The Byker Viaduct (also known as the Byker Metro Bridge) is a 2,674 ft (815 m) curved S-shaped light railway bridge, which carries the Tyne and Wear Metro over the River Ouseburn in Newcastle upon Tyne. It carries the line from Manors Metro station in the city centre to the west, to Byker Metro station in the area of Byker to the east, over the lower Ouseburn valley, with the river emptying into the north side of the River Tyne, to the south. It was one of two major bridges built specifically for the Tyne and Wear Metro, the other being the Queen Elizabeth II Bridge crossing the River Tyne.[1]

Byker Viaduct
The viaduct shortly after completion in 1979.
Coordinates54°58′34″N 1°35′35″W / 54.97613°N 1.593007°W / 54.97613; -1.593007
CarriesTyne and Wear Metro
CrossesOuseburn
LocaleTyneside
Characteristics
DesignBox girder bridge
MaterialConcrete
Total length2,674 ft (815 m)
Width27 ft (8.2 m)
Clearance below98 ft (30 m)
History
DesignerOve Arup and Partners
Constructed byJohn Mowlem & Co Ltd
Construction start1976; 48 years ago (1976)
Construction end1979; 45 years ago (1979)
Opened11 November 1982; 41 years ago (1982-11-11)
Location

It is one of three high level bridges in close proximity making the same crossing, with the Ouseburn railway viaduct to the north and the Byker road bridge to the south. The bridge and elevated section form an S-curve, which takes the track over the Byker road bridge at its east end.[2][3]

History edit

The Byker Viaduct was built specifically to carry the then-planned Tyne and Wear Metro across the Ouseburn Valley, permitting a direct connection between the centre of Newcastle and the east end of the city and the coastal areas beyond. It was designed by Ove Arup and Partners and constructed by Mowlem.[4] It was a notable structure for the era, being the first such structure in Britain to be built using cantilevered concrete sections with joints glued with epoxy resin.[5][3]

The viaduct was one of the largest challenges in terms of civil engineering in the construction of the whole Metro system.[3] This was in part due to the terrain, which not only comprised a densely populated area along with the need to accommodate a future road alignment, but also featured geology challenges in the form of faults abd multiple coal seams directly beneath the site that present design challenges.[6]

During June 1976, construction work on the viaduct commenced; it would take three years to complete.[3] Initial work was focused on the erection of the reinforced concrete piers, the highest of which being roughly 70 meters above the ground.[3] Towards the base of each pier, they flared outwards.[6]

A total of 253 concrete segments, each one weighing 40 tonnes, were cast on-site prior to being lifted into place using a crane and secured using an epoxy resin and steel cables.[3] The slopes of the valley prevented the effective use of a straightforward winch on the deck itself.[6]

Each web of the structure feature multiple large unreinforced shear keys, the 2.2m deep segments have three keys per web while up to five keys are used on the deeper sections.[6] A complete span could be erected on temporary supports using only bar prestressing, after which the cables were threaded and stressed.[6] The plateau section comprises eight short spans.[6]

The track comprised continuously welded rails laid upon reinforced concrete slabs with discreet rubberised pads in between and secured using Pandrol clips; deployed by a slipform paver, these had a specified tolerance of 3mm in 3m.[6] The surface of the deck was waterproofed after the track slabs were laid using a spray-on compound.[6]

On 11 November 1982, the viaduct was opened to traffic as part of the St James to Tynemouth section of the Metro.[3] The completed bridge is 27 ft (8.2 m) wide, and carries standard gauge double tracks up to 30 m (98 ft) above the ground, with 18 spans up to 226 ft (69 m) long; six of the spans are over the river valley, with the remainder continuing on the east side of the valley as a lower elevated section.[2][7]

During early 2017, a series of weekend closures of the viaduct were enacted so that a planned replacement of the track could be conducted.[8]

References edit

  1. ^ "Meet Your Metro" 1978 information booklet produced by Tyne and Wear Passenger Transport Executive.
  2. ^ a b "Byker Metro Bridge". Engineering Timelines. Retrieved 27 March 2017.
  3. ^ a b c d e f g Morton, David (10 November 2022). "Metro Viaduct at Byker that's bridged the Ouseburn Valley for 40 years". chroniclelive.co.uk.
  4. ^ "River Tyne Crossings & Newcastle Bridges: Local Studies Factsheet No. 1" (PDF). Newcastle City Council. June 2009.
  5. ^ Moavenzadeh, Fred (1990). Concise Encyclopedia of Building and Construction Materials. The Mit Press. ISBN 9780262132480. Retrieved 27 March 2017.
  6. ^ a b c d e f g h Benaim, Robert (November 1980). "Design of the Byker Viaduct". ETH-Bibliothek.
  7. ^ "Byker Viaduct". structurae.net. Retrieved 27 March 2016.
  8. ^ Morton, David (24 February 2017). "1982 Metro viaduct was a challenge to build". chroniclelive.co.uk.

External links edit

  •   Media related to Byker Metro Bridge at Wikimedia Commons
  • Constructing the Byker Viaduct. North East Film Archive - Contemporary film of the construction.

byker, viaduct, also, known, byker, metro, bridge, curved, shaped, light, railway, bridge, which, carries, tyne, wear, metro, over, river, ouseburn, newcastle, upon, tyne, carries, line, from, manors, metro, station, city, centre, west, byker, metro, station, . The Byker Viaduct also known as the Byker Metro Bridge is a 2 674 ft 815 m curved S shaped light railway bridge which carries the Tyne and Wear Metro over the River Ouseburn in Newcastle upon Tyne It carries the line from Manors Metro station in the city centre to the west to Byker Metro station in the area of Byker to the east over the lower Ouseburn valley with the river emptying into the north side of the River Tyne to the south It was one of two major bridges built specifically for the Tyne and Wear Metro the other being the Queen Elizabeth II Bridge crossing the River Tyne 1 Byker ViaductThe viaduct shortly after completion in 1979 Coordinates54 58 34 N 1 35 35 W 54 97613 N 1 593007 W 54 97613 1 593007CarriesTyne and Wear MetroCrossesOuseburnLocaleTynesideCharacteristicsDesignBox girder bridgeMaterialConcreteTotal length2 674 ft 815 m Width27 ft 8 2 m Clearance below98 ft 30 m HistoryDesignerOve Arup and PartnersConstructed byJohn Mowlem amp Co LtdConstruction start1976 48 years ago 1976 Construction end1979 45 years ago 1979 Opened11 November 1982 41 years ago 1982 11 11 LocationIt is one of three high level bridges in close proximity making the same crossing with the Ouseburn railway viaduct to the north and the Byker road bridge to the south The bridge and elevated section form an S curve which takes the track over the Byker road bridge at its east end 2 3 History editThe Byker Viaduct was built specifically to carry the then planned Tyne and Wear Metro across the Ouseburn Valley permitting a direct connection between the centre of Newcastle and the east end of the city and the coastal areas beyond It was designed by Ove Arup and Partners and constructed by Mowlem 4 It was a notable structure for the era being the first such structure in Britain to be built using cantilevered concrete sections with joints glued with epoxy resin 5 3 The viaduct was one of the largest challenges in terms of civil engineering in the construction of the whole Metro system 3 This was in part due to the terrain which not only comprised a densely populated area along with the need to accommodate a future road alignment but also featured geology challenges in the form of faults abd multiple coal seams directly beneath the site that present design challenges 6 During June 1976 construction work on the viaduct commenced it would take three years to complete 3 Initial work was focused on the erection of the reinforced concrete piers the highest of which being roughly 70 meters above the ground 3 Towards the base of each pier they flared outwards 6 A total of 253 concrete segments each one weighing 40 tonnes were cast on site prior to being lifted into place using a crane and secured using an epoxy resin and steel cables 3 The slopes of the valley prevented the effective use of a straightforward winch on the deck itself 6 Each web of the structure feature multiple large unreinforced shear keys the 2 2m deep segments have three keys per web while up to five keys are used on the deeper sections 6 A complete span could be erected on temporary supports using only bar prestressing after which the cables were threaded and stressed 6 The plateau section comprises eight short spans 6 The track comprised continuously welded rails laid upon reinforced concrete slabs with discreet rubberised pads in between and secured using Pandrol clips deployed by a slipform paver these had a specified tolerance of 3mm in 3m 6 The surface of the deck was waterproofed after the track slabs were laid using a spray on compound 6 On 11 November 1982 the viaduct was opened to traffic as part of the St James to Tynemouth section of the Metro 3 The completed bridge is 27 ft 8 2 m wide and carries standard gauge double tracks up to 30 m 98 ft above the ground with 18 spans up to 226 ft 69 m long six of the spans are over the river valley with the remainder continuing on the east side of the valley as a lower elevated section 2 7 During early 2017 a series of weekend closures of the viaduct were enacted so that a planned replacement of the track could be conducted 8 References edit Meet Your Metro 1978 information booklet produced by Tyne and Wear Passenger Transport Executive a b Byker Metro Bridge Engineering Timelines Retrieved 27 March 2017 a b c d e f g Morton David 10 November 2022 Metro Viaduct at Byker that s bridged the Ouseburn Valley for 40 years chroniclelive co uk River Tyne Crossings amp Newcastle Bridges Local Studies Factsheet No 1 PDF Newcastle City Council June 2009 Moavenzadeh Fred 1990 Concise Encyclopedia of Building and Construction Materials The Mit Press ISBN 9780262132480 Retrieved 27 March 2017 a b c d e f g h Benaim Robert November 1980 Design of the Byker Viaduct ETH Bibliothek Byker Viaduct structurae net Retrieved 27 March 2016 Morton David 24 February 2017 1982 Metro viaduct was a challenge to build chroniclelive co uk External links edit nbsp Media related to Byker Metro Bridge at Wikimedia Commons Constructing the Byker Viaduct North East Film Archive Contemporary film of the construction Retrieved from https en wikipedia org w index php title Byker Viaduct amp oldid 1212060187, wikipedia, wiki, book, books, library,

article

, read, download, free, free download, mp3, video, mp4, 3gp, jpg, jpeg, gif, png, picture, music, song, movie, book, game, games.