fbpx
Wikipedia

Lincs Wind Farm

The Lincs Wind Farm is a 270 MW offshore wind farm 8 kilometres (5.0 mi) off Skegness on the east coast of England. The total cost of the project is estimated at £1 billion including electrical transmission links. The farm was completed in 2013. It is adjacent to the smaller Lynn and Inner Dowsing Wind Farm.

Lincs Wind Farm
Lincs Offshore Wind Farm turbines behind those of Lynn and Inner Dowsing
Country
  • United Kingdom
LocationNorth Sea
Coordinates53°11′00″N 0°29′00″E / 53.1833°N 0.4833°E / 53.1833; 0.4833Coordinates: 53°11′00″N 0°29′00″E / 53.1833°N 0.4833°E / 53.1833; 0.4833
StatusOperational
Construction began2010
Commission date
  • September 2013
Construction cost£1 billion
Owner(s)
Operator(s)
Wind farm
Type
Distance from shore8 km (5.0 mi)
Hub height
  • 100 m (330 ft)
Rotor diameter
  • 120 m (390 ft)
Site area
  • 35 km2 (14 sq mi)
Power generation
Units operational75 × 3.6 MW
Make and modelSiemens Gamesa SWT-3.6-120 (75)
Nameplate capacity
  • 270 MW
External links
CommonsRelated media on Commons

History

Centrica acquired the Lincs Wind Farm project in 2004 from Renewable Energy Systems, in 2008 the company obtained planning permission for the project.[1][2]

In December 2009 Ørsted A/S (then named DONG Energy) and Siemens Project Ventures jointly acquired 50% of the project (25% share each) for £50 million, plus 50% of the capital cost of the project.[3]

Preparatory construction work for the development included the extension of the National Grid electricity substation at Walpole, Norfolk, which began in April 2009.[4][note 1] In June 2010 Siemens obtained the contract for the offshore electrical substation (£101 million).[7] Transmission cables from offshore to onshore electrical substations were installed in 2010–2011.[4][8] Construction of the offshore facilities of the wind farm began in 2011, with the installation of the offshore electricity substation foundations.[9] The Port of Hull was selected as one of the logistics bases for the wind farm turbine installation, supplying wind tower transition pieces. Jack-up barge JB114 arriving at the port in March 2012.[10] Great Yarmouth was also used as a base for the wind farm installation.[11]

Construction of the offshore 33 kV to 132 kV substation (structure sub-contracted to McNulty Offshore Construction/Atkins PLC.[12]) and of the onshore 132 kV to 400 kV substation was completed by April 2012.[13]

In August 2011, the consortia of Ørsted, Siemens, and Centrica began to seek financing for the £1 billion project, committing to providing £166.7, £75 and £333.3 million respectively (£575 million total). In June 2012 the consortia obtained financing for the project with £425 million of nonrecourse debt facilities provided from a consortium of 10 banks. Approximately 75% of the project cost was for the wind farm installation, the remainder for the high voltage electricity transmission link.[14]

Construction began in 2010; installation of the 75-monopile tower foundation by MT Højgaard was completed by June 2012, with the underwater installation phase completed by September 2012.[15] The first generator had been installed by 14 July 2012.[16] The wind farm was scheduled to become operational in the second half of 2012, and be complete by 2013:[17] the final turbine was installed by March 2013;[18] and the wind farm officially opened by Deputy Prime Minister Nick Clegg in August 2013,[19][20] with commissioning complete in September 2013.[21] The license for the electrical transmission link was awarded to TC Lincs OFTO Limited for £308 million in late 2014.[22]

Technical description

The scheme has 250 MW of generating capacity, with an additional 20 MW of turbine generating capacity constructed within the nearby Lynn Wind Farm and Dowsing Wind Farm but connected to the Lincs project transmission system.[23] The project uses 75 three blade 3.6 MW Siemens wind turbines. The wind turbines have 120 metres (390 ft) rotor diameter machines with 58.5 metres (192 ft) blades with a hub height of 100 metres (330 ft) on cylindrical steel towers. The turbines were installed in 10 to 15 metres (33 to 49 ft) water depth, with a spacing of approximately 500 metres (1,600 ft) within a 35 square kilometres (14 sq mi) wind farm.[8]

Transmission of electrical power to land is by 145 kV cables supplied by Nexans. Transmission voltage is 132 kV to land, being increased to 400 kV at Walpole substation for grid connection.[8]

The operation and maintenance base for the wind farm is based at Grimsby.[24]

As at 2019, the windfarm has a rolling capacity factor of 39%.[25] Its levelised cost has been estimated at £166/MWh.[26]

The wind farm has an expected lifespan of 40 years, with electrical equipment and wind turbines expected to be replaced after 20 years. After the end of the project's lifespan the farm is to be decommissioned, including removal of turbines and electrical equipment, and removal of offshore foundations or cut off to seabed level or lower. Connecting cables are not scheduled to be removed.[27]

See also

Notes

  1. ^ Lincs, Docking Shoal and Race Bank wind farms were to share the same onshore cable export route, and onshore substation.[5] The environmental statement for the onshore works was submitted as part of the Lincs Wind Farm application.[6]

References

  1. ^ (PDF) (Press release). Centrica. 21 October 2008. Archived from the original (PDF) on 13 February 2015. Retrieved 4 April 2012.
  2. ^ "Centrica's Lincolnshire development leads offshire windfarm stampeded". Utility Week. 29 October 2008. Archived from the original on 5 May 2013. Retrieved 4 April 2012.
  3. ^ Sources:
    • (Press release). DONG Energy. 23 December 2009. Archived from the original on 25 May 2011. Retrieved 4 April 2012.
    • Wearden, Graeme (28 October 2009). "Market forces breaking news: Centrica to build new wind farm". The Guardian. Retrieved 4 April 2012.
    • "Dong rides the wind". Upstream Online. NHST Media Group. 23 December 2009. Retrieved 1 January 2010.
    • (PDF) (Press release). Centrica. 23 December 2009. Archived from the original (PDF) on 13 February 2015. Retrieved 4 April 2012.
  4. ^ a b (PDF). Centrica. March 2012. Archived from the original (PDF) on 30 April 2015. Retrieved 4 April 2012. The power from Lincs will be transmitted to the National Grid substation at Walpole ... Work to build an extension to the substation commenced in 2010 to enable the power to be transformed from 132 kV to 400 kV ... Civil works commenced at the National Grid substation site at Walpole in April last year
  5. ^ (PDF). Centrica. January 2009. p. 3. Archived from the original (PDF) on 30 April 2015. Retrieved 11 May 2014.
  6. ^ Lincs Offshore Wind Farm ES : Non-Technical Summary (January 2007) pp. 3, 5, 11
  7. ^ "Siemens wins new £101 million order to connect Lincs offshore wind farm to the UK grid" (Press release). Siemens. 28 June 2010. Retrieved 8 June 2012.
  8. ^ a b c "Centrica Lincs Offshore Wind Project, United Kingdom". Power Technology. Retrieved 4 April 2012.
  9. ^ Sources:
    • . Skegness Standard. 1 April 2011. Archived from the original on 11 August 2013. Retrieved 4 April 2012.
    • "Lincs work has begun". This is Lincolnshire. 28 March 2011. Retrieved 4 April 2012.
  10. ^ Sources:
    • "Lincs Wind Farm chooses ABP's Port of Hull as a logistics base for its Lincs offshore wind farm" (Press release). ABP. 26 March 2012. Retrieved 4 April 2012.
    • "Hull's Albert Dock playing key role in North Sea wind farm as renewables era lifts off". This is Lincolnshire. 28 March 2012. Retrieved 4 April 2012.
  11. ^ "Lincs Offshore Wind Farm". www.4coffshore.com. 4C Offshore. Retrieved 24 January 2013.
  12. ^ . www.mcnultyoffshore.com. Archived from the original on 2 February 2014. Retrieved 8 June 2012.
  13. ^ (PDF). Centrica. April 2012. Archived from the original (PDF) on 30 April 2015. Retrieved 8 June 2012. Construction of the 3,000 tonne offshore substation, .. which will transform power from the wind farm from 33 kV to 132 kV .. is now complete, ... It has been built by McNulty, a subcontractor to Siemens Transmission and Distribution Limited, based in South Shields. [..] The testing and energisation of the onshore substation at Walpole, .. is now complete. This substation will boost the power from 132 kV to 400 kV
  14. ^ Sources:
    • Bakewell, Sally (19 August 2011). "Centrica, Siemens Seek Loans For 1 Billion-Pound U.K. Wind Deal". Bloomberg. Retrieved 7 June 2012.
    • Bakewell, Sally (7 June 2012). "Centrica, Siemens Receive $660 Million for U.K. Wind Project". Bloomberg Businessweek. Bloomberg. Retrieved 7 June 2012.
    • McKenna, John (7 June 2012). "Landmark UK offshore deal agreed". Windpower Monthly. Retrieved 7 June 2012.
  15. ^ Sources:
    • "UK: MT Højgaard Installs Last Foundation for Lincs Wind Farm". www.offshorewind.biz. 20 June 2012. Retrieved 27 September 2012.
    • "Turbine Installation Starts as MT Højgaard Completes Work on Lincs Wind Farm, UK". www.offshorewind.biz. 19 September 2012. Retrieved 27 September 2012.
  16. ^ "Lincs Wind Farm August 2012" (PDF). Centrica. August 2012. Retrieved 27 September 2012.[dead link]
  17. ^ "£425 million Lincs Wind Farm project financing agreements finalised" (Press release). Centrica. 7 June 2012. Retrieved 7 June 2012.
  18. ^ "UK: Final turbine installed at Lincs Offshore Wind Farm". worldmaritimenews.com. 3 April 2013. Retrieved 24 January 2014.
  19. ^ "Lincs offshore wind farm officially opened by Deputy Prime Minister Nick Clegg" (PDF) (press release). Siemens. 1 August 2013. Retrieved 24 January 2014.
  20. ^ "Nick Clegg opens Skegness offshore wind farm". BBC News. 2 August 2013. Retrieved 17 February 2016.
  21. ^ "Lincs offshore wind farm: mission complete". Centrica. 27 September 2013. Retrieved 24 January 2014.
  22. ^ "TCP pockets £308m Lincs licence". renews.biz. 4 November 2014. Retrieved 4 November 2014.
  23. ^ (PDF). Centrica. Archived from the original (PDF) on 30 December 2014. Retrieved 4 April 2012.
  24. ^ Sources:
    • "Jobs boost in Grimsby docks wind farm project". BBC News. 4 May 2011. Retrieved 4 April 2012.
    • (PDF) (Press release). Centrica. 4 May 2011. Archived from the original (PDF) on 13 February 2015. Retrieved 4 April 2012.
  25. ^ "Lincs Wind Farm". Renewable Energy Foundation.
  26. ^ Aldersey-Williams, John; Broadbent, Ian; Strachan, Peter (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT". Energy Policy. 128: 25–35.
  27. ^ (PDF). Centrica. December 2010. pp. 1–2. Archived from the original (PDF) on 13 February 2015. Retrieved 4 April 2012.

Sources

Centrica
  • (PDF). Centrica. January 2007. Archived from the original (PDF) on 12 May 2014. Statement for main wind farm area.
    • (PDF). Centrica. May 2010. Archived from the original (PDF) on 8 January 2015. Statement for 6 additional turbines of 20 MW within Lynn & Inner Dowsing farm area.
  • (PDF). Centrica. January 2011. Archived from the original (PDF) on 8 January 2015. Retrieved 7 June 2012. Project timeline and turbine locations (proposed).
  • (PDF). Centrica. Archived from the original (PDF) on 8 January 2015.
Other
  • "Lincs Offshore Wind Farm". www.4coffshore.com.

lincs, wind, farm, offshore, wind, farm, kilometres, skegness, east, coast, england, total, cost, project, estimated, billion, including, electrical, transmission, links, farm, completed, 2013, adjacent, smaller, lynn, inner, dowsing, wind, farm, lincs, offsho. The Lincs Wind Farm is a 270 MW offshore wind farm 8 kilometres 5 0 mi off Skegness on the east coast of England The total cost of the project is estimated at 1 billion including electrical transmission links The farm was completed in 2013 It is adjacent to the smaller Lynn and Inner Dowsing Wind Farm Lincs Wind FarmLincs Offshore Wind Farm turbines behind those of Lynn and Inner DowsingCountryUnited KingdomLocationNorth SeaCoordinates53 11 00 N 0 29 00 E 53 1833 N 0 4833 E 53 1833 0 4833 Coordinates 53 11 00 N 0 29 00 E 53 1833 N 0 4833 E 53 1833 0 4833StatusOperationalConstruction began2010Commission dateSeptember 2013Construction cost 1 billionOwner s Macquarie European Infrastructure Fund 5Green Investment GroupOrstedOperator s OrstedWind farmTypeOffshoreDistance from shore8 km 5 0 mi Hub height100 m 330 ft Rotor diameter120 m 390 ft Site area35 km2 14 sq mi Power generationUnits operational75 3 6 MWMake and modelSiemens Gamesa SWT 3 6 120 75 Nameplate capacity270 MWExternal linksCommonsRelated media on Commons edit on Wikidata Contents 1 History 2 Technical description 3 See also 4 Notes 5 References 5 1 SourcesHistory EditCentrica acquired the Lincs Wind Farm project in 2004 from Renewable Energy Systems in 2008 the company obtained planning permission for the project 1 2 In December 2009 Orsted A S then named DONG Energy and Siemens Project Ventures jointly acquired 50 of the project 25 share each for 50 million plus 50 of the capital cost of the project 3 Preparatory construction work for the development included the extension of the National Grid electricity substation at Walpole Norfolk which began in April 2009 4 note 1 In June 2010 Siemens obtained the contract for the offshore electrical substation 101 million 7 Transmission cables from offshore to onshore electrical substations were installed in 2010 2011 4 8 Construction of the offshore facilities of the wind farm began in 2011 with the installation of the offshore electricity substation foundations 9 The Port of Hull was selected as one of the logistics bases for the wind farm turbine installation supplying wind tower transition pieces Jack up barge JB114 arriving at the port in March 2012 10 Great Yarmouth was also used as a base for the wind farm installation 11 Construction of the offshore 33 kV to 132 kV substation structure sub contracted to McNulty Offshore Construction Atkins PLC 12 and of the onshore 132 kV to 400 kV substation was completed by April 2012 13 In August 2011 the consortia of Orsted Siemens and Centrica began to seek financing for the 1 billion project committing to providing 166 7 75 and 333 3 million respectively 575 million total In June 2012 the consortia obtained financing for the project with 425 million of nonrecourse debt facilities provided from a consortium of 10 banks Approximately 75 of the project cost was for the wind farm installation the remainder for the high voltage electricity transmission link 14 Construction began in 2010 installation of the 75 monopile tower foundation by MT Hojgaard was completed by June 2012 with the underwater installation phase completed by September 2012 15 The first generator had been installed by 14 July 2012 16 The wind farm was scheduled to become operational in the second half of 2012 and be complete by 2013 17 the final turbine was installed by March 2013 18 and the wind farm officially opened by Deputy Prime Minister Nick Clegg in August 2013 19 20 with commissioning complete in September 2013 21 The license for the electrical transmission link was awarded to TC Lincs OFTO Limited for 308 million in late 2014 22 Technical description EditThe scheme has 250 MW of generating capacity with an additional 20 MW of turbine generating capacity constructed within the nearby Lynn Wind Farm and Dowsing Wind Farm but connected to the Lincs project transmission system 23 The project uses 75 three blade 3 6 MW Siemens wind turbines The wind turbines have 120 metres 390 ft rotor diameter machines with 58 5 metres 192 ft blades with a hub height of 100 metres 330 ft on cylindrical steel towers The turbines were installed in 10 to 15 metres 33 to 49 ft water depth with a spacing of approximately 500 metres 1 600 ft within a 35 square kilometres 14 sq mi wind farm 8 Transmission of electrical power to land is by 145 kV cables supplied by Nexans Transmission voltage is 132 kV to land being increased to 400 kV at Walpole substation for grid connection 8 The operation and maintenance base for the wind farm is based at Grimsby 24 As at 2019 the windfarm has a rolling capacity factor of 39 25 Its levelised cost has been estimated at 166 MWh 26 The wind farm has an expected lifespan of 40 years with electrical equipment and wind turbines expected to be replaced after 20 years After the end of the project s lifespan the farm is to be decommissioned including removal of turbines and electrical equipment and removal of offshore foundations or cut off to seabed level or lower Connecting cables are not scheduled to be removed 27 See also Edit England portal Weather portal Renewable energy portal List of offshore wind farms in the United Kingdom List of offshore wind farms in the North Sea List of offshore wind farms Wind power in the United KingdomNotes Edit Lincs Docking Shoal and Race Bank wind farms were to share the same onshore cable export route and onshore substation 5 The environmental statement for the onshore works was submitted as part of the Lincs Wind Farm application 6 References Edit Centrica gains government consent for second generation offshore wind farm PDF Press release Centrica 21 October 2008 Archived from the original PDF on 13 February 2015 Retrieved 4 April 2012 Centrica s Lincolnshire development leads offshire windfarm stampeded Utility Week 29 October 2008 Archived from the original on 5 May 2013 Retrieved 4 April 2012 Sources DONG Energy and Siemens Project Ventures to join UK offshore wind farm project Press release DONG Energy 23 December 2009 Archived from the original on 25 May 2011 Retrieved 4 April 2012 Wearden Graeme 28 October 2009 Market forces breaking news Centrica to build new wind farm The Guardian Retrieved 4 April 2012 Dong rides the wind Upstream Online NHST Media Group 23 December 2009 Retrieved 1 January 2010 Centrica announces new equity partners and upgraded turbines for Lincs offshore wind farm improving the project economics PDF Press release Centrica 23 December 2009 Archived from the original PDF on 13 February 2015 Retrieved 4 April 2012 a b Lincs Offshore Wind Farm Construction Update PDF Centrica March 2012 Archived from the original PDF on 30 April 2015 Retrieved 4 April 2012 The power from Lincs will be transmitted to the National Grid substation at Walpole Work to build an extension to the substation commenced in 2010 to enable the power to be transformed from 132 kV to 400 kV Civil works commenced at the National Grid substation site at Walpole in April last year Race Bank Offshore Wind Farm Environmental Statement Non Technical Summary PDF Centrica January 2009 p 3 Archived from the original PDF on 30 April 2015 Retrieved 11 May 2014 Lincs Offshore Wind Farm ES Non Technical Summary January 2007 pp 3 5 11 Siemens wins new 101 million order to connect Lincs offshore wind farm to the UK grid Press release Siemens 28 June 2010 Retrieved 8 June 2012 a b c Centrica Lincs Offshore Wind Project United Kingdom Power Technology Retrieved 4 April 2012 Sources Skegness windfarm will double turbines Skegness Standard 1 April 2011 Archived from the original on 11 August 2013 Retrieved 4 April 2012 Lincs work has begun This is Lincolnshire 28 March 2011 Retrieved 4 April 2012 Sources Lincs Wind Farm chooses ABP s Port of Hull as a logistics base for its Lincs offshore wind farm Press release ABP 26 March 2012 Retrieved 4 April 2012 Hull s Albert Dock playing key role in North Sea wind farm as renewables era lifts off This is Lincolnshire 28 March 2012 Retrieved 4 April 2012 Lincs Offshore Wind Farm www 4coffshore com 4C Offshore Retrieved 24 January 2013 Siemens LINCS OSS McNulty Offshore Construction www mcnultyoffshore com Archived from the original on 2 February 2014 Retrieved 8 June 2012 Lincs Offshore Wind Farm Construction Update PDF Centrica April 2012 Archived from the original PDF on 30 April 2015 Retrieved 8 June 2012 Construction of the 3 000 tonne offshore substation which will transform power from the wind farm from 33 kV to 132 kV is now complete It has been built by McNulty a subcontractor to Siemens Transmission and Distribution Limited based in South Shields The testing and energisation of the onshore substation at Walpole is now complete This substation will boost the power from 132 kV to 400 kV Sources Bakewell Sally 19 August 2011 Centrica Siemens Seek Loans For 1 Billion Pound U K Wind Deal Bloomberg Retrieved 7 June 2012 Bakewell Sally 7 June 2012 Centrica Siemens Receive 660 Million for U K Wind Project Bloomberg Businessweek Bloomberg Retrieved 7 June 2012 McKenna John 7 June 2012 Landmark UK offshore deal agreed Windpower Monthly Retrieved 7 June 2012 Sources UK MT Hojgaard Installs Last Foundation for Lincs Wind Farm www offshorewind biz 20 June 2012 Retrieved 27 September 2012 Turbine Installation Starts as MT Hojgaard Completes Work on Lincs Wind Farm UK www offshorewind biz 19 September 2012 Retrieved 27 September 2012 Lincs Wind Farm August 2012 PDF Centrica August 2012 Retrieved 27 September 2012 dead link 425 million Lincs Wind Farm project financing agreements finalised Press release Centrica 7 June 2012 Retrieved 7 June 2012 UK Final turbine installed at Lincs Offshore Wind Farm worldmaritimenews com 3 April 2013 Retrieved 24 January 2014 Lincs offshore wind farm officially opened by Deputy Prime Minister Nick Clegg PDF press release Siemens 1 August 2013 Retrieved 24 January 2014 Nick Clegg opens Skegness offshore wind farm BBC News 2 August 2013 Retrieved 17 February 2016 Lincs offshore wind farm mission complete Centrica 27 September 2013 Retrieved 24 January 2014 TCP pockets 308m Lincs licence renews biz 4 November 2014 Retrieved 4 November 2014 Lincs Project History PDF Centrica Archived from the original PDF on 30 December 2014 Retrieved 4 April 2012 Sources Jobs boost in Grimsby docks wind farm project BBC News 4 May 2011 Retrieved 4 April 2012 Centrica signs long term lease for operations and maintenance base in Grimsby PDF Press release Centrica 4 May 2011 Archived from the original PDF on 13 February 2015 Retrieved 4 April 2012 Lincs Wind Farm Renewable Energy Foundation Aldersey Williams John Broadbent Ian Strachan Peter 2019 Better estimates of LCOE from audited accounts A new methodology with examples from United Kingdom offshore wind and CCGT Energy Policy 128 25 35 LINCS Offshore Wind Farm Decommissioning Plan On behalf of Lincs Wind Farm Limited PDF Centrica December 2010 pp 1 2 Archived from the original PDF on 13 February 2015 Retrieved 4 April 2012 Sources Edit Centrica Lincs Offshore Wind Farm Environmental Statement Non Technical Summary PDF Centrica January 2007 Archived from the original PDF on 12 May 2014 Statement for main wind farm area LID6 Environmental Statement On behalf of Lincs Wind Farm Limited Non Technical Summary PDF Centrica May 2010 Archived from the original PDF on 8 January 2015 Statement for 6 additional turbines of 20 MW within Lynn amp Inner Dowsing farm area Lincs Offshore Wind Farm Construction Activities PDF Centrica January 2011 Archived from the original PDF on 8 January 2015 Retrieved 7 June 2012 Project timeline and turbine locations proposed Lincs Wind Farm project history PDF Centrica Archived from the original PDF on 8 January 2015 Other Lincs Offshore Wind Farm www 4coffshore com Retrieved from https en wikipedia org w index php title Lincs Wind Farm amp oldid 1131293221, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.