The Huey P. Long Bridge,[4] located in Jefferson Parish, Louisiana, is a cantilevered steel through-truss bridge that carries a two-track railroad line over the Mississippi River at mile 106.1, with three lanes of US 90 on each side of the central tracks. It is several kilometers upriver from the city of New Orleans. The East Bank entrance is at Elmwood, Louisiana, and the West Bank at Bridge City.

Huey P. Long Bridge
The Huey Long Bridge in 2007, when widening work had just begun.
Coordinates29°56′39″N 90°10′08″W / 29.94417°N 90.16889°W / 29.94417; -90.16889
Carries6 lanes of US 90
2 tracks of the NOPB
CrossesMississippi River
LocaleJefferson Parish, Louisiana
Maintained byNew Orleans Public Belt Railroad
ID number022600060100001
Characteristics
DesignCantilever truss bridge
Total length8,076 feet (2,462 m) (road)
22,996 feet (7,009 m) (rail)
Longest span790 feet (241 m)
Clearance below153 feet (47 m)
History
Construction cost$13.4 million[1][2] (equivalent to $226 million in 2022 dollars)
OpenedDecember 1935
(widened June 2013)
Statistics
Daily traffic43,000 (2008)
Location

Opened in December 1935, the bridge was named for the late Governor Huey P. Long, who was assassinated on September 8 of that year. The bridge was the first Mississippi River span built in Louisiana and the 29th along the length of the river. It was designed by Polish-American engineer Ralph Modjeski and is designated as a National Historic Civil Engineering Landmark by the American Society of Civil Engineers.[5]

On June 16, 2013, a $1.2 billion widening project by the Louisiana Department of Transportation and Development was completed and opened to motorists. The bridge now consists of three 11-foot (3.4 m) lanes in each direction, with inside and outside shoulders. Prior to the expansion, there were two 9-foot (2.7 m) lanes in each direction with no shoulders. In both cases, the road lanes flanked the twin railroad tracks contained within the truss.

in 2014, a writer at The New Yorker described the bridge as "a structure so vaulting and high that it seems to extend from one white, towering Gulf Coast cloud to the next."[6]

Structure edit

 
USS New Orleans passes under the bridge, March 2007

The widest clear span is 790 feet (240 m) long while each of the three additional spans are 530 feet (160 m) long, making the total river crossing about 2,400 feet (730 m) long.[7] There are three navigation channels below the bridge, the widest being 750 feet (230 m). The vertical clearance below the structure is 152.9 feet (46.6 m).[8] The distinctive rail structure is 22,996 feet (7,009 m) long and extends as rail viaducts well into the city on both sides of the river from the central spans. It has sometimes been described as the longest rail bridge in the US, but the nearby Norfolk Southern Lake Pontchartrain Bridge, at 5.8 miles (9.3 km), is considerably longer. The highway structure is 8,076 feet (2,462 m) long with steep grades on both sides. As originally constructed, each roadway deck was 18 feet (5.5 m) wide, with two 9-foot (2.7 m) lanes; but because of the railroad component, it is unusually flat. Normally, bridges its height have a hump, but this bridge was designed flat to facilitate rail traffic.[9]

The bridge is a favorite railfan location. It is owned by the New Orleans Public Belt Railroad, which is owned by the City of New Orleans and managed by the Public Belt Railroad Commission. The bridge was hated by many drivers in the New Orleans area due to the narrow 9-foot-wide (2.7 m) lanes without shoulders before it was widened. Additionally, where the East Bank approach met the superstructure of the bridge, the two vehicular roadways "jogged" or shifted inwards towards the bridge centerline about 1+12 feet (0.46 m) since the through-truss portion of the superstructure was 3 feet (0.91 m) wider than the deck truss portion of the east approach.

The foundation of the bridge is also unique. The land in and around New Orleans was formed by silt deposits brought down the Mississippi River. The clay topsoil, known colloquially as "gumbo soil,"[10] is compressible and unsuitable for foundation loads. As bedrock is around 1,000 feet (300 m) below the surface, making it too deep for normal bridge foundation construction, the main piers are seated on a layer of fine sand 160 to 170 feet (49 to 52 m) below Mean Gulf Level and rely on their size and mass to hold them in place.

The bridge dates from an era when large bridges mixing rail tracks and highways were common, as typified by the MacArthur Bridge and McKinley Bridge in St. Louis, Missouri, and the Harahan Bridge in Memphis, Tennessee. A second Huey P. Long Bridge, which is very similar to the design of this bridge in New Orleans before its renovation, was built further upstream in 1940 in Baton Rouge, Louisiana. While both of the Long bridges still carry both types of traffic, most of the others have been converted either to entirely rail use (Harahan since 1949, MacArthur since 1981) or exclusive road use (McKinley since 1978), sometimes with bicycle and/or pedestrian use added (McKinley in 2007, Harahan in 2016).

History edit

As early as 1892 the Southern Pacific Railway proposed a high-level bridge, but a depression that year prevented further work on a project that would have been an overwhelming challenge for the engineers of the time due to soil conditions and extremely high clearances for river navigation. With the development of the Public Belt Railroad, interest in a river rail crossing grew and led to passage of a constitutional amendment in 1916 granting the city exclusive power to build and operate a crossing. Three general ideas emerged from the planning process: a low-level drawbridge, a tunnel, and a high-level bridge. The tunnel idea died first, because it would have provided limited capacity, and the War Department (after years of wrangling) ultimately rejected the idea of a drawbridge as too problematic for such a significant concentration of vital transportation infrastructure.

Work on the design of the bridge began in earnest in 1925 by the engineering firm of Modjeski and Masters. Some pilings were actually driven that year to prevent expiration of congressional authority and provide further information for the design. As the magnitude of the project became apparent and projected costs ballooned, financing difficulties compounded by the Great Depression delayed the project. Finally, on November 5, 1932, the bonds of the Public Belt Railroad Commission were guaranteed by a complex agreement between the Southern Pacific Railroad, the City of New Orleans and the State of Louisiana. Principal construction contracts were signed on December 30, 1932, and work formally started the following day. Construction of the bridge proceeded smoothly over a three-year period with only minor interruptions due to high water and a one-month strike in September 1933.

Expansion edit

The Huey P. Long Bridge Widening Project is a TIMED (Transportation Infrastructure Model for Economic Development) Program project. The TIMED Program was created by Act 16 of the 1989 Louisiana Legislature, was voted for by the people and is the single largest transportation program in state history. The Program is designed to enhance economic development in Louisiana through an investment in transportation projects.

The $1.2 billion widening project started in April 2006 and is the first change to the structure since it opened in 1935. The project expanded the highway on each side of the structure from two 9-foot (2.7 m) lanes to three 11-foot (3.4 m) lanes with a 2-foot (0.61 m) inside shoulder and an 8-foot (2.4 m) outside shoulder. It also included new signalized intersections to replace the traffic circles at Jefferson Highway and at Bridge City Avenue, both in Jefferson Parish, Louisiana.

Project details edit

This seven-year-long, four-phase project was completed in 2013. The timeline of the project was as follows:

Phase I: Main support widening (piers)
In this phase, completed in May 2009, four river piers and one land pier were widened to support the additional lanes. Reinforcing framework and concrete filled the void sections of the piers to strengthen them. In addition, w-shaped metal bridge struts were anchored to the upper part of each pier to support the additional new trusses and the existing truss.

Phase II: Railroad modifications
In October 2006, work to relocate five selected railroad supports was done to facilitate the construction of the new approaches. This phase was completed in June 2008.

Phase III: Main bridge widening (truss)
Completed in 2012, this phase widened the existing truss on either side to accommodate new travel lanes and shoulders.
The bridge, which is composed of four spans, was erected one span at a time. In November 2009, construction of the West Bank Anchor Span began by using the stick-built method, meaning each element of the span was individually placed. In order to minimize the use of falsework and river closures in the navigation or auxiliary channels, the three remaining spans were done through the span-by-span method. This method involved large barges transporting a pre-assembled span section, positioning it under the bridge, and lifting it into position using strand jacks. Temporary stability frames made up of floorbeams and towers were used to support each span section during the lifting process.

This phase was completed on April 29, 2012, when traffic was shifted from the original lanes (two 9-foot (2.7 m) lanes in each direction, cantilevered on each side of the original truss) to two temporary lanes in each direction on the widened portion of the truss.[11]

Phase IV: New approaches construction
During this phase of the project, the two temporary lanes were widened to three 11-foot (3.4 m) lanes in each direction with 8-foot (2.4 m) shoulders and 2-foot (0.61 m) inside shoulders. The traffic circles at each end of the bridge were replaced with signalized intersections. Also, new roadway and elevated structures were constructed.

Four cameras were installed to view the approaches and ramps construction[12] – two on the East Bank of Jefferson Parish and two on the West Bank of Jefferson Parish.

On February 5, 2013, Louisiana Department of Transportation and Development Secretary Sherri LeBas announced that the bridge would be fully open to drivers on June 16, 2013.

Incidents edit

  • On April 27, 2015, a severe storm knocked several double stack cars off the track as a train crossed the Huey P. Long Bridge, with no injuries reported. The accident was captured by a WGNO News Team dashcam.[13]

See also edit

References edit

  1. ^ Betsy Swanson (2003). Historic Jefferson Parish: From Shore to Shore. Pelican Publishing. p. 100.
  2. ^ Andrea Shaw (June 13, 2013), $1.2 billion Huey P. Long Bridge widening to end steering-wheel death grip, Nola, retrieved August 7, 2014
  3. ^ Nguyên, Trang (August 2, 2014). . Trẻ Weekly Magazine (in Vietnamese). Garland, Texas. Archived from the original on November 18, 2018. Retrieved August 23, 2018.
  4. ^ The bridge is also known by local Vietnamese Americans as the Huỳnh Phi Long bridge, a phono-semantic matching of Huey P. Long's name in the style of a Vietnamese name.[3]
  5. ^ Marking, Tonja Koob; Snape, Jennifer (2013). Huey P. Long Bridge. Images of America. Charleston, South Carolina: Acadia Publishing. p. 11. ISBN 9781439643457.
  6. ^ Frazier, Ian (June 2, 2014). "Streetscape: Do Not Cross". The New Yorker. p. 26.
  7. ^ . www.ctlgroup.com. Archived from the original on May 14, 2018. Retrieved February 16, 2019.
  8. ^ US0090 over MISSISSIPPI RIVER, BridgeReports.com National Bridge Inventory Data.
  9. ^ "US-90 Huey P. Long Bridge, New Orleans, LA".
  10. ^ "Huey P. Long Bridge". American Society of Civil Engineers. Retrieved January 29, 2022.
  11. ^ . Archived from the original on June 18, 2012. Retrieved June 29, 2012.
  12. ^ approaches and ramps construction
  13. ^ Carlie Kollath Wells (April 27, 2015). "Train cars blown off tracks on Huey P. Long Bridge, FOX 8 reports". The Times-Picayune.

External links edit

Original construction edit

  • Mississippi River Bridge at New Orleans, Louisiana – Final Report to the Public Belt Railroad Commission of the City of New Orleans (1941)

2006 road widening project edit

  • , Louisiana DOTD (June 2007) (archived copy).
  • "Huey Long Bridge - Full 3D" on YouTube, HNTB, August 9, 2011. Seven-minute animation of erection of trusses widening river spans to enlarge roadway.
  • "Crossing the Huey P. Long Bridge on Amtrak's Sunset Limited" on YouTube, May 11, 2012. Seventeen-minute-long video taken from the westbound Sunset Limited as it climbs the east bank viaduct, crosses the truss spans as construction continues on the new road lanes while old 18-foot (5.5 m) carriageways are still in use, and then descends the west bank viaduct to its landing.
  • "Crossing Huey Long" on YouTube, April 11, 2016. Fifteen-minute-long video very similar to 2012 video linked immediately above, showing completed highway lanes.

General edit

  • Historic American Engineering Record (HAER) No. LA-17, "Huey P. Long Bridge, Spanning Mississippi River, Jefferson, Jefferson Parish, LA", 213 photos, 28 measured drawings, 30 data pages, 52 photo caption pages
  • Huey P. Long Bridge at Structurae

huey, long, bridge, jefferson, parish, this, article, about, bridge, jefferson, parish, louisiana, second, huey, long, bridge, baton, rouge, louisiana, this, article, needs, additional, citations, verification, please, help, improve, this, article, adding, cit. This article is about a bridge in Jefferson Parish Louisiana a second Huey P Long Bridge is in Baton Rouge Louisiana This article needs additional citations for verification Please help improve this article by adding citations to reliable sources Unsourced material may be challenged and removed Find sources Huey P Long Bridge Jefferson Parish news newspapers books scholar JSTOR January 2023 Learn how and when to remove this template message The Huey P Long Bridge 4 located in Jefferson Parish Louisiana is a cantilevered steel through truss bridge that carries a two track railroad line over the Mississippi River at mile 106 1 with three lanes of US 90 on each side of the central tracks It is several kilometers upriver from the city of New Orleans The East Bank entrance is at Elmwood Louisiana and the West Bank at Bridge City Huey P Long BridgeThe Huey Long Bridge in 2007 when widening work had just begun Coordinates29 56 39 N 90 10 08 W 29 94417 N 90 16889 W 29 94417 90 16889Carries6 lanes of US 902 tracks of the NOPBCrossesMississippi RiverLocaleJefferson Parish LouisianaMaintained byNew Orleans Public Belt RailroadID number022600060100001CharacteristicsDesignCantilever truss bridgeTotal length8 076 feet 2 462 m road 22 996 feet 7 009 m rail Longest span790 feet 241 m Clearance below153 feet 47 m HistoryConstruction cost 13 4 million 1 2 equivalent to 226 million in 2022 dollars OpenedDecember 1935 widened June 2013 StatisticsDaily traffic43 000 2008 LocationOpened in December 1935 the bridge was named for the late Governor Huey P Long who was assassinated on September 8 of that year The bridge was the first Mississippi River span built in Louisiana and the 29th along the length of the river It was designed by Polish American engineer Ralph Modjeski and is designated as a National Historic Civil Engineering Landmark by the American Society of Civil Engineers 5 On June 16 2013 a 1 2 billion widening project by the Louisiana Department of Transportation and Development was completed and opened to motorists The bridge now consists of three 11 foot 3 4 m lanes in each direction with inside and outside shoulders Prior to the expansion there were two 9 foot 2 7 m lanes in each direction with no shoulders In both cases the road lanes flanked the twin railroad tracks contained within the truss in 2014 a writer at The New Yorker described the bridge as a structure so vaulting and high that it seems to extend from one white towering Gulf Coast cloud to the next 6 Contents 1 Structure 2 History 3 Expansion 3 1 Project details 4 Incidents 5 See also 6 References 7 External links 7 1 Original construction 7 2 2006 road widening project 7 3 GeneralStructure edit nbsp USS New Orleans passes under the bridge March 2007The widest clear span is 790 feet 240 m long while each of the three additional spans are 530 feet 160 m long making the total river crossing about 2 400 feet 730 m long 7 There are three navigation channels below the bridge the widest being 750 feet 230 m The vertical clearance below the structure is 152 9 feet 46 6 m 8 The distinctive rail structure is 22 996 feet 7 009 m long and extends as rail viaducts well into the city on both sides of the river from the central spans It has sometimes been described as the longest rail bridge in the US but the nearby Norfolk Southern Lake Pontchartrain Bridge at 5 8 miles 9 3 km is considerably longer The highway structure is 8 076 feet 2 462 m long with steep grades on both sides As originally constructed each roadway deck was 18 feet 5 5 m wide with two 9 foot 2 7 m lanes but because of the railroad component it is unusually flat Normally bridges its height have a hump but this bridge was designed flat to facilitate rail traffic 9 The bridge is a favorite railfan location It is owned by the New Orleans Public Belt Railroad which is owned by the City of New Orleans and managed by the Public Belt Railroad Commission The bridge was hated by many drivers in the New Orleans area due to the narrow 9 foot wide 2 7 m lanes without shoulders before it was widened Additionally where the East Bank approach met the superstructure of the bridge the two vehicular roadways jogged or shifted inwards towards the bridge centerline about 1 1 2 feet 0 46 m since the through truss portion of the superstructure was 3 feet 0 91 m wider than the deck truss portion of the east approach The foundation of the bridge is also unique The land in and around New Orleans was formed by silt deposits brought down the Mississippi River The clay topsoil known colloquially as gumbo soil 10 is compressible and unsuitable for foundation loads As bedrock is around 1 000 feet 300 m below the surface making it too deep for normal bridge foundation construction the main piers are seated on a layer of fine sand 160 to 170 feet 49 to 52 m below Mean Gulf Level and rely on their size and mass to hold them in place The bridge dates from an era when large bridges mixing rail tracks and highways were common as typified by the MacArthur Bridge and McKinley Bridge in St Louis Missouri and the Harahan Bridge in Memphis Tennessee A second Huey P Long Bridge which is very similar to the design of this bridge in New Orleans before its renovation was built further upstream in 1940 in Baton Rouge Louisiana While both of the Long bridges still carry both types of traffic most of the others have been converted either to entirely rail use Harahan since 1949 MacArthur since 1981 or exclusive road use McKinley since 1978 sometimes with bicycle and or pedestrian use added McKinley in 2007 Harahan in 2016 History editThis section does not cite any sources Please help improve this section by adding citations to reliable sources Unsourced material may be challenged and removed January 2023 Learn how and when to remove this template message As early as 1892 the Southern Pacific Railway proposed a high level bridge but a depression that year prevented further work on a project that would have been an overwhelming challenge for the engineers of the time due to soil conditions and extremely high clearances for river navigation With the development of the Public Belt Railroad interest in a river rail crossing grew and led to passage of a constitutional amendment in 1916 granting the city exclusive power to build and operate a crossing Three general ideas emerged from the planning process a low level drawbridge a tunnel and a high level bridge The tunnel idea died first because it would have provided limited capacity and the War Department after years of wrangling ultimately rejected the idea of a drawbridge as too problematic for such a significant concentration of vital transportation infrastructure Work on the design of the bridge began in earnest in 1925 by the engineering firm of Modjeski and Masters Some pilings were actually driven that year to prevent expiration of congressional authority and provide further information for the design As the magnitude of the project became apparent and projected costs ballooned financing difficulties compounded by the Great Depression delayed the project Finally on November 5 1932 the bonds of the Public Belt Railroad Commission were guaranteed by a complex agreement between the Southern Pacific Railroad the City of New Orleans and the State of Louisiana Principal construction contracts were signed on December 30 1932 and work formally started the following day Construction of the bridge proceeded smoothly over a three year period with only minor interruptions due to high water and a one month strike in September 1933 Expansion editThe Huey P Long Bridge Widening Project is a TIMED Transportation Infrastructure Model for Economic Development Program project The TIMED Program was created by Act 16 of the 1989 Louisiana Legislature was voted for by the people and is the single largest transportation program in state history The Program is designed to enhance economic development in Louisiana through an investment in transportation projects The 1 2 billion widening project started in April 2006 and is the first change to the structure since it opened in 1935 The project expanded the highway on each side of the structure from two 9 foot 2 7 m lanes to three 11 foot 3 4 m lanes with a 2 foot 0 61 m inside shoulder and an 8 foot 2 4 m outside shoulder It also included new signalized intersections to replace the traffic circles at Jefferson Highway and at Bridge City Avenue both in Jefferson Parish Louisiana Project details edit This seven year long four phase project was completed in 2013 The timeline of the project was as follows Phase I Main support widening piers In this phase completed in May 2009 four river piers and one land pier were widened to support the additional lanes Reinforcing framework and concrete filled the void sections of the piers to strengthen them In addition w shaped metal bridge struts were anchored to the upper part of each pier to support the additional new trusses and the existing truss Phase II Railroad modifications In October 2006 work to relocate five selected railroad supports was done to facilitate the construction of the new approaches This phase was completed in June 2008 Phase III Main bridge widening truss Completed in 2012 this phase widened the existing truss on either side to accommodate new travel lanes and shoulders The bridge which is composed of four spans was erected one span at a time In November 2009 construction of the West Bank Anchor Span began by using the stick built method meaning each element of the span was individually placed In order to minimize the use of falsework and river closures in the navigation or auxiliary channels the three remaining spans were done through the span by span method This method involved large barges transporting a pre assembled span section positioning it under the bridge and lifting it into position using strand jacks Temporary stability frames made up of floorbeams and towers were used to support each span section during the lifting process This phase was completed on April 29 2012 when traffic was shifted from the original lanes two 9 foot 2 7 m lanes in each direction cantilevered on each side of the original truss to two temporary lanes in each direction on the widened portion of the truss 11 Phase IV New approaches construction During this phase of the project the two temporary lanes were widened to three 11 foot 3 4 m lanes in each direction with 8 foot 2 4 m shoulders and 2 foot 0 61 m inside shoulders The traffic circles at each end of the bridge were replaced with signalized intersections Also new roadway and elevated structures were constructed Four cameras were installed to view the approaches and ramps construction 12 two on the East Bank of Jefferson Parish and two on the West Bank of Jefferson Parish On February 5 2013 Louisiana Department of Transportation and Development Secretary Sherri LeBas announced that the bridge would be fully open to drivers on June 16 2013 Incidents editOn April 27 2015 a severe storm knocked several double stack cars off the track as a train crossed the Huey P Long Bridge with no injuries reported The accident was captured by a WGNO News Team dashcam 13 See also edit nbsp Transport portal nbsp Engineering portal nbsp United States portal List of bridges documented by the Historic American Engineering Record in Louisiana List of bridges in the United States List of crossings of the Lower Mississippi River List of longest bridges Huey P Long Bridge Baton Rouge References edit Betsy Swanson 2003 Historic Jefferson Parish From Shore to Shore Pelican Publishing p 100 Andrea Shaw June 13 2013 1 2 billion Huey P Long Bridge widening to end steering wheel death grip Nola retrieved August 7 2014 Nguyen Trang August 2 2014 Ten đường thanh phố Trẻ Weekly Magazine in Vietnamese Garland Texas Archived from the original on November 18 2018 Retrieved August 23 2018 The bridge is also known by local Vietnamese Americans as the Huỳnh Phi Long bridge a phono semantic matching of Huey P Long s name in the style of a Vietnamese name 3 Marking Tonja Koob Snape Jennifer 2013 Huey P Long Bridge Images of America Charleston South Carolina Acadia Publishing p 11 ISBN 9781439643457 Frazier Ian June 2 2014 Streetscape Do Not Cross The New Yorker p 26 Largest Railroad Bridge Structural Health Monitoring System CTL Grp www ctlgroup com Archived from the original on May 14 2018 Retrieved February 16 2019 US0090 over MISSISSIPPI RIVER BridgeReports com National Bridge Inventory Data US 90 Huey P Long Bridge New Orleans LA Huey P Long Bridge American Society of Civil Engineers Retrieved January 29 2022 East Bank and West Bank Approaches amp Ramps Archived from the original on June 18 2012 Retrieved June 29 2012 approaches and ramps construction Carlie Kollath Wells April 27 2015 Train cars blown off tracks on Huey P Long Bridge FOX 8 reports The Times Picayune External links edit nbsp Wikimedia Commons has media related to Huey P Long Bridge Jefferson Parish Louisiana Original construction edit Mississippi River Bridge at New Orleans Louisiana Final Report to the Public Belt Railroad Commission of the City of New Orleans 1941 2006 road widening project edit Huey P Long Bridge Widening Project Louisiana DOTD June 2007 archived copy Huey Long Bridge Full 3D on YouTube HNTB August 9 2011 Seven minute animation of erection of trusses widening river spans to enlarge roadway Crossing the Huey P Long Bridge on Amtrak s Sunset Limited on YouTube May 11 2012 Seventeen minute long video taken from the westbound Sunset Limited as it climbs the east bank viaduct crosses the truss spans as construction continues on the new road lanes while old 18 foot 5 5 m carriageways are still in use and then descends the west bank viaduct to its landing Crossing Huey Long on YouTube April 11 2016 Fifteen minute long video very similar to 2012 video linked immediately above showing completed highway lanes General edit Historic American Engineering Record HAER No LA 17 Huey P Long Bridge Spanning Mississippi River Jefferson Jefferson Parish LA 213 photos 28 measured drawings 30 data pages 52 photo caption pages Huey P Long Bridge at Structurae Retrieved from https en wikipedia org w index php title Huey P Long Bridge Jefferson Parish amp oldid 1192457647, wikipedia, wiki, book, books, library,