In the United States Department of Defense, the Integrated Master Plan (IMP) and the Integrated Master Schedule (IMS) are important program management tools that provide significant assistance in the planning and scheduling of work efforts in large and complex materiel acquisitions.[1] The IMP is an event-driven plan that documents the significant accomplishments necessary to complete the work and ties each accomplishment to a key program event.[2] The IMP is expanded to a time-based IMS to produce a networked and multi-layered schedule showing all detailed tasks required to accomplish the work effort contained in the IMP. The IMS flows directly from the IMP and supplements it with additional levels of detail——both then form the foundations to implement an Earned Value Management System.

  • The IMP is a bilateral agreement between the Government and a contractor on what defines the “event-driven” program. The IMP documents the key events, accomplishments, and the evaluation "criteria" in the development, production and/or modification of a military system; moreover, the IMS provides sequential events and key decision points (generally meetings) to assess program progress. Usually the IMP is a contractual document.
  • Supporting the IMP is the IMS that is made up of "tasks" depicting the work effort needed to complete the "criteria".[3] It is a detailed time-driven plan for program execution that helps to ensure on-time delivery dates are achieved, and that tracking and status tool are used during program execution. These tools must show progress, interrelationships and dependencies.
This example of an IMP shows a table of events, accomplishments, and criteria—without a listing of the IMP narratives. The intent is to illustrate the hierarchical structure and relationship of events, accomplishments, criteria, and tasks.

In civic planning or urban planning, Integrated Master Plan is used at the levels of city [4] development,[5] county,[6] and state or province to refer to a document integrating diverse aspects of a public works project.

Purpose and Objectives edit

The primary purpose of the IMP—and the supporting detailed schedules of the IMS—is their use by the U.S. Government and Contractor acquisition team as the day-to-day tools for the planning, executing, and tracking program technical, schedule, and cost status, including risk mitigation efforts.[7] The IMP provides a better structure than either the Work Breakdown Structure (WBS) or Organizational Breakdown Structure (OBS) for measuring actual integrated master schedule (IMS) progress.[8]

The primary objective of the IMP is a single plan that establishes the program or project fundamentals. It provides a hierarchical, event-based plan that contains: Events; Significant accomplishments; Entry and exit criteria; however it does not include any dates or durations. Using the IMP provides sufficient definition for explain program process and completion tracking, as well as providing effective communication of the program/project content and the "What and How" of the program.

Rationale edit

The IMP is a collection of milestones (called "events") that form the process architecture of the program. This means the sequence of events must always result in a deliverable product or service. While delivering products or services is relatively straight forward in some instances (i.e., list the tasks to be done, arrange them in the proper sequence, and execute to this “plan”), in other cases, problems often arise: (i) the description of "complete" is often missing for intermediate activities; (ii) program partners, integration activities, and subcontractors all have unknown or possibly unknowable impacts on the program; and (iii) as products or services are delivered the maturity of the program changes (e.g., quality and functionality expectations, as well as other attributes)——this maturity provided by defining "complete" serves as an insurance policy against future problems encountered later in the program.

Often, it's easier to define the IMP by stating what it is not. The IMP is NOT BASED on calendar dates, and therefore it is not schedule oriented; each event is completed when its supporting accomplishments are completed, and this completion is evidenced by the satisfaction of the criteria supporting each of the accomplishments. Furthermore, many of the IMP events are fixed by customer-defined milestones (e.g., Preliminary or Critical Design Review, Production Deliver, etc.) while intermediate events are defined by the Supplier (e.g., integration and test, software build releases, Test Readiness Review, etc.).

The critical IMP attribute is its focus on events, when compared to effort or task focused planning. The event focus asks and answers the question what does done look like? rather than what work has been done. Certainly work must be done to complete a task, but a focus solely on the work hides the more important metric of are we meeting our commitments? While meeting commitments is critical, it's important to first define the criteria used for judging if the commitments are being met. This is where Significant Accomplishments (SA) and their Accomplishment Criteria (AC) become important. It is important to meet commitments, but recognizing when the commitment has been met is even more important.

Attributes and Characteristics edit

The IMP provides Program Traceability by expanding and complying with the program's Statement of Objectives (SOO), Technical Performance Requirements (TPRs), the Contract Work Breakdown Structure (CWBS), and the Contract Statement of Work (CSOW)—all of which are based on the Customer's WBS to form the basis of the IMS and all cost reporting. The IMP implements a measurable and trackable program structure to accomplish integrated product development, integrate the functional program activities, and incorporates functional, lower-level and subcontractor IMPs. The IMP provides a framework for independent evaluation of Program Maturity by allowing insight into the overall effort with a level-of-detail that is consistent with levied risk and complexity metrics. It uses the methodology of decomposing events into a logical series of accomplishments having measurable criteria to demonstrate the completion and/or quality of accomplishments.

Requirements Flowdown edit

A Government customer tasks a Supplier to prepare and implement an IMP that linked with the IMS and integrated with the EVMS. The IMP list the contract requirements documents (e.g., Systems Requirements Document and Technical Requirements Document (i.e., the system specification or similar document)) as well as the IMP events corresponding to development and/or production activities required by the contract. The IMP should include significant accomplishments encompassing all steps necessary to satisfy all contract objectives and requirements, manage all significant risks, and facilitate Government insight for each event. Significant accomplishments shall be networked to show their logical relationships and that they flow logically from one to another. The IMP, IMS, and EVMS products will usually include the prime contractor, subcontractor, and major vendor activities and products.[9]

Evaluation of an IMS edit

When evaluating a proposed IMS, the user should focus on realistic task durations, predecessor/successor relationships, and identification of critical path tasks with viable risk mitigation and contingency plans. An IMS summarized at too high a level may result in obscuring critical execution elements, and contributing to failure of the EVMS to report progress. A high-level IMS may fail to show related risk management approaches being used, which can result in long duration tasks and artificial linkages masking the true critical path. In general, the IMP is a top-down planning tool and the IMS as the bottom-up execution tool. The IMS is a scheduling tool for management control of program progression, not for cost collection purposes.[10]

An IMS would seek general consistency and a standardized approach to project planning, scheduling and analysis. It may use guides such as the PASEG Generally Accepted Schedule Principles (GASP) as guidance to improve execution and enable EVMS.[11]

Relationship to other Documents edit

The IMP/IMS are related to the product-based Work Breakdown Structure (WBS) as defined in MIL-STD-881, by giving a second type of view on the effort, for different audiences or to provide a combination which gives better overall understanding.[12] Linkage between the IMP/IMS and WBS is done by referencing the WBS numbering whenever the PE (Program Event), SA (Significant Accomplishment), or AC (Accomplishment Criteria) involves a deliverable product.

Reporting Formats edit

The IMP is often called out as a contract data deliverable on United States Department of Defense materiel acquisitions, as well as other U.S. Government procurements. Formats for these deliverables are covered in Data Item Descriptions (DIDs) that define the data content, format, and data usages. Recently, the DoD cancelled the DID (DI-MISC-81183A) that jointly addressed both the IMP and the IMS.[13] The replacement documents include DI-MGMT-81650 (Integrated Master Schedule), DI-MGMT-81334A (Contract Work Breakdown Structure) and DI-MGMT-81466 (Contract Performance Report).[14][15][16] In addition DFARS 252.242–7001 and 252.242–7002 provide guidance for integrating IMP/IMS with Earned Value Management.

References edit

  1. ^ "AFMC Pamphlet 63-5, Integrated Master Plan and Schedule Guide" (PDF). United States Air Force. November 11, 2004. Retrieved August 7, 2012.
  2. ^ "Integrated Master Plan (IMP) / Integrated Master Schedule (IMS)". Defense Acquisition University. Retrieved August 7, 2012.
  3. ^ "Scheduling Guide for Program Managers" (PDF). Defense Systems Management College Press, Fort Belvoir, VA. October 2001. Retrieved January 19, 2016.
  4. ^ "City of Riverside, Wastewater Integrated Master Plan".
  5. ^ "Integrated Master Plan for Lahore 2021" (PDF).[permanent dead link]
  6. ^ "Draft Preliminary Plan - Integrated Natural Resources Management Plan and Master Plan - Coyote Creek Parkway County Park". 2006. from the original on February 25, 2024.
  7. ^ (PDF). United States Department of Defense. October 31, 2005. Archived from the original (PDF) on August 20, 2018. Retrieved August 7, 2012.
  8. ^ Bachman, David C. (October 2011). (PDF). Defense Acquisition Research Journal. Defense Acquisition University. pp. 406–427. Archived from the original (PDF) on September 5, 2012. Retrieved August 7, 2012.
  9. ^ "SMC-S-019, Rev. A" (PDF). EverySpec. Space and Missile Systems Center, Air Force Space Command, El Segundo, CA. August 11, 2008. (PDF) from the original on March 3, 2016. Retrieved August 7, 2012.
  10. ^ . Mitre Corporation. May 8, 2012. Archived from the original on August 19, 2012. Retrieved August 7, 2012.
  11. ^ "Planning & Scheduling Excellence Guide (PASEG), Version 3.0". Humphreys & Associates. March 9, 2016. from the original on November 18, 2017. Retrieved November 17, 2017.
  12. ^ "Department of Defense Standard: Work Breakdown Structures (WBS) for Defense Material Items (Superseding MIL-HDBK-881A)" (PDF). United States Department of Defense. October 3, 2011. Retrieved August 7, 2012.[permanent dead link]
  13. ^ "DI-MISC-81183A, Data Item Description: Integrated Master Schedule (IMS)" (PDF). EverySpec. United States Department of Defense. February 9, 1996. Retrieved August 7, 2012.
  14. ^ "DI-MGMT-81650, Data Item Description: Integrated Master Schedule (IMS)" (PDF). EverySpec. United States Department of Defense. March 30, 2005. Retrieved August 7, 2012.
  15. ^ "DI-MISC-81334D, Data Item Description: Contract Work Breakdown Structure" (PDF). United States Department of Defense. May 18, 2011. Retrieved August 7, 2012.[permanent dead link]
  16. ^ "DI-MISC-81466A, Data Item Description: Cost Performance Report (CPR)" (PDF). EverySpec. United States Department of Defense. March 30, 2005. Retrieved August 7, 2012.

integrated, master, plan, united, states, department, defense, integrated, master, plan, integrated, master, schedule, important, program, management, tools, that, provide, significant, assistance, planning, scheduling, work, efforts, large, complex, materiel,. In the United States Department of Defense the Integrated Master Plan IMP and the Integrated Master Schedule IMS are important program management tools that provide significant assistance in the planning and scheduling of work efforts in large and complex materiel acquisitions 1 The IMP is an event driven plan that documents the significant accomplishments necessary to complete the work and ties each accomplishment to a key program event 2 The IMP is expanded to a time based IMS to produce a networked and multi layered schedule showing all detailed tasks required to accomplish the work effort contained in the IMP The IMS flows directly from the IMP and supplements it with additional levels of detail both then form the foundations to implement an Earned Value Management System The IMP is a bilateral agreement between the Government and a contractor on what defines the event driven program The IMP documents the key events accomplishments and the evaluation criteria in the development production and or modification of a military system moreover the IMS provides sequential events and key decision points generally meetings to assess program progress Usually the IMP is a contractual document Supporting the IMP is the IMS that is made up of tasks depicting the work effort needed to complete the criteria 3 It is a detailed time driven plan for program execution that helps to ensure on time delivery dates are achieved and that tracking and status tool are used during program execution These tools must show progress interrelationships and dependencies This example of an IMP shows a table of events accomplishments and criteria without a listing of the IMP narratives The intent is to illustrate the hierarchical structure and relationship of events accomplishments criteria and tasks In civic planning or urban planning Integrated Master Plan is used at the levels of city 4 development 5 county 6 and state or province to refer to a document integrating diverse aspects of a public works project Contents 1 Purpose and Objectives 2 Rationale 3 Attributes and Characteristics 4 Requirements Flowdown 5 Evaluation of an IMS 6 Relationship to other Documents 7 Reporting Formats 8 ReferencesPurpose and Objectives editThe primary purpose of the IMP and the supporting detailed schedules of the IMS is their use by the U S Government and Contractor acquisition team as the day to day tools for the planning executing and tracking program technical schedule and cost status including risk mitigation efforts 7 The IMP provides a better structure than either the Work Breakdown Structure WBS or Organizational Breakdown Structure OBS for measuring actual integrated master schedule IMS progress 8 The primary objective of the IMP is a single plan that establishes the program or project fundamentals It provides a hierarchical event based plan that contains Events Significant accomplishments Entry and exit criteria however it does not include any dates or durations Using the IMP provides sufficient definition for explain program process and completion tracking as well as providing effective communication of the program project content and the What and How of the program Rationale editThe IMP is a collection of milestones called events that form the process architecture of the program This means the sequence of events must always result in a deliverable product or service While delivering products or services is relatively straight forward in some instances i e list the tasks to be done arrange them in the proper sequence and execute to this plan in other cases problems often arise i the description of complete is often missing for intermediate activities ii program partners integration activities and subcontractors all have unknown or possibly unknowable impacts on the program and iii as products or services are delivered the maturity of the program changes e g quality and functionality expectations as well as other attributes this maturity provided by defining complete serves as an insurance policy against future problems encountered later in the program Often it s easier to define the IMP by stating what it is not The IMP is NOT BASED on calendar dates and therefore it is not schedule oriented each event is completed when its supporting accomplishments are completed and this completion is evidenced by the satisfaction of the criteria supporting each of the accomplishments Furthermore many of the IMP events are fixed by customer defined milestones e g Preliminary or Critical Design Review Production Deliver etc while intermediate events are defined by the Supplier e g integration and test software build releases Test Readiness Review etc The critical IMP attribute is its focus on events when compared to effort or task focused planning The event focus asks and answers the question what does done look like rather than what work has been done Certainly work must be done to complete a task but a focus solely on the work hides the more important metric of are we meeting our commitments While meeting commitments is critical it s important to first define the criteria used for judging if the commitments are being met This is where Significant Accomplishments SA and their Accomplishment Criteria AC become important It is important to meet commitments but recognizing when the commitment has been met is even more important Attributes and Characteristics editThe IMP provides Program Traceability by expanding and complying with the program s Statement of Objectives SOO Technical Performance Requirements TPRs the Contract Work Breakdown Structure CWBS and the Contract Statement of Work CSOW all of which are based on the Customer s WBS to form the basis of the IMS and all cost reporting The IMP implements a measurable and trackable program structure to accomplish integrated product development integrate the functional program activities and incorporates functional lower level and subcontractor IMPs The IMP provides a framework for independent evaluation of Program Maturity by allowing insight into the overall effort with a level of detail that is consistent with levied risk and complexity metrics It uses the methodology of decomposing events into a logical series of accomplishments having measurable criteria to demonstrate the completion and or quality of accomplishments Requirements Flowdown editA Government customer tasks a Supplier to prepare and implement an IMP that linked with the IMS and integrated with the EVMS The IMP list the contract requirements documents e g Systems Requirements Document and Technical Requirements Document i e the system specification or similar document as well as the IMP events corresponding to development and or production activities required by the contract The IMP should include significant accomplishments encompassing all steps necessary to satisfy all contract objectives and requirements manage all significant risks and facilitate Government insight for each event Significant accomplishments shall be networked to show their logical relationships and that they flow logically from one to another The IMP IMS and EVMS products will usually include the prime contractor subcontractor and major vendor activities and products 9 Evaluation of an IMS editWhen evaluating a proposed IMS the user should focus on realistic task durations predecessor successor relationships and identification of critical path tasks with viable risk mitigation and contingency plans An IMS summarized at too high a level may result in obscuring critical execution elements and contributing to failure of the EVMS to report progress A high level IMS may fail to show related risk management approaches being used which can result in long duration tasks and artificial linkages masking the true critical path In general the IMP is a top down planning tool and the IMS as the bottom up execution tool The IMS is a scheduling tool for management control of program progression not for cost collection purposes 10 An IMS would seek general consistency and a standardized approach to project planning scheduling and analysis It may use guides such as the PASEG Generally Accepted Schedule Principles GASP as guidance to improve execution and enable EVMS 11 Relationship to other Documents editThe IMP IMS are related to the product based Work Breakdown Structure WBS as defined in MIL STD 881 by giving a second type of view on the effort for different audiences or to provide a combination which gives better overall understanding 12 Linkage between the IMP IMS and WBS is done by referencing the WBS numbering whenever the PE Program Event SA Significant Accomplishment or AC Accomplishment Criteria involves a deliverable product Reporting Formats editThe IMP is often called out as a contract data deliverable on United States Department of Defense materiel acquisitions as well as other U S Government procurements Formats for these deliverables are covered in Data Item Descriptions DIDs that define the data content format and data usages Recently the DoD cancelled the DID DI MISC 81183A that jointly addressed both the IMP and the IMS 13 The replacement documents include DI MGMT 81650 Integrated Master Schedule DI MGMT 81334A Contract Work Breakdown Structure and DI MGMT 81466 Contract Performance Report 14 15 16 In addition DFARS 252 242 7001 and 252 242 7002 provide guidance for integrating IMP IMS with Earned Value Management References edit AFMC Pamphlet 63 5 Integrated Master Plan and Schedule Guide PDF United States Air Force November 11 2004 Retrieved August 7 2012 Integrated Master Plan IMP Integrated Master Schedule IMS Defense Acquisition University Retrieved August 7 2012 Scheduling Guide for Program Managers PDF Defense Systems Management College Press Fort Belvoir VA October 2001 Retrieved January 19 2016 City of Riverside Wastewater Integrated Master Plan Integrated Master Plan for Lahore 2021 PDF permanent dead link Draft Preliminary Plan Integrated Natural Resources Management Plan and Master Plan Coyote Creek Parkway County Park 2006 Archived from the original on February 25 2024 Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide Version 0 9 PDF United States Department of Defense October 31 2005 Archived from the original PDF on August 20 2018 Retrieved August 7 2012 Bachman David C October 2011 Better Schedule Performance Assessments Derived From Integrated Master Plan Referenced Schedule Metrics PDF Defense Acquisition Research Journal Defense Acquisition University pp 406 427 Archived from the original PDF on September 5 2012 Retrieved August 7 2012 SMC S 019 Rev A PDF EverySpec Space and Missile Systems Center Air Force Space Command El Segundo CA August 11 2008 Archived PDF from the original on March 3 2016 Retrieved August 7 2012 Systems Engineering Guide Integrated Master Schedule IMS Integrated Master Plan IMP Application Mitre Corporation May 8 2012 Archived from the original on August 19 2012 Retrieved August 7 2012 Planning amp Scheduling Excellence Guide PASEG Version 3 0 Humphreys amp Associates March 9 2016 Archived from the original on November 18 2017 Retrieved November 17 2017 Department of Defense Standard Work Breakdown Structures WBS for Defense Material Items Superseding MIL HDBK 881A PDF United States Department of Defense October 3 2011 Retrieved August 7 2012 permanent dead link DI MISC 81183A Data Item Description Integrated Master Schedule IMS PDF EverySpec United States Department of Defense February 9 1996 Retrieved August 7 2012 DI MGMT 81650 Data Item Description Integrated Master Schedule IMS PDF EverySpec United States Department of Defense March 30 2005 Retrieved August 7 2012 DI MISC 81334D Data Item Description Contract Work Breakdown Structure PDF United States Department of Defense May 18 2011 Retrieved August 7 2012 permanent dead link DI MISC 81466A Data Item Description Cost Performance Report CPR PDF EverySpec United States Department of Defense March 30 2005 Retrieved August 7 2012 Retrieved from https en wikipedia org w index php title Integrated master plan amp oldid 1210303017, wikipedia, wiki, book, books, library,