fbpx
Wikipedia

Morley Tunnel

Morley Tunnel is a railway tunnel in West Yorkshire, England, situated between Morley and Batley railway stations on the Huddersfield line. From its northern end (53°44′56″N 1°35′34″W / 53.7490°N 1.5927°W / 53.7490; -1.5927), it extends 3,369 yards (3,081 m), passing beneath Morley town centre, to its southern end (53°43′34″N 1°37′09″W / 53.7260°N 1.6192°W / 53.7260; -1.6192).

Morley Tunnel
Northern portal at Morley railway station
Overview
LineHuddersfield line
LocationWest Yorkshire
Coordinates53°44′23″N 1°36′12″W / 53.7397°N 1.6033°W / 53.7397; -1.6033
OS grid referenceSE 26261 27108
SystemNational Rail
StartMorley station
EndUpper Batley
Operation
Constructed1845–1848
OwnerNetwork Rail
Operator
TrafficTrain
CharacterPassenger
Technical
Design engineerThomas Granger[1]
Length3,369 yd (3,081 m)
No. of tracksDouble track
Track gauge4 ft 8+12 in (1,435 mm)
Tunnel clearance26 ft (7.9 m)
Width26 ft (7.9 m)
Morley Tunnel (West Yorkshire)
Southern portal

History edit

The construction of Morley Tunnel began in 1845.[2] The first stone was laid on 23 February 1846 by John Gott, the chairman of the Leeds, Dewsbury and Manchester Railway.[1] The tunnel was finally completed on 9 May 1848, when the last keystone was placed at the Morley end of the tunnel by Thomas Grainger,[3] the principal engineer. The completion of the tunnel created much excitement around the town, and a band marked this occasion when it played at the event.[4] The resident engineer was Henry Renton.[5] However, by 6 May 1846, the original contractors for the tunnel, Jones, Humphries and Pickering, were dismissed as work had been progressing from both ends of the tunnel that had been undertaken too fast, and the two sections would not have met in the middle due to a height difference.[6]

The completion of the tunnel provided a much needed rail link between Yorkshire and Lancashire. During construction, 18 working shafts were sunk so that work could proceed at a clearance rate of 300 yards (270 m) per month.[7] In addition, there are four permanent vent/construction shafts still in use today at Town End, Hopewell Farm, America Moor and Howley Park. At one time, men worked at 48 different points along the length of the tunnel. This was made possible by using steam engines to lower men down the working shafts to the level of the tunnel and raising stone and clay to the surface.[8]

To construct the tunnel, 11 powerful steam engines, 15 double horse gins, 2,000 men and 330 horses were used, and the work caused a huge change to the then known landscape, particularly in the area where Morley Low station is situated, where a huge cutting had to be excavated and the valley stream had to be culverted.[9] At its deepest point the tunnel is 400 feet below ground level. It is almost level throughout its length except for a slight gradient to allow for drainage. The tunnel is 3,369 yards (3,081 m) long,[10] 26 feet (7.9 m) high and 26 feet wide to accommodate two tracks. Between 1857 and 1961, the other station (Morley Top) was 200 feet (61 m) above the centre point of the tunnel.[11] The construction of the tunnel was undertaken in a shorter time-span than that of Standedge Tunnel, which was being built around the same time, even though Morley Tunnel is longer. However, the challenging conditions at Standedge made that work harder.[7]

Morley Tunnel was built above substantial coal measures that had been licensed to the Earl of Cardigan. Large sums in compensation money had to be paid out to his estate as mining underneath the tunnel would have led to subsidence issues.[12] In 1890, a decision was taken to quadruple the route between Leeds and Huddersfield, but Morley Tunnel proved to be too much of an engineering issue to overcome, so the Leeds New Line was promoted instead to provide extra traffic.[13] However, coal mining did create a myriad of problems as the tunnel was built over the workings of two local collieries; Morley Main and Howley Park.[14] The whole tunnel was rebuilt during the 1920s, with single line working implemented. The portal at the southern end (nearest Batley), was taken down completely and rebuilt using Staffordshire Blue Brick, with this work not being completed until 1933.[15]

The rock and clay brought to the surface from the tunnelling project was used as building material, producing bricks from the excavated clay. Much of the sandstone not suitable for this was used in road building.[16]

Today edit

Today, the tunnel is used by the local services run by Northern and the long distance services between Leeds and Manchester Piccadilly by TransPennine Express as part of the London North Eastern (LNE) route (Network Rail designation), between Leeds and Huddersfield.[17]

References edit

  1. ^ a b Baines, Thomas (1870). Yorkshire, past and present: Vol.2. London: W. Mackenzie. p. 452. Retrieved 18 April 2020.
  2. ^ "Leeds, Dewsbury & Manchester Railway tunnel contract". Leeds Mercury. No. 5816. Column E. 24 May 1845. p. 6. OCLC 751697369.
  3. ^ Chrimes, Mike (2002). Biographical dictionary of civil engineers in Great Britain and Ireland. Vol. 2, 1830-1890. London: The Institution of Civil Engineers. p. 265. ISBN 072772939X.
  4. ^ "Completion of Morley Tunnel". Leeds Mercury. No. 5971. Column A. 13 May 1848. p. 8. OCLC 751697369.
  5. ^ "Account of the construction of the Morley Tunnel, Leeds Dewsbury & Manchester Railway | Science Museum Group Collection". collection.sciencemuseumgroup.org.uk. Retrieved 25 October 2021.
  6. ^ Fraser 2019, p. 13.
  7. ^ a b Joy 2021, p. 88.
  8. ^ Smith, William (1876). The History and Antiquities of Morley. London: Longman, Greens & Co. p. 66. OCLC 500096973.
  9. ^ Ward 1973, p. 80.
  10. ^ Bairstow, Martin (1984). The Leeds, Huddersfield and Manchester Railway; the Standedge Line. Pudsey: Bairstow. p. 71. ISBN 0-90243830-1.
  11. ^ Joy, David (1984). A Regional History of the Railways of Great Britain, Volume 8: South and West Yorkshire (2 ed.). Newton Abbot: David & Charles. p. 85. ISBN 0-946537-11-9.
  12. ^ Fraser 2019, p. 18.
  13. ^ Fraser 2019, p. 113.
  14. ^ "Morley Tunnel at Morley Low Station". leodis.net. Retrieved 4 November 2021.
  15. ^ Fraser 2019, p. 149.
  16. ^ "Morley Conservation Area Appraisal" (PDF). leeds.gov.uk. 2012. p. 7. Retrieved 4 November 2021.
  17. ^ "Derailment in Summit tunnel, near Todmorden, West Yorkshire 28 December 2010" (PDF). assets.publishing.service.gov.uk. 2011. p. 33. Retrieved 25 October 2021.

Sources edit

  • Fraser, Neil (2019). Yorkshire Lines of the LNWR. Catrine: The Oakwood Press. ISBN 978-0-85361-561-3.
  • Joy, David (2021). Piercing the Pennines : heroic railways linking Lancashire and Yorkshire. Bradford: Great Northern Books. ISBN 978-1-914227-02-8.
  • Ward, Norrie (1973). "Genesis; the cutting of Morley Tunnel". There's no place like Morley. Driffield: Ridings Publishing. ISBN 0901934208.

External links edit

    morley, tunnel, railway, tunnel, west, yorkshire, england, situated, between, morley, batley, railway, stations, huddersfield, line, from, northern, 7490, 5927, 7490, 5927, extends, yards, passing, beneath, morley, town, centre, southern, 7260, 6192, 7260, 619. Morley Tunnel is a railway tunnel in West Yorkshire England situated between Morley and Batley railway stations on the Huddersfield line From its northern end 53 44 56 N 1 35 34 W 53 7490 N 1 5927 W 53 7490 1 5927 it extends 3 369 yards 3 081 m passing beneath Morley town centre to its southern end 53 43 34 N 1 37 09 W 53 7260 N 1 6192 W 53 7260 1 6192 Morley TunnelNorthern portal at Morley railway stationOverviewLineHuddersfield lineLocationWest YorkshireCoordinates53 44 23 N 1 36 12 W 53 7397 N 1 6033 W 53 7397 1 6033OS grid referenceSE 26261 27108SystemNational RailStartMorley stationEndUpper BatleyOperationConstructed1845 1848OwnerNetwork RailOperatorTransPennine ExpressNorthernTrafficTrainCharacterPassengerTechnicalDesign engineerThomas Granger 1 Length3 369 yd 3 081 m No of tracksDouble trackTrack gauge4 ft 8 1 2 in 1 435 mm Tunnel clearance26 ft 7 9 m Width26 ft 7 9 m Morley Tunnel West Yorkshire Southern portal Contents 1 History 2 Today 3 References 3 1 Sources 4 External linksHistory editThe construction of Morley Tunnel began in 1845 2 The first stone was laid on 23 February 1846 by John Gott the chairman of the Leeds Dewsbury and Manchester Railway 1 The tunnel was finally completed on 9 May 1848 when the last keystone was placed at the Morley end of the tunnel by Thomas Grainger 3 the principal engineer The completion of the tunnel created much excitement around the town and a band marked this occasion when it played at the event 4 The resident engineer was Henry Renton 5 However by 6 May 1846 the original contractors for the tunnel Jones Humphries and Pickering were dismissed as work had been progressing from both ends of the tunnel that had been undertaken too fast and the two sections would not have met in the middle due to a height difference 6 The completion of the tunnel provided a much needed rail link between Yorkshire and Lancashire During construction 18 working shafts were sunk so that work could proceed at a clearance rate of 300 yards 270 m per month 7 In addition there are four permanent vent construction shafts still in use today at Town End Hopewell Farm America Moor and Howley Park At one time men worked at 48 different points along the length of the tunnel This was made possible by using steam engines to lower men down the working shafts to the level of the tunnel and raising stone and clay to the surface 8 To construct the tunnel 11 powerful steam engines 15 double horse gins 2 000 men and 330 horses were used and the work caused a huge change to the then known landscape particularly in the area where Morley Low station is situated where a huge cutting had to be excavated and the valley stream had to be culverted 9 At its deepest point the tunnel is 400 feet below ground level It is almost level throughout its length except for a slight gradient to allow for drainage The tunnel is 3 369 yards 3 081 m long 10 26 feet 7 9 m high and 26 feet wide to accommodate two tracks Between 1857 and 1961 the other station Morley Top was 200 feet 61 m above the centre point of the tunnel 11 The construction of the tunnel was undertaken in a shorter time span than that of Standedge Tunnel which was being built around the same time even though Morley Tunnel is longer However the challenging conditions at Standedge made that work harder 7 Morley Tunnel was built above substantial coal measures that had been licensed to the Earl of Cardigan Large sums in compensation money had to be paid out to his estate as mining underneath the tunnel would have led to subsidence issues 12 In 1890 a decision was taken to quadruple the route between Leeds and Huddersfield but Morley Tunnel proved to be too much of an engineering issue to overcome so the Leeds New Line was promoted instead to provide extra traffic 13 However coal mining did create a myriad of problems as the tunnel was built over the workings of two local collieries Morley Main and Howley Park 14 The whole tunnel was rebuilt during the 1920s with single line working implemented The portal at the southern end nearest Batley was taken down completely and rebuilt using Staffordshire Blue Brick with this work not being completed until 1933 15 The rock and clay brought to the surface from the tunnelling project was used as building material producing bricks from the excavated clay Much of the sandstone not suitable for this was used in road building 16 Today editToday the tunnel is used by the local services run by Northern and the long distance services between Leeds and Manchester Piccadilly by TransPennine Express as part of the London North Eastern LNE route Network Rail designation between Leeds and Huddersfield 17 References edit a b Baines Thomas 1870 Yorkshire past and present Vol 2 London W Mackenzie p 452 Retrieved 18 April 2020 Leeds Dewsbury amp Manchester Railway tunnel contract Leeds Mercury No 5816 Column E 24 May 1845 p 6 OCLC 751697369 Chrimes Mike 2002 Biographical dictionary of civil engineers in Great Britain and Ireland Vol 2 1830 1890 London The Institution of Civil Engineers p 265 ISBN 072772939X Completion of Morley Tunnel Leeds Mercury No 5971 Column A 13 May 1848 p 8 OCLC 751697369 Account of the construction of the Morley Tunnel Leeds Dewsbury amp Manchester Railway Science Museum Group Collection collection sciencemuseumgroup org uk Retrieved 25 October 2021 Fraser 2019 p 13 a b Joy 2021 p 88 Smith William 1876 The History and Antiquities of Morley London Longman Greens amp Co p 66 OCLC 500096973 Ward 1973 p 80 Bairstow Martin 1984 The Leeds Huddersfield and Manchester Railway the Standedge Line Pudsey Bairstow p 71 ISBN 0 90243830 1 Joy David 1984 A Regional History of the Railways of Great Britain Volume 8 South and West Yorkshire 2 ed Newton Abbot David amp Charles p 85 ISBN 0 946537 11 9 Fraser 2019 p 18 Fraser 2019 p 113 Morley Tunnel at Morley Low Station leodis net Retrieved 4 November 2021 Fraser 2019 p 149 Morley Conservation Area Appraisal PDF leeds gov uk 2012 p 7 Retrieved 4 November 2021 Derailment in Summit tunnel near Todmorden West Yorkshire 28 December 2010 PDF assets publishing service gov uk 2011 p 33 Retrieved 25 October 2021 Sources edit Fraser Neil 2019 Yorkshire Lines of the LNWR Catrine The Oakwood Press ISBN 978 0 85361 561 3 Joy David 2021 Piercing the Pennines heroic railways linking Lancashire and Yorkshire Bradford Great Northern Books ISBN 978 1 914227 02 8 Ward Norrie 1973 Genesis the cutting of Morley Tunnel There s no place like Morley Driffield Ridings Publishing ISBN 0901934208 External links edit nbsp Wikimedia Commons has media related to Morley Tunnel Old image of tunnel Retrieved from https en wikipedia org w index php title Morley Tunnel amp oldid 1058998778, wikipedia, wiki, book, books, library,

    article

    , read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.