Dagenham wind turbines

The Dagenham wind turbines are two 85-metre (279 ft) high Enercon E-66 and one E-82[1] wind turbines located on the Dagenham estate of the Ford Motor Company in East London, England.[2] The first two turbines were completed in April 2004 and the third was installed in 2011.[3] They are landmarks of the skyline and the first wind farm to be built in London.[4]

Dagenham Wind Farm
CountryEngland
LocationDagenham, London
Coordinates51°31′19″N 0°9′4″E / 51.52194°N 0.15111°E / 51.52194; 0.15111
Commission date2004
Owner(s)Ford Motor Company
Power generation
Units operational3 Enercon turbines
Nameplate capacity5.9 MW

Planning and building edit

One turbine is located in the London Borough of Barking and Dagenham, (Turbine 1)[5] the second in the Hornchurch Marshes area of the London Borough of Havering (Turbine 2).[5] Planning consent was received from both boroughs.[6] The Mayor of London gave approval for the project in August 2003.[7]

The turbines were constructed by the green energy company Ecotricity.[2] Planning consent was also given for a third 65-metre (213 ft) high turbine (Turbine 3)[5] in Havering, with a viewing platform which was not constructed.[6][7] The planned operating date for the third wind turbine was by the first quarter of 2009,[1] and it was eventually installed in 2011.[3]

Specifications edit

The turbines are located 10 miles (16 km) east of the City of London at OS grid reference TQ492824 and TQ502818. They are 85 metres (279 ft) high to the hub, have a rotor diameter of 70 metres (230 ft) and a combined capacity of 5.9 MW. The total height to the top of the rotors is 120 metres (390 ft).[5]

Location edit


Gallery edit

References edit

  1. ^ a b "Third Turbine To Support Ford Plant". 24 April 2008. Retrieved 8 December 2008.
  2. ^ a b . Archived from the original on 1 March 2003.
  3. ^ a b . 15 August 2011. Archived from the original on 12 May 2012.
  4. ^ (PDF). September 2004. Archived from the original (PDF) on 30 September 2007.
  5. ^ a b c d . Greater London Authority. 4 June 2003. Archived from the original on 30 September 2007.
  6. ^ a b "Huge wind turbines win approval". BBC News. 27 August 2003.
  7. ^ a b . Archived from the original on 30 September 2007.

dagenham, wind, turbines, metre, high, enercon, wind, turbines, located, dagenham, estate, ford, motor, company, east, london, england, first, turbines, were, completed, april, 2004, third, installed, 2011, they, landmarks, skyline, first, wind, farm, built, l. The Dagenham wind turbines are two 85 metre 279 ft high Enercon E 66 and one E 82 1 wind turbines located on the Dagenham estate of the Ford Motor Company in East London England 2 The first two turbines were completed in April 2004 and the third was installed in 2011 3 They are landmarks of the skyline and the first wind farm to be built in London 4 Dagenham Wind FarmCountryEnglandLocationDagenham LondonCoordinates51 31 19 N 0 9 4 E 51 52194 N 0 15111 E 51 52194 0 15111Commission date2004Owner s Ford Motor CompanyPower generationUnits operational3 Enercon turbinesNameplate capacity5 9 MW edit on Wikidata Contents 1 Planning and building 2 Specifications 3 Location 4 Gallery 5 ReferencesPlanning and building editOne turbine is located in the London Borough of Barking and Dagenham Turbine 1 5 the second in the Hornchurch Marshes area of the London Borough of Havering Turbine 2 5 Planning consent was received from both boroughs 6 The Mayor of London gave approval for the project in August 2003 7 The turbines were constructed by the green energy company Ecotricity 2 Planning consent was also given for a third 65 metre 213 ft high turbine Turbine 3 5 in Havering with a viewing platform which was not constructed 6 7 The planned operating date for the third wind turbine was by the first quarter of 2009 1 and it was eventually installed in 2011 3 Specifications editThe turbines are located 10 miles 16 km east of the City of London at OS grid reference TQ492824 and TQ502818 They are 85 metres 279 ft high to the hub have a rotor diameter of 70 metres 230 ft and a combined capacity of 5 9 MW The total height to the top of the rotors is 120 metres 390 ft 5 Location editMap all coordinates using OpenStreetMap Download coordinates as KML GPX all coordinates GPX primary coordinates GPX secondary coordinates Point Coordinates links to map amp photo sources Notes Turbine 1 51 31 19 N 0 09 04 E 51 5220 N 0 1510 E 51 5220 0 1510 Turbine 1 1 8 MW Turbine 2 51 30 58 N 0 09 53 E 51 5160 N 0 1648 E 51 5160 0 1648 Turbine 2 1 8 MW Turbine 3 51 30 45 N 0 09 56 E 51 5125 N 0 1656 E 51 5125 0 1656 Turbine 3 2 3 MWGallery edit nbsp Turbine 2 nbsp Turbine 1 and several structures of the Ford plant nbsp Beam valley and turbine 2 nbsp A Ford Mondeo before one of the turbinesReferences edit a b Third Turbine To Support Ford Plant 24 April 2008 Retrieved 8 December 2008 a b London s first wind park at Ford Dagenham Archived from the original on 1 March 2003 a b Ford Dagenham s Third Wind Turbine Turns Up More Green Power 15 August 2011 Archived from the original on 12 May 2012 Thames Gateway London Partnership PDF September 2004 Archived from the original PDF on 30 September 2007 a b c d Wind Turbines Ford Estate Dagenham planning application Greater London Authority 4 June 2003 Archived from the original on 30 September 2007 a b Huge wind turbines win approval BBC News 27 August 2003 a b The Mayor s planning decisions meeting date 04 June 2003 Archived from the original on 30 September 2007 nbsp England portal nbsp Weather portal nbsp Renewable energy portal Retrieved from https en wikipedia org w index php title Dagenham wind turbines amp oldid 1147286634, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.