fbpx
Wikipedia

Vallur Thermal Power Station

Vallur Thermal Power Station is a power plant located in Vallur, Thiruvallur district, India. The power plant is operated by NTPC Tamil Nadu Energy Company Limited, a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each.[1]

Vallur Thermal Power Station
Vallur Thermal Power Plant as viewed from new Ennore Creek road bridge
CountryIndia
LocationVallur
Coordinates13°14′2″N 80°18′21″E / 13.23389°N 80.30583°E / 13.23389; 80.30583
StatusOperational
Construction beganSeptember 2007
Commission dateUnit 1: October 2010
Unit 2: March 2011
Unit 3: September 2012
Construction cost91.93 billion
Owner(s)NTPC Limited and TANGEDCO
Operator(s)NTPC Tamil Nadu Energy Company Limited
Thermal power station
Primary fuelCoal
Power generation
Units operational3 x 500 megawatts (670,000 hp)
Nameplate capacity1,500 megawatts (2,000,000 hp)
External links
CommonsRelated media on Commons

In January 2014, the units in the power plant achieved a record generation of 24.09 million units (kWh[2]) of electricity.[3][dubious ] The project adds nearly 24 million units a day to the grid. Tamil Nadu is the major beneficiary of power generated from this facility (about 750 MW), while some of it is supplied to Andhra Pradesh, Karnataka, Kerala, and Puducherry.[4]

The plant will consume 4.62 megatonnes (4,550,000 long tons; 5,090,000 short tons) of coal a year. Coal for the plant will be brought from Orissa through ship to Ennore Port, from where it will be transported by pipe conveyor crossing Ennore Creek.[4]

Location edit

The power plant is located on a triangular tract of land between Ennore Creek and Athipattu Pudhunagar railway station, southwest of Ennore Port, Chennai.

Construction edit

The plant was established under the mega power project policy.[4] The erstwhile Tamil Nadu Electricity Board (TNEB) and the NTPC, in a joint venture, formed the NTPC Tamil Nadu Energy Company Limited. The foundation stone for the Vallur thermal plant was laid on 5 September 2007, with an estimated cost of 80 billion (€100 million),[5] and the 19,900-million main plant package to supply steam generators and turbine for stage I was awarded to Bharat Heavy Electricals Limited (BHEL), a state-run power equipments manufacturer, on 13 August 2007.[6][7] The projected was constructed in two phases: phase I with two 500 MW units at a cost of 54 billion and phase II with one 500 MW unit at a cost of 30 billion. Initially expected to be operational by 2010, the project was delayed due to the late implementation of the coal-handling facility established by the BHEL.[5] Erection of the boiler column began on 5 January 2009.[6]

In September 2009, the 130 million contract to supply units for Vallur was given to BHEL, which supplied and installed steam generator and steam turbine packages. BHEL was responsible for the design, engineering manufacture, supply, erection and commissioning of the steam generators, turbine generators, electrostatic precipitators and associated auxiliaries, and controls and instrumentation systems in the plant.[4]

 
NTECL Power Plant in Vallur

The 216-tonne (213-long-ton; 238-short-ton) boiler drum of Unit I was erected in June 2010. Unit I was commissioned in March 2012 but operating at full capacity was delayed further due to problems with coal-handling facilities. Independent works on phase II began in 2010.[4]

The first, second and third units were synchronised with the grid on 9 March 2012, 26 February 2013 and 28 February 2014, respectively.[8] The total cost of the project without IDC was 91,930 million.[8] The plant commenced its commercial operation on 29 November 2012, with the operation of its first unit. The second unit commenced its commercial operations on 25 August 2013,[8] while that of the third unit was commenced on 28 February 2014.[9]

Cost and Finance edit

The cost of phase I was 54 billion ($1.15 billion) and that of phase II was 30 billion ($639 million). The debt equity ratio of the project is 7:3. The Rural Electrification Corporation (REC) sanctioned 38 billion ($809 million) to meet the entire debt portion of the project. REC advanced a loan of 21 billion ($447 million) for the second phase in April 2010.[4][unreliable source?]

Technology and operations edit

The boiler systems at the plant consists of single- or two-pass type, with front/rear/side mill layout, which can have single/bi-drum arrangement with natural or controlled circulation. There is constant or sliding pressure operation, and hot or cold primary air systems. Steam turbine operates at a speeds of 3,000 rpm. The main steam is at 130–250 bars (13,000–25,000 kPa) at 500–540 °C (930–1,000 °F). Steam reheat is at 30–70 bars (3,000–7,000 kPa) and 500–600 °C (930–1,100 °F). The back pressure is between 20 and 300 millibars (20 and 300 hPa).[4]

The plant has six induced draft cooling towers (IDCTs), which have a capacity of 30,000 cubic metres per hour (1,100,000 cu ft/h) with nine cells of 14 by 21 metres (46 ft × 69 ft) each.[4] The IDCTs use seawater, which is drawn from the intake channel of North Chennai Thermal Power Station, and fresh water requirement is met from a desalination plant. The plant has adopted closed cycle re-circulating type cooling water system for its operations.[4][10]

The coal conveyor system in the plant includes a 4.4-kilometre (2.7 mi)-long pipe conveyor with a capacity of 4,000 tonnes per hour (150,000 lb/min), which is the world's largest pipe conveyor.[8]

The plant requires 13,400 tonnes (13,200 long tons; 14,800 short tons) of coal per day. Domestic coalfields supply 53 percent of the need, and the remainder through coal imports.[11]

Installed capacity edit

Following is the unit-wise capacity of the 1,500 megawatts (2,000,000 hp) plant.

Stage Unit Number Installed Capacity (MW) Date of Commissioning Status
Stage I 1 500 29 November 2012 Running[8]
Stage I 2 500 25 August 2013 Running[12]
Stage I 3 500 28 February 2014 Running[9]

The share of Tamil Nadu would be 375 megawatts (503,000 hp) from each of the three units in the plant.[5]

Environmental Impact edit

 
NTPC Tamil Nadu Energy Station at night

The Vallur Thermal Power Station is environmentally friendly & non-polluting plant.[citation needed]

See also edit

References edit

  1. ^ https://www.tangedco.gov.in/linkpdf/vallur.pdf[bare URL PDF]
  2. ^ "Get enlightened about electricity". The Financial Express. 20 December 2004. Archived from the original on 8 September 2012. Retrieved 29 November 2009.
  3. ^ PTI (8 March 2014). "Power generation suspended from second unit of Vallur plant". Business Line. Chennai: The Hindu. Retrieved 30 March 2014.
  4. ^ a b c d e f g h i "Vallur Conventional Thermal Power Plant, India". Power-technology.com. Retrieved 30 March 2014.
  5. ^ a b c Ramakrishnan, T. (22 August 2012). "Vallur project to start power generation by October". The Hindu. Chennai. Retrieved 30 March 2014.
  6. ^ a b . The Hindu. Chennai. 29 March 2009. Archived from the original on 22 June 2011. Retrieved 30 March 2014.
  7. ^ "BHEL bags order for Vallur thermal power project". Live Mint. Tiruchirapalli: LiveMint.com. 5 September 2007. Retrieved 30 March 2014.
  8. ^ a b c d e "Vallur Thermal Power Project". Tangedco.gov.in. Retrieved 30 March 2014.
  9. ^ a b "NTPC's Unit III of 500 MW of Vallur Thermal Power Project commissioned". MoneyControl.com. 1 March 2014. Retrieved 30 March 2014.
  10. ^ "NTPC to set up 500 MW Vallur Thermal Power Project Stage-I, Phase-II at Thiruvallur". ThermalPowerIndustryFocus.net. Retrieved 30 March 2014.
  11. ^ Jagannath, G. (22 December 2013). "Coal shortage affects Unit-1 of Vallur plant". Deccan Chronicle. Chennai. Retrieved 30 March 2014.
  12. ^ Jagannath, G. (27 August 2013). "Vallur unit II to give power relief for Tamil Nadu". Deccan Chronicle. Chennai. Retrieved 30 March 2014.

External links edit

  • Vallur Thermal Power Project on TANGEDCO website
  • Page in Global Energy Observatory

vallur, thermal, power, station, power, plant, located, vallur, thiruvallur, district, india, power, plant, operated, ntpc, tamil, nadu, energy, company, limited, joint, venture, between, ntpc, limited, tangedco, three, units, with, each, vallur, thermal, powe. Vallur Thermal Power Station is a power plant located in Vallur Thiruvallur district India The power plant is operated by NTPC Tamil Nadu Energy Company Limited a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each 1 Vallur Thermal Power StationVallur Thermal Power Plant as viewed from new Ennore Creek road bridgeCountryIndiaLocationVallurCoordinates13 14 2 N 80 18 21 E 13 23389 N 80 30583 E 13 23389 80 30583StatusOperationalConstruction beganSeptember 2007Commission dateUnit 1 October 2010Unit 2 March 2011Unit 3 September 2012Construction cost 91 93 billionOwner s NTPC Limited and TANGEDCOOperator s NTPC Tamil Nadu Energy Company LimitedThermal power stationPrimary fuelCoalPower generationUnits operational3 x 500 megawatts 670 000 hp Nameplate capacity1 500 megawatts 2 000 000 hp External linksCommonsRelated media on Commons edit on Wikidata In January 2014 the units in the power plant achieved a record generation of 24 09 million units kWh 2 of electricity 3 dubious discuss The project adds nearly 24 million units a day to the grid Tamil Nadu is the major beneficiary of power generated from this facility about 750 MW while some of it is supplied to Andhra Pradesh Karnataka Kerala and Puducherry 4 The plant will consume 4 62 megatonnes 4 550 000 long tons 5 090 000 short tons of coal a year Coal for the plant will be brought from Orissa through ship to Ennore Port from where it will be transported by pipe conveyor crossing Ennore Creek 4 Contents 1 Location 2 Construction 3 Cost and Finance 4 Technology and operations 4 1 Installed capacity 5 Environmental Impact 6 See also 7 References 8 External linksLocation editThe power plant is located on a triangular tract of land between Ennore Creek and Athipattu Pudhunagar railway station southwest of Ennore Port Chennai Construction editThe plant was established under the mega power project policy 4 The erstwhile Tamil Nadu Electricity Board TNEB and the NTPC in a joint venture formed the NTPC Tamil Nadu Energy Company Limited The foundation stone for the Vallur thermal plant was laid on 5 September 2007 with an estimated cost of 80 billion 100 million 5 and the 19 900 million main plant package to supply steam generators and turbine for stage I was awarded to Bharat Heavy Electricals Limited BHEL a state run power equipments manufacturer on 13 August 2007 6 7 The projected was constructed in two phases phase I with two 500 MW units at a cost of 54 billion and phase II with one 500 MW unit at a cost of 30 billion Initially expected to be operational by 2010 the project was delayed due to the late implementation of the coal handling facility established by the BHEL 5 Erection of the boiler column began on 5 January 2009 6 In September 2009 the 130 million contract to supply units for Vallur was given to BHEL which supplied and installed steam generator and steam turbine packages BHEL was responsible for the design engineering manufacture supply erection and commissioning of the steam generators turbine generators electrostatic precipitators and associated auxiliaries and controls and instrumentation systems in the plant 4 nbsp NTECL Power Plant in VallurThe 216 tonne 213 long ton 238 short ton boiler drum of Unit I was erected in June 2010 Unit I was commissioned in March 2012 but operating at full capacity was delayed further due to problems with coal handling facilities Independent works on phase II began in 2010 4 The first second and third units were synchronised with the grid on 9 March 2012 26 February 2013 and 28 February 2014 respectively 8 The total cost of the project without IDC was 91 930 million 8 The plant commenced its commercial operation on 29 November 2012 with the operation of its first unit The second unit commenced its commercial operations on 25 August 2013 8 while that of the third unit was commenced on 28 February 2014 9 Cost and Finance editThe cost of phase I was 54 billion 1 15 billion and that of phase II was 30 billion 639 million The debt equity ratio of the project is 7 3 The Rural Electrification Corporation REC sanctioned 38 billion 809 million to meet the entire debt portion of the project REC advanced a loan of 21 billion 447 million for the second phase in April 2010 4 unreliable source Technology and operations editThe boiler systems at the plant consists of single or two pass type with front rear side mill layout which can have single bi drum arrangement with natural or controlled circulation There is constant or sliding pressure operation and hot or cold primary air systems Steam turbine operates at a speeds of 3 000 rpm The main steam is at 130 250 bars 13 000 25 000 kPa at 500 540 C 930 1 000 F Steam reheat is at 30 70 bars 3 000 7 000 kPa and 500 600 C 930 1 100 F The back pressure is between 20 and 300 millibars 20 and 300 hPa 4 The plant has six induced draft cooling towers IDCTs which have a capacity of 30 000 cubic metres per hour 1 100 000 cu ft h with nine cells of 14 by 21 metres 46 ft 69 ft each 4 The IDCTs use seawater which is drawn from the intake channel of North Chennai Thermal Power Station and fresh water requirement is met from a desalination plant The plant has adopted closed cycle re circulating type cooling water system for its operations 4 10 The coal conveyor system in the plant includes a 4 4 kilometre 2 7 mi long pipe conveyor with a capacity of 4 000 tonnes per hour 150 000 lb min which is the world s largest pipe conveyor 8 The plant requires 13 400 tonnes 13 200 long tons 14 800 short tons of coal per day Domestic coalfields supply 53 percent of the need and the remainder through coal imports 11 Installed capacity edit Following is the unit wise capacity of the 1 500 megawatts 2 000 000 hp plant Stage Unit Number Installed Capacity MW Date of Commissioning StatusStage I 1 500 29 November 2012 Running 8 Stage I 2 500 25 August 2013 Running 12 Stage I 3 500 28 February 2014 Running 9 The share of Tamil Nadu would be 375 megawatts 503 000 hp from each of the three units in the plant 5 Environmental Impact edit nbsp NTPC Tamil Nadu Energy Station at nightThe Vallur Thermal Power Station is environmentally friendly amp non polluting plant citation needed See also edit nbsp Energy portal nbsp India portalList of power stations in IndiaReferences edit https www tangedco gov in linkpdf vallur pdf bare URL PDF Get enlightened about electricity The Financial Express 20 December 2004 Archived from the original on 8 September 2012 Retrieved 29 November 2009 PTI 8 March 2014 Power generation suspended from second unit of Vallur plant Business Line Chennai The Hindu Retrieved 30 March 2014 a b c d e f g h i Vallur Conventional Thermal Power Plant India Power technology com Retrieved 30 March 2014 a b c Ramakrishnan T 22 August 2012 Vallur project to start power generation by October The Hindu Chennai Retrieved 30 March 2014 a b Vallur power plant works progressing The Hindu Chennai 29 March 2009 Archived from the original on 22 June 2011 Retrieved 30 March 2014 BHEL bags order for Vallur thermal power project Live Mint Tiruchirapalli LiveMint com 5 September 2007 Retrieved 30 March 2014 a b c d e Vallur Thermal Power Project Tangedco gov in Retrieved 30 March 2014 a b NTPC s Unit III of 500 MW of Vallur Thermal Power Project commissioned MoneyControl com 1 March 2014 Retrieved 30 March 2014 NTPC to set up 500 MW Vallur Thermal Power Project Stage I Phase II at Thiruvallur ThermalPowerIndustryFocus net Retrieved 30 March 2014 Jagannath G 22 December 2013 Coal shortage affects Unit 1 of Vallur plant Deccan Chronicle Chennai Retrieved 30 March 2014 Jagannath G 27 August 2013 Vallur unit II to give power relief for Tamil Nadu Deccan Chronicle Chennai Retrieved 30 March 2014 nbsp Wikimedia Commons has media related to Vallur Thermal Power Station External links editVallur Thermal Power Project on TANGEDCO website Page in Global Energy Observatory Retrieved from https en wikipedia org w index php title Vallur Thermal Power Station amp oldid 1181237651, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.