The Carrizo Energy Solar Farm was a proposed 177 megawatt (MW) solar thermal power plant, to be built by Ausra in California's Carrizo Plain, near Simmler. The location gets less sun than the Mojave Desert, where several other solar thermal plants are under consideration, but is near an existing transmission line from Diablo Canyon Power Plant, reducing the cost and time needed to construct the plant.[1]

The $550 million[2] power plant would have provided enough power for 60,000 homes, and Pacific Gas and Electric (PG&E) entered into a contract to buy all the power from the power plant. Ausra claimed its technology can deliver power at 10.4 cents per kilowatt-hour (¢/kW·h).[3] Ausra planned to have the plant generating power by 2010, using Ausra's Compact Linear Fresnel Reflector (CLFR) solar technology.[4][5]

In November 2009, Ausra announced that it had sold its options to the 640 acres (260 ha) of land to First Solar and canceled its contract with PG&E. First Solar will use some of the land for its Topaz Solar Farm.[6][7][8]

References edit

  1. ^ Kilcrease, April (2007-11-05). . Red Herring. Archived from the original on 2008-05-13. Retrieved 2008-08-19.
  2. ^ Nauman, Matt (October 23, 2008). "Ausra's day in the sun: Palo Alto solar start-up opens plant near Bakersfield". San Jose Mercury News. Retrieved 2008-10-24.
  3. ^ St. John, Jeff (October 23, 2008). . Greentech Media. Archived from the original on October 25, 2008. Retrieved 2008-10-24.
  4. ^ Kanellos, Michael (November 5, 2007). "PG&E links with Ausra for 177 megawatts of solar thermal power". Cnet News. Retrieved 2008-10-24.
  5. ^ Kho, Jennifer (November 5, 2007). "Ausra to Build 177-Megawatt Solar-Thermal Plant". Greentech Media. Retrieved 2008-10-24.
  6. ^ Woody, Todd (November 5, 2009). "Ausra Sells Planned Plant to First Solar". The New York Times. Retrieved 2009-11-05.
  7. ^ Sneed, David (November 5, 2009). "Solar power company drops out of plans for Carrizo Plain in eastern San Luis Obispo County". The Tribune. Archived from the original on February 2, 2013. Retrieved 2009-11-05.
  8. ^ Wang, Ucilia (November 5, 2009). "First Solar Buys Land Option From Ausra for Topaz Project". Greentech Media. Retrieved 2009-11-05.

External links edit

carrizo, energy, solar, farm, proposed, megawatt, solar, thermal, power, plant, built, ausra, california, carrizo, plain, near, simmler, location, gets, less, than, mojave, desert, where, several, other, solar, thermal, plants, under, consideration, near, exis. The Carrizo Energy Solar Farm was a proposed 177 megawatt MW solar thermal power plant to be built by Ausra in California s Carrizo Plain near Simmler The location gets less sun than the Mojave Desert where several other solar thermal plants are under consideration but is near an existing transmission line from Diablo Canyon Power Plant reducing the cost and time needed to construct the plant 1 The 550 million 2 power plant would have provided enough power for 60 000 homes and Pacific Gas and Electric PG amp E entered into a contract to buy all the power from the power plant Ausra claimed its technology can deliver power at 10 4 cents per kilowatt hour kW h 3 Ausra planned to have the plant generating power by 2010 using Ausra s Compact Linear Fresnel Reflector CLFR solar technology 4 5 In November 2009 Ausra announced that it had sold its options to the 640 acres 260 ha of land to First Solar and canceled its contract with PG amp E First Solar will use some of the land for its Topaz Solar Farm 6 7 8 References edit Kilcrease April 2007 11 05 Solar Startup Ausra Inks 1B Deal With PG amp E Red Herring Archived from the original on 2008 05 13 Retrieved 2008 08 19 Nauman Matt October 23 2008 Ausra s day in the sun Palo Alto solar start up opens plant near Bakersfield San Jose Mercury News Retrieved 2008 10 24 St John Jeff October 23 2008 Ausra s First U S Solar Thermal Plant Lights Up Greentech Media Archived from the original on October 25 2008 Retrieved 2008 10 24 Kanellos Michael November 5 2007 PG amp E links with Ausra for 177 megawatts of solar thermal power Cnet News Retrieved 2008 10 24 Kho Jennifer November 5 2007 Ausra to Build 177 Megawatt Solar Thermal Plant Greentech Media Retrieved 2008 10 24 Woody Todd November 5 2009 Ausra Sells Planned Plant to First Solar The New York Times Retrieved 2009 11 05 Sneed David November 5 2009 Solar power company drops out of plans for Carrizo Plain in eastern San Luis Obispo County The Tribune Archived from the original on February 2 2013 Retrieved 2009 11 05 Wang Ucilia November 5 2009 First Solar Buys Land Option From Ausra for Topaz Project Greentech Media Retrieved 2009 11 05 External links edit nbsp California portal nbsp Renewable energy portal Carrizo Energy Solar Farm Power Plant Licensing Case California Energy Commission 2008 07 28 Retrieved 2008 08 19 Retrieved from https en wikipedia org w index php title Carrizo Energy Solar Farm amp oldid 1058645192, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.