Line 7 (Mumbai Metro)

Red Line 7 is a rapid transit line in Mumbai, Maharashtra, India, and part of the Mumbai Metro system. When fully completed, the 30.08 km (18.69 mi) line will connect Bhayander with the Chhatrapati Shivaji Maharaj International Airport with 24 stations. The line is mostly elevated (27.89 km (17.33 mi)) and partially underground (2.19 km (1.36 mi)).[2]

Mumbai Metro Red Line 7
Overview
StatusOperational (extension under construction)
OwnerMMRDA
Line number7
LocaleMumbai, Maharashtra, India
Termini
Stations14
WebsiteLine 7
Service
TypeRapid transit
SystemMumbai Metro
Depot(s)Charkop (temporary)
Bhayandar (planned)
Rolling stockBEML
Daily ridership212,000 (July 2023)[1]
History
Commenced8 August 2016 (2016-08-08)
Opened2 April 2022; 18 months ago (2022-04-02)
Technical
Line length16.5 km (10.3 mi)
Number of tracks2
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification25 kV 50 Hz AC overhead line
Line 7 map

Line 7
to Red Line 9
Dahisar Depot
to Yellow Line 2
0.0000
Dahisar East
1.1404
Ovaripada
2.1484
Rashtriya Udyan
3.2749
Devipada
4.0972
Magathane
5.8249
Poisar
6.4492
Akurli
7.4569
Kurar
8.3449
Dindoshi
9.4249
Aarey
11.7434
Goregaon East
13.1110
Jogeshwari East on Pink Line 6
14.2951
Mogra
15.5249
Gundavali
Western Express Highway on Blue Line 1
16.0849
Airport Colony
to Aqua Line 3
18.9342
CSMIA International
to Gold Line 8

A section of the line from Dahisar East to Aarey was opened on 2 April 2022, and another section from Aarey to Gundavli in Andheri (East) was inaugurated on 19 January 2023. An under construction 11.386 km section of Line 7, from Bhayander to Dahisar, is part of Red Line 9. A southward extension to the airport is also currently under construction.

The line is served by six-car trains, manufactured by Bharat Earth Movers Limited, with a headway of 10 minutes. Line 7 currently uses Line 2's depot at Charkop, due to an issue acquiring land for a depot. Services currently operate between Gundavali and Andheri West (on Line 2) via Dahisar East.

Planning Edit

An 18 km (11 mi) metro line connecting Andheri East and Dahisar East was proposed as Line 7 in the original Mumbai Metro master plan unveiled by the Mumbai Metropolitan Region Development Authority (MMRDA) in 2004.[3] In June 2015, the MMRDA proposed building Line 7 as part of a plan to build 6 new metro lines at a total estimated cost of 64,000 crore (US$8.0 billion).[4] The MMRDA approved the detailed project report for Line 7 in August 2015. The report proposed a 16.5 km (10.3 mi) elevated line between Andheri East and Dahisar East at an estimated cost of 4,737 crore (US$590 million).[5]

Over the course of two weeks in March–April 2017, Mumbai residents saved nearly 4,000 trees planted on dividers and along the WEH that had been planned to be felled for metro construction. Residents replanted these trees at their own housing societies, as well as schools and other locations. Nearly 210 people and over 40 housing societies participated in the initiative coordinating their efforts through WhatsApp messages.[6]

In April 2017, the Ministry of Civil Aviation approved the transfer of 40 acres of land in Dahisar for the construction of the metro depot.[7][8] The Airports Authority of India and the MMRDA signed a formal agreement on 24 April 2017.[9] In June 2017, the Maharashtra Government transferred three plots of land at Aarey Colony, measuring a total of 20,387 sqm (5.03 acres), to the MMRDA for a labour camp and a casting yard for Line 7, and a centralised operation centre for the metro system.[10] In November 2021, the MMRDA cancelled the plan to build the line's depot at Dahisar and instead proposed building the depot for Line 7, and its extensions, at Rai Murdhe in Bhayandar.[11]

In February 2020, MMRDA metropolitan commissioner R.A. Rajeev stated that Line 7 would be identified as the Red Line.[12] A study by World Resources Institute (WRI) India, published in May 2021, estimated that Line 7 and Line 2A had the potential to create 1.1 million jobs in the city.[13]

Extensions Edit

In February 2017, the MMRDA announced that the DMRC was preparing a detailed project report (DPR) on a proposed 9 km (5.6 mi) extension of Line 7 from Dahisar to Bhayander, via Mira Road.[14] The extension would have 9 stations, with an inter-station distance of 1 km (0.62 mi). The line would run parallel to the Surat-Dahisar Highway, then turn left at Kashi Mira Junction, before passing through Mira Road-Bhayander, and terminating at Golden Nest Circle in Bhayander. The project is estimated to cost 3,600 crore (US$450 million).[15][16][17] In March 2017, the MMRDA stated that the DMRC was conducting a feasibility study to extend the line to Terminal 2 of the Chhatrapati Shivaji Maharaj International Airport. The proposed 3.17 km (1.97 mi) extension, called Line 7A, from Andheri to the airport will pass beneath Line 1's Western Express Highway station.[18]

The extensions to Mira-Bhayander and the airport were officially announced by Chief Minister Fadnavis on 30 March 2017.[19][20][21] The alignment for the extension from Andheri to Chhatrapati Shivaji Maharaj International Terminus was approved by the State Cabinet on 12 April 2017.[22] In June 2018, the MMRDA stated that it had decided to terminate the proposed extension at the international airport and not extend it to the domestic terminal due technical challenges. As the metro extension is proposed to be underground it would have to constructed below or above Line 3 which also passes under the airport.[23] The 3.17 km (1.97 mi) extension includes a 0.98 km (0.61 mi) elevated stretch and 2.19 km (1.36 mi) twin tunnel. The Maharashtra Cabinet approved the implementation of both extensions in September 2018.[24][25]

History
Section Extension date Termini Length Stations
Line 7[26] 2 April 2022 Dahisar East Aarey 10.7 kilometers (6.6 mi) 10
19 January 2023 Aarey Gundavali 5.8 kilometers (3.6 mi) 4
Line 7A Gundavali CSMIA International 3.175 kilometers (1.973 mi) 2
Dahisar East CSMIA International 19.675 kilometers (12.225 mi) 16

Depot and Line 2 link Edit

The depot for Line 7 was proposed to be located at Dahisar.[27] However, land acquisition for the Dahisar depot was delayed by litigation filed in 2016. In 2020, the MMRDA proposed using the depot at Charkop to serve both Line 2 and Line 7 by building a ring metro line to connect the two corridors. The MMRDA utilized an empty plot of land located after Ovaripada station on Line 7 to build pillars for the link connecting the two lines.[28][29] Line 2 of the Mumbai Metro connects Dahisar East with Andheri West. In November 2021, the MMRDA cancelled the plan to build the depot at Dahisar and instead proposed building the depot for Lines 7, 7A and 9 at Rai Murdhe in Bhayandar.[30]

Line 2 and Line 7 were both commissioned on 2 April 2022, with services operating between Aarey and Dahanukarwadi via Dahisar East. Both lines were extended on 19 January 2023, providing circular service between Gundavali and Andheri West via Dahisar East.[31] The Charkop depot currently serves as the depot for Line 2 and Line 7. The under construction Mandale depot will be used to serve Line 2 once completed.[32]

Construction Edit

The bhoomipujan ceremony for Line 7 was performed by Prime Minister Narendra Modi during his visit to Mumbai on 11 October 2015.[33] Line 7 was implemented through the engineering, procurement and construction (EPC) model.[34] The MMRDA invited bids for the project in December 2015.[35] Tendering for the design and construction of the corridor was split into 3 packages. The first package included an elevated viaduct and 5 elevated stations – Andheri East, Shankarwadi, JVLR Junction, Mahanand and new Ashok Nagar. The second package included an elevated viaduct and 6 elevated stations – Aarey, Dindoshi, Pathan Wadi, Pushpa Park, Bandongri and Mahindra & Mahindra, and an elevated viaduct and 5 elevated stations – Magathane, Devipada, National Park, Ovaripada and Dahisar East. A total of 16 companies expressed interest, and 9 bids were submitted. In April 2016, the MMRDA awarded contracts to Simplex Infrastructure, J Kumar Infraprojects, and Nagarjuna Construction Company for the first, second and third packages respectively. The project is estimated to cost 6,208 crore (US$780 million).[36][37] The contract awarded to Simplex Infrastructure was worth 348 crore (US$44 million).[38]

Construction work on the corridor began on 8 August 2016. The contractors were expected to complete construction of the corridor and all 14 stations within 30 months from the day of commencement of work.[39] On 18 February 2017, MMRDA officials stated that 15% of piling, pile caps and pier work on the corridor had been completed.[40] By the end of April 2017, 25% of piling work, 60% of barricading work and 77% of the soil testing for pier foundation had been completed.[41] Line 7 stations were built on a single pier, unlike the three piers used to support stations on Line 1. The single pier design was chosen to facilitate the construction of smaller stations and reduce the amount of land occupied on the Western Express Highway which could obstruct traffic flow.[42]

On 14 March 2017, the Mumbai High Court temporarily stayed all construction activities at Metro 7's casting yard in Bandra Reclamation. The Court was hearing a PIL filed by Mohammed Furqan Ali Mohammed Qureshi who alleged that the site of the casting yard had been reserved by the Brihanmumbai Municipal Corporation (BMC) for use as a Sunni Muslim cemetery.[43][44] Piling work in Kandivli resulted in a gas pipeline bursting on 29 March 2017. The damage to the Mahanagar Gas pipeline resulted in temporary disruptions in the supply of CNG to Kandivli, Borivli, Dahisar, Mira Road and Bhayander.[45][46] Mahanagar Gas began repairing the pipeline on the evening of 31 March, and completed the work by the following evening.[47] The BMC accused Nagarjuna Construction Company of illegally operating an unlicensed concrete ready mix plant at its casting yard in April 2017.[48]

The MMRDA announced that construction of viaducts would begin in April 2017. The agency had completed construction of piers on several sections of the corridor, and the viaducts will be built at locations where pier caps have been built. The first viaduct was constructed in the section between JVLR to Mahanand. Construction of all pier caps along the corridor will be completed by the end of 2017.[49][50] The first U-girder, the concrete structure on which metro tracks are laid, was launched near Pathanwadi Junction in Malad on 2 May 2017.[51] In total, Metro 7 required 1,400 U-girders.[52] Work on erecting the U-girders, as well as disposal and dumping of muck generated from underground work was done only between 11:30 pm and 6:00 am. During this period, multi-axle trailers transported U-girders weighing 170 tonne from the casting yard in Bandra to the location where it is to be erected. The trailer had to move slowly to avoid causing imbalance to the heavy load which can result in toppling, and took roughly two hours to complete the journey. Lifting the girder and attaching it to the pier caps was also a difficult process and was carried out at night time. Traffic diversions were placed around the launching site to reduce the possibility of accidents. Officials erected an average of two girders every day.[53]

The MMRDA issued notices to all three contractors working on the project on 11 August 2017 over the "poor progress" of work. The agency stated that the although contractors were required to deploy 600 workers each, Simplex had only deployed 320, J Kumar Infraprojects had deployed 395, and NCC had deployed 318 labourers. The MMRDA had also issued a similar notice on 4 July 2017.[54] By August 2017, about 600-700 metres of each package had been constructed, 63 piers and 22 girders had been erected, and barricades had been placed on 67% of the entire route.[55] Track laying work on the line began in June 2019.[56] The first escalator on Line 7 was installed at Bandongri station in August 2019.[57]

In January 2020, the MMRDA terminated the contract awarded to Simplex Infrastructure for the first package over delay in completing the work. The next month, the agency invited bids to replace Simplex. The work was split into two tenders including one for a 6.25km viaduct and another to complete work on 4 stations. In July 2020, the MMRDA awarded a 174.76 crore (US$22 million) and 127.78 crore (US$16 million) contract to J Kumar Infraprojects and Nagarjuna Construction Company respectively to complete the work.[58] The MMRDA also encashed a bank guarantee of 35 crore (US$4.4 million) provided by Simplex.[59] Simplex had completed around 75% of work at the time its contract was terminated.[60]

MMRDA metropolitan commissioner R.A. Rajeev stated in September 2020 that almost 80% of construction work had been completed.[61] The MMRDA began conducting pre-trials on the rolling stock at the Charkop depot in February 2021.[62] The MMRDA announced that electrification of the line had been completed on 26 May, and the first trial runs were conducted from 31 May.[63][64] The MMRDA began a dynamic test and trial run on the 20 km stretch between Dhanukarwadi and Aarey (including a portion of Line 2) on 19 June.[65] The stretch between Dhanukarwadi and Aarey received provisional approval from the Research Designs and Standards Organisation (RDSO) in January 2022.[66] The Commissioner of Metro Rail Safety (CMRS) began inspecting the line in February 2022.[67]

A section of Line 7 from Dahisar East to Aarey (along with the section of Line 2 from Dhanukarwadi to Dahisar East ) was opened on 2 April 2022. Chief Minister Uddhav Thackeray flagged off the first train at 4pm in the presence of Deputy Chief Minister Ajit Pawar, Urban Development Minister Eknath Shinde, NCP chief Sharad Pawar and the Leader of Opposition in the Legislative Council, Pravin Darekar. The line opened for public service from 8pm, with services operating between Aarey and Dahanukarwadi (on Line 2) via Dahisar East.[68]

The remaining section of Line 7 from Goregaon East to Gundavali received approval from the RDSO in October 2022.[69] The CMRS began inspecting the line in December 2022.[70] The final section of the line (along with the final section of Line 2A from Dhanukarwadi to Andheri West) was inaugurated on 19 January 2023 by Prime Minister Narendra Modi.[71][72]

Line 7A Edit

Line 7A is a 3.175 km (1.973 mi) southward extension of Line 7 to Chhatrapati Shivaji Maharaj International Airport, with 2 stations. The section includes a 0.98 km (0.61 mi) elevated stretch and 2.195 km (1.364 mi) long twin tunnels.[73] Work on the airport extension began in March 2020. The MMRDA awarded the construction contract to J. Kumar Infrastructure.[74] Around 25% of work on the extension was completed by November 2022.[75]

Current Status for Line 7A Edit

Sr. No. Name of Work Status for year 2021[76]
1 March 2021 1 May 2021 1 June 2021 2 August 2021 30 September 2021
1 Survey Work 100%
2 Barricading board fixing 15% 27% 30%
3 Soil Investigation Works 86% 89% 92%
4 Utility Identification Works 28% 29% 32%
5 Piling Works 19%
Test Pile 100%
6 Working Pile 22%
7 Pile cap 9%

Stations Edit

Line 7 has 14 operational stations, with two more stations under construction.

Red Line 7
# Station Name[77] Opening Connections Layout
English Marathi
1 Dahisar East दहिसर पूर्व 2 April 2022 Yellow Line 2 and
Red Line 9 (Under Construction)
Elevated
2 Ovaripada ओवरीपाडा 2 April 2022 None Elevated
3 Rashtriya Udyan राष्ट्रीय उद्यान 2 April 2022 None Elevated
4 Devipada देवीपाडा 2 April 2022 None Elevated
5 Magathane मागाठाणे 2 April 2022 None Elevated
6 Poisar पोईसर 2 April 2022 None Elevated
7 Akurli आकुर्ली 2 April 2022 None Elevated
8 Kurar कुरार 2 April 2022 None Elevated
9 Dindoshi दिंडोशी 2 April 2022 None Elevated
10 Aarey आरे 2 April 2022 None Elevated
11 Goregaon East गोरेगाव पूर्व 19 January 2023 None Elevated
12 Jogeshwari East जोगेश्वरी पूर्व 19 January 2023 Pink Line 6 (Under Construction) Elevated
13 Mogra मोगरा 19 January 2023 None Elevated
14 Gundavali गुंदवली 19 January 2023 Blue Line 1 Elevated
15 Airport Colony विमानतळ वसाहत Under Construction None Elevated
16 CSMIA International सीएसएमआयए आंतरराष्ट्रीय Under Construction Aqua Line 3 (Under Construction)
and Gold Line 8 (Proposed)
Underground

Cost Edit

Line 7 is estimated to cost 6,208 crore (US$780 million).[78] The Asian Development Bank (ADB) will provide 43-48% of the total project cost through a loan at an interest rate of 1.4%. The Government of Maharashtra is the guarantor for the loan.[52] On 2 March 2019, the Union Ministry of Finance stated that it signed a $926 million loan agreement with the ADB to fund the construction of Line 2 and Line 7. This was the single largest infrastructure loan ever extended by the ADB. The funds will be used to procure 63 six-car trainsets and for signaling and safety systems on both corridors.[79]

The proposed extension of Line 7 from Dahisar to Bhayander (called Line 9) is estimated to cost 3,600 crore (US$450 million), and the underground extension to the International Airport shall cost an additional 600 crore (US$75 million).[80]

The MMRDA allotted 340 crore (US$43 million) to the DMRC to implement and commission rolling stock, signalling and telecommunication work for the Metro 2A and Metro 7 corridors on 26 November 2016.[81][82][83]

Infrastructure Edit

Rolling stock Edit

BEML was awarded a 3,015 crore (US$380 million) contract to supply 378 metro cars (63 trainsets) for Line 7 and Line 2 in November 2018.[84] An additional 126 metro cars (21 trainsets) were ordered from BEML to cater to metro extensions.[85] All trainsets were manufactured at BEML's Rail Coach Factory in Bangalore, Karnataka. The rakes are capable of driverless operation making them the first driverless metro trains to be made in India.[86] BEML began manufacturing the coaches on 29 July 2019,[87] built the first metro coach in 75 days and unveiled it in September 2019.[88] The first trainset arrived in Mumbai on 28 January 2021.[89]

Each trainset is made up of 6 coaches with a total passenger capacity of 1,660 and dense crush load capacity of 2,092. The trainset is 3.2 metres wide, made of stainless steel and each coach has 4 doors on each side. The rake employs a regenerative braking system.[90][85]

Signalling Edit

Line 7 utilises the Alstom Urbalis 400 communications-based train control (CBTC) signalling system. Alstom was awarded a EUR90 million contract to supply the signalling and telecommunications systems for Mumbai Metro Line 2 and Line 7, as well as Pune Metro Line 1 and Line 7.[91][92]

Power Edit

Line 7 is electrified at 25 kV 50 Hz AC, with power provided via an overhead catenary. The MMRDA signed an agreement with Adani Electricity Mumbai Limited to supply electricity to Line 7 and Line 2A on 2 December 2022. Around 120 million units is required to power both lines.[93][94]

Fare collection Edit

A consortium of Indian company Datamatics and Italian company AEP Ticketing solutions S.R.L was awarded a 160 crore (US$20 million) contract to implement the automated fare collection system for Line 7 and Line 2 in February 2019.[95][96][97]

References Edit

  1. ^ "Two Mumbai Metro lines report record single-day ridership of 2.14 lakh amid heavy rain". cnbctv18.com. 20 July 2023. Retrieved 30 September 2023.
  2. ^ "Mumbai Metropolitan Region Development Authority - Metro Line - 9". mmrda.maharashtra.gov.in. Retrieved 10 July 2023.
  3. ^ . Mmrdamumbai.org. Archived from the original on 19 March 2012. Retrieved 12 March 2014.
  4. ^ "Over 130 km of Metro lines to criss-cross city by 2020". The Indian Express. 16 June 2015. Retrieved 9 July 2023.
  5. ^ "MMRDA sanctions Rs 35,400 cr for 118 km Mumbai metro network Andheri East and Dahisar East". Business Standard. Retrieved 9 July 2023.
  6. ^ Anthony, Hepzi (5 April 2017). "Mumbaikars save 4,000 plants on WEH from Metro axe". The Hindu. Retrieved 6 April 2017.
  7. ^ "Aviation ministry nod for Metro car depot in Dahisar - Times of India". The Times of India. 25 April 2017. Retrieved 3 May 2017.
  8. ^ "Study of building height restrictions near Mumbai airport soon | Latest News & Updates at Daily News & Analysis". dna. 24 April 2017. Retrieved 3 May 2017.
  9. ^ "Airports authority to give land for Metro-7 car shed at Dahisar in Mumbai". Hindustan Times. 23 April 2017. Retrieved 10 July 2023.
  10. ^ "Three plots at Mumbai's Aarey Milk Colony allotted for Andheri East-Dahisar Metro-7 corridor". Hindustan Times. 15 June 2017. Retrieved 10 July 2023.
  11. ^ "Mumbai: MMRDA changes location of 2 Metro depots". The Indian Express. 18 November 2021. Retrieved 10 July 2023.
  12. ^ "Metro-2A will be Yellow line, 7 to be Red". Hindustan Times. 29 February 2020. Retrieved 9 July 2023.
  13. ^ "Metro lines 2A, 7 have potential to create 1.1 million jobs: Study". Hindustan Times. 24 March 2021. Retrieved 9 July 2023.
  14. ^ "Bidding for Metro 10 line to start later this year | Latest News & Updates at Daily News & Analysis". dna. 22 March 2017. Retrieved 24 March 2017.
  15. ^ "Mira-Bhayander to be connected with Metro". The Times of India. 25 February 2017. Retrieved 25 February 2017.
  16. ^ "Plans to extend metro stations to Bhayander may be implemented soon". dna. 25 February 2017. Retrieved 25 February 2017.
  17. ^ "Dahisar metro extension work to begin in December 2017". Asian Age. 25 February 2017. Retrieved 25 February 2017.
  18. ^ "Metro VII may extend to domestic airport - Times of India". The Times of India. 22 March 2017. Retrieved 24 March 2017.
  19. ^ "Maharashtra government to extend Mumbai Metro corridors to Mira-Bhayandar | Latest News & Updates at Daily News & Analysis". dna. 30 March 2017. Retrieved 30 March 2017.
  20. ^ "Will extend Metro network to Mira-Bhayandar and airport: Maha CM Devendra Fadnavis". Hindustan Times. 30 March 2017. Retrieved 30 March 2017.
  21. ^ "Metro to extend to Mira-Bhayander and airport: Chief Minister Devendra Fadnavis". The Indian Express. 30 March 2017. Retrieved 30 March 2017.
  22. ^ Naik, Yogesh (12 April 2017). "State clears extension of Metro 7 up to Terminal 2". Mumbai Mirror. Retrieved 13 April 2017.
  23. ^ "Mumbai Metro 7 will not be extended to domestic terminal". Hindustan Times. 10 July 2018. Retrieved 10 July 2023.
  24. ^ "Maha Cabinet clears Metro 7-A, 9 lines". The Asian Age. 12 September 2018. Retrieved 9 October 2018.
  25. ^ "Mumbai To Get Two New Metro Lines". NDTV.com. Retrieved 9 October 2018.
  26. ^ "Metro Line - 7". mmrda.maharashtra.gov.in. Retrieved 10 July 2023.
  27. ^ "Charkop Car Depot To Now House Metro 7 and 2-A". Mumbai Live. 10 February 2020. Retrieved 9 July 2023.
  28. ^ Rao, Shashank. "Obstacles in getting car shed at Dahisar gives birth to a semi-circular metro line". Mumbai Mirror. Retrieved 9 July 2023.
  29. ^ "Work on Mumbai Metro lines 2A, 7 delayed, likely to start operation by Jan 2022". The Indian Express. 4 September 2020. Retrieved 9 July 2023.
  30. ^ "Mumbai: MMRDA changes location of 2 Metro depots". The Indian Express. 18 November 2021. Retrieved 10 July 2023.
  31. ^ "PM Narendra Modi to inaugurate Mumbai Metro Lines 2A, 7 today: All you need to know". The Indian Express. 14 January 2023. Retrieved 9 July 2023.
  32. ^ "Metro Line 2A to use Charkop depot till work on Line 2B & Mandale depot is completed". The Indian Express. 28 December 2022. Retrieved 9 July 2023.
  33. ^ "MMRDA invites civil work bids for two Metro projects". The Times of India. 5 January 2017. from the original on 12 February 2017. Retrieved 10 February 2017.
  34. ^ Mishra, Lalatendu (4 May 2016). "Work on Mumbai Metro 7 to start by September". The Hindu. Retrieved 10 February 2017.
  35. ^ "MMRDA invites bids for Andheri-Dahisar metro line". The Economic Times. 16 December 2015. ISSN 0013-0389. Retrieved 10 July 2023.
  36. ^ www.ETRealty.com. "Simplex Infra, JKumar, NCC to develop Mumbai's Metro-7 corridor - ET RealEstate". ETRealty.com. Retrieved 10 July 2023.
  37. ^ Nandgaonkar, Satish (18 April 2016). "MMRDA awards contracts for Andheri-Dahisar metro". The Hindu. Retrieved 10 February 2017.
  38. ^ "Days after MMRDA removes contractor: Three bidders in race for Metro line 7 construction". The Indian Express. 29 February 2020. Retrieved 10 July 2023.
  39. ^ "Metro VII work begins today, may hit WEH traffic | Mumbai News - Times of India". The Times of India. 7 August 2016.
  40. ^ Mishra, Lalatendu (18 February 2017). "Metro 7 contractors told to speed up work". The Hindu. Retrieved 19 February 2017.
  41. ^ "Northbound WEH lanes to be shut at night". Asian Age. 3 May 2017. Retrieved 3 May 2017.
  42. ^ "Mumbai Metro-7 line to have 14 stations along Western Express Highway". The Asian Age. 2 January 2018. Retrieved 10 July 2023.
  43. ^ "Stay on metro casting yard at Bandra". Asian Age. 15 March 2017. Retrieved 16 March 2017.
  44. ^ "Bombay High Court stalls Metro 7 work over burial ground | Free Press Journal". Free Press Journal. Retrieved 16 March 2017.
  45. ^ "Metro work damages gas pipeline, accident averted". The Indian Express. 30 March 2017. Retrieved 30 March 2017.
  46. ^ "Pipeline bursts, gas supply to Mumbai's western suburbs hit". Hindustan Times. 29 March 2017. Retrieved 30 March 2017.
  47. ^ "Mumbai: Repair of MGL gas pipeline puncture to begin today". dna. 31 March 2017. Retrieved 4 April 2017.
  48. ^ Dhupkar, Alka (16 April 2017). "Ready mix concrete plant for Metro 7 is illegal: BMC". Mumbai Mirror. Retrieved 10 July 2023.
  49. ^ "Within 10 months, Metro 7 moves to second stage of construction". The Indian Express. 4 April 2017. Retrieved 4 April 2017.
  50. ^ "Metro VII piers work to begin next week - Times of India". The Times of India. 6 April 2017. Retrieved 6 April 2017.
  51. ^ "In pics: CM puts Mumbai's Metro 7 on right track; western express highway opens after 5 hours". Hindustan Times. 3 May 2017. Retrieved 3 May 2017.
  52. ^ a b "Hoping to open Mumbai Metro 7 by 2019, Maharashtra to invite bids for coaches". Hindustan Times. 7 May 2017. Retrieved 8 May 2017.
  53. ^ "Metro takes up toughest task at night". The Indian Express. 25 June 2017. Retrieved 5 July 2017.
  54. ^ "MMRDA issues notices to Mumbai Metro 7 contractors for 'poor progress'". Hindustan Times. 19 August 2017. Retrieved 10 July 2023.
  55. ^ "Western Express Highway: Barricades for Metro 7 construction to be removed by next monsoon". The Indian Express. 18 August 2017. Retrieved 10 July 2023.
  56. ^ "Work on track: MMRDA starts laying rail lines for Metro 2A, 7". Hindustan Times. 18 June 2019. Retrieved 9 July 2023.
  57. ^ "First escalator of Metro 7 installed". The Hindu. 13 August 2019. ISSN 0971-751X. Retrieved 10 July 2023.
  58. ^ "Contractor expelled, MMRDA gives Metro-7 works at higher costs". Hindustan Times. 10 July 2020. Retrieved 10 July 2023.
  59. ^ "MMRDA terminates contracts for Metro Line 2B over delays". The Hindu. 4 February 2020. ISSN 0971-751X. Retrieved 10 July 2023.
  60. ^ "Mumbai: Two new contractors appointed for balance civil works on Metro Line 7". The Times of India. 16 May 2020. ISSN 0971-8257. Retrieved 10 July 2023.
  61. ^ "Mumbai Metro 2A, 7 trials to start from Jan 14". The Indian Express. 11 September 2020. Retrieved 9 July 2023.
  62. ^ "MMRDA begins pre-trials for Mumbai's Metro trains". Hindustan Times. 25 February 2021. Retrieved 9 July 2023.
  63. ^ "MMRDA to conduct test run for two elevated Metro lines next week". Mumbai Mirror. IANS. 26 May 2021. Retrieved 9 July 2023.
  64. ^ "Mumbai: Trial run for Metro Line 2A and 7 flagged off". The Indian Express. 1 June 2021. Retrieved 10 July 2023.
  65. ^ "Mumbai: Dynamic trial run begins on Metro corridors 2A and 7". The Indian Express. 20 June 2021. Retrieved 9 July 2023.
  66. ^ "Mumbai: Metro corridors 2A, 7 get RDSO provisional certificate". The Indian Express. 29 January 2022. Retrieved 9 July 2023.
  67. ^ "Mumbai: CMRS starts inspection of Phase 1 of Metro corridors 2A and 7". The Indian Express. 20 February 2022. Retrieved 9 July 2023.
  68. ^ "Mumbai: Phase 1 of Metro Line 2A and 7 opened for public". The Indian Express. 3 April 2022. Retrieved 9 July 2023.
  69. ^ "Mumbai's Metro Line 2A, 7 clear designs & standards testing". The Indian Express. 13 October 2022. Retrieved 9 July 2023.
  70. ^ "Supervision of Mumbai Metro Lines 2A and 7 by Commission of Metro Rail Safety underway". The Indian Express. 30 November 2022. Retrieved 9 July 2023.
  71. ^ "PM Narendra Modi inaugurates Mumbai Metro lines 2A and 7; what you need to know about the new routes". The Economic Times. 19 January 2023. ISSN 0013-0389. Retrieved 9 July 2023.
  72. ^ Livemint (18 January 2023). "PM Modi to inaugurate Mumbai Metro Rail Lines 2A and 7 on 19 January. 10 points". mint. Retrieved 9 July 2023.
  73. ^ "Metro 7A in Mumbai to get twin tunnels". Hindustan Times. 24 January 2019. Retrieved 10 July 2023.
  74. ^ "Mumbai: Work on second underground Metro line 7A begins". Indian Express. 5 March 2020. Retrieved 15 May 2020.
  75. ^ "Mumbai: Here is latest update of more than dozen Metro projects in the city". Free Press Journal. Retrieved 10 July 2023.
  76. ^ "Mumbai Metropolitan Region Development Authority - Metro Line - 9". mmrda.maharashtra.gov.in. Retrieved 2 May 2021.
  77. ^ "Line 7-Project Features-Stations". MMRDA. Retrieved 7 June 2017.
  78. ^ "MMRDA approves cost hike for two packages of Mumbai Metro-7, but says overall cost won't be hit". Hindustan Times. 6 December 2020. Retrieved 10 July 2023.
  79. ^ "Asian Development Bank To Lend $926 Million For Mumbai Metro Rail Project". NDTV.com. Retrieved 14 March 2019.
  80. ^ "State clears extension of Metro 7 up to Terminal 2". Mumbai Mirror. 12 April 2017. Retrieved 7 June 2017.
  81. ^ "Consultant for MTHL finalized". The Times of India. 26 November 2016. Retrieved 26 November 2016.
  82. ^ "Mumbai Trans-Harbour Link: MMRDA approves appointment of general consultants". The Indian Express. 26 November 2016. Retrieved 26 November 2016.
  83. ^ "General consultant appointed for MTHL project". dna. 25 November 2016. Retrieved 26 November 2016.
  84. ^ Shah, Narendra (23 November 2018). "BEML bags Rs.3,015 Crore Contract for Mumbai Metro Corridor". Metro Rail News. Retrieved 9 July 2023.
  85. ^ a b "Mumbai: Manufacturing of coaches commences for Metro Lines 2A, 2B and 7". Mid-day. 1 August 2019. Retrieved 9 July 2023.
  86. ^ "BEML delivers first India-made driverless metro cars to Mumbai Metro". domain-b.com. Retrieved 9 July 2023.
  87. ^ "BEML starts work on Mumbai metro cars". Deccan Herald. 30 July 2019. Retrieved 10 July 2023.
  88. ^ "Mumbai Metro gets first 'Make in India' driverless metro cars with bi-cycle parking facility; details here". Financialexpress. 8 September 2019. Retrieved 9 July 2023.
  89. ^ "Mumbai: 1st rake for Metro-2A arrives; CM to unveil it on Friday". Hindustan Times. 28 January 2021. Retrieved 9 July 2023.
  90. ^ "BEML bags Rs3,015-cr order for Mumbai Metro Corridor". domain-b.com. Retrieved 9 July 2023.
  91. ^ "Alstom to provide state-of-the-art signalling system for Mumbai Metro and Pune Metro". Financialexpress. 1 April 2019. Retrieved 9 July 2023.
  92. ^ "Alstom bags Rs 700 crore contracts from Mumbai, Pune metros". Construction Week. Retrieved 9 July 2023.
  93. ^ "Adani to supply power for MMRDA's two new metro lines". Hindustan Times. 2 December 2022. Retrieved 9 July 2023.
  94. ^ "Adani Electricity to power Mumbai Metro Lines 2A & 7 connecting Andheri to Dahisar". Free Press Journal. Retrieved 9 July 2023.
  95. ^ Release, Press. "Datamatics wins AFC System contract for Mumbai Metro Line 2A, 2B & 7". www.datamatics.com.
  96. ^ Mahale, Ajeet (7 February 2019). "MMRDA finalises firm for AFC on 3 Metro lines". The Hindu. Retrieved 5 December 2022.
  97. ^ "Datamatics Wins Automated Fare Collection Contract for Mumbai Metro Line 2A, 2B and 7". Business Standard India. Press Trust of India. 8 February 2019. Retrieved 5 December 2022.

line, mumbai, metro, line, rapid, transit, line, mumbai, maharashtra, india, part, mumbai, metro, system, when, fully, completed, line, will, connect, bhayander, with, chhatrapati, shivaji, maharaj, international, airport, with, stations, line, mostly, elevate. Red Line 7 is a rapid transit line in Mumbai Maharashtra India and part of the Mumbai Metro system When fully completed the 30 08 km 18 69 mi line will connect Bhayander with the Chhatrapati Shivaji Maharaj International Airport with 24 stations The line is mostly elevated 27 89 km 17 33 mi and partially underground 2 19 km 1 36 mi 2 Mumbai Metro Red Line 7OverviewStatusOperational extension under construction OwnerMMRDALine number7LocaleMumbai Maharashtra IndiaTerminiDahisar EastGundavaliStations14WebsiteLine 7ServiceTypeRapid transitSystemMumbai MetroDepot s Charkop temporary Bhayandar planned Rolling stockBEMLDaily ridership212 000 July 2023 1 HistoryCommenced8 August 2016 2016 08 08 Opened2 April 2022 18 months ago 2022 04 02 TechnicalLine length16 5 km 10 3 mi Number of tracks2CharacterElevatedTrack gauge1 435 mm 4 ft 8 1 2 in standard gaugeElectrification25 kV 50 Hz AC overhead lineLine 7 mapLegendLine 7to Red Line 9Dahisar Depotto Yellow Line 20 0000 Dahisar East1 1404 Ovaripada2 1484 Rashtriya Udyan3 2749 Devipada4 0972 Magathane5 8249 Poisar6 4492 Akurli7 4569 Kurar8 3449 Dindoshi9 4249 Aarey11 7434 Goregaon East13 1110 Jogeshwari East on Pink Line 614 2951 Mogra15 5249 GundavaliWestern Express Highway on Blue Line 116 0849 Airport Colonyto Aqua Line 318 9342 CSMIA Internationalto Gold Line 8A section of the line from Dahisar East to Aarey was opened on 2 April 2022 and another section from Aarey to Gundavli in Andheri East was inaugurated on 19 January 2023 An under construction 11 386 km section of Line 7 from Bhayander to Dahisar is part of Red Line 9 A southward extension to the airport is also currently under construction The line is served by six car trains manufactured by Bharat Earth Movers Limited with a headway of 10 minutes Line 7 currently uses Line 2 s depot at Charkop due to an issue acquiring land for a depot Services currently operate between Gundavali and Andheri West on Line 2 via Dahisar East Contents 1 Planning 1 1 Extensions 1 2 Depot and Line 2 link 2 Construction 2 1 Line 7A 2 2 Current Status for Line 7A 3 Stations 4 Cost 5 Infrastructure 5 1 Rolling stock 5 2 Signalling 5 3 Power 5 4 Fare collection 6 ReferencesPlanning EditAn 18 km 11 mi metro line connecting Andheri East and Dahisar East was proposed as Line 7 in the original Mumbai Metro master plan unveiled by the Mumbai Metropolitan Region Development Authority MMRDA in 2004 3 In June 2015 the MMRDA proposed building Line 7 as part of a plan to build 6 new metro lines at a total estimated cost of 64 000 crore US 8 0 billion 4 The MMRDA approved the detailed project report for Line 7 in August 2015 The report proposed a 16 5 km 10 3 mi elevated line between Andheri East and Dahisar East at an estimated cost of 4 737 crore US 590 million 5 Over the course of two weeks in March April 2017 Mumbai residents saved nearly 4 000 trees planted on dividers and along the WEH that had been planned to be felled for metro construction Residents replanted these trees at their own housing societies as well as schools and other locations Nearly 210 people and over 40 housing societies participated in the initiative coordinating their efforts through WhatsApp messages 6 In April 2017 the Ministry of Civil Aviation approved the transfer of 40 acres of land in Dahisar for the construction of the metro depot 7 8 The Airports Authority of India and the MMRDA signed a formal agreement on 24 April 2017 9 In June 2017 the Maharashtra Government transferred three plots of land at Aarey Colony measuring a total of 20 387 sqm 5 03 acres to the MMRDA for a labour camp and a casting yard for Line 7 and a centralised operation centre for the metro system 10 In November 2021 the MMRDA cancelled the plan to build the line s depot at Dahisar and instead proposed building the depot for Line 7 and its extensions at Rai Murdhe in Bhayandar 11 In February 2020 MMRDA metropolitan commissioner R A Rajeev stated that Line 7 would be identified as the Red Line 12 A study by World Resources Institute WRI India published in May 2021 estimated that Line 7 and Line 2A had the potential to create 1 1 million jobs in the city 13 Extensions Edit Further information Line 9 Mumbai Metro In February 2017 the MMRDA announced that the DMRC was preparing a detailed project report DPR on a proposed 9 km 5 6 mi extension of Line 7 from Dahisar to Bhayander via Mira Road 14 The extension would have 9 stations with an inter station distance of 1 km 0 62 mi The line would run parallel to the Surat Dahisar Highway then turn left at Kashi Mira Junction before passing through Mira Road Bhayander and terminating at Golden Nest Circle in Bhayander The project is estimated to cost 3 600 crore US 450 million 15 16 17 In March 2017 the MMRDA stated that the DMRC was conducting a feasibility study to extend the line to Terminal 2 of the Chhatrapati Shivaji Maharaj International Airport The proposed 3 17 km 1 97 mi extension called Line 7A from Andheri to the airport will pass beneath Line 1 s Western Express Highway station 18 The extensions to Mira Bhayander and the airport were officially announced by Chief Minister Fadnavis on 30 March 2017 19 20 21 The alignment for the extension from Andheri to Chhatrapati Shivaji Maharaj International Terminus was approved by the State Cabinet on 12 April 2017 22 In June 2018 the MMRDA stated that it had decided to terminate the proposed extension at the international airport and not extend it to the domestic terminal due technical challenges As the metro extension is proposed to be underground it would have to constructed below or above Line 3 which also passes under the airport 23 The 3 17 km 1 97 mi extension includes a 0 98 km 0 61 mi elevated stretch and 2 19 km 1 36 mi twin tunnel The Maharashtra Cabinet approved the implementation of both extensions in September 2018 24 25 HistorySection Extension date Termini Length StationsLine 7 26 2 April 2022 Dahisar East Aarey 10 7 kilometers 6 6 mi 1019 January 2023 Aarey Gundavali 5 8 kilometers 3 6 mi 4Line 7A Gundavali CSMIA International 3 175 kilometers 1 973 mi 2Dahisar East CSMIA International 19 675 kilometers 12 225 mi 16Depot and Line 2 link Edit The depot for Line 7 was proposed to be located at Dahisar 27 However land acquisition for the Dahisar depot was delayed by litigation filed in 2016 In 2020 the MMRDA proposed using the depot at Charkop to serve both Line 2 and Line 7 by building a ring metro line to connect the two corridors The MMRDA utilized an empty plot of land located after Ovaripada station on Line 7 to build pillars for the link connecting the two lines 28 29 Line 2 of the Mumbai Metro connects Dahisar East with Andheri West In November 2021 the MMRDA cancelled the plan to build the depot at Dahisar and instead proposed building the depot for Lines 7 7A and 9 at Rai Murdhe in Bhayandar 30 Line 2 and Line 7 were both commissioned on 2 April 2022 with services operating between Aarey and Dahanukarwadi via Dahisar East Both lines were extended on 19 January 2023 providing circular service between Gundavali and Andheri West via Dahisar East 31 The Charkop depot currently serves as the depot for Line 2 and Line 7 The under construction Mandale depot will be used to serve Line 2 once completed 32 Construction EditThe bhoomipujan ceremony for Line 7 was performed by Prime Minister Narendra Modi during his visit to Mumbai on 11 October 2015 33 Line 7 was implemented through the engineering procurement and construction EPC model 34 The MMRDA invited bids for the project in December 2015 35 Tendering for the design and construction of the corridor was split into 3 packages The first package included an elevated viaduct and 5 elevated stations Andheri East Shankarwadi JVLR Junction Mahanand and new Ashok Nagar The second package included an elevated viaduct and 6 elevated stations Aarey Dindoshi Pathan Wadi Pushpa Park Bandongri and Mahindra amp Mahindra and an elevated viaduct and 5 elevated stations Magathane Devipada National Park Ovaripada and Dahisar East A total of 16 companies expressed interest and 9 bids were submitted In April 2016 the MMRDA awarded contracts to Simplex Infrastructure J Kumar Infraprojects and Nagarjuna Construction Company for the first second and third packages respectively The project is estimated to cost 6 208 crore US 780 million 36 37 The contract awarded to Simplex Infrastructure was worth 348 crore US 44 million 38 Construction work on the corridor began on 8 August 2016 The contractors were expected to complete construction of the corridor and all 14 stations within 30 months from the day of commencement of work 39 On 18 February 2017 MMRDA officials stated that 15 of piling pile caps and pier work on the corridor had been completed 40 By the end of April 2017 25 of piling work 60 of barricading work and 77 of the soil testing for pier foundation had been completed 41 Line 7 stations were built on a single pier unlike the three piers used to support stations on Line 1 The single pier design was chosen to facilitate the construction of smaller stations and reduce the amount of land occupied on the Western Express Highway which could obstruct traffic flow 42 On 14 March 2017 the Mumbai High Court temporarily stayed all construction activities at Metro 7 s casting yard in Bandra Reclamation The Court was hearing a PIL filed by Mohammed Furqan Ali Mohammed Qureshi who alleged that the site of the casting yard had been reserved by the Brihanmumbai Municipal Corporation BMC for use as a Sunni Muslim cemetery 43 44 Piling work in Kandivli resulted in a gas pipeline bursting on 29 March 2017 The damage to the Mahanagar Gas pipeline resulted in temporary disruptions in the supply of CNG to Kandivli Borivli Dahisar Mira Road and Bhayander 45 46 Mahanagar Gas began repairing the pipeline on the evening of 31 March and completed the work by the following evening 47 The BMC accused Nagarjuna Construction Company of illegally operating an unlicensed concrete ready mix plant at its casting yard in April 2017 48 The MMRDA announced that construction of viaducts would begin in April 2017 The agency had completed construction of piers on several sections of the corridor and the viaducts will be built at locations where pier caps have been built The first viaduct was constructed in the section between JVLR to Mahanand Construction of all pier caps along the corridor will be completed by the end of 2017 49 50 The first U girder the concrete structure on which metro tracks are laid was launched near Pathanwadi Junction in Malad on 2 May 2017 51 In total Metro 7 required 1 400 U girders 52 Work on erecting the U girders as well as disposal and dumping of muck generated from underground work was done only between 11 30 pm and 6 00 am During this period multi axle trailers transported U girders weighing 170 tonne from the casting yard in Bandra to the location where it is to be erected The trailer had to move slowly to avoid causing imbalance to the heavy load which can result in toppling and took roughly two hours to complete the journey Lifting the girder and attaching it to the pier caps was also a difficult process and was carried out at night time Traffic diversions were placed around the launching site to reduce the possibility of accidents Officials erected an average of two girders every day 53 The MMRDA issued notices to all three contractors working on the project on 11 August 2017 over the poor progress of work The agency stated that the although contractors were required to deploy 600 workers each Simplex had only deployed 320 J Kumar Infraprojects had deployed 395 and NCC had deployed 318 labourers The MMRDA had also issued a similar notice on 4 July 2017 54 By August 2017 about 600 700 metres of each package had been constructed 63 piers and 22 girders had been erected and barricades had been placed on 67 of the entire route 55 Track laying work on the line began in June 2019 56 The first escalator on Line 7 was installed at Bandongri station in August 2019 57 In January 2020 the MMRDA terminated the contract awarded to Simplex Infrastructure for the first package over delay in completing the work The next month the agency invited bids to replace Simplex The work was split into two tenders including one for a 6 25km viaduct and another to complete work on 4 stations In July 2020 the MMRDA awarded a 174 76 crore US 22 million and 127 78 crore US 16 million contract to J Kumar Infraprojects and Nagarjuna Construction Company respectively to complete the work 58 The MMRDA also encashed a bank guarantee of 35 crore US 4 4 million provided by Simplex 59 Simplex had completed around 75 of work at the time its contract was terminated 60 MMRDA metropolitan commissioner R A Rajeev stated in September 2020 that almost 80 of construction work had been completed 61 The MMRDA began conducting pre trials on the rolling stock at the Charkop depot in February 2021 62 The MMRDA announced that electrification of the line had been completed on 26 May and the first trial runs were conducted from 31 May 63 64 The MMRDA began a dynamic test and trial run on the 20 km stretch between Dhanukarwadi and Aarey including a portion of Line 2 on 19 June 65 The stretch between Dhanukarwadi and Aarey received provisional approval from the Research Designs and Standards Organisation RDSO in January 2022 66 The Commissioner of Metro Rail Safety CMRS began inspecting the line in February 2022 67 A section of Line 7 from Dahisar East to Aarey along with the section of Line 2 from Dhanukarwadi to Dahisar East was opened on 2 April 2022 Chief Minister Uddhav Thackeray flagged off the first train at 4pm in the presence of Deputy Chief Minister Ajit Pawar Urban Development Minister Eknath Shinde NCP chief Sharad Pawar and the Leader of Opposition in the Legislative Council Pravin Darekar The line opened for public service from 8pm with services operating between Aarey and Dahanukarwadi on Line 2 via Dahisar East 68 The remaining section of Line 7 from Goregaon East to Gundavali received approval from the RDSO in October 2022 69 The CMRS began inspecting the line in December 2022 70 The final section of the line along with the final section of Line 2A from Dhanukarwadi to Andheri West was inaugurated on 19 January 2023 by Prime Minister Narendra Modi 71 72 Line 7A Edit Line 7A is a 3 175 km 1 973 mi southward extension of Line 7 to Chhatrapati Shivaji Maharaj International Airport with 2 stations The section includes a 0 98 km 0 61 mi elevated stretch and 2 195 km 1 364 mi long twin tunnels 73 Work on the airport extension began in March 2020 The MMRDA awarded the construction contract to J Kumar Infrastructure 74 Around 25 of work on the extension was completed by November 2022 75 Current Status for Line 7A Edit Sr No Name of Work Status for year 2021 76 1 March 2021 1 May 2021 1 June 2021 2 August 2021 30 September 20211 Survey Work 100 2 Barricading board fixing 15 27 30 3 Soil Investigation Works 86 89 92 4 Utility Identification Works 28 29 32 5 Piling Works 19 Test Pile 100 6 Working Pile 22 7 Pile cap 9 Stations EditLine 7 has 14 operational stations with two more stations under construction Red Line 7 Station Name 77 Opening Connections LayoutEnglish Marathi1 Dahisar East दह सर प र व 2 April 2022 Yellow Line 2 andRed Line 9 Under Construction Elevated2 Ovaripada ओवर प ड 2 April 2022 None Elevated3 Rashtriya Udyan र ष ट र य उद य न 2 April 2022 None Elevated4 Devipada द व प ड 2 April 2022 None Elevated5 Magathane म ग ठ ण 2 April 2022 None Elevated6 Poisar प ईसर 2 April 2022 None Elevated7 Akurli आक र ल 2 April 2022 None Elevated8 Kurar क र र 2 April 2022 None Elevated9 Dindoshi द ड श 2 April 2022 None Elevated10 Aarey आर 2 April 2022 None Elevated11 Goregaon East ग र ग व प र व 19 January 2023 None Elevated12 Jogeshwari East ज ग श वर प र व 19 January 2023 Pink Line 6 Under Construction Elevated13 Mogra म गर 19 January 2023 None Elevated14 Gundavali ग दवल 19 January 2023 Blue Line 1 Elevated15 Airport Colony व म नतळ वस हत Under Construction None Elevated16 CSMIA International स एसएमआयए आ तरर ष ट र य Under Construction Aqua Line 3 Under Construction and Gold Line 8 Proposed UndergroundCost EditLine 7 is estimated to cost 6 208 crore US 780 million 78 The Asian Development Bank ADB will provide 43 48 of the total project cost through a loan at an interest rate of 1 4 The Government of Maharashtra is the guarantor for the loan 52 On 2 March 2019 the Union Ministry of Finance stated that it signed a 926 million loan agreement with the ADB to fund the construction of Line 2 and Line 7 This was the single largest infrastructure loan ever extended by the ADB The funds will be used to procure 63 six car trainsets and for signaling and safety systems on both corridors 79 The proposed extension of Line 7 from Dahisar to Bhayander called Line 9 is estimated to cost 3 600 crore US 450 million and the underground extension to the International Airport shall cost an additional 600 crore US 75 million 80 The MMRDA allotted 340 crore US 43 million to the DMRC to implement and commission rolling stock signalling and telecommunication work for the Metro 2A and Metro 7 corridors on 26 November 2016 81 82 83 Infrastructure EditRolling stock Edit BEML was awarded a 3 015 crore US 380 million contract to supply 378 metro cars 63 trainsets for Line 7 and Line 2 in November 2018 84 An additional 126 metro cars 21 trainsets were ordered from BEML to cater to metro extensions 85 All trainsets were manufactured at BEML s Rail Coach Factory in Bangalore Karnataka The rakes are capable of driverless operation making them the first driverless metro trains to be made in India 86 BEML began manufacturing the coaches on 29 July 2019 87 built the first metro coach in 75 days and unveiled it in September 2019 88 The first trainset arrived in Mumbai on 28 January 2021 89 Each trainset is made up of 6 coaches with a total passenger capacity of 1 660 and dense crush load capacity of 2 092 The trainset is 3 2 metres wide made of stainless steel and each coach has 4 doors on each side The rake employs a regenerative braking system 90 85 Signalling Edit Line 7 utilises the Alstom Urbalis 400 communications based train control CBTC signalling system Alstom was awarded a EUR90 million contract to supply the signalling and telecommunications systems for Mumbai Metro Line 2 and Line 7 as well as Pune Metro Line 1 and Line 7 91 92 Power Edit Line 7 is electrified at 25 kV 50 Hz AC with power provided via an overhead catenary The MMRDA signed an agreement with Adani Electricity Mumbai Limited to supply electricity to Line 7 and Line 2A on 2 December 2022 Around 120 million units is required to power both lines 93 94 Fare collection Edit A consortium of Indian company Datamatics and Italian company AEP Ticketing solutions S R L was awarded a 160 crore US 20 million contract to implement the automated fare collection system for Line 7 and Line 2 in February 2019 95 96 97 References Edit Two Mumbai Metro lines report record single day ridership of 2 14 lakh amid heavy rain cnbctv18 com 20 July 2023 Retrieved 30 September 2023 Mumbai Metropolitan Region Development Authority Metro Line 9 mmrda maharashtra gov in Retrieved 10 July 2023 Mmrda Projects Mumbai Metro Rail Project Mmrdamumbai org Archived from the original on 19 March 2012 Retrieved 12 March 2014 Over 130 km of Metro lines to criss cross city by 2020 The Indian Express 16 June 2015 Retrieved 9 July 2023 MMRDA sanctions Rs 35 400 cr for 118 km Mumbai metro network Andheri East and Dahisar East Business Standard Retrieved 9 July 2023 Anthony Hepzi 5 April 2017 Mumbaikars save 4 000 plants on WEH from Metro axe The Hindu Retrieved 6 April 2017 Aviation ministry nod for Metro car depot in Dahisar Times of India The Times of India 25 April 2017 Retrieved 3 May 2017 Study of building height restrictions near Mumbai airport soon Latest News amp Updates at Daily News amp Analysis dna 24 April 2017 Retrieved 3 May 2017 Airports authority to give land for Metro 7 car shed at Dahisar in Mumbai Hindustan Times 23 April 2017 Retrieved 10 July 2023 Three plots at Mumbai s Aarey Milk Colony allotted for Andheri East Dahisar Metro 7 corridor Hindustan Times 15 June 2017 Retrieved 10 July 2023 Mumbai MMRDA changes location of 2 Metro depots The Indian Express 18 November 2021 Retrieved 10 July 2023 Metro 2A will be Yellow line 7 to be Red Hindustan Times 29 February 2020 Retrieved 9 July 2023 Metro lines 2A 7 have potential to create 1 1 million jobs Study Hindustan Times 24 March 2021 Retrieved 9 July 2023 Bidding for Metro 10 line to start later this year Latest News amp Updates at Daily News amp Analysis dna 22 March 2017 Retrieved 24 March 2017 Mira Bhayander to be connected with Metro The Times of India 25 February 2017 Retrieved 25 February 2017 Plans to extend metro stations to Bhayander may be implemented soon dna 25 February 2017 Retrieved 25 February 2017 Dahisar metro extension work to begin in December 2017 Asian Age 25 February 2017 Retrieved 25 February 2017 Metro VII may extend to domestic airport Times of India The Times of India 22 March 2017 Retrieved 24 March 2017 Maharashtra government to extend Mumbai Metro corridors to Mira Bhayandar Latest News amp Updates at Daily News amp Analysis dna 30 March 2017 Retrieved 30 March 2017 Will extend Metro network to Mira Bhayandar and airport Maha CM Devendra Fadnavis Hindustan Times 30 March 2017 Retrieved 30 March 2017 Metro to extend to Mira Bhayander and airport Chief Minister Devendra Fadnavis The Indian Express 30 March 2017 Retrieved 30 March 2017 Naik Yogesh 12 April 2017 State clears extension of Metro 7 up to Terminal 2 Mumbai Mirror Retrieved 13 April 2017 Mumbai Metro 7 will not be extended to domestic terminal Hindustan Times 10 July 2018 Retrieved 10 July 2023 Maha Cabinet clears Metro 7 A 9 lines The Asian Age 12 September 2018 Retrieved 9 October 2018 Mumbai To Get Two New Metro Lines NDTV com Retrieved 9 October 2018 Metro Line 7 mmrda maharashtra gov in Retrieved 10 July 2023 Charkop Car Depot To Now House Metro 7 and 2 A Mumbai Live 10 February 2020 Retrieved 9 July 2023 Rao Shashank Obstacles in getting car shed at Dahisar gives birth to a semi circular metro line Mumbai Mirror Retrieved 9 July 2023 Work on Mumbai Metro lines 2A 7 delayed likely to start operation by Jan 2022 The Indian Express 4 September 2020 Retrieved 9 July 2023 Mumbai MMRDA changes location of 2 Metro depots The Indian Express 18 November 2021 Retrieved 10 July 2023 PM Narendra Modi to inaugurate Mumbai Metro Lines 2A 7 today All you need to know The Indian Express 14 January 2023 Retrieved 9 July 2023 Metro Line 2A to use Charkop depot till work on Line 2B amp Mandale depot is completed The Indian Express 28 December 2022 Retrieved 9 July 2023 MMRDA invites civil work bids for two Metro projects The Times of India 5 January 2017 Archived from the original on 12 February 2017 Retrieved 10 February 2017 Mishra Lalatendu 4 May 2016 Work on Mumbai Metro 7 to start by September The Hindu Retrieved 10 February 2017 MMRDA invites bids for Andheri Dahisar metro line The Economic Times 16 December 2015 ISSN 0013 0389 Retrieved 10 July 2023 www ETRealty com Simplex Infra JKumar NCC to develop Mumbai s Metro 7 corridor ET RealEstate ETRealty com Retrieved 10 July 2023 Nandgaonkar Satish 18 April 2016 MMRDA awards contracts for Andheri Dahisar metro The Hindu Retrieved 10 February 2017 Days after MMRDA removes contractor Three bidders in race for Metro line 7 construction The Indian Express 29 February 2020 Retrieved 10 July 2023 Metro VII work begins today may hit WEH traffic Mumbai News Times of India The Times of India 7 August 2016 Mishra Lalatendu 18 February 2017 Metro 7 contractors told to speed up work The Hindu Retrieved 19 February 2017 Northbound WEH lanes to be shut at night Asian Age 3 May 2017 Retrieved 3 May 2017 Mumbai Metro 7 line to have 14 stations along Western Express Highway The Asian Age 2 January 2018 Retrieved 10 July 2023 Stay on metro casting yard at Bandra Asian Age 15 March 2017 Retrieved 16 March 2017 Bombay High Court stalls Metro 7 work over burial ground Free Press Journal Free Press Journal Retrieved 16 March 2017 Metro work damages gas pipeline accident averted The Indian Express 30 March 2017 Retrieved 30 March 2017 Pipeline bursts gas supply to Mumbai s western suburbs hit Hindustan Times 29 March 2017 Retrieved 30 March 2017 Mumbai Repair of MGL gas pipeline puncture to begin today dna 31 March 2017 Retrieved 4 April 2017 Dhupkar Alka 16 April 2017 Ready mix concrete plant for Metro 7 is illegal BMC Mumbai Mirror Retrieved 10 July 2023 Within 10 months Metro 7 moves to second stage of construction The Indian Express 4 April 2017 Retrieved 4 April 2017 Metro VII piers work to begin next week Times of India The Times of India 6 April 2017 Retrieved 6 April 2017 In pics CM puts Mumbai s Metro 7 on right track western express highway opens after 5 hours Hindustan Times 3 May 2017 Retrieved 3 May 2017 a b Hoping to open Mumbai Metro 7 by 2019 Maharashtra to invite bids for coaches Hindustan Times 7 May 2017 Retrieved 8 May 2017 Metro takes up toughest task at night The Indian Express 25 June 2017 Retrieved 5 July 2017 MMRDA issues notices to Mumbai Metro 7 contractors for poor progress Hindustan Times 19 August 2017 Retrieved 10 July 2023 Western Express Highway Barricades for Metro 7 construction to be removed by next monsoon The Indian Express 18 August 2017 Retrieved 10 July 2023 Work on track MMRDA starts laying rail lines for Metro 2A 7 Hindustan Times 18 June 2019 Retrieved 9 July 2023 First escalator of Metro 7 installed The Hindu 13 August 2019 ISSN 0971 751X Retrieved 10 July 2023 Contractor expelled MMRDA gives Metro 7 works at higher costs Hindustan Times 10 July 2020 Retrieved 10 July 2023 MMRDA terminates contracts for Metro Line 2B over delays The Hindu 4 February 2020 ISSN 0971 751X Retrieved 10 July 2023 Mumbai Two new contractors appointed for balance civil works on Metro Line 7 The Times of India 16 May 2020 ISSN 0971 8257 Retrieved 10 July 2023 Mumbai Metro 2A 7 trials to start from Jan 14 The Indian Express 11 September 2020 Retrieved 9 July 2023 MMRDA begins pre trials for Mumbai s Metro trains Hindustan Times 25 February 2021 Retrieved 9 July 2023 MMRDA to conduct test run for two elevated Metro lines next week Mumbai Mirror IANS 26 May 2021 Retrieved 9 July 2023 Mumbai Trial run for Metro Line 2A and 7 flagged off The Indian Express 1 June 2021 Retrieved 10 July 2023 Mumbai Dynamic trial run begins on Metro corridors 2A and 7 The Indian Express 20 June 2021 Retrieved 9 July 2023 Mumbai Metro corridors 2A 7 get RDSO provisional certificate The Indian Express 29 January 2022 Retrieved 9 July 2023 Mumbai CMRS starts inspection of Phase 1 of Metro corridors 2A and 7 The Indian Express 20 February 2022 Retrieved 9 July 2023 Mumbai Phase 1 of Metro Line 2A and 7 opened for public The Indian Express 3 April 2022 Retrieved 9 July 2023 Mumbai s Metro Line 2A 7 clear designs amp standards testing The Indian Express 13 October 2022 Retrieved 9 July 2023 Supervision of Mumbai Metro Lines 2A and 7 by Commission of Metro Rail Safety underway The Indian Express 30 November 2022 Retrieved 9 July 2023 PM Narendra Modi inaugurates Mumbai Metro lines 2A and 7 what you need to know about the new routes The Economic Times 19 January 2023 ISSN 0013 0389 Retrieved 9 July 2023 Livemint 18 January 2023 PM Modi to inaugurate Mumbai Metro Rail Lines 2A and 7 on 19 January 10 points mint Retrieved 9 July 2023 Metro 7A in Mumbai to get twin tunnels Hindustan Times 24 January 2019 Retrieved 10 July 2023 Mumbai Work on second underground Metro line 7A begins Indian Express 5 March 2020 Retrieved 15 May 2020 Mumbai Here is latest update of more than dozen Metro projects in the city Free Press Journal Retrieved 10 July 2023 Mumbai Metropolitan Region Development Authority Metro Line 9 mmrda maharashtra gov in Retrieved 2 May 2021 Line 7 Project Features Stations MMRDA Retrieved 7 June 2017 MMRDA approves cost hike for two packages of Mumbai Metro 7 but says overall cost won t be hit Hindustan Times 6 December 2020 Retrieved 10 July 2023 Asian Development Bank To Lend 926 Million For Mumbai Metro Rail Project NDTV com Retrieved 14 March 2019 State clears extension of Metro 7 up to Terminal 2 Mumbai Mirror 12 April 2017 Retrieved 7 June 2017 Consultant for MTHL finalized The Times of India 26 November 2016 Retrieved 26 November 2016 Mumbai Trans Harbour Link MMRDA approves appointment of general consultants The Indian Express 26 November 2016 Retrieved 26 November 2016 General consultant appointed for MTHL project dna 25 November 2016 Retrieved 26 November 2016 Shah Narendra 23 November 2018 BEML bags Rs 3 015 Crore Contract for Mumbai Metro Corridor Metro Rail News Retrieved 9 July 2023 a b Mumbai Manufacturing of coaches commences for Metro Lines 2A 2B and 7 Mid day 1 August 2019 Retrieved 9 July 2023 BEML delivers first India made driverless metro cars to Mumbai Metro domain b com Retrieved 9 July 2023 BEML starts work on Mumbai metro cars Deccan Herald 30 July 2019 Retrieved 10 July 2023 Mumbai Metro gets first Make in India driverless metro cars with bi cycle parking facility details here Financialexpress 8 September 2019 Retrieved 9 July 2023 Mumbai 1st rake for Metro 2A arrives CM to unveil it on Friday Hindustan Times 28 January 2021 Retrieved 9 July 2023 BEML bags Rs3 015 cr order for Mumbai Metro Corridor domain b com Retrieved 9 July 2023 Alstom to provide state of the art signalling system for Mumbai Metro and Pune Metro Financialexpress 1 April 2019 Retrieved 9 July 2023 Alstom bags Rs 700 crore contracts from Mumbai Pune metros Construction Week Retrieved 9 July 2023 Adani to supply power for MMRDA s two new metro lines Hindustan Times 2 December 2022 Retrieved 9 July 2023 Adani Electricity to power Mumbai Metro Lines 2A amp 7 connecting Andheri to Dahisar Free Press Journal Retrieved 9 July 2023 Release Press Datamatics wins AFC System contract for Mumbai Metro Line 2A 2B amp 7 www datamatics com Mahale Ajeet 7 February 2019 MMRDA finalises firm for AFC on 3 Metro lines The Hindu Retrieved 5 December 2022 Datamatics Wins Automated Fare Collection Contract for Mumbai Metro Line 2A 2B and 7 Business Standard India Press Trust of India 8 February 2019 Retrieved 5 December 2022 Retrieved from https en wikipedia org w index php title Line 7 Mumbai Metro amp oldid 1177884368, wikipedia, wiki, book, books, library,