Bangalore–Chennai Expressway

The Bangalore–Chennai Expressway, or National Expressway 7 (NE-7), is an under construction 258 km (160 mi) long, 4-lane wide[2] access-controlled expressway between the cities of Bangalore, the capital of Karnataka and Chennai, the capital of Tamil Nadu. It will run from Hoskote in Bangalore Metropolitan Region Development Authority to Sriperumbudur in Chennai Metropolitan Area. It is planned to allow vehicles to reach 120 km/h (75 mph).[3] This expressway was designated as a National Expressway on 1 January 2021.[4] The total project value is ₹ 17,930 crore.[5] It will be completed by March 2024.[6]

Bangalore – Chennai Expressway (National Expressway 7)
Route information
Maintained by National Highways Authority of India (NHAI)
Length258 km (160 mi)
ExistedMarch 2024[1]–present
Major junctions
West endHoskote, Bangalore Rural district, Karnataka (Bangalore Metropolitan Region Development Authority)
East endSriperumbudur, Kanchipuram district, Tamil Nadu (Chennai Metropolitan Area)
Location
CountryIndia
States
Districts
Towns
Highway system

Mepladi in Vellore district and Ponapanthangal in ranipet district will be major intersection points for transfers and real estate [7]


Prospects

The National Highways Development Project (NHDP) Phase-VI has been established, following expectations of the new government's involvement, and before the real estate prices begin to rise along the expressways, mainly near Ranipet -Ponnapanthangal-Arakkonam[8] (Tamil Nadu).[9]

Also Adani power and Reliance industries are planning to setup warehouses since the road connects to new parandhur airport and upcoming chennai bangalore expressways which will boost manpower jobs and also economy of local area.

SIPCOT for leather industry has been announced by Tamilnadu chief minister M.K.Stalin and Ranipet already being a hub of leather manufacturers and exporters are rushing to purchase lands to setup factories and warehouses. TATA Bachi shoes has already purchased 12 acres of land costing 30 Crores and projects have been initiated.

Also Intersection and merging point has been decided to be setup in Mangalam near banavaram and ponapanthangal since TVS brakes unit will be able to make transfers to new parandhur airport connected via this expressways

[10]

Construction

The NHAI has divided the construction work of 258 km long Bangalore–Chennai Expressway into 3 Phases with a total of 10 construction packages.[citation needed] It which will be executed simultaneously by 6 construction companies.[citation needed]

Phase-1

Sr. No Package Length in km Contractor
1. HoskoteMalur 18 Dilip Buildcon[11]
2. MalurBangarapet 27.1 Dilip Buildcon[11]
3. BangarapetBethamangala 17.5 KCC Buildcon

Phase-2

Sr. No Package Length in km Contractor
1. BethamangalaBaireddipalle 25.0 Montecarlo Construction
2. BaireddipalleBangarupalem 31.0 Apco Infratech[12]
3. BangarupalemGudipala 29.0 Dilip Buildcon

Phase-3

Sr. No Package Length in km Contractor
1. GudipalaWalajapettai 24.0 Montecarlo Construction
2. WalajapettaiArakkonam 24.5 KCC Buildcon
3. ArakkonamKanchipuram 25.5 DP Jain & Co.
4. KanchipuramSriperumbudur 32.1 Ramalingam Construction Co.

Extension

The Indian National Expressway Network was proposed by the Ministry of Road, Transport and Highways (MoRTH). The Government of India envisioned a Bangalore–Mangalore Greenfield Expressway.[13] A Mangaluru–Chennai Expressway through Bangalore has also been proposed.[14]

Status updates

  • Aug 2018: Land acquisition was announced to start soon.[15]
  • Dec 2018: ₹1,370 crores were already spent by the Government of India on pre-construction activities of this ₹17,930 crores expressway.[16]
  • Feb 2019: More than 60% of land required for 262 km expressway was now acquired. Work was announced to begin in six months. The deadline of the Expressway was set to 2023.[17]
  • Nov 2020: Acquisition of required 2,650 hectares of land was nearly done. Tenders were invited for 3 out of total 10 packages.[18]
  • Feb 2021: The expressway was later shortened to be 4 laned instead earlier planned 8 lanes.[19] Dilip Buildcon Ltd declared lowest bidder for Package 1 (Hoskote - Malur) and Package 2 (Malur - Bangarapet).
  • Sep 2021: Dilip Buildcon Ltd receives Letter of Agreement (LoA) from National Highways Authority of India (NHAI) for construction of the expressway.
  • Jan 2023: The expressway will have 8 lanes only, and will be completed by March 2024.[20]
  • Jan 2023: As of 26 January, around 15% work has been completed on the expressway.[21]

See also

References

  1. ^ Sharma, Anurakti (6 January 2023). "Bengaluru-Chennai Expressway to be completed by March 2024". Times Now. Retrieved 10 January 2023.
  2. ^ Sharma, Anurakti (6 January 2023). "Bengaluru-Chennai Expressway to be completed by March 2024". Times Now. Retrieved 10 January 2023.
  3. ^ . The Hindu. 21 October 2011. Archived from the original on 2 May 2012. Retrieved 16 August 2012.
  4. ^ Gazette notification dated 1 January 2021
  5. ^ Akram Mohammed (18 December 2018). "Expressway to reduce travel time between Bengaluru, Chennai". The New Indian Express. Retrieved 23 March 2023.
  6. ^ Sharma, Anurakti (6 January 2023). "Bengaluru-Chennai Expressway to be completed by March 2024". Times Now. Retrieved 10 January 2023.
  7. ^ "Real Estate in Bangalore & Chennai to get elevated with the upcoming Bangalore-Chennai Expressway!". www.sulekha.com. Retrieved 5 May 2023.
  8. ^ "Keezhveeranam - soul searchers - Maitreya - Dharmakshetra Real estate Project".[permanent dead link]
  9. ^ . The Hindu. 20 June 2010. Archived from the original on 24 June 2010. Retrieved 13 November 2010.
  10. ^ https://en.bharatpedia.org/wiki/Chennai_Bangalore_Industrial_Corridor#Real_Estate
  11. ^ a b "Dilip Buildcon declared L1 bidder for projects worth Rs 2,439 crores". Business Standard. 24 February 2021.
  12. ^ "Apco will build NHAI's Bangalore-Chennai Expressway segment". Construction World. 18 March 2021.
  13. ^ Project Report on Indian National Expressway Network
  14. ^ . web.archive.org. 8 July 2013. Retrieved 10 January 2023.
  15. ^ "Notice issued to get land: Notice issued to get land for highway | Chennai News - Times of India".
  16. ^ "Expressway to reduce travel time between Bengaluru, Chennai".
  17. ^ "Chennai-Bangalore Expressway work to start in six months: Nirmala Sitharaman".
  18. ^ "NHAI invites tenders for Bengaluru-Chennai Expressway".
  19. ^ "Chennai-Bengaluru expressway downgraded due to traffic, alternative road".
  20. ^ Sharma, Anurakti (6 January 2023). "Bengaluru-Chennai Expressway to be completed by March 2024". Times Now. Retrieved 10 January 2023.
  21. ^ Shivakumar, C. (26 January 2023). "Chennai-Bengaluru expressway: 14km road work complete". The New Indian Express. Retrieved 26 January 2023.

bangalore, chennai, expressway, national, expressway, under, construction, long, lane, wide, access, controlled, expressway, between, cities, bangalore, capital, karnataka, chennai, capital, tamil, nadu, will, from, hoskote, bangalore, metropolitan, region, de. The Bangalore Chennai Expressway or National Expressway 7 NE 7 is an under construction 258 km 160 mi long 4 lane wide 2 access controlled expressway between the cities of Bangalore the capital of Karnataka and Chennai the capital of Tamil Nadu It will run from Hoskote in Bangalore Metropolitan Region Development Authority to Sriperumbudur in Chennai Metropolitan Area It is planned to allow vehicles to reach 120 km h 75 mph 3 This expressway was designated as a National Expressway on 1 January 2021 4 The total project value is 17 930 crore 5 It will be completed by March 2024 6 Bangalore Chennai Expressway National Expressway 7 Route informationMaintained by National Highways Authority of India NHAI Length258 km 160 mi ExistedMarch 2024 1 presentMajor junctionsWest endHoskote Bangalore Rural district Karnataka Bangalore Metropolitan Region Development Authority East endSriperumbudur Kanchipuram district Tamil Nadu Chennai Metropolitan Area LocationCountryIndiaStatesKarnataka Andhra Pradesh Tamil NaduDistrictsBangalore Rural district Karnataka Kolar district Karnataka Chittoor district Andhra Pradesh Ranipettai district Tamil Nadu Kanchipuram district Tamil NaduTownsHoskote Bangalore Rural district Karnataka Malur Kolar district Karnataka Bangarapet Kolar district Karnataka Kolar Gold Fields Kolar district Karnataka Bethamangala Kolar district Karnataka Venkatagirikota Chittoor district Andhra Pradesh Palamaner Chittoor district Andhra Pradesh Bangarupalem Chittoor district Andhra Pradesh Chittoor Chittoor district Andhra Pradesh Ranipet Ranipettai district Tamil Nadu Walajapet Ranipettai district Tamil Nadu Arakkonam Ranipettai district Tamil Nadu Sriperumbudur Kanchipuram district Tamil NaduHighway systemRoads in IndiaExpressways National State AsianMepladi in Vellore district and Ponapanthangal in ranipet district will be major intersection points for transfers and real estate 7 Contents 1 Prospects 2 Construction 2 1 Phase 1 2 2 Phase 2 2 3 Phase 3 3 Extension 4 Status updates 5 See also 6 ReferencesProspects EditThe National Highways Development Project NHDP Phase VI has been established following expectations of the new government s involvement and before the real estate prices begin to rise along the expressways mainly near Ranipet Ponnapanthangal Arakkonam 8 Tamil Nadu 9 Also Adani power and Reliance industries are planning to setup warehouses since the road connects to new parandhur airport and upcoming chennai bangalore expressways which will boost manpower jobs and also economy of local area SIPCOT for leather industry has been announced by Tamilnadu chief minister M K Stalin and Ranipet already being a hub of leather manufacturers and exporters are rushing to purchase lands to setup factories and warehouses TATA Bachi shoes has already purchased 12 acres of land costing 30 Crores and projects have been initiated Also Intersection and merging point has been decided to be setup in Mangalam near banavaram and ponapanthangal since TVS brakes unit will be able to make transfers to new parandhur airport connected via this expressways 10 Construction EditThe NHAI has divided the construction work of 258 km long Bangalore Chennai Expressway into 3 Phases with a total of 10 construction packages citation needed It which will be executed simultaneously by 6 construction companies citation needed Phase 1 Edit Sr No Package Length in km Contractor1 Hoskote Malur 18 Dilip Buildcon 11 2 Malur Bangarapet 27 1 Dilip Buildcon 11 3 Bangarapet Bethamangala 17 5 KCC BuildconPhase 2 Edit Sr No Package Length in km Contractor1 Bethamangala Baireddipalle 25 0 Montecarlo Construction2 Baireddipalle Bangarupalem 31 0 Apco Infratech 12 3 Bangarupalem Gudipala 29 0 Dilip BuildconPhase 3 Edit Sr No Package Length in km Contractor1 Gudipala Walajapettai 24 0 Montecarlo Construction2 Walajapettai Arakkonam 24 5 KCC Buildcon3 Arakkonam Kanchipuram 25 5 DP Jain amp Co 4 Kanchipuram Sriperumbudur 32 1 Ramalingam Construction Co Extension EditThe Indian National Expressway Network was proposed by the Ministry of Road Transport and Highways MoRTH The Government of India envisioned a Bangalore Mangalore Greenfield Expressway 13 A Mangaluru Chennai Expressway through Bangalore has also been proposed 14 Status updates EditAug 2018 Land acquisition was announced to start soon 15 Dec 2018 1 370 crores were already spent by the Government of India on pre construction activities of this 17 930 crores expressway 16 Feb 2019 More than 60 of land required for 262 km expressway was now acquired Work was announced to begin in six months The deadline of the Expressway was set to 2023 17 Nov 2020 Acquisition of required 2 650 hectares of land was nearly done Tenders were invited for 3 out of total 10 packages 18 Feb 2021 The expressway was later shortened to be 4 laned instead earlier planned 8 lanes 19 Dilip Buildcon Ltd declared lowest bidder for Package 1 Hoskote Malur and Package 2 Malur Bangarapet Sep 2021 Dilip Buildcon Ltd receives Letter of Agreement LoA from National Highways Authority of India NHAI for construction of the expressway Jan 2023 The expressway will have 8 lanes only and will be completed by March 2024 20 Jan 2023 As of 26 January around 15 work has been completed on the expressway 21 See also EditBangalore Mysore Infrastructure Corridor Chittoor Thatchur Expressway Expressways in India National Highways Development Project Delhi Mumbai ExpresswayReferences Edit Sharma Anurakti 6 January 2023 Bengaluru Chennai Expressway to be completed by March 2024 Times Now Retrieved 10 January 2023 Sharma Anurakti 6 January 2023 Bengaluru Chennai Expressway to be completed by March 2024 Times Now Retrieved 10 January 2023 Project report on Chennai Expressway may get ready by March The Hindu 21 October 2011 Archived from the original on 2 May 2012 Retrieved 16 August 2012 Gazette notification dated 1 January 2021 Akram Mohammed 18 December 2018 Expressway to reduce travel time between Bengaluru Chennai The New Indian Express Retrieved 23 March 2023 Sharma Anurakti 6 January 2023 Bengaluru Chennai Expressway to be completed by March 2024 Times Now Retrieved 10 January 2023 Real Estate in Bangalore amp Chennai to get elevated with the upcoming Bangalore Chennai Expressway www sulekha com Retrieved 5 May 2023 Keezhveeranam soul searchers Maitreya Dharmakshetra Real estate Project permanent dead link Karnataka Bangalore News Chennai Expressway to be ready in three years The Hindu 20 June 2010 Archived from the original on 24 June 2010 Retrieved 13 November 2010 https en bharatpedia org wiki Chennai Bangalore Industrial Corridor Real Estate a b Dilip Buildcon declared L1 bidder for projects worth Rs 2 439 crores Business Standard 24 February 2021 Apco will build NHAI s Bangalore Chennai Expressway segment Construction World 18 March 2021 Project Report on Indian National Expressway Network Greenfield express corridor from Mangalore to Chennai on the anvil Times Of India web archive org 8 July 2013 Retrieved 10 January 2023 Notice issued to get land Notice issued to get land for highway Chennai News Times of India Expressway to reduce travel time between Bengaluru Chennai Chennai Bangalore Expressway work to start in six months Nirmala Sitharaman NHAI invites tenders for Bengaluru Chennai Expressway Chennai Bengaluru expressway downgraded due to traffic alternative road Sharma Anurakti 6 January 2023 Bengaluru Chennai Expressway to be completed by March 2024 Times Now Retrieved 10 January 2023 Shivakumar C 26 January 2023 Chennai Bengaluru expressway 14km road work complete The New Indian Express Retrieved 26 January 2023 Retrieved from https en wikipedia org w index php title Bangalore Chennai Expressway amp oldid 1153932859, wikipedia, wiki, book, books, library,