fbpx
Wikipedia

Churchill Falls Generating Station

The Churchill Falls Generating Station is a hydroelectric underground power station in Labrador. At 5,428 MW, it is the sixteenth largest in the world, and the second-largest in Canada, after the Robert-Bourassa generating station in northwestern Quebec.

Churchill Falls Generating Station
Location of Churchill Falls Generating Station in Newfoundland and Labrador
LocationNewfoundland and Labrador,
Canada
Coordinates53°31′43.45″N 63°57′57.15″W / 53.5287361°N 63.9658750°W / 53.5287361; -63.9658750Coordinates: 53°31′43.45″N 63°57′57.15″W / 53.5287361°N 63.9658750°W / 53.5287361; -63.9658750
Construction began1967
Opening date1974
Construction cost946 million CAD
Owner(s)CFLCo
Dam and spillways
Type of dam88 rock-filled dikes
ImpoundsChurchill River
Length64 km (40 mi)
Dam volume2,200,000 m3 (2,900,000 cu yd)
Reservoir
CreatesSmallwood Reservoir
Ossokmanuan Reservoir
Total capacity32.64 km3 (1.153×1012 cu ft)
Catchment area71,750 km2 (27,700 sq mi)
Surface area6,988 km2 (2,698 sq mi)
Power Station
Operator(s)CFLCo
Commission date1971-74
Hydraulic head312.4 m (1,025 ft)
Turbines11
Installed capacity5,428 MW
Capacity factor73.6%
Annual generation35,000 GWh (130,000 TJ)
Website
nalcorenergy.com/nalcor-operations/churchill-falls/

Rather than a single large dam, the plant's reservoir is contained by 88 dykes, totalling 64 km in length. Now called the Smallwood Reservoir, it has a capacity of 33 cubic kilometres in a catchment area of about 72,000 square kilometres, an area larger than the Republic of Ireland. It drops over 305 metres to the site of the plant's 11 turbines.

The plant's power house was hewn from solid granite 300 metres underground. It is about 300 metres long and as high as a 15-story building.[1]

The station cost almost a billion Canadian dollars to build in 1970. Commissioned from 1971 to 1974, it is owned and operated by the Churchill Falls Labrador Corporation Limited, a joint venture between Nalcor Energy (65.8%) and Hydro-Québec (34.2%). Workers at the station live in the purpose-built company town of Churchill Falls.

The ongoing Lower Churchill Project is a joint venture between Nalcor and Emera[2] to develop the remaining 35 percent of the Churchill River basin.

Toponymy

Originally called the Mishtashipu (Big River)[3] by the Innu, in 1821 the river was called Hamilton by Captain William Martin of HM brig Clinker, after Sir Charles Hamilton the Governor of Newfoundland from 1818 to 1823. The waterfall itself was called Grand Falls. In 1965, after the death of Winston Churchill the falls, river, town, and generating station were all renamed again.

History

Early investigations

 
In 1931, the Dominion of Newfoundland issued a 30-cent stamp depicting the falls.

In 1915 Wilfred Thibaudeau surveyed the Labrador Plateau. He designed a channel scheme to divert water before it arrived at the falls. The scheme would use the natural capacity of the drainage basin, which covers over 23,300 sq mi (60,000 km2), eliminating the need for the construction of dams. The advantage of the site was the river's drop of more than 300 metres in less than 32 km, and steady supply of water. These findings were confirmed in a 1947 survey, but development did not proceed due to the remoteness of the site and the distance from markets for the power.[4]

In 1954 the region was opened up by the completion of the Quebec North Shore and Labrador Railway which runs north from Sept-Îles, Quebec 575 km north through Labrador to Schefferville, Quebec. In 1963 a 225 MW generating station was built at Twin Falls to supply power to iron mining industries in western Labrador.

Finance

Canada is a federation where legal authority is split between the federal and provincial governments; natural resources such as lumber, petroleum, and inland waterways are under the jurisdiction of provincial, rather than the national government.[5] Since Labrador had no internal market for the power, it had to negotiate with neighbouring Quebec to export the power. Controversy over the ownership of the Labrador Peninsula added to the difficulties of negotiating between Newfoundland and Quebec. A British colony at the time, Newfoundland disputed ownership with the Canadian province of Quebec. The Judicial Committee of the Privy Council in the United Kingdom ruled in favour of the Dominion of Newfoundland in 1927,[6] an unpopular judgment in Quebec. Member of the Legislative Assembly of Quebec Jacques Dumoulin stated that for Canada, the best judges are Canadians.[7] The Quebec government did not accept this judgement as seen by borders on maps issued in 1939 by the Quebec Ministry of Energy and Natural Resources. Certain newspapers called for a takeover of the territory,[8]

In 1953 the British Newfoundland Development Corporation (BRINCO) was formed[9] for the purpose of exploiting Labrador's resources. In 1958, it created a subsidiary, the Hamilton Falls (Labrador) Corporation Limited to develop the hydroelectric project.[10] Through this subsidiary BRINCO obtained a 99 year monopoly on the sale of Labrador hydro power.[6]

BRINCO could not get funding for the generating station without a guaranteed market for its power. In 1963 Quebec nationalized all of its hydro-electric facilities, and proposed to Newfoundland that it do the same with the Hamilton Falls project, which Premier Joey Smallwood refused.[6] BRINCO explored alternatives to sending the electricity to neighbouring Quebec, including sending it to New Brunswick and asking for federal intervention. This proposal was known as the Anglo-Saxon route [fr].[11] But the only practical solution was to negotiate an agreement with Quebec. By 1969, after 16 years of attempts to finance the project, BRINCO was in dire financial straits whereas Quebec was flush with money, further strengthening Quebec's negotiating position. In the end BRINCO would sell 90 percent of the power to Hydro Quebec, at a fixed price, over 40 years renewable for a further 25.

At the time BRINCO was praised for having built the station with no public money from Newfoundland, while Hydro-Québec assumed nearly all the financial risk. It is unlikely that BRINCO would have found other investors willing to take on that risk.[12] In 1981 it made a good return on the investment at almost no risk.[6]

Construction

 
Churchill Falls as it appeared in 2008, four decades after the water was redirected.

Construction started in July, 1967, at the time the largest civil engineering project ever undertaken in North America[13] and the largest underground power station in the world.

After five years of non-stop work by 6,300 workers and a cost of almost a billion dollars in 1970, the first two generating units began delivering power in 1971, almost half a year ahead of schedule. In 1974 the station went into full-time production.

The 225 MW Twin Falls power station, opened in 1963, was essential to the later power development at Churchill Falls. It helped open up the area and supplied the power required during the construction phase of the project. In the planning stage, however, it became apparent that greater efficiency in the production of electricity could be achieved by diverting the flow of water from the Ossokmanuan Reservoir into the Smallwood Reservoir. Utilizing this water at the Churchill Falls plant enabled approximately three times as much electricity to be produced from the same volume of water. In July 1974 the Twin Falls plant was closed and the water diverted into the Smallwood Reservoir under an agreement with CFLCo.

Technical characteristics

 
One of the main turbines of the station during repairs

The drainage area for the Churchill River includes much of western and central Labrador. Ossokmanuan Reservoir, originally developed as part of the Twin Falls Power System also drains into this system. Churchill River's natural drainage area covers over 60,000 km2 (23,000 sq mi). Dyking Orma and Sail lakes brought the total to 72,000 km2 (28,000 sq mi). Studies showed this drainage area collected 410 mm (16 in) of rainfall plus 391 cm (154 in) of snowfall annually equalling 12.5 cu mi (52 km3) of water per year; more than enough to meet the project's needs.

Total natural drop of the water starting at Ashuanipi Lake and ending at Lake Melville is 1,735 ft (529 m). As a comparison, the water starting 30 km (19 mi) upriver until it enters the power plant drops over 1,000 ft (300 m).

The machine hall, hewn from solid granite, is almost 300 m (980 ft) underground. The 1,800,000 cubic metres of rock excavated was used in roads, building the town site, and as dike material. The hall is about 300 m (980 ft) long, up to 25 m (82 ft) wide and about 50 m (160 ft) high. It houses 11 generating units. The francis turbine wheels are cast of stainless steel and weigh 73 tonnes each.

Water is contained by a reservoir created not by a single large dam, but by a series of 88 dikes that have a total length of 64 km (40 mi). The reservoir, later known as Smallwood Reservoir, covers 5,700 km2 (2,200 sq mi) and can contain more than 1×1012 cu ft (2.8×1010 m3) of water.

Post-construction legal challenges

In Newfoundland and Labrador, the contract between Churchill Falls (Labrador) Corporation (CFLCo) and Hydro-Québec has created a great deal of resentment. Events unforeseen at the time of the 1969 negotiation have greatly increased Hydro-Quebec's profit margin on the fixed price of energy from the station.[9]

The Government of Newfoundland and Labrador has unsuccessfully challenged the 1969 contract in court. In November 2018, the Supreme Court of Canada rejected a bid to force Hydro-Québec to reopen the contract before 2041, deciding that the high profits of Hydro-Québec did not justify re-opening the contract. The majority decision held that the unforeseeability of future energy price increases was a risk that the CFLCo had assumed when the contract was signed and the court could not force the parties to re-open the contract. Gascon additionally said that unforeseeability would justify overturning the contract only if it made the contract less beneficial to one party and not in this case, where it merely made the contract more beneficial to one party (Hydro-Québec).[14][15]

In 2019 Quebec's highest court, the Quebec Court of Appeal ruled that Hydro-Quebec's right to sell Churchill Falls energy had a monthly cap, simplifying the management of water resources for the Lower Churchill Project's Muskrat Falls station.[16]

Newfoundland and Labrador will be able to renegotiate the project in 2041, when the contract expires.[17]

Legal cases brought forward by the Innu Nation

The Churchill Falls hydroelectric plant development was undertaken in the absence of any agreement with the Innu people, but has resulted in significant damage to their traditional territory. The plant caused flooding of over 5,000 km2 (1,900 sq mi), which damaged the habitats of many animals, disrupted caribou migratory routes, and drowned wildlife such as beavers.[18] Furthermore, Innu burial sites and hunting grounds were destroyed, causing irreparable damage to the traditions and livelihoods of the Innu people.[19] A 2016 study commissioned by the Nunatsiavut Government (government of the Labrador Inuit) concluded that the flooding produced methylmercury and could contaminate the local water, food sources, and health of the Innu in the region.[20] These negative impacts infringe on the aboriginal rights and treaty rights of the Innu people.[18]

In February 2010, the Government of Newfoundland and Labrador and the Innu Nation initialed an agreement to compensate for the negative impacts of the Churchill Falls plant. The agreement offered the Labrador Innu hunting rights within 34,000 km2 (13,000 sq mi) of land, plus $2 million (CAD) annually in compensation from Nalcor Energy.[21]

In October 2020, the Innu Nation of Labrador filed a $4 billion (CAD) claim against Hydro-Québec through the Supreme Court of Newfoundland and Labrador.[19] The $4 billion (CAD) figure represents a fair share of Hydro-Quebec's $80 billion (CAD) profits over the 50-years that the hydro-electric plant has been in operation.[22] Furthermore, the Innu Nation have united with First Nations in Canada and the United States to oppose Hydro-Québec's planned transmission line to Massachusetts. A large portion of the energy for this project would be generated in the Churchill Falls hydroelectric plant.[23]

The timing of this lawsuit comes as the Innu Nation seeks to formalise a land claims agreement with the Government of Canada.[24]

See also

References

  1. ^ "Top 10 hydroelectric dams in Canada". Canadian Mining & Energy. Retrieved 2019-07-21.
  2. ^ McCarthy, Shawn (18 November 2010). "Churchill hydro deal signals era of Atlantic co-operation – The Globe and Mail". The Globe and Mail. Toronto.
  3. ^ . Canadian Geographic. Archived from the original on 1 February 2020. Retrieved 17 July 2019.
  4. ^ Green, Peter. "The History of Churchill Falls". Institute of Electrical and Electronics Engineers. Retrieved 17 July 2019.
  5. ^ Thompson, Andrew R. "Resource Rights". The Canadian Encyclopedia. Retrieved 19 July 2019.
  6. ^ a b c d Churchill, Jason L. (1999). "Pragmatic Federalism: The Politics Behind the 1969 Churchill Falls Contract". Newfoundland and Labrador Studies. 15 (2). Retrieved 17 July 2019.
  7. ^ Toupin, Nicholas. "Introduction historique". Assemblée Nationale du Québec. Retrieved 19 July 2019.
  8. ^ "Land Grab?". Time (Canadian ed.). 22 September 1947. p. 17.
  9. ^ a b Feehan, James P.; Baker, Melvin (2005). "The Renewal Clause in the Churchill Falls Contract: The Origins of a Coming Crisis" (PDF). Dalhousie Law Journal. Retrieved 17 July 2019.
  10. ^ Cleo Research Associates (2003). "Power Politics and Questions of Political Will: A History of Hydroelectric Development in Labrador's Churchill River Basin, 1949-2002" (PDF). Royal Commission on Renewing and Strengthening Our Place in Canada. Retrieved 17 July 2019.
  11. ^ Martin, Melanie (2006). "The 1969 Contract". Heritage Newfoundland and Labrador. Retrieved 2 March 2022. he explored the possibility of transmitting Churchill Falls power to the Maritimes and New England by the so-called Anglo-Saxon route.
  12. ^ Feehan, James (2009). "The Churchill Falls Project: What Happened and What's to Come" (PDF). Memorial University of Newfoundland. Retrieved 18 July 2019.
  13. ^ James Marsh (2010). "Churchill Falls". The Canadian Encyclopedia. Retrieved June 9, 2010.
  14. ^ Harris, Kathleen (November 2, 2018). "Supreme Court rejects Churchill Falls Corp.'s bid to reopen energy deal with Hydro-Québec". CBC News. Retrieved November 3, 2018.
  15. ^ "Churchill Falls (Labrador) Corp. v. Hydro‑Québec - SCC Cases (Lexum)". scc-csc.lexum.com. November 2, 2018. Retrieved November 3, 2018.
  16. ^ "Quebec's top court rules for N.L. in Churchill Falls dispute with Hydro-Québec". CBC. Retrieved 19 July 2019.
  17. ^ Baril, Hélène (4 February 2009). . La Presse (in French). Montreal. Archived from the original on 17 April 2009. Retrieved 2009-12-14.
  18. ^ a b "Innu Nation Claim against Hydro-Quebec". OKT | Olthuis Kleer Townshend LLP. Retrieved 2022-02-13.
  19. ^ a b "Fifty-year-old bill comes due". Past Due. 2022. Retrieved 13 February 2022.
  20. ^ "First Nations in Canada Urge Northeast U.S. to Reject Greenwashed Canadian Hydropower". www.culturalsurvival.org. Retrieved 2022-02-13.
  21. ^ "Lower Churchill Project - Agreement with Innu Nation of Labrador | Government of Newfoundland and Labrador". www.gov.nl.ca. Retrieved 2022-02-13.
  22. ^ Quinn, Mark (6 October 2020). "Innu Nation suing over disruption to land and culture caused by Churchill Falls project". CBC News. Retrieved 13 February 2022.
  23. ^ "News release (March 30, 2021)". Retrieved 2022-02-13.
  24. ^ Richardson, Lindsay (2020-10-08). "Innu of Labrador launch $4B lawsuit against Hydro Quebec". APTN News. Retrieved 2022-02-13.

External links

  • Churchill Falls Hydroelectric project overview at the Institute of Electrical and Electronics Engineers
  • Nalcor's website

churchill, falls, generating, station, hydroelectric, underground, power, station, labrador, sixteenth, largest, world, second, largest, canada, after, robert, bourassa, generating, station, northwestern, quebec, location, newfoundland, labradorlocationnewfoun. The Churchill Falls Generating Station is a hydroelectric underground power station in Labrador At 5 428 MW it is the sixteenth largest in the world and the second largest in Canada after the Robert Bourassa generating station in northwestern Quebec Churchill Falls Generating StationLocation of Churchill Falls Generating Station in Newfoundland and LabradorLocationNewfoundland and Labrador CanadaCoordinates53 31 43 45 N 63 57 57 15 W 53 5287361 N 63 9658750 W 53 5287361 63 9658750 Coordinates 53 31 43 45 N 63 57 57 15 W 53 5287361 N 63 9658750 W 53 5287361 63 9658750Construction began1967Opening date1974Construction cost946 million CADOwner s CFLCoDam and spillwaysType of dam88 rock filled dikesImpoundsChurchill RiverLength64 km 40 mi Dam volume2 200 000 m3 2 900 000 cu yd ReservoirCreatesSmallwood ReservoirOssokmanuan ReservoirTotal capacity32 64 km3 1 153 1012 cu ft Catchment area71 750 km2 27 700 sq mi Surface area6 988 km2 2 698 sq mi Power StationOperator s CFLCoCommission date1971 74Hydraulic head312 4 m 1 025 ft Turbines11Installed capacity5 428 MWCapacity factor73 6 Annual generation35 000 GWh 130 000 TJ Websitenalcorenergy wbr com wbr nalcor operations wbr churchill falls wbr Rather than a single large dam the plant s reservoir is contained by 88 dykes totalling 64 km in length Now called the Smallwood Reservoir it has a capacity of 33 cubic kilometres in a catchment area of about 72 000 square kilometres an area larger than the Republic of Ireland It drops over 305 metres to the site of the plant s 11 turbines The plant s power house was hewn from solid granite 300 metres underground It is about 300 metres long and as high as a 15 story building 1 The station cost almost a billion Canadian dollars to build in 1970 Commissioned from 1971 to 1974 it is owned and operated by the Churchill Falls Labrador Corporation Limited a joint venture between Nalcor Energy 65 8 and Hydro Quebec 34 2 Workers at the station live in the purpose built company town of Churchill Falls The ongoing Lower Churchill Project is a joint venture between Nalcor and Emera 2 to develop the remaining 35 percent of the Churchill River basin Contents 1 Toponymy 2 History 2 1 Early investigations 2 2 Finance 2 3 Construction 3 Technical characteristics 4 Post construction legal challenges 4 1 Legal cases brought forward by the Innu Nation 5 See also 6 References 7 External linksToponymy EditOriginally called the Mishtashipu Big River 3 by the Innu in 1821 the river was called Hamilton by Captain William Martin of HM brig Clinker after Sir Charles Hamilton the Governor of Newfoundland from 1818 to 1823 The waterfall itself was called Grand Falls In 1965 after the death of Winston Churchill the falls river town and generating station were all renamed again History EditEarly investigations Edit In 1931 the Dominion of Newfoundland issued a 30 cent stamp depicting the falls In 1915 Wilfred Thibaudeau surveyed the Labrador Plateau He designed a channel scheme to divert water before it arrived at the falls The scheme would use the natural capacity of the drainage basin which covers over 23 300 sq mi 60 000 km2 eliminating the need for the construction of dams The advantage of the site was the river s drop of more than 300 metres in less than 32 km and steady supply of water These findings were confirmed in a 1947 survey but development did not proceed due to the remoteness of the site and the distance from markets for the power 4 In 1954 the region was opened up by the completion of the Quebec North Shore and Labrador Railway which runs north from Sept Iles Quebec 575 km north through Labrador to Schefferville Quebec In 1963 a 225 MW generating station was built at Twin Falls to supply power to iron mining industries in western Labrador Finance Edit Canada is a federation where legal authority is split between the federal and provincial governments natural resources such as lumber petroleum and inland waterways are under the jurisdiction of provincial rather than the national government 5 Since Labrador had no internal market for the power it had to negotiate with neighbouring Quebec to export the power Controversy over the ownership of the Labrador Peninsula added to the difficulties of negotiating between Newfoundland and Quebec A British colony at the time Newfoundland disputed ownership with the Canadian province of Quebec The Judicial Committee of the Privy Council in the United Kingdom ruled in favour of the Dominion of Newfoundland in 1927 6 an unpopular judgment in Quebec Member of the Legislative Assembly of Quebec Jacques Dumoulin stated that for Canada the best judges are Canadians 7 The Quebec government did not accept this judgement as seen by borders on maps issued in 1939 by the Quebec Ministry of Energy and Natural Resources Certain newspapers called for a takeover of the territory 8 In 1953 the British Newfoundland Development Corporation BRINCO was formed 9 for the purpose of exploiting Labrador s resources In 1958 it created a subsidiary the Hamilton Falls Labrador Corporation Limited to develop the hydroelectric project 10 Through this subsidiary BRINCO obtained a 99 year monopoly on the sale of Labrador hydro power 6 BRINCO could not get funding for the generating station without a guaranteed market for its power In 1963 Quebec nationalized all of its hydro electric facilities and proposed to Newfoundland that it do the same with the Hamilton Falls project which Premier Joey Smallwood refused 6 BRINCO explored alternatives to sending the electricity to neighbouring Quebec including sending it to New Brunswick and asking for federal intervention This proposal was known as the Anglo Saxon route fr 11 But the only practical solution was to negotiate an agreement with Quebec By 1969 after 16 years of attempts to finance the project BRINCO was in dire financial straits whereas Quebec was flush with money further strengthening Quebec s negotiating position In the end BRINCO would sell 90 percent of the power to Hydro Quebec at a fixed price over 40 years renewable for a further 25 At the time BRINCO was praised for having built the station with no public money from Newfoundland while Hydro Quebec assumed nearly all the financial risk It is unlikely that BRINCO would have found other investors willing to take on that risk 12 In 1981 it made a good return on the investment at almost no risk 6 Construction Edit Churchill Falls as it appeared in 2008 four decades after the water was redirected Construction started in July 1967 at the time the largest civil engineering project ever undertaken in North America 13 and the largest underground power station in the world After five years of non stop work by 6 300 workers and a cost of almost a billion dollars in 1970 the first two generating units began delivering power in 1971 almost half a year ahead of schedule In 1974 the station went into full time production The 225 MW Twin Falls power station opened in 1963 was essential to the later power development at Churchill Falls It helped open up the area and supplied the power required during the construction phase of the project In the planning stage however it became apparent that greater efficiency in the production of electricity could be achieved by diverting the flow of water from the Ossokmanuan Reservoir into the Smallwood Reservoir Utilizing this water at the Churchill Falls plant enabled approximately three times as much electricity to be produced from the same volume of water In July 1974 the Twin Falls plant was closed and the water diverted into the Smallwood Reservoir under an agreement with CFLCo Technical characteristics Edit One of the main turbines of the station during repairs The drainage area for the Churchill River includes much of western and central Labrador Ossokmanuan Reservoir originally developed as part of the Twin Falls Power System also drains into this system Churchill River s natural drainage area covers over 60 000 km2 23 000 sq mi Dyking Orma and Sail lakes brought the total to 72 000 km2 28 000 sq mi Studies showed this drainage area collected 410 mm 16 in of rainfall plus 391 cm 154 in of snowfall annually equalling 12 5 cu mi 52 km3 of water per year more than enough to meet the project s needs Total natural drop of the water starting at Ashuanipi Lake and ending at Lake Melville is 1 735 ft 529 m As a comparison the water starting 30 km 19 mi upriver until it enters the power plant drops over 1 000 ft 300 m The machine hall hewn from solid granite is almost 300 m 980 ft underground The 1 800 000 cubic metres of rock excavated was used in roads building the town site and as dike material The hall is about 300 m 980 ft long up to 25 m 82 ft wide and about 50 m 160 ft high It houses 11 generating units The francis turbine wheels are cast of stainless steel and weigh 73 tonnes each Water is contained by a reservoir created not by a single large dam but by a series of 88 dikes that have a total length of 64 km 40 mi The reservoir later known as Smallwood Reservoir covers 5 700 km2 2 200 sq mi and can contain more than 1 1012 cu ft 2 8 1010 m3 of water Post construction legal challenges EditIn Newfoundland and Labrador the contract between Churchill Falls Labrador Corporation CFLCo and Hydro Quebec has created a great deal of resentment Events unforeseen at the time of the 1969 negotiation have greatly increased Hydro Quebec s profit margin on the fixed price of energy from the station 9 The Government of Newfoundland and Labrador has unsuccessfully challenged the 1969 contract in court In November 2018 the Supreme Court of Canada rejected a bid to force Hydro Quebec to reopen the contract before 2041 deciding that the high profits of Hydro Quebec did not justify re opening the contract The majority decision held that the unforeseeability of future energy price increases was a risk that the CFLCo had assumed when the contract was signed and the court could not force the parties to re open the contract Gascon additionally said that unforeseeability would justify overturning the contract only if it made the contract less beneficial to one party and not in this case where it merely made the contract more beneficial to one party Hydro Quebec 14 15 In 2019 Quebec s highest court the Quebec Court of Appeal ruled that Hydro Quebec s right to sell Churchill Falls energy had a monthly cap simplifying the management of water resources for the Lower Churchill Project s Muskrat Falls station 16 Newfoundland and Labrador will be able to renegotiate the project in 2041 when the contract expires 17 Legal cases brought forward by the Innu Nation Edit The Churchill Falls hydroelectric plant development was undertaken in the absence of any agreement with the Innu people but has resulted in significant damage to their traditional territory The plant caused flooding of over 5 000 km2 1 900 sq mi which damaged the habitats of many animals disrupted caribou migratory routes and drowned wildlife such as beavers 18 Furthermore Innu burial sites and hunting grounds were destroyed causing irreparable damage to the traditions and livelihoods of the Innu people 19 A 2016 study commissioned by the Nunatsiavut Government government of the Labrador Inuit concluded that the flooding produced methylmercury and could contaminate the local water food sources and health of the Innu in the region 20 These negative impacts infringe on the aboriginal rights and treaty rights of the Innu people 18 In February 2010 the Government of Newfoundland and Labrador and the Innu Nation initialed an agreement to compensate for the negative impacts of the Churchill Falls plant The agreement offered the Labrador Innu hunting rights within 34 000 km2 13 000 sq mi of land plus 2 million CAD annually in compensation from Nalcor Energy 21 In October 2020 the Innu Nation of Labrador filed a 4 billion CAD claim against Hydro Quebec through the Supreme Court of Newfoundland and Labrador 19 The 4 billion CAD figure represents a fair share of Hydro Quebec s 80 billion CAD profits over the 50 years that the hydro electric plant has been in operation 22 Furthermore the Innu Nation have united with First Nations in Canada and the United States to oppose Hydro Quebec s planned transmission line to Massachusetts A large portion of the energy for this project would be generated in the Churchill Falls hydroelectric plant 23 The timing of this lawsuit comes as the Innu Nation seeks to formalise a land claims agreement with the Government of Canada 24 See also EditList of largest power stations in CanadaReferences Edit Top 10 hydroelectric dams in Canada Canadian Mining amp Energy Retrieved 2019 07 21 McCarthy Shawn 18 November 2010 Churchill hydro deal signals era of Atlantic co operation The Globe and Mail The Globe and Mail Toronto Churchill River Canadian Geographic Archived from the original on 1 February 2020 Retrieved 17 July 2019 Green Peter The History of Churchill Falls Institute of Electrical and Electronics Engineers Retrieved 17 July 2019 Thompson Andrew R Resource Rights The Canadian Encyclopedia Retrieved 19 July 2019 a b c d Churchill Jason L 1999 Pragmatic Federalism The Politics Behind the 1969 Churchill Falls Contract Newfoundland and Labrador Studies 15 2 Retrieved 17 July 2019 Toupin Nicholas Introduction historique Assemblee Nationale du Quebec Retrieved 19 July 2019 Land Grab Time Canadian ed 22 September 1947 p 17 a b Feehan James P Baker Melvin 2005 The Renewal Clause in the Churchill Falls Contract The Origins of a Coming Crisis PDF Dalhousie Law Journal Retrieved 17 July 2019 Cleo Research Associates 2003 Power Politics and Questions of Political Will A History of Hydroelectric Development in Labrador s Churchill River Basin 1949 2002 PDF Royal Commission on Renewing and Strengthening Our Place in Canada Retrieved 17 July 2019 Martin Melanie 2006 The 1969 Contract Heritage Newfoundland and Labrador Retrieved 2 March 2022 he explored the possibility of transmitting Churchill Falls power to the Maritimes and New England by the so called Anglo Saxon route Feehan James 2009 The Churchill Falls Project What Happened and What s to Come PDF Memorial University of Newfoundland Retrieved 18 July 2019 James Marsh 2010 Churchill Falls The Canadian Encyclopedia Retrieved June 9 2010 Harris Kathleen November 2 2018 Supreme Court rejects Churchill Falls Corp s bid to reopen energy deal with Hydro Quebec CBC News Retrieved November 3 2018 Churchill Falls Labrador Corp v Hydro Quebec SCC Cases Lexum scc csc lexum com November 2 2018 Retrieved November 3 2018 Quebec s top court rules for N L in Churchill Falls dispute with Hydro Quebec CBC Retrieved 19 July 2019 Baril Helene 4 February 2009 Privatisation d Hydro Quebec Claude Garcia s explique La Presse in French Montreal Archived from the original on 17 April 2009 Retrieved 2009 12 14 a b Innu Nation Claim against Hydro Quebec OKT Olthuis Kleer Townshend LLP Retrieved 2022 02 13 a b Fifty year old bill comes due Past Due 2022 Retrieved 13 February 2022 First Nations in Canada Urge Northeast U S to Reject Greenwashed Canadian Hydropower www culturalsurvival org Retrieved 2022 02 13 Lower Churchill Project Agreement with Innu Nation of Labrador Government of Newfoundland and Labrador www gov nl ca Retrieved 2022 02 13 Quinn Mark 6 October 2020 Innu Nation suing over disruption to land and culture caused by Churchill Falls project CBC News Retrieved 13 February 2022 News release March 30 2021 Retrieved 2022 02 13 Richardson Lindsay 2020 10 08 Innu of Labrador launch 4B lawsuit against Hydro Quebec APTN News Retrieved 2022 02 13 External links EditChurchill Falls Hydroelectric project overview at the Institute of Electrical and Electronics Engineers Nalcor s website Retrieved from https en wikipedia org w index php title Churchill Falls Generating Station amp oldid 1139469581, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.