fbpx
Wikipedia

Jakarta Monorail

The Jakarta Monorail (abbr. JET Monorail) was a cancelled monorail network project in Jakarta, Indonesia. If completed, it would have comprised two lines, totalling up to 29 km (18 mi).[1][2]

Jakarta Eco Transport Monorail
Overview
OwnerProvince of DKI Jakarta
LocaleJakarta, Indonesia
Transit typeMonorail
Number of lines2 (projected)
Number of stations27 (projected)
HeadquartersSouth Jakarta, DKI Jakarta
Operation
Operator(s)PT. Jakarta Monorail
Number of vehicles10 & 18 per train
Project plan (2013)

The project had a tumultuous history. First awarded in 2003, the contract changed owners three times by 2005, before being abandoned with little more than some pillars built in 2008. The project was revived in February 2013,[3] but cancelled again in 2015 due to financial problems and legal disputes.[4] Jakarta Governor Basuki "Ahok" Tjahaja Purnama confirmed in September 2015 that the project would not continue.[1]

History edit

Planning and early construction edit

The project was initially awarded in 2003 to Malaysian company MTrans, the technology owner and builders of the KL Monorail. Construction started in June 2004 but was halted after only a few weeks after the funds for the project stopped. MTrans' memorandum of understanding (MoU) was then cancelled after MTrans didn't respond adequately, and the MoU did not move towards a formal agreement.

The project was subsequently awarded to the Singaporean-led Omnico consortium, which proposed to use the Hitachi Monorail system (the base used for the KL Monorail) and then later on switched to the maglev technology by South Korean company Rotem.

In July 2005, the project changed hands again with a new MoU granted to a consortium of PT Bukaka Teknik Utama, PT INKA and Siemens Indonesia (former vice president Jusuf Kalla, who then assumed office, owns a large stake in Bukaka). Omnico contested this move, but construction continued nonetheless, under the assumption that the basic foundation piles and pillars can be used by whichever consortium and technology wins in the end. By 2006, a change in shareholder structure resulted to PT Indonesia Transit Central (ITC) controlling 98 percent of the shares in the company, leaving partner Omnico with only 2 percent, reduced from its initial 45 percent. Reports indicate fares of Rp 5,000 per trip were considered with government subsidies and that the Dubai Islamic Bank was sought as an investor of up to US$500 million but had pulled out when the government refused to provide guarantees if ridership were to fall below 160,000 per day.[5]

 
Support pillars for the stalled monorail project in October 2008

In March 2008, developers PT Jakarta Monorail officially abandoned the project.[4] Then, in April, numerous pylons to support the future track were illegally demolished, probably by metal thieves.[6]

In September 2011, the Jakarta administration called off the monorail project with a maximum Rp.204 billion ($23.3 million) compensation to PT Jakarta Monorail.[7]

Construction resumes edit

In February 2013, the revival of the monorail project was announced by Dedy S. Priatna, deputy of infrastructure at the National Development Planning Agency (Bappenas), as part of plans to improve public transport in Jakarta.[3]

Private corporation PT Jakarta Monorail undertook the project's development. The consortium was 90% owned by Singapore-based Ortus Group and 10% by PT Indonesia Transit Central (ITC). Ortus Group has reportedly paid Rp 2.3 trillion (US$238 million) for its share[8] in the consortium. A deal has been signed to buy the pylons built between 2004 and 2007 from PT Adhi Karya for Rp 190 billion (US$19.5 million). The consortium plans to finance the Rp 8 trillion project with 70% debt and the balance by equity.[9][10]

In April 2013, Chinese firm Changchun Railway Vehicles Co., Ltd. (CNR) was declared the preferred manufacturer of the trains for the railway. A prototype vehicle was displayed at Monas (National Monument) in central Jakarta from 22 June to 14 July 2013.[11] In early May 2013 marketing firm XM JWT Jakarta was appointed to handle all branding, advertising, events, PR and digital marketing.[12] The consortium ran a public competition on its website[13] to choose the name the new system: "JET", an acronym for "Jakarta Eco Transit".

On 29 June 2013, Jakarta Governor Joko "Jokowi" Widodo signed an agreement with PT Jakarta Monorail to allow the project to proceed. Fares are proposed at Rp 10,000 (US $1.01) per trip with an initial capacity of 274,000 passengers per day with a design capacity of 35,000 passengers per hour per direction.[14] In announcing the deal the Governor called for work to commence as soon as possible and said the line should open by 2016; he also said that he hoped the other consortium proposing a regional monorail in greater Jakarta would make progress (see section below). Details of the agreement do not seem to have been made public.

Groundbreaking took place on 16 October 2013.[15]

Contract termination edit

In 2014, the project was stalled after disagreement between PT Jakarta Monorel as the contractor and developer with Jakarta Municipal Government, over the design of the stations as well as the land acquisition for the monorail depot. The proposed elevated grand monorail station in Dukuh Atas, Stadion Madya Senayan and Kuningan Sentral for example, has raised critical questions since the supporting pylons of this grand stations will occupy public spaces; street, canal, pedestrian and public parks.[16]

The design of grand monorail stations and operator insistence on the right to lease the spaces in stations, also has sparked arguments over the suspicions that the operator is actually intends to build some new malls, shopping centres or office spaces over Jakarta's street in the guise of monorail stations. The Dukuh Atas monorail station for example is proposed to rise up to 10 storey building, while Kuningan Sentral would rise to 5 or 4 storey building that will occupy Rasuna Said boulevard.[17] The Jakarta municipal government refuses PT Jakarta Monorel's proposal to build a monorail depot over Setiabudi reservoir near Dukuh Atas and West Jakarta Flood Canal near Tanah Abang, arguing that the construction would harm the canal and dam structure. Dinas Tata Ruang DKI (Jakarta Spatial Planning Agency) rejected the use of proposed land for the construction of a monorail depot and station, argued that the land proposed must be sterile from commercial buildings.[16]

In January 2015, The Jakarta administration decided to cancel its contract with monorail project operator PT Jakarta Monorail (JM) to develop the monorail routes proposed by the firm. Reasons cited were that the route JM proposed to build was not feasible and doubts over the company's ability to fund the project.[18]

The project edit

Intracity monorail edit

The original monorail was planned to be two main lines. The loop line known as the Green line would have served the business districts of the city (Casablanca and Rasuna Said Area), 14.8 km (9.2 mi) with 15 stops. The second line known as the Blue line would have been 14.2 km (8.8 mi) with 12 stops and would have run from Kampung Melayu to Tanah Abang. The whole system would have had the total of 29 km. It would have had two interchange stations at Casablanca and Karet to allow passengers to switch between these two lines, and the Sudirman Dukuh Atas station would also have allowed passengers to switch to the Jakarta Busway and the Jakarta railway network.

The system was due to have an initial capacity of 10,000 passengers per hour per direction (pphpd) expandable to 30,000 pphpd.[19] In the opening year, the Jakarta Monorail was planned to carry on average 274,000 people per day with plans to scale up capacity size quickly as the design capacity is set to carry 35,000 passengers per hour per direction.[20]

Connection to intercity project edit

A consortium of five state owned enterprises (SOEs), led by PT Adhi Karya (previously part of the Jakarta Monorail consortium), has said they have plans to build a 39.036 km (24 mi) monorail line connecting Cibubur-Cawang-Kuningan and Bekasi-Cawang across Greater Jakarta.[21] The line will connect to the 'Green' and 'Blue' lines to be built by PT Jakarta Monorail[22] In early May 2013 the SOE consortium unveiled a mockup of their own prototype monorail car, built by PT INKA in Jakarta.[23] The consortium said they are waiting for a permit from the central government as their routes would cover three government regions. It is expected to cost between Rp 7 trillion (US$800 million) and Rp 9 trillion (US$923 million) with financing to come from the SOEs and loans from state owned banks.[24] Ridership is estimated at 191,600 per day.[25]

This plan eventually evolved into the Jabodebek LRT, which is not based on monorail technology, but will reuse some of the monorail pillars.[26]

Criticism edit

A number of commentators and analysts have criticised the monorail on grounds of costs (compared to busway) or lack of capacity (compared to a subway or heavy rail) as well as unrealistic predictions.

In 2005, the non-governmental organization Pelangi said "based on (these) sustainability requirements, the busway outweighs the subway or monorail"; they recommended that Jakarta should focus on extending and improving the TransJakarta bus rapid transit (BRT) network rather than build subways or monorails as the busway would have lower capital costs and did not require operational subsidies. Also given the lower costs the busway could be extended to serve a great proportion of the population for the same amount of money.[27] (Transjakarta has already the worlds longest BRT network at 172 km with 200 stations and operates with 520 buses carrying 350,000 people per day).

In 2008, the former Mayor of Bogotá, Colombia, Enrique Peñalosa also called for Jakarta to expand the busways instead of monorail or subways; he told a seminar that "[A] subway would cost three times its contract value, yet it would only cover several lines, (but) with the same amount of money you could reach all parts of the city with the (busway) network,".[28] Bogota has one of the world's most extensive and busiest BRT networks, the TransMilenio.

The monorail line design; loop Green line and Blue line, has gained criticism, as it only connects shopping malls in Jakarta's city center, and would not connect to suburban Jakarta that desperately need transportation infrastructure; thus would not be useful for many Jakartan commuters. Transportation experts deemed that the city center monorail project would not answer Jakarta's traffic problems, but would only serves as a novelty tourists' ride.[29]

In November 2012, the Director of the Institute of Transportation Studies, Darmaningtyas, said the capacity of the monorail was too limited, it was not economic and not suitable for Jakarta: "Everything has to be built, including the train depot. This is not economical. The fare can be over Rp 10,000 per person. If seen from the monorail’s planned coverage in Jakarta, with a radius of less than 10km, this is too expensive"[30]

The project was further criticised in February 2013 by Bambang Susantono, the deputy minister of transportation, on the grounds that it was not sustainable in the long term and other public transport modes better suited Jakarta's requirements.[31] The two line project agreed to in June 2013 is supposed to be built without any government financing. The Jakarta City Council has set up a committee to ensure the project does not draw on funds from the City's budget.[32]

Cancellation edit

Jakarta Governor Basuki "Ahok" Tjahaja Purnama stated on 10 September 2015 that negotiations with monorail project operator PT Jakarta Monorail (JM) would not continue, meaning total discontinuation of the infrastructure project. State-owned construction company PT Adhi Karya is to use the numerous monorail support poles to develop the Jabodebek LRT.[1]

The shift of choice from monorail to light rail transit (LRT) system was based on several considerations; compared to monorail, LRT has higher passenger capacity, simpler intersection and switching system, and cheaper maintenance cost. With common track gauge of 1,435 mm (4 ft 8+12 in), would make LRT easier to integrate with existing commuter railways and Jakarta MRT.[33]

See also edit

References edit

  1. ^ a b c "Ahok confirms cancellation of monorail project". The Jakarta Post. Jakarta. 10 September 2015. Retrieved 21 September 2015.
  2. ^ "Pembangunan Monorel Dilanjutkan, Mohon Bersabar..." (in Indonesian). Kompas. 16 October 2013.
  3. ^ a b "Abandoned monorail plan to be revived".
  4. ^ a b , The Jakarta Post, 2008-03-15, archived from the original on 2011-06-07, retrieved 2010-07-10
  5. ^ . Jakarta Post. December 26, 2006. Archived from the original on November 10, 2014. Retrieved July 4, 2013.
  6. ^ "Jakarta Monorail pylons disappear". 2008-04-09. Retrieved 2008-09-17.
  7. ^ "No more monorail for Jakarta, Governor". September 19, 2011.
  8. ^ "With Rp 2.3 trillion, Ortus is the Latest With a Monorail Plan".
  9. ^ "Monorail Project Tender Alleged to be Not Transparent". Archived from the original on 2013-06-15. Retrieved 2013-05-18.
  10. ^ "Bureaucracy delays monorail project". Jakarta Post. June 20, 2013.
  11. ^ "Chinese firm wins tender for monorail trains".
  12. ^ . Archived from the original on 2013-06-25. Retrieved 2013-05-18.
  13. ^ . Archived from the original on 2004-09-07.
  14. ^ FAQ ~ Jakarta Monorail
  15. ^ . October 16, 2013. Archived from the original on October 17, 2013. Retrieved October 16, 2013.
  16. ^ a b "Jokowi Minta Perbaiki Konsep-Desain Proyek Monorel". Jawa Pos (in Indonesian). 21 August 2014. Retrieved 27 September 2015.
  17. ^ Syailendra (16 October 2013). "Begini Desain Stasiun Monorel Jakarta". Retrieved 27 September 2015.
  18. ^ "Jakarta Post". Retrieved 18 April 2015.
  19. ^ . Archived from the original on 2013-12-02. Retrieved 2013-06-02.
  20. ^ "Jakarta Monorail FAQ".
  21. ^ . Archived from the original on 2019-09-06. Retrieved 2013-05-18.
  22. ^ "State Firms Propose Jakarta Monorail Extension". Jakarta Globe. May 6, 2013.
  23. ^ "SOE consortium launches mock-up of Rp 12t monorail system".
  24. ^ . Archived from the original on 2015-04-02. Retrieved 2013-07-04.
  25. ^ "Indonesia to Build Jakarta Monorail to Ease Rising Traffic Jams". Bloomberg. Feb 7, 2013.
  26. ^ "Ahok confirms cancellation of monorail project - City - The Jakarta Post".
  27. ^ "NGO prefers busway to monorail". The Jakarta Post. 2005-04-11.
  28. ^ "Jakarta doesn't need subway nor monorail".
  29. ^ Wiji Nurhayat (27 October 2012). "Monorel Lebih Cocok Untuk Angkutan Wisata". Detik Finance (in Indonesian). Retrieved 21 September 2015.
  30. ^ "Review the Monorail Project". Archived from the original on 2013-06-15. Retrieved 2013-05-19.
  31. ^ "Jakarta Monorail Not Sustainable, Official Insists". Retrieved 19 February 2013.
  32. ^ "Jakarta Monorail Must Not Use City Budget, Says Official". July 17, 2013.
  33. ^ Desy Afrianti, Fajar Ginanjar Mukti (10 June 2014). "Keunggulan Light Rail Transit untuk Jakarta, LRT ini jadi alternatif jika monorel gagal". Viva.co.id (in Indonesian). Retrieved 22 September 2015.

External links edit

  • Jakarta Monorail homepage (in Indonesian)

jakarta, monorail, abbr, monorail, cancelled, monorail, network, project, jakarta, indonesia, completed, would, have, comprised, lines, totalling, jakarta, transport, monorailoverviewownerprovince, jakartalocalejakarta, indonesiatransit, typemonorailnumber, li. The Jakarta Monorail abbr JET Monorail was a cancelled monorail network project in Jakarta Indonesia If completed it would have comprised two lines totalling up to 29 km 18 mi 1 2 Jakarta Eco Transport MonorailOverviewOwnerProvince of DKI JakartaLocaleJakarta IndonesiaTransit typeMonorailNumber of lines2 projected Number of stations27 projected HeadquartersSouth Jakarta DKI JakartaOperationOperator s PT Jakarta MonorailNumber of vehicles10 amp 18 per trainProject plan 2013 The project had a tumultuous history First awarded in 2003 the contract changed owners three times by 2005 before being abandoned with little more than some pillars built in 2008 The project was revived in February 2013 3 but cancelled again in 2015 due to financial problems and legal disputes 4 Jakarta Governor Basuki Ahok Tjahaja Purnama confirmed in September 2015 that the project would not continue 1 Contents 1 History 1 1 Planning and early construction 1 2 Construction resumes 1 3 Contract termination 2 The project 2 1 Intracity monorail 2 2 Connection to intercity project 3 Criticism 4 Cancellation 5 See also 6 References 7 External linksHistory editPlanning and early construction edit The project was initially awarded in 2003 to Malaysian company MTrans the technology owner and builders of the KL Monorail Construction started in June 2004 but was halted after only a few weeks after the funds for the project stopped MTrans memorandum of understanding MoU was then cancelled after MTrans didn t respond adequately and the MoU did not move towards a formal agreement The project was subsequently awarded to the Singaporean led Omnico consortium which proposed to use the Hitachi Monorail system the base used for the KL Monorail and then later on switched to the maglev technology by South Korean company Rotem In July 2005 the project changed hands again with a new MoU granted to a consortium of PT Bukaka Teknik Utama PT INKA and Siemens Indonesia former vice president Jusuf Kalla who then assumed office owns a large stake in Bukaka Omnico contested this move but construction continued nonetheless under the assumption that the basic foundation piles and pillars can be used by whichever consortium and technology wins in the end By 2006 a change in shareholder structure resulted to PT Indonesia Transit Central ITC controlling 98 percent of the shares in the company leaving partner Omnico with only 2 percent reduced from its initial 45 percent Reports indicate fares of Rp 5 000 per trip were considered with government subsidies and that the Dubai Islamic Bank was sought as an investor of up to US 500 million but had pulled out when the government refused to provide guarantees if ridership were to fall below 160 000 per day 5 nbsp Support pillars for the stalled monorail project in October 2008In March 2008 developers PT Jakarta Monorail officially abandoned the project 4 Then in April numerous pylons to support the future track were illegally demolished probably by metal thieves 6 In September 2011 the Jakarta administration called off the monorail project with a maximum Rp 204 billion 23 3 million compensation to PT Jakarta Monorail 7 Construction resumes edit In February 2013 the revival of the monorail project was announced by Dedy S Priatna deputy of infrastructure at the National Development Planning Agency Bappenas as part of plans to improve public transport in Jakarta 3 Private corporation PT Jakarta Monorail undertook the project s development The consortium was 90 owned by Singapore based Ortus Group and 10 by PT Indonesia Transit Central ITC Ortus Group has reportedly paid Rp 2 3 trillion US 238 million for its share 8 in the consortium A deal has been signed to buy the pylons built between 2004 and 2007 from PT Adhi Karya for Rp 190 billion US 19 5 million The consortium plans to finance the Rp 8 trillion project with 70 debt and the balance by equity 9 10 In April 2013 Chinese firm Changchun Railway Vehicles Co Ltd CNR was declared the preferred manufacturer of the trains for the railway A prototype vehicle was displayed at Monas National Monument in central Jakarta from 22 June to 14 July 2013 11 In early May 2013 marketing firm XM JWT Jakarta was appointed to handle all branding advertising events PR and digital marketing 12 The consortium ran a public competition on its website 13 to choose the name the new system JET an acronym for Jakarta Eco Transit On 29 June 2013 Jakarta Governor Joko Jokowi Widodo signed an agreement with PT Jakarta Monorail to allow the project to proceed Fares are proposed at Rp 10 000 US 1 01 per trip with an initial capacity of 274 000 passengers per day with a design capacity of 35 000 passengers per hour per direction 14 In announcing the deal the Governor called for work to commence as soon as possible and said the line should open by 2016 he also said that he hoped the other consortium proposing a regional monorail in greater Jakarta would make progress see section below Details of the agreement do not seem to have been made public Groundbreaking took place on 16 October 2013 15 Contract termination edit In 2014 the project was stalled after disagreement between PT Jakarta Monorel as the contractor and developer with Jakarta Municipal Government over the design of the stations as well as the land acquisition for the monorail depot The proposed elevated grand monorail station in Dukuh Atas Stadion Madya Senayan and Kuningan Sentral for example has raised critical questions since the supporting pylons of this grand stations will occupy public spaces street canal pedestrian and public parks 16 The design of grand monorail stations and operator insistence on the right to lease the spaces in stations also has sparked arguments over the suspicions that the operator is actually intends to build some new malls shopping centres or office spaces over Jakarta s street in the guise of monorail stations The Dukuh Atas monorail station for example is proposed to rise up to 10 storey building while Kuningan Sentral would rise to 5 or 4 storey building that will occupy Rasuna Said boulevard 17 The Jakarta municipal government refuses PT Jakarta Monorel s proposal to build a monorail depot over Setiabudi reservoir near Dukuh Atas and West Jakarta Flood Canal near Tanah Abang arguing that the construction would harm the canal and dam structure Dinas Tata Ruang DKI Jakarta Spatial Planning Agency rejected the use of proposed land for the construction of a monorail depot and station argued that the land proposed must be sterile from commercial buildings 16 In January 2015 The Jakarta administration decided to cancel its contract with monorail project operator PT Jakarta Monorail JM to develop the monorail routes proposed by the firm Reasons cited were that the route JM proposed to build was not feasible and doubts over the company s ability to fund the project 18 The project editIntracity monorail edit The original monorail was planned to be two main lines The loop line known as the Green line would have served the business districts of the city Casablanca and Rasuna Said Area 14 8 km 9 2 mi with 15 stops The second line known as the Blue line would have been 14 2 km 8 8 mi with 12 stops and would have run from Kampung Melayu to Tanah Abang The whole system would have had the total of 29 km It would have had two interchange stations at Casablanca and Karet to allow passengers to switch between these two lines and the Sudirman Dukuh Atas station would also have allowed passengers to switch to the Jakarta Busway and the Jakarta railway network The system was due to have an initial capacity of 10 000 passengers per hour per direction pphpd expandable to 30 000 pphpd 19 In the opening year the Jakarta Monorail was planned to carry on average 274 000 people per day with plans to scale up capacity size quickly as the design capacity is set to carry 35 000 passengers per hour per direction 20 Connection to intercity project edit See also Jabodebek LRT A consortium of five state owned enterprises SOEs led by PT Adhi Karya previously part of the Jakarta Monorail consortium has said they have plans to build a 39 036 km 24 mi monorail line connecting Cibubur Cawang Kuningan and Bekasi Cawang across Greater Jakarta 21 The line will connect to the Green and Blue lines to be built by PT Jakarta Monorail 22 In early May 2013 the SOE consortium unveiled a mockup of their own prototype monorail car built by PT INKA in Jakarta 23 The consortium said they are waiting for a permit from the central government as their routes would cover three government regions It is expected to cost between Rp 7 trillion US 800 million and Rp 9 trillion US 923 million with financing to come from the SOEs and loans from state owned banks 24 Ridership is estimated at 191 600 per day 25 This plan eventually evolved into the Jabodebek LRT which is not based on monorail technology but will reuse some of the monorail pillars 26 Criticism editA number of commentators and analysts have criticised the monorail on grounds of costs compared to busway or lack of capacity compared to a subway or heavy rail as well as unrealistic predictions In 2005 the non governmental organization Pelangi said based on these sustainability requirements the busway outweighs the subway or monorail they recommended that Jakarta should focus on extending and improving the TransJakarta bus rapid transit BRT network rather than build subways or monorails as the busway would have lower capital costs and did not require operational subsidies Also given the lower costs the busway could be extended to serve a great proportion of the population for the same amount of money 27 Transjakarta has already the worlds longest BRT network at 172 km with 200 stations and operates with 520 buses carrying 350 000 people per day In 2008 the former Mayor of Bogota Colombia Enrique Penalosa also called for Jakarta to expand the busways instead of monorail or subways he told a seminar that A subway would cost three times its contract value yet it would only cover several lines but with the same amount of money you could reach all parts of the city with the busway network 28 Bogota has one of the world s most extensive and busiest BRT networks the TransMilenio The monorail line design loop Green line and Blue line has gained criticism as it only connects shopping malls in Jakarta s city center and would not connect to suburban Jakarta that desperately need transportation infrastructure thus would not be useful for many Jakartan commuters Transportation experts deemed that the city center monorail project would not answer Jakarta s traffic problems but would only serves as a novelty tourists ride 29 In November 2012 the Director of the Institute of Transportation Studies Darmaningtyas said the capacity of the monorail was too limited it was not economic and not suitable for Jakarta Everything has to be built including the train depot This is not economical The fare can be over Rp 10 000 per person If seen from the monorail s planned coverage in Jakarta with a radius of less than 10km this is too expensive 30 The project was further criticised in February 2013 by Bambang Susantono the deputy minister of transportation on the grounds that it was not sustainable in the long term and other public transport modes better suited Jakarta s requirements 31 The two line project agreed to in June 2013 is supposed to be built without any government financing The Jakarta City Council has set up a committee to ensure the project does not draw on funds from the City s budget 32 Cancellation editJakarta Governor Basuki Ahok Tjahaja Purnama stated on 10 September 2015 that negotiations with monorail project operator PT Jakarta Monorail JM would not continue meaning total discontinuation of the infrastructure project State owned construction company PT Adhi Karya is to use the numerous monorail support poles to develop the Jabodebek LRT 1 The shift of choice from monorail to light rail transit LRT system was based on several considerations compared to monorail LRT has higher passenger capacity simpler intersection and switching system and cheaper maintenance cost With common track gauge of 1 435 mm 4 ft 8 1 2 in would make LRT easier to integrate with existing commuter railways and Jakarta MRT 33 See also editList of monorail systemsReferences edit a b c Ahok confirms cancellation of monorail project The Jakarta Post Jakarta 10 September 2015 Retrieved 21 September 2015 Pembangunan Monorel Dilanjutkan Mohon Bersabar in Indonesian Kompas 16 October 2013 a b Abandoned monorail plan to be revived a b Editorial Monorail fate The Jakarta Post 2008 03 15 archived from the original on 2011 06 07 retrieved 2010 07 10 Jakarta expects no share from monorail profits Jakarta Post December 26 2006 Archived from the original on November 10 2014 Retrieved July 4 2013 Jakarta Monorail pylons disappear 2008 04 09 Retrieved 2008 09 17 No more monorail for Jakarta Governor September 19 2011 With Rp 2 3 trillion Ortus is the Latest With a Monorail Plan Monorail Project Tender Alleged to be Not Transparent Archived from the original on 2013 06 15 Retrieved 2013 05 18 Bureaucracy delays monorail project Jakarta Post June 20 2013 Chinese firm wins tender for monorail trains NEW XM JWT JOINT VENTURE NAMED AOR FOR JAKARTA MONORAIL Archived from the original on 2013 06 25 Retrieved 2013 05 18 Under Construction Archived from the original on 2004 09 07 FAQ Jakarta Monorail Edward Soeryadjaya Senang Pembangunan Proyek Monorel Dilanjutkan October 16 2013 Archived from the original on October 17 2013 Retrieved October 16 2013 a b Jokowi Minta Perbaiki Konsep Desain Proyek Monorel Jawa Pos in Indonesian 21 August 2014 Retrieved 27 September 2015 Syailendra 16 October 2013 Begini Desain Stasiun Monorel Jakarta Retrieved 27 September 2015 Jakarta Post Retrieved 18 April 2015 Jakarta Monorail Feasibility Study Indonesia Mott McDonald Archived from the original on 2013 12 02 Retrieved 2013 06 02 Jakarta Monorail FAQ Adhi Karya Bangun Monorel Cibubur Cawang Kuningan Investor Daily Archived from the original on 2019 09 06 Retrieved 2013 05 18 State Firms Propose Jakarta Monorail Extension Jakarta Globe May 6 2013 SOE consortium launches mock up of Rp 12t monorail system Monorail to Take up Budget of Rp 7 Trillion Archived from the original on 2015 04 02 Retrieved 2013 07 04 Indonesia to Build Jakarta Monorail to Ease Rising Traffic Jams Bloomberg Feb 7 2013 Ahok confirms cancellation of monorail project City The Jakarta Post NGO prefers busway to monorail The Jakarta Post 2005 04 11 Jakarta doesn t need subway nor monorail Wiji Nurhayat 27 October 2012 Monorel Lebih Cocok Untuk Angkutan Wisata Detik Finance in Indonesian Retrieved 21 September 2015 Review the Monorail Project Archived from the original on 2013 06 15 Retrieved 2013 05 19 Jakarta Monorail Not Sustainable Official Insists Retrieved 19 February 2013 Jakarta Monorail Must Not Use City Budget Says Official July 17 2013 Desy Afrianti Fajar Ginanjar Mukti 10 June 2014 Keunggulan Light Rail Transit untuk Jakarta LRT ini jadi alternatif jika monorel gagal Viva co id in Indonesian Retrieved 22 September 2015 External links editJakarta Monorail homepage in Indonesian Retrieved from https en wikipedia org w index php title Jakarta Monorail amp oldid 1214464527, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.