fbpx
Wikipedia

Wind power in Massachusetts

The U.S. state of Massachusetts has vast wind energy resources offshore, as well as significant resources onshore. The 2016 update to the states's Clean Energy and Climate Plan had a goal of reducing 1990 baseline greenhouse gas emissions levels by 25% by 2020.[1] Current goals include installing 3,500 megawatts (MW) of offshore wind power in the state by 2035.[2] However, as of Q4 2021 the state had only 120 MW of wind powered electricity generating capacity, responsible for generating 0.9% of in-state electricity production. The state has awarded contracts to two offshore projects, the 800 MW Vineyard Wind project and 804 MW Mayflower Wind project.[3] Construction began on the Vineyard Wind 1 project on November 18, 2021, after a long fight for approval.[4] Commonwealth Wind was selected for development in 2021, but the developer has attempted to cancel the project due to increased costs. There are eight projects planned for off the southern coast of Massachusetts, though some will deliver power to Rhode Island, Connecticut, and New York.[5]

Massachusetts Maritime Academy
wind turbine
IBEW wind turbine along I-93

Notable onshore projects edit

Installed in 2005, the International Brotherhood of Electrical Workers (IBEW) 100 kW wind turbine along I-93 south of Boston drew attention to wind power to tens of thousands of commuters.[6] In 2009, a similar wind turbine was installed along I93 north of Boston, in Medford, expected to generate 170,000 kWh/year.[7][8]

A GE Wind Energy 1.5 MW turbine was the first wind turbine to be installed at a ski resort in the United States of America at Jiminy Peak in Hancock, MA. The turbine, installed in 2007, is visible from many of the slopes on the mountain and it produces 4,600 MWh annually, about one third of the facilities electricity demands.[9]

At the Joint Base Cape Cod three turbines generate power for the base and construction is underway for two additional 1.68 MW turbines to power the radar unit. The three, soon to be five, turbines are highly visible from both the Bourne Bridge and the Sagamore Bridge looking to the East. The turbines have resulted in significant savings for the base, the turbines also do not generate any controversy because they are located well within the base boundaries far from civilian homes.[10]

In June 2017, the Massachusetts courts shut down two town-owned 1.65-megawatt wind turbines in Falmouth, Massachusetts. Each turbine generates up to 110 decibels of noise requiring almost 3000-foot setback. The decibel level for two wind turbines operating at the same time is unknown. Massachusetts has twenty-one communities with noise and alleged shadow flicker health issues. The neighbors describe the noise as torture. The Town of Falmouth in November 2019 approved 2.5 million to disassemble and store the wind turbines. The turbines were designed in the late 1990s and have the original gearboxes and blades.[11]

Offshore wind edit

 
Wind energy lease areas off the southern coasts of Massachusetts and Rhode Island as of October 2022

Cape Wind was an offshore wind farm that would have produced 450 MW, enough electricity to power nearly 420,000 homes using 130 wind turbines,[12] The project made its first federal filings in 2001, and faced a lengthy federal, state, and municipal permitting processes and considerable local controversy because of its location (in federal waters) between Cape Cod, Nantucket, and Martha's Vineyard, within sight of the mainland. It was cancelled in 2017 after losing utility support.

On August 8, 2016 the Massachusetts governor signed Bill H.4568 which mandates that Massachusetts utilities obtain 1.6 GW of offshore wind power by 2027.[13][14] Policy also mandated that utilities acquire 1.2 GW of power from other renewable sources, including onshore wind.[15]

On December 14, 2018, the U.S. Bureau of Ocean Energy Management (BOEM) opened bids for leases on three parcels, each 13,000 acres, located in federal waters south of Martha's Vineyard and Nantucket. The three tentative winners, subject to final negotiations, were:

The auction raised a total of $405 million. The three areas could support 4.1 gigawatts of wind nameplate power, according to BOEM estimates.[17]

In April 2019, Vineyard Wind was awarded a contract to supply 800 MW of power to Massachusetts utilities at a price of 8.9 cents/kWh and will also spend $15 million on battery systems for energy storage.[18] They plan to install 84 turbines, with their power line running between the Vineyard and Nantucket to Covell Beach in Centerville, and from there via land to the grid.[19] The vessels used must comply with the Jones Act.[20] Final major federal approval was granted on May 11, 2021.[21] Power from the first turbine started flowing into the ISO New England grid on January 2, 2024.[22] Construction is expected to be complete by the end of 2024.[22]

Commonwealth Wind (lease area OCS-A 0534)[23] was selected for development in 2021, and signed agreements with all three major Massachusetts electric utilities - Eversource, National Grid, and Unitil.[24] In 2022, developer Avangrid asked that its project be canceled and rebid due to higher supply costs. The Massachusetts Department of Public Utilities rejected this request and approved the Commonwealth Wind and Mayflower Wind agreements instead.[25] A Mayflower Wind cable is expected to come ashore at the site of the former coal-powered Brayton Point Power Station,[26] which already has transmission infrastructure.

The Park City Wind project[27] would supply power to Connecticut but land cables in Barnstable on Cape Cod. Avangrid attempted to renegotiate its agreement with Connecticut due to cost increases.[26]

The proposed offshore Bay State Wind project failed to arrange purchasing agreements in Massachusetts. The joint venture between Eversource and Ørsted proposed a new design called Revolution Wind 2, to supply clean electricity to Rhode Island Energy.[28]

Current state support edit

The state has implemented policy and infrastructure to support efforts to reduce greenhouse gas emissions. These policies and infrastructure are partially focused on promoting on- and off-shore wind power.

Policy edit

Green Communities Act (2008): created a commission to provide technical and financial support to reduce energy costs, strengthen local economies, and support renewable energy efforts.[2]

Green Jobs Act (2008): created the Massachusetts Clean Energy Center (MassCEC), which is a state authority designated for “job development and economic development in the clean energy sector.” The Act created the Alternative and Clean Energy Investment Trust Fund to further this economic development.[29]

Global Warming Solutions Act (2008): requires reduction in 1990 greenhouse gas emission levels to 25% by 2020, and at least an 80% reduction by 2050. Policy information and figures depicting state progress can be viewed on the Mass.gov website.[30]

New Bedford Marine Commerce Terminal edit

The New Bedford Marine Commerce Terminal is the first hub in the country designed for the deployment of offshore wind farms.[31] The terminal is managed by the Massachusetts Clean Energy Center which supports the fabrication and implementation of offshore wind projects and the transportation of large scale marine cargo. The Terminal contains 26 acres of storage space that can be used by businesses and to aid shipping and transportation. Besides the auxiliary I-195 interstate running directly through New Bedford's downtown, it also has access roads to two highways, I-495 and I-95, and is accessible from other ports.[32]

Wind Technology Testing Center (WTTC) edit

 
Massachusetts Wind Technology Testing Center

The Massachusetts Wind Technology Testing Center in Charlestown is managed by the Massachusetts Clean Energy Center. The center offers testing for blades up to 90 meters long and different prototyping methods in order to support the production and installation of land and offshore wind turbines. The blade testing is required for turbines to meet international qualifications and to be certified for use.[33]

Charlie Baker administration (2015–2023) edit

In July 2015, the administration of Massachusetts Governor Charlie Baker announced that Baker filed legislation to require the state to procure 1,600 megawatts of offshore wind power, as well as 1,200 megawatts of hydropower.[34] In March 2016, the legislation received the endorsement of all three of the Energy and Environmental Affairs Secretaries of the Deval Patrick administration,[35] and the following August, Baker signed the legislation into law.[36] In September 2016, Baker's administration announced that the offshore wind companies Deepwater Wind, DONG Energy, and OffshoreMW agreed to use the New Bedford Marine Commerce Terminal built during the Patrick administration as a staging area for their projects.[37] In June 2017, Massachusetts utilities issued the first RFP under the energy diversification law signed by Baker in August 2016,[38] and the following month, five major bids were submitted.[39]

In May 2018, Baker's administration selected Vineyard Wind to construct an 800-megawatt offshore wind farm off the southern coast of Martha's Vineyard,[40] and the following October, Vineyard Wind announced that it had signed an 18-month lease to also conduct their staging operations at the New Bedford Marine Commerce Terminal.[41] In December 2018, the Bureau of Ocean Energy Management announced the sale of three wind lease plots of 390,000 acres of ocean south of Nantucket and Martha's Vineyard to Equinor Wind, Mayflower Wind, and Vineyard Wind for a national record of $405 million that the agency estimated could generate as much as 4,100 megawatts of wind power.[42] In May 2021, the U.S. Department of the Interior announced that a record of decision had been issued giving final federal approval for the Vineyard Wind project.[43]

An Offshore Wind Study published in mid-2020 analyzed procuring an additional 1.6 GW of off-shore capacity in addition to the 1.6 GW already in progress.[44]

In late 2020, the Baker Administration released a Decarbonization Roadmap that aims for net zero greenhouse gas emissions by 2050. The plan calls for major investments in offshore wind and solar energy.[45][46]

Capacity edit

 

Installed edit

The following table shows the growth in wind power installed nameplate capacity in MW for Massachusetts since 1999.[47][48][49][50][51]

Year Amount (MW) Change (MW) % Change
1999 0.3 0
2000 0.3 0 0%
2001 1 0.7 233%
2002 1 0 0%
2003 1 0 0%
2004 1 0 0%
2005 1.1 0.1 10%
2006 3.5 2.4 218%
2007 5 1.5 43%
2008 5.7 0.7 14%
2009 15 9 163%
2010 17.7 2.7 18%
2011 47 29.3 166%
2012 103 56 119%
2013 106 3 3%
2014 107 1 1%
2015 107 0 0%
2016 115 8 7%
2017 115 0 0%
2018 113 -2 -2%
2019 120 7 6%
2020 120 0 0%
 
Offshore Wind Power Capacity

Potential edit

In early 2010, the National Renewable Energy Laboratory released the first comprehensive update of wind energy potential by state since 1993, showing that Massachusetts had potential to install 1,028 MW of onshore wind power, using 80 meter high wind turbines,[52] and 1,913 MW of 100 MW wind turbines could achieve 30% or better capacity factor - and of those, almost 500 MW could reach a capacity factor of 40%.[53]

Locations edit

In 2009, the Massachusetts Department of Energy Resources (DOER) contracted Navigant Consulting to determine new locations of potential wind turbine sites throughout the state. The study identified 44 locations with 947 MW of potential power. The locations are centrally focused in the Berkshire and Barnstable counties.[54] The Massachusetts Executive Office of Energy and Environmental Affairs has this information publicly available with a Wind Energy Site Screening Tool.[55]

Imports edit

To meet renewable power minimums and with state approval, Massachusetts utilities agreed to pay for 40% of the output of the proposed King Pine wind farm in Aroostook County, Maine developed by Longroad Energy. As of January 2023 was approved by the Maine Public Utilities Commission but required further design and approval of the transmission line developed by LS Power of New York.[56]

See also edit

References edit

  1. ^ eea (2016-01-19). "Massachusetts Clean Energy and Climate Plan for 2020". Energy and Environmental Affairs. from the original on 2017-09-16. Retrieved 2017-10-16.
  2. ^ a b (PDF). Archived from the original (PDF) on 2017-02-15. Retrieved 2017-10-16.{{cite web}}: CS1 maint: archived copy as title (link)
  3. ^ "Massachusetts Wind Energy" (PDF). U.S. Wind Energy State Facts. American Wind Energy Association. Retrieved April 30, 2020.
  4. ^ Frangoul, Anmar (November 19, 2021). "Construction starts at America's first major offshore wind farm". CNBC. from the original on November 28, 2021. Retrieved November 26, 2021.
  5. ^ "Offshore wind farms off Cape Cod and Martha's Vineyard: A guide of what to know". Cape Cod Times. from the original on 2023-01-27. Retrieved 2023-01-30.
  6. ^ "Boston's First Wind Turbine Serves as Example". from the original on 2013-05-29. Retrieved 2012-05-15.
  7. ^ "Medford readies wind turbine at site along I-93". from the original on 2012-05-18. Retrieved 2012-05-15.
  8. ^ "Medford Clean Energy Committee". from the original on 2012-05-18. Retrieved 2012-05-15.
  9. ^ . Archived from the original on 2013-09-18. Retrieved 2013-09-10.
  10. ^ "Two more turbines coming soon to cape base". September 7, 2013. from the original on August 9, 2014. Retrieved September 9, 2013.
  11. ^ "Falmouth Town Meeting Approves Funding to Dismantle Town's Turbines". from the original on 2019-12-22. Retrieved 2020-04-03.
  12. ^ "Cape Wind - America's First Offshore Wind Farm". from the original on 2012-05-18. Retrieved 2012-05-15.
  13. ^ "Massachusetts passes bill easing path for 1.6 GW of offshore wind". from the original on 6 August 2016. Retrieved 2 August 2016.
  14. ^ "Bill H.4568". from the original on 2016-11-28. Retrieved 2016-08-02.
  15. ^ "Massachusetts passes bill easing path for 1.6GW of offshore wind". from the original on 2017-08-01. Retrieved 2017-10-16.
  16. ^ "Project". Beacon Wind. September 18, 2023.
  17. ^ Gerdes, Justin (December 17, 2018). "Record-Breaking Massachusetts Offshore Wind Auction Reaps $405 Million in Winning Bids". Green Tech Media. from the original on June 10, 2019. Retrieved May 29, 2019.
  18. ^ Geuss, Megan (April 24, 2019). "Massachusetts offshore wind project gets green light at roughly 8.9 cents/kWh". from the original on May 7, 2021. Retrieved May 29, 2019.]
  19. ^ Gellerman, Bruce (January 19, 2021). "Offshore Wind Backers Hope Vineyard Wind Permitting Woes Will End Under Biden". WBUR. from the original on 2021-01-19. Retrieved 2021-01-20.
  20. ^ Mercure, Matthew (31 March 2021). "Vineyard Wind Selects Contractor for Transport, Installation of Turbines | North American Windpower". nawindpower.com. from the original on 26 April 2021. Retrieved 14 April 2021.
  21. ^ "Biden administration grants Vineyard Wind its final major permit". The Boston Globe. from the original on 2021-05-20. Retrieved 2021-05-28.
  22. ^ a b Sabrina Shankman (January 3, 2024). "With a flip of the switch, offshore wind energy enters New England's grid". The Boston Globe.
  23. ^ "Commonwealth Wind". Commonwealth Wind. August 3, 2023.
  24. ^ Seonwoo, Eunki (December 28, 2022). "Commonwealth Wind wants to back out of contracts".
  25. ^ Service, Colin A. Young | State House News (January 2, 2023). "DPU rejects bid to scrap wind contracts, approves them instead". Salem News.{{cite web}}: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link)
  26. ^ a b "Offshore wind projects face uncertainty with existing contracts. Cape Codders respond". Cape Cod Times.
  27. ^ "Park City Wind". Park City Wind. August 3, 2023.
  28. ^ "Developers pitch new wind power project, enough to power 500,000 R.I. homes - The Boston Globe". BostonGlobe.com.
  29. ^ "The Green Jobs Act of 2008 | Massachusetts' Businesses for Clean Energy". www.mabizforcleanenergy.com. from the original on 2017-10-16. Retrieved 2017-10-16.
  30. ^ eea (2012-05-09). "Massachusetts Global Warming Solutions Act (GWSA)". Energy and Environmental Affairs. from the original on 2017-10-16. Retrieved 2017-10-16.
  31. ^ "Massachusetts Offshore Wind Energy Hub Gets The Green Light". from the original on 2023-02-15. Retrieved 2012-11-21.
  32. ^ "New Bedford Marine Commerce Terminal". Massachusetts Clean Energy Center. 30 May 2017. from the original on 7 September 2017. Retrieved 7 September 2017.
  33. ^ "Wind Technology Testing Center". Mass CEC. 5 March 2013. from the original on 2017-10-30. Retrieved 2017-10-16.
  34. ^ "Baker-Polito Administration Files Hydropower Legislation to Increase Access to Clean, Cost-Effective Renewable Energy". www.mass.gov. July 9, 2015. from the original on March 16, 2018. Retrieved March 11, 2018.
  35. ^ Dezenski, Lauren (March 23, 2016). "Baker musters energy secretaries to push action on hydro bill". Politico. Capitol News Company. from the original on March 12, 2018. Retrieved March 11, 2018.
  36. ^ Schoenberg, Shira (August 8, 2016). "Gov. Charlie Baker signs hydropower, wind energy bill into law". MassLive.com. Advance Publications. from the original on March 12, 2018. Retrieved March 11, 2018.
  37. ^ Serreze, Mary C. (September 6, 2016). "Offshore wind developers agree to use New Bedford Marine Terminal". MassLive.com. Advance Publications. from the original on March 12, 2018. Retrieved March 11, 2018.
  38. ^ Serreze, Mary C. (July 3, 2017). "Massachusetts utilities release first offshore wind RFP under new state energy law". MassLive.com. Advance Publications. from the original on March 12, 2018. Retrieved March 11, 2018.
  39. ^ Serreze, Mary C. (July 28, 2017). "5 major transmission, hydro and wind partners bid into Massachusetts Clean Energy RFP". MassLive.com. Advance Publications. from the original on March 12, 2018. Retrieved March 11, 2018.
  40. ^ Murphy, Matt (May 23, 2018). "Mass. Selects Vineyard Wind For 800-Megawatt Offshore Wind Farm". WBUR. from the original on June 21, 2018. Retrieved June 21, 2018.
  41. ^ "Vineyard Wind Signs Lease For Staging Operations In New Bedford". WBUR. October 22, 2018. from the original on November 15, 2018. Retrieved November 15, 2018.
  42. ^ Moran, Barbara (December 14, 2018). "Offshore Wind Auction For 390,000 Acres South Of Mass. Blows Through Sale Record". WBUR. from the original on December 18, 2018. Retrieved December 17, 2018.
  43. ^ Frangoul, Anmar (May 12, 2021). "'A huge moment': U.S. gives go-ahead for its first major offshore wind farm". CNBC. from the original on July 18, 2022. Retrieved July 18, 2022.
  44. ^ "Massachusetts Offshore Wind Study, 2020". from the original on 2021-01-06. Retrieved 2021-01-05.
  45. ^ Martin, Naomi (December 30, 2020). "Mass. to require all new cars sold to be electric by 2035 as part of climate-change measures". The Boston Globe. from the original on January 26, 2021. Retrieved January 5, 2021.
  46. ^ "Massachusetts 2050 Decarbonization Roadmap". from the original on 2021-01-01. Retrieved 2021-01-05.
  47. ^ Office of Energy Efficiency and Renewable Energy (2010-03-05). . United States Department of Energy. Archived from the original on 2014-03-14. Retrieved 2010-03-12.
  48. ^ Office of Energy Efficiency and Renewable Energy (2010-02-04). . United States Department of Energy. Archived from the original on 2011-10-16. Retrieved 2010-03-12.
  49. ^ "U.S. Installed and Potential Wind Power Capacity and Generation". WINDExchange. U.S. Department of Energy's Wind Energy Technologies Office. from the original on 2020-12-06. Retrieved 2019-03-07.
  50. ^ "Wind Energy in Massachusetts". from the original on 2020-08-05. Retrieved 2020-05-07.
  51. ^ "WINDExchange: U.S. Installed and Potential Wind Power Capacity and Generation". from the original on 2020-12-06. Retrieved 2019-03-07.
  52. ^ National Renewable Energy Laboratory (2010-02-04). . U.S. Department of Energy. Archived from the original on 2013-05-30. Retrieved 2010-03-27.
  53. ^ "WINDExchange: Massachusetts Wind Resource Map and Potential Wind Capacity". from the original on 2012-04-29. Retrieved 2012-05-15.
  54. ^ doer (2009-06-12). "Locating Wind Sites - Resources". Energy and Environmental Affairs. from the original on 2017-09-15. Retrieved 2017-10-16.
  55. ^ "Wind Energy Site Screening Tool". from the original on 2017-10-17. Retrieved 2017-10-16.
  56. ^ Writer, Tux TurkelStaff (January 31, 2023). "Northern Maine wind power project wins PUC approval". Press Herald.

External links edit

  • Vineyard Wind official site
  • New England Wind Forum official webpage

wind, power, massachusetts, state, massachusetts, vast, wind, energy, resources, offshore, well, significant, resources, onshore, 2016, update, states, clean, energy, climate, plan, goal, reducing, 1990, baseline, greenhouse, emissions, levels, 2020, current, . The U S state of Massachusetts has vast wind energy resources offshore as well as significant resources onshore The 2016 update to the states s Clean Energy and Climate Plan had a goal of reducing 1990 baseline greenhouse gas emissions levels by 25 by 2020 1 Current goals include installing 3 500 megawatts MW of offshore wind power in the state by 2035 2 However as of Q4 2021 the state had only 120 MW of wind powered electricity generating capacity responsible for generating 0 9 of in state electricity production The state has awarded contracts to two offshore projects the 800 MW Vineyard Wind project and 804 MW Mayflower Wind project 3 Construction began on the Vineyard Wind 1 project on November 18 2021 after a long fight for approval 4 Commonwealth Wind was selected for development in 2021 but the developer has attempted to cancel the project due to increased costs There are eight projects planned for off the southern coast of Massachusetts though some will deliver power to Rhode Island Connecticut and New York 5 Massachusetts Maritime Academy wind turbine IBEW wind turbine along I 93 Contents 1 Notable onshore projects 2 Offshore wind 3 Current state support 3 1 Policy 3 2 New Bedford Marine Commerce Terminal 3 3 Wind Technology Testing Center WTTC 3 4 Charlie Baker administration 2015 2023 4 Capacity 4 1 Installed 4 2 Potential 4 3 Locations 5 Imports 6 See also 7 References 8 External linksNotable onshore projects editInstalled in 2005 the International Brotherhood of Electrical Workers IBEW 100 kW wind turbine along I 93 south of Boston drew attention to wind power to tens of thousands of commuters 6 In 2009 a similar wind turbine was installed along I93 north of Boston in Medford expected to generate 170 000 kWh year 7 8 A GE Wind Energy 1 5 MW turbine was the first wind turbine to be installed at a ski resort in the United States of America at Jiminy Peak in Hancock MA The turbine installed in 2007 is visible from many of the slopes on the mountain and it produces 4 600 MWh annually about one third of the facilities electricity demands 9 At the Joint Base Cape Cod three turbines generate power for the base and construction is underway for two additional 1 68 MW turbines to power the radar unit The three soon to be five turbines are highly visible from both the Bourne Bridge and the Sagamore Bridge looking to the East The turbines have resulted in significant savings for the base the turbines also do not generate any controversy because they are located well within the base boundaries far from civilian homes 10 In June 2017 the Massachusetts courts shut down two town owned 1 65 megawatt wind turbines in Falmouth Massachusetts Each turbine generates up to 110 decibels of noise requiring almost 3000 foot setback The decibel level for two wind turbines operating at the same time is unknown Massachusetts has twenty one communities with noise and alleged shadow flicker health issues The neighbors describe the noise as torture The Town of Falmouth in November 2019 approved 2 5 million to disassemble and store the wind turbines The turbines were designed in the late 1990s and have the original gearboxes and blades 11 Offshore wind editSee also List of offshore wind farms in the United States nbsp Wind energy lease areas off the southern coasts of Massachusetts and Rhode Island as of October 2022 Cape Wind was an offshore wind farm that would have produced 450 MW enough electricity to power nearly 420 000 homes using 130 wind turbines 12 The project made its first federal filings in 2001 and faced a lengthy federal state and municipal permitting processes and considerable local controversy because of its location in federal waters between Cape Cod Nantucket and Martha s Vineyard within sight of the mainland It was cancelled in 2017 after losing utility support On August 8 2016 the Massachusetts governor signed Bill H 4568 which mandates that Massachusetts utilities obtain 1 6 GW of offshore wind power by 2027 13 14 Policy also mandated that utilities acquire 1 2 GW of power from other renewable sources including onshore wind 15 On December 14 2018 the U S Bureau of Ocean Energy Management BOEM opened bids for leases on three parcels each 13 000 acres located in federal waters south of Martha s Vineyard and Nantucket The three tentative winners subject to final negotiations were Beacon Wind jointly owned by BP and Equinor Wind US 16 a division of the Norwegian oil company Equinor formerly Statoil Mayflower Wind Energy LLC jointly owned by Shell and EDP Renewables Vineyard Wind LLC jointly owned by Copenhagen Infrastructure Partners and Avangrid Renewables The auction raised a total of 405 million The three areas could support 4 1 gigawatts of wind nameplate power according to BOEM estimates 17 In April 2019 Vineyard Wind was awarded a contract to supply 800 MW of power to Massachusetts utilities at a price of 8 9 cents kWh and will also spend 15 million on battery systems for energy storage 18 They plan to install 84 turbines with their power line running between the Vineyard and Nantucket to Covell Beach in Centerville and from there via land to the grid 19 The vessels used must comply with the Jones Act 20 Final major federal approval was granted on May 11 2021 21 Power from the first turbine started flowing into the ISO New England grid on January 2 2024 22 Construction is expected to be complete by the end of 2024 22 Commonwealth Wind lease area OCS A 0534 23 was selected for development in 2021 and signed agreements with all three major Massachusetts electric utilities Eversource National Grid and Unitil 24 In 2022 developer Avangrid asked that its project be canceled and rebid due to higher supply costs The Massachusetts Department of Public Utilities rejected this request and approved the Commonwealth Wind and Mayflower Wind agreements instead 25 A Mayflower Wind cable is expected to come ashore at the site of the former coal powered Brayton Point Power Station 26 which already has transmission infrastructure The Park City Wind project 27 would supply power to Connecticut but land cables in Barnstable on Cape Cod Avangrid attempted to renegotiate its agreement with Connecticut due to cost increases 26 The proposed offshore Bay State Wind project failed to arrange purchasing agreements in Massachusetts The joint venture between Eversource and Orsted proposed a new design called Revolution Wind 2 to supply clean electricity to Rhode Island Energy 28 Current state support editThe state has implemented policy and infrastructure to support efforts to reduce greenhouse gas emissions These policies and infrastructure are partially focused on promoting on and off shore wind power Policy edit Main article Climate change in Massachusetts Green Communities Act 2008 created a commission to provide technical and financial support to reduce energy costs strengthen local economies and support renewable energy efforts 2 Green Jobs Act 2008 created the Massachusetts Clean Energy Center MassCEC which is a state authority designated for job development and economic development in the clean energy sector The Act created the Alternative and Clean Energy Investment Trust Fund to further this economic development 29 Global Warming Solutions Act 2008 requires reduction in 1990 greenhouse gas emission levels to 25 by 2020 and at least an 80 reduction by 2050 Policy information and figures depicting state progress can be viewed on the Mass gov website 30 New Bedford Marine Commerce Terminal edit Main article New Bedford Marine Commerce Terminal The New Bedford Marine Commerce Terminal is the first hub in the country designed for the deployment of offshore wind farms 31 The terminal is managed by the Massachusetts Clean Energy Center which supports the fabrication and implementation of offshore wind projects and the transportation of large scale marine cargo The Terminal contains 26 acres of storage space that can be used by businesses and to aid shipping and transportation Besides the auxiliary I 195 interstate running directly through New Bedford s downtown it also has access roads to two highways I 495 and I 95 and is accessible from other ports 32 Wind Technology Testing Center WTTC edit nbsp Massachusetts Wind Technology Testing Center The Massachusetts Wind Technology Testing Center in Charlestown is managed by the Massachusetts Clean Energy Center The center offers testing for blades up to 90 meters long and different prototyping methods in order to support the production and installation of land and offshore wind turbines The blade testing is required for turbines to meet international qualifications and to be certified for use 33 Charlie Baker administration 2015 2023 edit Main article Governorship of Charlie Baker In July 2015 the administration of Massachusetts Governor Charlie Baker announced that Baker filed legislation to require the state to procure 1 600 megawatts of offshore wind power as well as 1 200 megawatts of hydropower 34 In March 2016 the legislation received the endorsement of all three of the Energy and Environmental Affairs Secretaries of the Deval Patrick administration 35 and the following August Baker signed the legislation into law 36 In September 2016 Baker s administration announced that the offshore wind companies Deepwater Wind DONG Energy and OffshoreMW agreed to use the New Bedford Marine Commerce Terminal built during the Patrick administration as a staging area for their projects 37 In June 2017 Massachusetts utilities issued the first RFP under the energy diversification law signed by Baker in August 2016 38 and the following month five major bids were submitted 39 In May 2018 Baker s administration selected Vineyard Wind to construct an 800 megawatt offshore wind farm off the southern coast of Martha s Vineyard 40 and the following October Vineyard Wind announced that it had signed an 18 month lease to also conduct their staging operations at the New Bedford Marine Commerce Terminal 41 In December 2018 the Bureau of Ocean Energy Management announced the sale of three wind lease plots of 390 000 acres of ocean south of Nantucket and Martha s Vineyard to Equinor Wind Mayflower Wind and Vineyard Wind for a national record of 405 million that the agency estimated could generate as much as 4 100 megawatts of wind power 42 In May 2021 the U S Department of the Interior announced that a record of decision had been issued giving final federal approval for the Vineyard Wind project 43 An Offshore Wind Study published in mid 2020 analyzed procuring an additional 1 6 GW of off shore capacity in addition to the 1 6 GW already in progress 44 In late 2020 the Baker Administration released a Decarbonization Roadmap that aims for net zero greenhouse gas emissions by 2050 The plan calls for major investments in offshore wind and solar energy 45 46 Capacity edit nbsp Installed edit Parts of this article those related to the table which needs to show the growth in wind power installed nameplate capacity in MW for Massachusetts since 1999 last update was only for 2020 need to be updated Please help update this article to reflect recent events or newly available information September 2023 The following table shows the growth in wind power installed nameplate capacity in MW for Massachusetts since 1999 47 48 49 50 51 Year Amount MW Change MW Change 1999 0 3 0 2000 0 3 0 0 2001 1 0 7 233 2002 1 0 0 2003 1 0 0 2004 1 0 0 2005 1 1 0 1 10 2006 3 5 2 4 218 2007 5 1 5 43 2008 5 7 0 7 14 2009 15 9 163 2010 17 7 2 7 18 2011 47 29 3 166 2012 103 56 119 2013 106 3 3 2014 107 1 1 2015 107 0 0 2016 115 8 7 2017 115 0 0 2018 113 2 2 2019 120 7 6 2020 120 0 0 nbsp Offshore Wind Power Capacity Potential edit In early 2010 the National Renewable Energy Laboratory released the first comprehensive update of wind energy potential by state since 1993 showing that Massachusetts had potential to install 1 028 MW of onshore wind power using 80 meter high wind turbines 52 and 1 913 MW of 100 MW wind turbines could achieve 30 or better capacity factor and of those almost 500 MW could reach a capacity factor of 40 53 Locations edit In 2009 the Massachusetts Department of Energy Resources DOER contracted Navigant Consulting to determine new locations of potential wind turbine sites throughout the state The study identified 44 locations with 947 MW of potential power The locations are centrally focused in the Berkshire and Barnstable counties 54 The Massachusetts Executive Office of Energy and Environmental Affairs has this information publicly available with a Wind Energy Site Screening Tool 55 Imports editTo meet renewable power minimums and with state approval Massachusetts utilities agreed to pay for 40 of the output of the proposed King Pine wind farm in Aroostook County Maine developed by Longroad Energy As of January 2023 was approved by the Maine Public Utilities Commission but required further design and approval of the transmission line developed by LS Power of New York 56 See also edit nbsp Wind power portal nbsp Renewable energy portal nbsp Energy portal nbsp United States portal nbsp Massachusetts portal Solar power in Massachusetts Cape Wind List of offshore wind farms in the United States Wind power in the United States Renewable energy in the United StatesReferences edit eea 2016 01 19 Massachusetts Clean Energy and Climate Plan for 2020 Energy and Environmental Affairs Archived from the original on 2017 09 16 Retrieved 2017 10 16 a b Archived copy PDF Archived from the original PDF on 2017 02 15 Retrieved 2017 10 16 a href Template Cite web html title Template Cite web cite web a CS1 maint archived copy as title link Massachusetts Wind Energy PDF U S Wind Energy State Facts American Wind Energy Association Retrieved April 30 2020 Frangoul Anmar November 19 2021 Construction starts at America s first major offshore wind farm CNBC Archived from the original on November 28 2021 Retrieved November 26 2021 Offshore wind farms off Cape Cod and Martha s Vineyard A guide of what to know Cape Cod Times Archived from the original on 2023 01 27 Retrieved 2023 01 30 Boston s First Wind Turbine Serves as Example Archived from the original on 2013 05 29 Retrieved 2012 05 15 Medford readies wind turbine at site along I 93 Archived from the original on 2012 05 18 Retrieved 2012 05 15 Medford Clean Energy Committee Archived from the original on 2012 05 18 Retrieved 2012 05 15 Wind Turbine FAQ Family activities in New England Jiminy Peak Mountain Resort Hancock Massachusetts MA Archived from the original on 2013 09 18 Retrieved 2013 09 10 Two more turbines coming soon to cape base September 7 2013 Archived from the original on August 9 2014 Retrieved September 9 2013 Falmouth Town Meeting Approves Funding to Dismantle Town s Turbines Archived from the original on 2019 12 22 Retrieved 2020 04 03 Cape Wind America s First Offshore Wind Farm Archived from the original on 2012 05 18 Retrieved 2012 05 15 Massachusetts passes bill easing path for 1 6 GW of offshore wind Archived from the original on 6 August 2016 Retrieved 2 August 2016 Bill H 4568 Archived from the original on 2016 11 28 Retrieved 2016 08 02 Massachusetts passes bill easing path for 1 6GW of offshore wind Archived from the original on 2017 08 01 Retrieved 2017 10 16 Project Beacon Wind September 18 2023 Gerdes Justin December 17 2018 Record Breaking Massachusetts Offshore Wind Auction Reaps 405 Million in Winning Bids Green Tech Media Archived from the original on June 10 2019 Retrieved May 29 2019 Geuss Megan April 24 2019 Massachusetts offshore wind project gets green light at roughly 8 9 cents kWh Archived from the original on May 7 2021 Retrieved May 29 2019 Gellerman Bruce January 19 2021 Offshore Wind Backers Hope Vineyard Wind Permitting Woes Will End Under Biden WBUR Archived from the original on 2021 01 19 Retrieved 2021 01 20 Mercure Matthew 31 March 2021 Vineyard Wind Selects Contractor for Transport Installation of Turbines North American Windpower nawindpower com Archived from the original on 26 April 2021 Retrieved 14 April 2021 Biden administration grants Vineyard Wind its final major permit The Boston Globe Archived from the original on 2021 05 20 Retrieved 2021 05 28 a b Sabrina Shankman January 3 2024 With a flip of the switch offshore wind energy enters New England s grid The Boston Globe Commonwealth Wind Commonwealth Wind August 3 2023 Seonwoo Eunki December 28 2022 Commonwealth Wind wants to back out of contracts Service Colin A Young State House News January 2 2023 DPU rejects bid to scrap wind contracts approves them instead Salem News a href Template Cite web html title Template Cite web cite web a CS1 maint multiple names authors list link CS1 maint numeric names authors list link a b Offshore wind projects face uncertainty with existing contracts Cape Codders respond Cape Cod Times Park City Wind Park City Wind August 3 2023 Developers pitch new wind power project enough to power 500 000 R I homes The Boston Globe BostonGlobe com The Green Jobs Act of 2008 Massachusetts Businesses for Clean Energy www mabizforcleanenergy com Archived from the original on 2017 10 16 Retrieved 2017 10 16 eea 2012 05 09 Massachusetts Global Warming Solutions Act GWSA Energy and Environmental Affairs Archived from the original on 2017 10 16 Retrieved 2017 10 16 Massachusetts Offshore Wind Energy Hub Gets The Green Light Archived from the original on 2023 02 15 Retrieved 2012 11 21 New Bedford Marine Commerce Terminal Massachusetts Clean Energy Center 30 May 2017 Archived from the original on 7 September 2017 Retrieved 7 September 2017 Wind Technology Testing Center Mass CEC 5 March 2013 Archived from the original on 2017 10 30 Retrieved 2017 10 16 Baker Polito Administration Files Hydropower Legislation to Increase Access to Clean Cost Effective Renewable Energy www mass gov July 9 2015 Archived from the original on March 16 2018 Retrieved March 11 2018 Dezenski Lauren March 23 2016 Baker musters energy secretaries to push action on hydro bill Politico Capitol News Company Archived from the original on March 12 2018 Retrieved March 11 2018 Schoenberg Shira August 8 2016 Gov Charlie Baker signs hydropower wind energy bill into law MassLive com Advance Publications Archived from the original on March 12 2018 Retrieved March 11 2018 Serreze Mary C September 6 2016 Offshore wind developers agree to use New Bedford Marine Terminal MassLive com Advance Publications Archived from the original on March 12 2018 Retrieved March 11 2018 Serreze Mary C July 3 2017 Massachusetts utilities release first offshore wind RFP under new state energy law MassLive com Advance Publications Archived from the original on March 12 2018 Retrieved March 11 2018 Serreze Mary C July 28 2017 5 major transmission hydro and wind partners bid into Massachusetts Clean Energy RFP MassLive com Advance Publications Archived from the original on March 12 2018 Retrieved March 11 2018 Murphy Matt May 23 2018 Mass Selects Vineyard Wind For 800 Megawatt Offshore Wind Farm WBUR Archived from the original on June 21 2018 Retrieved June 21 2018 Vineyard Wind Signs Lease For Staging Operations In New Bedford WBUR October 22 2018 Archived from the original on November 15 2018 Retrieved November 15 2018 Moran Barbara December 14 2018 Offshore Wind Auction For 390 000 Acres South Of Mass Blows Through Sale Record WBUR Archived from the original on December 18 2018 Retrieved December 17 2018 Frangoul Anmar May 12 2021 A huge moment U S gives go ahead for its first major offshore wind farm CNBC Archived from the original on July 18 2022 Retrieved July 18 2022 Massachusetts Offshore Wind Study 2020 Archived from the original on 2021 01 06 Retrieved 2021 01 05 Martin Naomi December 30 2020 Mass to require all new cars sold to be electric by 2035 as part of climate change measures The Boston Globe Archived from the original on January 26 2021 Retrieved January 5 2021 Massachusetts 2050 Decarbonization Roadmap Archived from the original on 2021 01 01 Retrieved 2021 01 05 Office of Energy Efficiency and Renewable Energy 2010 03 05 U S Installed Wind Capacity and Wind Project Locations United States Department of Energy Archived from the original on 2014 03 14 Retrieved 2010 03 12 Office of Energy Efficiency and Renewable Energy 2010 02 04 Installed Wind Capacity by State United States Department of Energy Archived from the original on 2011 10 16 Retrieved 2010 03 12 U S Installed and Potential Wind Power Capacity and Generation WINDExchange U S Department of Energy s Wind Energy Technologies Office Archived from the original on 2020 12 06 Retrieved 2019 03 07 Wind Energy in Massachusetts Archived from the original on 2020 08 05 Retrieved 2020 05 07 WINDExchange U S Installed and Potential Wind Power Capacity and Generation Archived from the original on 2020 12 06 Retrieved 2019 03 07 National Renewable Energy Laboratory 2010 02 04 State wind energy potential 2010 U S Department of Energy Archived from the original on 2013 05 30 Retrieved 2010 03 27 WINDExchange Massachusetts Wind Resource Map and Potential Wind Capacity Archived from the original on 2012 04 29 Retrieved 2012 05 15 doer 2009 06 12 Locating Wind Sites Resources Energy and Environmental Affairs Archived from the original on 2017 09 15 Retrieved 2017 10 16 Wind Energy Site Screening Tool Archived from the original on 2017 10 17 Retrieved 2017 10 16 Writer Tux TurkelStaff January 31 2023 Northern Maine wind power project wins PUC approval Press Herald External links edit nbsp Wikimedia Commons has media related to Wind power in Massachusetts Vineyard Wind official site New England Wind Forum official webpage Retrieved from https en wikipedia org w index php title Wind power in Massachusetts amp oldid 1213737348, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.