fbpx
Wikipedia

Kölnbrein Dam

The Kölnbrein Dam is an arch dam in the Hohe Tauern range within Carinthia, Austria. It was constructed between 1971 and 1979 and at 200 metres (660 ft) high, it is the tallest dam in Austria.[1] The dam's reservoir serves as the primary storage in a three-stage pumped-storage power system that consists of nine dams, four hydroelectric power plants and a series of pipeline and penstocks. The complex is owned by Verbund power company and is referred to as the Malta-Reisseck Power Plant Group. The installed capacity of the group is 1,028.5 MW and its annual generation is 1,216 gigawatt-hours (4,380 TJ).

Kölnbrein Dam
Location of Kölnbrein Dam in Austria
Official nameKölnbreinsperre
LocationMalta, Carinthia,
Austria
Coordinates47°04′45″N 13°20′21″E / 47.07917°N 13.33917°E / 47.07917; 13.33917Coordinates: 47°04′45″N 13°20′21″E / 47.07917°N 13.33917°E / 47.07917; 13.33917
StatusIn use
Construction began1971
Opening date1977
Dam and spillways
Type of damConcrete arch
ImpoundsMalta River
Height200 m (660 ft)
Length626 m (2,054 ft)
Width (crest)7.6 m (25 ft)
Width (base)41 m (135 ft)
Dam volume1,580,000 m3 (2,070,000 cu yd)
Reservoir
Total capacity205,000,000 m3 (166,000 acre⋅ft)
Catchment area129 km2 (50 sq mi)
Surface area2.55 km2 (0.98 sq mi)
Power Station
Operator(s)Verbund AG
Commission date1948-1979
Installed capacityUpper stage: 120 MW (160,000 hp)
Main stage: 730 MW (980,000 hp)
Lower stage: 41 MW (55,000 hp)
Reisseck plants: 137.5 MW (184,400 hp)
Total: 1,028.5 MW (1,379,200 hp)
Annual generation1,216 GWh (4,380 TJ)

While the dam's reservoir was filling, several cracks appeared in the dam and it took more than a decade of repairs before the reservoir could operate at maximum levels.[2][3][4] Currently, the Reisseck II pumped-storage power plant is under construction and will effectively connect both the Malta and Reisseck groups and add an additional 430 MW of production capacity.

Construction

 
Concrete pouring in 1975

Plans for the dam were already drafted in the late 1930s by the German AEG engineering company, when the Kaprun power plant was built north of the Alpine divide. The project was resumed by the Austrian authorities after World War II with extended exploratory drilling from 1957 onwards, nevertheless the construction of the Kölnbrein Dam did not begin until 1971.

Before cement and other construction materials could be moved on site, an access road had to be constructed. This proved difficult as the steep Malta Valley rises over 300 metres (980 ft) along a 14 kilometres (8.7 mi) stretch and at times has 13 percent gradients. To complete the road, six tunnels were excavated. In 1973, as superstructure construction progressed, cement was transported on site and mixed with aggregate from local sources. To reduce thermal expansion, concrete was poured 30 cubic metres (39 cu yd) at a time and pipes with circulating water were placed throughout the mass. The structure consisted of 30 columns with each joint grouted. Construction conditions high in the valley were not ideal as workers coped with snow and rain along with wind speeds of 80 kilometres per hour (50 mph; 43 kn).[1]

Completion and cracks

By 1977, construction on the dam had reached an advanced stage where it could begin to impound its reservoir. While filling with water, cracks began to appear in the dam on its upstream heel when the reservoir level was 42 metres (138 ft) below its maximum operating level of 1,902 metres (6,240 ft) above sea level. Uplift pressure on the dam had unexpectedly increased as well and engineers worried that the structure's grout curtain had been damaged. Because the dam is in a "U"-shaped valley instead of the usual "V"-shaped for arch dams, hydrostatic pressure is exceptionally strong on the center-bottom (heel) upstream portion of the dam. As excessive water leaked into lower areas of the dam, the water level was drawn down and engineers increased drainage.

 
Dam in 2007, with "thrust block" at base

In 1979, the grout curtain was strengthened and another full impoundment was unsuccessfully attempted. Between 1980 and 1981, a polyurethane resin grout was used to re-grout joints and they were frozen during the next impoundment attempt, allowing them to thaw naturally. As remedial works progressed, cracks near the abutments (flanks) of the dam formed as well; on the downstream side and in a horizontal direction.[5] A plastic sheet-covered concrete blanket was laid on the upstream valley floor behind the dam between 1981 and 1983. In the next few years, the sheets had to be repaired and the grout curtain re-grouted. In 1984, the reservoir was able to reach 90 percent full. In 1979 and 1983, it had temporarily reached its maximum level as well but it could not be safely sustained. In 1984, the reservoir levels were limited to 15–20 m (49–66 ft) below maximum, and at those levels it was able to operate safely though at reduced capacities.

Notwithstanding these remedial actions, a long-term solution was required. This came in the form of a 70 m (230 ft) tall "thrust block" that had to be constructed at the downstream base of the dam in order to absorb load from the dam and pressure on its abutments. Its construction was approved in 1988 and executed between 1989 and 1992. Joining the dam and the block are over 600 special neoprene pads which adjust to forces from the reservoir rising and lowering. In addition, joints and fissures in the dam were re-grouted again but with a water-tight resin epoxy.[5][6][7] The reservoir was able to operate at maximum levels and operate as normal in 1993.[8]

Design and operation

 
Kölnbrein Dam and Galgenbichl reservoir

The water in the reservoir is used to generate electricity. It is drawn down as electric load demands. Because the catchment area around the dam can only supply half the needed water to sustain its reservoir levels, a series pumps and pumped-storage power plants are utilized to supplement storage capacity. These pumps operate during periods of low power demand, filling the reservoir. When demand is high, water is released back into the system to produce hydroelectricity.[1]

Immediately downstream from the Kölnbrein Dam is the Galgenbichl dam and reservoir. This reservoir serves to receive water from several different locations in Malta via pipeline and is the lower reservoir for the Upper stage pumped-storage power station. From the northeast, water is pumped in from several smaller reservoirs and tributaries.

Reisseck-Kreuzeck power plants

The water collected above in the Reisseck mountains runs downhill towards the valley of the Möll River. Water is principally received from sources and Kreuzeck mountains to the south though. Of the power plant group, the Reisseck-Kreuzeck plants were constructed between 1948 and 1961 and the Malta group from 1971 to 1979.[9]

On the south side of the Möll River, water is used to generate power at the Niklai power station near Sachsenburg. From there, the water is then received at the Rosswiese reservoir and utilized to generate power at the Kolbnitz station down in the Möll Valley. At Kolbnitz, water can be released into the river which flows into a reservoir created by the Rottau Dam. This reservoir also serves as the lower reservoir for pumping by the Rottau (Main stage) power plant which is located downstream of Kolbnitz.

Water can also be received and pumped from sources to the north which primarily includes the Grosser Mühldorfer reservoir (Reisseck annual reservoir). The Grosser Mühldorfer also receives water from the Kleiner Mühldorfer, Hochalmsee and Radlsee reservoirs as well. From the Grosser Mühldorfer, water can be released back down to Kolbnitz for power production. Additional water from the Reisseck daily reservoir, about halfway between Grosser and Kolbnitz, can be used as well. This completes the Reisseck scheme of plants which all together have an installed capacity of 138 MW.[10]

In the Malta group, water from the Rottau reservoir down in the Möll River Valley is pumped via the Main stage (Rottau) to the Galgenbichl reservoir below the Kölnbrein. Along the tunneled route, the Gösskar reservoir, and various tributaries provide additional water via pipeline as well. Water storage in the Galgenbichl reservoir is eventually pumped via the Upper storage pumped-storage station into the Kölnbrein reservoir. When generating electricity, water from the upper Kölnbrein reservoir is released about 200 m (656 ft) back down to the Upper stage power plant. The upper stage consists of two reversible Francis turbine generators with a total installed capacity of 120 MW. Water can then be released back through 20.4 km (13 mi) of pipeline south towards the Möll River Valley. Ultimately, it will drop from 1,704 m (5,591 ft) above sea level to 598 m (1,962 ft) through two 1.9 km (1 mi) penstocks where the Main stage (Rottau) power plant is located.

The Main stage is operated by four Pelton turbines with an installed capacity of 730 MW. Water released from this plant enters Rottau reservoir on the Möll. Prior its confluence with the Drava (Drau) River, water is diverted through a 2.5 km (2 mi) canal on the right bank of the river which converts into a 1.75 km (1 mi) long tunnel which feeds the Lower stage (Möllbrücke) power station. It is powered by two Kaplan turbine generators with an installed capacity of 120 MW. From the Lower stage, water is discharged into the Drau upstream from the mouth of the Möll.[10] The turbines are up to 92% efficient.[11]

Expansion: Reisseck II

Verbund began constructing the Reisseck II pumped-storage station in 2010, and started testing in 2016.[21] It uses the Grosser Mühldorfer reservoir as an upper reservoir and the Gösskar reservoir as its lower.[22] A 5.3 km (3 mi) ø7m headrace tunnel from the Grosser Mühldorfer was excavated and connects to the existing headrace tunnel of the Rottau main stage. Feeding water into the Reisseck II power station is a 820 km (510 mi) long penstock. The power station is located 200 m (656 ft) underground and contains two 215 MW reversible-Francis turbines. It has a total installed capacity of 430 MW[23] and increases the overall capacity of the power plant group by 40%; from 1,026 to 1,459 MW. Cost was €400 million.[9][24][25]

Tourism

 
Skywalk

The Kölnbrein Dam is the terminus of a 14.3 kilometres (8.9 mi) long scenic route through the Maltatal, the former construction site road, including a restaurant, a hotel and an exhibition on hydroelectricity. Verbund also offers tours of the power plant group and the dam.[4] Tours on the dam are conducted daily while the road is open between 9 May and 26 October each year.[26][27]

In 2010 a "skywalk", a horseshoe-shaped cantilever bridge, was installed on top of the dam for visitors which is also a popular bungee jumping venue. The dam lies within the High Tauern National Park and is a destination for mountaineers as well. Moreover, the reservoir is used by rowers for altitude training.

In popular culture

  • The dam features in the 1978 film The Boys From Brazil, standing in for a location in Sweden. The movie was shot between late 1977 and early 1978 and shows the newly erected dam with a low reservoir level. In the film the character of the inspector of the local power company (and former SS Major) is thrown off the top of the snow-covered dam by an assassin sent by a fictional Josef Mengele. Various shots around and on top of the dam are shown in the 3 minute 15 second scene at approximately 55 minutes into the film.

References

  1. ^ a b c Langdon, John (August 2008). . John Milton Langdon. Archived from the original on 24 March 2012. Retrieved 4 June 2011.
  2. ^ . Verbund. Archived from the original on 29 April 2011. Retrieved 29 May 2011.
  3. ^ "Kolnbrein". Austrian National Committee on Large Dams. Retrieved 29 May 2011.
  4. ^ a b . Verbund. Archived from the original on 19 April 2011. Retrieved 1 June 2011.
  5. ^ a b Lombardi, G. (June 1991). "Kolnbrein dam: an unusual solution for an unusual problem". Water Power & Dam Construction. Retrieved 4 June 2011.
  6. ^ "Kolnbrein Background". SimScience. from the original on March 21, 2012. Retrieved 21 September 2018.
  7. ^ Smoltczyk, ed.: Ulrich (2003). Procedures. Berlin [u.a.]: Ernst. p. 85. ISBN 3-433-01450-7. {{cite book}}: |first= has generic name (help)
  8. ^ "Kolnbrein Current Status". SimScience. Retrieved 21 September 2018.
  9. ^ a b "Thyssen Schachtbau wins contract for an 820 m raise-bore shaft for the pumped storage power station in Kärnten" (PDF). Thyssen Schachtbau. Retrieved 4 June 2011.
  10. ^ a b c "Composite storage power plants in the AHP in Carinthia (Map)". Verbund (on Wikimedia Commons). Retrieved 1 June 2011.
  11. ^ Richard Hammond (7 November 2020). How the Turbines in the Kölnbrein Dam are 92% Efficient. Discovery Channel.
  12. ^ (PDF). Verbund. Archived from the original (PDF) on 24 March 2012. Retrieved 1 June 2011.
  13. ^ . Verbund. Archived from the original on 6 August 2011. Retrieved 1 June 2011On the interactive map, the power plants have the following numbers: Malta upper (60), Malta main (59), Malta lower (61), Reisseck annual (85), Reisseck daily (86), Kreuzeck/Reisseck (51), Niklai (69){{cite web}}: CS1 maint: postscript (link)
  14. ^ "Koelnbrein". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  15. ^ "Galgenbichl". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  16. ^ "Radlsee". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  17. ^ "Hochalmsee". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  18. ^ "Kleiner Mühldorfer". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  19. ^ "Grosser Mühldorfer". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  20. ^ "Rosswiese". Austrian National Committee on Large Dams. Retrieved 1 June 2011.
  21. ^ "Reisseck II pumped storage power station in test o..." Structurae.
  22. ^ "The interaction of wind, solar and hydropower | Voith". voith.com. Diagram
  23. ^ "The 240 MVA motor generators for the Reisseck II pumped-storage plant | Hydropower & Dams International". www.hydropower-dams.com.
  24. ^ "Verbund power plant Reisseck II will not start" (in German). Wirtschaftsblatt Medien. 15 July 2015. Retrieved 21 July 2015.
  25. ^ "VERBUND-Pumped Storage Power Plant Reisseck II". www.verbund.com. from the original on 28 January 2020.
  26. ^ "Malta High Alpine Road". Nationalpark-Region Hohe Tauern. Retrieved 4 June 2011.
  27. ^ "Malta. At the gateway to the Hohe Tauern National Park". Kärnten Information. Retrieved 4 June 2011.

External links

Map all coordinates using: OpenStreetMap 
Download coordinates as: KML

kölnbrein, arch, hohe, tauern, range, within, carinthia, austria, constructed, between, 1971, 1979, metres, high, tallest, austria, reservoir, serves, primary, storage, three, stage, pumped, storage, power, system, that, consists, nine, dams, four, hydroelectr. The Kolnbrein Dam is an arch dam in the Hohe Tauern range within Carinthia Austria It was constructed between 1971 and 1979 and at 200 metres 660 ft high it is the tallest dam in Austria 1 The dam s reservoir serves as the primary storage in a three stage pumped storage power system that consists of nine dams four hydroelectric power plants and a series of pipeline and penstocks The complex is owned by Verbund power company and is referred to as the Malta Reisseck Power Plant Group The installed capacity of the group is 1 028 5 MW and its annual generation is 1 216 gigawatt hours 4 380 TJ Kolnbrein DamLocation of Kolnbrein Dam in AustriaOfficial nameKolnbreinsperreLocationMalta Carinthia AustriaCoordinates47 04 45 N 13 20 21 E 47 07917 N 13 33917 E 47 07917 13 33917 Coordinates 47 04 45 N 13 20 21 E 47 07917 N 13 33917 E 47 07917 13 33917StatusIn useConstruction began1971Opening date1977Dam and spillwaysType of damConcrete archImpoundsMalta RiverHeight200 m 660 ft Length626 m 2 054 ft Width crest 7 6 m 25 ft Width base 41 m 135 ft Dam volume1 580 000 m3 2 070 000 cu yd ReservoirTotal capacity205 000 000 m3 166 000 acre ft Catchment area129 km2 50 sq mi Surface area2 55 km2 0 98 sq mi Power StationOperator s Verbund AGCommission date1948 1979Installed capacityUpper stage 120 MW 160 000 hp Main stage 730 MW 980 000 hp Lower stage 41 MW 55 000 hp Reisseck plants 137 5 MW 184 400 hp Total 1 028 5 MW 1 379 200 hp Annual generation1 216 GWh 4 380 TJ While the dam s reservoir was filling several cracks appeared in the dam and it took more than a decade of repairs before the reservoir could operate at maximum levels 2 3 4 Currently the Reisseck II pumped storage power plant is under construction and will effectively connect both the Malta and Reisseck groups and add an additional 430 MW of production capacity Contents 1 Construction 1 1 Completion and cracks 2 Design and operation 2 1 Reisseck Kreuzeck power plants 2 2 Expansion Reisseck II 3 Tourism 4 In popular culture 5 References 6 External linksConstruction Edit Concrete pouring in 1975 Plans for the dam were already drafted in the late 1930s by the German AEG engineering company when the Kaprun power plant was built north of the Alpine divide The project was resumed by the Austrian authorities after World War II with extended exploratory drilling from 1957 onwards nevertheless the construction of the Kolnbrein Dam did not begin until 1971 Before cement and other construction materials could be moved on site an access road had to be constructed This proved difficult as the steep Malta Valley rises over 300 metres 980 ft along a 14 kilometres 8 7 mi stretch and at times has 13 percent gradients To complete the road six tunnels were excavated In 1973 as superstructure construction progressed cement was transported on site and mixed with aggregate from local sources To reduce thermal expansion concrete was poured 30 cubic metres 39 cu yd at a time and pipes with circulating water were placed throughout the mass The structure consisted of 30 columns with each joint grouted Construction conditions high in the valley were not ideal as workers coped with snow and rain along with wind speeds of 80 kilometres per hour 50 mph 43 kn 1 Completion and cracks Edit By 1977 construction on the dam had reached an advanced stage where it could begin to impound its reservoir While filling with water cracks began to appear in the dam on its upstream heel when the reservoir level was 42 metres 138 ft below its maximum operating level of 1 902 metres 6 240 ft above sea level Uplift pressure on the dam had unexpectedly increased as well and engineers worried that the structure s grout curtain had been damaged Because the dam is in a U shaped valley instead of the usual V shaped for arch dams hydrostatic pressure is exceptionally strong on the center bottom heel upstream portion of the dam As excessive water leaked into lower areas of the dam the water level was drawn down and engineers increased drainage Dam in 2007 with thrust block at base In 1979 the grout curtain was strengthened and another full impoundment was unsuccessfully attempted Between 1980 and 1981 a polyurethane resin grout was used to re grout joints and they were frozen during the next impoundment attempt allowing them to thaw naturally As remedial works progressed cracks near the abutments flanks of the dam formed as well on the downstream side and in a horizontal direction 5 A plastic sheet covered concrete blanket was laid on the upstream valley floor behind the dam between 1981 and 1983 In the next few years the sheets had to be repaired and the grout curtain re grouted In 1984 the reservoir was able to reach 90 percent full In 1979 and 1983 it had temporarily reached its maximum level as well but it could not be safely sustained In 1984 the reservoir levels were limited to 15 20 m 49 66 ft below maximum and at those levels it was able to operate safely though at reduced capacities Notwithstanding these remedial actions a long term solution was required This came in the form of a 70 m 230 ft tall thrust block that had to be constructed at the downstream base of the dam in order to absorb load from the dam and pressure on its abutments Its construction was approved in 1988 and executed between 1989 and 1992 Joining the dam and the block are over 600 special neoprene pads which adjust to forces from the reservoir rising and lowering In addition joints and fissures in the dam were re grouted again but with a water tight resin epoxy 5 6 7 The reservoir was able to operate at maximum levels and operate as normal in 1993 8 Design and operation Edit Kolnbrein Dam and Galgenbichl reservoir The water in the reservoir is used to generate electricity It is drawn down as electric load demands Because the catchment area around the dam can only supply half the needed water to sustain its reservoir levels a series pumps and pumped storage power plants are utilized to supplement storage capacity These pumps operate during periods of low power demand filling the reservoir When demand is high water is released back into the system to produce hydroelectricity 1 Immediately downstream from the Kolnbrein Dam is the Galgenbichl dam and reservoir This reservoir serves to receive water from several different locations in Malta via pipeline and is the lower reservoir for the Upper stage pumped storage power station From the northeast water is pumped in from several smaller reservoirs and tributaries Reisseck Kreuzeck power plants Edit The water collected above in the Reisseck mountains runs downhill towards the valley of the Moll River Water is principally received from sources and Kreuzeck mountains to the south though Of the power plant group the Reisseck Kreuzeck plants were constructed between 1948 and 1961 and the Malta group from 1971 to 1979 9 On the south side of the Moll River water is used to generate power at the Niklai power station near Sachsenburg From there the water is then received at the Rosswiese reservoir and utilized to generate power at the Kolbnitz station down in the Moll Valley At Kolbnitz water can be released into the river which flows into a reservoir created by the Rottau Dam This reservoir also serves as the lower reservoir for pumping by the Rottau Main stage power plant which is located downstream of Kolbnitz Water can also be received and pumped from sources to the north which primarily includes the Grosser Muhldorfer reservoir Reisseck annual reservoir The Grosser Muhldorfer also receives water from the Kleiner Muhldorfer Hochalmsee and Radlsee reservoirs as well From the Grosser Muhldorfer water can be released back down to Kolbnitz for power production Additional water from the Reisseck daily reservoir about halfway between Grosser and Kolbnitz can be used as well This completes the Reisseck scheme of plants which all together have an installed capacity of 138 MW 10 In the Malta group water from the Rottau reservoir down in the Moll River Valley is pumped via the Main stage Rottau to the Galgenbichl reservoir below the Kolnbrein Along the tunneled route the Gosskar reservoir and various tributaries provide additional water via pipeline as well Water storage in the Galgenbichl reservoir is eventually pumped via the Upper storage pumped storage station into the Kolnbrein reservoir When generating electricity water from the upper Kolnbrein reservoir is released about 200 m 656 ft back down to the Upper stage power plant The upper stage consists of two reversible Francis turbine generators with a total installed capacity of 120 MW Water can then be released back through 20 4 km 13 mi of pipeline south towards the Moll River Valley Ultimately it will drop from 1 704 m 5 591 ft above sea level to 598 m 1 962 ft through two 1 9 km 1 mi penstocks where the Main stage Rottau power plant is located The Main stage is operated by four Pelton turbines with an installed capacity of 730 MW Water released from this plant enters Rottau reservoir on the Moll Prior its confluence with the Drava Drau River water is diverted through a 2 5 km 2 mi canal on the right bank of the river which converts into a 1 75 km 1 mi long tunnel which feeds the Lower stage Mollbrucke power station It is powered by two Kaplan turbine generators with an installed capacity of 120 MW From the Lower stage water is discharged into the Drau upstream from the mouth of the Moll 10 The turbines are up to 92 efficient 11 Malta Reisseck Power Plant Group 10 12 13 Name Type Capacity MW Annual generation GWh Commission CoordinatesMalta upper stage Galgenbichl Pumped storage 120 76 1979 47 04 08 N 13 21 16 E 47 06889 N 13 35444 E 47 06889 13 35444 Malta upper stage Malta main stage Rottau Pumped storage 730 715 1979 46 52 14 N 13 19 46 E 46 87056 N 13 32944 E 46 87056 13 32944 Malta main stage Malta lower stage Mollbrucke Run of the river 41 120 1979 46 49 59 N 13 21 36 E 46 83306 N 13 36000 E 46 83306 13 36000 Malta lower stage Reisseck annual reservoir Kolbnitz Pumped storage 67 7 73 1962 46 54 55 N 13 22 28 E 46 91528 N 13 37444 E 46 91528 13 37444 Reisseck annual reservoir Reisseck daily reservoir Kolbnitz Storage 23 2 62 1953 46 52 52 N 13 20 13 E 46 88111 N 13 33694 E 46 88111 13 33694 Reisseck daily reservoir Reisseck Kreuzeck reservoir Kolbnitz Storage 45 163 1963 46 51 37 N 13 18 18 E 46 86028 N 13 30500 E 46 86028 13 30500 Reisseck Kreuzeck reservoir Niklai Inter system 1 6 7 1960 46 49 29 N 13 17 39 E 46 82472 N 13 29417 E 46 82472 13 29417 Niklai inter power plant Total 1 028 5 1 216Dams of the Malta Reisseck Power Plant GroupName Type Height Length Storage capacity Elevation Catchment area Year built CoordinatesKolnbrein Arch 200 m 656 ft 626 m 2 054 ft 205 000 000 m3 166 196 acre ft 1 902 m 6 240 ft 129 km2 50 sq mi 1977 47 04 45 N 13 20 21 E 47 07917 N 13 33917 E 47 07917 13 33917 Kolnbrein Dam 14 Galgenbichl Gravity rock fill 50 m 164 ft 200 m 656 ft 4 800 000 m3 3 891 acre ft 1 704 m 5 591 ft 53 km2 20 sq mi 1974 47 03 59 N 13 21 05 E 47 06639 N 13 35139 E 47 06639 13 35139 Galgenbichl Dam 15 Gosskar Embankment 55 m 180 ft 260 m 853 ft 520 000 m3 422 acre ft 1 704 m 5 591 ft 1979 46 58 56 N 13 19 52 E 46 98222 N 13 33111 E 46 98222 13 33111 Gosskar Dam Radlsee Rock fill 12 m 39 ft 212 m 696 ft 2 600 000 m3 2 108 acre ft 2 399 m 7 871 ft 2 km2 1 sq mi 1958 46 56 26 N 13 22 33 E 46 94056 N 13 37583 E 46 94056 13 37583 Radlsee Dam 16 Hochalmsee Gravity rock fill 34 m 112 ft 357 m 1 171 ft 4 100 000 m3 3 324 acre ft 2 379 m 7 805 ft 160 km2 62 sq mi 1958 46 56 53 N 13 20 17 E 46 94806 N 13 33806 E 46 94806 13 33806 Hochalmsee Dam 17 Kleiner Muhldorfer Gravity 41 m 135 ft 159 m 522 ft 2 800 000 m3 2 270 acre ft 2 379 m 7 805 ft 160 km2 62 sq mi 1958 46 55 18 N 13 22 12 E 46 92167 N 13 37000 E 46 92167 13 37000 Kleiner Muhldorfer Dam 18 Grosser Muhldorfer Gravity 46 m 151 ft 433 m 1 421 ft 7 700 000 m3 6 242 acre ft 2 319 m 7 608 ft 158 km2 61 sq mi 1957 46 54 55 N 13 22 29 E 46 91528 N 13 37472 E 46 91528 13 37472 Grosser Muhldorfer Dam 19 Rottau Gravity 13 7 m 45 ft 68 m 223 ft 500 000 m3 405 acre ft 598 m 1 962 ft 1979 46 51 49 N 13 20 06 E 46 86361 N 13 33500 E 46 86361 13 33500 Rottau Dam Rosswiese Embankment 16 m 52 ft 320 m 1 050 ft 204 000 m3 165 acre ft 1 194 m 3 917 ft 115 km2 44 sq mi 1958 46 51 59 N 13 20 06 E 46 86639 N 13 33500 E 46 86639 13 33500 Rosswiese Dam 20 Expansion Reisseck II Edit Verbund began constructing the Reisseck II pumped storage station in 2010 and started testing in 2016 21 It uses the Grosser Muhldorfer reservoir as an upper reservoir and the Gosskar reservoir as its lower 22 A 5 3 km 3 mi o7m headrace tunnel from the Grosser Muhldorfer was excavated and connects to the existing headrace tunnel of the Rottau main stage Feeding water into the Reisseck II power station is a 820 km 510 mi long penstock The power station is located 200 m 656 ft underground and contains two 215 MW reversible Francis turbines It has a total installed capacity of 430 MW 23 and increases the overall capacity of the power plant group by 40 from 1 026 to 1 459 MW Cost was 400 million 9 24 25 Tourism Edit Skywalk The Kolnbrein Dam is the terminus of a 14 3 kilometres 8 9 mi long scenic route through the Maltatal the former construction site road including a restaurant a hotel and an exhibition on hydroelectricity Verbund also offers tours of the power plant group and the dam 4 Tours on the dam are conducted daily while the road is open between 9 May and 26 October each year 26 27 In 2010 a skywalk a horseshoe shaped cantilever bridge was installed on top of the dam for visitors which is also a popular bungee jumping venue The dam lies within the High Tauern National Park and is a destination for mountaineers as well Moreover the reservoir is used by rowers for altitude training In popular culture EditThe dam features in the 1978 film The Boys From Brazil standing in for a location in Sweden The movie was shot between late 1977 and early 1978 and shows the newly erected dam with a low reservoir level In the film the character of the inspector of the local power company and former SS Major is thrown off the top of the snow covered dam by an assassin sent by a fictional Josef Mengele Various shots around and on top of the dam are shown in the 3 minute 15 second scene at approximately 55 minutes into the film The dam also appears in the 2017 Indian film Vivegam in the opening sequence of the film References Edit a b c Langdon John August 2008 Kolnbreinsperre John Milton Langdon Archived from the original on 24 March 2012 Retrieved 4 June 2011 The pumped storage power plant an intelligent power storage system Verbund Archived from the original on 29 April 2011 Retrieved 29 May 2011 Kolnbrein Austrian National Committee on Large Dams Retrieved 29 May 2011 a b Visitor Centres Verbund Archived from the original on 19 April 2011 Retrieved 1 June 2011 a b Lombardi G June 1991 Kolnbrein dam an unusual solution for an unusual problem Water Power amp Dam Construction Retrieved 4 June 2011 Kolnbrein Background SimScience Archived from the original on March 21 2012 Retrieved 21 September 2018 Smoltczyk ed Ulrich 2003 Procedures Berlin u a Ernst p 85 ISBN 3 433 01450 7 a href Template Cite book html title Template Cite book cite book a first has generic name help Kolnbrein Current Status SimScience Retrieved 21 September 2018 a b Thyssen Schachtbau wins contract for an 820 m raise bore shaft for the pumped storage power station in Karnten PDF Thyssen Schachtbau Retrieved 4 June 2011 a b c Composite storage power plants in the AHP in Carinthia Map Verbund on Wikimedia Commons Retrieved 1 June 2011 Richard Hammond 7 November 2020 How the Turbines in the Kolnbrein Dam are 92 Efficient Discovery Channel Austrian Hydro Power Brochure PDF Verbund Archived from the original PDF on 24 March 2012 Retrieved 1 June 2011 Following electricity s traces with the interactive VERBUND power plant map Verbund Archived from the original on 6 August 2011 Retrieved 1 June 2011 On the interactive map the power plants have the following numbers Malta upper 60 Malta main 59 Malta lower 61 Reisseck annual 85 Reisseck daily 86 Kreuzeck Reisseck 51 Niklai 69 a href Template Cite web html title Template Cite web cite web a CS1 maint postscript link Koelnbrein Austrian National Committee on Large Dams Retrieved 1 June 2011 Galgenbichl Austrian National Committee on Large Dams Retrieved 1 June 2011 Radlsee Austrian National Committee on Large Dams Retrieved 1 June 2011 Hochalmsee Austrian National Committee on Large Dams Retrieved 1 June 2011 Kleiner Muhldorfer Austrian National Committee on Large Dams Retrieved 1 June 2011 Grosser Muhldorfer Austrian National Committee on Large Dams Retrieved 1 June 2011 Rosswiese Austrian National Committee on Large Dams Retrieved 1 June 2011 Reisseck II pumped storage power station in test o Structurae The interaction of wind solar and hydropower Voith voith com Diagram The 240 MVA motor generators for the Reisseck II pumped storage plant Hydropower amp Dams International www hydropower dams com Verbund power plant Reisseck II will not start in German Wirtschaftsblatt Medien 15 July 2015 Retrieved 21 July 2015 VERBUND Pumped Storage Power Plant Reisseck II www verbund com Archived from the original on 28 January 2020 Malta High Alpine Road Nationalpark Region Hohe Tauern Retrieved 4 June 2011 Malta At the gateway to the Hohe Tauern National Park Karnten Information Retrieved 4 June 2011 External links Edit Austria portal Water portal Renewable energy portal Map all coordinates using OpenStreetMap Download coordinates as KML Wikimedia Commons has media related to Kolnbrein Dam Retrieved from https en wikipedia org w index php title Kolnbrein Dam amp oldid 1097259985, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.