fbpx
Wikipedia

Responsibility assignment matrix

A responsibility assignment matrix[1] (RAM), also known as RACI matrix[2] (/ˈrsi/) or linear responsibility chart[3] (LRC), describes the participation by various roles in completing tasks or deliverables[4] for a project or business process. RACI is an acronym derived from the four key responsibilities most typically used: responsible, accountable, consulted, and informed.[5][4] It is used for clarifying and defining roles and responsibilities in cross-functional or departmental projects and processes.[6] There are a number of alternatives to the RACI model.

Key responsibility roles in RACI model edit

Role distinction edit

There is a distinction between a role and individually identified people: a role is a descriptor of an associated set of tasks; may be performed by many people; and one person can perform many roles. For example, an organization may have ten people who can perform the role of project manager, although traditionally each project only has one project manager at any one time; and a person who is able to perform the role of project manager may also be able to perform the role of business analyst and tester.

R = Responsible (also recommender)
Those who do the work to complete the task.[7] There is at least one role with a participation type of responsible, although others can be delegated to assist in the work required. (See also RASCI below for separately identifying those who participate in a supporting role.)
A = Accountable (also approver or final approving authority)
The one ultimately answerable for the correct and thorough completion of the deliverable or task, the one who ensures the prerequisites of the task are met and who delegates the work to those responsible.[7] In other words, an accountable must sign off (approve) work that responsible provides. There must be only one accountable specified for each task or deliverable.[8]
C = Consulted (sometimes consultant or counsel)
Those whose opinions are sought, typically subject-matter experts, and with whom there is two-way communication.[7]
I = Informed (also informee)
Those who are kept up-to-date on progress, often only on completion of the task or deliverable, and with whom there is just one-way communication.[7]

Very often the role that is accountable for a task or deliverable may also be responsible for completing it (indicated on the matrix by the task or deliverable having a role accountable for it, but no role responsible for its completion, i.e. it is implied). Outside of this exception, it is generally recommended that each role in the project or process for each task receive, at most, just one of the participation types. Where more than one participation type is shown, this generally implies that participation has not yet been fully resolved, which can impede the value of this technique in clarifying the participation of each role on each task.

Assigning people to facilities edit

The matrix is typically created with a vertical axis (left-hand column) of tasks (from a work breakdown structure) or deliverables (from a product breakdown structure), and a horizontal axis (top row) of roles (from an organizational chart).

Example of a responsibility assignment (or RACI) matrix
Code Name Project sponsor Business analyst Project manager Technical architect Applications development
Stage A Manage sales
Stage B Assess job
Stage C Initiate project
- C04 Security governance (draft) C C A I I
- C10 Functional requirements A R I C I
- C11 Business acceptance criteria A R I C I
Stage D Design solution

Another example from the maintenance and reliability community:

Maintenance crew KPI RACI chart
Tasks Maintenance supervisors Maintenance analyst Maintenance planner Maintenance technician Maintenance support Rel specialist CMMS project engineer
Inputting failure data A C I R C C
Work order completion R C C C A I I
Work order closeout C R C I I A
QA of failure data input C R I C I C A
Analyze failure reports C C I C A R I
Maintenance strategy adjustments C I I C A R R
Implementing new strategies R I R C A I I

Alternatives edit

There are a number of alternatives to the RACI participation types:

RACI ROLES SHORTEN: Roles are the following

Responsible
Does the work to complete the task  
Accountable
Delegates work and is the last one to review the task or deliverable before it's deemed complete
Consulted
Provides input based on either how it will impact their future project work or their domain of expertise on the deliverable itself
Informed
Needs to be kept in the loop on project progress, rather than roped into details of every deliverable

PARIS edit

This is an early version[9] of a responsibility assignment matrix, with the roles defined as:
Participant
Accountable
Review required
Input required
Sign-off required

PACSI edit

This is a version very useful to organizations where the output of activities under the accountability of a single person/function can be reviewed and vetoed by multiple stakeholders, due to the collaborative nature of the culture.
Perform
The person/function carrying out the activity.
Accountable
The person/function ultimately answerable for the correct and thorough completion of the deliverable or task, and often the one who delegates the work to the performer.
Control
The person/function reviewing the result of the activity. They have a right of veto; their advice is binding.
Suggest
The person/function consulted to give advice based upon recognized expertise. The advice is non-binding.
Informed
The person/function who must be informed of the result of the activity.

RASIC or RASCI edit

This is an expanded version[10] of the standard RACI, less frequently known as RASCI,[11] breaking the responsible participation into:
Responsible
Those responsible for the task, who ensure that it is done as per the approver
Support
Resources allocated to responsible. Unlike consulted, who may provide input to the task, support helps complete the task.

RASI edit

This is an alternative version[12] of the standard RACI, foregoing the consulted participation and replacing it with:
Support
Resources which play a supporting role in implementation.

RACI + F edit

This is an expanded version of the standard RACI, with an additional participation type: Facilitate. This variation was introduced by Christophe Le Coent in 2012.[13] Coent argued that the facilitator or coach role is important in agile software development environments and should therefore be explicitly included in the RAM.[13] The use of RAM in Agile environments is considered contentious because some practitioners believe that everyone working in an agile team should be jointly responsible and accountable.[14]
Facilitates
Facilitate activities during a Scrum project.

RACIQ edit

This is an expanded version of the standard RACI, with an additional participation type:
Quality review
Those who check whether the product meets the quality requirements.

RACI-VS edit

This is an expanded version[5] of the standard RACI, with two additional participation types:
Verifier
Those who check whether the product meets the acceptance criteria set forth in the product description.
Signatory
Those who approve the verify decision and authorize the product hand-off. The signatory should be the party being accountable for its success.

CAIRO edit

This is an expanded version[15] of the standard RACI, also known as RACIO[16] with one additional participation type.
Out of the loop (or omitted)
Designating individuals or groups who are specifically not part of the task. Specifying that a resource does not participate can be as beneficial to a task's completion as specifying those who do participate.

DACI edit

Another version that has been used to centralize decision making, and clarify who can re-open discussions.[17]
Driver
A single driver of overall project like the person steering a car.
Approver
One or more approvers who make most project decisions, and are responsible if it fails.
Contributors
Are the worker-bees who are responsible for deliverables; and with whom there is two-way communication.
Informed
Those who are impacted by the project and are provided status and informed of decisions; and with whom there is one-way communication.

RAPID edit

Another tool used to clarify decision roles and thereby improve decision making, is RAPID, which was created by and is a registered trademark of Bain & Company.
Recommend
The recommend role typically involves 80 percent of the work in a decision. The recommender gathers relevant input and proposes a course of action—sometimes alternative courses, complete with pros and cons so that the decision maker's choices are as clear, simple and timely as possible.
Agree
The agree role represents a formal approval of a recommendation. The 'A' and the 'R' should work together to come to a mutually satisfactory proposal to bring forward to the decider. But not all decisions will need an agree role, as this is typically reserved for those situations where some form of regulatory or compliance sign-off is required.
Perform
The perform role defines who is accountable for executing or implementing the decision once it is made. Best-practice companies typically define P's and gather input from them early in the process.
Input
The input role provides relevant information and facts so that the recommender and decider can assess all the relevant facts to make the right decision. However, the 'I' role is strictly advisory. Recommenders should consider all input, but they don't have to reflect every point of view in the final recommendation.
Decide
The decide role is for the single person who ultimately is accountable for making the final decision, committing the group to action and ensuring the decision gets implemented.

RATSI edit

Another tool used in organization design or roles analysis.
Responsibility
Identify who is in charge of making sure the work is done.
Authority
Identify who has final decision power on the work.
Task
Identify who actually does the work.
Support
Identify who is involved to provide support to the work.
Informed
Identify who is informed that the work has been done (or will be started)

DRASCI edit

A variant of RASCI developed by three Whitehall theorists (Kane, Jackson, Gilbert). This scheme is adapted for use in matrix management environments, and differs only from RASCI in having an additional role of Driver and a narrower definition of Support:
Driver
An individual or party that assists those who are responsible for delivering a task by both producing supporting collateral and setting timescales for delivery in line with the overarching aim of the individual or party who is accountable for the overall accomplishment of the objective. The distinction between driver and support lies in that the former reinforces and clarifies the parameters of the task on behalf of those who are accountable, while the latter refers to those who help those who are responsible in reaching a given goal.

PDQA edit

A version developed at U Tokyo and MIT for model-based project management. The PDQA set of roles corresponds to demand for capabilities of teams. Roles include those for work on scope, handling of dependencies as coordination, and exception handling through error detection and decisions across a project organization. PDQA is used in agent-based modeling to simulate the supply of these capabilities by teams in projects.[18]
Primary
Provides skill-based effort within capacity to complete scope and also manages dependencies through coordination.
Decision
Handles any decision, including scope acceptable and exception handling decisions leading to rework. (Does not generation nominal scope).
Quality
Reviews scope as it progresses to detect poor quality and escalates to decision-maker as so. (Does not general nominal scope).
Assist
Provides skill-based effort with the capacity to complete scope, in assistance to the primary. (Does not manage dependencies through coordination).

DCI edit

A minimal set of decision-making categories used in organisation design or roles analysis.
Decision maker
Individuals who make the decision and is accountable for its impact on the business.
Consulted
Individuals accountable for providing guidance based on functional expertise and experience, highlighting issues and raising alternatives to support the Decision Maker.
Informed
Impacted stakeholders are notified after the decision has been made and who will need to support the execution of the decision.

RASCEIO edit

To be used when working on governance, risk, compliance (GRC) and outsourcing matters:

Responsible
Accountable
Support
Consult
Execute
Third parties contracted to execute activities in accordance with a service level agreement
Inform
Overview
Key GRC roles, such as risk owner, policy owner - where accountability is devolved, but a role is needed to oversee whether accountabilities all fit together

Variations edit

There are also a number of variations to the meaning of RACI participation types:

RACI (alternative scheme) edit

There is an alternative coding, less widely published but used by some practitioners and process mapping software, which modifies the application of the R and A codes of the original scheme. The overall methodology remains the same but this alternative avoids potential confusion of the terms accountable and responsible, which may be understood by management professionals but not always so clearly differentiated by others:
Responsible
Those responsible for the performance of the task. There should be exactly one person with this assignment for each task.
Assists
Those who assist in the completion of the task
Consulted
Those whose opinions are sought; and with whom there is two-way communication.
Informed
Those who are kept up-to-date on progress; and with whom there is one-way communication.

ARCI (decisions) edit

This alternative is focused only on documenting who has the authority to make which decisions. This can work across all sized workgroups.
Accountable
Authorized to approve an answer to the decision.
Responsible
Responsible to recommend an answer to the decision.
Consulted
Those whose opinions are sought, and with whom there is two-way communication.
Informed
Those who are informed after the decision is made, and with whom there is one-way communication.

Citations edit

  1. ^ "9.1.2.1 Organization Charts and Position Descriptions". A Guide to the Project Management Body of Knowledge (PMBOK Guide) (5th ed.). Project Management Institute. 2013. p. 262. ISBN 978-1-935589-67-9.
  2. ^ Jacka, Mike; Keller, Paulette (2009). Business Process Mapping: Improving Customer Satisfaction. John Wiley and Sons. p. 257. ISBN 978-0-470-44458-0.
  3. ^ Cleland, David; Ireland, Lewis (2006). Project management: strategic design and implementation. McGraw-Hill Professional. p. 234. ISBN 0-07-147160-X.
  4. ^ a b Project Management Institute 2021, §4.6.6 Focus on Value.
  5. ^ a b Blokdijk, Gerard (2008). The Service Level Agreement SLA Guide - SLA Book, Templates for Service Level Management and Service Level Agreement Forms. Fast and Easy Way to Write Your SLA. Lulu. p. 81. ISBN 978-1-921523-62-5.
  6. ^ Brennan, Kevin (2009). A Guide to the Business Analysis Body of Knowledge (BABOK Guide). International Institute of Business Analysis. p. 29. ISBN 978-0-9811292-1-1.
  7. ^ a b c d Smith, Michael L.; Erwin, James. "Role & Responsibility Charting (RACI)" (PDF). Project Management Institute California Inland Empire Chapter. p. 5. from the original on 16 September 2022. Retrieved 18 May 2023.
  8. ^ Tiziana Margaria: Leveraging Applications of Formal Methods, Verification, and Validation: 4th International Symposium on Leveraging Applications Proceedings, Part 1, Springer, 2010, p. 492
  9. ^ A Guide to the Project Management Body of Knowledge. Project Management Institute. 2000. p. 111. ISBN 1-880410-22-2.
  10. ^ Hightower, Rose (2008). Internal controls policies and procedures. John Wiley & Sons. p. 83. ISBN 978-0-470-28717-0.
  11. ^ Baker, Dean (2009). Multi-Company Project Management: Maximizing Business Results Through Strategic Collaboration. J Ross. p. 58. ISBN 978-1-60427-035-8.
  12. ^ Mikes, Joe; Denton, Tara (2011). Training Speeds Continuous Improvement. Life Cycle Engineering.
  13. ^ a b . www.scrumalliance.org. Archived from the original on 16 October 2017. Retrieved 10 August 2022.
  14. ^ "RACI Matrix | Definition and Example | How to".
  15. ^ Bolman, Lee (2008). Reframing organizations: artistry, choice, and leadership. John Wiley & Sons. p. 112. ISBN 978-0-7879-8799-2.
  16. ^ Dickstein, Dennis (2008). No Excuses: A Business Process Approach to Managing Operational Risk. John Wiley & Sons. ISBN 978-0-470-48110-3.
  17. ^ Kendrick, Tom (2006). Results without authority: controlling a project when the team doesn't report to you. AMACOM Books, division of the American Management Association. p. 106. ISBN 0-8144-7343-1.
  18. ^ Moser, B. R.; Wood, R. T. (2015). "Design of Complex Programs as Sociotechnical Systems". Concurrent Engineering in the 21st Century. Springer. pp. 197–220. doi:10.1007/978-3-319-13776-6_8. ISBN 978-3-319-13775-9.

References edit

  • Project Management Institute (2021). A guide to the project management body of knowledge (PMBOK guide). Project Management Institute (7th ed.). Newtown Square, PA. ISBN 978-1-62825-664-2.{{cite book}}: CS1 maint: location missing publisher (link)

External links edit

    responsibility, assignment, matrix, responsibility, assignment, matrix, also, known, raci, matrix, linear, responsibility, chart, describes, participation, various, roles, completing, tasks, deliverables, project, business, process, raci, acronym, derived, fro. A responsibility assignment matrix 1 RAM also known as RACI matrix 2 ˈ r eɪ s i or linear responsibility chart 3 LRC describes the participation by various roles in completing tasks or deliverables 4 for a project or business process RACI is an acronym derived from the four key responsibilities most typically used responsible accountable consulted and informed 5 4 It is used for clarifying and defining roles and responsibilities in cross functional or departmental projects and processes 6 There are a number of alternatives to the RACI model Contents 1 Key responsibility roles in RACI model 1 1 Role distinction 2 Assigning people to facilities 3 Alternatives 3 1 PARIS 3 2 PACSI 3 3 RASIC or RASCI 3 4 RASI 3 5 RACI F 3 6 RACIQ 3 7 RACI VS 3 8 CAIRO 3 9 DACI 3 10 RAPID 3 11 RATSI 3 12 DRASCI 3 13 PDQA 3 14 DCI 3 15 RASCEIO 4 Variations 4 1 RACI alternative scheme 4 2 ARCI decisions 5 Citations 6 References 7 External linksKey responsibility roles in RACI model editRole distinction edit There is a distinction between a role and individually identified people a role is a descriptor of an associated set of tasks may be performed by many people and one person can perform many roles For example an organization may have ten people who can perform the role of project manager although traditionally each project only has one project manager at any one time and a person who is able to perform the role of project manager may also be able to perform the role of business analyst and tester R Responsible also recommender Those who do the work to complete the task 7 There is at least one role with a participation type of responsible although others can be delegated to assist in the work required See also RASCI below for separately identifying those who participate in a supporting role A Accountable also approver or final approving authority The one ultimately answerable for the correct and thorough completion of the deliverable or task the one who ensures the prerequisites of the task are met and who delegates the work to those responsible 7 In other words an accountable must sign off approve work that responsible provides There must be only one accountable specified for each task or deliverable 8 C Consulted sometimes consultant or counsel Those whose opinions are sought typically subject matter experts and with whom there is two way communication 7 I Informed also informee Those who are kept up to date on progress often only on completion of the task or deliverable and with whom there is just one way communication 7 Very often the role that is accountable for a task or deliverable may also be responsible for completing it indicated on the matrix by the task or deliverable having a role accountable for it but no role responsible for its completion i e it is implied Outside of this exception it is generally recommended that each role in the project or process for each task receive at most just one of the participation types Where more than one participation type is shown this generally implies that participation has not yet been fully resolved which can impede the value of this technique in clarifying the participation of each role on each task Assigning people to facilities editThe matrix is typically created with a vertical axis left hand column of tasks from a work breakdown structure or deliverables from a product breakdown structure and a horizontal axis top row of roles from an organizational chart Example of a responsibility assignment or RACI matrix Code Name Project sponsor Business analyst Project manager Technical architect Applications developmentStage A Manage salesStage B Assess jobStage C Initiate project C04 Security governance draft C C A I I C10 Functional requirements A R I C I C11 Business acceptance criteria A R I C IStage D Design solutionAnother example from the maintenance and reliability community Maintenance crew KPI RACI chart Tasks Maintenance supervisors Maintenance analyst Maintenance planner Maintenance technician Maintenance support Rel specialist CMMS project engineerInputting failure data A C I R C CWork order completion R C C C A I IWork order closeout C R C I I AQA of failure data input C R I C I C AAnalyze failure reports C C I C A R IMaintenance strategy adjustments C I I C A R RImplementing new strategies R I R C A I IAlternatives editThere are a number of alternatives to the RACI participation types RACI ROLES SHORTEN Roles are the following Responsible Does the work to complete the task Accountable Delegates work and is the last one to review the task or deliverable before it s deemed complete Consulted Provides input based on either how it will impact their future project work or their domain of expertise on the deliverable itself Informed Needs to be kept in the loop on project progress rather than roped into details of every deliverablePARIS edit This is an early version 9 of a responsibility assignment matrix with the roles defined as Participant dd Accountable dd Review required dd Input required dd Sign off required dd PACSI edit This is a version very useful to organizations where the output of activities under the accountability of a single person function can be reviewed and vetoed by multiple stakeholders due to the collaborative nature of the culture Perform dd The person function carrying out the activity dd Accountable dd The person function ultimately answerable for the correct and thorough completion of the deliverable or task and often the one who delegates the work to the performer dd Control The person function reviewing the result of the activity They have a right of veto their advice is binding dd Suggest dd The person function consulted to give advice based upon recognized expertise The advice is non binding dd Informed dd The person function who must be informed of the result of the activity dd RASIC or RASCI edit This is an expanded version 10 of the standard RACI less frequently known as RASCI 11 breaking the responsible participation into Responsible dd Those responsible for the task who ensure that it is done as per the approver dd Support Resources allocated to responsible Unlike consulted who may provide input to the task support helps complete the task dd RASI edit This is an alternative version 12 of the standard RACI foregoing the consulted participation and replacing it with Support Resources which play a supporting role in implementation dd RACI F edit This is an expanded version of the standard RACI with an additional participation type Facilitate This variation was introduced by Christophe Le Coent in 2012 13 Coent argued that the facilitator or coach role is important in agile software development environments and should therefore be explicitly included in the RAM 13 The use of RAM in Agile environments is considered contentious because some practitioners believe that everyone working in an agile team should be jointly responsible and accountable 14 Facilitates Facilitate activities during a Scrum project dd RACIQ edit This is an expanded version of the standard RACI with an additional participation type Quality review Those who check whether the product meets the quality requirements dd RACI VS edit This is an expanded version 5 of the standard RACI with two additional participation types Verifier Those who check whether the product meets the acceptance criteria set forth in the product description dd Signatory dd Those who approve the verify decision and authorize the product hand off The signatory should be the party being accountable for its success dd CAIRO edit This is an expanded version 15 of the standard RACI also known as RACIO 16 with one additional participation type Out of the loop or omitted Designating individuals or groups who are specifically not part of the task Specifying that a resource does not participate can be as beneficial to a task s completion as specifying those who do participate dd DACI edit Another version that has been used to centralize decision making and clarify who can re open discussions 17 Driver A single driver of overall project like the person steering a car dd Approver One or more approvers who make most project decisions and are responsible if it fails dd Contributors Are the worker bees who are responsible for deliverables and with whom there is two way communication dd Informed Those who are impacted by the project and are provided status and informed of decisions and with whom there is one way communication dd RAPID edit Another tool used to clarify decision roles and thereby improve decision making is RAPID which was created by and is a registered trademark of Bain amp Company Recommend The recommend role typically involves 80 percent of the work in a decision The recommender gathers relevant input and proposes a course of action sometimes alternative courses complete with pros and cons so that the decision maker s choices are as clear simple and timely as possible dd Agree The agree role represents a formal approval of a recommendation The A and the R should work together to come to a mutually satisfactory proposal to bring forward to the decider But not all decisions will need an agree role as this is typically reserved for those situations where some form of regulatory or compliance sign off is required dd Perform The perform role defines who is accountable for executing or implementing the decision once it is made Best practice companies typically define P s and gather input from them early in the process dd Input The input role provides relevant information and facts so that the recommender and decider can assess all the relevant facts to make the right decision However the I role is strictly advisory Recommenders should consider all input but they don t have to reflect every point of view in the final recommendation dd Decide The decide role is for the single person who ultimately is accountable for making the final decision committing the group to action and ensuring the decision gets implemented dd RATSI edit Another tool used in organization design or roles analysis Responsibility Identify who is in charge of making sure the work is done dd Authority Identify who has final decision power on the work dd Task Identify who actually does the work dd Support Identify who is involved to provide support to the work dd Informed Identify who is informed that the work has been done or will be started dd DRASCI edit A variant of RASCI developed by three Whitehall theorists Kane Jackson Gilbert This scheme is adapted for use in matrix management environments and differs only from RASCI in having an additional role of Driver and a narrower definition of Support Driver An individual or party that assists those who are responsible for delivering a task by both producing supporting collateral and setting timescales for delivery in line with the overarching aim of the individual or party who is accountable for the overall accomplishment of the objective The distinction between driver and support lies in that the former reinforces and clarifies the parameters of the task on behalf of those who are accountable while the latter refers to those who help those who are responsible in reaching a given goal dd PDQA edit A version developed at U Tokyo and MIT for model based project management The PDQA set of roles corresponds to demand for capabilities of teams Roles include those for work on scope handling of dependencies as coordination and exception handling through error detection and decisions across a project organization PDQA is used in agent based modeling to simulate the supply of these capabilities by teams in projects 18 Primary Provides skill based effort within capacity to complete scope and also manages dependencies through coordination dd Decision Handles any decision including scope acceptable and exception handling decisions leading to rework Does not generation nominal scope dd Quality Reviews scope as it progresses to detect poor quality and escalates to decision maker as so Does not general nominal scope dd Assist Provides skill based effort with the capacity to complete scope in assistance to the primary Does not manage dependencies through coordination dd DCI edit A minimal set of decision making categories used in organisation design or roles analysis Decision maker Individuals who make the decision and is accountable for its impact on the business dd Consulted Individuals accountable for providing guidance based on functional expertise and experience highlighting issues and raising alternatives to support the Decision Maker dd Informed Impacted stakeholders are notified after the decision has been made and who will need to support the execution of the decision dd RASCEIO edit To be used when working on governance risk compliance GRC and outsourcing matters Responsible dd Accountable dd Support dd Consult dd Execute Third parties contracted to execute activities in accordance with a service level agreement Inform dd Overview Key GRC roles such as risk owner policy owner where accountability is devolved but a role is needed to oversee whether accountabilities all fit together dd Variations editThis section does not cite any sources Please help improve this section by adding citations to reliable sources Unsourced material may be challenged and removed February 2017 Learn how and when to remove this template message There are also a number of variations to the meaning of RACI participation types RACI alternative scheme edit There is an alternative coding less widely published but used by some practitioners and process mapping software which modifies the application of the R and A codes of the original scheme The overall methodology remains the same but this alternative avoids potential confusion of the terms accountable and responsible which may be understood by management professionals but not always so clearly differentiated by others Responsible Those responsible for the performance of the task There should be exactly one person with this assignment for each task dd Assists Those who assist in the completion of the task dd Consulted Those whose opinions are sought and with whom there is two way communication dd Informed Those who are kept up to date on progress and with whom there is one way communication dd ARCI decisions edit This alternative is focused only on documenting who has the authority to make which decisions This can work across all sized workgroups Accountable Authorized to approve an answer to the decision dd Responsible Responsible to recommend an answer to the decision dd Consulted Those whose opinions are sought and with whom there is two way communication dd Informed Those who are informed after the decision is made and with whom there is one way communication dd Citations edit 9 1 2 1 Organization Charts and Position Descriptions A Guide to the Project Management Body of Knowledge PMBOK Guide 5th ed Project Management Institute 2013 p 262 ISBN 978 1 935589 67 9 Jacka Mike Keller Paulette 2009 Business Process Mapping Improving Customer Satisfaction John Wiley and Sons p 257 ISBN 978 0 470 44458 0 Cleland David Ireland Lewis 2006 Project management strategic design and implementation McGraw Hill Professional p 234 ISBN 0 07 147160 X a b Project Management Institute 2021 4 6 6 Focus on Value a b Blokdijk Gerard 2008 The Service Level Agreement SLA Guide SLA Book Templates for Service Level Management and Service Level Agreement Forms Fast and Easy Way to Write Your SLA Lulu p 81 ISBN 978 1 921523 62 5 Brennan Kevin 2009 A Guide to the Business Analysis Body of Knowledge BABOK Guide International Institute of Business Analysis p 29 ISBN 978 0 9811292 1 1 a b c d Smith Michael L Erwin James Role amp Responsibility Charting RACI PDF Project Management Institute California Inland Empire Chapter p 5 Archived from the original on 16 September 2022 Retrieved 18 May 2023 Tiziana Margaria Leveraging Applications of Formal Methods Verification and Validation 4th International Symposium on Leveraging Applications Proceedings Part 1 Springer 2010 p 492 A Guide to the Project Management Body of Knowledge Project Management Institute 2000 p 111 ISBN 1 880410 22 2 Hightower Rose 2008 Internal controls policies and procedures John Wiley amp Sons p 83 ISBN 978 0 470 28717 0 Baker Dean 2009 Multi Company Project Management Maximizing Business Results Through Strategic Collaboration J Ross p 58 ISBN 978 1 60427 035 8 Mikes Joe Denton Tara 2011 Training Speeds Continuous Improvement Life Cycle Engineering a b The RACI F Matrix Scrum Alliance www scrumalliance org Archived from the original on 16 October 2017 Retrieved 10 August 2022 RACI Matrix Definition and Example How to Bolman Lee 2008 Reframing organizations artistry choice and leadership John Wiley amp Sons p 112 ISBN 978 0 7879 8799 2 Dickstein Dennis 2008 No Excuses A Business Process Approach to Managing Operational Risk John Wiley amp Sons ISBN 978 0 470 48110 3 Kendrick Tom 2006 Results without authority controlling a project when the team doesn t report to you AMACOM Books division of the American Management Association p 106 ISBN 0 8144 7343 1 Moser B R Wood R T 2015 Design of Complex Programs as Sociotechnical Systems Concurrent Engineering in the 21st Century Springer pp 197 220 doi 10 1007 978 3 319 13776 6 8 ISBN 978 3 319 13775 9 References editProject Management Institute 2021 A guide to the project management body of knowledge PMBOK guide Project Management Institute 7th ed Newtown Square PA ISBN 978 1 62825 664 2 a href Template Cite book html title Template Cite book cite book a CS1 maint location missing publisher link External links editComprehensive Series on RACI Retrieved from https en wikipedia org w index php title Responsibility assignment matrix amp oldid 1173787501, wikipedia, wiki, book, books, library,

    article

    , read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.