fbpx
Wikipedia

Federal Shipbuilding and Drydock Company

The Federal Shipbuilding and Drydock Company was a United States shipyard in New Jersey active from 1917 to 1948. It was founded during World War I to build ships for the United States Shipping Board. Unlike many shipyards, it remained active during the shipbuilding slump of the 1920s and early 1930s that followed the World War I boom years. During World War II, it built merchant ships as part of the U.S. Government's Emergency Shipbuilding program, at the same time producing more destroyers for the United States Navy than any yard other than the Bath Iron Works. Operated by a subsidiary of the United States Steel Corporation, the shipyard was located at Kearny Point where the mouth of the Hackensack River meets Newark Bay in the Port of New York and New Jersey.

Federal Shipbuilding and Drydock Company
Federal Shipbuilding and Dry Dock Company, 1945
IndustryShipbuilding
FoundedJuly 24, 1917 (1917-07-24)[1]
Defunct1948
Fateliquidated
HeadquartersKearny, New Jersey
ParentUnited States Steel Corporation

Around 570 vessels were contracted for construction by Federal SB&DD Company with about 100 not delivered fully completed due to the end of the World War II. Federal also had a yard at Port Newark during World War II that built destroyers and landing craft.[2]

History of the Federal Yard at Kearny Edit

 
Aerial view of Federal Shipbuilding in May 1945

Federal Shipbuilding and Dry Dock Company was founded July 24, 1917, as a subsidiary of United States Steel Corporation to supply ships for the United States Shipping Board during World War I.[1] The site on Kearny Point was first surveyed during the summer of 1917.[3] The shipyard was to consist of everything needed to fully complete a ship from a facility power plant to a wood joining shop. A steel plate mill and boiler shop were to be built as well. $10 million ($228 million today) was allocated for construction. The American Bridge Company was contracted to provide 10,000 tons of steel for the structures. E.H. Gary was president of Federal in August 1917.[4] The ship-ways were completed by the fall of 1917 with keels being laid by November 1917. Federal completed a 9,600-ton ship around six weeks before World War I ended as well as two other ships before the close of 1918. 27 ships were delivered to the Emergency Fleet Corporation in 1919. Federal accounted for 5% of the steel merchant tonnage built in 1919.[3]

By June 1921, the Federal yard at Kearny had a 535 by 161.5 feet (163.1 m × 49.2 m) boiler construction shop to build Scotch marine boilers, exhaust stacks, tanks, uptakes and other related items. 235 boilers had been constructed from September 1919 to June 1921. Boilers constructed there were mostly 15 feet (4.6 m) diameter or larger. At that time, 250 men were able to construct three boilers a week with a single 8-hour shift each day.[5]

By November 1921, Federal had shipbuilding ways for twelve 15,000-ton vessels and had constructed a 9,000-ton floating dry dock. The dry dock was first used June 23, 1921, when Transmarine corp's SS Suhulco docked. The Kearny yard was 17 acres (6.9 ha) with 2,400 feet (730 m) of frontage on the Hackensack River. A wet basin was located at the southern end with a 100-ton 3-legged jib crane for fitting out new ships.[6]

On Sunday night, May 18, 1924, a fire destroyed the largest building at the Kearny yard causing an initially estimated $500,000 in damage.[7] Other estimates were $1.6 million or as high as several million dollars in damage. Firemen used four mobile cranes to try to extinguish fires in the pattern building and the plate shop. Over a thousand workers were idled by the fire.[8] The shipyard had around 5,000 workers at the time and was said to be one of the largest steel fabrication plants in the world. Fireboats and numerous firemen from around the area were called in to fight the fire which spread rapidly through the wooden structures at the Kearny yard.[9]

The Federal yard at Kearny remained operational during the difficult interwar period and Great Depression when many shipyards across the country did not.

1940 to closure Edit

 
May 1942 launch of USS Fletcher (DD-445) and USS Radford (DD-446) at Federal. 2 of the 4 destroyers launched on May 4, 1942.

Federal made national news when around 16,000 workers went on strike at Kearny from August 7 to August 25, 1941. Work was stopped on $493 million ($9.81 billion today) in Navy and merchant shipbuilding contracts as the nation ramped up ship construction before entering World War II. The strike was ended when President Franklin D. Roosevelt ordered the Navy to seize control of the facility.[10] The final sticking point in negotiations had been the refusal of management at Federal to accept demands to require a "maintenance of membership" clause which would effectively make the shipyard a closed shop. Company president Lynn H. Korndorff offered the shipyard to the Navy rather than accept the demands to become a closed shop.[11]

When the Navy took over, the yard fell under the supervision of Rear Admiral Harold G. Bowen Sr. as Officer-in-charge. It was the first take over of an industrial plant by the Navy in that era. While the union was enthusiastic about the seizure, they did not get the response they were expecting when the Navy took control. According to Rear Admiral Bowen in his autobiography, while he was cordial with labor, he refused to acknowledge any union's right to collectively bargain for the workers at Kearny. He also refused to take steps to implement the "maintenance of membership" issue.[12] By November 1941, the "maintenance of membership" clause was still not being enforced and the union sought relief from the Defense Mediation Board.[13]

After 134 days of operation by the Navy, control of the shipyard was returned to the company on January 6, 1942. Under Navy control the shipyard laid 12 keels, launched 10 and commissioned 7 ships. Secretary of the Navy Frank Knox returned the shipyard and asked that the company and union work out the remaining issue. Failing that, the two parties would use newly established national machinery to resolve the dispute.[14] The "maintenance of membership" issue had still not been resolved. In May 1942, Federal finally gave in to demands to require membership in the CIO Industrial Union of Marine and Shipbuilding Workers. Company president Lynn H. Korndorff said Federal only complied with the order of the National War Labor Board because of the war emergency. The incident was viewed as one of the first major tests of the NWLB.[15][16]

According to John T. Cunningham in "Made in New Jersey," Federal "completely proved its might". On one day alone in May 1942, the company launched four destroyers in a 50-minute period.[17] By 1943, Federal Shipbuilding was employing 52,000 people and building ships faster than any other yard in the world."[18]

Federal continued to set company construction speed records throughout the war. In July 1943, Federal claimed records of 170 days from keel to commissioning on the 2,050-ton Fletcher-class destroyer USS Dashiell (DD-659) and 137 days on the 1,630-ton Gleaves-class destroyer USS Thorn (DD-647). Federal also said Type C2 ships were being built in an average time of 82 days. In July 1943, destroyer escorts were being launched about once a week since spring of 1943.[19] Between the Newark and Kearny yards, Federal launched a company record of 11 ships in 29 days during March 1943.[20]

After World War II ended, a number of destroyers were cancelled including some that were partially constructed. Federal had contracts to build several cargo ships for the United States Maritime Commission. Five Type C3-class ships were for Lykes Lines and six for American South African Line. Two bulk carriers were built for National Gypsum and three Type C2 ships for Grace Line's "Santa" / South American passenger-freight service. Federal also converted SS Uruguay from wartime service for Moore-McCormack starting in 1946.[2][21][22][23]

4,000 shipyard workers at Federal joined 90,000 other east coast shipyard workers in a strike action on 1 July 1947.[24] The strike at Federal ended in November 1947 after 140 days.[25]

 
Site of the former Federal yard at Kearny in foreground on left, c.1974.

On April 23, 1948, Lynn H. Korndorff, the President of Federal Shipbuilding and Drydock Company announced that the US Navy had agreed to purchase facilities at Kearny for around $2,375,000 ($28.9 million today), its depreciated book value.[26] The Navy planned to hold the facility in a standby state for potential emergency reactivation.[27] The New York Times regarded this sale price to be "astounding low".[28] In July 1948, Federal's large floating dry dock was towed 1,700 miles in 19 days to Gulf Shipbuilding Corporation's Chickasaw, Alabama, shipyard, which had been constructed during World War I by U.S. Steel, parent of Federal SB&DD.[29]

Around 465 ships were delivered by Federal SB&DD Company out of its 569 hull numbers allocated. 325 were delivered from the Kearny yard and 140 from Port Newark.[2]

Instead of building ships, the site eventually hosted a salvaging operation where numerous ships were scrapped. In 1975, the former Federal yard was described as one of the nation's largest ship breaking yards. According to the 1975 head of the River Terminal Development Corp, the first ship to be scrapped at the yard was USS Enterprise (CV-6) in 1959. Other carriers scrapped there included Essex, Randolph, Boxer, Wasp and Antietam. Battleships, battle cruisers, cruisers and submarines had also been scrapped at the former Federal yard as of the mid-1970s.[30] Texas Tower 3 was also scrapped at the Federal yard by Lipsett Corp.[31]

Ships built at Kearny Edit

Military ships Edit

The Federal Shipbuilding and Drydock Company built eleven classes of ships for the U.S. military. Of the 387 ships of those classes constructed nationally, 108 came from Kearny. Of the 415 World War II–era destroyers of all classes produced nationally, 69 came from Kearny.

Canceled orders Edit

USS Buffalo (CL-84) and USS Newark (CL-88) were cancelled 16 December 1940.[32][clarification needed]

Merchant ships Edit

The last ships for the United States Shipping Board were delivered by January 1920. Federal Kearny built 30 of the 48 Design 1037 ships. These were the very first ships built at the site, with yard numbers 1 through 30.

For private contractors

Several ships for the Maritime Commission were built before the war broke out.

Federal Yard at Port Newark Edit

 
yard at Newark in 1945

In January 1942, Federal Shipbuilding and Drydock Company announced they were expanding their facilities to increase capacity and employ an additional 10,000 workers.[38] They expanded to the site of the former Submarine Boat Corporation at Port Newark (40°41′35″N 74°07′47″W / 40.69306°N 74.12960°W / 40.69306; -74.12960). After nine months of construction to rebuild the facility, the first ships were launched at the Port Newark yard on October 10, 1942.[39] All of the Gearing-class destroyers built at Federal were built at the Newark yard.[40] The Port Newark yard closed after the war and the site gained some notoriety in late 1947 during a dispute over the scrapping of the battleship New Mexico and two others by Lipsett Corp.[41] The site was an automobile terminal parking lot in the 2010s.[42]

See also Edit

References Edit

  1. ^ a b Dickie, Alexander J., ed. (February 1922). "Federal Shipbuilding Yard Busy". Pacific Marine Review. Pacific American Steamship Association. 19: 121.
  2. ^ a b c . shipbuildinghistory.com. Archived from the original on May 2, 2015. Retrieved May 17, 2015.
  3. ^ a b "Federal Shipbuilding and Drydock Company". Port of New York Annual: 274. 1920.
  4. ^ "Biggest Yard for Building Ships". The Day. New London, CT. Wall Street Journal. August 25, 1917. p. 11.
  5. ^ "Quantity Production of Scotch Marine Boilers". Marine Engineering & Shipping Age. Aldrich Publishing Company. 26: 443. June 1921.
  6. ^ "Federal Shipyard takes up Ship Repairing". Marine Engineering & Shipping Age. Aldrich Publishing Company. 26: 835. November 1921.
  7. ^ "Half Million Shipyard Burns". Billings Gazette. Billings, MT. May 19, 1924. p. 1.
  8. ^ "Firemen fight flames from moving cranes". Anniston Star. Anniston, AL. United Press. May 19, 1924. p. 1.
  9. ^ "Big Fire Raging in N. J. Shipyard". The Gazette. Montreal. May 19, 1924.
  10. ^ "Kearny Plant to Resume Full Operations Tuesday". Sheboygan Press. Sheboygan, WI. United Press. August 25, 1941.
  11. ^ Reynolds, T. F. (August 24, 1941). "US Seizes Kearny Shipyard". The Sunday Morning Star. Wilmington, DE. United Press. p. 1. (Page 6 contains text of FDR's executive order signed August 23, 1941, to seize the plant)
  12. ^ Bowen, Harold G. (1954). "5". Ships, Machinery and Mossbacks: The Autobiography of a Naval Engineer. Princeton, N.J.: Princeton Univ. Press. p. 221.
  13. ^ "Mediation Board Decision Would Affect CIO Parley". The Pittsburgh Press. November 16, 1941. p. 9.
  14. ^ "Navy Turns Plant Over to Owner". Spokane Daily Chronicle. AP. January 6, 1942. p. 6.
  15. ^ "Big Steel Accepts Labor Board Order". The Telegraph. Nashua, NH. May 9, 1942. p. 2.
  16. ^ "Shipyard Dispute is Terminated". Schenectady Gazette. AP. May 9, 1942. p. 3.
  17. ^ "4 Destroyers Launched from Kearny Yards". The Lewiston Daily Sun. Lewiston, ME. May 4, 1942. p. 1. Fletcher, Radford, Quick, and Mervine
  18. ^ Genovese, Peter (October 7, 2011), "'Jersey State of Mind': A gritty little hub with heart", The Star-Ledger, retrieved 2011-10-06, The Federal Shipbuilding Co., a U.S. Steel subsidiary based in South Kearny, played a key role in supplying ships for both World Wars. Scarcely six months after Pearl Harbor, according to John Cunningham in "Made in New Jersey," Federal "completely proved its might. On one day alone in May 1942, the company launched four destroyers. By 1943, Federal Shipbuilding was employing 52,000 people and building ships faster than any other yard in the world."
  19. ^ "Real Speed". The Palm Beach Post. July 2, 1943. p. 5.
  20. ^ "Newark Launches Four Warships". St. Petersburg Times. AP. March 29, 1943. p. 9.
  21. ^ "Various". Pacific Marine Review. 43. 1946.
  22. ^ "Various". Pacific Marine Review. 44. 1947.
  23. ^ "Various". Pacific Marine Review. 45. 1948.
  24. ^ "More Shipyard Workers Strike". New Castle News. INS. July 1, 1947.
  25. ^ "Ship Builders End Strike". Evening Telegraph November 14, 1947. Dixon, IL. AP.
  26. ^ "Navy Buys New Jersey Shipyard". Indiana Evening Gazette. AP. April 23, 1948.
  27. ^ "US Steel has gone out of the shipbuilding business". Press Telegram. Long Beach, CA. April 22, 1948.
  28. ^ "Plant of U.S. Steel is Sold to Navy". The New York Times. April 22, 1948. Federal Shipbuilding Goes for $2,375,000, Regarded as Astoundingly Low
  29. ^ "Big Floating Dry Dock coming to Mobile". Dothan Eagle. AP. July 28, 1948.
  30. ^ "Famed Ships scrapped at ship-breaking yard". Anderson Herald Bulletin. AP. September 1, 1975.
  31. ^ "Texas Tower May Get New Job". Bergen Record. AP. August 11, 1964.
  32. ^ Friedman, Norman (1984). U.S. Cruisers, An Illustrated Design History. ISBN 978-0-87021-718-0.
  33. ^ a b c d e f g https://vesselhistory.marad.dot.gov/Search; covers name, approximate tonnage, launch year, original owner
  34. ^ "Joseph Lykes (1940) - Lloyds Register of Ships".
  35. ^ "Zoella Lykes (1940) - Lloyds Register of Ships".
  36. ^ "Reuben Tipton (1940) - Lloyds Register of Ships".
  37. ^ "John Lykes (1940) - Lloyds Register of Ships".
  38. ^ "Federal Shipbuilding Will Expand Facilities to Handle War Orders". The Pittsburgh Press. Pittsburgh, PA. United Press. January 26, 1942. p. 20.
  39. ^ "Two Vessels Launched". The Spartanburg Herald-Journal. Spartanburg, SC. AP. October 11, 1942. p. 3.
  40. ^ "Newark Bay Yard". Globalsecurity.org. Retrieved May 16, 2015.
  41. ^ Staff Writer (November 13, 1947). "Pact To Stave Off Battle In Newark Sought". Ellensburg Daily Record. Ellensburg, Washington. Retrieved 2009-10-15.
  42. ^ "Federal Shipbuilding & Dry Dock Co, Port Newark". Destroyer History Foundation. Retrieved 16 May 2015.
  43. ^ "Epperson". Dictionary of American Naval Fighting Ships. Navy Department, Naval History and Heritage Command.

Further reading Edit

  • Bowen, Harold G. (1954). "5". Ships, Machinery and Mossbacks: The Autobiography of a Naval Engineer. Princeton, N.J.: Princeton Univ. Press. p. 205. - Written by Admiral Harold G. Bowen Sr., chapter 5 details his operation of the Kearny yard in 1941 during the time the government had seized the shipyard.
  • Palmer, David (1998). Organizing the Shipyards: Union Strategy in Three Northeast Ports, 1933–1945. Cornell University Press. ISBN 978-0-8014-2734-3. - details the labor issues surrounding this shipyard and others in the New York area

External links Edit

  • "Kearny Yard history". globalsecurity.org.
  • "Federal Shipbuilding & Dry Dock Co, Kearny". Destroyer History Foundation. - Yard background and photographs from 1945 and 2003
  • . phillyseaport.org. Archived from the original on 2015-12-19. - A web exhibit of ship christening photos that includes half a dozen images of launching ceremonies at the Kearny Yard
  • "River Terminal Development". riverterminal.com. - on the site of the shipyard.

40°43′26″N 74°06′22″W / 40.723790°N 74.106168°W / 40.723790; -74.106168

federal, shipbuilding, drydock, company, united, states, shipyard, jersey, active, from, 1917, 1948, founded, during, world, build, ships, united, states, shipping, board, unlike, many, shipyards, remained, active, during, shipbuilding, slump, 1920s, early, 19. The Federal Shipbuilding and Drydock Company was a United States shipyard in New Jersey active from 1917 to 1948 It was founded during World War I to build ships for the United States Shipping Board Unlike many shipyards it remained active during the shipbuilding slump of the 1920s and early 1930s that followed the World War I boom years During World War II it built merchant ships as part of the U S Government s Emergency Shipbuilding program at the same time producing more destroyers for the United States Navy than any yard other than the Bath Iron Works Operated by a subsidiary of the United States Steel Corporation the shipyard was located at Kearny Point where the mouth of the Hackensack River meets Newark Bay in the Port of New York and New Jersey Federal Shipbuilding and Drydock CompanyFederal Shipbuilding and Dry Dock Company 1945IndustryShipbuildingFoundedJuly 24 1917 1917 07 24 1 Defunct1948FateliquidatedHeadquartersKearny New JerseyParentUnited States Steel CorporationAround 570 vessels were contracted for construction by Federal SB amp DD Company with about 100 not delivered fully completed due to the end of the World War II Federal also had a yard at Port Newark during World War II that built destroyers and landing craft 2 Contents 1 History of the Federal Yard at Kearny 1 1 1940 to closure 2 Ships built at Kearny 2 1 Military ships 2 1 1 Canceled orders 2 2 Merchant ships 3 Federal Yard at Port Newark 4 See also 5 References 6 Further reading 7 External linksHistory of the Federal Yard at Kearny Edit nbsp Aerial view of Federal Shipbuilding in May 1945Federal Shipbuilding and Dry Dock Company was founded July 24 1917 as a subsidiary of United States Steel Corporation to supply ships for the United States Shipping Board during World War I 1 The site on Kearny Point was first surveyed during the summer of 1917 3 The shipyard was to consist of everything needed to fully complete a ship from a facility power plant to a wood joining shop A steel plate mill and boiler shop were to be built as well 10 million 228 million today was allocated for construction The American Bridge Company was contracted to provide 10 000 tons of steel for the structures E H Gary was president of Federal in August 1917 4 The ship ways were completed by the fall of 1917 with keels being laid by November 1917 Federal completed a 9 600 ton ship around six weeks before World War I ended as well as two other ships before the close of 1918 27 ships were delivered to the Emergency Fleet Corporation in 1919 Federal accounted for 5 of the steel merchant tonnage built in 1919 3 By June 1921 the Federal yard at Kearny had a 535 by 161 5 feet 163 1 m 49 2 m boiler construction shop to build Scotch marine boilers exhaust stacks tanks uptakes and other related items 235 boilers had been constructed from September 1919 to June 1921 Boilers constructed there were mostly 15 feet 4 6 m diameter or larger At that time 250 men were able to construct three boilers a week with a single 8 hour shift each day 5 By November 1921 Federal had shipbuilding ways for twelve 15 000 ton vessels and had constructed a 9 000 ton floating dry dock The dry dock was first used June 23 1921 when Transmarine corp s SS Suhulco docked The Kearny yard was 17 acres 6 9 ha with 2 400 feet 730 m of frontage on the Hackensack River A wet basin was located at the southern end with a 100 ton 3 legged jib crane for fitting out new ships 6 On Sunday night May 18 1924 a fire destroyed the largest building at the Kearny yard causing an initially estimated 500 000 in damage 7 Other estimates were 1 6 million or as high as several million dollars in damage Firemen used four mobile cranes to try to extinguish fires in the pattern building and the plate shop Over a thousand workers were idled by the fire 8 The shipyard had around 5 000 workers at the time and was said to be one of the largest steel fabrication plants in the world Fireboats and numerous firemen from around the area were called in to fight the fire which spread rapidly through the wooden structures at the Kearny yard 9 The Federal yard at Kearny remained operational during the difficult interwar period and Great Depression when many shipyards across the country did not 1940 to closure Edit nbsp May 1942 launch of USS Fletcher DD 445 and USS Radford DD 446 at Federal 2 of the 4 destroyers launched on May 4 1942 Federal made national news when around 16 000 workers went on strike at Kearny from August 7 to August 25 1941 Work was stopped on 493 million 9 81 billion today in Navy and merchant shipbuilding contracts as the nation ramped up ship construction before entering World War II The strike was ended when President Franklin D Roosevelt ordered the Navy to seize control of the facility 10 The final sticking point in negotiations had been the refusal of management at Federal to accept demands to require a maintenance of membership clause which would effectively make the shipyard a closed shop Company president Lynn H Korndorff offered the shipyard to the Navy rather than accept the demands to become a closed shop 11 When the Navy took over the yard fell under the supervision of Rear Admiral Harold G Bowen Sr as Officer in charge It was the first take over of an industrial plant by the Navy in that era While the union was enthusiastic about the seizure they did not get the response they were expecting when the Navy took control According to Rear Admiral Bowen in his autobiography while he was cordial with labor he refused to acknowledge any union s right to collectively bargain for the workers at Kearny He also refused to take steps to implement the maintenance of membership issue 12 By November 1941 the maintenance of membership clause was still not being enforced and the union sought relief from the Defense Mediation Board 13 After 134 days of operation by the Navy control of the shipyard was returned to the company on January 6 1942 Under Navy control the shipyard laid 12 keels launched 10 and commissioned 7 ships Secretary of the Navy Frank Knox returned the shipyard and asked that the company and union work out the remaining issue Failing that the two parties would use newly established national machinery to resolve the dispute 14 The maintenance of membership issue had still not been resolved In May 1942 Federal finally gave in to demands to require membership in the CIO Industrial Union of Marine and Shipbuilding Workers Company president Lynn H Korndorff said Federal only complied with the order of the National War Labor Board because of the war emergency The incident was viewed as one of the first major tests of the NWLB 15 16 According to John T Cunningham in Made in New Jersey Federal completely proved its might On one day alone in May 1942 the company launched four destroyers in a 50 minute period 17 By 1943 Federal Shipbuilding was employing 52 000 people and building ships faster than any other yard in the world 18 Federal continued to set company construction speed records throughout the war In July 1943 Federal claimed records of 170 days from keel to commissioning on the 2 050 ton Fletcher class destroyer USS Dashiell DD 659 and 137 days on the 1 630 ton Gleaves class destroyer USS Thorn DD 647 Federal also said Type C2 ships were being built in an average time of 82 days In July 1943 destroyer escorts were being launched about once a week since spring of 1943 19 Between the Newark and Kearny yards Federal launched a company record of 11 ships in 29 days during March 1943 20 After World War II ended a number of destroyers were cancelled including some that were partially constructed Federal had contracts to build several cargo ships for the United States Maritime Commission Five Type C3 class ships were for Lykes Lines and six for American South African Line Two bulk carriers were built for National Gypsum and three Type C2 ships for Grace Line s Santa South American passenger freight service Federal also converted SS Uruguay from wartime service for Moore McCormack starting in 1946 2 21 22 23 4 000 shipyard workers at Federal joined 90 000 other east coast shipyard workers in a strike action on 1 July 1947 24 The strike at Federal ended in November 1947 after 140 days 25 nbsp Site of the former Federal yard at Kearny in foreground on left c 1974 On April 23 1948 Lynn H Korndorff the President of Federal Shipbuilding and Drydock Company announced that the US Navy had agreed to purchase facilities at Kearny for around 2 375 000 28 9 million today its depreciated book value 26 The Navy planned to hold the facility in a standby state for potential emergency reactivation 27 The New York Times regarded this sale price to be astounding low 28 In July 1948 Federal s large floating dry dock was towed 1 700 miles in 19 days to Gulf Shipbuilding Corporation s Chickasaw Alabama shipyard which had been constructed during World War I by U S Steel parent of Federal SB amp DD 29 Around 465 ships were delivered by Federal SB amp DD Company out of its 569 hull numbers allocated 325 were delivered from the Kearny yard and 140 from Port Newark 2 Instead of building ships the site eventually hosted a salvaging operation where numerous ships were scrapped In 1975 the former Federal yard was described as one of the nation s largest ship breaking yards According to the 1975 head of the River Terminal Development Corp the first ship to be scrapped at the yard was USS Enterprise CV 6 in 1959 Other carriers scrapped there included Essex Randolph Boxer Wasp and Antietam Battleships battle cruisers cruisers and submarines had also been scrapped at the former Federal yard as of the mid 1970s 30 Texas Tower 3 was also scrapped at the Federal yard by Lipsett Corp 31 Ships built at Kearny EditMilitary ships Edit The Federal Shipbuilding and Drydock Company built eleven classes of ships for the U S military Of the 387 ships of those classes constructed nationally 108 came from Kearny Of the 415 World War II era destroyers of all classes produced nationally 69 came from Kearny Light cruisers Atlanta class 2 of 8 CL 51 CL 52 in 1940 1941 Juneau class all 3 CL 119 CL 121 in 1945 1946 Destroyers Mahan class 2 of 18 DD 368 DD 369 Somers class 2 of 5 DD 381 DD 383 Benham class 3 of 10 DD 397 DD 399 Sims class 2 of 12 DD 411 DD 412 Gleaves class 26 of 66 4 of 18 interwar era DD 431 DD 432 DD 439 DD 440 22 of 48 WWII era DD 453 DD 456 DD 483 DD 490 DD 618 DD 623 DD 645 DD 648 Fletcher class 29 of 175 DD 445 DD 448 DD 465 DD 466 DD 498 DD 502 DD 659 DD 661 DD 666 DD 680 Allen M Sumner class 18 of 58 DD 692 DD 709 Attack cargo ships Andromeda class 21 of 32 AKA 15 AKA 20 AKA 53 AKA 55 AKA 58 AKA 63 AKA 94 AKA 100Canceled orders Edit USS Buffalo CL 84 and USS Newark CL 88 were cancelled 16 December 1940 32 clarification needed Merchant ships Edit The last ships for the United States Shipping Board were delivered by January 1920 Federal Kearny built 30 of the 48 Design 1037 ships These were the very first ships built at the site with yard numbers 1 through 30 USSB 955 964 Liberty Federal gt Fukuzan Maru Piave Mercer Marne gt Yuzan Maru The Lambs Homestead Duquesne McKeesport Braddock USSB 1422 1441 Donora Lorain Waukegan Youngstown Ambridge Clairton Innoko Wytheville Belfort Westmoreland Bellbuckle Vincent Bellhaven Winona County Bellepline Anaconda Bellerose Kearny Bellflower BelleminaFor private contractors 18 cargo ships for the parent company U S Steel the Isthmian Steamship Company Steel Age Steel Maker Steel Voyager Steel Worker Steel Mariner 6 000t 1920 Steel Trader Steel Exporter Steel Engineer Steel Inventor Steel Ranger 6 000t 1920 Steel Seafarer Steel Scientist Steel Navigator 6 000t 1921 Steel Traveler 7 000t 1922 Steel Motor Steel Vendor 1 700t 1923 Steel Chemist Steel Electrician 1 700t 1926 See also related work done in Chicksaw 11 tankers for Standard Oil of New Jersey Walter Jennings E T Bedford 33 J A Moffet Jr 33 9 600t 9 800t 1921 R P Resor T C McCobb 7 500t 1936 Esso Bayonne Esso Bayway 7 700t 1937 33 Esso Houston 33 Esso Boston 7 700t 1938 Esso Montpelier Esso Concord 7 700t 1940 33 4 passenger ships for the Grace Line 9 100t 33 Santa Rosa Santa Paula 1932 Santa Lucia Santa Elena 1933 5 tankers for Pan American Patroleum 33 Pan Maine Pan Florida 7 200t 1936 Pan New York Pan Maryland 7 700t 1938 Pan Rhode Island 7 700t 1941 2 tankers for Imperial Oil in 1921 11 000t 1921 Vancolite Victolite tanker Gulfpride for Gulf Oil in 1927 12 500t passenger Dixie for the Southern Pacific SS Line 1928 8 200t 2 tankers for Standard Shipping in 1930 G Harrison Smith W S FarishSeveral ships for the Maritime Commission were built before the war broke out 3 T3 in 1939 Markey Neosho Esso Trenton 6 C2 in 1939 and 1940 Challenge Red Jacket Lightning Flying Cloud Flying Fish 6 C3 in 1940 and 1941 Sea Fox Sea Hound Sea Panther Almeria Lykes Howell Lykes Mormacyork 5 C1 B in 1940 and 1941 Joseph Lykes Zoella Lykes Reuben Tipton Fred Morris John Lykes 2 DeLaval Trenton steam turbines double reduction gears 1 shaft 34 35 36 37 uncertain Fred MorrisFederal Yard at Port Newark Edit nbsp yard at Newark in 1945In January 1942 Federal Shipbuilding and Drydock Company announced they were expanding their facilities to increase capacity and employ an additional 10 000 workers 38 They expanded to the site of the former Submarine Boat Corporation at Port Newark 40 41 35 N 74 07 47 W 40 69306 N 74 12960 W 40 69306 74 12960 After nine months of construction to rebuild the facility the first ships were launched at the Port Newark yard on October 10 1942 39 All of the Gearing class destroyers built at Federal were built at the Newark yard 40 The Port Newark yard closed after the war and the site gained some notoriety in late 1947 during a dispute over the scrapping of the battleship New Mexico and two others by Lipsett Corp 41 The site was an automobile terminal parking lot in the 2010s 42 36 of 923 LCI L 161 196 52 of 563 destroyer escorts and APDs 36 of 72 Cannon class destroyer escorts built October 1942 January 1944 Levy DE 162 Roche DE 197 16 of 83 John C Butler class destroyer escorts built November 1943 August 1944 Corbesier DE 438 Joseph E Connolly DE 450 Gilligan DE 508 Heyliger DE 510 10 of 415 destroyers 10 of 98 Gearing class Gearing DD 710 Hamner DD 718 Epperson DD 719 completed by Bath Iron Works 43 Castle DD 720 scrapped incomplete Woodrow R Thompson DD 721 scrapped incomplete 42 of 558 Landing Ship Medium LSM 253 LSM 294See also EditChickasaw Shipyard Village Historic District the site of a U S Steel shipbuilding yard in Chickasaw Alabama which was later owned by Gulf Shipbuilding Corporation a subsidiary of Waterman Steamship Corporation during World War II References Edit a b Dickie Alexander J ed February 1922 Federal Shipbuilding Yard Busy Pacific Marine Review Pacific American Steamship Association 19 121 a b c Federal Shipbuilding Kearny and Newark NJ shipbuildinghistory com Archived from the original on May 2 2015 Retrieved May 17 2015 a b Federal Shipbuilding and Drydock Company Port of New York Annual 274 1920 Biggest Yard for Building Ships The Day New London CT Wall Street Journal August 25 1917 p 11 Quantity Production of Scotch Marine Boilers Marine Engineering amp Shipping Age Aldrich Publishing Company 26 443 June 1921 Federal Shipyard takes up Ship Repairing Marine Engineering amp Shipping Age Aldrich Publishing Company 26 835 November 1921 Half Million Shipyard Burns Billings Gazette Billings MT May 19 1924 p 1 Firemen fight flames from moving cranes Anniston Star Anniston AL United Press May 19 1924 p 1 Big Fire Raging in N J Shipyard The Gazette Montreal May 19 1924 Kearny Plant to Resume Full Operations Tuesday Sheboygan Press Sheboygan WI United Press August 25 1941 Reynolds T F August 24 1941 US Seizes Kearny Shipyard The Sunday Morning Star Wilmington DE United Press p 1 Page 6 contains text of FDR s executive order signed August 23 1941 to seize the plant Bowen Harold G 1954 5 Ships Machinery and Mossbacks The Autobiography of a Naval Engineer Princeton N J Princeton Univ Press p 221 Mediation Board Decision Would Affect CIO Parley The Pittsburgh Press November 16 1941 p 9 Navy Turns Plant Over to Owner Spokane Daily Chronicle AP January 6 1942 p 6 Big Steel Accepts Labor Board Order The Telegraph Nashua NH May 9 1942 p 2 Shipyard Dispute is Terminated Schenectady Gazette AP May 9 1942 p 3 4 Destroyers Launched from Kearny Yards The Lewiston Daily Sun Lewiston ME May 4 1942 p 1 Fletcher Radford Quick and Mervine Genovese Peter October 7 2011 Jersey State of Mind A gritty little hub with heart The Star Ledger retrieved 2011 10 06 The Federal Shipbuilding Co a U S Steel subsidiary based in South Kearny played a key role in supplying ships for both World Wars Scarcely six months after Pearl Harbor according to John Cunningham in Made in New Jersey Federal completely proved its might On one day alone in May 1942 the company launched four destroyers By 1943 Federal Shipbuilding was employing 52 000 people and building ships faster than any other yard in the world Real Speed The Palm Beach Post July 2 1943 p 5 Newark Launches Four Warships St Petersburg Times AP March 29 1943 p 9 Various Pacific Marine Review 43 1946 Various Pacific Marine Review 44 1947 Various Pacific Marine Review 45 1948 More Shipyard Workers Strike New Castle News INS July 1 1947 Ship Builders End Strike Evening Telegraph November 14 1947 Dixon IL AP Navy Buys New Jersey Shipyard Indiana Evening Gazette AP April 23 1948 US Steel has gone out of the shipbuilding business Press Telegram Long Beach CA April 22 1948 Plant of U S Steel is Sold to Navy The New York Times April 22 1948 Federal Shipbuilding Goes for 2 375 000 Regarded as Astoundingly Low Big Floating Dry Dock coming to Mobile Dothan Eagle AP July 28 1948 Famed Ships scrapped at ship breaking yard Anderson Herald Bulletin AP September 1 1975 Texas Tower May Get New Job Bergen Record AP August 11 1964 Friedman Norman 1984 U S Cruisers An Illustrated Design History ISBN 978 0 87021 718 0 a b c d e f g https vesselhistory marad dot gov Search covers name approximate tonnage launch year original owner Joseph Lykes 1940 Lloyds Register of Ships Zoella Lykes 1940 Lloyds Register of Ships Reuben Tipton 1940 Lloyds Register of Ships John Lykes 1940 Lloyds Register of Ships Federal Shipbuilding Will Expand Facilities to Handle War Orders The Pittsburgh Press Pittsburgh PA United Press January 26 1942 p 20 Two Vessels Launched The Spartanburg Herald Journal Spartanburg SC AP October 11 1942 p 3 Newark Bay Yard Globalsecurity org Retrieved May 16 2015 Staff Writer November 13 1947 Pact To Stave Off Battle In Newark Sought Ellensburg Daily Record Ellensburg Washington Retrieved 2009 10 15 Federal Shipbuilding amp Dry Dock Co Port Newark Destroyer History Foundation Retrieved 16 May 2015 Epperson Dictionary of American Naval Fighting Ships Navy Department Naval History and Heritage Command Further reading EditBowen Harold G 1954 5 Ships Machinery and Mossbacks The Autobiography of a Naval Engineer Princeton N J Princeton Univ Press p 205 Written by Admiral Harold G Bowen Sr chapter 5 details his operation of the Kearny yard in 1941 during the time the government had seized the shipyard Palmer David 1998 Organizing the Shipyards Union Strategy in Three Northeast Ports 1933 1945 Cornell University Press ISBN 978 0 8014 2734 3 details the labor issues surrounding this shipyard and others in the New York areaExternal links EditDetailed record of all ships built at Federal Shipbuilding and Drydock Company Kearny and Newark Kearny Yard history globalsecurity org Federal Shipbuilding amp Dry Dock Co Kearny Destroyer History Foundation Yard background and photographs from 1945 and 2003 Ladies Who Launch phillyseaport org Archived from the original on 2015 12 19 A web exhibit of ship christening photos that includes half a dozen images of launching ceremonies at the Kearny Yard River Terminal Development riverterminal com on the site of the shipyard 40 43 26 N 74 06 22 W 40 723790 N 74 106168 W 40 723790 74 106168 nbsp Wikimedia Commons has media related to Federal Shipbuilding and Drydock Company Retrieved from https en wikipedia org w index php title Federal Shipbuilding and Drydock Company amp oldid 1163368003, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.