fbpx
Wikipedia

Waterview Connection

The Waterview Connection is a motorway section through west/central Auckland, New Zealand. It connects State Highway 20 in the south at Mt Roskill to State Highway 16 in the west at Point Chevalier, and is a part of the Western Ring Route.

Waterview Connection
While generally considered a "tunnel project", the Waterview Connection also included other large motorway works. The connection consists of the purple (above ground) and dark blue (bored tunnels) sections. The section of SH16 with extra lanes added is shown in light blue.
LocationAuckland, New Zealand
ProposerNZ Transport Agency
Project websitehttp://www.nzta.govt.nz/projects/waterviewconnection
StatusOpened 2 July 2017
TypeRoad & tunnel
Cost estimate$1.7 billion[1]
StakeholdersGovernment of New Zealand, NZ Transport Agency, Auckland Council, Campaign for Better Transport, Cycle Action Auckland, Friends of Oakley Creek, North West Community Association, various further community groups and submitters

The Waterview Connection is 4.5 km long, of which 2.5 km are in the form of twin tunnels. The Waterview Tunnel supersedes the Lyttelton Road Tunnel as New Zealand's longest road tunnels. By 2026, the link is expected to carry 83,000 vehicles a day.[1][2] There are three lanes of traffic in each tunnel.[3]

Planning history Edit

The project had an extensive planning history, with the earliest consultation in 2000,[4] though the proposal for a route roughly in the area dates from much earlier.[citation needed]

Routes considered Edit

 
Oakley Creek, near where the bored tunnels in the final (2010) alignments stop (and was joined to cut and cover built tunnels for the last section towards SH16).

Several routes were considered, all being variations of either a connection to SH16 along the Rosebank Peninsula (e.g. AR1, AR3) or at the Great North Road interchange at Waterview (e.g. AW1, AW4).[5] It was generally assumed that below-ground construction would be required where AR3 passed through Avondale Heights, to a maximum depth of 41 m. On the basis of technical and environmental assessments, the AR3 and AW4 route options were dismissed.[citation needed]

Transit New Zealand selected the Waterview connection as its preferred route,[6] with the support of the Auckland City Council[7] and Waitakere City Council,[8][9] over the Rosebank option, which was the preferred route of the Auckland Regional Council.[10] The previous AW1 and AW4 routes favoured a New North Road interchange with ramps facing south, and full connections at the Waterview interchange. The preferred route was announced with a Great North Road interchange replacing New North Road and no southbound access at Waterview. This proved unpopular with local residents, and it was considered unlikely a bored tunnel could accommodate an interchange because of its depth.[11]

Bored tunnels preferred Edit

On 7 February 2008, bored tunnels were announced as Transit's preferred option.[12] The NZ Transport Agency's preferred option was a pair of two-lane tunnels costing $1.89 billion, rather than a pair of three-lane tunnels costing $2.14 billion. NZTA's traffic modelling indicated that two-lane tunnels would reach capacity within 10 years of operation.[13] Map of Tunnel Route

Transit NZ's board resolved to seek a designation over land for a $1.89 billion pair of motorway tunnels through Waterview.[14] The board called for a report from officials on managing fumes from the tunnel "to benchmark the proposed approach incorporated in the design work to date against current international best practice". In response to submissions questioning the adequacy of just two traffic lanes running in each direction, it sought a comparative assessment of the operational performance and costs of providing three-lane tunnels, initially estimated at $2.14 billion.[15]

Public-private partnership investigation Edit

The government set up a joint public-private sector steering group to investigate the feasibility of a public-private partnership (PPP) as a procurement method for the Waterview Connection Project, evaluating the PPP alongside a conventional public sector procurement method to determine how the two methods compared in terms of value for money. The steering group had as an independent chairperson, Sir Brian Elwood, and reported directly to the Ministers of Finance and Transport.[16]

It was announced on 26 August 2008 that the steering group had advised the Government that a public-private partnership (PPP) - which would require a $2 toll per trip - was the best way of building the new $2 billion section of the city's Western Ring Route. Transport Minister Annette King asked officials to do more work on several critical factors before the Government committed to a PPP.[17]

Air quality concerns Edit

In October 2008 the NZ Transport Agency released report findings which showed that tunnel emissions would have a negligible effect on local air quality.[18] These findings were disputed by Waterview Primary School representatives, who claimed that the report hadn't taken into account the impact of tolling "which could add more traffic to surface roads", hadn't given sufficient consideration to "international best practice on air filtering", and had failed to account for "ventilation fans being turned off during off-peak times, allowing emissions to escape through the tunnel openings". They also asked for reconsideration of "taking a section of the school’s playing field for use during the five-year construction period".[19]

Concern was also expressed by developer Greg Burgess, who had consent for building 83 new homes 19 metres away from the Owairaka ventilation stack. The developer wanted the ventilation stack moved further away, but there were worries that fumes might be pushed closer to Christ the King School.[20]

Request to reconsider Rosebank route Edit

The Auckland Regional Council requested NZTA to reconsider whether the proposed Waterview Connection was the most cost-effective way of completing the Western Ring Road, with a reconsideration of the costs and benefits of the alternative Rosebank route.[21][22]

Cost of bored tunnels questioned Edit

In 2009, the CEO of Federated Farmers, Conor English (brother of Finance Minister Bill English), announced that Federated Farmers wanted the government to review the tunnelling with a view to cancelling it. He argued in an editorial that the project represented a "tunnel with no hill", costed at that time at about $1.9 billion or about $600 million a kilometre. Therefore, the motorway should instead be built as a surface road, and the savings invested into water storage projects benefitting farming.[23]

On 30 January 2009 Transport Minister Steven Joyce announced his concern with the $3.16 billion cost (including financing costs of more than $500 million and an upgrade of the nearby Northwestern Motorway for $240 million) of three-lane tunnels. Because he was "not comfortable" with the idea of reducing the tunnels to two lanes with no ability to enlarge them for future traffic demand, he gave officials until April to review all options for a connection of State Highway 20 to the Northwestern Motorway at Waterview, including a potentially disruptive surface route through Mount Albert and previously discarded "cut and cover" proposals. He was unable to predict a completion date for Auckland's 42 km western ring route, saying officials regarded a 2015 target of the previous Labour government as "aspirational".[24]

Combination tunnel method announced Edit

 
Local protests, such as here at the end of the existing stub of SH20, played a role in a combined surface and tunnel being reconsidered.

On 13 May 2009 NZTA announced its new preferred route for the Waterview Connection motorway as a combination of surface, bored tunnel and cut and cover tunnel. The tunnels would be constructed with provision for three lanes in each direction.[25]

A raised surface motorway through Alan Wood Park[26] and the short section between the bored and cut and cover tunnel portals near the Great North Rd and Blockhouse Bay Rd intersection[27] were the largest differences between this new preferred route and the previous bored tunnel option.[28] At $1,165 million, it was cheaper than the $1,974 million two-lane bored tunnel option and the $2,335 million three-lane bored tunnel option.[29]

Combined surface/tunnel alignment confirmed Edit

On 11 September 2009 the NZTA Board confirmed the combined surface/tunnel alignment for the Waterview Connection. The Board was confident that the project's effects could be managed in a fair and reasonable way and that many of the community concerns would be addressed through good design. Over the following two months the NZTA was to provide the Board with details on how a range of issues would be addressed,[30] including:

  • the subsequent process of engagement to be adopted with respect to the community and other stakeholders;
  • air quality effects;
  • open space replacement and enhancement;
  • noise mitigation;
  • other environmental impacts;
  • tunnel design options to minimise or remove the separation between the 'bored' and 'cut and cover' tunnels;
  • urban design – including cycle and walkway connections and access; and investigating a 'central' interchange;[31]

Subject to board approval on 27 November 2009 of a final design for the motorway, the NZTA was to lodge a land designation application early in 2010 with Auckland City, for a construction start in 2011-12 and completion in 2015.[32][33]

"Final" alignment confirmed Edit

On 21 December 2009, NZTA announced that the tunnels would be built further east as continuous tunnels without an (open) gap halfway, and expressed confidence that they would be able to be completed within the original project budget. NZTA argued that this would be the most cost-effective option for constructing this section, and would require 205 houses to be bulldozed.[34] Underground land would need to be purchased from 105 properties. The board had decided against including a central interchange at New North Road. Construction on the project was proposed to start in mid to late 2011 with an anticipated completion date in the 2015/16 financial year.[35]

The revised route map[36] shows road header constructed tunnels running from Alan Wood Park opposite Range View / Stewart Roads, under the north end of Hendon Ave and under Pak 'n Save, continuing under the ends of Powell St & Craddock St, under the Phyllis St softball fields, under the Oakley Creek waterfall and reserve with a final section of cut & cover under Great North Rd and emerging in Waterview Park as per previous options.

"Road of National Significance" & Fast-tracking Edit

In 2009, Minister of Transport Steven Joyce declared the project one of the "Roads of National Significance". Crucially, this step allowed the application to be considered by a new governmental body, the Environmental Protection Authority, a fast-track process which bypasses normal resource consent and Environment Court processes, in favour of a fixed 9-month process led by a "Board of Enquiry", whose decision cannot be appealed except on points of law. The decision to fast-track was cited as necessary to avoid approval delays which had held up other projects for over 15 years, though local groups were pessimistic about their chance to achieve fair mitigation within the tight process.[37]

The tunnel sections would now be approximately 2.4 km long. Also included in the fast-tracked project was the decision to undertake significant capacity-related widening works on State Highway 16, which are outside of the Waterview area (from St Lukes Road interchange to beyond Te Atatū), which were bundled into the application process which consists of 54 resource consents and 7 designations.[38]

With around 40 folders of materials and plans to go through, local community groups expressed anger in October 2010 that they would have only four weeks to formulate submissions regarding the fast-tracked applications. Calls by Auckland City Council and an affected community board to extend the deadline were rejected on the grounds of the tight statutory timeframe.[38]

Consent approvals Edit

Process and hearing Edit

The consenting process continued in parallel with the tendering process in order to save time. On 3 September 2010, NZTA's application for designation and resource consents for the Waterview Connection section of the Western Ring Route 'road of national significance project' was referred to a Board of Inquiry.[39]

The EPA publicly notified the application package on 18 September 2010, with the period for public submissions closing 15 October 2010. Evidence needed to be produced and provided to NZTA by 17 December 2010. The Board of Inquiry hearing took 16 days, finishing in March), with the final decision due by 20 June 2011, later amended to 30 June.[39]

A number of matters came into public focus during the hearings process. One of them was the shape and locations of the two proposed ventilation shaft buildings near the northern and southern tunnel entries, and their likely effect on local visual amenity (with the shafts, at 25m-27m height, proposed to tower visibly over surrounding suburban areas) and local air pollution levels (where an independent report considered that the NZTA had been too optimistic in terms of pollution conditions during traffic jams and due to induced demand).[2][40] Other matters included effects on local neighbourhoods, even those where demolition was not expected, such as for several apartment buildings directly adjacent to a multi-year construction site.[41]

Board of Inquiry decision Edit

On 9 May 2011 it was reported that the board had directed NZTA to, among other mitigation changes:[39]

  • build the northern tunnel exhaust tower on the other (eastern) side of Great North Rd, further away from Waterview Primary School than planned - NZTA had opposed the change arguing extra costs of up to $29 million
  • build the southern tunnel exhaust tower, in Owairaka, 70 to 80 metres southeast of NZTA's preferred site, away from a narrow chokepoint in Alan Wood Park, requiring a short extension to the 2.5 km tunnels, also reducing the project's open space displacement - NZTA had opposed the change arguing extra costs of up to $21 million
  • build the two towers to a height of "15 metres above ground - not more - not less"
  • pay $8 million towards construction of a walk- and cycleway between Owairaka and Waterview, to mitigate open space loss by providing local connections for the communities

The draft decision on the overall project was released end of May 2011, confirming the matters of the earlier direction, with the final result not significantly different[39] when released end of June 2011.[42]

While community groups still expressed negative views about the motorway after the hearings process, many noted that they felt that the tunneling (compared to a 2009 surface alignment) and the added mitigation prescribed on NZTA by the board, had helped to make the result more acceptable for the local communities. While some described the process as a "David and Goliath" fight, most agreed that the board had handled the process well, and listened to local concerns.[1][4][39]

Construction Edit

Start of enabling works Edit

In March 2010, NZTA announced that $10 million enabling works would start at the southeastern end of the route, diverting a sewer line and a tributary of Oakley Creek in preparation for the new Maioro St interchange. While the works would occur on land already designated as motorway, local groups were concerned that the move preempted the consenting process for the main alignment, which still was to happen at that stage.[43]

In October 2010, NZTA signed a contract with Fletcher construction to complete stage 2 of the $40m project at the Maioro Street interchange.[44] In November 2010, NZTA continued to negotiate the acquiring of the Faulkner Collins factory and offices from Stoddard Rd in Mt Roskill under the public works act, in order to make way for the Maioro St interchange connection to Stoddard Rd. Faulkner Collins employees took turns sleeping at the factory, fearing that NZTA would change the locks during the night.[45][46][47]

Contract awarded Edit

16 November 2010, NZTA announced the two shortlisted competitors to construct the project, being two alliances of companies, one jointly led by McConnell Dowell and Fletcher Construction and one led by Fulton Hogan in partnership with Australia's Leighton Contractors. A third consortium led by Baulderstone missed out on selection. As of May 2010, it was known that each of the two remaining tenderers had about 140-150 staff preparing bids for the project, and one tenderer, after the decision, noted that they had spent about $18 million preparing the bid. Construction start was expected to be before Christmas 2011.[4][48][49]

In mid-2011, it was announced that the 'Well Connected' consortium led by Fletcher Construction had won the tender, for $1.3 billion.[49] The consortium also included McConnell Dowell Obayashi Corporation, PB New Zealand, Beca Infrastructure and Tonkin + Taylor, as well as five sub-alliance partners and contractors: SICE, Wilson Tunnelling, Downer EDI Works, Boffa Miskell and Warren and Mahoney. The consortium worked on the alliance model, in which financial risks and incentives are shared among all partners.

Proposal to relocate northern vent stack Edit

In December 2011, the construction consortium proposed relocating the northern stack from the east side of Great North Rd, to the north side of Herdman Street. As the Earth Pressure Balance tunnel boring machine (TBM) would be able to bore much closer to the surface than techniques assumed during the design phase, the cut and cover tunneling technique was not required below Great North Road. That meant that a duct below Great North Rd to a stack on the east side could not be constructed at the same time as the tunnels. The northern location for the stack had been studied earlier but dismissed because of greater cost, and the location had also created concerns among locals due to greater visual effects than that finally chosen by the Board of Inquiry.[50]

Enabling works Edit

Enabling works began in January 2012 between the Maioro Street interchange and Alan Wood Park and included:

  • Establishment activities (e.g. construction zone fencing /project and way-finding signage)
  • Removal of properties from within designation
  • Construction of two temporary soccer fields (senior and junior), ablution block and a temporary car park at Valonia Street (with field drainage and grass seeding from March 2012)
  • Site access for heavy vehicles from Richardson Rd (and 8-metre-wide haul road west through Hendon Park)
  • Construction of temporary stream crossings (for construction vehicle access)
  • Excavation and temporary diversion of a section of Oakley Creek adjacent to the sports fields to facilitate their construction
  • Excavation of new stream channels in Alan Wood Park and temporary diversion of sections of Oakley Creek into the new alignment
  • Diversion of utility services around Richardson Road to enable the construction of a road diversion
  • Temporary realignment of Richardson Road while building new Richardson Rd bridge.[51]

Local electricity distribution company Vector also carried out enabling works to supply electricity to the tunnel portal sites for construction, and included:[52]

  • Installing an 11 kV feeder line from the Chevalier zone substation on Great North Road to the northern portal site to supply the northern portal during construction.
  • Installing a 33 kV capable, 22 kV operating, underground cable from the Avondale zone substation on Blockhouse Bay Road to the southern portal site to supply the southern portal and the TBM during construction. This also involved installing a 33 kV capable switchboard at Avondale to connect the tunnel supply to the two 22 kV cables feeding Avondale zone substation from the national grid at Mount Roskill.
  • Installing a new 11 kV local feeder line from Chevalier zone substation to the Waterview area, to transfer some existing load off Avondale zone substation, as Avondale could not supply both the TBM and its existing load without overloading.
  • Installing a second 22/11 kV transformer at the Chevalier zone substation, as the existing transformer could not supply the northern portal and Waterview feeder lines without overloading.

Southern Portal works Edit

Beginning July 2012[53]

Northern Portal works and Great North Road Interchange Edit

Beginning May 2013[53] (note that works at the northern end will not initially involve tunnel boring)

Tunnelling Edit

Opening Edit

On 24 March 2017, it was announced that the planned April 2017 opening of the $1.6 billion project was being held up for another two months because of issues with its fire sprinklers.[54] On 11 June 2017 it was announced that the tunnel would open in early July 2017.[55] The tunnels opened at 12:47 am on 2 July 2017, with three police cars leading the first vehicles through the northbound tunnel.[56]

Mitigation and related projects Edit

 
Great North Road and the overbridge of the Northwestern Cycleway. The tunnel will surface just to the west (right hand of the picture).

A number of not directly motorway-related projects will form part of the SH20 connection works, either to mitigate negative effects on the environment, or to provide for other transport modes.

Avondale–Southdown railway line Edit

Enabling works and allowance for the Avondale–Southdown Line are a part of constructing SH20.[57][58] KiwiRail sees this route as strategically important as it is the only real alternative for a cross-isthmus heavy rail route, as upgrading of the existing Newmarket Line is not realistically feasible or possible. KiwiRail requested that any tunnel construction not preclude rail above it in the future, nor the possibility of rail being trenched to cross below New North Road to connect to the existing North Auckland Line.[59]

Passive open space Edit

Passive open space will be lost during construction of the motorway to construction lay down areas and lost permanently where the motorway & associated structures are built. NZTA has proposed replacement passive open space below & around the Waterview interchange ramps, and the existing privately owned empty site adjoining Alan Wood Park and future surface motorway.[60]

Active open space Edit

The existing fields at Waterview Reserve and Alan Wood Park will be lost. NZTA propose to construct new fields adjacent to the Waterview interchange, and above the tunnel entrances at Alan Wood Park. These would likely be used as construction lay down areas during construction.[60] During the project Expo's, NZTA had proposed to develop additional fields at Phyllis St for use during the construction period but this was dropped for the EPA submission.[61]

Walkways and cycleways Edit

Documents shown during the public consultation phase in early 2010 showed a proposed walkway and cycleway generally following the line of the motorway / tunnel alignment, connecting the existing SH16 Cycleway with the end of the then-existing SH20 Cycleway, including a walking/cycling bridge over Oakley Creek at Phyllis Street.[61][62] However, at lodgement time in 2010, NZTA clarified that it would only build cycleways along the sections that are not located in a tunnel, leaving the potential for a connecting cycleway between SH16 and SH20 in doubt.[63]

After a several-months-long hearing process, the Board of Inquiry in mid-2011 however came to the decision that a walkway and cycleway along the tunnel alignment was a required mitigation for open space loss in the areas around both tunnel portals (though not technically as transport mitigation), and that NZTA will have to pay for (though not build) the facility.[39] Cycling advocates Cycle Action Auckland lauded the decision as a resounding win for cycling in Auckland, and a key part in making the Waterview Connection into a truly multi-modal project. The approximate route of the cycleway will be from near Alford Street in Waterview, crossing a new bridge over Oakley Creek, then through Phyllis Reserve, before crossing to Alan Wood Park in New Windsor/Owairaka via a new bridge over the rail line at Soljak Place.[63]

The bridge from Soljak Place over the railway to Harbutt Reserve is the first priority of the Alan Wood Park / Soljak Place to Waterview area cycleway, public consultation to be undertaken early 2012.[64]

Auckland Transport designed the 2.5 km long "Waterview Shared Path" from Alan Wood reserve, with construction happening from March 2016[65] to mid-2017.[66]

Maioro Street to New Lynn Edit

As part of the SH20 Mt Roskill extension, NZTA widened Maioro Street from two to four lanes, completed mid-2009.[67] The Auckland City Council was responsible for widening the remaining route to New Lynn, i.e. New Windsor Road, Tiverton Road and Wolverton Road.[68] While it completed some widening of Tiverton Road in 2007, Council deferred completing any more widening until 2015–2020.[69] In late 2011, Auckland Transport called for expressions of interest from contractors to complete the works. Construction was expected to start in the first half of 2012 subject to tender and NZTA funding, and take up to two years to complete.[70] On 17 April 2012 Auckland Transport announced that NZTA would fund 53% of the project.[71]

See also Edit

References Edit

  1. ^ a b c "Waterview makes most of tunnel". Central Leader. 3 June 2011. Retrieved 27 June 2011.
  2. ^ a b Dearnaley, Mathew (24 January 2010). "Agency chided over pollution figures". The New Zealand Herald. Retrieved 7 February 2011.
  3. ^ "Auckland's Waterview Connection on schedule to open in early 2017". Stuff.co.nz. 9 June 2016. Retrieved 15 May 2017.
  4. ^ a b c Dearnaley, Mathew (27 May 2011). "Waterview approval starts race to win contract". The New Zealand Herald. Retrieved 13 June 2011.
  5. ^ Consultation (from the Transit New Zealand website)
  6. ^ "AW1 is the confirmed preferred route for the Waterview Connection" Newsletter 8, February 2006 (from the SH20 project website of Transit New Zealand)
  7. ^ December 2005, Auckland City voted to support the extension of SH20 through Waterview
  8. ^ "Waitakere City conditionally support Waterview option" 9 February 2006, City Development Committee page 2-9
  9. ^ "Waitakere City conditionally support Waterview option" 27 November 2006, Council page 8
  10. ^ 14 March 2006, ARC media release ARC supports Rosebank route for SH20 extension
  11. ^ Mathew Dearnaley (30 August 2006). "Transit may ditch Mt Albert interchange plan". The New Zealand Herald. Retrieved 10 September 2011.
  12. ^ Transit New Zealand. "Transit - Waterview Connection". Retrieved 8 February 2008.
  13. ^ Mathew Dearnaley (17 April 2008). "Groups call for three-lane tunnels". The New Zealand Herald. Retrieved 10 September 2011.
  14. ^ 4 June 2008 TRANSIT BOARD SEEKS TO PROTECT TUNNEL ROUTE FOR WATERVIEW
  15. ^ Mathew Dearnaley (5 June 2008). "Designation sought over motorway land despite opposition". The New Zealand Herald. Retrieved 10 September 2011.
  16. ^ "Government to investigate feasibility of PPP for Waterview Connection". The Beehive. Retrieved 14 May 2017.
  17. ^ "Motorway tolls move a step closer". The New Zealand Herald. 26 August 2008. Retrieved 10 September 2011.
  18. ^ "Waterview Tunnel emissions will meet air quality standards | NZ Transport Agency". nzta.govt.nz. Retrieved 14 May 2017.
  19. ^ "School gets help in air quality dispute". Stuff. Retrieved 14 May 2017.
  20. ^ "Tunnel holds up building new homes". Central Leader. 27 November 2008. Retrieved 2 December 2011.
  21. ^ ARC agenda 24 November 2008
  22. ^ ARC minutes 24 November 2008
  23. ^ "Conor English: We can bank on wealth of water". The New Zealand Herald. 12 January 2009. Retrieved 8 February 2011.
  24. ^ Mathew Dearnaley (31 January 2009). "Cost blowout threatens tunnel plan". The New Zealand Herald. Retrieved 10 September 2011.
  25. ^ "Residents hit by Waterview decision contacted from today". The New Zealand Herald. 13 May 2009. Retrieved 10 September 2011.
  26. ^ Transit Waterview Connection website, Allan Wood Reserve cross-section
  27. ^ Transit Waterview Connection website, Artist's impression of tunnel portal at Avondale Heights
  28. ^ Transit Waterview Connection website, Route Map
  29. ^ Transit Waterview Connection website, presentation of preferred route
  30. ^ NZTA Media Release 11 Sep 09
  31. ^ NZTA Board paper 09/08/0250 Report on Community and Stakeholder Engagement (Supplementary Paper)
  32. ^ Dearnaley, Mathew (12 September 2009). "Motorway to go ahead despite concerns". The New Zealand Herald. Retrieved 2 December 2011.
  33. ^ NZTA Board meeting dates and agendas
  34. ^ "Final alignment for Western Ring Route unveiled". The New Zealand Herald. 21 December 2009. Retrieved 10 September 2011.
  35. ^ NZTA Media Release 21 Dec 09
  36. ^ Revised Route Map 21 Dec 09
  37. ^ Dearnaley, Mathew (4 September 2010). "Waterview project on fast track". The New Zealand Herald. Retrieved 4 October 2010.
  38. ^ a b Dearnaley, Mathew (4 October 2010). "Residents refused more time to fight motorway". The New Zealand Herald. Retrieved 4 October 2010.
  39. ^ a b c d e f Dearnaley, Mathew (9 May 2011). "Objectors get their way on towers". The New Zealand Herald. Retrieved 26 May 2011.
  40. ^ Dearnaley, Mathew (19 January 2011). "Filter tunnel fumes, report tells agency". The New Zealand Herald. Retrieved 7 February 2011.
  41. ^ Dearnaley, Mathew (17 January 2011). "Tunnels cause worry for Unitec". The New Zealand Herald. Retrieved 27 June 2011.
  42. ^ Dearnaley, Mathew (9 May 2011). "Objectors get their way on towers". The New Zealand Herald. Retrieved 9 May 2011.
  43. ^ Dearnaley, Mathew (8 March 2010). "Early start at Waterview". The New Zealand Herald. Retrieved 10 March 2010.
  44. ^ NZTA media release, 29 Oct 2010
  45. ^ Mathew Dearnaley (15 November 2010). "Factory fight costs Crown $500,000". The New Zealand Herald. Retrieved 10 September 2011.
  46. ^ Local jobs must be protected in Faulkner Collins dispute say Local Board Members, InfoNews 12 Nov 2010
  47. ^ "Auckland company fights eviction by NZTA". One News. 8 November 2010. Retrieved 2 December 2011.
  48. ^ "NZTA announces shortlist to deliver Waterview Connection". Press Release. NZ Transport Agency. 16 November 2010. Retrieved 13 June 2011.
  49. ^ a b Gibson, Anne (24 August 2011). "Price 'decisive' for Waterview contract". The New Zealand Herald. Retrieved 3 September 2011.
  50. ^ Dearnaley, Mathew (16 December 2011). "Ventilation tower for tunnels may be moved". The New Zealand Herald. Retrieved 16 December 2011.
  51. ^ "Construction on the Waterview Connection project". Press Release. NZ Transport Agency. 29 November 2011. Retrieved 29 November 2011.
  52. ^ "Electricity Asset Management Plan 2012–2022" (PDF). Vector Limited. April 2012. p. 5.86–5.88. Retrieved 18 April 2012.
  53. ^ a b "Construction Programme" (PDF). Press Release. NZ Transport Agency. 28 November 2011. Retrieved 28 November 2011.
  54. ^ "Waterview Connection held up by faulty sprinklers". Stuff.co.nz. 24 March 2017. Retrieved 24 March 2017.
  55. ^ "Auckland's $1.4 billion Waterview tunnel to open in early July". Retrieved 11 June 2017.
  56. ^ "Auckland's Waterview Tunnel open to traffic at last". Stuff.co.nz. 2 July 2017. Retrieved 2 July 2017.
  57. ^ FAQ How will the new section of motorway affect the existing Southdown rail designation (from the SH20 project website of Transit New Zealand)
  58. ^ SH20 Mt Roskill includes enabling works for a future rail line (from the Transit New Zealand website)
  59. ^ "Evidence of Pamela Marie Butler on behalf of KiwiRail" (PDF). KiwiRail / Environmental Protection Authority. 17 December 2010. Retrieved 15 January 2011.
  60. ^ a b NZTA project website
  61. ^ a b Expo Posters
  62. ^ "Council seeks improvements for Waterview". CityScene. Auckland City Council. 25 July 2010.
  63. ^ a b "Deal for cyclists takes step up". The New Zealand Herald. 13 June 2011. Retrieved 17 June 2011.
  64. ^ ONW community liaison meeting 2, meeting notes, 13 Dec 2011
  65. ^ Parminter, Alice (10 February 2016). "Auckland's Waterview cycle and walkway under construction". Auckland Now. Retrieved 3 July 2017.
  66. ^ "Waterview Shared Path". Auckland Transport.
  67. ^ Transit: Mt Roskill extension Project Details
  68. ^ Auckland City Council, Tiverton Road/Wolverton Street upgrade
  69. ^ Dearnaley, Mathew (21 December 2007). "Road widening to wait until after World Cup". The New Zealand Herald. Retrieved 7 February 2011.
  70. ^ Auckland Transport, Tiverton Wolverton upgrade
  71. ^ Auckland Transport, Funding approval given for Tiverton-Wolverton

External links Edit

  • Waterview Connection (official NZTA project website)
  • Auckland Motorways

waterview, connection, motorway, section, through, west, central, auckland, zealand, connects, state, highway, south, roskill, state, highway, west, point, chevalier, part, western, ring, route, while, generally, considered, tunnel, project, also, included, ot. The Waterview Connection is a motorway section through west central Auckland New Zealand It connects State Highway 20 in the south at Mt Roskill to State Highway 16 in the west at Point Chevalier and is a part of the Western Ring Route Waterview ConnectionWhile generally considered a tunnel project the Waterview Connection also included other large motorway works The connection consists of the purple above ground and dark blue bored tunnels sections The section of SH16 with extra lanes added is shown in light blue LocationAuckland New ZealandProposerNZ Transport AgencyProject websitehttp www nzta govt nz projects waterviewconnectionStatusOpened 2 July 2017TypeRoad amp tunnelCost estimate 1 7 billion 1 StakeholdersGovernment of New Zealand NZ Transport Agency Auckland Council Campaign for Better Transport Cycle Action Auckland Friends of Oakley Creek North West Community Association various further community groups and submittersThe Waterview Connection is 4 5 km long of which 2 5 km are in the form of twin tunnels The Waterview Tunnel supersedes the Lyttelton Road Tunnel as New Zealand s longest road tunnels By 2026 the link is expected to carry 83 000 vehicles a day 1 2 There are three lanes of traffic in each tunnel 3 Contents 1 Planning history 1 1 Routes considered 1 2 Bored tunnels preferred 1 3 Public private partnership investigation 1 4 Air quality concerns 1 5 Request to reconsider Rosebank route 1 6 Cost of bored tunnels questioned 1 7 Combination tunnel method announced 1 8 Combined surface tunnel alignment confirmed 1 9 Final alignment confirmed 1 10 Road of National Significance amp Fast tracking 2 Consent approvals 2 1 Process and hearing 2 2 Board of Inquiry decision 3 Construction 3 1 Start of enabling works 3 2 Contract awarded 3 3 Proposal to relocate northern vent stack 3 4 Enabling works 3 5 Southern Portal works 3 6 Northern Portal works and Great North Road Interchange 3 7 Tunnelling 4 Opening 5 Mitigation and related projects 5 1 Avondale Southdown railway line 5 2 Passive open space 5 3 Active open space 5 4 Walkways and cycleways 5 5 Maioro Street to New Lynn 6 See also 7 References 8 External linksPlanning history EditThe project had an extensive planning history with the earliest consultation in 2000 4 though the proposal for a route roughly in the area dates from much earlier citation needed Routes considered Edit nbsp Oakley Creek near where the bored tunnels in the final 2010 alignments stop and was joined to cut and cover built tunnels for the last section towards SH16 Several routes were considered all being variations of either a connection to SH16 along the Rosebank Peninsula e g AR1 AR3 or at the Great North Road interchange at Waterview e g AW1 AW4 5 It was generally assumed that below ground construction would be required where AR3 passed through Avondale Heights to a maximum depth of 41 m On the basis of technical and environmental assessments the AR3 and AW4 route options were dismissed citation needed Transit New Zealand selected the Waterview connection as its preferred route 6 with the support of the Auckland City Council 7 and Waitakere City Council 8 9 over the Rosebank option which was the preferred route of the Auckland Regional Council 10 The previous AW1 and AW4 routes favoured a New North Road interchange with ramps facing south and full connections at the Waterview interchange The preferred route was announced with a Great North Road interchange replacing New North Road and no southbound access at Waterview This proved unpopular with local residents and it was considered unlikely a bored tunnel could accommodate an interchange because of its depth 11 Bored tunnels preferred Edit On 7 February 2008 bored tunnels were announced as Transit s preferred option 12 The NZ Transport Agency s preferred option was a pair of two lane tunnels costing 1 89 billion rather than a pair of three lane tunnels costing 2 14 billion NZTA s traffic modelling indicated that two lane tunnels would reach capacity within 10 years of operation 13 Map of Tunnel RouteTransit NZ s board resolved to seek a designation over land for a 1 89 billion pair of motorway tunnels through Waterview 14 The board called for a report from officials on managing fumes from the tunnel to benchmark the proposed approach incorporated in the design work to date against current international best practice In response to submissions questioning the adequacy of just two traffic lanes running in each direction it sought a comparative assessment of the operational performance and costs of providing three lane tunnels initially estimated at 2 14 billion 15 Public private partnership investigation Edit The government set up a joint public private sector steering group to investigate the feasibility of a public private partnership PPP as a procurement method for the Waterview Connection Project evaluating the PPP alongside a conventional public sector procurement method to determine how the two methods compared in terms of value for money The steering group had as an independent chairperson Sir Brian Elwood and reported directly to the Ministers of Finance and Transport 16 It was announced on 26 August 2008 that the steering group had advised the Government that a public private partnership PPP which would require a 2 toll per trip was the best way of building the new 2 billion section of the city s Western Ring Route Transport Minister Annette King asked officials to do more work on several critical factors before the Government committed to a PPP 17 Air quality concerns Edit In October 2008 the NZ Transport Agency released report findings which showed that tunnel emissions would have a negligible effect on local air quality 18 These findings were disputed by Waterview Primary School representatives who claimed that the report hadn t taken into account the impact of tolling which could add more traffic to surface roads hadn t given sufficient consideration to international best practice on air filtering and had failed to account for ventilation fans being turned off during off peak times allowing emissions to escape through the tunnel openings They also asked for reconsideration of taking a section of the school s playing field for use during the five year construction period 19 Concern was also expressed by developer Greg Burgess who had consent for building 83 new homes 19 metres away from the Owairaka ventilation stack The developer wanted the ventilation stack moved further away but there were worries that fumes might be pushed closer to Christ the King School 20 Request to reconsider Rosebank route Edit The Auckland Regional Council requested NZTA to reconsider whether the proposed Waterview Connection was the most cost effective way of completing the Western Ring Road with a reconsideration of the costs and benefits of the alternative Rosebank route 21 22 Cost of bored tunnels questioned Edit In 2009 the CEO of Federated Farmers Conor English brother of Finance Minister Bill English announced that Federated Farmers wanted the government to review the tunnelling with a view to cancelling it He argued in an editorial that the project represented a tunnel with no hill costed at that time at about 1 9 billion or about 600 million a kilometre Therefore the motorway should instead be built as a surface road and the savings invested into water storage projects benefitting farming 23 On 30 January 2009 Transport Minister Steven Joyce announced his concern with the 3 16 billion cost including financing costs of more than 500 million and an upgrade of the nearby Northwestern Motorway for 240 million of three lane tunnels Because he was not comfortable with the idea of reducing the tunnels to two lanes with no ability to enlarge them for future traffic demand he gave officials until April to review all options for a connection of State Highway 20 to the Northwestern Motorway at Waterview including a potentially disruptive surface route through Mount Albert and previously discarded cut and cover proposals He was unable to predict a completion date for Auckland s 42 km western ring route saying officials regarded a 2015 target of the previous Labour government as aspirational 24 Combination tunnel method announced Edit nbsp Local protests such as here at the end of the existing stub of SH20 played a role in a combined surface and tunnel being reconsidered On 13 May 2009 NZTA announced its new preferred route for the Waterview Connection motorway as a combination of surface bored tunnel and cut and cover tunnel The tunnels would be constructed with provision for three lanes in each direction 25 A raised surface motorway through Alan Wood Park 26 and the short section between the bored and cut and cover tunnel portals near the Great North Rd and Blockhouse Bay Rd intersection 27 were the largest differences between this new preferred route and the previous bored tunnel option 28 At 1 165 million it was cheaper than the 1 974 million two lane bored tunnel option and the 2 335 million three lane bored tunnel option 29 Combined surface tunnel alignment confirmed Edit On 11 September 2009 the NZTA Board confirmed the combined surface tunnel alignment for the Waterview Connection The Board was confident that the project s effects could be managed in a fair and reasonable way and that many of the community concerns would be addressed through good design Over the following two months the NZTA was to provide the Board with details on how a range of issues would be addressed 30 including the subsequent process of engagement to be adopted with respect to the community and other stakeholders air quality effects open space replacement and enhancement noise mitigation other environmental impacts tunnel design options to minimise or remove the separation between the bored and cut and cover tunnels urban design including cycle and walkway connections and access and investigating a central interchange 31 Subject to board approval on 27 November 2009 of a final design for the motorway the NZTA was to lodge a land designation application early in 2010 with Auckland City for a construction start in 2011 12 and completion in 2015 32 33 Final alignment confirmed Edit On 21 December 2009 NZTA announced that the tunnels would be built further east as continuous tunnels without an open gap halfway and expressed confidence that they would be able to be completed within the original project budget NZTA argued that this would be the most cost effective option for constructing this section and would require 205 houses to be bulldozed 34 Underground land would need to be purchased from 105 properties The board had decided against including a central interchange at New North Road Construction on the project was proposed to start in mid to late 2011 with an anticipated completion date in the 2015 16 financial year 35 The revised route map 36 shows road header constructed tunnels running from Alan Wood Park opposite Range View Stewart Roads under the north end of Hendon Ave and under Pak n Save continuing under the ends of Powell St amp Craddock St under the Phyllis St softball fields under the Oakley Creek waterfall and reserve with a final section of cut amp cover under Great North Rd and emerging in Waterview Park as per previous options Road of National Significance amp Fast tracking Edit In 2009 Minister of Transport Steven Joyce declared the project one of the Roads of National Significance Crucially this step allowed the application to be considered by a new governmental body the Environmental Protection Authority a fast track process which bypasses normal resource consent and Environment Court processes in favour of a fixed 9 month process led by a Board of Enquiry whose decision cannot be appealed except on points of law The decision to fast track was cited as necessary to avoid approval delays which had held up other projects for over 15 years though local groups were pessimistic about their chance to achieve fair mitigation within the tight process 37 The tunnel sections would now be approximately 2 4 km long Also included in the fast tracked project was the decision to undertake significant capacity related widening works on State Highway 16 which are outside of the Waterview area from St Lukes Road interchange to beyond Te Atatu which were bundled into the application process which consists of 54 resource consents and 7 designations 38 With around 40 folders of materials and plans to go through local community groups expressed anger in October 2010 that they would have only four weeks to formulate submissions regarding the fast tracked applications Calls by Auckland City Council and an affected community board to extend the deadline were rejected on the grounds of the tight statutory timeframe 38 Consent approvals EditProcess and hearing Edit The consenting process continued in parallel with the tendering process in order to save time On 3 September 2010 NZTA s application for designation and resource consents for the Waterview Connection section of the Western Ring Route road of national significance project was referred to a Board of Inquiry 39 The EPA publicly notified the application package on 18 September 2010 with the period for public submissions closing 15 October 2010 Evidence needed to be produced and provided to NZTA by 17 December 2010 The Board of Inquiry hearing took 16 days finishing in March with the final decision due by 20 June 2011 later amended to 30 June 39 A number of matters came into public focus during the hearings process One of them was the shape and locations of the two proposed ventilation shaft buildings near the northern and southern tunnel entries and their likely effect on local visual amenity with the shafts at 25m 27m height proposed to tower visibly over surrounding suburban areas and local air pollution levels where an independent report considered that the NZTA had been too optimistic in terms of pollution conditions during traffic jams and due to induced demand 2 40 Other matters included effects on local neighbourhoods even those where demolition was not expected such as for several apartment buildings directly adjacent to a multi year construction site 41 Board of Inquiry decision Edit On 9 May 2011 it was reported that the board had directed NZTA to among other mitigation changes 39 build the northern tunnel exhaust tower on the other eastern side of Great North Rd further away from Waterview Primary School than planned NZTA had opposed the change arguing extra costs of up to 29 million build the southern tunnel exhaust tower in Owairaka 70 to 80 metres southeast of NZTA s preferred site away from a narrow chokepoint in Alan Wood Park requiring a short extension to the 2 5 km tunnels also reducing the project s open space displacement NZTA had opposed the change arguing extra costs of up to 21 million build the two towers to a height of 15 metres above ground not more not less pay 8 million towards construction of a walk and cycleway between Owairaka and Waterview to mitigate open space loss by providing local connections for the communitiesThe draft decision on the overall project was released end of May 2011 confirming the matters of the earlier direction with the final result not significantly different 39 when released end of June 2011 42 While community groups still expressed negative views about the motorway after the hearings process many noted that they felt that the tunneling compared to a 2009 surface alignment and the added mitigation prescribed on NZTA by the board had helped to make the result more acceptable for the local communities While some described the process as a David and Goliath fight most agreed that the board had handled the process well and listened to local concerns 1 4 39 Construction EditThis section s factual accuracy may be compromised due to out of date information Please help update this article to reflect recent events or newly available information September 2012 Start of enabling works Edit In March 2010 NZTA announced that 10 million enabling works would start at the southeastern end of the route diverting a sewer line and a tributary of Oakley Creek in preparation for the new Maioro St interchange While the works would occur on land already designated as motorway local groups were concerned that the move preempted the consenting process for the main alignment which still was to happen at that stage 43 In October 2010 NZTA signed a contract with Fletcher construction to complete stage 2 of the 40m project at the Maioro Street interchange 44 In November 2010 NZTA continued to negotiate the acquiring of the Faulkner Collins factory and offices from Stoddard Rd in Mt Roskill under the public works act in order to make way for the Maioro St interchange connection to Stoddard Rd Faulkner Collins employees took turns sleeping at the factory fearing that NZTA would change the locks during the night 45 46 47 Contract awarded Edit 16 November 2010 NZTA announced the two shortlisted competitors to construct the project being two alliances of companies one jointly led by McConnell Dowell and Fletcher Construction and one led by Fulton Hogan in partnership with Australia s Leighton Contractors A third consortium led by Baulderstone missed out on selection As of May 2010 it was known that each of the two remaining tenderers had about 140 150 staff preparing bids for the project and one tenderer after the decision noted that they had spent about 18 million preparing the bid Construction start was expected to be before Christmas 2011 4 48 49 In mid 2011 it was announced that the Well Connected consortium led by Fletcher Construction had won the tender for 1 3 billion 49 The consortium also included McConnell Dowell Obayashi Corporation PB New Zealand Beca Infrastructure and Tonkin Taylor as well as five sub alliance partners and contractors SICE Wilson Tunnelling Downer EDI Works Boffa Miskell and Warren and Mahoney The consortium worked on the alliance model in which financial risks and incentives are shared among all partners Proposal to relocate northern vent stack Edit In December 2011 the construction consortium proposed relocating the northern stack from the east side of Great North Rd to the north side of Herdman Street As the Earth Pressure Balance tunnel boring machine TBM would be able to bore much closer to the surface than techniques assumed during the design phase the cut and cover tunneling technique was not required below Great North Road That meant that a duct below Great North Rd to a stack on the east side could not be constructed at the same time as the tunnels The northern location for the stack had been studied earlier but dismissed because of greater cost and the location had also created concerns among locals due to greater visual effects than that finally chosen by the Board of Inquiry 50 Enabling works Edit Enabling works began in January 2012 between the Maioro Street interchange and Alan Wood Park and included Establishment activities e g construction zone fencing project and way finding signage Removal of properties from within designation Construction of two temporary soccer fields senior and junior ablution block and a temporary car park at Valonia Street with field drainage and grass seeding from March 2012 Site access for heavy vehicles from Richardson Rd and 8 metre wide haul road west through Hendon Park Construction of temporary stream crossings for construction vehicle access Excavation and temporary diversion of a section of Oakley Creek adjacent to the sports fields to facilitate their construction Excavation of new stream channels in Alan Wood Park and temporary diversion of sections of Oakley Creek into the new alignment Diversion of utility services around Richardson Road to enable the construction of a road diversion Temporary realignment of Richardson Road while building new Richardson Rd bridge 51 Local electricity distribution company Vector also carried out enabling works to supply electricity to the tunnel portal sites for construction and included 52 Installing an 11 kV feeder line from the Chevalier zone substation on Great North Road to the northern portal site to supply the northern portal during construction Installing a 33 kV capable 22 kV operating underground cable from the Avondale zone substation on Blockhouse Bay Road to the southern portal site to supply the southern portal and the TBM during construction This also involved installing a 33 kV capable switchboard at Avondale to connect the tunnel supply to the two 22 kV cables feeding Avondale zone substation from the national grid at Mount Roskill Installing a new 11 kV local feeder line from Chevalier zone substation to the Waterview area to transfer some existing load off Avondale zone substation as Avondale could not supply both the TBM and its existing load without overloading Installing a second 22 11 kV transformer at the Chevalier zone substation as the existing transformer could not supply the northern portal and Waterview feeder lines without overloading Southern Portal works Edit Beginning July 2012 53 Northern Portal works and Great North Road Interchange Edit Beginning May 2013 53 note that works at the northern end will not initially involve tunnel boring Tunnelling Edit Main article Waterview TunnelOpening EditOn 24 March 2017 it was announced that the planned April 2017 opening of the 1 6 billion project was being held up for another two months because of issues with its fire sprinklers 54 On 11 June 2017 it was announced that the tunnel would open in early July 2017 55 The tunnels opened at 12 47 am on 2 July 2017 with three police cars leading the first vehicles through the northbound tunnel 56 Mitigation and related projects EditThis section s factual accuracy may be compromised due to out of date information Please help update this article to reflect recent events or newly available information September 2012 nbsp Great North Road and the overbridge of the Northwestern Cycleway The tunnel will surface just to the west right hand of the picture A number of not directly motorway related projects will form part of the SH20 connection works either to mitigate negative effects on the environment or to provide for other transport modes Avondale Southdown railway line Edit Enabling works and allowance for the Avondale Southdown Line are a part of constructing SH20 57 58 KiwiRail sees this route as strategically important as it is the only real alternative for a cross isthmus heavy rail route as upgrading of the existing Newmarket Line is not realistically feasible or possible KiwiRail requested that any tunnel construction not preclude rail above it in the future nor the possibility of rail being trenched to cross below New North Road to connect to the existing North Auckland Line 59 Passive open space Edit Passive open space will be lost during construction of the motorway to construction lay down areas and lost permanently where the motorway amp associated structures are built NZTA has proposed replacement passive open space below amp around the Waterview interchange ramps and the existing privately owned empty site adjoining Alan Wood Park and future surface motorway 60 Active open space Edit The existing fields at Waterview Reserve and Alan Wood Park will be lost NZTA propose to construct new fields adjacent to the Waterview interchange and above the tunnel entrances at Alan Wood Park These would likely be used as construction lay down areas during construction 60 During the project Expo s NZTA had proposed to develop additional fields at Phyllis St for use during the construction period but this was dropped for the EPA submission 61 Walkways and cycleways Edit Documents shown during the public consultation phase in early 2010 showed a proposed walkway and cycleway generally following the line of the motorway tunnel alignment connecting the existing SH16 Cycleway with the end of the then existing SH20 Cycleway including a walking cycling bridge over Oakley Creek at Phyllis Street 61 62 However at lodgement time in 2010 NZTA clarified that it would only build cycleways along the sections that are not located in a tunnel leaving the potential for a connecting cycleway between SH16 and SH20 in doubt 63 After a several months long hearing process the Board of Inquiry in mid 2011 however came to the decision that a walkway and cycleway along the tunnel alignment was a required mitigation for open space loss in the areas around both tunnel portals though not technically as transport mitigation and that NZTA will have to pay for though not build the facility 39 Cycling advocates Cycle Action Auckland lauded the decision as a resounding win for cycling in Auckland and a key part in making the Waterview Connection into a truly multi modal project The approximate route of the cycleway will be from near Alford Street in Waterview crossing a new bridge over Oakley Creek then through Phyllis Reserve before crossing to Alan Wood Park in New Windsor Owairaka via a new bridge over the rail line at Soljak Place 63 The bridge from Soljak Place over the railway to Harbutt Reserve is the first priority of the Alan Wood Park Soljak Place to Waterview area cycleway public consultation to be undertaken early 2012 64 Auckland Transport designed the 2 5 km long Waterview Shared Path from Alan Wood reserve with construction happening from March 2016 65 to mid 2017 66 Maioro Street to New Lynn Edit As part of the SH20 Mt Roskill extension NZTA widened Maioro Street from two to four lanes completed mid 2009 67 The Auckland City Council was responsible for widening the remaining route to New Lynn i e New Windsor Road Tiverton Road and Wolverton Road 68 While it completed some widening of Tiverton Road in 2007 Council deferred completing any more widening until 2015 2020 69 In late 2011 Auckland Transport called for expressions of interest from contractors to complete the works Construction was expected to start in the first half of 2012 subject to tender and NZTA funding and take up to two years to complete 70 On 17 April 2012 Auckland Transport announced that NZTA would fund 53 of the project 71 See also EditList of motorways expressways and highways in AucklandReferences Edit a b c Waterview makes most of tunnel Central Leader 3 June 2011 Retrieved 27 June 2011 a b Dearnaley Mathew 24 January 2010 Agency chided over pollution figures The New Zealand Herald Retrieved 7 February 2011 Auckland s Waterview Connection on schedule to open in early 2017 Stuff co nz 9 June 2016 Retrieved 15 May 2017 a b c Dearnaley Mathew 27 May 2011 Waterview approval starts race to win contract The New Zealand Herald Retrieved 13 June 2011 Consultation from the Transit New Zealand website AW1 is the confirmed preferred route for the Waterview Connection Newsletter 8 February 2006 from the SH20 project website of Transit New Zealand December 2005 Auckland City voted to support the extension of SH20 through Waterview Waitakere City conditionally support Waterview option 9 February 2006 City Development Committee page 2 9 Waitakere City conditionally support Waterview option 27 November 2006 Council page 8 14 March 2006 ARC media release ARC supports Rosebank route for SH20 extension Mathew Dearnaley 30 August 2006 Transit may ditch Mt Albert interchange plan The New Zealand Herald Retrieved 10 September 2011 Transit New Zealand Transit Waterview Connection Retrieved 8 February 2008 Mathew Dearnaley 17 April 2008 Groups call for three lane tunnels The New Zealand Herald Retrieved 10 September 2011 4 June 2008 TRANSIT BOARD SEEKS TO PROTECT TUNNEL ROUTE FOR WATERVIEW Mathew Dearnaley 5 June 2008 Designation sought over motorway land despite opposition The New Zealand Herald Retrieved 10 September 2011 Government to investigate feasibility of PPP for Waterview Connection The Beehive Retrieved 14 May 2017 Motorway tolls move a step closer The New Zealand Herald 26 August 2008 Retrieved 10 September 2011 Waterview Tunnel emissions will meet air quality standards NZ Transport Agency nzta govt nz Retrieved 14 May 2017 School gets help in air quality dispute Stuff Retrieved 14 May 2017 Tunnel holds up building new homes Central Leader 27 November 2008 Retrieved 2 December 2011 ARC agenda 24 November 2008 ARC minutes 24 November 2008 Conor English We can bank on wealth of water The New Zealand Herald 12 January 2009 Retrieved 8 February 2011 Mathew Dearnaley 31 January 2009 Cost blowout threatens tunnel plan The New Zealand Herald Retrieved 10 September 2011 Residents hit by Waterview decision contacted from today The New Zealand Herald 13 May 2009 Retrieved 10 September 2011 Transit Waterview Connection website Allan Wood Reserve cross section Transit Waterview Connection website Artist s impression of tunnel portal at Avondale Heights Transit Waterview Connection website Route Map Transit Waterview Connection website presentation of preferred route NZTA Media Release 11 Sep 09 NZTA Board paper 09 08 0250 Report on Community and Stakeholder Engagement Supplementary Paper Dearnaley Mathew 12 September 2009 Motorway to go ahead despite concerns The New Zealand Herald Retrieved 2 December 2011 NZTA Board meeting dates and agendas Final alignment for Western Ring Route unveiled The New Zealand Herald 21 December 2009 Retrieved 10 September 2011 NZTA Media Release 21 Dec 09 Revised Route Map 21 Dec 09 Dearnaley Mathew 4 September 2010 Waterview project on fast track The New Zealand Herald Retrieved 4 October 2010 a b Dearnaley Mathew 4 October 2010 Residents refused more time to fight motorway The New Zealand Herald Retrieved 4 October 2010 a b c d e f Dearnaley Mathew 9 May 2011 Objectors get their way on towers The New Zealand Herald Retrieved 26 May 2011 Dearnaley Mathew 19 January 2011 Filter tunnel fumes report tells agency The New Zealand Herald Retrieved 7 February 2011 Dearnaley Mathew 17 January 2011 Tunnels cause worry for Unitec The New Zealand Herald Retrieved 27 June 2011 Dearnaley Mathew 9 May 2011 Objectors get their way on towers The New Zealand Herald Retrieved 9 May 2011 Dearnaley Mathew 8 March 2010 Early start at Waterview The New Zealand Herald Retrieved 10 March 2010 NZTA media release 29 Oct 2010 Mathew Dearnaley 15 November 2010 Factory fight costs Crown 500 000 The New Zealand Herald Retrieved 10 September 2011 Local jobs must be protected in Faulkner Collins dispute say Local Board Members InfoNews 12 Nov 2010 Auckland company fights eviction by NZTA One News 8 November 2010 Retrieved 2 December 2011 NZTA announces shortlist to deliver Waterview Connection Press Release NZ Transport Agency 16 November 2010 Retrieved 13 June 2011 a b Gibson Anne 24 August 2011 Price decisive for Waterview contract The New Zealand Herald Retrieved 3 September 2011 Dearnaley Mathew 16 December 2011 Ventilation tower for tunnels may be moved The New Zealand Herald Retrieved 16 December 2011 Construction on the Waterview Connection project Press Release NZ Transport Agency 29 November 2011 Retrieved 29 November 2011 Electricity Asset Management Plan 2012 2022 PDF Vector Limited April 2012 p 5 86 5 88 Retrieved 18 April 2012 a b Construction Programme PDF Press Release NZ Transport Agency 28 November 2011 Retrieved 28 November 2011 Waterview Connection held up by faulty sprinklers Stuff co nz 24 March 2017 Retrieved 24 March 2017 Auckland s 1 4 billion Waterview tunnel to open in early July Retrieved 11 June 2017 Auckland s Waterview Tunnel open to traffic at last Stuff co nz 2 July 2017 Retrieved 2 July 2017 FAQ How will the new section of motorway affect the existing Southdown rail designation from the SH20 project website of Transit New Zealand SH20 Mt Roskill includes enabling works for a future rail line from the Transit New Zealand website Evidence of Pamela Marie Butler on behalf of KiwiRail PDF KiwiRail Environmental Protection Authority 17 December 2010 Retrieved 15 January 2011 a b NZTA project website a b Expo Posters Council seeks improvements for Waterview CityScene Auckland City Council 25 July 2010 a b Deal for cyclists takes step up The New Zealand Herald 13 June 2011 Retrieved 17 June 2011 ONW community liaison meeting 2 meeting notes 13 Dec 2011 Parminter Alice 10 February 2016 Auckland s Waterview cycle and walkway under construction Auckland Now Retrieved 3 July 2017 Waterview Shared Path Auckland Transport Transit Mt Roskill extension Project Details Auckland City Council Tiverton Road Wolverton Street upgrade Dearnaley Mathew 21 December 2007 Road widening to wait until after World Cup The New Zealand Herald Retrieved 7 February 2011 Auckland Transport Tiverton Wolverton upgrade Auckland Transport Funding approval given for Tiverton WolvertonExternal links EditWaterview Connection official NZTA project website Auckland Motorways Retrieved from https en wikipedia org w index php title Waterview Connection amp oldid 1145089464, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.