Pre-engineered building

In structural engineering, a pre-engineered building (PEB) is designed by a PEB supplier or PEB manufacturer with a single design to be fabricated using various materials and methods to satisfy a wide range of structural and aesthetic design requirements. This is contrasted with a building built to a design that was created specifically for that building. Within some geographic industry sectors pre-engineered buildings are also called pre-engineered metal buildings (PEMB) or, as is becoming increasingly common due to the reduced amount of pre-engineering involved in custom computer-aided designs, simply engineered metal buildings (EMB).

A pre-engineered metal building under construction

During the 1960s, standardized engineering designs for buildings were first marketed as PEBs.[1] Historically, the primary framing structure of a pre-engineered building is an assembly of I-shaped members, often referred to as I-beams. In pre-engineered buildings, the I beams used are usually formed by welding together steel plates to form the I section. The I beams are then field-assembled (e.g. bolted connections) to form the entire frame of the pre-engineered building. Some manufacturers taper the framing members (varying in web depth) according to the local loading effects. Larger plate dimensions are used in areas of higher load effects.

Other forms of primary framing can include trusses, mill sections rather than three-plate welded, castellated beams, etc. The choice of economic form can vary depending on factors such as local capabilities (e.g. manufacturing, transportation, construction) and variations in material vs. labour costs.

Typically, primary frames are 2D type frames (i.e. may be analyzed using two-dimensional techniques). Advances in computer-aided design technology, materials and manufacturing capabilities have assisted a growth in alternate forms of pre-engineered building such as the tension fabric building and more sophisticated analysis (e.g. three-dimensional) as is required by some building codes.[2]

Cold formed Z- and C-shaped members may be used as secondary structural elements to fasten and support the external cladding.

Roll-formed profiled steel sheet, wood, tensioned fabric, precast concrete, masonry block, glass curtainwall or other materials may be used for the external cladding of the building.

In order to accurately design a pre-engineered building, engineers consider the clear span between bearing points, bay spacing, roof slope, live loads, dead loads, collateral loads, wind uplift, deflection criteria, internal crane system and maximum practical size and weight of fabricated members. Historically, pre-engineered building manufacturers have developed pre-calculated tables for different structural elements in order to allow designers to select the most efficient I beams size for their projects. However, the table selection procedures are becoming rare with the evolution in computer-aided custom designs.

While pre-engineered buildings can be adapted to suit a wide variety of structural applications, the greatest economy will be realized when utilising standard details. An efficiently designed pre-engineered building can be lighter than the conventional steel buildings by up to 30%. Lighter weight equates to less steel and a potential price savings in structural framework.

Project professionals and manufacturer-designed buildings edit

The project architect, sometimes called the Architect of Record, is typically responsible for aspects such as aesthetic, dimensional, occupant comfort and fire safety. When a pre-engineered building is selected for a project, the architect accepts conditions inherent in the manufacturer's product offerings for aspects such as materials, colours, structural form, dimensional modularity, etc. Despite the existence of the manufacturer's standard assembly details, the architect remains responsible to ensure that the manufacturer's product and assembly is consistent with the building code requirements (e.g. continuity of air/vapour retarders, insulation, rain screen; size and location of exits; fire rated assemblies) and occupant/owner expectations.

Many jurisdictions recognize the distinction between the project engineer, sometimes called the Engineer of Record, and the manufacturer's employee or subcontract engineer, sometimes called a specialty engineer. The principal differences between these two entities on a project are the limits of commercial obligation, professional responsibility and liability.

The structural Engineer of Record is responsible to specify the design parameters for the project (e.g. materials, loads, design standards, service limits) and to ensure that the element and assembly designs by others are consistent in the global context of the finished building.

The specialty engineer is responsible to design only those elements which the manufacturer is commercially obligated to supply (e.g. by contract) and to communicate the assembly procedures, design assumptions and responses, to the extent that the design relies on or affects work by others, to the Engineer of Record – usually described in the manufacturer's erection drawings and assembly manuals. The manufacturer produces an engineered product but does not typically provide engineering services to the project.

In the context described, the Architect and Engineer of Record are the designers of the building and bear ultimate responsibility for the performance of the completed work. A buyer should be aware of the project professional distinctions when developing the project plan.

These prefabricated structures are widely used in the residential as well as industrial sector [3] for its unmatched characteristics.

References edit

  1. ^ Newman, Alexander (2004). Metal Building Systems (2nd ed.). New York: McGraw-Hill Education. p. 3. ISBN 9780070463790.
  2. ^ National Building Code of Canada 2005
  3. ^ "Why PEB is Preferred Choice For Industrial Sheds". 2022-09-12.

engineered, building, this, article, need, rewritten, comply, with, wikipedia, quality, standards, help, talk, page, contain, suggestions, january, 2020, this, article, needs, additional, citations, verification, please, help, improve, this, article, adding, c. This article may need to be rewritten to comply with Wikipedia s quality standards You can help The talk page may contain suggestions January 2020 This article needs additional citations for verification Please help improve this article by adding citations to reliable sources Unsourced material may be challenged and removed Find sources Pre engineered building news newspapers books scholar JSTOR June 2011 Learn how and when to remove this template message In structural engineering a pre engineered building PEB is designed by a PEB supplier or PEB manufacturer with a single design to be fabricated using various materials and methods to satisfy a wide range of structural and aesthetic design requirements This is contrasted with a building built to a design that was created specifically for that building Within some geographic industry sectors pre engineered buildings are also called pre engineered metal buildings PEMB or as is becoming increasingly common due to the reduced amount of pre engineering involved in custom computer aided designs simply engineered metal buildings EMB A pre engineered metal building under constructionDuring the 1960s standardized engineering designs for buildings were first marketed as PEBs 1 Historically the primary framing structure of a pre engineered building is an assembly of I shaped members often referred to as I beams In pre engineered buildings the I beams used are usually formed by welding together steel plates to form the I section The I beams are then field assembled e g bolted connections to form the entire frame of the pre engineered building Some manufacturers taper the framing members varying in web depth according to the local loading effects Larger plate dimensions are used in areas of higher load effects Other forms of primary framing can include trusses mill sections rather than three plate welded castellated beams etc The choice of economic form can vary depending on factors such as local capabilities e g manufacturing transportation construction and variations in material vs labour costs Typically primary frames are 2D type frames i e may be analyzed using two dimensional techniques Advances in computer aided design technology materials and manufacturing capabilities have assisted a growth in alternate forms of pre engineered building such as the tension fabric building and more sophisticated analysis e g three dimensional as is required by some building codes 2 Cold formed Z and C shaped members may be used as secondary structural elements to fasten and support the external cladding Roll formed profiled steel sheet wood tensioned fabric precast concrete masonry block glass curtainwall or other materials may be used for the external cladding of the building In order to accurately design a pre engineered building engineers consider the clear span between bearing points bay spacing roof slope live loads dead loads collateral loads wind uplift deflection criteria internal crane system and maximum practical size and weight of fabricated members Historically pre engineered building manufacturers have developed pre calculated tables for different structural elements in order to allow designers to select the most efficient I beams size for their projects However the table selection procedures are becoming rare with the evolution in computer aided custom designs While pre engineered buildings can be adapted to suit a wide variety of structural applications the greatest economy will be realized when utilising standard details An efficiently designed pre engineered building can be lighter than the conventional steel buildings by up to 30 Lighter weight equates to less steel and a potential price savings in structural framework Project professionals and manufacturer designed buildings editThe project architect sometimes called the Architect of Record is typically responsible for aspects such as aesthetic dimensional occupant comfort and fire safety When a pre engineered building is selected for a project the architect accepts conditions inherent in the manufacturer s product offerings for aspects such as materials colours structural form dimensional modularity etc Despite the existence of the manufacturer s standard assembly details the architect remains responsible to ensure that the manufacturer s product and assembly is consistent with the building code requirements e g continuity of air vapour retarders insulation rain screen size and location of exits fire rated assemblies and occupant owner expectations Many jurisdictions recognize the distinction between the project engineer sometimes called the Engineer of Record and the manufacturer s employee or subcontract engineer sometimes called a specialty engineer The principal differences between these two entities on a project are the limits of commercial obligation professional responsibility and liability The structural Engineer of Record is responsible to specify the design parameters for the project e g materials loads design standards service limits and to ensure that the element and assembly designs by others are consistent in the global context of the finished building The specialty engineer is responsible to design only those elements which the manufacturer is commercially obligated to supply e g by contract and to communicate the assembly procedures design assumptions and responses to the extent that the design relies on or affects work by others to the Engineer of Record usually described in the manufacturer s erection drawings and assembly manuals The manufacturer produces an engineered product but does not typically provide engineering services to the project In the context described the Architect and Engineer of Record are the designers of the building and bear ultimate responsibility for the performance of the completed work A buyer should be aware of the project professional distinctions when developing the project plan These prefabricated structures are widely used in the residential as well as industrial sector 3 for its unmatched characteristics References edit Newman Alexander 2004 Metal Building Systems 2nd ed New York McGraw Hill Education p 3 ISBN 9780070463790 National Building Code of Canada 2005 Why PEB is Preferred Choice For Industrial Sheds 2022 09 12 Retrieved from https en wikipedia org w index php title Pre engineered building amp oldid 1209375651, wikipedia, wiki, book, books, library,