fbpx
Wikipedia

Gabčíkovo–Nagymaros Dams

The Gabčíkovo–Nagymaros Dams (more precisely Gabčíkovo–Nagymaros Waterworks, Hungarian: Bős–nagymarosi vízlépcső, Slovak: Sústava vodných diel Gabčíkovo – Nagymaros) is a large barrage project on the Danube. It was initiated by the Budapest Treaty of 16 September 1977 between the Czechoslovak Socialist Republic and the Hungarian People's Republic. The project aimed at preventing catastrophic floods, improving river navigability and producing clean electricity.

Gabčíkovo–Nagymaros Dams
Gabčíkovo: Aerial view

Only a part of the project has been finished in Slovakia, under the name Gabčíkovo Dam, because Hungary first suspended, then tried to terminate, the project due to environmental and economic concerns.[1] Slovakia proceeded with an alternative solution, called "Variant C", which involved diverting the Danube, the border river. These caused a still unresolved international dispute between Slovakia and Hungary. Both parties turned to the International Court of Justice for a ruling.

Budapest Treaty edit

The joint Hungarian–Czechoslovak project was agreed upon on 16 September 1977 in the "Budapest Treaty". The treaty envisioned a cross-border barrage system between the towns of Gabčíkovo, Czechoslovak Socialist Republic (now Slovak Republic) and Nagymaros, People's Republic of Hungary (now Hungary). The dams would eliminate regular flooding (like the disastrous ones of 1954 and 1965) and provide a clean source of electric power. They would also allow year-long navigability of the river and serve as a part of the Rhine-Main-Danube Canal system of inland navigation.

The plan was to divert part of the river into an artificial canal at Dunakiliti (a village in Hungary) to the hydroelectric power plant near Gabčíkovo (eight turbines, 720 MW). The canal would return the water into a deepened original riverbed and at Nagymaros a smaller dam and power-plant (158 MW) would be constructed. The plant in Gabčíkovo was to be a peak-power plant and the dam in Nagymaros, about 100 km downstream, was to limit fluctuations of the water level.

Because most of the construction was planned to occur in Slovak territory, the Hungarian government was obligated to participate in some construction in Slovakia, to ensure equal investment by both sides. Electricity produced was to be shared equally between the two countries.

An important provision of the treaty was its Article 15.1, which stated: "the Contracting Parties shall ensure, by the means specified in the joint contractual plan, that the quality of the water in the Danube is not impaired as a result of the construction and operation of the System of Locks".[2]

Limited project edit

In 1981 the two countries agreed to slow down the project because of their economic problems.[3][unreliable source?] In 1984 a movement protesting against the dam, the "Danube Circle" (Duna Kör), was founded in Hungary, which was later awarded the Right Livelihood Award[4] and the Goldman Environmental Prize[5] for protecting the Danube. The group objected to the withholding of information on the project from the public by the Communist government to avoid debate on its environmental impact. Biologists worried that the dams would damage both the treasured scenery of the Danube Bend and the underground water reserves on which more than a million Hungarians depend,[6] especially around Budapest. After an intensive campaign the project became widely hated in Hungary as a symbol of the old regime. In Slovakia, construction continued and many people were involved in building the hydro-electric plant. The Hungarian government eventually decided to suspend work until the environmental effects of the project were fully assessed.[7] Soon after, the Slovak authorities decided to unilaterally proceed with an alternative solution, called "Variant C".[7] This effectively diverted the Danube into Slovak territory and kept the development entirely within its borders.[7] This scheme dramatically reduced the amount of water flowing into Hungary and had a significant impact on that nation's water supply and environment.[7] As a result, the Hungarian government attempted to terminate the 1977 Treaty.

The 7 proposals originally put forward by experts from Czechoslovakia in 1992 were as follows.

Proposal Description Comment
A Complete the original plans from 1977 together with Hungary. Slovak preference
B Complete only the Czechoslovak part of the waterworks.
C Reduce the reservoir, build the waterworks only on the territory of the Slovak Republic and postpone construction at Nagymaros in Hungary. Split the shared reservoir into two with a dam and instead of the dam in Dunakiliti build a dam in Čunovo. This variant is called temporal, as it is technically possible to build the Dunakiliti dam and flood the Čunovo dam in order to finish the waterworks according to the 1977 treaty. winning project
D Complete only the upper part of the dam and finish the Dunakiliti dam.
E Use the waterworks only for flood prevention and ensure navigability.
F Stop construction and retain the site in its current state.
G Remove all buildings and return the river to its original state. Hungarian preference

In the end it was decided to switch to an alternative solution on a smaller scale, Proposal C. The artificial canal would start at Čunovo, part of the Slovak capital city Bratislava, and the Gabčíkovo power plant would operate in run-of-the-river mode with no water level fluctuation. Construction started in November 1991. In October 1992 diversion of part of the water into the canal started and the Čunovo reservoir was filled; the secondary structures (such as the power-plant) were finished and made operational in 1996.

Parts of the waterworks edit

Built parts edit

 
Hydroelectric power station at Gabčíkovo Dam
  • Supply channel for Čunovo Dam conveys water from Bratislava about 10 km to Čunovo.
  • Čunovo Dam is the first level of the Waterworks, producing 24 MW of electricity, and there is an additional smaller power plant with 1 MW power output. Čunovo includes also the Čunovo Water Sports Centre, a site of world championships in water slalom and rafting.
  • Hrušov reservoir (replacing the joint Slovak-Hungarian Dunakiliti reservoir) accumulates water for the main power plant in Gabčíkovo and also regulates water level. It is 16 km long and from 1 to 4 km wide. Its capacity is 196 million cubic metres. As part of the Proposal C redesign, the reservoir was reduced in size and separated from Hungarian territory by a 10.5 km long embankment.
  • Gabčíkovo Dam is the main part of the waterworks. It consists of two main structures: a hydropower plant and two lock chambers. This level of the waterworks was designed to use differential water level to produce electricity, to allow ships to pass safely through locks and to divert flood water. The chambers are on the left bank of the Danube and the difference in water levels is about 20 metres. The power plant on the right riverbank was designed to produce 2650 GWh annually. A 10 m wide road bridge passes over the complex. Operation of the power plant is fully automated. In 2012, after 20 years of service, 300.000 ships have passed through the locks with totally 5.000.000 passengers.[8]
  • Outlet channel leads water back to the old riverbed and also helps against floods. The channel is 185 m wide at the bottom and 8.2 km long and re-enters the Danube at Sap.
  • Regulations in the old Danube riverbed.[9]

Nagymaros edit

The waterworks on the Danube were designed to have an additional level at Nagymaros, consisting of a reservoir 95 km long and the Nagymaros power plant. This level was to be located between the Hungarian towns of Visegrád and Nagymaros and its purpose was to use the gradient of the reservoir for production of electricity and also to allow ships to pass. The Gabčíkovo works were designed for control and peak running of the power plant, and the Nagymaros works as an equalising power plant to provide better conditions for shipping and to regulate peak outflow from Gabčíkovo. Because the Nagymaros works were not built, the Gabčíkovo power plant cannot work at peak efficiency, which causes appreciable economic damage.[citation needed] Non-existence of Nagymaros dam also causes main obstacle of inland navigation on the 2400 km Danube Pan-European corridor due to low levels of water. Hungary requests Slovakia to manage regulation works on problematic stretch of Danube that were supposed to be solved by Nagymaros backwater. Transportation damages include also missing upgrade of river Váh waterway in Slovakia.[9]

Lawsuit edit

After Czechoslovakia split up in 1993, the newly established Slovak Republic carried on with the project. In 1989 Hungary abandoned the site when scientists on both sides of the border expressed fears about the environmental consequences.[10] After Hungary tried to terminate the 1977 treaty in May 1992, both[6] parties (Hungary and Slovakia) agreed to take their dispute to the International Court of Justice in The Hague. In 1994, the Socialists came back into power in Hungary but could hardly back out of the court case, which was hailed as a landmark: for the first time, the court would rule over an environmental dispute. Hearings on the case were held between 3 March and 15 April 1997, and the Court paid a site visit (the first ever in its history). Besides other issues, the Hungarian representatives wanted the court to decide whether or not Czechoslovakia was entitled to embark on Proposal C, and to rule that the 1977 treaty was not binding on Slovakia and Hungary. The court handed down a decision in 1997:

  • The Court found that Hungary had breached their legal obligations in almost all points. It ordered Hungary to finish the Nagymaros part of waterworks. Per the Court decision, Czechoslovakia and later Slovakia was entitled to build alternative workaround after Hungary stopped work, but Slovakia breached on one point - it should not have started to operate an alternative temporary solution before the court handed down its ruling. It called on both States to negotiate in good faith to complete the objectives of the 1977 Budapest Treaty, which the Court declared was still in force, while taking account of the factual situation that had developed since 1989.[11]
  • Each Party must compensate the other Party for the damage caused by its conduct.[12][13]

Another four months of negotiations between Slovakia and Hungary led to a treaty between the two countries about the ICJ judgment. In March 1998 the government of Slovakia approved this treaty, but the government of Hungary, which was supposed to build Nagymaros or a Pilismarót waterworks, delayed approving the treaty and proclaimed a competition for the project. After elections in Hungary, the new government cancelled this competition.[13] In 1998, after two appeals to Hungary, the Slovak government turned to the International Court, demanding the Nagymaros part be built.

The international dispute was not resolved for more than a decade.[14] In June 2017, the Slovak Government requested that the International Court of Justice "place on record the discontinuance of the proceedings". In a letter dated 12 July 2017, the Agent of Hungary stated that his Government "did not oppose the discontinuance of the proceedings instituted by means of the Request of Slovakia of 3 September 1998 for an additional judgment".[15]

Technical parameters edit

 
Control tower of the Gabčíkovo Dam
 
Gabčíkovo sluice
  • The area of the Čunovo reservoir is 40 km2, exclusively on the Slovak side (the original Hrušov-Dunakiliti reservoir was to be 60 km2). The operational water level is 131.1 metres above sea level (minimal and maximum levels are 129 and 131.5 m respectively).
  • The power station has eight vertical Kaplan turbines with runners 9.3 m in diameter and a maximum capacity of 90 MW each. Total capacity is 720 MW at operational discharge of 4000 m3/s. Water level differences are 24 and 12.88 m.
  • The original river bed has a discharge of between 250 and 600 m3/s.
  • Two navigation locks were built. A bypass canal will handle floods.
  • In 1996, Europe's largest artificial whitewater slalom course, the Water Sports Centre Čunovo, was built on a river island at the head of the bypass canal. When operating at capacity, it diverts 22 m3/s into the bypass canal.
  • The Gabčíkovo Hydroelectric Power Station produces 2600 GWh of electricity annually, making it the largest hydroelectric plant in Slovakia. It supplies around 8% of the country's electricity consumption.

Environmental consequences edit

Regarding the environmental consequences of the dam, results of a 1996–2002 study by K. Holubová, Z. Capeková and J. Szolgay[16] were:

  • Intensive degradation of the Danube River bed downstream (especially at the Old Danube river bed) caused by the absence of the Nagymaros waterworks.[16]
  • Decreased water level,[16]
  • Increased sediment supply,[16]
  • Increased amounts of bedload and higher intensity of bedload movements,[16]
  • Reduced flood capacity,[16]
  • Decreased channel stability,[16]

Annual joint studies of the Slovak-Hungarian governments claim:

  • Stabilization of groundwater levels, local improvement of groundwater quality,[17][18][19]
  • Stabilization of the riverbed of the old Danube.[18][19][20]
  • Improved living conditions of aquatic animals and forest animals in areas around old Danube.[20][verification needed]

Differences between 2002 study and newer works may be attributed to size of studied area. As 1996–2002 study was done on area from Vienna to end of Slovak-Hungarian Danube. Government studies are targeting only Gabčíkovo waterworks and immediate area around it.

Groundwater levels are dependent on big floods, like in 2002, which removed fine silt from river bottom and allowed increased filtration. After that groundwater levels on many places reached pre-reservoir filling levels, on some places reached even higher.[21] Damming of the Danube improved ground water quality at Rusovce and Čuňovo water supply[22] which are on right side of Danube. It was due changed infiltration conditions and changed groundwater flow direction from NW-SE to N-S.[23] The ground water quality at water supplies situated on the left side of the Danube were not influenced to the same extent as on the right side.

One of the same problems identified is increased sedimentation upstream and riverbed erosion downstream from reservoir, which is a typical problem of water reservoirs.

See also edit

References edit

  1. ^ Aaron Schwabach, Diverting the Danube: The Gabcikovo-Nagymaros Dispute and International Freshwater Law, 1996, p. 7
  2. ^ P. K. Rao: International Environmental Law and Economics, Blackwell Publishers Ltd., 2002, page 230 [1]
  3. ^ "A bős-nagymarosi vízlépcsőrendszer és a hágai per története". www.szigetkoz.biz.
  4. ^ . Right Livelihood Award. Archived from the original on 30 November 2010. Retrieved 21 February 2011.
  5. ^ . Goldman Environmental Prize. Archived from the original on 23 November 2010. Retrieved 8 January 2011.
  6. ^ a b "New Scientist". New Science Publications. 3 February 1994 – via Google Books.
  7. ^ a b c d Owen McIntyre: Gabčíkovo – Nagymaros Project: A Test Case for International Water Law?, In: Anton Earle, Anders Jagerskog and Joakim Öjendal (editors): Transboundary Water Management: Principles and Practice, Stockholm International Water Institute, 2010, page 228 [2]
  8. ^ "Cez Gabčíkovo sa preplavilo viac ako päť miliónov ľudí". TERAZ.sk. 4 November 2012.
  9. ^ a b "SVD Gabčíkovo – Nagymaros | Vodohospodárska výstavba, š.p." www.vvb.sk.
  10. ^ "New Scientist". New Scientist. 143 (73–74): 28. 1994.
  11. ^ Report of the International Court of Justice, 1 August 2005 – 31 July 2006 (Report). United Nations Publications. 2006. p. 25.[permanent dead link]
  12. ^ Summaries of Judgments, Advisory Opinions and Orders of the International Court of Justice: 1972–2002 (Report). United Nations International Court of Justice.[permanent dead link]
  13. ^ a b . gabcikovo.gov.sk. Archived from the original on 21 October 2013.
  14. ^ . The Slovak Spectator. 4 January 2006. Archived from the original on 27 September 2007. Retrieved 23 February 2008.
  15. ^ (PDF). International Court of Justice. Archived from the original (PDF) on 27 January 2018. Retrieved 13 December 2018.
  16. ^ a b c d e f g Massimo Greco, Armando Carravetta, Renata Della Morte, River Flow 2004, Volume 1, Taylor & Francis, 2004, pp. 138–141
  17. ^ . Archived from the original on 17 May 2009. Retrieved 30 March 2009.
  18. ^ a b . Archived from the original on 8 October 2009. Retrieved 4 June 2013.
  19. ^ a b . www.vvb.sk. Archived from the original on 17 March 2016. Retrieved 4 November 2012.
  20. ^ a b Joint annual report on the environment monitoring in 2010
  21. ^ (PDF). Archived from the original (PDF) on 29 September 2021. Retrieved 3 February 2021.
  22. ^ Slovak – Hungarian Environmental Monitoring on the Danube, 2006
  23. ^ Ground water regime monitoring, page 5[permanent dead link]

Sources edit

  • Chmelár, V.: Dunaj energetický, vyd. Electra Žilina, 1992

External links edit

  • Treaty between the Hungarian People´s Republic and the Czechoslovak Socialist Republic concerning the construction and operation of the Gabčíkovo – Nagymaros system of locks 4 November 2007 at the Wayback Machine
  • Documents about the Gabčíkovo dam and its impact ()
  • Details of the conflict over the project 14 September 2006 at the Wayback Machine (PDF)
  • Bibliography on Water Resources and International Law, Peace Palace Library
  • Annual reports on environmental monitoring 17 May 2009 at the Wayback Machine
  • Gabčíkovo Dam Virtual Tour
  • Historie Soustavy vodních děl Gabčíkovo-Nagymaros
  • Gabčíkovo: patálie bez konce

47°52′48″N 17°32′21″E / 47.88000°N 17.53917°E / 47.88000; 17.53917

gabčíkovo, nagymaros, dams, gabčíkovo, reservoir, particular, gabčíkovo, neutrality, this, article, disputed, relevant, discussion, found, talk, page, please, remove, this, message, until, conditions, january, 2020, learn, when, remove, this, message, more, pr. For Gabcikovo Dam and reservoir in particular see Gabcikovo Dam The neutrality of this article is disputed Relevant discussion may be found on the talk page Please do not remove this message until conditions to do so are met January 2020 Learn how and when to remove this message The Gabcikovo Nagymaros Dams more precisely Gabcikovo Nagymaros Waterworks Hungarian Bos nagymarosi vizlepcso Slovak Sustava vodnych diel Gabcikovo Nagymaros is a large barrage project on the Danube It was initiated by the Budapest Treaty of 16 September 1977 between the Czechoslovak Socialist Republic and the Hungarian People s Republic The project aimed at preventing catastrophic floods improving river navigability and producing clean electricity Gabcikovo Nagymaros Dams Gabcikovo Aerial view Only a part of the project has been finished in Slovakia under the name Gabcikovo Dam because Hungary first suspended then tried to terminate the project due to environmental and economic concerns 1 Slovakia proceeded with an alternative solution called Variant C which involved diverting the Danube the border river These caused a still unresolved international dispute between Slovakia and Hungary Both parties turned to the International Court of Justice for a ruling Contents 1 Budapest Treaty 2 Limited project 3 Parts of the waterworks 3 1 Built parts 3 2 Nagymaros 4 Lawsuit 5 Technical parameters 6 Environmental consequences 7 See also 8 References 9 Sources 10 External linksBudapest Treaty editThe joint Hungarian Czechoslovak project was agreed upon on 16 September 1977 in the Budapest Treaty The treaty envisioned a cross border barrage system between the towns of Gabcikovo Czechoslovak Socialist Republic now Slovak Republic and Nagymaros People s Republic of Hungary now Hungary The dams would eliminate regular flooding like the disastrous ones of 1954 and 1965 and provide a clean source of electric power They would also allow year long navigability of the river and serve as a part of the Rhine Main Danube Canal system of inland navigation The plan was to divert part of the river into an artificial canal at Dunakiliti a village in Hungary to the hydroelectric power plant near Gabcikovo eight turbines 720 MW The canal would return the water into a deepened original riverbed and at Nagymaros a smaller dam and power plant 158 MW would be constructed The plant in Gabcikovo was to be a peak power plant and the dam in Nagymaros about 100 km downstream was to limit fluctuations of the water level Because most of the construction was planned to occur in Slovak territory the Hungarian government was obligated to participate in some construction in Slovakia to ensure equal investment by both sides Electricity produced was to be shared equally between the two countries An important provision of the treaty was its Article 15 1 which stated the Contracting Parties shall ensure by the means specified in the joint contractual plan that the quality of the water in the Danube is not impaired as a result of the construction and operation of the System of Locks 2 Limited project editIn 1981 the two countries agreed to slow down the project because of their economic problems 3 unreliable source In 1984 a movement protesting against the dam the Danube Circle Duna Kor was founded in Hungary which was later awarded the Right Livelihood Award 4 and the Goldman Environmental Prize 5 for protecting the Danube The group objected to the withholding of information on the project from the public by the Communist government to avoid debate on its environmental impact Biologists worried that the dams would damage both the treasured scenery of the Danube Bend and the underground water reserves on which more than a million Hungarians depend 6 especially around Budapest After an intensive campaign the project became widely hated in Hungary as a symbol of the old regime In Slovakia construction continued and many people were involved in building the hydro electric plant The Hungarian government eventually decided to suspend work until the environmental effects of the project were fully assessed 7 Soon after the Slovak authorities decided to unilaterally proceed with an alternative solution called Variant C 7 This effectively diverted the Danube into Slovak territory and kept the development entirely within its borders 7 This scheme dramatically reduced the amount of water flowing into Hungary and had a significant impact on that nation s water supply and environment 7 As a result the Hungarian government attempted to terminate the 1977 Treaty The 7 proposals originally put forward by experts from Czechoslovakia in 1992 were as follows Proposal Description Comment A Complete the original plans from 1977 together with Hungary Slovak preference B Complete only the Czechoslovak part of the waterworks C Reduce the reservoir build the waterworks only on the territory of the Slovak Republic and postpone construction at Nagymaros in Hungary Split the shared reservoir into two with a dam and instead of the dam in Dunakiliti build a dam in Cunovo This variant is called temporal as it is technically possible to build the Dunakiliti dam and flood the Cunovo dam in order to finish the waterworks according to the 1977 treaty winning project D Complete only the upper part of the dam and finish the Dunakiliti dam E Use the waterworks only for flood prevention and ensure navigability F Stop construction and retain the site in its current state G Remove all buildings and return the river to its original state Hungarian preference In the end it was decided to switch to an alternative solution on a smaller scale Proposal C The artificial canal would start at Cunovo part of the Slovak capital city Bratislava and the Gabcikovo power plant would operate in run of the river mode with no water level fluctuation Construction started in November 1991 In October 1992 diversion of part of the water into the canal started and the Cunovo reservoir was filled the secondary structures such as the power plant were finished and made operational in 1996 Parts of the waterworks editBuilt parts edit nbsp Hydroelectric power station at Gabcikovo Dam Supply channel for Cunovo Dam conveys water from Bratislava about 10 km to Cunovo Cunovo Dam is the first level of the Waterworks producing 24 MW of electricity and there is an additional smaller power plant with 1 MW power output Cunovo includes also the Cunovo Water Sports Centre a site of world championships in water slalom and rafting Hrusov reservoir replacing the joint Slovak Hungarian Dunakiliti reservoir accumulates water for the main power plant in Gabcikovo and also regulates water level It is 16 km long and from 1 to 4 km wide Its capacity is 196 million cubic metres As part of the Proposal C redesign the reservoir was reduced in size and separated from Hungarian territory by a 10 5 km long embankment Gabcikovo Dam is the main part of the waterworks It consists of two main structures a hydropower plant and two lock chambers This level of the waterworks was designed to use differential water level to produce electricity to allow ships to pass safely through locks and to divert flood water The chambers are on the left bank of the Danube and the difference in water levels is about 20 metres The power plant on the right riverbank was designed to produce 2650 GWh annually A 10 m wide road bridge passes over the complex Operation of the power plant is fully automated In 2012 after 20 years of service 300 000 ships have passed through the locks with totally 5 000 000 passengers 8 Outlet channel leads water back to the old riverbed and also helps against floods The channel is 185 m wide at the bottom and 8 2 km long and re enters the Danube at Sap Regulations in the old Danube riverbed 9 Nagymaros edit The waterworks on the Danube were designed to have an additional level at Nagymaros consisting of a reservoir 95 km long and the Nagymaros power plant This level was to be located between the Hungarian towns of Visegrad and Nagymaros and its purpose was to use the gradient of the reservoir for production of electricity and also to allow ships to pass The Gabcikovo works were designed for control and peak running of the power plant and the Nagymaros works as an equalising power plant to provide better conditions for shipping and to regulate peak outflow from Gabcikovo Because the Nagymaros works were not built the Gabcikovo power plant cannot work at peak efficiency which causes appreciable economic damage citation needed Non existence of Nagymaros dam also causes main obstacle of inland navigation on the 2400 km Danube Pan European corridor due to low levels of water Hungary requests Slovakia to manage regulation works on problematic stretch of Danube that were supposed to be solved by Nagymaros backwater Transportation damages include also missing upgrade of river Vah waterway in Slovakia 9 Lawsuit editAfter Czechoslovakia split up in 1993 the newly established Slovak Republic carried on with the project In 1989 Hungary abandoned the site when scientists on both sides of the border expressed fears about the environmental consequences 10 After Hungary tried to terminate the 1977 treaty in May 1992 both 6 parties Hungary and Slovakia agreed to take their dispute to the International Court of Justice in The Hague In 1994 the Socialists came back into power in Hungary but could hardly back out of the court case which was hailed as a landmark for the first time the court would rule over an environmental dispute Hearings on the case were held between 3 March and 15 April 1997 and the Court paid a site visit the first ever in its history Besides other issues the Hungarian representatives wanted the court to decide whether or not Czechoslovakia was entitled to embark on Proposal C and to rule that the 1977 treaty was not binding on Slovakia and Hungary The court handed down a decision in 1997 The Court found that Hungary had breached their legal obligations in almost all points It ordered Hungary to finish the Nagymaros part of waterworks Per the Court decision Czechoslovakia and later Slovakia was entitled to build alternative workaround after Hungary stopped work but Slovakia breached on one point it should not have started to operate an alternative temporary solution before the court handed down its ruling It called on both States to negotiate in good faith to complete the objectives of the 1977 Budapest Treaty which the Court declared was still in force while taking account of the factual situation that had developed since 1989 11 Each Party must compensate the other Party for the damage caused by its conduct 12 13 Another four months of negotiations between Slovakia and Hungary led to a treaty between the two countries about the ICJ judgment In March 1998 the government of Slovakia approved this treaty but the government of Hungary which was supposed to build Nagymaros or a Pilismarot waterworks delayed approving the treaty and proclaimed a competition for the project After elections in Hungary the new government cancelled this competition 13 In 1998 after two appeals to Hungary the Slovak government turned to the International Court demanding the Nagymaros part be built The international dispute was not resolved for more than a decade 14 In June 2017 the Slovak Government requested that the International Court of Justice place on record the discontinuance of the proceedings In a letter dated 12 July 2017 the Agent of Hungary stated that his Government did not oppose the discontinuance of the proceedings instituted by means of the Request of Slovakia of 3 September 1998 for an additional judgment 15 Technical parameters edit nbsp Control tower of the Gabcikovo Dam This section does not cite any sources Please help improve this section by adding citations to reliable sources Unsourced material may be challenged and removed November 2012 Learn how and when to remove this message nbsp Gabcikovo sluice The area of the Cunovo reservoir is 40 km2 exclusively on the Slovak side the original Hrusov Dunakiliti reservoir was to be 60 km2 The operational water level is 131 1 metres above sea level minimal and maximum levels are 129 and 131 5 m respectively The power station has eight vertical Kaplan turbines with runners 9 3 m in diameter and a maximum capacity of 90 MW each Total capacity is 720 MW at operational discharge of 4000 m3 s Water level differences are 24 and 12 88 m The original river bed has a discharge of between 250 and 600 m3 s Two navigation locks were built A bypass canal will handle floods In 1996 Europe s largest artificial whitewater slalom course the Water Sports Centre Cunovo was built on a river island at the head of the bypass canal When operating at capacity it diverts 22 m3 s into the bypass canal The Gabcikovo Hydroelectric Power Station produces 2600 GWh of electricity annually making it the largest hydroelectric plant in Slovakia It supplies around 8 of the country s electricity consumption Environmental consequences editRegarding the environmental consequences of the dam results of a 1996 2002 study by K Holubova Z Capekova and J Szolgay 16 were Intensive degradation of the Danube River bed downstream especially at the Old Danube river bed caused by the absence of the Nagymaros waterworks 16 Decreased water level 16 Increased sediment supply 16 Increased amounts of bedload and higher intensity of bedload movements 16 Reduced flood capacity 16 Decreased channel stability 16 Annual joint studies of the Slovak Hungarian governments claim Stabilization of groundwater levels local improvement of groundwater quality 17 18 19 Stabilization of the riverbed of the old Danube 18 19 20 Improved living conditions of aquatic animals and forest animals in areas around old Danube 20 verification needed Differences between 2002 study and newer works may be attributed to size of studied area As 1996 2002 study was done on area from Vienna to end of Slovak Hungarian Danube Government studies are targeting only Gabcikovo waterworks and immediate area around it Groundwater levels are dependent on big floods like in 2002 which removed fine silt from river bottom and allowed increased filtration After that groundwater levels on many places reached pre reservoir filling levels on some places reached even higher 21 Damming of the Danube improved ground water quality at Rusovce and Cunovo water supply 22 which are on right side of Danube It was due changed infiltration conditions and changed groundwater flow direction from NW SE to N S 23 The ground water quality at water supplies situated on the left side of the Danube were not influenced to the same extent as on the right side One of the same problems identified is increased sedimentation upstream and riverbed erosion downstream from reservoir which is a typical problem of water reservoirs See also editList of crossings of the Danube RiverReferences edit Aaron Schwabach Diverting the Danube The Gabcikovo Nagymaros Dispute and International Freshwater Law 1996 p 7 P K Rao International Environmental Law and Economics Blackwell Publishers Ltd 2002 page 230 1 A bos nagymarosi vizlepcsorendszer es a hagai per tortenete www szigetkoz biz Duna Kor Janos Vargha Hungary Right Livelihood Award Archived from the original on 30 November 2010 Retrieved 21 February 2011 Europe 1990 Janos Vargha Hungary Rivers amp Dams Goldman Environmental Prize Archived from the original on 23 November 2010 Retrieved 8 January 2011 a b New Scientist New Science Publications 3 February 1994 via Google Books a b c d Owen McIntyre Gabcikovo Nagymaros Project A Test Case for International Water Law In Anton Earle Anders Jagerskog and Joakim Ojendal editors Transboundary Water Management Principles and Practice Stockholm International Water Institute 2010 page 228 2 Cez Gabcikovo sa preplavilo viac ako pat milionov ľudi TERAZ sk 4 November 2012 a b SVD Gabcikovo Nagymaros Vodohospodarska vystavba s p www vvb sk New Scientist New Scientist 143 73 74 28 1994 Report of the International Court of Justice 1 August 2005 31 July 2006 Report United Nations Publications 2006 p 25 permanent dead link Summaries of Judgments Advisory Opinions and Orders of the International Court of Justice 1972 2002 Report United Nations International Court of Justice permanent dead link a b ROZSUDOK MEDZINARODNEHO SUDNEHO DVORA Z 25 SEPTEMBRA 1997 gabcikovo gov sk Archived from the original on 21 October 2013 Slovakia again discussing completion of Gabcikovo Nagymaros The Slovak Spectator 4 January 2006 Archived from the original on 27 September 2007 Retrieved 23 February 2008 The Court places on record the discontinuance by Slovakia of the procedure begun by means of its Request for an additional judgment PDF International Court of Justice Archived from the original PDF on 27 January 2018 Retrieved 13 December 2018 a b c d e f g Massimo Greco Armando Carravetta Renata Della Morte River Flow 2004 Volume 1 Taylor amp Francis 2004 pp 138 141 Environmental monitoring Archived from the original on 17 May 2009 Retrieved 30 March 2009 a b Groundwater quality processes after the bank infiltration from the Danube at Cunovo Archived from the original on 8 October 2009 Retrieved 4 June 2013 a b Monitoring prirodneho prostredia VR 2008 www vvb sk Archived from the original on 17 March 2016 Retrieved 4 November 2012 a b Joint annual report on the environment monitoring in 2010 Monitorovanie prirodneho prostredia v oblasti vplyvu VD Gabcikovo Monitoring of the natural environment in the area of influence Gabcikovo PDF Archived from the original PDF on 29 September 2021 Retrieved 3 February 2021 Slovak Hungarian Environmental Monitoring on the Danube 2006 Ground water regime monitoring page 5 permanent dead link Sources editChmelar V Dunaj energeticky vyd Electra Zilina 1992External links editTreaty between the Hungarian People s Republic and the Czechoslovak Socialist Republic concerning the construction and operation of the Gabcikovo Nagymaros system of locks Archived 4 November 2007 at the Wayback Machine Documents about the Gabcikovo dam and its impact alternative link Details of the conflict over the project Archived 14 September 2006 at the Wayback Machine PDF Bibliography on Water Resources and International Law Peace Palace Library Annual reports on environmental monitoring Archived 17 May 2009 at the Wayback Machine Gabcikovo Dam Virtual Tour Historie Soustavy vodnich del Gabcikovo Nagymaros Gabcikovo patalie bez konce 47 52 48 N 17 32 21 E 47 88000 N 17 53917 E 47 88000 17 53917 Retrieved from https en wikipedia org w index php title Gabcikovo Nagymaros Dams amp oldid 1211773808, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.