The Burbo Bank Offshore Wind Farm is a 348 MW offshore wind farm located on the Burbo Flats in Liverpool Bay on the west coast of the UK in the Irish Sea. It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017.

Burbo Bank Offshore Wind Farm
Country
  • United Kingdom
LocationBurbo Flats in Liverpool Bay at the entrance to the River Mersey, Merseyside
Coordinates53°29′00″N 3°10′00″W / 53.4833°N 3.1667°W / 53.4833; -3.1667
StatusOperational
Commission date
  • 2007
Owner(s)
Wind farm
Type
Max. water depth0.5 to 13 m (1 ft 8 in to 42 ft 8 in)
Rotor diameter
  • 107 m (351 ft)
Power generation
Units operational25 × 3.6 MW
32 × 8 MW
Make and modelSiemens Gamesa SWT-3.6-107 (25)
Vestas V164-8.0MW (32)
Nameplate capacity
  • 348 MW
Capacity factor~30%
External links
CommonsRelated media on Commons
Wind farm layout

The wind farm was developed in the 2000s by SeaScape Energy, which was acquired by DONG Energy (now Ørsted) in 2005. A 25 turbine installation using Siemens Wind Power 3.6 MW turbines was constructed from 2005, and officially opened in 2007. A further 32 8 MW turbines were constructed in 2016–17.

Initial Construction edit

In September 2002 SeaScape Energy ( Zilkha Renewable Energy, enXco A/S, Wind Prospect Ltd. joint venture.[1]) submitted an application to develop a Round 1 offshore wind farm site.[2] The site, located on Burbo Flats in Liverpool bay (~7 km northwest of Wirral and ~6 km west of the Sefton coastline) was selected due to shallow water depths (0.5 to 8m at low tide), high wind speeds ~7 m/s (23 ft/s), and a generally favourable location including proximity to an electrical grid connection. Initial expectations were for a 30 × 3 MW turbine wind farm, with monopile foundations on a site of approximately 10 km2 (3.9 sq mi). An electrical connection to the mainland grid was to be made by a seabed cable running southeast to Wirral, followed by a ~3.5 km underground cable to a substation at Wallasey.[3] SeaScape received a capital grant of £10 million in 2003 to aid development of the project.[4]

In 2003 EDF subsidiary enXco bought the interests of Wind Prospect in the project,[5] the project became a joint venture between Elsam and EDF Energies Nouvelles in 2004 with Elsam taking 50% of the projecty.[6] In September 2005 Siemens Wind Power was selected as the turbine supplier, with 25 3.6 MW turbines ordered at a cost of over €90 million.[7][8] In December 2005 Dong Energy (now Ørsted) became sole owner of the project.[9]

 
The logo of Orsted who owns the wind farm.

Construction began in June 2006.[2] Contractor for the foundation installation was MT Højgaard:[10] the foundation design was by Ramboll,[11] Smulders supplied the WTG foundations,[12] turbine towers by Bladt Industries,[13] monopiles and transition pieces were from Sif;[14] piling was done by Menck,[15] with Mammoet Van Oord supplying lifting barge platform Jumping Jack.[2][16][17]

The contractor for the substation was EDF Energy Contracting, cable installation was by McNicholas Construction Services Ltd. (onshore) and Submarine Cable & Pipe (offshore), with cables supplied by ABB Group.[18] Inter turbine and grid connection to the substation was at 33 kV, with voltage step up to 132 kV at the substation for grid connection.[19]

The facility began generating power in July 2007,[2][20] and the wind farm was officially inaugurated on 18 October 2007,[21] and the facility was commercially operational by the end of 2007;[18] the capital cost of developing the wind farm was €181 million.[22] Its levelised cost has been estimated as £87/MWh.[23]

Between 2008 and 2010, the capacity factor was between 32 and 35%.[24] In 2009 the whole wind farm was put out of action for 4 weeks due to a failure in the underground electrical cable connecting to the National Grid.[25] During summer 2010 Siemens decided to change the blade bearings on all 25 turbines as a pre-emptive measure after corrosion was found in blade bearings found on other sites.[26]

At the end of the windfarm's operational life (25 years) the wind farm will be decommissioned.[27]

Extension edit

Planning, funding and design edit

In 2009 the Crown Estate announced that wind farm operators could apply for extensions to their Round 1 or Round 2 offshore wind farms; DONG Energy identified Burbo Bank as a potential site and began consultation on a ~90 km2 (35 sq mi) extension westwards of the original wind farm. Between 2009 and 2010 the area of the site was reduced to the north increase clearance from the shipping lanes to the Port of Liverpool; to the south and to the west, reducing potential impact on recreational sailing activities and on certain species of sea bird, and due to potential conflicts with ship anchoring sites; also reducing the visual impact from land. In April 2010 the Crown Estate awarded an area of 40 km2 (15 sq mi) for lease.[28]

Water depths in the area are between 6 and 13 metres (20 and 43 ft).[29] The sea bed consisted primarily of sand.[30] The underlying geology is sand overlaying clay overlaying mudstone. Samples within the turbine area showed sand followed by clay down to around 30m before weak mudstone was found.[31]

The initial cable export route and grid connection identified was one making landfall near to the existing Burbo Bank land connection, and connected to a 275 kV substation in Birkenhead; subsequently a potential grid connection at the 400 kV Deeside substation (near Deeside Power Station, Wales) was identified; and later a connection with landfall at Ffrith Beach, (nr. Prestatyn, Wales) to an extension of the new Bodelwyddan 400 kV substation under construction for the Gwynt y Môr Offshore Wind Farm. In 2011 the developer reached an agreement with the National Grid to use to a connection near the Bodelwyddan substation.[32]

The planned export cable route crossed a number of pre-existing cables and pipelines: a set of pipelines related to the Liverpool Bay oil and gas field, connecting the Douglas Complex to landfall were crossed in the Mid-Hoyle channel[33] the export cable route also ran close to the North Hoyle Offshore Wind Farm export cable;[34] and crossed the 500 MW East–West Interconnector, as well as the planned route of the 2000 MW Western HVDC Link.[35]

Initial expectations were for construction to start in early 2015, and be complete by early 2017, subject to final specifications;[36] neither foundation nor turbine type was specified,[37] an offshore substation to step up the inter turbine voltage (either 33 or 66 kV) to an export voltage of either 132 or 275 kV, connection to the National Grid would be made at 400 kV, stepped up at an onshore substation at Bodelwyddan.[38]

The wind farm extension received contract for difference renewable energy subsidy funding from the UK government in April 2014,[39] with a strike price of £150 per MWh (2012 prices).[40] DONG made the decision to proceed with construction of the wind farm in December 2014.[41]

DONG Energy (now Ørsted) sold half of the wind farm extension to KIRKBI A/S (Lego holding company) and Danish pension fund PKA for £660 million in February 2016.[42]

 
Svanen, lifting ship, Burbo Banks Offshore Windfarm Extension

Construction edit

 
Turbines viewed from the shore

In early 2014, DONG Energy announced that the Vestas' V164 8.0 MW turbine was the preferred model for the development,[43] and made preliminary agreements to buy 32 units in August 2014.[44] The order for 32 turbines was confirmed in December 2014, the first series production of the type.[45] The nacelles are to be produced at the former Odense Steel Shipyard, while the blades are made at Vestas' Isle of Wight facilities. Assembly will take place in Belfast.[46]

In August 2014 ABB was awarded the contract to supply export cables.[47] Suppliers for inter array cabling was Nexans;[48] DONG Energy having agreed to a long-term supply arrangement for inter array cabling with Nexans in August 2014.[49]

In January 2015 RXPE (Rongxin Power Engineering) was awarded the design and build contract for the Burbo 2 extension Dynamic Reactive Compensation electrical equipment (STATCOM);[48] and Bladt Industries and EEW obtained the contract to construct wind turbine foundations and structures, with transition pieces to be manufactured by Bladt/EEW jv Offshore Structures (Britain) Ltd. (former TAG Energy Solutions plant in Billingham, UK), and by Bladt at Aalborg (Denmark) with monopiles made at EEW's factory in Rostock (Germany).[50]

In April 2015 A2SEA was contracted to for turbine installations,[51][52][53] and Jan De Nul contracted to install the offshore export cable.[54] In June 2015 Van Oord were contracted for foundation installation.[55][56] In October 2015 DONG Energy's two 200 tonne transformers were delivered by Collett & Sons Ltd[57] to the onshore substation via 550 Tonne capacity girder bridge. In early 2016 DONG Energy acquired a lease on Cammell Laird's yard in Birkenhead to be used as a base during the construction of the wind farm.[58]

The first 8MW turbine was installed in September 2016.[59] The wind farm extension was commissioned in April 2017.[60] Its levelised cost has been estimated at £147/MWh.[61]

After around 20–25 years of operation the wind farm would be expected to be decommissioned, including removal off all offshore components above seabed level.[62]

See also edit

References edit

  1. ^ Non-Technical Summary (SeaScape Energy, 2002) p. 2
  2. ^ a b c d Burbo Bank 1 Offshore Wind Farm (Lorc) Timeline & Track records
  3. ^ Non-Technical Summary (SeaScape Energy, 2002) pp. 2–4
  4. ^ "More offshore plant go ahead", windpowermonthly.com, 1 December 2003
  5. ^ "British consents for four in North Sea", windpowermonthly.com, 1 November 2003, Enxco - a subsidiary of French energy company EdF, bought out the interests of small developer Wind Prospect in their joint development at Burbo Bank
  6. ^ "Nuclear utility with a wind portfolio", windpowermonthly.com, 1 September 2005, EDF Energies Nouvelles' offshore ambitions are closer to fruition in Britain, where work should start next year on the 90 MW Burbo Offshore plant in Liverpool Bay. The project is being developed by Seascape Energy Ltd, owned jointly by EDF Energies Nouvelles and Danish electricity company Elsam, which bought a 50% stake of the project in 2004
  7. ^ "Elsam og EDF Energie Nouvelle, køber offshore møller hos Siemens til engelsk projekt" (PDF), Press release (in Danish), Elsam, 21 September 2005
  8. ^ "Siemens' first turbine order for UK waters", windpowermonthly.com, 1 October 2005
  9. ^ Burbo Bank (4C Offshore) Developers/Owners/Operators
  10. ^ , mth.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  11. ^ "Burbo Bank offshore wind farm", ramboll.co.uk, retrieved 24 April 2014
  12. ^ , smulders-hoboken.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  13. ^ , stateofgreen.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  14. ^ (PDF), Sif, archived from the original (PDF) on 24 April 2014, retrieved 23 April 2014
  15. ^ , menck.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  16. ^ de Vries, Eize (1 May 2007), North Sea construction: Installing monopiles for the Dutch Q7 offshore wind farm
  17. ^ Verrinder, James (1 December 2006), , International Cranes & Specialised Transport, archived from the original on 24 April 2014
  18. ^ a b Vestergaard 2007, p. 5.
  19. ^ Burbo Offshore Wind Farm, River Mersey, Liverpool Bay, United Kingdom (www.renewable-technology.com)
  20. ^ Vestergaard 2007, p. 6.
  21. ^ "Inauguration of DONG Energy's Burbo Bank offshore wind farm" (Press release). DONG Energy. 18 October 2007. from the original on 7 April 2008.
  22. ^ Kaiser, Mark J.; Snyder, Brian (2012), Offshore Wind Energy Cost Modeling: Installation and Decommissioning, Springer, Table 8.1, p.138
  23. ^ Aldersey-Williams, John (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT". Energy Policy. 128: 25–35. doi:10.1016/j.enpol.2018.12.044. hdl:10059/3298. S2CID 158158724.
  24. ^ UK Renewable Energy Data - Monthly Generation Statistics, April 2002 – March 2010 (PDF), Renewable Energy Foundation, August 2010, pp. 95–96
  25. ^ Dunn, Justin (16 October 2009), "EXCLUSIVE: Burbo Bank wind farm off Wirral shore out of action for four weeks after cabling failure", wirralglobe.co.uk
  26. ^ Godske, Bjørn (24 August 2010), [Corrosion forces Siemens to replace bearings in Wind Turbines], Ing.dk (in Danish), archived from the original on 27 August 2010, retrieved 25 August 2010
  27. ^ Non-Technical Summary (SeaScape Energy, 2002) p. 4
  28. ^ (5.1.1.5) Site Selection and Alternatives (Dong) sec.5.3.3-5.3.14, fig.5.1, 5.2
  29. ^ EIA Scoping report 2010, §2.3, 3.2.2.1.
  30. ^ EIA Scoping report 2010, §3.2.2.2.
  31. ^ (PDF), Dong Energy, 26 July 2013, archived from the original (PDF) on 23 February 2016, retrieved 15 February 2016
  32. ^ (5.1.1.5) Site Selection and Alternatives (Dong) sec.5.3.15-5.3.30 , fig.5.3, 5.4
  33. ^ (5.1.2.23) Other Infrastructure and Licensed Activities (Dong) sec.23.6.13, fig.23.5 Oil and gas infrastructure
  34. ^ (5.1.2.23) Other Infrastructure and Licensed Activities (Dong) sec.23.6.21, fig.23.6 Telecommunication and power cables
  35. ^ (5.1.2.23) Other Infrastructure and Licensed Activities (Dong) sec.23.6.25-23.6.26, fig.23.6 Telecommunication and power cables
  36. ^ (5.1.1.6) Project Description (Dong) sec.6.3
  37. ^ (5.1.1.6) Project Description (Dong) sec.6.6, 6.7
  38. ^ (5.1.1.6) Project Description (Dong) sec.6.8.3, 6.8.23, 6.10
  39. ^ , renews.biz, 23 April 2014, archived from the original on 20 February 2016, retrieved 15 February 2016
  40. ^ State aid SA.38758 (2014/N), SA.38759 (2014/N), SA.38761 (2014/N), SA.38763 (2014/N) & SA.38812 (2014/N) – United Kingdom - Support for five Offshore Wind Farms: Walney, Dudgeon, Hornsea, Burbo Bank and Beatrice (PDF), European Commission, 23 July 2014, Table 2, pp.4-5c ; § 29
  41. ^ (Press release) (in Danish), 19 December 2014, archived from the original on 24 March 2017, retrieved 24 December 2014
  42. ^ "DONG Sells Half of Burbo Bank Extension to PKA, LEGO", offshorewind.biz, 11 February 2016
  43. ^ , breakbulk.com, 24 February 2014, archived from the original on 24 April 2014, retrieved 23 April 2014
  44. ^ Snieckus, Darius (21 August 2014), MHI Vestas 8MW gets Burbo deal
  45. ^ "Nu starter Vestas produktion af gigantisk havvindmølle", Børsen (in Danish), 22 December 2014
  46. ^ Bredsdorff, Magnus (22 December 2014), "Nu indleder Vestas serieproduktion af verdens største havmølle", Ingeniøren (in Danish)
  47. ^ "ABB's Cables for Dong's Burbo Bank Extension OWF", subseaworldnews.com, 13 August 2014
  48. ^ a b , renews.biz, 8 January 2015, archived from the original on 12 January 2015, retrieved 8 January 2015
  49. ^ "DONG Energy, Nexans Ink Offshore Wind Cable Deal (UK)", subseaworldnews.com, 27 August 2014
  50. ^ , renews.biz, 27 January 2015, archived from the original on 23 February 2016, retrieved 15 February 2016
  51. ^ "A2SEA SIGNS CONTRACT FOR BURBO BANK EXTENSION OWF", a2sea.com (press release), 24 April 2014
  52. ^ "A2SEA's 'SEA CHALLENGER' to Install Burbo Bank Extension Turbines", offshorewind.biz, 24 April 2015
  53. ^ , renews.biz, 24 April 2015, archived from the original on 23 February 2016, retrieved 15 February 2016
  54. ^ "Jan De Nul Wins Burbo Bank Extension Wires", offshorewind.biz, 21 April 2015
  55. ^ "Van Oord signs contract for Burbo Bank Extension offshore wind farm", vanoord.com (press release), 25 June 2015
  56. ^ "Van Oord to Install Burbo Bank Extension Foundations", offshorewind.biz, 24 June 2015
  57. ^ Walker, Shell. "Transforming Burbo Bank Wind Farm". Collett & Sons. Retrieved 12 February 2019.
  58. ^ DONG Energy secures construction base for latest wind farm (press release), Dong Energy, 27 January 2016
  59. ^ "First 8MW giant up at Burbo 2", renews.biz, 8 September 2016
  60. ^ "Showtime at Burbo 2". 27 April 2017.
  61. ^ Aldersey-Williams, John; Broadbent, Ian; Strachan, Peter (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT". Energy Policy. 128: 25–35. doi:10.1016/j.enpol.2018.12.044. hdl:10059/3298. S2CID 158158724.
  62. ^ (5.1.1.6) Project Description (Dong) sec.6.14

Sources edit

Burbo Bank edit

  • (PDF), Burbo Offshore Wind Farm, SeaScape Energy Ltd., vol. 1, September 2002, archived from the original (PDF) on 24 April 2014
  • Vestergaard, Søren (October 2007), Burbo Bank, DONG Energy
  • , archived from the original on 12 June 2009, retrieved 24 April 2014
  • Burbo Bank Offshore Wind Farm, Ramboll, retrieved 24 April 2014
  • "Burbo Bank 1 Offshore Wind Farm", lorc.dk, retrieved 24 April 2014
  • "Burbo Offshore Wind Farm, River Mersey, Liverpool Bay, United Kingdom", renewable-technology.com
    • , 4C Offshore, archived from the original on 26 September 2010, retrieved 24 April 2014

Burbo Bank Extension edit

  • , The Planning Inspectorate, archived from the original on 24 April 2014, retrieved 23 April 2014
    • (PDF), October 2010, archived from the original (PDF) on 23 February 2016, retrieved 15 February 2016
    • (PDF), Environmental Statement, vol. 1, archived from the original (PDF) on 24 April 2014, retrieved 23 April 2014
    • (PDF), Environmental Statement, DONG Energy Burbo Extension (UK) Ltd., vol. 2, March 2013, archived from the original (PDF) on 23 February 2016, retrieved 15 February 2016
    • (PDF), Environmental Statement, DONG Energy Burbo Extension (UK) Ltd., vol. 1, March 2013, archived from the original (PDF) on 24 April 2014, retrieved 23 April 2014

External links edit

  • , burbobank.co.uk (official website), Dong Energy, archived from the original on 24 February 2016

burbo, bank, offshore, wind, farm, offshore, wind, farm, located, burbo, flats, liverpool, west, coast, irish, consists, original, wind, farm, commissioned, 2007, extension, completed, 2017, countryunited, kingdomlocationburbo, flats, liverpool, entrance, rive. The Burbo Bank Offshore Wind Farm is a 348 MW offshore wind farm located on the Burbo Flats in Liverpool Bay on the west coast of the UK in the Irish Sea It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017 Burbo Bank Offshore Wind FarmCountryUnited KingdomLocationBurbo Flats in Liverpool Bay at the entrance to the River Mersey MerseysideCoordinates53 29 00 N 3 10 00 W 53 4833 N 3 1667 W 53 4833 3 1667StatusOperationalCommission date2007Owner s OrstedWind farmTypeOffshoreMax water depth0 5 to 13 m 1 ft 8 in to 42 ft 8 in Rotor diameter107 m 351 ft Power generationUnits operational25 3 6 MW32 8 MWMake and modelSiemens Gamesa SWT 3 6 107 25 Vestas V164 8 0MW 32 Nameplate capacity348 MWCapacity factor 30 External linksCommonsRelated media on Commons edit on Wikidata Wind farm layout The wind farm was developed in the 2000s by SeaScape Energy which was acquired by DONG Energy now Orsted in 2005 A 25 turbine installation using Siemens Wind Power 3 6 MW turbines was constructed from 2005 and officially opened in 2007 A further 32 8 MW turbines were constructed in 2016 17 Contents 1 Initial Construction 2 Extension 2 1 Planning funding and design 2 2 Construction 3 See also 4 References 4 1 Sources 4 2 Burbo Bank 4 3 Burbo Bank Extension 5 External linksInitial Construction editIn September 2002 SeaScape Energy Zilkha Renewable Energy enXco A S Wind Prospect Ltd joint venture 1 submitted an application to develop a Round 1 offshore wind farm site 2 The site located on Burbo Flats in Liverpool bay 7 km northwest of Wirral and 6 km west of the Sefton coastline was selected due to shallow water depths 0 5 to 8m at low tide high wind speeds 7 m s 23 ft s and a generally favourable location including proximity to an electrical grid connection Initial expectations were for a 30 3 MW turbine wind farm with monopile foundations on a site of approximately 10 km2 3 9 sq mi An electrical connection to the mainland grid was to be made by a seabed cable running southeast to Wirral followed by a 3 5 km underground cable to a substation at Wallasey 3 SeaScape received a capital grant of 10 million in 2003 to aid development of the project 4 In 2003 EDF subsidiary enXco bought the interests of Wind Prospect in the project 5 the project became a joint venture between Elsam and EDF Energies Nouvelles in 2004 with Elsam taking 50 of the projecty 6 In September 2005 Siemens Wind Power was selected as the turbine supplier with 25 3 6 MW turbines ordered at a cost of over 90 million 7 8 In December 2005 Dong Energy now Orsted became sole owner of the project 9 nbsp The logo of Orsted who owns the wind farm Construction began in June 2006 2 Contractor for the foundation installation was MT Hojgaard 10 the foundation design was by Ramboll 11 Smulders supplied the WTG foundations 12 turbine towers by Bladt Industries 13 monopiles and transition pieces were from Sif 14 piling was done by Menck 15 with Mammoet Van Oord supplying lifting barge platform Jumping Jack 2 16 17 The contractor for the substation was EDF Energy Contracting cable installation was by McNicholas Construction Services Ltd onshore and Submarine Cable amp Pipe offshore with cables supplied by ABB Group 18 Inter turbine and grid connection to the substation was at 33 kV with voltage step up to 132 kV at the substation for grid connection 19 The facility began generating power in July 2007 2 20 and the wind farm was officially inaugurated on 18 October 2007 21 and the facility was commercially operational by the end of 2007 18 the capital cost of developing the wind farm was 181 million 22 Its levelised cost has been estimated as 87 MWh 23 Between 2008 and 2010 the capacity factor was between 32 and 35 24 In 2009 the whole wind farm was put out of action for 4 weeks due to a failure in the underground electrical cable connecting to the National Grid 25 During summer 2010 Siemens decided to change the blade bearings on all 25 turbines as a pre emptive measure after corrosion was found in blade bearings found on other sites 26 At the end of the windfarm s operational life 25 years the wind farm will be decommissioned 27 Extension editPlanning funding and design edit In 2009 the Crown Estate announced that wind farm operators could apply for extensions to their Round 1 or Round 2 offshore wind farms DONG Energy identified Burbo Bank as a potential site and began consultation on a 90 km2 35 sq mi extension westwards of the original wind farm Between 2009 and 2010 the area of the site was reduced to the north increase clearance from the shipping lanes to the Port of Liverpool to the south and to the west reducing potential impact on recreational sailing activities and on certain species of sea bird and due to potential conflicts with ship anchoring sites also reducing the visual impact from land In April 2010 the Crown Estate awarded an area of 40 km2 15 sq mi for lease 28 Water depths in the area are between 6 and 13 metres 20 and 43 ft 29 The sea bed consisted primarily of sand 30 The underlying geology is sand overlaying clay overlaying mudstone Samples within the turbine area showed sand followed by clay down to around 30m before weak mudstone was found 31 The initial cable export route and grid connection identified was one making landfall near to the existing Burbo Bank land connection and connected to a 275 kV substation in Birkenhead subsequently a potential grid connection at the 400 kV Deeside substation near Deeside Power Station Wales was identified and later a connection with landfall at Ffrith Beach nr Prestatyn Wales to an extension of the new Bodelwyddan 400 kV substation under construction for the Gwynt y Mor Offshore Wind Farm In 2011 the developer reached an agreement with the National Grid to use to a connection near the Bodelwyddan substation 32 The planned export cable route crossed a number of pre existing cables and pipelines a set of pipelines related to the Liverpool Bay oil and gas field connecting the Douglas Complex to landfall were crossed in the Mid Hoyle channel 33 the export cable route also ran close to the North Hoyle Offshore Wind Farm export cable 34 and crossed the 500 MW East West Interconnector as well as the planned route of the 2000 MW Western HVDC Link 35 Initial expectations were for construction to start in early 2015 and be complete by early 2017 subject to final specifications 36 neither foundation nor turbine type was specified 37 an offshore substation to step up the inter turbine voltage either 33 or 66 kV to an export voltage of either 132 or 275 kV connection to the National Grid would be made at 400 kV stepped up at an onshore substation at Bodelwyddan 38 The wind farm extension received contract for difference renewable energy subsidy funding from the UK government in April 2014 39 with a strike price of 150 per MWh 2012 prices 40 DONG made the decision to proceed with construction of the wind farm in December 2014 41 DONG Energy now Orsted sold half of the wind farm extension to KIRKBI A S Lego holding company and Danish pension fund PKA for 660 million in February 2016 42 nbsp Svanen lifting ship Burbo Banks Offshore Windfarm ExtensionConstruction edit nbsp Turbines viewed from the shoreIn early 2014 DONG Energy announced that the Vestas V164 8 0 MW turbine was the preferred model for the development 43 and made preliminary agreements to buy 32 units in August 2014 44 The order for 32 turbines was confirmed in December 2014 the first series production of the type 45 The nacelles are to be produced at the former Odense Steel Shipyard while the blades are made at Vestas Isle of Wight facilities Assembly will take place in Belfast 46 In August 2014 ABB was awarded the contract to supply export cables 47 Suppliers for inter array cabling was Nexans 48 DONG Energy having agreed to a long term supply arrangement for inter array cabling with Nexans in August 2014 49 In January 2015 RXPE Rongxin Power Engineering was awarded the design and build contract for the Burbo 2 extension Dynamic Reactive Compensation electrical equipment STATCOM 48 and Bladt Industries and EEW obtained the contract to construct wind turbine foundations and structures with transition pieces to be manufactured by Bladt EEW jv Offshore Structures Britain Ltd former TAG Energy Solutions plant in Billingham UK and by Bladt at Aalborg Denmark with monopiles made at EEW s factory in Rostock Germany 50 In April 2015 A2SEA was contracted to for turbine installations 51 52 53 and Jan De Nul contracted to install the offshore export cable 54 In June 2015 Van Oord were contracted for foundation installation 55 56 In October 2015 DONG Energy s two 200 tonne transformers were delivered by Collett amp Sons Ltd 57 to the onshore substation via 550 Tonne capacity girder bridge In early 2016 DONG Energy acquired a lease on Cammell Laird s yard in Birkenhead to be used as a base during the construction of the wind farm 58 The first 8MW turbine was installed in September 2016 59 The wind farm extension was commissioned in April 2017 60 Its levelised cost has been estimated at 147 MWh 61 After around 20 25 years of operation the wind farm would be expected to be decommissioned including removal off all offshore components above seabed level 62 See also edit nbsp England portal nbsp Weather portal nbsp Renewable energy portal List of offshore wind farms List of offshore wind farms in the United Kingdom List of offshore wind farms in the Irish SeaReferences edit Non Technical Summary SeaScape Energy 2002 p 2 a b c d Burbo Bank 1 Offshore Wind Farm Lorc Timeline amp Track records Non Technical Summary SeaScape Energy 2002 pp 2 4 More offshore plant go ahead windpowermonthly com 1 December 2003 British consents for four in North Sea windpowermonthly com 1 November 2003 Enxco a subsidiary of French energy company EdF bought out the interests of small developer Wind Prospect in their joint development at Burbo Bank Nuclear utility with a wind portfolio windpowermonthly com 1 September 2005 EDF Energies Nouvelles offshore ambitions are closer to fruition in Britain where work should start next year on the 90 MW Burbo Offshore plant in Liverpool Bay The project is being developed by Seascape Energy Ltd owned jointly by EDF Energies Nouvelles and Danish electricity company Elsam which bought a 50 stake of the project in 2004 Elsam og EDF Energie Nouvelle kober offshore moller hos Siemens til engelsk projekt PDF Press release in Danish Elsam 21 September 2005 Siemens first turbine order for UK waters windpowermonthly com 1 October 2005 Burbo Bank 4C Offshore Developers Owners Operators Burbo Bank Offshore Wind Farm mth com archived from the original on 24 April 2014 retrieved 24 April 2014 Burbo Bank offshore wind farm ramboll co uk retrieved 24 April 2014 Burbo Project smulders hoboken com archived from the original on 24 April 2014 retrieved 24 April 2014 Arklow Bank amp Burbo Bank Offshore Windfarms Towers stateofgreen com archived from the original on 24 April 2014 retrieved 24 April 2014 References Offshore Wind PDF Sif archived from the original PDF on 24 April 2014 retrieved 23 April 2014 Reference Projects Burbo Bank menck com archived from the original on 24 April 2014 retrieved 24 April 2014 de Vries Eize 1 May 2007 North Sea construction Installing monopiles for the Dutch Q7 offshore wind farm Verrinder James 1 December 2006 Wind it on International Cranes amp Specialised Transport archived from the original on 24 April 2014 a b Vestergaard 2007 p 5 Burbo Offshore Wind Farm River Mersey Liverpool Bay United Kingdom www renewable technology com Vestergaard 2007 p 6 Inauguration of DONG Energy s Burbo Bank offshore wind farm Press release DONG Energy 18 October 2007 Archived from the original on 7 April 2008 Kaiser Mark J Snyder Brian 2012 Offshore Wind Energy Cost Modeling Installation and Decommissioning Springer Table 8 1 p 138 Aldersey Williams John 2019 Better estimates of LCOE from audited accounts A new methodology with examples from United Kingdom offshore wind and CCGT Energy Policy 128 25 35 doi 10 1016 j enpol 2018 12 044 hdl 10059 3298 S2CID 158158724 UK Renewable Energy Data Monthly Generation Statistics April 2002 March 2010 PDF Renewable Energy Foundation August 2010 pp 95 96 Dunn Justin 16 October 2009 EXCLUSIVE Burbo Bank wind farm off Wirral shore out of action for four weeks after cabling failure wirralglobe co uk Godske Bjorn 24 August 2010 Korrosion tvinger Siemens til skift af vingelejer i havmoller Corrosion forces Siemens to replace bearings in Wind Turbines Ing dk in Danish archived from the original on 27 August 2010 retrieved 25 August 2010 Non Technical Summary SeaScape Energy 2002 p 4 5 1 1 5 Site Selection and Alternatives Dong sec 5 3 3 5 3 14 fig 5 1 5 2 EIA Scoping report 2010 2 3 3 2 2 1 EIA Scoping report 2010 3 2 2 2 Summary of Geotechnical Investigations for the Burbo Bank Extension Project and Comparison of These to Preliminary Geophysical Survey and Interpretation PDF Dong Energy 26 July 2013 archived from the original PDF on 23 February 2016 retrieved 15 February 2016 5 1 1 5 Site Selection and Alternatives Dong sec 5 3 15 5 3 30 fig 5 3 5 4 5 1 2 23 Other Infrastructure and Licensed Activities Dong sec 23 6 13 fig 23 5 Oil and gas infrastructure 5 1 2 23 Other Infrastructure and Licensed Activities Dong sec 23 6 21 fig 23 6 Telecommunication and power cables 5 1 2 23 Other Infrastructure and Licensed Activities Dong sec 23 6 25 23 6 26 fig 23 6 Telecommunication and power cables 5 1 1 6 Project Description Dong sec 6 3 5 1 1 6 Project Description Dong sec 6 6 6 7 5 1 1 6 Project Description Dong sec 6 8 3 6 8 23 6 10 UK awards contracts for 4 5GW renews biz 23 April 2014 archived from the original on 20 February 2016 retrieved 15 February 2016 State aid SA 38758 2014 N SA 38759 2014 N SA 38761 2014 N SA 38763 2014 N amp SA 38812 2014 N United Kingdom Support for five Offshore Wind Farms Walney Dudgeon Hornsea Burbo Bank and Beatrice PDF European Commission 23 July 2014 Table 2 pp 4 5c 29 DONG Energy skal opfore Burbo Bank Extension Havmollepark i Storbritannien Press release in Danish 19 December 2014 archived from the original on 24 March 2017 retrieved 24 December 2014 DONG Sells Half of Burbo Bank Extension to PKA LEGO offshorewind biz 11 February 2016 Dong Taps Vestas for Burbo Bank Offshore Wind breakbulk com 24 February 2014 archived from the original on 24 April 2014 retrieved 23 April 2014 Snieckus Darius 21 August 2014 MHI Vestas 8MW gets Burbo deal Nu starter Vestas produktion af gigantisk havvindmolle Borsen in Danish 22 December 2014 Bredsdorff Magnus 22 December 2014 Nu indleder Vestas serieproduktion af verdens storste havmolle Ingenioren in Danish ABB s Cables for Dong s Burbo Bank Extension OWF subseaworldnews com 13 August 2014 a b Chinese land Burbo 2 electricals renews biz 8 January 2015 archived from the original on 12 January 2015 retrieved 8 January 2015 DONG Energy Nexans Ink Offshore Wind Cable Deal UK subseaworldnews com 27 August 2014 EEW Bladt win Burbo 2 foundations renews biz 27 January 2015 archived from the original on 23 February 2016 retrieved 15 February 2016 A2SEA SIGNS CONTRACT FOR BURBO BANK EXTENSION OWF a2sea com press release 24 April 2014 A2SEA s SEA CHALLENGER to Install Burbo Bank Extension Turbines offshorewind biz 24 April 2015 A2Sea to tackle Burbo 8MW giants renews biz 24 April 2015 archived from the original on 23 February 2016 retrieved 15 February 2016 Jan De Nul Wins Burbo Bank Extension Wires offshorewind biz 21 April 2015 Van Oord signs contract for Burbo Bank Extension offshore wind farm vanoord com press release 25 June 2015 Van Oord to Install Burbo Bank Extension Foundations offshorewind biz 24 June 2015 Walker Shell Transforming Burbo Bank Wind Farm Collett amp Sons Retrieved 12 February 2019 DONG Energy secures construction base for latest wind farm press release Dong Energy 27 January 2016 First 8MW giant up at Burbo 2 renews biz 8 September 2016 Showtime at Burbo 2 27 April 2017 Aldersey Williams John Broadbent Ian Strachan Peter 2019 Better estimates of LCOE from audited accounts A new methodology with examples from United Kingdom offshore wind and CCGT Energy Policy 128 25 35 doi 10 1016 j enpol 2018 12 044 hdl 10059 3298 S2CID 158158724 5 1 1 6 Project Description Dong sec 6 14 Sources edit Burbo Bank edit Non Technical Summary PDF Burbo Offshore Wind Farm SeaScape Energy Ltd vol 1 September 2002 archived from the original PDF on 24 April 2014 Vestergaard Soren October 2007 Burbo Bank DONG Energy The Burbo Bank Project archived from the original on 12 June 2009 retrieved 24 April 2014 Burbo Bank Offshore Wind Farm Ramboll retrieved 24 April 2014 Burbo Bank 1 Offshore Wind Farm lorc dk retrieved 24 April 2014 Burbo Offshore Wind Farm River Mersey Liverpool Bay United Kingdom renewable technology com Burbo Bank 4C Offshore archived from the original on 26 September 2010 retrieved 24 April 2014 Burbo Bank Extension edit Burbo Bank Extension offshore wind farm The Planning Inspectorate archived from the original on 24 April 2014 retrieved 23 April 2014 Burbo Bank Extension offshore wind farm Environmental Impact Assessment Scoping Report PDF October 2010 archived from the original PDF on 23 February 2016 retrieved 15 February 2016 Chapter 6 5 1 1 6 Project Description PDF Environmental Statement vol 1 archived from the original PDF on 24 April 2014 retrieved 23 April 2014 Chapter 23 5 1 2 23 Other Infrastructure and Licensed Activities PDF Environmental Statement DONG Energy Burbo Extension UK Ltd vol 2 March 2013 archived from the original PDF on 23 February 2016 retrieved 15 February 2016 Chapter 5 5 1 1 5 Site Selection and Alternatives PDF Environmental Statement DONG Energy Burbo Extension UK Ltd vol 1 March 2013 archived from the original PDF on 24 April 2014 retrieved 23 April 2014External links edit nbsp Wikimedia Commons has media related to Burbo Bank Offshore Wind Farm Burbo Bank Offshore Wind Farm burbobank co uk official website Dong Energy archived from the original on 24 February 2016 Retrieved from https en wikipedia org w index php title Burbo Bank Offshore Wind Farm amp oldid 1153787910, wikipedia, wiki, book, books, library,