Petrobras EDF and Duke Energy are the main shareholders in the plants Both plants which have been financed through the FONINVEMEM total investment amounts up to US 1 097 million are expected to start full operations at the beginning of 2009 46 In addition the Planning Ministry announced in July 2007 the commissioning of five new thermal plants with a total capacity of 1 6 GW and an overall investment of US 3 250 million These dual generation turbine gas or fuel oil plants which are expected to start operations in 2008 will be located in Ensenada 540 MW Necochea 270 MW Campana 540 MW Santa Fe 125 MW and Cordoba 125 MW 47 Finally Enarsa has recently launched bidding for eleven small and transportable generation units 15 30 MW each and for other three larger generation units 50 100 MW to be installed on barges These new units whose base price is still unknown will add between 400 and 500 MW of new generation capacity 48 Nuclear power edit In 2006 the Argentine government launched a plan to boost nuclear energy The Atucha II nuclear power plant whose construction started in 1981 was to be completed and to add 750 MW of generation capacity by 2010 The plant started producing power in June 2014 In addition the Embalse nuclear power plant with 648 MW of generation capacity was to be refurbished to extend its operational life beyond 2011 49 Hydropower edit nbsp The Yacyreta dam It is planned to increase its height to increase the electricity generation capacity in Argentina and Paraguay On the hydropower side the Yacyreta dam s reservoir was elevated by 7 m to the height of 83 m as contemplated in its original design which increased its capacity from 1 700 to 3 100 MW This will lead to a 60 increase in its electricity output from 11 450 GW h to 18 500 GW h 10 The reservoir rise was complete in February 2011 despite a serious controversy regarding the resettlement of people 50 51 52 Additionally in 2006 bidding for the expansion of Yacyreta with the construction of a new 3 turbine plant in the Ana Cua arm of the Parana River was announced by the Government This expansion to be finalized in 2010 would add 300 MW of new generation capacity 53 Transmission edit In regard to transmission the Federal Plan for Transport of Electric Energy at 500 kV is under implementation under the umbrella of the FFTEF Fondo Fiduciario para el Transporte Electrico Federal 10 The main lines of the plan Linea Patagonica Linea Minera Yacyreta Puerto Madryn Pico Truncado NEA NOA Comahue Cuyo Pico Truncado Rio Turbio Rio Gallegos are already built or currently under construction The lines built between 2007 and 2009 will add 4 813 new kilometers of high voltage transmission capacity 23 54 In addition the Federal Plan for Transport of Electric Energy II defined in 2003 and updated in 2006 has the objective of addressing the constraints faced by the regional transmission networks in the period up to 2010 This complementary plan has prioritized the necessary works according to their ability to address short term demand issues 109 of the 240 works identified in 2003 were considered of high priority and have already been completed or are under execution Initially investment for high priority works was estimated at US 376 million while estimated investment for the rest of the works totaled US 882 2 million However this budget is under revision due to the increasing costs of materials such as steel and aluminum and of labor 10 Summary of private participation in the electricity sector editPrior to 1991 the electricity sector in Argentina was vertically integrated The new legal framework for the electricity sector included vertical and horizontal unbundling of generation transmission and distribution opening up of all segments to the private sector and separation of the regulatory function from policy setting Currently private and state owned companies carry out generation in a completive mostly liberalized electricity market with 75 of total installed capacity in private hands The publicly owned share corresponds to nuclear generation and to the two bi national hydropower plants Yacyreta Argentina Paraguay and Salto Grande Argentina Uruguay On the other hand the transmission and distribution sectors are highly regulated and less competitive than generation In transmission the Compania Nacional de Transporte Energetico en Alta Tension Transener operates the national electricity transmission grid while in the distribution sector three private companies Edenor Empresa Distribuidora y Comercializadora Norte Edesur Electricidad Distribuidora Sur and Edelap Empresa de Electricidad de la Plata dominate a market with 75 control by private firms Activity Private participation Generation 75 of installed capacityTransmission 100 Distribution 75 of clientsElectricity and the Environment editResponsibility for the environment edit The Secretariat of Environment and Sustainable Development holds responsibility for the environment in Argentina Greenhouse gas emissions edit OLADE Organizacion Latinoamericana de Energia estimated that CO2 emissions from electricity production in 2003 were 20 5 million tons of CO2 which represents 17 of total emissions for the energy sector 55 In 2011 according to the International Energy Agency the actual CO2 emissions from electricity generation were 67 32 million metric tons a share of 36 7 of the countries total CO2 emissions from fuel combustion 56 CDM projects in electricity edit As of August 2007 there are only three energy related registered CDM projects in Argentina with expected total emissions reductions of 673 650 tons of CO2e per year 57 Of the three projects only one is large scale the 10 56 MW Antonio Moran wind power plant in the Patagonia region Production of electricity from biomass waste in the Aceitera General Deheza and methane recovery and electricity generation from the Norte III B landfill are the two small scale existing projects External assistance editWorld Bank edit The only active energy project financed by the World Bank in Argentina is the Renewable Energy in the Rural Market Project PERMER This project has the objective of guaranteeing access to electricity to 1 8 million people 314 000 households and to 6 000 public services schools hospitals etc located far from electricity distribution centers Electrification of this dispersed market will be mostly carried out through the installation of solar photovoltaic systems but also through other technologies such as micro hydraulic turbines wind and eventually diesel generators 13 The project which started in 1999 and is expected to end in December 2008 has received a US 10 million grant from GEF and a US 30 million loan from the World Bank 58 The Argentine Energy Secretariat has recently presented an Energy Efficiency project to the GEF The objective of the project is to improve energy use reducing its costs to consumers and contributing to the sustainability of the energy sector in the long term A reduction in greenhouse gas emissions is also sought 59 Inter American Development Bank edit In November 2006 the Inter American Development Bank approved a 580 million loan for the construction of a new 760 mile transmission line in northern Argentina that will connect separate grids in the northeastern and northwestern parts of the country the Norte Grande Electricity Transmission Program Andean Development Corporation CAF edit In 2006 Argentina received financing from CAF Andean Development Corporation for two electricity projects the Electricity Interconection Comahue Cuyo US 200 million and the Electricity Interconnection Rincon Santa Maria Rodriguez US 300 million two of the high voltage transmission lines included in the Federal Transportation Plan 60 In the same year Argentina also borrowed US 210 million from CAF for a program that aims at repairing the country s hydroelectric infrastructure In June 2007 CAF approved a US 45 million loan to the Buenos Aires province for partial financing of the electricity transport capacity in the North of the province 61 Sources editCamara Argentina de la Construccion 2006 La construccion como herramienta del crecimiento continuado Sector electrico Evaluacion de las inversiones necesarias para el sector electrico nacional en el mediano plazo Consultor Dr Ing Alberto del Rosso Coordinacion de Energias Renovables 2006 Potencial de los aprovechamientos energeticos en la Republica Argentina Oxford Analytica 2006 Argentina Energy issues threaten sustained growth Secretaria de Energia 2006 Informe del Sector Electrico 2005 Secretaria de Energia 2007 Balance Energetico Nacional Avance 2006See also edit nbsp Argentina portal nbsp Energy portalArgentina Argentine economic crisis 1999 2002 Argentine energy crisis 2004 Water supply and sanitation in Argentina National Atomic Energy Commission Renewable energy by country 2019 Argentina and Uruguay blackoutNotes edit a b c World Bank Access to Electricity of total population World Bank Potencia Instalada Energia Electrica a b Monthly Report Main variables of the month April 2019 PDF CAMMESA p 11 Oxford Analytica 2006 Econometrica Atucha 2 reaches 100 rated power World Nuclear News www cammesa com www cammesa com Retrieved 18 February 2021 a b c Secretaria de Energia 2006 a b c d e EIA Archived from the original on 26 August 2007 Retrieved 24 September 2007 a b c d e f Camara Argentina de la Construccion 2006 El Pais a b c Coordinacion de Energias Renovables 2006 a b PERMER Archived from the original on 30 November 2012 Retrieved 30 November 2012 a b c Benchmarking data of the electricity distribution sector in Latin America and Caribbean Region 1995 2005 Electric Power Federal Council CFEE Archived from the original on 12 October 2007 Retrieved 28 September 2007 RENEWABLE CAPACITY STATISTICS 2022 PDF IRENA Retrieved 19 May 2022 a b c Coordinacion de Energias Renovables Archived 29 July 2007 at the Wayback Machine RENEWABLE CAPACITY STATISTICS 2022 PDF IRENA Retrieved 19 May 2022 Renewable Energy for Argentina ABO Wind Dark horse Argentina could challenge Brazil in South America s offshore wind race Recharge 7 September 2021 Dark horse Argentina could challenge Brazil in South America s offshore wind race Recharge 7 September 2021 Instituto Nacional de Tecnologia Industrial a b Public works news RENEWABLE CAPACITY STATISTICS 2022 PDF IRENA Retrieved 19 May 2022 SENER 2007 Parque Solar Fotovoltaico Canada Honda a b La Energia Electrica en la Republica Argentina a b ENRE a b Standard and Poor s PDF Archived from the original PDF on 3 March 2016 Retrieved 27 April 2019 Resolution 24 2008 Secretariat of Energy a b Decree 140 2007 La Nacion 5 January 2008 a b La Nacion 4 March 2008 La Nacion 15 March 2008 General Resolution No 04 2008 PDF Archived from the original PDF on 19 February 2009 Retrieved 18 April 2008 El Santafesino Archived from the original on 26 June 2008 Retrieved 18 April 2008 Diario Panorama Archived from the original on 10 July 2011 Retrieved 18 April 2008 Prensa Mendoza Archived from the original on 29 July 2007 Retrieved 18 April 2008 a b Urgente 24 Resolution ENRE 356 08 Resolutions ENRE 327 328 08 Diario Clarin 16th Aug 2008 Resolutions Energy Secretariat 864 865 866 08 Electric Power Federal Council CFEE permanent dead link Camara de Diputados SIEMENS Archived from the original on 14 December 2007 Retrieved 24 September 2007 Aristotelizar online news Archived from the original on 7 July 2011 Retrieved 24 September 2007 Electroindustria National Atomic Commission Archived from the original on 17 November 2007 Retrieved 24 September 2007 Kerr Juliette 25 February 2011 Argentine and Paraguayan Presidents to Inaugurate Completion of Key Hydroelectric Project Global Insight Archived from the original on 13 March 2012 Retrieved 3 March 2011 Udall Lori World Bank Inspection Panel PDF World Commission on Dams Archived from the original PDF on 13 June 2010 Retrieved 3 March 2011 Argentina Paraguay celebrate Yacyreta dam completion Google cache ADPnews 28 February 2011 Retrieved 3 March 2011 permanent dead link Na Nacion CFEE Archived from the original on 7 February 2007 Retrieved 24 September 2007 OLADE Archived 28 September 2007 at the Wayback Machine Argentina CO2 emissions index mundi Retrieved 20 April 2016 UNFCCC World Bank Energy Efficiency Coordination Archived from the original on 29 July 2007 Retrieved 24 September 2007 CAF a CAF b Archived from the original on 2 October 2007 Retrieved 24 September 2007 External links editPublic entities edit Energy Secretariat Energy Office Province of Buenos Aires Secretariat of Environment and Sustainable Development Electric Power Federal Council CFEE Administrator of the Wholesale Electricity Market CAMMESA National Electricity Regulator ENRE TransenerElectricity distributors edit Edenor Edesur Edelap Federacion Argentina de Cooperativas de Electricidad y Otros Servicios Publicos LimitadaExternal partners edit List of World Bank projects in Argentina List of Inter American Development Bank projects in ArgentinaOther edit Energy Efficiency Programs and Projects Climate Change Scenarios for Argentina La Energia Electrica en la Republica Argentina Early History of the electricity sector in Argentina in Spanish CNEA Electricity Bulletin Retrieved from https en wikipedia org w index php title Electricity sector in Argentina amp oldid 1186217399, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.