fbpx
Wikipedia

Bay Area Rapid Transit expansion

Throughout the history of Bay Area Rapid Transit, there have been plans to extend service to other areas.

History edit

The initial 1962 BART maps approved by voters included several lines beyond the core system marked as Possible Future Extensions.[1] Some have since come to fruition as previous extensions of the system:[2]

  • The extension from Concord to Antioch was carried out in phases with service to North Concord / Martinez in 1995, Pittsburg / Bay Point in 1996, and the eBART spur which started service in 2018.
  • A line to Livermore was completed as far as Dublin/Pleasanton by 1997, with final completion of the envisioned corridor to be carried out by Valley Link.
  • Service south of Fremont is expected to reach San Jose and Santa Clara (partially via the Caltrain right of way) by 2030. It was extended to Warm Springs in 2017 and Berryessa in 2020.
  • Extension from Daly City to the south was completed in phases as the Colma Station opened in 1996 and the line to Millbrae was completed in 2003 with a spur to San Francisco International Airport. The full Southern Pacific (now Caltrain) right of way is being electrified for frequent service with mainline trains, separate from BART.
  • The Marin Line via Geary was initially cancelled due to the county exiting the planning district over funding and engineering issues. There were two possible routes: (1) via Geary to Park Presidio, then across the Golden Gate Bridge via rails that would have been built into the truss supports under the roadway, then after tunneling through the Waldo Grade to Marin City, would have emerged from underground and followed the old train tracks north through the county; (2) alternatively, to tunnel from Fort Mason/Aquatic Park to downtown Sausalito and follow the right-of-way from the old train tracks.

An additional corridor not part of the 1962 plan completed since the agency's inception is the automated guideway transit spur line that connects BART to Oakland International Airport which opened in 2014.[3]

 
As of August 2021, the BART map has one route marked for Future Service: the second phase of the Silicon Valley BART extension into San Jose, shown as a thick, gray dashed line. The planned Irvington station is also shown.

Proposed extensions edit

San Jose subway extension (Phase 2) edit

 
BART will eventually terminate at Santa Clara Transit Center.

The original plan for the Silicon Valley extension was to continue into downtown San Jose and Santa Clara via subway. However, in February 2009, projections of lower-than-expected sales-tax receipts from the funding measures forced the Santa Clara Valley Transportation Authority to scale back the extension, ending it at the Berryessa/North San José station and delaying tunneling under downtown San Jose to a future phase of construction (making it essentially a "Phase 2" of the project). The originally-planned complete extension from Fremont to Santa Clara had been projected to cost $6.1 billion, but the VTA estimates the extension to Berryessa (Phase 1 only) would cost just $2.3 billion.[4][5]

The plans for the downtown subway start with a portal before crossing under US 101, with subway stations at 28th Street/Little Portugal, Downtown San Jose station (The Downtown San Jose station was combined in 2005 from earlier plans for separate subway stations at Civic Plaza/San Jose State University and Market Street.),[6] and Diridon/Arena. The line would exit to the surface after crossing under I-880 and terminate at a Santa Clara BART station co-located at the existing Santa Clara Depot. Separate construction plans by San Jose International Airport would bring a people-mover train to either the Santa Clara Depot or to Diridon Station.[7]

For the subway segment in San Jose, VTA plans to use a tunnel boring machine for most of the length in order to reduce disruptions to downtown during construction.[8] Only the station locations would have cut and cover construction.[9] This is different from how BART subways and stations were built in San Francisco and Oakland, which used the cut and cover method. The construction of the cut and cover stations in downtown San Jose would still cause major albeit temporary disruption, including closing several blocks of Santa Clara Street and severing the VTA light rail line at that street. The extension to downtown San Jose could open 2026, contingent on approval of funding.[10] As of April 2018, the plan was to have a single-bore tunnel under Santa Clara Street with cut and cover construction at the station locations only.[11] Utility relocation started and soil samples were taken in February 2019, with construction to begin in 2022.[12][13]

Funding and electoral history (2000–2008) edit

Because Santa Clara County is not among the member counties of the BART District (having opted out at the district's inception, like neighboring San Mateo County), VTA is responsible for building the extension within Santa Clara County. VTA allocated initial funds for constructing BART using the proceeds from a sales tax referendum which was passed by Santa Clara County voters in 2000. In December 2002, VTA purchased a freight railroad corridor from Union Pacific Railroad which will serve as much of the necessary right-of-way for both the Warm Springs and San Jose extensions for $80 million.[14]

In 2004, the Federal Transit Administration decided to wait to fund the project, citing worries that BART did not have enough money to operate the extension.[15] In addition, the San Jose extension project received a "not recommended" rating from the Federal Transit Administration, placing the federal portion of the funding in jeopardy because of concerns about operation and maintenance funding.[16]

Santa Clara County voters passed Measure B in 2008, a 18-cent sales tax raise.[17] Projections by an independent consultant recommended by the Federal Transit Administration predicted that the 18-cent sales tax would more than cover operation and maintenance of the proposed extension.[18][19][20][21]

San Jose voters passed Measure B in 2016, which allowed for final funding of the subway.[22][8]

Livermore extension: I-580/Tri-Valley Corridor edit

A proposed extension will further service from Dublin/Pleasanton station east to Livermore, either via traditional BART infrastructure, diesel multiple unit technology[23][24] similar to eBART, or enhanced bus service.[25] It could possibly continue over the Altamont Pass into Tracy and the Central Valley along I-580 and/or go north through Dublin, San Ramon, Danville, and Alamo to the existing Walnut Creek station via the I-680 corridor.

An existing diesel commuter rail line, the Altamont Corridor Express (ACE), currently operates through Livermore. The two systems are linked, though not directly, by a free shuttle bus which transfers passengers between the ACE Pleasanton station and the BART Dublin/Pleasanton station.[26][27][28]

A preferred alignment was selected July 1, 2010 and originally had the support of the Livermore City Council. This plan would have involved the construction of a station in downtown Livermore, and a second station on Vasco Road near Lawrence Livermore National Laboratory and Sandia National Laboratories. Both proposed stations would have provided nearby connections to Altamont Corridor Express service.[29] However, in July 2011, the Livermore City Council reversed its position in response to a petition requesting that the alignment stay within or nearby the Interstate 580 right-of-way, and now favors stations be built at the Interstate 580 interchanges with Isabel Avenue and Greenville Road.[30] BART's Environmental Impact Report Notice of Preparation, issued in September 2012, proposed a single station at I-580 and Isabel Avenue, with possible express bus services connecting to the Vasco Road ACE station and a park-and-ride lot at I-580 and Greenville Road.[31] Land use plans and studies were being prepared by the city of Livermore in September 2015, with completion envisioned in 2026.[25][32][33] Additional funding for consulting and planning were allocated in late 2016, against the wishes of then BART District President Tom Radulovich.[34] On July 31, 2017, BART released the Draft Environmental Impact Report of the project.[citation needed] The direct BART to ACE connection was studied in preparation for ACEforward projects.[citation needed]

In 2017, citing lack of interest in the project from BART, the Livermore City Council proposed a newly established local entity to undertake planning and construction of the extension,[35] which was also recommended by the California State Assembly Transportation Committee.[24] The Tri-Valley-San Joaquin Valley Regional Rail Authority was established that year "for purposes of planning, developing, and delivering cost-effective and responsive transit connectivity between the Bay Area Rapid Transit District's rapid transit system and the Altamont Corridor Express commuter rail service in the Tri-Valley, that meets the goals and objectives of the community."[36] On May 24, 2018, the BART board voted against a full rapid transit BART build or a bus rapid transit system to extend service east from Dublin/Pleasanton station, thus granting the new authority oversight and funding for constructing a new service. Moneys previously allocated to BART to construct a Livermore extension were forfeited to the authority by July 1, 2018.[37]

BART Metro Vision edit

Key components of the overall vision for BART's future, dubbed BART Metro Vision, include more capacity in stations, increased train frequency to allow for "show up and go" service at stations within the system's operational core, and increased performance reliability. The most recent report from BART Metro Vision also identifies improvements to its rolling stock, the Hayward Maintenance Complex, and the modernization of its train control system as key improvements for securing the system's long-term viability.[38]

Second Transbay crossing edit

Part of BART's 50th anniversary service planning included a new separate Transbay Tube beneath San Francisco Bay running parallel to and south of the existing tube. This would emerge at the Transbay Transit Center to provide connecting service to Caltrain and the planned California High-Speed Rail (CAHSR) system. The additional four-bore Transbay Tube would provide two additional tracks for BART trains, and two tracks for conventional/high-speed rail (the BART system and conventional U.S. rail use different and incompatible rail gauges, and operate under different sets of safety regulations).[39]

Transit advocacy groups in the Bay Area, such as SPUR,[40] have long promoted larger-scale expansion of the BART system through various capital projects - one identified as a long-term goal in the Metro Vision is the construction of a second, four-bore rail tunnel under San Francisco Bay, increasing connectivity and capacity of the system. The second crossing would likely route to the Transbay Transit Center for connections with conventional mainline rail services. In 2018, BART announced that a feasibility study for installing a second transbay crossing would commence the following year.[41] By 2019, the Capitol Corridor Joint Powers Authority had joined with BART to study a multi-modal crossing, which could also allow Capitol Corridor and San Joaquin routes to serve San Francisco directly.[42]

In 2021, the Link21 program was announced, using funding from Regional Measure 3. The program initially proposed a 4-track transbay crossing for both BART and commuter rail; however, this was pared back to 2 tracks. The likely long-term plan is for the second transbay crossing to be electrified commuter rail, connecting CalTrain (which is partially governed by BART) to the Capitol Corridor.[43]

eBART extension edit

Expansions of the DMU-serviced eBART system come at a lower cost-per-mile than conventional wide-gauge BART infrastructure. Service could extend to Oakley[44][45] or Brentwood.[46]

Geary Subway edit

Part of the plan for the original system before Marin County's departure from the BART District was a line running under Geary Street and turning north to the Golden Gate Bridge. When Marin County pulled out of the transit district, some plans called for a subway only extending down Geary, but these too were soon scrapped. In 1995, the San Francisco Municipal Railway hired Merrill & Associates to study the possibility of building a new BART subway beneath Geary in conjunction with adding light rail on the surface. The estimated cost of construction as far as Park Presidio Boulevard was $1.4 billion in 1995 ($2.8 billion adjusted for inflation). Projections from this study put BART ridership at 18,000 daily boardings, and the alignment would allow for a further extension to Marin. These plans were dropped, according to former Senator Quentin L. Kopp, due to merchant and resident opposition, citing potential blight similar to that caused by Market Street Subway construction two decades earlier.[47]

Ongoing studies will determine whether the corridor may one day be served by future BART service. It may be constructed as an extension of the second Transbay Tube.[39][47]

wBART extension edit

The only branch of the original BART system that has not been extended since service commenced is the line ending at Richmond station. Possible alignments for an extension further north were examined in 1983,[48] 1992,[49] and 2017.[50] Both newly constructed BART wide-gauge electrified rail and the use of existing freight rail rights of way and tracks with more readily available standard gauge trains were considered. Potential station locations include Hilltop Mall, Pinole, and Hercules Transit Center. The cost of an extension to Hercules Transit Center utilizing mainline BART technology was estimated at $3.6 billion in 2017 with a ridership of 21,980 by 2040.[51] The extension to Hercules is controversial in that the main proponent wants to build it directly from the El Cerrito del Norte BART station while the city of Richmond is very opposed to this. Furthermore, the majority of the Hercules city council opposes the extension as they believe it will detract from their plan to develop Hercules station.[52][53][54][55]

I-680 Corridor edit

Service in the Tri-Valley area had previously been considered with diesel multiple service originating at Walnut Creek and running as far east as Tracy.[56] As part of BART's 50th anniversary and envisioning another fifty years of service, planners foresaw a new East Bay alignment originating at Warm Springs station and running via Interstate 680 to the Martinez Amtrak station. It would connect to the existing stations at Dublin / Pleasanton and Walnut Creek.[39]

Menlo Park extension edit

In 1999, a short-lived proposal to extend BART from the Millbrae station (then under construction) to Menlo Park was advanced by the San Mateo County Economic Development Association (SAMCEDA). The proposed routing would have followed the Caltrain tracks to the Broadway station in Burlingame, and then would run along the median of Bayshore Freeway to Menlo Park, with stations in San Mateo, Belmont/San Carlos, Redwood City, and Menlo Park. Cost estimates ranged up to US$2,500,000,000 (equivalent to $4,570,000,000 in 2023), drawing funding from a 1/2-cent sales tax increase in San Mateo County.[57] BART leadership warned the timing was not appropriate for a push further south into San Mateo County, and SAMCEDA withdrew the proposal by the summer of 1999.[58]

Infill stations edit

Infill stations are stations constructed on existing line segments between two existing stations. The Embarcadero (1976) and West Dublin/​Pleasanton (2011) stations are the only infill stations currently in the BART system. The Doolittle Maintenance and Storage Facility, initially slated to be opened as a full station along the Oakland Airport Connector, may be repurposed for passenger service at a later date.

Construction costs for a planned 30th Street Mission station in San Francisco, between the existing 24th Street Mission and Glen Park stations, were estimated at $500 million in 2003.[59][60] A proposal for a Jack London Square station in Oakland was rejected in 2004 as being incompatible with existing track geometry; a one-station stub line at the foot of Broadway and the use of other transit modes also were studied.[61] BART planners studied additional stations at four other sites within the system in 2007: Albany, Calaveras, Irvington, and 30th Street Mission.[38] Other potential stations noted in 2014 included a station at 30th Street/Mission in San Francisco, an infill station between Richmond and El Cerrito del Norte, and four Oakland stations at Children's Hospital Oakland, San Antonio/Brooklyn Basin, Melrose and Elmhurst.[62]

The City of Fremont re-evaluated the Irvington station's environmental impact report in 2017, and a station area plan was adopted by the Fremont City Council and approved by the BART Board of Directors in 2019.[63][64] As of January 2019, estimates from the city anticipated construction to begin in 2022, with the Irvington station opening for service in 2026.[64]

References edit

  1. ^ "The Composite Report Bay Area Rapid Transit". Archive.org. Parsons Brinckerhoff / Tudor / Bechtel. Retrieved July 23, 2018.
  2. ^ "Celebrating 40 Years of Service 1972 • 2012 Forty BART Achievements Over the Years" (PDF). Bay Area Rapid Transit (BART). 2012. Retrieved December 2, 2014.
  3. ^ "New BART service to Oakland International Airport now open". Bay Area Rapid Transit (BART). November 21, 2014. Retrieved December 2, 2014.
  4. ^ Childress, Brandi (March 12, 2012). . VTA News. Archived from the original on October 19, 2017. Retrieved April 13, 2018.
  5. ^ "BART to Berryessa: Sales tax projections force VTA to scale back plans". San Jose Mercury News. February 27, 2009. Retrieved February 27, 2009.
  6. ^ . Santa Clara Valley Transportation Authority (VTA). June 22, 2005. Archived from the original on September 30, 2007. Retrieved August 27, 2007.
  7. ^ . www.sanjoseca.gov. Archived from the original on April 14, 2018. Retrieved April 13, 2018.
  8. ^ a b Meacham, Jody (January 23, 2017). "Are you ready for a subway? Digging for BART begins in two years". Silicon Valley Business Journal. Retrieved February 15, 2017.
  9. ^ "Downtown San Jose Subway Fact Sheet" (PDF). Santa Clara Valley Transportation Authority (VTA). May 14, 2002. (PDF) from the original on September 27, 2007. Retrieved August 27, 2007.
  10. ^ . KGO-TV ABC San Francisco. May 8, 2009. Archived from the original on June 29, 2011. Retrieved September 17, 2010.
  11. ^ "VTA Board Approves Staff Recommendation for BART Silicon Valley Phase II Project". www.vta.org. Retrieved April 13, 2018.
  12. ^ Plater, Roz (January 20, 2019). "BART Construction Prep to Cause Delays in Downtown San Jose". NBC. Retrieved March 3, 2019.
  13. ^ "Santa Clara VTA first agency to submit expedited federal funding request for BART Phase II". Mass Transit. June 29, 2020. Retrieved May 28, 2021.
  14. ^ "Union Pacific closes land and track sale to VTA". Silicon Valley/San Jose Business Journal. December 2002. Retrieved August 27, 2007.
  15. ^ Tom, Bulger (February 24, 2005). . Government Relations Inc. Archived from the original (DOC) on December 29, 2016. Retrieved July 15, 2014.
  16. ^ "History of BART to the South Bay". San Jose Mercury News. January 8, 2005. Retrieved July 15, 2014.
  17. ^ "LIST OF LOCAL MEASURES PRESIDENTIAL GENERAL ELECTION" (PDF). COUNTY OF SANTA CLARA 2/3 Vote. November 4, 2008. Archived from the original (PDF) on December 19, 2008.
  18. ^ . Santa Clara Valley Transportation Authority (VTA). August 7, 2008. Archived from the original (PDF) on July 19, 2014. Retrieved July 15, 2014.
  19. ^ "Measure B reaches two-thirds approval in late vote counting". San Jose Mercury News. November 17, 2008. Retrieved November 17, 2008.
  20. ^ "BART backers pop open champagne, celebrate vision for San Jose's Grand Central Station". San Jose Mercury News. November 21, 2008. Retrieved November 21, 2008.
  21. ^ "November 4 Presidential Primary Election SUMMARY RESULTS - MEASURE B". Santa Clara County Government. November 21, 2008. from the original on November 16, 2008. Retrieved November 21, 2008.
  22. ^ Lin II, Rong-Gong (November 9, 2016). "Bay Area voters supporting BART renovation and extension to downtown San Jose". Los Angeles Times. Retrieved February 15, 2017.
  23. ^ . BART. January 23, 2013. Archived from the original on March 9, 2021. Retrieved July 26, 2013.
  24. ^ a b Matthews, Sam (April 28, 2017). "Closer to a BART connection". Tracy Press. Retrieved June 2, 2017.
  25. ^ a b "BART Pauses Planning for Dublin Parking Garage". The Independent. February 16, 2017. Retrieved February 16, 2017.
  26. ^ . Altamont Commuter Express. Archived from the original on July 3, 2010. Retrieved August 10, 2010.
  27. ^ . Livermore Amador Valley Transit Authority. Archived from the original on April 19, 2011. Retrieved August 10, 2010.
  28. ^ "Wheels - Fares and Sales". Livermore Amador Valley Transit Authority. from the original on August 1, 2010. Retrieved August 10, 2010.
  29. ^ "BART Board selects alignment for Livermore extension". Transbayblog.com. Retrieved November 17, 2008.
  30. ^ Courtney, Jennifer (July 12, 2011). . Livermore Patch. Archived from the original on September 10, 2011. Retrieved January 8, 2013.
  31. ^ "BART to Livermore Extension Project". Bay Area Rapid Transit (BART). June 12, 2014. Retrieved July 16, 2014.
  32. ^ Richards, Gary (December 18, 2015). . San Jose Mercury News. Archived from the original on March 12, 2016. Retrieved March 9, 2016.
  33. ^ "Isabel BART Station Plans in the Works". The Independent. September 17, 2015. Retrieved November 1, 2015.
  34. ^ Matier, Phil; Ross, Andy (October 3, 2016). "Politicians look for way to link BART to Central Valley". San Francisco Chronicle. Retrieved October 4, 2016.
  35. ^ Angela Ruggiero, Angela Ruggiero (April 11, 2017). "Livermore says BART board doesn't care, wants local control". Vallejo Times-Herald. Retrieved May 23, 2017.
  36. ^ "AB-758 Transportation: Tri-Valley-San Joaquin Valley Regional Rail Authority". Retrieved October 17, 2017.
  37. ^ Baldassari, Erin (May 24, 2018). "BART rejects Livermore expansion; mayor vows rail connection". East Bay Times. Retrieved May 25, 2018.
  38. ^ a b (PDF). Bay Area Rapid Transit (BART). April 25, 2013. Archived from the original (PDF) on July 19, 2014. Retrieved July 15, 2014.
  39. ^ a b c Cabanatuan, Michael (June 22, 2007). "BART's New Vision: More, Bigger, Faster". San Francisco Chronicle. p. A1. Retrieved May 27, 2017.
  40. ^ Rudick, Roger (April 20, 2016). "SPUR Meeting Pushes Second Transbay Tube". Streetsblog SF. Retrieved June 18, 2018.
  41. ^ Fortson, Jobina (November 15, 2018). "BART considering 2nd Transbay Tube, 24 hour service". ABC 7 KGO-TV. Retrieved November 18, 2018.
  42. ^ Bizjak, Tony (February 20, 2019). "How trains under the bay - not high-speed rail - may connect Sacramento and San Francisco". Sacramento Bee. Retrieved February 28, 2019.
  43. ^ "Link21".
  44. ^ Szymanski, Kyle. "eBART extension to Brentwood still a distant idea". The Press. Brentwood, California: Brentwood Press & Publishing. Retrieved May 27, 2016.
  45. ^ CDM Smith. "eBART Next Segment Study" (PDF). Bay Area Rapid Transit (BART). Retrieved January 19, 2016.
  46. ^ "BART: Board vote brings commuter rail closer to Brentwood". The Mercury News. May 12, 2017. Retrieved May 15, 2017.
  47. ^ a b Rodriguez, Joe Fitzgerald (October 19, 2019). "BART looking west toward Geary Boulevard in transbay crossing study". San Francisco Examiner. Retrieved October 21, 2019.
  48. ^ Drake, Gerard. (PDF). Wilbur Smith and Associates. Archived from the original (PDF) on October 13, 2016. Retrieved February 15, 2017.
  49. ^ (PDF). Korve Engineering, Inc. Archived from the original (PDF) on September 13, 2015. Retrieved February 15, 2017.
  50. ^ (PDF). West County High-Capacity Transit Study. West Contra Costa Transportation Advisory Committee. Archived from the original (PDF) on August 9, 2017. Retrieved January 27, 2019.
  51. ^ Radin, Rick (March 28, 2017). "West Contra Costa studying I-80 corridor gridlock solutions". East Bay Times. Retrieved April 9, 2017.
  52. ^ . Archived from the original on March 29, 2018. Retrieved August 9, 2017.
  53. ^ "BART extension to Hercules raises questions about housing density and station location". May 13, 2013.
  54. ^ "Hercules says no to BART extension study". May 16, 2013.
  55. ^ "Should BART Extend to Pinole and Hercules?". March 26, 2013.
  56. ^ Cabanatuan, Michael (June 13, 2003). "BART ponders eastern extensions / Planned routes call for unfamiliar trains". San Francisco Gate. Retrieved July 17, 2018.
  57. ^ "SAMCEDA 1999 proposal for BART via 101 to Menlo Park". Bay Rail Alliance. June 27, 2004. Retrieved March 15, 2016.
  58. ^ Softky, Marion (July 21, 1999). "Plan dumped to extend BART down Bayshore Freeway to Menlo Park". The Almanac News. Menlo Park. Retrieved March 15, 2016.
  59. ^ John T. Warren and Associates Inc (May 2003). "Cost Estimates" (PDF). Feasibility Study for an Infill BART Station in San Francisco, at 30th & Mission Streets. Bay Area Rapid Transit (BART). p. 64. Retrieved July 16, 2014.
  60. ^ Topakian, Karen (May 2002). "A 30th Street BART Station Would Cost Half a Billion and Take 7 Years to Get Here". The Noe Valley Voice. Retrieved August 15, 2017.
  61. ^ "The Jack London BART Feasibility Study" (PDF). Bay Area Rapid Transit (BART). December 2004. pp. 17–31. Retrieved July 16, 2014.
  62. ^ "BART Vision Plan" (PDF). Bay Area Rapid Transit (BART). 2015. p. 6. Retrieved June 26, 2021.
  63. ^ Geha, Joseph (March 30, 2017). "Fremont: Irvington BART site to be re-evaluated for almost $3 million". East Bay Times. Retrieved March 31, 2017.
  64. ^ a b "Irvington BART Station". City of Fremont. Retrieved October 8, 2019.

External links edit

area, rapid, transit, expansion, throughout, history, area, rapid, transit, there, have, been, plans, extend, service, other, areas, contents, history, proposed, extensions, jose, subway, extension, phase, funding, electoral, history, 2000, 2008, livermore, ex. Throughout the history of Bay Area Rapid Transit there have been plans to extend service to other areas Contents 1 History 2 Proposed extensions 2 1 San Jose subway extension Phase 2 2 1 1 Funding and electoral history 2000 2008 2 2 Livermore extension I 580 Tri Valley Corridor 2 3 BART Metro Vision 2 4 Second Transbay crossing 2 5 eBART extension 2 6 Geary Subway 2 7 wBART extension 2 8 I 680 Corridor 2 9 Menlo Park extension 3 Infill stations 4 References 5 External linksHistory editFurther information History of Bay Area Rapid Transit vteBART Marin Line Legend nbsp NWP right of way nbsp nbsp Ignacio nbsp future phase nbsp Santa Venetia nbsp San Rafael nbsp nbsp nbsp nbsp nbsp nbsp nbsp Corte Madera Creek nbsp nbsp nbsp Corte Madera nbsp nbsp nbsp nbsp Mill Valley nbsp nbsp nbsp Sausalito nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp nbsp Golden Gate Bridgeover the Golden Gate nbsp nbsp nbsp Presidio Avenue nbsp Fillmore Street nbsp Van Ness Avenue nbsp Union Square nbsp nbsp nbsp Kearny Street nbsp nbsp nbsp Montgomery Street nbsp nbsp nbsp The initial 1962 BART maps approved by voters included several lines beyond the core system marked as Possible Future Extensions 1 Some have since come to fruition as previous extensions of the system 2 The extension from Concord to Antioch was carried out in phases with service to North Concord Martinez in 1995 Pittsburg Bay Point in 1996 and the eBART spur which started service in 2018 A line to Livermore was completed as far as Dublin Pleasanton by 1997 with final completion of the envisioned corridor to be carried out by Valley Link Service south of Fremont is expected to reach San Jose and Santa Clara partially via the Caltrain right of way by 2030 It was extended to Warm Springs in 2017 and Berryessa in 2020 Extension from Daly City to the south was completed in phases as the Colma Station opened in 1996 and the line to Millbrae was completed in 2003 with a spur to San Francisco International Airport The full Southern Pacific now Caltrain right of way is being electrified for frequent service with mainline trains separate from BART The Marin Line via Geary was initially cancelled due to the county exiting the planning district over funding and engineering issues There were two possible routes 1 via Geary to Park Presidio then across the Golden Gate Bridge via rails that would have been built into the truss supports under the roadway then after tunneling through the Waldo Grade to Marin City would have emerged from underground and followed the old train tracks north through the county 2 alternatively to tunnel from Fort Mason Aquatic Park to downtown Sausalito and follow the right of way from the old train tracks An additional corridor not part of the 1962 plan completed since the agency s inception is the automated guideway transit spur line that connects BART to Oakland International Airport which opened in 2014 3 nbsp As of August 2021 update the BART map has one route marked for Future Service the second phase of the Silicon Valley BART extension into San Jose shown as a thick gray dashed line The planned Irvington station is also shown Proposed extensions editSan Jose subway extension Phase 2 edit nbsp BART will eventually terminate at Santa Clara Transit Center Main article Silicon Valley BART extension The original plan for the Silicon Valley extension was to continue into downtown San Jose and Santa Clara via subway However in February 2009 projections of lower than expected sales tax receipts from the funding measures forced the Santa Clara Valley Transportation Authority to scale back the extension ending it at the Berryessa North San Jose station and delaying tunneling under downtown San Jose to a future phase of construction making it essentially a Phase 2 of the project The originally planned complete extension from Fremont to Santa Clara had been projected to cost 6 1 billion but the VTA estimates the extension to Berryessa Phase 1 only would cost just 2 3 billion 4 5 The plans for the downtown subway start with a portal before crossing under US 101 with subway stations at 28th Street Little Portugal Downtown San Jose station The Downtown San Jose station was combined in 2005 from earlier plans for separate subway stations at Civic Plaza San Jose State University and Market Street 6 and Diridon Arena The line would exit to the surface after crossing under I 880 and terminate at a Santa Clara BART station co located at the existing Santa Clara Depot Separate construction plans by San Jose International Airport would bring a people mover train to either the Santa Clara Depot or to Diridon Station 7 For the subway segment in San Jose VTA plans to use a tunnel boring machine for most of the length in order to reduce disruptions to downtown during construction 8 Only the station locations would have cut and cover construction 9 This is different from how BART subways and stations were built in San Francisco and Oakland which used the cut and cover method The construction of the cut and cover stations in downtown San Jose would still cause major albeit temporary disruption including closing several blocks of Santa Clara Street and severing the VTA light rail line at that street The extension to downtown San Jose could open 2026 contingent on approval of funding 10 As of April 2018 the plan was to have a single bore tunnel under Santa Clara Street with cut and cover construction at the station locations only 11 Utility relocation started and soil samples were taken in February 2019 with construction to begin in 2022 12 13 Funding and electoral history 2000 2008 edit Because Santa Clara County is not among the member counties of the BART District having opted out at the district s inception like neighboring San Mateo County VTA is responsible for building the extension within Santa Clara County VTA allocated initial funds for constructing BART using the proceeds from a sales tax referendum which was passed by Santa Clara County voters in 2000 In December 2002 VTA purchased a freight railroad corridor from Union Pacific Railroad which will serve as much of the necessary right of way for both the Warm Springs and San Jose extensions for 80 million 14 In 2004 the Federal Transit Administration decided to wait to fund the project citing worries that BART did not have enough money to operate the extension 15 In addition the San Jose extension project received a not recommended rating from the Federal Transit Administration placing the federal portion of the funding in jeopardy because of concerns about operation and maintenance funding 16 Santa Clara County voters passed Measure B in 2008 a 1 8 cent sales tax raise 17 Projections by an independent consultant recommended by the Federal Transit Administration predicted that the 1 8 cent sales tax would more than cover operation and maintenance of the proposed extension 18 19 20 21 San Jose voters passed Measure B in 2016 which allowed for final funding of the subway 22 8 Livermore extension I 580 Tri Valley Corridor edit A proposed extension will further service from Dublin Pleasanton station east to Livermore either via traditional BART infrastructure diesel multiple unit technology 23 24 similar to eBART or enhanced bus service 25 It could possibly continue over the Altamont Pass into Tracy and the Central Valley along I 580 and or go north through Dublin San Ramon Danville and Alamo to the existing Walnut Creek station via the I 680 corridor An existing diesel commuter rail line the Altamont Corridor Express ACE currently operates through Livermore The two systems are linked though not directly by a free shuttle bus which transfers passengers between the ACE Pleasanton station and the BART Dublin Pleasanton station 26 27 28 A preferred alignment was selected July 1 2010 and originally had the support of the Livermore City Council This plan would have involved the construction of a station in downtown Livermore and a second station on Vasco Road near Lawrence Livermore National Laboratory and Sandia National Laboratories Both proposed stations would have provided nearby connections to Altamont Corridor Express service 29 However in July 2011 the Livermore City Council reversed its position in response to a petition requesting that the alignment stay within or nearby the Interstate 580 right of way and now favors stations be built at the Interstate 580 interchanges with Isabel Avenue and Greenville Road 30 BART s Environmental Impact Report Notice of Preparation issued in September 2012 proposed a single station at I 580 and Isabel Avenue with possible express bus services connecting to the Vasco Road ACE station and a park and ride lot at I 580 and Greenville Road 31 Land use plans and studies were being prepared by the city of Livermore in September 2015 with completion envisioned in 2026 25 32 33 Additional funding for consulting and planning were allocated in late 2016 against the wishes of then BART District President Tom Radulovich 34 On July 31 2017 BART released the Draft Environmental Impact Report of the project citation needed The direct BART to ACE connection was studied in preparation for ACEforward projects citation needed In 2017 citing lack of interest in the project from BART the Livermore City Council proposed a newly established local entity to undertake planning and construction of the extension 35 which was also recommended by the California State Assembly Transportation Committee 24 The Tri Valley San Joaquin Valley Regional Rail Authority was established that year for purposes of planning developing and delivering cost effective and responsive transit connectivity between the Bay Area Rapid Transit District s rapid transit system and the Altamont Corridor Express commuter rail service in the Tri Valley that meets the goals and objectives of the community 36 On May 24 2018 the BART board voted against a full rapid transit BART build or a bus rapid transit system to extend service east from Dublin Pleasanton station thus granting the new authority oversight and funding for constructing a new service Moneys previously allocated to BART to construct a Livermore extension were forfeited to the authority by July 1 2018 37 BART Metro Vision edit Key components of the overall vision for BART s future dubbed BART Metro Vision include more capacity in stations increased train frequency to allow for show up and go service at stations within the system s operational core and increased performance reliability The most recent report from BART Metro Vision also identifies improvements to its rolling stock the Hayward Maintenance Complex and the modernization of its train control system as key improvements for securing the system s long term viability 38 Second Transbay crossing edit Part of BART s 50th anniversary service planning included a new separate Transbay Tube beneath San Francisco Bay running parallel to and south of the existing tube This would emerge at the Transbay Transit Center to provide connecting service to Caltrain and the planned California High Speed Rail CAHSR system The additional four bore Transbay Tube would provide two additional tracks for BART trains and two tracks for conventional high speed rail the BART system and conventional U S rail use different and incompatible rail gauges and operate under different sets of safety regulations 39 Transit advocacy groups in the Bay Area such as SPUR 40 have long promoted larger scale expansion of the BART system through various capital projects one identified as a long term goal in the Metro Vision is the construction of a second four bore rail tunnel under San Francisco Bay increasing connectivity and capacity of the system The second crossing would likely route to the Transbay Transit Center for connections with conventional mainline rail services In 2018 BART announced that a feasibility study for installing a second transbay crossing would commence the following year 41 By 2019 the Capitol Corridor Joint Powers Authority had joined with BART to study a multi modal crossing which could also allow Capitol Corridor and San Joaquin routes to serve San Francisco directly 42 In 2021 the Link21 program was announced using funding from Regional Measure 3 The program initially proposed a 4 track transbay crossing for both BART and commuter rail however this was pared back to 2 tracks The likely long term plan is for the second transbay crossing to be electrified commuter rail connecting CalTrain which is partially governed by BART to the Capitol Corridor 43 eBART extension edit Expansions of the DMU serviced eBART system come at a lower cost per mile than conventional wide gauge BART infrastructure Service could extend to Oakley 44 45 or Brentwood 46 Geary Subway edit Main article Geary Subway Part of the plan for the original system before Marin County s departure from the BART District was a line running under Geary Street and turning north to the Golden Gate Bridge When Marin County pulled out of the transit district some plans called for a subway only extending down Geary but these too were soon scrapped In 1995 the San Francisco Municipal Railway hired Merrill amp Associates to study the possibility of building a new BART subway beneath Geary in conjunction with adding light rail on the surface The estimated cost of construction as far as Park Presidio Boulevard was 1 4 billion in 1995 2 8 billion adjusted for inflation Projections from this study put BART ridership at 18 000 daily boardings and the alignment would allow for a further extension to Marin These plans were dropped according to former Senator Quentin L Kopp due to merchant and resident opposition citing potential blight similar to that caused by Market Street Subway construction two decades earlier 47 Ongoing studies will determine whether the corridor may one day be served by future BART service It may be constructed as an extension of the second Transbay Tube 39 47 wBART extension edit The only branch of the original BART system that has not been extended since service commenced is the line ending at Richmond station Possible alignments for an extension further north were examined in 1983 48 1992 49 and 2017 50 Both newly constructed BART wide gauge electrified rail and the use of existing freight rail rights of way and tracks with more readily available standard gauge trains were considered Potential station locations include Hilltop Mall Pinole and Hercules Transit Center The cost of an extension to Hercules Transit Center utilizing mainline BART technology was estimated at 3 6 billion in 2017 with a ridership of 21 980 by 2040 51 The extension to Hercules is controversial in that the main proponent wants to build it directly from the El Cerrito del Norte BART station while the city of Richmond is very opposed to this Furthermore the majority of the Hercules city council opposes the extension as they believe it will detract from their plan to develop Hercules station 52 53 54 55 I 680 Corridor edit Service in the Tri Valley area had previously been considered with diesel multiple service originating at Walnut Creek and running as far east as Tracy 56 As part of BART s 50th anniversary and envisioning another fifty years of service planners foresaw a new East Bay alignment originating at Warm Springs station and running via Interstate 680 to the Martinez Amtrak station It would connect to the existing stations at Dublin Pleasanton and Walnut Creek 39 Menlo Park extension edit In 1999 a short lived proposal to extend BART from the Millbrae station then under construction to Menlo Park was advanced by the San Mateo County Economic Development Association SAMCEDA The proposed routing would have followed the Caltrain tracks to the Broadway station in Burlingame and then would run along the median of Bayshore Freeway to Menlo Park with stations in San Mateo Belmont San Carlos Redwood City and Menlo Park Cost estimates ranged up to US 2 500 000 000 equivalent to 4 570 000 000 in 2023 drawing funding from a 1 2 cent sales tax increase in San Mateo County 57 BART leadership warned the timing was not appropriate for a push further south into San Mateo County and SAMCEDA withdrew the proposal by the summer of 1999 58 Infill stations editInfill stations are stations constructed on existing line segments between two existing stations The Embarcadero 1976 and West Dublin Pleasanton 2011 stations are the only infill stations currently in the BART system The Doolittle Maintenance and Storage Facility initially slated to be opened as a full station along the Oakland Airport Connector may be repurposed for passenger service at a later date Construction costs for a planned 30th Street Mission station in San Francisco between the existing 24th Street Mission and Glen Park stations were estimated at 500 million in 2003 59 60 A proposal for a Jack London Square station in Oakland was rejected in 2004 as being incompatible with existing track geometry a one station stub line at the foot of Broadway and the use of other transit modes also were studied 61 BART planners studied additional stations at four other sites within the system in 2007 Albany Calaveras Irvington and 30th Street Mission 38 Other potential stations noted in 2014 included a station at 30th Street Mission in San Francisco an infill station between Richmond and El Cerrito del Norte and four Oakland stations at Children s Hospital Oakland San Antonio Brooklyn Basin Melrose and Elmhurst 62 The City of Fremont re evaluated the Irvington station s environmental impact report in 2017 and a station area plan was adopted by the Fremont City Council and approved by the BART Board of Directors in 2019 63 64 As of January 2019 update estimates from the city anticipated construction to begin in 2022 with the Irvington station opening for service in 2026 64 References edit The Composite Report Bay Area Rapid Transit Archive org Parsons Brinckerhoff Tudor Bechtel Retrieved July 23 2018 Celebrating 40 Years of Service 1972 2012 Forty BART Achievements Over the Years PDF Bay Area Rapid Transit BART 2012 Retrieved December 2 2014 New BART service to Oakland International Airport now open Bay Area Rapid Transit BART November 21 2014 Retrieved December 2 2014 Childress Brandi March 12 2012 VTA and FTA Seal the Deal for BART Silicon Valley VTA News Archived from the original on October 19 2017 Retrieved April 13 2018 BART to Berryessa Sales tax projections force VTA to scale back plans San Jose Mercury News February 27 2009 Retrieved February 27 2009 Minutes of Silicon Valley Rapid Transit Corridor BART Extension Policy Advisory Board Meeting Santa Clara Valley Transportation Authority VTA June 22 2005 Archived from the original on September 30 2007 Retrieved August 27 2007 San Jose CA Official Website Automated Transit Network www sanjoseca gov Archived from the original on April 14 2018 Retrieved April 13 2018 a b Meacham Jody January 23 2017 Are you ready for a subway Digging for BART begins in two years Silicon Valley Business Journal Retrieved February 15 2017 Downtown San Jose Subway Fact Sheet PDF Santa Clara Valley Transportation Authority VTA May 14 2002 Archived PDF from the original on September 27 2007 Retrieved August 27 2007 South Bay BART initiatives move forward KGO TV ABC San Francisco May 8 2009 Archived from the original on June 29 2011 Retrieved September 17 2010 VTA Board Approves Staff Recommendation for BART Silicon Valley Phase II Project www vta org Retrieved April 13 2018 Plater Roz January 20 2019 BART Construction Prep to Cause Delays in Downtown San Jose NBC Retrieved March 3 2019 Santa Clara VTA first agency to submit expedited federal funding request for BART Phase II Mass Transit June 29 2020 Retrieved May 28 2021 Union Pacific closes land and track sale to VTA Silicon Valley San Jose Business Journal December 2002 Retrieved August 27 2007 Tom Bulger February 24 2005 February 2005 Monthly Report for MTC Government Relations Inc Archived from the original DOC on December 29 2016 Retrieved July 15 2014 History of BART to the South Bay San Jose Mercury News January 8 2005 Retrieved July 15 2014 LIST OF LOCAL MEASURES PRESIDENTIAL GENERAL ELECTION PDF COUNTY OF SANTA CLARA 2 3 Vote November 4 2008 Archived from the original PDF on December 19 2008 BOARD OF DIRECTORS MEETING AGENDA Santa Clara Valley Transportation Authority VTA August 7 2008 Archived from the original PDF on July 19 2014 Retrieved July 15 2014 Measure B reaches two thirds approval in late vote counting San Jose Mercury News November 17 2008 Retrieved November 17 2008 BART backers pop open champagne celebrate vision for San Jose s Grand Central Station San Jose Mercury News November 21 2008 Retrieved November 21 2008 November 4 Presidential Primary Election SUMMARY RESULTS MEASURE B Santa Clara County Government November 21 2008 Archived from the original on November 16 2008 Retrieved November 21 2008 Lin II Rong Gong November 9 2016 Bay Area voters supporting BART renovation and extension to downtown San Jose Los Angeles Times Retrieved February 15 2017 Livermore Extension BART January 23 2013 Archived from the original on March 9 2021 Retrieved July 26 2013 a b Matthews Sam April 28 2017 Closer to a BART connection Tracy Press Retrieved June 2 2017 a b BART Pauses Planning for Dublin Parking Garage The Independent February 16 2017 Retrieved February 16 2017 Pleasanton Station ACE Rail Stations Altamont Commuter Express Archived from the original on July 3 2010 Retrieved August 10 2010 Wheels Timetables Route 54 Pleasanaton Fairgrounds ACE Shuttle Livermore Amador Valley Transit Authority Archived from the original on April 19 2011 Retrieved August 10 2010 Wheels Fares and Sales Livermore Amador Valley Transit Authority Archived from the original on August 1 2010 Retrieved August 10 2010 BART Board selects alignment for Livermore extension Transbayblog com Retrieved November 17 2008 Courtney Jennifer July 12 2011 City Council OKs Initiative to Keep BART on I 580 Livermore Patch Archived from the original on September 10 2011 Retrieved January 8 2013 BART to Livermore Extension Project Bay Area Rapid Transit BART June 12 2014 Retrieved July 16 2014 Richards Gary December 18 2015 Roadshow BART down I 680 not a consideration San Jose Mercury News Archived from the original on March 12 2016 Retrieved March 9 2016 Isabel BART Station Plans in the Works The Independent September 17 2015 Retrieved November 1 2015 Matier Phil Ross Andy October 3 2016 Politicians look for way to link BART to Central Valley San Francisco Chronicle Retrieved October 4 2016 Angela Ruggiero Angela Ruggiero April 11 2017 Livermore says BART board doesn t care wants local control Vallejo Times Herald Retrieved May 23 2017 AB 758 Transportation Tri Valley San Joaquin Valley Regional Rail Authority Retrieved October 17 2017 Baldassari Erin May 24 2018 BART rejects Livermore expansion mayor vows rail connection East Bay Times Retrieved May 25 2018 a b BART Metro Vision Update PDF Bay Area Rapid Transit BART April 25 2013 Archived from the original PDF on July 19 2014 Retrieved July 15 2014 a b c Cabanatuan Michael June 22 2007 BART s New Vision More Bigger Faster San Francisco Chronicle p A1 Retrieved May 27 2017 Rudick Roger April 20 2016 SPUR Meeting Pushes Second Transbay Tube Streetsblog SF Retrieved June 18 2018 Fortson Jobina November 15 2018 BART considering 2nd Transbay Tube 24 hour service ABC 7 KGO TV Retrieved November 18 2018 Bizjak Tony February 20 2019 How trains under the bay not high speed rail may connect Sacramento and San Francisco Sacramento Bee Retrieved February 28 2019 Link21 Szymanski Kyle eBART extension to Brentwood still a distant idea The Press Brentwood California Brentwood Press amp Publishing Retrieved May 27 2016 CDM Smith eBART Next Segment Study PDF Bay Area Rapid Transit BART Retrieved January 19 2016 BART Board vote brings commuter rail closer to Brentwood The Mercury News May 12 2017 Retrieved May 15 2017 a b Rodriguez Joe Fitzgerald October 19 2019 BART looking west toward Geary Boulevard in transbay crossing study San Francisco Examiner Retrieved October 21 2019 Drake Gerard West Contra Costa Extension Study Final Report PDF Wilbur Smith and Associates Archived from the original PDF on October 13 2016 Retrieved February 15 2017 West Contra Costa Extension Alignment Study PDF Korve Engineering Inc Archived from the original PDF on September 13 2015 Retrieved February 15 2017 West Contra Costa High Capacity Transit Study PDF West County High Capacity Transit Study West Contra Costa Transportation Advisory Committee Archived from the original PDF on August 9 2017 Retrieved January 27 2019 Radin Rick March 28 2017 West Contra Costa studying I 80 corridor gridlock solutions East Bay Times Retrieved April 9 2017 BART extension to Hercules still being studied and sorely needed director says Richmond Standard Archived from the original on March 29 2018 Retrieved August 9 2017 BART extension to Hercules raises questions about housing density and station location May 13 2013 Hercules says no to BART extension study May 16 2013 Should BART Extend to Pinole and Hercules March 26 2013 Cabanatuan Michael June 13 2003 BART ponders eastern extensions Planned routes call for unfamiliar trains San Francisco Gate Retrieved July 17 2018 SAMCEDA 1999 proposal for BART via 101 to Menlo Park Bay Rail Alliance June 27 2004 Retrieved March 15 2016 Softky Marion July 21 1999 Plan dumped to extend BART down Bayshore Freeway to Menlo Park The Almanac News Menlo Park Retrieved March 15 2016 John T Warren and Associates Inc May 2003 Cost Estimates PDF Feasibility Study for an Infill BART Station in San Francisco at 30th amp Mission Streets Bay Area Rapid Transit BART p 64 Retrieved July 16 2014 Topakian Karen May 2002 A 30th Street BART Station Would Cost Half a Billion and Take 7 Years to Get Here The Noe Valley Voice Retrieved August 15 2017 The Jack London BART Feasibility Study PDF Bay Area Rapid Transit BART December 2004 pp 17 31 Retrieved July 16 2014 BART Vision Plan PDF Bay Area Rapid Transit BART 2015 p 6 Retrieved June 26 2021 Geha Joseph March 30 2017 Fremont Irvington BART site to be re evaluated for almost 3 million East Bay Times Retrieved March 31 2017 a b Irvington BART Station City of Fremont Retrieved October 8 2019 External links edit nbsp Wikimedia Commons has media related to BART construction BART home page BART Projects BART Planning BART Silicon Valley Extension at Santa Clara Valley Transportation Authority VTA Oakland Airport Connector Animation Retrieved from https en wikipedia org w index php title Bay Area Rapid Transit expansion amp oldid 1213224906, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.