fbpx
Wikipedia

Humber Gateway Wind Farm

Humber Gateway Wind Farm is an offshore wind farm 8 kilometres (5 mi) east of Spurn Point off the coast of North East Lincolnshire, in the North Sea, England; the wind farm is located in water depths around 15 metres (49 ft) and covers an area of approximately 25 square kilometres (9.7 sq mi). The wind farm became operational in June 2015.

Humber Gateway Wind Farm
Humber Gateway visible on the horizon, under construction in March 2015
Country
  • United Kingdom
Location8 km east of Spurn Point, East Riding of Yorkshire
Coordinates53°38′38″N 0°17′35″E / 53.644°N 0.293°E / 53.644; 0.293
StatusOperational
Commission date
  • June 2015
Construction cost£736 million
Owner(s)
Operator(s)
Wind farm
Type
Max. water depth15 m
Distance from shore8 km (5 mi)
Hub height80 m
Rotor diameter
  • 112 m (367 ft)
Site area
  • 35 km2 (14 sq mi)
Power generation
Units operational73 × 3 MW
Make and modelVestas V112-3.0MW (73)
Nameplate capacity
  • 219 MW
Capacity factor41.9% (projected)[1]
Annual net output803 GW·h (planned)
External links
Websiteuk-ireland.rwe.com/locations/humber-gateway-offshore-wind-farm
CommonsRelated media on Commons
Wind farm layout

It was developed by Humber Wind Limited, a wholly owned subsidiary of E.ON UK plc.; the wind farm consists of seventy-three 3 MW wind turbines, with the electrical cable making landfall at Easington, and connecting to the National Grid, at Salt End, on the eastern outskirts of Kingston upon Hull.

In 2020, the ownership of Humber Gateway was transferred to RWE alongside E.ON's other renewables business. [2]

History edit

In 2003 EON submitted a bid to the Crown Estate to develop a wind farm in the 'Greater Wash Strategic Area';[note 1][4] a planning application was submitted in 2008 for a 300 MW, £700 million, wind farm.[5][note 2] Additional planning applications for onshore substation, and onshore underground cable were submitted in 2009/2008, and approved in 2010.[7][8]

The site was located over 8 km east of Easington, in an area roughly 35 km2 (14 sq mi) with a water depth of around 15 m (49 ft), and approximately 15 km north-northeast from Donna Nook on the Lincolnshire coast. Cable connections were to make land fall at Easington and connect via about a 30 km underground cable connection with the National Grid near Salt End (near Hull).[9] Initial plans were for a 300 MW wind farm, with 42–83 turbines.[10] The wind farm had an expected operational life of 40 years based on the length of the Crown Estate lease, with possible turbine replacement after 20–25 years.[11]

Governmental planning approval for a 230 MW (77 turbine) wind farm was given in early 2011.[12][13] In December 2011 E ON published plans for a 73 turbine, 219 MW wind farm, using Vestas V112 3.0 MW turbines, with an initial completion date scheduled for spring 2015.[14]

Contracts, design and construction edit

In 2012 CG (Avantha) was awarded the main contract for the design to installation of both onshore and offshore substations for the project.[15] In early 2013 contract for the supply of turbine monopile foundations were split between TAG Energy Solutions (UK) (16 foundations), with the remainder supplied by Sif (Netherlands).[16][17] ABB Group was contracted to supply 132kV submarine export cables in March 2012,[18] the inter turbine cabling supply contract was awarded to General Cable subsidiary Norddeutsche Seekabelwerke Gmbh. in August 2012.[19]

Harland and Wolff was contracted to design and supply the about 1300t substation foundation structure and piles in March 2013.[20]

The first turbine foundation was installed in September 2013.[21] In December 2013 two 600t offshore substations were delivered to the Port of Sunderland for installation at the wind farm.[22]

By January 2014 the submarine export cables to the offshore transformer had been laid.[21] The first turbine was installed mid 2014.[23][24] Offshore substation installation was completed in late 2014.[25] The wind farm first generated power in early 2015, with 58 of the turbines installed,[26] and became fully operational by June 2015.[27][28] The wind farm was formally opened by Andrea Leadsom (MP) 30 September 2015.[29] Its levelised cost has been estimated at £147/MWh.[30]

In September 2015 Balfour Beatty Equitix Consortium (Balfour Beatty/Equitix) became preferred bidder to own and operate the £162.9 million electricity export cable.[31] The European Investment Bank provides £82 million for the transmission.[32]

Grimsby operations centre edit

53°34′45″N 0°03′29″W / 53.57919°N 0.05798°W / 53.57919; -0.05798 (E.ON Operations and Maintenance Facility Grimsby Docks)

In mid 2012 E ON submitted a planning application to build an operations and maintenance centre at the Port of Grimsby, for the maintenance of the Humber Gateway wind farm.[33][34] Construction firm ISG was awarded a £3 million contract to construct the centre in March 2013, including 5,920 sq ft (550 m2) and 4,047 sq ft (376.0 m2) warehouse and storage buildings.[35][36] Construction was completed by September 2013.[37] The centre was formally opened by Eric Pickles on 1 August 2014.[24]

Notes edit

  1. ^ The 'Greater Wash Strategic Environmental Assessment Area' was a region identified as a potential wind farm area in the UK Round 2 wind farm development, including areas in the sea off the east coast of England in Holderness, Lincolnshire, the Wash and north Norfolk.[3]
  2. ^ Planning application was undertaken by Humber Wind Limited, a wholly owned subsidiary of E ON UK plc.[6]

References edit

  1. ^ "Humber Gateway". eonenergy.com. Retrieved 5 March 2017.
  2. ^ "RWE closes deal with E.ON". Retrieved 3 January 2023.
  3. ^ Offshore Wind Farm Development: Strategic Environmental Assessment (R2 Wind): Environmental Report, Department of Energy & Climate Change, 29 April 2003, Annex 2, retrieved 31 January 2014
  4. ^ Humber Gateway project timeline, (E ON)
  5. ^ E.ON submits planning application to build one of the UK's largest offshore wind farms off the Yorkshire coast, hopes for swift resolution to MoD objection (PDF) (press release), E ON, 7 April 2008, retrieved 31 January 2014
  6. ^ Humber Gateway – Non-Technical Summary, (E ON), p.4
  7. ^ (09/04287/STPLFE) Erection of electrical substation .., East Riding of Yorkshire Council, 29 October 2009, retrieved 31 January 2014
  8. ^ (08/01993/STPLFE) Construction of onshore sub-surface cables from Easington to substation at Saltend .., East Riding of Yorkshire Council, 7 April 2008, retrieved 31 January 2014
  9. ^ (PDF). Dong Energy. October 2009. p. 4. Archived from the original (PDF) on 19 April 2011. Retrieved 26 September 2012.
  10. ^ Humber Gateway – Non-Technical Summary, (E ON), pp.6–7
  11. ^ Humber Gateway – Non-Technical Summary, (E ON), p.9
  12. ^ "Humber Gateway wind farm gets government approval", BBC News Humberside, 9 February 2011, retrieved 26 February 2011
  13. ^ "Humber Gateway offshore wind farm given go-ahead", www.gov.uk, 9 February 2011, retrieved 31 January 2014
  14. ^ (press release), E ON, 15 December 2011, archived from the original on 21 March 2015, retrieved 31 January 2014
  15. ^ "CG to Supply Substations for E.ON's Offshore Wind Farm (UK)", www.offshorewind.biz, 11 January 2012, retrieved 31 January 2014
  16. ^ Gill, Erin (7 March 2013), "Sif to supply Humber Gateway and Amrumbank West", www.windpoweroffshore.com, retrieved 31 January 2014
  17. ^ , TAG Energy Solutions, 27 February 2013, archived from the original on 2 February 2014, retrieved 31 January 2014
  18. ^ "ABB Wins Subsea Cable Order For UK's Humber Gateway Offshore Wind Farm", www.epcengineer.com, 7 March 2012, retrieved 31 January 2014
  19. ^ , www.yourcableandwirenews, 17 August 2012, archived from the original on 3 March 2016, retrieved 31 January 2014
  20. ^ "E.ON places major contract with Harland and Wolff", www.harland-wolff.com, 26 March 2013, retrieved 31 January 2014
  21. ^ a b "E.on's Humber Gateway offshore wind farm project making 'good progress'". Grimsby Telegraph. 7 January 2014. Retrieved 13 April 2017.
  22. ^ Gibson, Robert (2 December 2013), , The Journal, archived from the original on 6 December 2013, retrieved 31 January 2014
  23. ^ "Eon opens Humber turbines tally", renews.biz, 1 August 2014, retrieved 1 August 2014
  24. ^ a b (press release), EON, 1 August 2014, archived from the original on 21 March 2015, retrieved 1 August 2014
  25. ^ "MPI polishes off Humber platform", renews.biz, 3 November 2014, retrieved 3 November 2014
  26. ^ "Eon delivers first power at Humber", renews.biz, 24 February 2015, retrieved 24 February 2015
  27. ^ "219MW Humber steams ahead", renews.biz, 5 June 2015, retrieved 5 June 2015
  28. ^ . Grimsby Telegraph. Archived from the original on 19 June 2015. Retrieved 15 June 2015.
  29. ^ "Eon opens Humber Gateway", renews.biz, 30 September 2015, retrieved 30 September 2015
  30. ^ Aldersey-Williams, John; Broadbent, Ian D.; Strachan, Peter A. (1 May 2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT". Energy Policy. 128: 25–35. doi:10.1016/j.enpol.2018.12.044. hdl:10059/3298.
  31. ^ "Balfour Beatty Equitix wins Humber", renews.biz, 24 September 2015, retrieved 24 September 2015
  32. ^ "Humber Gateway Offshore Transmission Project Reaches Financial Close". CleanTechnica. 8 September 2016. Retrieved 9 September 2016.
  33. ^ . Grimsby Telegraph. 5 July 2012. Archived from the original on 24 September 2015. Retrieved 31 January 2014.
  34. ^ (DC/453/12/EMA) Erection of an operations & maintenance building with warehouse and offices .., North East Lincolnshire Council, 27 June 2012, retrieved 31 January 2014
  35. ^ "£3m Grimsby wind farm base contract handed out". Grimsby Telegraph. 27 March 2013. Retrieved 31 January 2014.
  36. ^ , ISG, archived from the original on 2 February 2014, retrieved 31 January 2014
  37. ^ , www.humber-gateway.com, 9 September 2013, archived from the original on 2 February 2014, retrieved 31 January 2014

Sources edit

  • , EON, archived from the original on 10 February 2015, retrieved 31 January 2014
  • (PDF), EON UK, archived from the original (PDF) on 16 December 2010, retrieved 26 February 2011
  • Onshore route and offshore site map (PDF), E ON, retrieved 31 January 2014

External links edit

  • "Humber Gateway". E.ON Energy.
  • "Humber Gateway". www.4coffshore.com.

humber, gateway, wind, farm, offshore, wind, farm, kilometres, east, spurn, point, coast, north, east, lincolnshire, north, england, wind, farm, located, water, depths, around, metres, covers, area, approximately, square, kilometres, wind, farm, became, operat. Humber Gateway Wind Farm is an offshore wind farm 8 kilometres 5 mi east of Spurn Point off the coast of North East Lincolnshire in the North Sea England the wind farm is located in water depths around 15 metres 49 ft and covers an area of approximately 25 square kilometres 9 7 sq mi The wind farm became operational in June 2015 Humber Gateway Wind FarmHumber Gateway visible on the horizon under construction in March 2015CountryUnited KingdomLocation8 km east of Spurn Point East Riding of YorkshireCoordinates53 38 38 N 0 17 35 E 53 644 N 0 293 E 53 644 0 293StatusOperationalCommission dateJune 2015Construction cost 736 millionOwner s Greencoat UK WindRWE AGOperator s RWE AGWind farmTypeOffshoreMax water depth15 mDistance from shore8 km 5 mi Hub height80 mRotor diameter112 m 367 ft Site area35 km2 14 sq mi Power generationUnits operational73 3 MWMake and modelVestas V112 3 0MW 73 Nameplate capacity219 MWCapacity factor41 9 projected 1 Annual net output803 GW h planned External linksWebsiteuk ireland wbr rwe wbr com wbr locations wbr humber gateway offshore wind farmCommonsRelated media on Commons edit on Wikidata Wind farm layout It was developed by Humber Wind Limited a wholly owned subsidiary of E ON UK plc the wind farm consists of seventy three 3 MW wind turbines with the electrical cable making landfall at Easington and connecting to the National Grid at Salt End on the eastern outskirts of Kingston upon Hull In 2020 the ownership of Humber Gateway was transferred to RWE alongside E ON s other renewables business 2 Contents 1 History 1 1 Contracts design and construction 1 2 Grimsby operations centre 2 Notes 3 References 3 1 Sources 4 External linksHistory editIn 2003 EON submitted a bid to the Crown Estate to develop a wind farm in the Greater Wash Strategic Area note 1 4 a planning application was submitted in 2008 for a 300 MW 700 million wind farm 5 note 2 Additional planning applications for onshore substation and onshore underground cable were submitted in 2009 2008 and approved in 2010 7 8 The site was located over 8 km east of Easington in an area roughly 35 km2 14 sq mi with a water depth of around 15 m 49 ft and approximately 15 km north northeast from Donna Nook on the Lincolnshire coast Cable connections were to make land fall at Easington and connect via about a 30 km underground cable connection with the National Grid near Salt End near Hull 9 Initial plans were for a 300 MW wind farm with 42 83 turbines 10 The wind farm had an expected operational life of 40 years based on the length of the Crown Estate lease with possible turbine replacement after 20 25 years 11 Governmental planning approval for a 230 MW 77 turbine wind farm was given in early 2011 12 13 In December 2011 E ON published plans for a 73 turbine 219 MW wind farm using Vestas V112 3 0 MW turbines with an initial completion date scheduled for spring 2015 14 Contracts design and construction edit In 2012 CG Avantha was awarded the main contract for the design to installation of both onshore and offshore substations for the project 15 In early 2013 contract for the supply of turbine monopile foundations were split between TAG Energy Solutions UK 16 foundations with the remainder supplied by Sif Netherlands 16 17 ABB Group was contracted to supply 132kV submarine export cables in March 2012 18 the inter turbine cabling supply contract was awarded to General Cable subsidiary Norddeutsche Seekabelwerke Gmbh in August 2012 19 Harland and Wolff was contracted to design and supply the about 1300t substation foundation structure and piles in March 2013 20 The first turbine foundation was installed in September 2013 21 In December 2013 two 600t offshore substations were delivered to the Port of Sunderland for installation at the wind farm 22 By January 2014 the submarine export cables to the offshore transformer had been laid 21 The first turbine was installed mid 2014 23 24 Offshore substation installation was completed in late 2014 25 The wind farm first generated power in early 2015 with 58 of the turbines installed 26 and became fully operational by June 2015 27 28 The wind farm was formally opened by Andrea Leadsom MP 30 September 2015 29 Its levelised cost has been estimated at 147 MWh 30 In September 2015 Balfour Beatty Equitix Consortium Balfour Beatty Equitix became preferred bidder to own and operate the 162 9 million electricity export cable 31 The European Investment Bank provides 82 million for the transmission 32 Grimsby operations centre edit 53 34 45 N 0 03 29 W 53 57919 N 0 05798 W 53 57919 0 05798 E ON Operations and Maintenance Facility Grimsby Docks In mid 2012 E ON submitted a planning application to build an operations and maintenance centre at the Port of Grimsby for the maintenance of the Humber Gateway wind farm 33 34 Construction firm ISG was awarded a 3 million contract to construct the centre in March 2013 including 5 920 sq ft 550 m2 and 4 047 sq ft 376 0 m2 warehouse and storage buildings 35 36 Construction was completed by September 2013 37 The centre was formally opened by Eric Pickles on 1 August 2014 24 Notes edit The Greater Wash Strategic Environmental Assessment Area was a region identified as a potential wind farm area in the UK Round 2 wind farm development including areas in the sea off the east coast of England in Holderness Lincolnshire the Wash and north Norfolk 3 Planning application was undertaken by Humber Wind Limited a wholly owned subsidiary of E ON UK plc 6 References edit Humber Gateway eonenergy com Retrieved 5 March 2017 RWE closes deal with E ON Retrieved 3 January 2023 Offshore Wind Farm Development Strategic Environmental Assessment R2 Wind Environmental Report Department of Energy amp Climate Change 29 April 2003 Annex 2 retrieved 31 January 2014 Humber Gateway project timeline E ON E ON submits planning application to build one of the UK s largest offshore wind farms off the Yorkshire coast hopes for swift resolution to MoD objection PDF press release E ON 7 April 2008 retrieved 31 January 2014 Humber Gateway Non Technical Summary E ON p 4 09 04287 STPLFE Erection of electrical substation East Riding of Yorkshire Council 29 October 2009 retrieved 31 January 2014 08 01993 STPLFE Construction of onshore sub surface cables from Easington to substation at Saltend East Riding of Yorkshire Council 7 April 2008 retrieved 31 January 2014 Westermost Rough Offshore Wind Farm Non technical summary PDF Dong Energy October 2009 p 4 Archived from the original PDF on 19 April 2011 Retrieved 26 September 2012 Humber Gateway Non Technical Summary E ON pp 6 7 Humber Gateway Non Technical Summary E ON p 9 Humber Gateway wind farm gets government approval BBC News Humberside 9 February 2011 retrieved 26 February 2011 Humber Gateway offshore wind farm given go ahead www gov uk 9 February 2011 retrieved 31 January 2014 E ON announces 736m plan for Humber Gateway offshore wind farm press release E ON 15 December 2011 archived from the original on 21 March 2015 retrieved 31 January 2014 CG to Supply Substations for E ON s Offshore Wind Farm UK www offshorewind biz 11 January 2012 retrieved 31 January 2014 Gill Erin 7 March 2013 Sif to supply Humber Gateway and Amrumbank West www windpoweroffshore com retrieved 31 January 2014 E ON awards wind farm foundations contract to TAG Energy Solutions TAG Energy Solutions 27 February 2013 archived from the original on 2 February 2014 retrieved 31 January 2014 ABB Wins Subsea Cable Order For UK s Humber Gateway Offshore Wind Farm www epcengineer com 7 March 2012 retrieved 31 January 2014 Norddeutsche Seekabelwerke GmbH to supply inter array cabling for offshore wind farm Humber Gateway www yourcableandwirenews 17 August 2012 archived from the original on 3 March 2016 retrieved 31 January 2014 E ON places major contract with Harland and Wolff www harland wolff com 26 March 2013 retrieved 31 January 2014 a b E on s Humber Gateway offshore wind farm project making good progress Grimsby Telegraph 7 January 2014 Retrieved 13 April 2017 Gibson Robert 2 December 2013 Substations arrive at Port of Sunderland The Journal archived from the original on 6 December 2013 retrieved 31 January 2014 Eon opens Humber turbines tally renews biz 1 August 2014 retrieved 1 August 2014 a b Secretary of State opens E ON s Humber Gateway Offshore Wind Farm Operations and maintenance base press release EON 1 August 2014 archived from the original on 21 March 2015 retrieved 1 August 2014 MPI polishes off Humber platform renews biz 3 November 2014 retrieved 3 November 2014 Eon delivers first power at Humber renews biz 24 February 2015 retrieved 24 February 2015 219MW Humber steams ahead renews biz 5 June 2015 retrieved 5 June 2015 Eon energy project sees every turbine generating Grimsby Telegraph Archived from the original on 19 June 2015 Retrieved 15 June 2015 Eon opens Humber Gateway renews biz 30 September 2015 retrieved 30 September 2015 Aldersey Williams John Broadbent Ian D Strachan Peter A 1 May 2019 Better estimates of LCOE from audited accounts A new methodology with examples from United Kingdom offshore wind and CCGT Energy Policy 128 25 35 doi 10 1016 j enpol 2018 12 044 hdl 10059 3298 Balfour Beatty Equitix wins Humber renews biz 24 September 2015 retrieved 24 September 2015 Humber Gateway Offshore Transmission Project Reaches Financial Close CleanTechnica 8 September 2016 Retrieved 9 September 2016 E ON to create 50 Grimsby jobs in Humber Gateway wind farm project Grimsby Telegraph 5 July 2012 Archived from the original on 24 September 2015 Retrieved 31 January 2014 DC 453 12 EMA Erection of an operations amp maintenance building with warehouse and offices North East Lincolnshire Council 27 June 2012 retrieved 31 January 2014 3m Grimsby wind farm base contract handed out Grimsby Telegraph 27 March 2013 Retrieved 31 January 2014 ISG takes Humber Gateway scheme with E ON ISG archived from the original on 2 February 2014 retrieved 31 January 2014 HUMBER GATEWAY HANDOVER www humber gateway com 9 September 2013 archived from the original on 2 February 2014 retrieved 31 January 2014 Sources edit Humber Gateway project timeline EON archived from the original on 10 February 2015 retrieved 31 January 2014 Humber Gateway Offshore Wind Farm Non Technical Summary of the Offshore Environmental Statement and Onshore Cable Route Environmental Statement PDF EON UK archived from the original PDF on 16 December 2010 retrieved 26 February 2011 Onshore route and offshore site map PDF E ON retrieved 31 January 2014External links edit nbsp England portal nbsp Weather portal nbsp Renewable energy portal Humber Gateway E ON Energy Humber Gateway www 4coffshore com Retrieved from https en wikipedia org w index php title Humber Gateway Wind Farm amp oldid 1153965340, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.