The Tuen Mun–Chek Lap Kok Link (Chinese: 屯門至赤鱲角連接路, abbreviated as TM–CLKL) is a road project in the New Territories, Hong Kong. It comprises two elements: the "Northern Connection" and the "Southern Connection". The Northern Connection comprises an undersea tunnel crossing the Urmston Road, linking Tuen Mun to the "Boundary Crossing Facilities" (BCF), an artificial peninsula connected to Hong Kong International Airport. The Southern Connection, officially named Shun Long Road (順朗路), comprises viaducts linking the BCF to North Lantau Highway on Lantau Island.

Tuen Mun–Chek Lap Kok Link
Tuen Mun–Chek Lap Kok Link under construction
Overview
Official nameShun Long Road (for the Southern Connection)
LocationNew Territories, Hong Kong
Coordinates22°18′24.6″N 113°57′52″E / 22.306833°N 113.96444°E / 22.306833; 113.96444
StatusActive
CrossesUrmston Road
StartLung Fu Road, Tuen Mun
EndChek Lap Kok, Lantau Island
Operation
OpenedShun Long Road (Southern Connection) - 24 October 2018; 5 years ago (2018-10-24)
Northern Connection (Tuen Mun-Chek Lap Kok Tunnel) - 27 December 2020; 3 years ago (2020-12-27)
OwnerHong Kong Government
TrafficAutomotive
TollNo
Technical
Length5 kilometres (3.1 mi) (sub-sea tunnel)
No. of lanes4 lanes (2 lanes per direction)
Operating speed80 kilometres per hour (50 mph)

The construction of the link has helped facilitate travel between the Northwest New Territories (Tuen Mun and Yuen Long Districts) and the Hong Kong International Airport and the Hong Kong–Zhuhai–Macau Bridge (Hong Kong Port).

Though the project lies entirely within Hong Kong territory, its construction is associated with the new Hong Kong–Zhuhai–Macau Bridge (HZMB). The estimated cost of the design, site investigation, and construction of the TM–CLKL (including associated works, like land reclamation) is about HK$46.71 billion. The Southern Connection mainline opened on 24 October 2018 to tie in with HZMB's commissioning[1] and the remaining Northern Connection to Tuen Mun opened on 27 December 2020.

History edit

 
View of the Urmston Road, with construction of the tunnel's northern landfall visible

The contract to construct the Northern Connection tunnel (No. HY/2012/08) was awarded to the Dragages-Bouygues Joint Venture on 26 July 2013. It commenced on 5 August 2013.[2] The contract to construct the southern section was awarded to Gammon Construction in June 2013.[3] The entire project opened to traffic on 27 December 2020.

Design edit

The tunnel portion is a two-lane dual carriageway approximately 5 kilometres long.[4]

Construction edit

The dual sub-sea tunnels were bored up to 55 metres below sea level using the Tuen Mun–Chek Lap Kok TBM, the world's largest tunnel boring machine.[5]

Originally scheduled for opening in 2018, completion of the link had been delayed for two years.[6][4][7] It opened to traffic on 27 December 2020.

References edit

  1. ^ "Bridge link taxi area gazetted". news.gov.hk. 2018-10-22.
  2. ^ "Introduction". Contract No. HY/2014/08: Tuen Mun - Chek Lap Kok Link Northern Connection Sub-sea Tunnel Section. Highways Department. Retrieved 8 May 2018.
  3. ^ "Gammon Bags Tuen Mun-Chek Lap Kok Link Viaduct Job". Construction Post. 20 June 2013. Retrieved 15 December 2019.
  4. ^ a b "Tuen Mun – Chek Lap Kok Link (TM-CLKL)". Highways Department. Retrieved 24 September 2022.
  5. ^ Hansford, Mark (9 May 2017). "Rise of the machines". New Civil Engineer.
  6. ^ "Tuen Mun to airport link road delayed till 2020". Radio Television Hong Kong. 17 March 2017.
  7. ^ "Contractor criticised as delays hit big Hong Kong tunnel". Global Construction Review. 22 March 2017. Retrieved 14 February 2019.

External links edit

  • Official website

tuen, chek, link, chinese, 屯門至赤鱲角連接路, abbreviated, clkl, road, project, territories, hong, kong, comprises, elements, northern, connection, southern, connection, northern, connection, comprises, undersea, tunnel, crossing, urmston, road, linking, tuen, boundar. The Tuen Mun Chek Lap Kok Link Chinese 屯門至赤鱲角連接路 abbreviated as TM CLKL is a road project in the New Territories Hong Kong It comprises two elements the Northern Connection and the Southern Connection The Northern Connection comprises an undersea tunnel crossing the Urmston Road linking Tuen Mun to the Boundary Crossing Facilities BCF an artificial peninsula connected to Hong Kong International Airport The Southern Connection officially named Shun Long Road 順朗路 comprises viaducts linking the BCF to North Lantau Highway on Lantau Island Tuen Mun Chek Lap Kok LinkTuen Mun Chek Lap Kok Link under constructionOverviewOfficial nameShun Long Road for the Southern Connection LocationNew Territories Hong KongCoordinates22 18 24 6 N 113 57 52 E 22 306833 N 113 96444 E 22 306833 113 96444StatusActiveCrossesUrmston RoadStartLung Fu Road Tuen MunEndChek Lap Kok Lantau IslandOperationOpenedShun Long Road Southern Connection 24 October 2018 5 years ago 2018 10 24 Northern Connection Tuen Mun Chek Lap Kok Tunnel 27 December 2020 3 years ago 2020 12 27 OwnerHong Kong GovernmentTrafficAutomotiveTollNoTechnicalLength5 kilometres 3 1 mi sub sea tunnel No of lanes4 lanes 2 lanes per direction Operating speed80 kilometres per hour 50 mph The construction of the link has helped facilitate travel between the Northwest New Territories Tuen Mun and Yuen Long Districts and the Hong Kong International Airport and the Hong Kong Zhuhai Macau Bridge Hong Kong Port Though the project lies entirely within Hong Kong territory its construction is associated with the new Hong Kong Zhuhai Macau Bridge HZMB The estimated cost of the design site investigation and construction of the TM CLKL including associated works like land reclamation is about HK 46 71 billion The Southern Connection mainline opened on 24 October 2018 to tie in with HZMB s commissioning 1 and the remaining Northern Connection to Tuen Mun opened on 27 December 2020 Contents 1 History 2 Design 3 Construction 4 References 5 External linksHistory edit nbsp View of the Urmston Road with construction of the tunnel s northern landfall visible The contract to construct the Northern Connection tunnel No HY 2012 08 was awarded to the Dragages Bouygues Joint Venture on 26 July 2013 It commenced on 5 August 2013 2 The contract to construct the southern section was awarded to Gammon Construction in June 2013 3 The entire project opened to traffic on 27 December 2020 Design editThe tunnel portion is a two lane dual carriageway approximately 5 kilometres long 4 Construction editThe dual sub sea tunnels were bored up to 55 metres below sea level using the Tuen Mun Chek Lap Kok TBM the world s largest tunnel boring machine 5 Originally scheduled for opening in 2018 completion of the link had been delayed for two years 6 4 7 It opened to traffic on 27 December 2020 References edit Bridge link taxi area gazetted news gov hk 2018 10 22 Introduction Contract No HY 2014 08 Tuen Mun Chek Lap Kok Link Northern Connection Sub sea Tunnel Section Highways Department Retrieved 8 May 2018 Gammon Bags Tuen Mun Chek Lap Kok Link Viaduct Job Construction Post 20 June 2013 Retrieved 15 December 2019 a b Tuen Mun Chek Lap Kok Link TM CLKL Highways Department Retrieved 24 September 2022 Hansford Mark 9 May 2017 Rise of the machines New Civil Engineer Tuen Mun to airport link road delayed till 2020 Radio Television Hong Kong 17 March 2017 Contractor criticised as delays hit big Hong Kong tunnel Global Construction Review 22 March 2017 Retrieved 14 February 2019 External links edit nbsp Wikimedia Commons has media related to Tuen Mun Chek Lap Kok Link Official website Retrieved from https en wikipedia org w index php title Tuen Mun Chek Lap Kok Link amp oldid 1192972924, wikipedia, wiki, book, books, library,