Beleghata metro station

Beleghata (also known as Metropolitan), is a station of Line 6 of the Kolkata Metro located in Beleghata at Biswa Bangla Sarani, Dhapa of Kolkata, West Bengal, India, serving Beleghata and Metropolitan areas.[2][3][4] The station is elevated beside the Eastern Metropolitan Bypass.[5][6][7][8]

Beleghata

বেলেঘাটা
Kolkata Metro station
General information
LocationBeleghata, Metropolitan, Dhapa, Kolkata - 700105
Coordinates22°33′03″N 88°24′15″E / 22.550703°N 88.404094°E / 22.550703; 88.404094
Operated byMetro Railway, Kolkata
Line(s)Orange Line
Platforms2 side platforms
Tracks2
Construction
Structure typeElevated
ParkingYes
History
OpenedUnder Construction. Expected to open in 2024.[1]
Electrified750 V DC third rail
Services
Preceding station Kolkata Metro Following station
Barun Sengupta
towards Kavi Subhash
Orange Line Gour Kishore Ghosh
towards Jai Hind
Route map
Location
Beleghata metro station

Location edit

This station is located in Beleghata across the service road and footpath on the eastern side of Biswa Bangla Sarani.[9][10][11] The main elevated structure of the station is situated along the service road and footpath adjacent to the New Garia-bound lane of Biswa Bangla Sarani near the end of Maa Flyover.[12][13][14] It is geographically located at 22°33′03″N 88°24′15″E / 22.550703°N 88.404094°E / 22.550703; 88.404094.[15][16][17] The previous station of the station is Barun Sengupta metro station at a distance of 0.9 km (0.56 mi) and the next station is Gour Kishore Ghosh metro station at a distance of 1.7 km (1.1 mi).[18][19][20]

History edit

This project was sanctioned in the budget of 2010–11 by Mamata Banerjee with a project deadline of six years.[21] The execution of this project has been entrusted to RVNL at a cost of Rs 3951.98 crore.[22] It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport. In October 2011, RVNL awarded Gammon India Limited, the tender for the construction of the metro corridor from VIP Bazar Metro Station to Nikko Park (Nalban metro station),[23][24] including stations, as part of Package-II of Line 6.[25] Amongst those metro stations, one near Beleghata was also sanctioned.[26][27][21] In January 2012, the construction of the metro station along with the metro line started.[28] The construction of the station was stopped in 2015 due to land dispute at Tagore Park culvert and a pair of its own footover bridges.[29] The construction of the station started again in May 2017.[30][31][32][33][34][32][35] But the metro couldn't be started due to a viaduct gap over Tagore Park culvert.[36][37]

A week later after inauguration and a day after commercial run started on Kavi Subhash-Hemanta Mukhopadhyay section, in March 2024, RVNL announced the completion of that 76 m viaduct gap after construction of a single-span hanging steel bridge over the disputed Tagore Park culvert.[38][39] This completed the viaduct upto Beleghata metro station, clearing the way for commercial operations at this station.[40][41][42] Trial runs have started in March 2024.[43][44][45]

As of May 2024, for the Beleghata station and the stretch from Hemanta Mukhopadhyay till this station to be inaugurated, construction of safety limit of 90 m (300 ft) metro viaduct beyond the station and footover bridges is yet to be completed.[46] The station is expected to be operational by late 2024.[47][48][49]

Station edit

Structure edit

Beleghata Metro Station is an elevated metro station and has a total of 3 levels. Station entrances and exits begin or end at the first level or ground level. Second-level or L1 or intermediate level houses station fare control, station agents, metro vending machines, crossovers, etc.[50] The third level or L2 or the final level houses the platforms and rail tracks. The station is 200 meters long and 25 meters wide.[51][52]

The station has four entrances and exits. The station is being built with state-of-the-art technology. In addition to staircases, it will be equipped with lifts and escalators. The station also has drinking water and toilet facilities.[51][53]

Layout edit

Beleghata track layout
 
 
 
 
P2
 
 
 
P1
 
 
 
 
Station with two tracks and two side platforms
Layout
G Street Level Exit/Entrance
L1 Mezzanine Fare control, station agent, Metro Card vending machines, crossover
L2 Side platform doors will open on the left  
Southbound Towards →Kavi Subhash→ next station is Barun Sengupta
Northbound Towards ←Jai Hindnext station is Gour Kishore Ghosh
Side platform doors will open on the left  
L2

Power and signal systems edit

Like other stations and lines of Kolkata Metro, this station has 750 volt DC powered third rail.[54] The electricity system will be used to operate the train.[55]

Train movement at this station will be managed by communication based train control signaling system. With this signal system, trains can be operated at intervals of 90 seconds.[56]

Services edit

Services have not started from this station. Currently the station is under construction and is set to be opened in 2024.[30][57]

See also edit

References edit

  1. ^ Chakraborty, Ajanta (20 February 2023). "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja". The Times of India. from the original on 22 February 2023. Retrieved 11 March 2023.
  2. ^ Abbas, Ajmal (30 January 2023). "First phase of Kolkata Metro's Orange Line all set for launch; covers Kavi Subash to Hemanta Mukherjee in 7 minutes". TimesNow. from the original on 30 January 2023. Retrieved 11 March 2023.
  3. ^ Reporter, Staff (30 March 2024). "Kolkata Metro: CCRS Inspects Beleghata-Hemanta Muk. Stretch - Metro Rail News". Retrieved 8 May 2024.
  4. ^ Basu, Kinsuk. "Metro Railway accuses state government of non-cooperation ; government refutes claim". Telegraph India.
  5. ^ "TRIAL RUN FOR TRAFFIC DIVERSION NEAR BELEGHATA METRO STATION STARTED".
  6. ^ "Trial run for traffic diversion near Beleghata Metro started".
  7. ^ "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja". The Times of India. 20 February 2023. ISSN 0971-8257. Retrieved 23 August 2023.
  8. ^ Reporter, Staff (23 August 2023). "Kolkata Metro: GM Reviews Orange Line's Kavi Subhas to Airport Stretch". Metro Rail News. Retrieved 23 August 2023.
  9. ^ "Beleghata-Ruby Section of Kolkata Metro Undergoes Inspection, Here's Why". News18. 30 March 2024. Retrieved 8 May 2024.
  10. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  11. ^ Ghosh, Shreya (26 April 2024). "Kolkata Metro: From Stations To Trial Runs, Here's All About The Ruby-Beleghata Stretch". Curly Tales. Retrieved 8 May 2024.
  12. ^ "Kolkata Metro: বাইপাসের উপর 'প্রায় তৈরি' নয়া মেট্রো স্টেশন, কবে জুড়বে গড়িয়া-এয়ারপোর্ট রুট?". Aaj Tak বাংলা (in Bengali). Retrieved 8 May 2024.
  13. ^ "Kolkata Metro conducts trial runs on Orange Line from Ruby Crossing to Beleghata | Metro Rail Today". Metro Rail Today: Gateway to Rail & Metro Industry. Retrieved 8 May 2024.
  14. ^ "Metro block after Bypass trial chaos". The Times of India. 9 February 2024. ISSN 0971-8257. Retrieved 8 May 2024.
  15. ^ "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja". The Times of India. 20 February 2023. ISSN 0971-8257. Retrieved 8 May 2024.
  16. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  17. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  18. ^ Reporter, Staff (30 April 2024). "Kolkata Metro Conducts Trial Runs On New Orange Line Stretch - Metro Rail News". Retrieved 8 May 2024.
  19. ^ "Kolkata Metro Update: Trial runs to commence on extended Orange line from Ruby Crossing to Beleghata". Financialexpress. 25 April 2024. Retrieved 8 May 2024.
  20. ^ MPost (30 March 2024). "Min & Kolkata Police refute Metro's claim of non-cooperation from state". www.millenniumpost.in. Retrieved 8 May 2024.
  21. ^ ""Seven projects meant to change the face of Calcutta are entangled in a web of land politics and pandering. Metro explores the tunnel vision"". Telegraph india.
  22. ^ "বরুণ সেনগুপ্ত মেট্রো স্টেশনের নির্মাণ কাজ তুঙ্গে, অন্দরমহলটা দেখে নিন". Eisamay (in Bengali). Retrieved 8 May 2024.
  23. ^ "Kolkata Metro Update: Chief Commissioner of Railway Safety inspects Beleghata-Ruby section". Financialexpress. 30 March 2024. Retrieved 8 May 2024.
  24. ^ MP, Team (29 March 2024). "Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay (Ruby) stretch". www.millenniumpost.in. Retrieved 8 May 2024.
  25. ^ (PDF). Archived from the original (PDF) on 19 March 2020. Retrieved 30 March 2024.
  26. ^ ""Road Ahead….. Projects sanctioned"". mtp.indianrailways.gov.in. Retrieved 28 March 2024.
  27. ^ MP, Team (29 March 2024). "Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay (Ruby) stretch". www.millenniumpost.in. Retrieved 8 May 2024.
  28. ^ ""Construction of VIP Bazar station begins after two years"".
  29. ^ a b "Airport-New Garia Metro: Site visit next week to bridge VIP Bazar gap". The Times of India. 12 March 2023. ISSN 0971-8257. Retrieved 28 March 2024.
  30. ^ "Man electrocuted at construction site". The Times of India. 19 February 2024. ISSN 0971-8257. Retrieved 28 March 2024.
  31. ^ a b "শেষের মুখে কলকাতা মেট্রোর আরও ১ স্টেশনের কাজ! ভিতরটা কেমন হল? রইল 'ফার্স্ট লুক'". Hindustantimes Bangla (in Bengali). 28 September 2023. Retrieved 29 March 2023.
  32. ^ "মেট্রোর পথ করতে নোনাডাঙায় সরছে পুরোনো ভিআইপি বাজার". Eisamay (in Bengali). Retrieved 28 March 2024.
  33. ^ "CRS check till Metropolitan: No Ruby ops on Thurs, Fri". The Times of India. 27 March 2024. ISSN 0971-8257. Retrieved 29 March 2024.
  34. ^ "Kolkata: Pipe bridge lifted out of Metro alignment". The Times of India. 15 July 2020. ISSN 0971-8257. Retrieved 29 March 2024.
  35. ^ "Ritwik Ghatak Metro Station: ঋত্বিক ঘটক মেট্রো স্টেশনের কাজ শেষ পর্যায়ে, ফাস্ট লুকেই হাঁকাল ছক্কা! » Najarbandi 24X7". najarbandi.in (in Bengali). 29 September 2023. Retrieved 29 March 2024.
  36. ^ "Hanging bridge on Bypass solves Metro problem at Tagore Park". The Times of India. 3 November 2023. ISSN 0971-8257. Retrieved 29 March 2024.
  37. ^ MP, Team (29 March 2024). "Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay (Ruby) stretch". www.millenniumpost.in. Retrieved 8 May 2024.
  38. ^ PTI (25 April 2024). "Kolkata Metro to start trial runs along Ruby-Beleghata stretch". ThePrint. Retrieved 8 May 2024.
  39. ^ "Traffic starts moving along Tagore Park western flank". The Times of India. ISSN 0971-8257. Retrieved 16 March 2024.
  40. ^ "Kolkata Metro Orange Line Expands for Beleghata: Trials Start - TimesProperty". timesproperty.com. Retrieved 8 May 2024.
  41. ^ SNS (1 April 2024). "Blame game between Kolkata Metro, city police over Orange Line delays". The Statesman. Retrieved 8 May 2024.
  42. ^ "Kolkata Metro: Trial Runs Begin For Seamless Commutes From Ruby Crossing To Beleghata". News18. 26 April 2024. Retrieved 8 May 2024.
  43. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  44. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  45. ^ MP, Team (29 March 2024). "Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay (Ruby) stretch". www.millenniumpost.in. Retrieved 8 May 2024.
  46. ^ "Metro Railway rues delay in getting NOC from police for construction work near Beleghata station". The Telegraph Online.
  47. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  48. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  49. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  50. ^ a b "Ritwik Ghatak Metro Station: ঋত্বিক ঘটক মেট্রো স্টেশন চোখ ধাঁধানো, কাজ প্রায় শেষ, কেমন হল? দেখুন". Aaj Tak বাংলা (in Bengali). Retrieved 29 March 2024.
  51. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
  52. ^ "নিউ গড়িয়া-বিমানবন্দর মেট্রো করিডোরে বড় খবর, নতুন স্টেশনের ছবি দেখুন". Eisamay (in Bengali). Retrieved 29 March 2024.
  53. ^ "Kolkata Metro update: Authorities conduct trial runs on extended Orange line from Ruby Crossing to Beleghata – Details inside". Financialexpress. 28 April 2024. Retrieved 8 May 2024.
  54. ^ MP, Team (29 April 2024). "Trial run by Metro from Hemanta Mukhopadhyay (Ruby) to Beleghata". www.millenniumpost.in. Retrieved 8 May 2024.
  55. ^ PTI (29 March 2024). "Beleghata-Ruby section of Kolkata Metro undergoes inspection". ThePrint. Retrieved 8 May 2024.
  56. ^ "Beleghata-Ruby Section of Kolkata Metro Undergoes Inspection, Here's Why". News18. 30 March 2024. Retrieved 8 May 2024.

beleghata, metro, station, beleghata, also, known, metropolitan, station, line, kolkata, metro, located, beleghata, biswa, bangla, sarani, dhapa, kolkata, west, bengal, india, serving, beleghata, metropolitan, areas, station, elevated, beside, eastern, metropo. Beleghata also known as Metropolitan is a station of Line 6 of the Kolkata Metro located in Beleghata at Biswa Bangla Sarani Dhapa of Kolkata West Bengal India serving Beleghata and Metropolitan areas 2 3 4 The station is elevated beside the Eastern Metropolitan Bypass 5 6 7 8 Beleghataব ল ঘ ট Kolkata Metro stationGeneral informationLocationBeleghata Metropolitan Dhapa Kolkata 700105Coordinates22 33 03 N 88 24 15 E 22 550703 N 88 404094 E 22 550703 88 404094Operated byMetro Railway KolkataLine s Orange LinePlatforms2 side platformsTracks2ConstructionStructure typeElevatedParkingYesHistoryOpenedUnder Construction Expected to open in 2024 1 Electrified750 V DC third railServicesPreceding station Kolkata Metro Following station Barun Senguptatowards Kavi Subhash Orange Line Gour Kishore Ghoshtowards Jai HindRoute mapLegend Sealdah South New Garia Depot Kavi Subhash Blue Line Blue Line Line 1 Sealdah South Satyajit Ray Jyotirindra Nandi Panchanangram Canal Kavi Sukanta Rashbehari Avenue Hemanta Mukhopadhyay VIP Bazar Ritwik Ghatak Storm Water Outlet Canal Barun Sengupta Beleghata Captain Bhery Eastern Metropolitan Bypass Gour Kishore Ghosh Nalban 3rd Avenue IT Centre Green Line Green Line Line 2 Nabadiganta Keshtopur Canal Nazrul Tirtha Swapnabhor Biswa Bangla Convention Centre Keshtopur Canal Shiksha Tirtha Mother s Wax Museum Eco Park Mangaldeep City Centre 2 Rajarhat Road Chinar Park Green Line Line 2 VIP Road Green Line Yellow Line Line 4 Jai Hind Yellow Line Airport Depot Yellow Line Line 4 Location Beleghata metro station Contents 1 Location 2 History 3 Station 3 1 Structure 3 2 Layout 4 Power and signal systems 5 Services 6 See also 7 ReferencesLocation editThis station is located in Beleghata across the service road and footpath on the eastern side of Biswa Bangla Sarani 9 10 11 The main elevated structure of the station is situated along the service road and footpath adjacent to the New Garia bound lane of Biswa Bangla Sarani near the end of Maa Flyover 12 13 14 It is geographically located at 22 33 03 N 88 24 15 E 22 550703 N 88 404094 E 22 550703 88 404094 15 16 17 The previous station of the station is Barun Sengupta metro station at a distance of 0 9 km 0 56 mi and the next station is Gour Kishore Ghosh metro station at a distance of 1 7 km 1 1 mi 18 19 20 History editThis project was sanctioned in the budget of 2010 11 by Mamata Banerjee with a project deadline of six years 21 The execution of this project has been entrusted to RVNL at a cost of Rs 3951 98 crore 22 It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport In October 2011 RVNL awarded Gammon India Limited the tender for the construction of the metro corridor from VIP Bazar Metro Station to Nikko Park Nalban metro station 23 24 including stations as part of Package II of Line 6 25 Amongst those metro stations one near Beleghata was also sanctioned 26 27 21 In January 2012 the construction of the metro station along with the metro line started 28 The construction of the station was stopped in 2015 due to land dispute at Tagore Park culvert and a pair of its own footover bridges 29 The construction of the station started again in May 2017 30 31 32 33 34 32 35 But the metro couldn t be started due to a viaduct gap over Tagore Park culvert 36 37 A week later after inauguration and a day after commercial run started on Kavi Subhash Hemanta Mukhopadhyay section in March 2024 RVNL announced the completion of that 76 m viaduct gap after construction of a single span hanging steel bridge over the disputed Tagore Park culvert 38 39 This completed the viaduct upto Beleghata metro station clearing the way for commercial operations at this station 40 41 42 Trial runs have started in March 2024 43 44 45 As of May 2024 for the Beleghata station and the stretch from Hemanta Mukhopadhyay till this station to be inaugurated construction of safety limit of 90 m 300 ft metro viaduct beyond the station and footover bridges is yet to be completed 46 The station is expected to be operational by late 2024 47 48 49 Station editStructure edit Beleghata Metro Station is an elevated metro station and has a total of 3 levels Station entrances and exits begin or end at the first level or ground level Second level or L1 or intermediate level houses station fare control station agents metro vending machines crossovers etc 50 The third level or L2 or the final level houses the platforms and rail tracks The station is 200 meters long and 25 meters wide 51 52 The station has four entrances and exits The station is being built with state of the art technology In addition to staircases it will be equipped with lifts and escalators The station also has drinking water and toilet facilities 51 53 Layout edit Beleghata track layout Legend nbsp nbsp nbsp nbsp to Gour Kishore Ghosh P2 nbsp nbsp nbsp P1 nbsp nbsp nbsp to Barun Sengupta nbsp Station with two tracks and two side platforms Layout G Street Level Exit Entrance L1 Mezzanine Fare control station agent Metro Card vending machines crossover L2 Side platform doors will open on the left nbsp Southbound Towards Kavi Subhash next station is Barun Sengupta Northbound Towards Jai Hind next station is Gour Kishore Ghosh Side platform doors will open on the left nbsp L2Power and signal systems editLike other stations and lines of Kolkata Metro this station has 750 volt DC powered third rail 54 The electricity system will be used to operate the train 55 Train movement at this station will be managed by communication based train control signaling system With this signal system trains can be operated at intervals of 90 seconds 56 Services editServices have not started from this station Currently the station is under construction and is set to be opened in 2024 30 57 See also editList of Kolkata Metro stationsReferences edit Chakraborty Ajanta 20 February 2023 Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja The Times of India Archived from the original on 22 February 2023 Retrieved 11 March 2023 Abbas Ajmal 30 January 2023 First phase of Kolkata Metro s Orange Line all set for launch covers Kavi Subash to Hemanta Mukherjee in 7 minutes TimesNow Archived from the original on 30 January 2023 Retrieved 11 March 2023 Reporter Staff 30 March 2024 Kolkata Metro CCRS Inspects Beleghata Hemanta Muk Stretch Metro Rail News Retrieved 8 May 2024 Basu Kinsuk Metro Railway accuses state government of non cooperation government refutes claim Telegraph India TRIAL RUN FOR TRAFFIC DIVERSION NEAR BELEGHATA METRO STATION STARTED Trial run for traffic diversion near Beleghata Metro started Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja The Times of India 20 February 2023 ISSN 0971 8257 Retrieved 23 August 2023 Reporter Staff 23 August 2023 Kolkata Metro GM Reviews Orange Line s Kavi Subhas to Airport Stretch Metro Rail News Retrieved 23 August 2023 Beleghata Ruby Section of Kolkata Metro Undergoes Inspection Here s Why News18 30 March 2024 Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 Ghosh Shreya 26 April 2024 Kolkata Metro From Stations To Trial Runs Here s All About The Ruby Beleghata Stretch Curly Tales Retrieved 8 May 2024 Kolkata Metro ব ইপ স র উপর প র য ত র নয ম ট র স ট শন কব জ ড ব গড য এয রপ র ট র ট Aaj Tak ব ল in Bengali Retrieved 8 May 2024 Kolkata Metro conducts trial runs on Orange Line from Ruby Crossing to Beleghata Metro Rail Today Metro Rail Today Gateway to Rail amp Metro Industry Retrieved 8 May 2024 Metro block after Bypass trial chaos The Times of India 9 February 2024 ISSN 0971 8257 Retrieved 8 May 2024 Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja The Times of India 20 February 2023 ISSN 0971 8257 Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 Reporter Staff 30 April 2024 Kolkata Metro Conducts Trial Runs On New Orange Line Stretch Metro Rail News Retrieved 8 May 2024 Kolkata Metro Update Trial runs to commence on extended Orange line from Ruby Crossing to Beleghata Financialexpress 25 April 2024 Retrieved 8 May 2024 MPost 30 March 2024 Min amp Kolkata Police refute Metro s claim of non cooperation from state www millenniumpost in Retrieved 8 May 2024 a b Rail set to take over East West The Telegraph Calcutta India 8 February 2011 Archived from the original on 13 February 2011 Seven projects meant to change the face of Calcutta are entangled in a web of land politics and pandering Metro explores the tunnel vision Telegraph india বর ণ স নগ প ত ম ট র স ট শন র ন র ম ণ ক জ ত ঙ গ অন দরমহলট দ খ ন ন Eisamay in Bengali Retrieved 8 May 2024 Kolkata Metro Update Chief Commissioner of Railway Safety inspects Beleghata Ruby section Financialexpress 30 March 2024 Retrieved 8 May 2024 MP Team 29 March 2024 Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay Ruby stretch www millenniumpost in Retrieved 8 May 2024 Details of tenders contracts PDF Archived from the original PDF on 19 March 2020 Retrieved 30 March 2024 Road Ahead Projects sanctioned mtp indianrailways gov in Retrieved 28 March 2024 MP Team 29 March 2024 Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay Ruby stretch www millenniumpost in Retrieved 8 May 2024 Construction of VIP Bazar station begins after two years a b Airport New Garia Metro Site visit next week to bridge VIP Bazar gap The Times of India 12 March 2023 ISSN 0971 8257 Retrieved 28 March 2024 Man electrocuted at construction site The Times of India 19 February 2024 ISSN 0971 8257 Retrieved 28 March 2024 a b শ ষ র ম খ কলক ত ম ট র র আরও ১ স ট শন র ক জ ভ তরট ক মন হল রইল ফ র স ট ল ক Hindustantimes Bangla in Bengali 28 September 2023 Retrieved 29 March 2023 ম ট র র পথ করত ন ন ড ঙ য সরছ প র ন ভ আইপ ব জ র Eisamay in Bengali Retrieved 28 March 2024 CRS check till Metropolitan No Ruby ops on Thurs Fri The Times of India 27 March 2024 ISSN 0971 8257 Retrieved 29 March 2024 Kolkata Pipe bridge lifted out of Metro alignment The Times of India 15 July 2020 ISSN 0971 8257 Retrieved 29 March 2024 Ritwik Ghatak Metro Station ঋত ব ক ঘটক ম ট র স ট শন র ক জ শ ষ পর য য ফ স ট ল ক ই হ ক ল ছক ক Najarbandi 24X7 najarbandi in in Bengali 29 September 2023 Retrieved 29 March 2024 Hanging bridge on Bypass solves Metro problem at Tagore Park The Times of India 3 November 2023 ISSN 0971 8257 Retrieved 29 March 2024 MP Team 29 March 2024 Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay Ruby stretch www millenniumpost in Retrieved 8 May 2024 PTI 25 April 2024 Kolkata Metro to start trial runs along Ruby Beleghata stretch ThePrint Retrieved 8 May 2024 Traffic starts moving along Tagore Park western flank The Times of India ISSN 0971 8257 Retrieved 16 March 2024 Kolkata Metro Orange Line Expands for Beleghata Trials Start TimesProperty timesproperty com Retrieved 8 May 2024 SNS 1 April 2024 Blame game between Kolkata Metro city police over Orange Line delays The Statesman Retrieved 8 May 2024 Kolkata Metro Trial Runs Begin For Seamless Commutes From Ruby Crossing To Beleghata News18 26 April 2024 Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 MP Team 29 March 2024 Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay Ruby stretch www millenniumpost in Retrieved 8 May 2024 Metro Railway rues delay in getting NOC from police for construction work near Beleghata station The Telegraph Online Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 a b Ritwik Ghatak Metro Station ঋত ব ক ঘটক ম ট র স ট শন চ খ ধ ধ ন ক জ প র য শ ষ ক মন হল দ খ ন Aaj Tak ব ল in Bengali Retrieved 29 March 2024 Metro Railway Kolkata Indian Railways Portal mtp indianrailways gov in Retrieved 8 May 2024 ন উ গড য ব ম নবন দর ম ট র কর ড র বড খবর নত ন স ট শন র ছব দ খ ন Eisamay in Bengali Retrieved 29 March 2024 Kolkata Metro update Authorities conduct trial runs on extended Orange line from Ruby Crossing to Beleghata Details inside Financialexpress 28 April 2024 Retrieved 8 May 2024 MP Team 29 April 2024 Trial run by Metro from Hemanta Mukhopadhyay Ruby to Beleghata www millenniumpost in Retrieved 8 May 2024 PTI 29 March 2024 Beleghata Ruby section of Kolkata Metro undergoes inspection ThePrint Retrieved 8 May 2024 Beleghata Ruby Section of Kolkata Metro Undergoes Inspection Here s Why News18 30 March 2024 Retrieved 8 May 2024 nbsp This article about a railway station in the Indian state of West Bengal is a stub You can help Wikipedia by expanding it vte nbsp This Asian rapid transit article is a stub You can help Wikipedia by expanding it vte Retrieved from https en wikipedia org w index php title Beleghata metro station amp oldid 1224454537, wikipedia, wiki, book, books, library,