fbpx
Wikipedia

Metro Line

The Metro Line is a light rail transit line on the Edmonton LRT system. The line operates from northwest Edmonton to south Edmonton, and began operation on September 6, 2015. The line consists of ten stations, three of which are exclusive to the line and the remaining seven are shared with the Capital Line.

Metro Line
Siemens-Duewag U2 LRVs on Metro Line service at Kingsway/Royal Alex station
Overview
LocaleEdmonton
Termini
Stations10 (originally 14)
Service
TypeLight rail
SystemEdmonton LRT
Operator(s)Edmonton Transit Service
Depot(s)D.L. MacDonald Yard
Northwest LRT Yard (proposed)[1]
History
OpenedSeptember 6, 2015[2]
Technical
Line length8 km (5.0 mi)
Number of tracks2
Track gauge1,435 mm (4 ft 8+12 in)
Operating speed70 kilometres per hour (43 mph)
Route map

A one-stop extension to Blatchford Gate station was completed in late 2023 but has yet to open. An extension to the northwest city limits, at the border with the city of St. Albert, has completed conceptual design,[3] while St. Albert has mapped a possible extension through that city, along Highway 2/St. Albert Trail.[4]

History edit

In spring 2007, the funding for a concept plan and preliminary engineering was commissioned, and the City approved the plan the next year.[5] In 2008, during construction of the Epcor Tower, the City ordered that the tunnel section below the tower be dug before the tower was completed, this saved $140 million from digging after the tower was built.[6][7] The remainder of the tunnel, under Downtown Edmonton, was constructed using the sequential excavation method, and completed in November 2012.[8] In 2009 the City approved the relocation of funds from the Gorman extension to the Metro Line, as the City felt northwest was a higher priority.[9][10] In 2010, the city began preparation work, including utility relocations, building removals, roadwork, Kingsway road reconstruction and track slab construction.[5][11] The permanent closure of 105 Avenue between 102 Street and 105 Street was performed so MacEwan Station could be built. 105 Street was permanently closed to vehicular traffic between 107 Avenue and 108 Avenue to allow the line to continue along the existing road corridor, which alleviated the need to widen the corridor and remove some existing trees. 104 Street was closed between 108 Avenue and Kingsway in a similar fashion.[12] Construction was completed in 2014 in time to accommodate a spring 2014 opening.[11] Bus service began for the first Metro Line facility, the Kingsway/Royal Alex Transit Centre, on June 29, 2014.[11] The public plaza surrounding MacEwan Station, except for the area required to build Rogers Place, opened for use by people other than the construction crew in December 2014.[13]

On September 6, 2015, the three stations and 3.3 kilometres (2.1 mi) of track,[14] opened to the public.

The cost of the project was $665 million, jointly funded by the City of Edmonton, Province of Alberta, and the Government of Canada.[14][15] It was the first new line that was not an extension of the existing line. The line was expected to add 13,200 riders per weekday.[16]

On August 30, 2021 (late evenings and Sundays starting June 27, 2021[17]), service on the Metro Line was modified to end at Health Sciences/Jubilee station, as was originally planned but delayed due to signalling issues which caused trains to run a reduced frequency to the interim terminus at Century Park station to ensure the Capital Line could run at full frequency.[18]

Signalling issues edit

Testing began in July 2013,[12] and the line began operation in September 2015 with restrictions.[19][11][20][21][22] There were three delays in beginning operations on the line: one from April to June 2014, one from June to December 2014, and another from December 2014 to February 2015. The delays were caused by issues with the signalling system built by Thales.[23][24][25] Thales gave control of the system to the City of Edmonton in March 2015, but failed to provide adequate documentation to place the line into service.[20] In February 2017, trains were cleared to travel at 50 km/h.[26] The Thales signalling system used communications-based train control (CBTC) where trains occupy a "footprint", measure, and adjust their operation relative to the next train in front of them, hence the term "moving block" (as opposed to a traditional fixed block signal where each block is occupied by a train).

In September 2018, the Toronto Star reported that Edmonton had given Thales until April 30, 2017, to bring the system to full functionality.[27] Edmonton had withheld $22 million from Thales, until the system was fully functional. When Thales did not meet this deadline Edmonton gave Thales a "notice of default". On September 13, 2018, Edmonton announced Thales had promised the signalling system would be fully functional by December 2018.[28] Edmonton also announced there was a backup plan, to keep the route functioning, if Thales failed to deliver.

In April 2019, the City of Edmonton terminated its contract with Thales, and sought other options to complete the line and bring it up to full service. According to testing completed in December 2018, the Thales signalling system could not keep trains on schedule, and caused trains to stop unexpectedly.[29] Alstom was selected to replace the Thales system.

In March 2021 the Alstom signalling system came online, fully replacing the Thales system. This allows the line to operate at full speed every 5 minutes when demand calls for it.[30] Alstom's system is a fixed-block system similar to the existing Capital Line, which will allow inter-operation between the shared track from Century Park to Churchill without compatibility issues arising.

Future edit

 
Approved LRT lines and stations

Edmonton extension edit

An extension from the permanent NAIT/Blatchford Market station is in the planning phases by the City of Edmonton.[31] The recommendation, released in May 2010,[32] extends the Metro Line through Blatchford (the sustainable community being developed on the grounds of the former City Centre Airport) over Yellowhead Trail and the CN Railway yard, along 113A Street and 153 Avenue to the City of St. Albert limits.[14] The extension would have eight stations, including stops in Blatchford, Rosslyn, Griesbach, Castle Downs, The Palisades, and at Campbell Road.[31] As part of this extension, a park and ride is proposed at Campbell Rd and 153 Ave. This type of line is planned to run with less separation from other traffic, mostly with lower track speeds, no higher than general purpose traffic, still with traffic signal priority and dedicated lanes. This extension is 11 km (6.8 mi) long, and will have 8 new stations and a rebuilt NAIT station slightly to the west of its current location. This section of the line is not planned to use gate arms, bells and flashing lights as has been done with the Metro Line from NAIT to Churchill.[33]

Expansion of the Metro Line will occur in three phases.[34] In June 2020, construction began on phase one: The extension of the Metro Line to Blatchford.[35] This extension consists of two stops: NAIT/Blatchford Market, which replaced the temporary NAIT station in use for 8 years, and Blatchford Gate.[35] According to the city of Edmonton, the second phase will move forward when funding becomes available.[34] NAIT/Blatchford Market station opened on January 20, 2024, replacing the temporary NAIT station, and Blatchford Gate station has an uncertain opening date.[36]

St. Albert extension edit

The City of St. Albert began studying extending Edmonton's LRT in early 2013, identifying four possible locations for stations.[37] On November 12, 2013, St. Albert council decided to continue studying LRT alignment options, but not to put any money into purchasing land or rail cars.[38] The selected corridor was approved by St. Albert city council on December 2, 2014, which will run on St. Albert Trail and proposed four possible station locations. The line is proposed to be primarily aligned to the east of St. Albert Trail, reducing it to four lanes north of Hebert Road. As well, there are three new bridges proposed along the St. Albert extension to span Anthony Henday Drive, Sir Winston Churchill Avenue, and the Sturgeon River.[39]

Stations edit

Station Grade-Level Transfer Area Opened Location
NAIT/Blatchford Market[a] Surface Northwest January 20, 2024 53°34′0″N 113°30′33″W / 53.56667°N 113.50917°W / 53.56667; -113.50917 (NAIT)
Kingsway/Royal Alex Surface Northwest September 6, 2015 53°33′28″N 113°30′4″W / 53.55778°N 113.50111°W / 53.55778; -113.50111 (Kingsway/Royal Alex)
MacEwan Surface Downtown September 6, 2015 53°32′52″N 113°29′57″W / 53.54778°N 113.49917°W / 53.54778; -113.49917 (MacEwan)
Churchill Underground   Capital Line
  Valley Line
Downtown April 22, 1978 53°32′39″N 113°29′21″W / 53.54417°N 113.48917°W / 53.54417; -113.48917 (Churchill)
Central Underground   Capital Line Downtown April 22, 1978 53°32′28″N 113°29′31″W / 53.54111°N 113.49194°W / 53.54111; -113.49194 (Central)
Bay/Enterprise Square Underground   Capital Line Downtown June 21, 1983 53°32′27″N 113°29′54″W / 53.54083°N 113.49833°W / 53.54083; -113.49833 (Bay/Enterprise Square)
Corona Underground   Capital Line Downtown June 21, 1983 53°32′27″N 113°30′21″W / 53.54083°N 113.50583°W / 53.54083; -113.50583 (Corona)
Government Centre Underground   Capital Line Downtown September 1989 53°32′10″N 113°30′37″W / 53.53611°N 113.51028°W / 53.53611; -113.51028 (Grandin)
University Underground   Capital Line South August 23, 1992 53°31′30″N 113°31′19″W / 53.52500°N 113.52194°W / 53.52500; -113.52194 (University)
Health Sciences/Jubilee Surface   Capital Line South January 3, 2006 53°31′13″N 113°31′33″W / 53.52028°N 113.52583°W / 53.52028; -113.52583 (Health Sciences/Jubilee)

Future stations edit

The City of Edmonton approved the concept plan for a northwest LRT line, and nine stations, on May 1, 2013.[40][41][42]

Station Area Location
Nakî Northwest 53°36′56″N 113°35′38″W / 53.61556°N 113.59389°W / 53.61556; -113.59389 (Naki)
137 Street Northwest 53°36′52″N 113°33′30″W / 53.61444°N 113.55833°W / 53.61444; -113.55833 (137 Street)
127 Street Northwest 53°37′1″N 113°32′23″W / 53.61694°N 113.53972°W / 53.61694; -113.53972 (127 Street)
Castle Downs Northwest 53°36′52″N 113°31′8″W / 53.61444°N 113.51889°W / 53.61444; -113.51889 (Castle Downs)
145 Avenue Northwest 53°36′28″N 113°31′0″W / 53.60778°N 113.51667°W / 53.60778; -113.51667 (145 Avenue)
137 Avenue Northwest 53°36′2″N 113°30′59″W / 53.60056°N 113.51639°W / 53.60056; -113.51639 (Griesbach)
132 Avenue Northwest 53°35′28″N 113°31′0″W / 53.59111°N 113.51667°W / 53.59111; -113.51667 (132 Avenue)
Blatchford Gate Northwest 53°34′33″N 113°30′37″W / 53.57583°N 113.51028°W / 53.57583; -113.51028 (Blatchford)

Proposed stations edit

The City of St. Albert identified four possible locations for stations in early 2013. In October 2015, the preferred location and alignment of the St. Albert extension was published in the Phase 2 report for the extension. Transit stations are proposed for the Downtown St. Albert, and the North St. Albert stations while park and ride services are only proposed for North St. Albert station.[39]

Former stations edit

Notes edit

  1. ^ A temporary station at NAIT was in use from 2015 to 2024.

References edit

  1. ^ "Northwest LRT - Campbell Station" (PDF). City of Edmonton. Retrieved December 12, 2014.
  2. ^ Ramsay, Caley (September 6, 2015). "After lengthy delay, Metro Line LRT opens to riders". Global Edmonton. Retrieved September 6, 2015.
  3. ^ . City of Edmonton. Archived from the original on March 26, 2015. Retrieved December 2, 2014.
  4. ^ Dubois, Stephanie (December 2, 2014). "St. Albert council approves alignment for LRT in city". Metronews.ca. from the original on May 18, 2015. Retrieved December 2, 2014.
  5. ^ a b . City of Edmonton. Archived from the original on September 4, 2013. Retrieved August 26, 2013.
  6. ^ . Edmonton Journal. Canada.com. April 3, 2008. Archived from the original on January 30, 2014. Retrieved August 26, 2013.
  7. ^ . Edmonton Journal. Canada.com. April 9, 2008. Archived from the original on October 5, 2008. Retrieved August 26, 2013.
  8. ^ Callsen, Laurie (November 16, 2012). "New Edmonton LRT tunneling for NAIT line completed". Metro News. Retrieved August 26, 2013.
  9. ^ Van Alstine, Brendan (May 25, 2009). "LRT expansion takes people by surprise". Metro News. Retrieved August 26, 2013.
  10. ^ Gould, Brian (February 8, 2010). "Council setting the right tone for LRT expansion". Metro News. Retrieved August 26, 2013.
  11. ^ a b c d Edmonton, City of (August 29, 2018). "Metro Line North Project History". www.edmonton.ca. Retrieved August 29, 2018.
  12. ^ a b "North LRT to NAIT (Metro Line)". City of Edmonton. Retrieved August 26, 2013.
  13. ^ (PDF). City of Edmonton. Archived from the original (PDF) on December 24, 2014. Retrieved December 24, 2014. Metro Line to open in early 2015
  14. ^ a b c Dykstra, Matt (May 9, 2013). "Edmonton city crews promise to finish north extension of LRT line to NAIT by next spring". Edmonton Sun. Retrieved August 26, 2013.
  15. ^ Lent, Gordon (April 10, 2014). "NAIT LRT savings to help Valley Line budget, report says". Edmonton Journal. Retrieved April 10, 2014.
  16. ^ Callsen, Laurie (October 25, 2012). "Five projects to watch go up in downtown Edmonton". Metro News. Retrieved August 26, 2013.
  17. ^ . City of Edmonton. Archived from the original on July 2, 2021.
  18. ^ Cook, Dustin (August 19, 2021). "Back on track: Five-minute train frequency to be fully restored on Edmonton's Capital Line LRT after seven-year signalling issue". Edmonton Journal. Postmedia. from the original on August 20, 2021. Retrieved February 26, 2024.
  19. ^ (PDF). City of Edmonton. October 8, 2014. Archived from the original (PDF) on October 13, 2014. Retrieved October 8, 2014.
  20. ^ a b Kent, Gordon (August 1, 2015). "City explores 'interim service' for problem-plagued Edmonton Metro LRT line". Edmonton Journal. Retrieved August 3, 2015.
  21. ^ "NAIT LRT opening delayed by two months for system testing". CTV News Edmonton. December 4, 2013. Retrieved December 4, 2013.
  22. ^ "NAIT LRT extension delayed by two months". CBC News. December 4, 2013. Retrieved December 4, 2013.
  23. ^ Tumilty, Ryan (December 4, 2013). "Edmonton's new NAIT LRT line won't open on time". Metro News. Retrieved December 16, 2014.
  24. ^ Tumilty, Ryan (March 20, 2014). "Edmonton's NAIT LRT line delayed". Metro News. Retrieved December 16, 2014.
  25. ^ Mertz, Emily (October 8, 2014). "Opening of Edmonton's Metro LRT Line delayed for third time". Global News. Retrieved December 16, 2014.
  26. ^ "Metro LRT gets green light to run full speed through intersections | CBC News".
  27. ^ Kevin Maimann (September 18, 2018). "Edmonton council reassured Metro Line LRT will keep running if contractor can't deliver". Toronto Star. Edmonton. Retrieved September 21, 2018. The Metro Line has seen a series of failures over the past four years, working through delays and a slower LRT schedule due to a semifunctional signalling system.
  28. ^ Kashmala Fida (September 13, 2018). "Rejoice! The Metro Line could be fully functional by December: city". Toronto Star. Edmonton. Retrieved September 21, 2018. However, the report does note that if the contract fails, the city has developed an alternate signalling system that will replace Thales's Communication Based Train Control (CBTC) system to make sure that Edmontonians don't lose any service on the Metro Line.
  29. ^ Snowdon, Wallis (April 9, 2019). "'End of the line': City terminates Thales' troubled Metro Line LRT contract". CBC News. Retrieved September 8, 2019.
  30. ^ "Edmonton's Metro Line LRT no longer running on Thales signalling system". Global News. Retrieved March 3, 2021.
  31. ^ a b . City of Edmonton. Archived from the original on September 3, 2013. Retrieved August 26, 2013.
  32. ^ Ho, Clara (May 19, 2010). "City announces planned LRT route to St. Albert". Edmonton Sun. Retrieved August 26, 2013.
  33. ^ (PDF). Archived from the original (PDF) on September 4, 2013. Retrieved September 13, 2013.
  34. ^ a b Edmonton, City of (September 22, 2020). "Metro Line - Northwest Extension". www.edmonton.ca. Retrieved September 22, 2020.
  35. ^ a b "Edmonton Metro Line Northwest construction begins". Railway PRO. June 9, 2020. Retrieved September 22, 2020.
  36. ^ Siemens, Nicole (January 16, 2024). "New NAIT LRT station ahead of schedule, opening of other Blatchford stop remains unclear". Global News. Corus Entertainment. Retrieved January 20, 2024.
  37. ^ (PDF). City of St. Albert. February 23, 2013. Archived from the original (PDF) on May 20, 2013. Retrieved August 26, 2013.
  38. ^ Paterson, Victoria (November 13, 2013). "Council rejects delay to LRT study". St. Albert Gazette. Retrieved November 17, 2013.
  39. ^ a b "St. Albert LRT Planning Study: Phase 2 - Alignment Selection Report" (PDF). AECOM and ISL Engineering and Land Services. October 2015. Retrieved December 28, 2016.
  40. ^ . City of Edmonton. Archived from the original on September 4, 2013. Retrieved September 13, 2013.
  41. ^ (PDF). City of Edmonton. May 1, 2013. Archived from the original (PDF) on September 4, 2013. Retrieved September 13, 2013.
  42. ^ (PDF). City of Edmonton. April 2013. Archived from the original (PDF) on September 4, 2013. Retrieved September 13, 2013.

External links edit

  • ETS Metro Line web page – The City of Edmonton
  • Metro Line (NAIT to North City Limits) Project page - City of Edmonton
  • North LRT - Churchill to NAIT on YouTube published by the City of Edmonton. Animated tour of the Metro Line from Churchill station to NAIT station.

metro, line, other, uses, metro, line, disambiguation, light, rail, transit, line, edmonton, system, line, operates, from, northwest, edmonton, south, edmonton, began, operation, september, 2015, line, consists, stations, three, which, exclusive, line, remaini. For other uses see Metro line disambiguation The Metro Line is a light rail transit line on the Edmonton LRT system The line operates from northwest Edmonton to south Edmonton and began operation on September 6 2015 The line consists of ten stations three of which are exclusive to the line and the remaining seven are shared with the Capital Line Metro LineSiemens Duewag U2 LRVs on Metro Line service at Kingsway Royal Alex stationOverviewLocaleEdmontonTerminiNAIT Blatchford MarketHealth Sciences JubileeStations10 originally 14 ServiceTypeLight railSystemEdmonton LRTOperator s Edmonton Transit ServiceDepot s D L MacDonald YardNorthwest LRT Yard proposed 1 HistoryOpenedSeptember 6 2015 2 TechnicalLine length8 km 5 0 mi Number of tracks2Track gauge1 435 mm 4 ft 8 1 2 in Operating speed70 kilometres per hour 43 mph Route mapLegend Blatchford Gate NAIT Blatchford Market Kingsway Royal Alex MacEwan Capital Lineto Clareview Churchill Valley Line to102 Street and Mill Woods Central Bay Enterprise Square Corona Government Centre Dudley B Menzies Bridge overNorth Saskatchewan River University Health Sciences Jubilee Capital Lineto Century Park All stations are accessible This diagram viewtalkedit Show diagram mapShow static map A one stop extension to Blatchford Gate station was completed in late 2023 but has yet to open An extension to the northwest city limits at the border with the city of St Albert has completed conceptual design 3 while St Albert has mapped a possible extension through that city along Highway 2 St Albert Trail 4 Contents 1 History 1 1 Signalling issues 2 Future 2 1 Edmonton extension 2 2 St Albert extension 3 Stations 3 1 Future stations 3 2 Proposed stations 3 3 Former stations 4 Notes 5 References 6 External linksHistory editThis section needs to be updated Please help update this article to reflect recent events or newly available information February 2024 In spring 2007 the funding for a concept plan and preliminary engineering was commissioned and the City approved the plan the next year 5 In 2008 during construction of the Epcor Tower the City ordered that the tunnel section below the tower be dug before the tower was completed this saved 140 million from digging after the tower was built 6 7 The remainder of the tunnel under Downtown Edmonton was constructed using the sequential excavation method and completed in November 2012 8 In 2009 the City approved the relocation of funds from the Gorman extension to the Metro Line as the City felt northwest was a higher priority 9 10 In 2010 the city began preparation work including utility relocations building removals roadwork Kingsway road reconstruction and track slab construction 5 11 The permanent closure of 105 Avenue between 102 Street and 105 Street was performed so MacEwan Station could be built 105 Street was permanently closed to vehicular traffic between 107 Avenue and 108 Avenue to allow the line to continue along the existing road corridor which alleviated the need to widen the corridor and remove some existing trees 104 Street was closed between 108 Avenue and Kingsway in a similar fashion 12 Construction was completed in 2014 in time to accommodate a spring 2014 opening 11 Bus service began for the first Metro Line facility the Kingsway Royal Alex Transit Centre on June 29 2014 11 The public plaza surrounding MacEwan Station except for the area required to build Rogers Place opened for use by people other than the construction crew in December 2014 13 On September 6 2015 the three stations and 3 3 kilometres 2 1 mi of track 14 opened to the public The cost of the project was 665 million jointly funded by the City of Edmonton Province of Alberta and the Government of Canada 14 15 It was the first new line that was not an extension of the existing line The line was expected to add 13 200 riders per weekday 16 On August 30 2021 late evenings and Sundays starting June 27 2021 17 service on the Metro Line was modified to end at Health Sciences Jubilee station as was originally planned but delayed due to signalling issues which caused trains to run a reduced frequency to the interim terminus at Century Park station to ensure the Capital Line could run at full frequency 18 Signalling issues edit Testing began in July 2013 12 and the line began operation in September 2015 with restrictions 19 11 20 21 22 There were three delays in beginning operations on the line one from April to June 2014 one from June to December 2014 and another from December 2014 to February 2015 The delays were caused by issues with the signalling system built by Thales 23 24 25 Thales gave control of the system to the City of Edmonton in March 2015 but failed to provide adequate documentation to place the line into service 20 In February 2017 trains were cleared to travel at 50 km h 26 The Thales signalling system used communications based train control CBTC where trains occupy a footprint measure and adjust their operation relative to the next train in front of them hence the term moving block as opposed to a traditional fixed block signal where each block is occupied by a train In September 2018 the Toronto Star reported that Edmonton had given Thales until April 30 2017 to bring the system to full functionality 27 Edmonton had withheld 22 million from Thales until the system was fully functional When Thales did not meet this deadline Edmonton gave Thales a notice of default On September 13 2018 Edmonton announced Thales had promised the signalling system would be fully functional by December 2018 28 Edmonton also announced there was a backup plan to keep the route functioning if Thales failed to deliver In April 2019 the City of Edmonton terminated its contract with Thales and sought other options to complete the line and bring it up to full service According to testing completed in December 2018 the Thales signalling system could not keep trains on schedule and caused trains to stop unexpectedly 29 Alstom was selected to replace the Thales system In March 2021 the Alstom signalling system came online fully replacing the Thales system This allows the line to operate at full speed every 5 minutes when demand calls for it 30 Alstom s system is a fixed block system similar to the existing Capital Line which will allow inter operation between the shared track from Century Park to Churchill without compatibility issues arising Future edit nbsp Approved LRT lines and stations Edmonton extension edit An extension from the permanent NAIT Blatchford Market station is in the planning phases by the City of Edmonton 31 The recommendation released in May 2010 32 extends the Metro Line through Blatchford the sustainable community being developed on the grounds of the former City Centre Airport over Yellowhead Trail and the CN Railway yard along 113A Street and 153 Avenue to the City of St Albert limits 14 The extension would have eight stations including stops in Blatchford Rosslyn Griesbach Castle Downs The Palisades and at Campbell Road 31 As part of this extension a park and ride is proposed at Campbell Rd and 153 Ave This type of line is planned to run with less separation from other traffic mostly with lower track speeds no higher than general purpose traffic still with traffic signal priority and dedicated lanes This extension is 11 km 6 8 mi long and will have 8 new stations and a rebuilt NAIT station slightly to the west of its current location This section of the line is not planned to use gate arms bells and flashing lights as has been done with the Metro Line from NAIT to Churchill 33 Expansion of the Metro Line will occur in three phases 34 In June 2020 construction began on phase one The extension of the Metro Line to Blatchford 35 This extension consists of two stops NAIT Blatchford Market which replaced the temporary NAIT station in use for 8 years and Blatchford Gate 35 According to the city of Edmonton the second phase will move forward when funding becomes available 34 NAIT Blatchford Market station opened on January 20 2024 replacing the temporary NAIT station and Blatchford Gate station has an uncertain opening date 36 St Albert extension edit The City of St Albert began studying extending Edmonton s LRT in early 2013 identifying four possible locations for stations 37 On November 12 2013 St Albert council decided to continue studying LRT alignment options but not to put any money into purchasing land or rail cars 38 The selected corridor was approved by St Albert city council on December 2 2014 which will run on St Albert Trail and proposed four possible station locations The line is proposed to be primarily aligned to the east of St Albert Trail reducing it to four lanes north of Hebert Road As well there are three new bridges proposed along the St Albert extension to span Anthony Henday Drive Sir Winston Churchill Avenue and the Sturgeon River 39 Stations editStation Grade Level Transfer Area Opened Location NAIT Blatchford Market a Surface Northwest January 20 2024 53 34 0 N 113 30 33 W 53 56667 N 113 50917 W 53 56667 113 50917 NAIT Kingsway Royal Alex Surface Northwest September 6 2015 53 33 28 N 113 30 4 W 53 55778 N 113 50111 W 53 55778 113 50111 Kingsway Royal Alex MacEwan Surface Downtown September 6 2015 53 32 52 N 113 29 57 W 53 54778 N 113 49917 W 53 54778 113 49917 MacEwan Churchill Underground nbsp Capital Line nbsp Valley Line Downtown April 22 1978 53 32 39 N 113 29 21 W 53 54417 N 113 48917 W 53 54417 113 48917 Churchill Central Underground nbsp Capital Line Downtown April 22 1978 53 32 28 N 113 29 31 W 53 54111 N 113 49194 W 53 54111 113 49194 Central Bay Enterprise Square Underground nbsp Capital Line Downtown June 21 1983 53 32 27 N 113 29 54 W 53 54083 N 113 49833 W 53 54083 113 49833 Bay Enterprise Square Corona Underground nbsp Capital Line Downtown June 21 1983 53 32 27 N 113 30 21 W 53 54083 N 113 50583 W 53 54083 113 50583 Corona Government Centre Underground nbsp Capital Line Downtown September 1989 53 32 10 N 113 30 37 W 53 53611 N 113 51028 W 53 53611 113 51028 Grandin University Underground nbsp Capital Line South August 23 1992 53 31 30 N 113 31 19 W 53 52500 N 113 52194 W 53 52500 113 52194 University Health Sciences Jubilee Surface nbsp Capital Line South January 3 2006 53 31 13 N 113 31 33 W 53 52028 N 113 52583 W 53 52028 113 52583 Health Sciences Jubilee Future stations edit The City of Edmonton approved the concept plan for a northwest LRT line and nine stations on May 1 2013 40 41 42 Station Area Location Naki Northwest 53 36 56 N 113 35 38 W 53 61556 N 113 59389 W 53 61556 113 59389 Naki 137 Street Northwest 53 36 52 N 113 33 30 W 53 61444 N 113 55833 W 53 61444 113 55833 137 Street 127 Street Northwest 53 37 1 N 113 32 23 W 53 61694 N 113 53972 W 53 61694 113 53972 127 Street Castle Downs Northwest 53 36 52 N 113 31 8 W 53 61444 N 113 51889 W 53 61444 113 51889 Castle Downs 145 Avenue Northwest 53 36 28 N 113 31 0 W 53 60778 N 113 51667 W 53 60778 113 51667 145 Avenue 137 Avenue Northwest 53 36 2 N 113 30 59 W 53 60056 N 113 51639 W 53 60056 113 51639 Griesbach 132 Avenue Northwest 53 35 28 N 113 31 0 W 53 59111 N 113 51667 W 53 59111 113 51667 132 Avenue Blatchford Gate Northwest 53 34 33 N 113 30 37 W 53 57583 N 113 51028 W 53 57583 113 51028 Blatchford Proposed stations edit The City of St Albert identified four possible locations for stations in early 2013 In October 2015 the preferred location and alignment of the St Albert extension was published in the Phase 2 report for the extension Transit stations are proposed for the Downtown St Albert and the North St Albert stations while park and ride services are only proposed for North St Albert station 39 Location Locale Approximate coordinates North St Albert St Albert 53 39 59 N 113 38 27 W 53 66639 N 113 64083 W 53 66639 113 64083 North St Albert Boudreau St Albert 53 39 17 N 113 37 45 W 53 65472 N 113 62917 W 53 65472 113 62917 Boudreau Downtown St Albert St Albert 53 38 12 6 N 113 37 24 9 W 53 636833 N 113 623583 W 53 636833 113 623583 Downtown St Albert Hebert St Albert 53 37 19 3 N 113 36 36 7 W 53 622028 N 113 610194 W 53 622028 113 610194 Herbert Road Former stations edit Station Grade Level Transfer Area Opened Location McKernan Belgravia Surface nbsp Capital Line South 53 30 47 N 113 31 34 W 53 51306 N 113 52611 W 53 51306 113 52611 McKernan Belgravia South Campus Fort Edmonton Park Surface nbsp Capital Line South 53 30 10 N 113 31 43 W 53 50278 N 113 52861 W 53 50278 113 52861 South Campus Southgate Surface nbsp Capital Line South 53 29 8 N 113 31 0 W 53 48556 N 113 51667 W 53 48556 113 51667 Southgate Century Park Surface nbsp Capital Line South 53 27 27 N 113 30 59 W 53 45750 N 113 51639 W 53 45750 113 51639 Century Park Map all coordinates using OpenStreetMap Download coordinates as KML GPX all coordinates GPX primary coordinates GPX secondary coordinates Notes edit A temporary station at NAIT was in use from 2015 to 2024 References edit Northwest LRT Campbell Station PDF City of Edmonton Retrieved December 12 2014 Ramsay Caley September 6 2015 After lengthy delay Metro Line LRT opens to riders Global Edmonton Retrieved September 6 2015 Metro Line NAIT to North City Limits City of Edmonton Archived from the original on March 26 2015 Retrieved December 2 2014 Dubois Stephanie December 2 2014 St Albert council approves alignment for LRT in city Metronews ca Archived from the original on May 18 2015 Retrieved December 2 2014 a b North LRT Metro Line Project History City of Edmonton Archived from the original on September 4 2013 Retrieved August 26 2013 Work on LRT s third leg to start in June Edmonton Journal Canada com April 3 2008 Archived from the original on January 30 2014 Retrieved August 26 2013 LRT line likely to go under Epcor Edmonton Journal Canada com April 9 2008 Archived from the original on October 5 2008 Retrieved August 26 2013 Callsen Laurie November 16 2012 New Edmonton LRT tunneling for NAIT line completed Metro News Retrieved August 26 2013 Van Alstine Brendan May 25 2009 LRT expansion takes people by surprise Metro News Retrieved August 26 2013 Gould Brian February 8 2010 Council setting the right tone for LRT expansion Metro News Retrieved August 26 2013 a b c d Edmonton City of August 29 2018 Metro Line North Project History www edmonton ca Retrieved August 29 2018 a b North LRT to NAIT Metro Line City of Edmonton Retrieved August 26 2013 METRO LINE UPDATE PDF City of Edmonton Archived from the original PDF on December 24 2014 Retrieved December 24 2014 Metro Line to open in early 2015 a b c Dykstra Matt May 9 2013 Edmonton city crews promise to finish north extension of LRT line to NAIT by next spring Edmonton Sun Retrieved August 26 2013 Lent Gordon April 10 2014 NAIT LRT savings to help Valley Line budget report says Edmonton Journal Retrieved April 10 2014 Callsen Laurie October 25 2012 Five projects to watch go up in downtown Edmonton Metro News Retrieved August 26 2013 TLC for LRT June 27 late August 15 minute Capital Metro Line service City of Edmonton Archived from the original on July 2 2021 Cook Dustin August 19 2021 Back on track Five minute train frequency to be fully restored on Edmonton s Capital Line LRT after seven year signalling issue Edmonton Journal Postmedia Archived from the original on August 20 2021 Retrieved February 26 2024 Metro Line Delay FAQ PDF City of Edmonton October 8 2014 Archived from the original PDF on October 13 2014 Retrieved October 8 2014 a b Kent Gordon August 1 2015 City explores interim service for problem plagued Edmonton Metro LRT line Edmonton Journal Retrieved August 3 2015 NAIT LRT opening delayed by two months for system testing CTV News Edmonton December 4 2013 Retrieved December 4 2013 NAIT LRT extension delayed by two months CBC News December 4 2013 Retrieved December 4 2013 Tumilty Ryan December 4 2013 Edmonton s new NAIT LRT line won t open on time Metro News Retrieved December 16 2014 Tumilty Ryan March 20 2014 Edmonton s NAIT LRT line delayed Metro News Retrieved December 16 2014 Mertz Emily October 8 2014 Opening of Edmonton s Metro LRT Line delayed for third time Global News Retrieved December 16 2014 Metro LRT gets green light to run full speed through intersections CBC News Kevin Maimann September 18 2018 Edmonton council reassured Metro Line LRT will keep running if contractor can t deliver Toronto Star Edmonton Retrieved September 21 2018 The Metro Line has seen a series of failures over the past four years working through delays and a slower LRT schedule due to a semifunctional signalling system Kashmala Fida September 13 2018 Rejoice The Metro Line could be fully functional by December city Toronto Star Edmonton Retrieved September 21 2018 However the report does note that if the contract fails the city has developed an alternate signalling system that will replace Thales s Communication Based Train Control CBTC system to make sure that Edmontonians don t lose any service on the Metro Line Snowdon Wallis April 9 2019 End of the line City terminates Thales troubled Metro Line LRT contract CBC News Retrieved September 8 2019 Edmonton s Metro Line LRT no longer running on Thales signalling system Global News Retrieved March 3 2021 a b Northwest LRT to City Limits City of Edmonton Archived from the original on September 3 2013 Retrieved August 26 2013 Ho Clara May 19 2010 City announces planned LRT route to St Albert Edmonton Sun Retrieved August 26 2013 Northwest LRT Recommended Concept Plan PDF Archived from the original PDF on September 4 2013 Retrieved September 13 2013 a b Edmonton City of September 22 2020 Metro Line Northwest Extension www edmonton ca Retrieved September 22 2020 a b Edmonton Metro Line Northwest construction begins Railway PRO June 9 2020 Retrieved September 22 2020 Siemens Nicole January 16 2024 New NAIT LRT station ahead of schedule opening of other Blatchford stop remains unclear Global News Corus Entertainment Retrieved January 20 2024 St Albert LRT PDF City of St Albert February 23 2013 Archived from the original PDF on May 20 2013 Retrieved August 26 2013 Paterson Victoria November 13 2013 Council rejects delay to LRT study St Albert Gazette Retrieved November 17 2013 a b St Albert LRT Planning Study Phase 2 Alignment Selection Report PDF AECOM and ISL Engineering and Land Services October 2015 Retrieved December 28 2016 Northwest LRT Project History City of Edmonton Archived from the original on September 4 2013 Retrieved September 13 2013 Concept Planning Study Northwest LRT PDF City of Edmonton May 1 2013 Archived from the original PDF on September 4 2013 Retrieved September 13 2013 Northwest LRT Recommended Concept Plan PDF City of Edmonton April 2013 Archived from the original PDF on September 4 2013 Retrieved September 13 2013 External links edit nbsp Wikimedia Commons has media related to Edmonton Metro Line LRT ETS Metro Line web page The City of Edmonton Metro Line NAIT to North City Limits Project page City of Edmonton North LRT Churchill to NAIT on YouTube published by the City of Edmonton Animated tour of the Metro Line from Churchill station to NAIT station Retrieved from https en wikipedia org w index php title Metro Line amp oldid 1221377253, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.