fbpx
Wikipedia

Nadikudi–Srikalahasti section

The Nadikudi–Srikalahasti section is an ongoing railway section project of the Indian Railways.[1] The section falls under the administration of Guntur of South Central Railway Zone. This serves as alternative route to Tirupati-Secundrabad.

Nadikudi–Srikalahasti section
Nadikudi-srikalahasti route details
Overview
StatusUnder construction
OwnerIndian Railways
LocaleAndhra Pradesh
Termini
Service
Operator(s)South Central Railway zone
Technical
Line length308 km (191 mi)
Track gauge1,676 mm (5 ft 6 in)
ElectrificationOngoing
Operating speed130 km/h
Route map

km
0
Nadikudi Junction
12
Tummalacheruvu
15
Kamepalli
22
Piduguralla
27
Sitaramapuram Junction
39
Nekarikallu
49
Kunkaraguntla halt
55
Rompicherala
67
Velpuru North halt
73
Savalyapuram Junction
83
Vinukonda
90
Cheekategalapalem
96
Gundlakamma Junction
110
Dekanakonda
123
Darsi
130
Rajampalle halt
139
Mallawaram halt
147
Podili
162
Gautuvaripalle
170
Garlapeta Road halt
175
Kanigiri
181
Lingareddypalle halt
194
Ballipalle
199
Narmarella halt
209
Pamuru
220
Kakullavaripalle halt
228
Gollavaripalle
241
Ravipadu halt
249
Vinjamur
256
Dubagunta halt
262
Pamidipallu halt
270
Atmakur
279
Obulayapalle
284
Kottavuru halt
300
Venkatapuram
311
Aduripalli
Krishnapatnam Port
Nidiguntapalem
Venkatachalam Road Junction
Kasumuru
Bapanapalli
Adurupalli
325
Rapuru Junction
Vellikallu
Cherlopalli
Mangampetta
Obulavaripalli Junction
335
Vellampalle halt
343
Alturupadu
349
Balasamundram halt
358
Venkatagiri Junction
364
Yataluru
370
Yellakaru
378
Akkurti
383
Srikalahasti
km

The project edit

The project was sanctioned in the year 2010–11.[1] It connects Secunderabad–Guntur branch line at Piduguralla of Guntur district and Gudur–Katpadi branch line at Venkatagiri of Nellore district in the Indian state of Andhra Pradesh.[2] The total length of the section is 308 km (191 mi) estimated cost of the project is 2,452 crore (US$310 million).[3] The railway stations of which lies between the nodal stations are Nekarikallu, Rompicherla, Vinukonda, Gundlakamma, Darsi, Podili, Kanigiri, Pamuru, Vinjamuru, Atmakuru, Rapur and Venkatagiri.[4]

Phase-1 edit

Nadikudi (Guntur–Hyderabad route) to Savalyapuram (Guntur–Guntakal route) track, trial run completed. Electrification proposals for the completed route are sent to Higher authorities. By the end of 2018, this new route will be added to Guntur–Guntakal route. DRM Guntur says that project deadline is 2022.[5] At Rapur railway station (junction) both Nadikudi–Srikalahasti and Krishnapatnam–Obulavaripalle railway line cross each other.

Proposed list of stations edit

It starts from Nadikudi railway Junction in Secunderabad–Guntur lane and passes through Piduguralla and from there new line starts with Nakarikallu, Rompicherla and connects with Guntur–Gunthakal section at Savalyapuram and passes through Vinukonda and again enters new line from Gundlakamma which passes through Darsi, Podili, Kanigiri, Pamuru, Vinjamuru, Dubagunta, Atmakuru, Obulayapalle, Rapuru and finally connects Venkatagiri at Gudur–Renigunta section.

References edit

  1. ^ a b "Surveys" (PDF). South Central Railway, Indian Railways. 24 July 2015. p. 14. Retrieved 3 May 2019.
  2. ^ "Nadikudi-Srikalahasti Rail Line". Railnews. Amaravati: South Central Railway. 19 December 2018. Retrieved 24 April 2019.
  3. ^ "PM Narendra Modi Reviews Railway Projects in Andhra Pradesh". NDTV. Retrieved 24 May 2016.
  4. ^ "Nadikudi – Srikalahasti line to ensure better connectivity". The Hindu. 9 November 2015. ISSN 0971-751X. Retrieved 24 May 2016.
  5. ^ "SCR GM and government officials review rail projects". The Hindu. 16 July 2018. Retrieved 12 August 2018.

nadikudi, srikalahasti, section, ongoing, railway, section, project, indian, railways, section, falls, under, administration, guntur, south, central, railway, zone, this, serves, alternative, route, tirupati, secundrabad, nadikudi, srikalahasti, route, details. The Nadikudi Srikalahasti section is an ongoing railway section project of the Indian Railways 1 The section falls under the administration of Guntur of South Central Railway Zone This serves as alternative route to Tirupati Secundrabad Nadikudi Srikalahasti sectionNadikudi srikalahasti route detailsOverviewStatusUnder constructionOwnerIndian RailwaysLocaleAndhra PradeshTerminiNadikudiSrikalahastiServiceOperator s South Central Railway zoneTechnicalLine length308 km 191 mi Track gauge1 676 mm 5 ft 6 in ElectrificationOngoingOperating speed130 km hRoute mapLegendkmPagidipalli Nallapadu sectionNadikudi Macherla branch line0 Nadikudi Junction12 Tummalacheruvu15 Kamepalli22 Piduguralla27 Sitaramapuram JunctionPagidipalli Nallapadu section39 Nekarikallu49 Kunkaraguntla halt55 Rompicherala67 Velpuru North haltNallapadu Nandyal section73 Savalyapuram Junction83 Vinukonda90 Cheekategalapalem96 Gundlakamma JunctionNallapadu Nandyal section110 Dekanakonda123 Darsi130 Rajampalle halt139 Mallawaram halt147 Podili162 Gautuvaripalle170 Garlapeta Road halt175 Kanigiri181 Lingareddypalle halt194 Ballipalle199 Narmarella halt209 Pamuru220 Kakullavaripalle halt228 Gollavaripalle241 Ravipadu halt249 Vinjamur256 Dubagunta halt262 Pamidipallu halt270 Atmakur279 Obulayapalle284 Kottavuru halt300 Venkatapuram311 AduripalliKrishnapatnam PortNidiguntapalemVenkatachalam Road JunctionVijayawada Gudur sectionKasumuruBapanapalliAdurupalli325 Rapuru JunctionVellikalluCherlopalliMangampettaGuntakal Renigunta sectionObulavaripalli JunctionGuntakal Renigunta section335 Vellampalle halt343 Alturupadu349 Balasamundram haltGudur Chennai section358 Venkatagiri Junction364 Yataluru370 Yellakaru378 Akkurti383 SrikalahastiGudur Chennai sectionkm Contents 1 The project 2 Phase 1 3 Proposed list of stations 4 ReferencesThe project editThe project was sanctioned in the year 2010 11 1 It connects Secunderabad Guntur branch line at Piduguralla of Guntur district and Gudur Katpadi branch line at Venkatagiri of Nellore district in the Indian state of Andhra Pradesh 2 The total length of the section is 308 km 191 mi estimated cost of the project is 2 452 crore US 310 million 3 The railway stations of which lies between the nodal stations are Nekarikallu Rompicherla Vinukonda Gundlakamma Darsi Podili Kanigiri Pamuru Vinjamuru Atmakuru Rapur and Venkatagiri 4 Phase 1 editNadikudi Guntur Hyderabad route to Savalyapuram Guntur Guntakal route track trial run completed Electrification proposals for the completed route are sent to Higher authorities By the end of 2018 this new route will be added to Guntur Guntakal route DRM Guntur says that project deadline is 2022 5 At Rapur railway station junction both Nadikudi Srikalahasti and Krishnapatnam Obulavaripalle railway line cross each other Proposed list of stations editIt starts from Nadikudi railway Junction in Secunderabad Guntur lane and passes through Piduguralla and from there new line starts with Nakarikallu Rompicherla and connects with Guntur Gunthakal section at Savalyapuram and passes through Vinukonda and again enters new line from Gundlakamma which passes through Darsi Podili Kanigiri Pamuru Vinjamuru Dubagunta Atmakuru Obulayapalle Rapuru and finally connects Venkatagiri at Gudur Renigunta section References edit a b Surveys PDF South Central Railway Indian Railways 24 July 2015 p 14 Retrieved 3 May 2019 Nadikudi Srikalahasti Rail Line Railnews Amaravati South Central Railway 19 December 2018 Retrieved 24 April 2019 PM Narendra Modi Reviews Railway Projects in Andhra Pradesh NDTV Retrieved 24 May 2016 Nadikudi Srikalahasti line to ensure better connectivity The Hindu 9 November 2015 ISSN 0971 751X Retrieved 24 May 2016 SCR GM and government officials review rail projects The Hindu 16 July 2018 Retrieved 12 August 2018 Retrieved from https en wikipedia org w index php title Nadikudi Srikalahasti section amp oldid 1217272000, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.